better zsoil, better geotechnical analysis · · 2015-11-26better zsoil, better geotechnical...
TRANSCRIPT
Better ZSOIL,Better Geotechnical Analysis
——Practice of Pile Foundation Treatment Based on ZSOIL.PC
SYMPOSIUM : NUMERICS IN GEOTECHNICS & STRUCTURES
26 YEARS ZSOIL.PC
DATE :1-2.09.2011
YIN JI 1,2
Email:[email protected]
1.Shanghai Geotechnical Investigation & Design, co,.ltd.
2.GEOFEM
CONTENTS
Functions related to Pile Foundation Design of ZSOIL.PC Pile element Borehole Nodal link
Practice of Pile Foundation TreatmentGeneral information Challenge Pile static load test 3D FEM analysis
Acknowledgements
Functions related to Pile Foundation Design of ZSOIL.PCPile elementBoreholeNodal link
Functions related to Pile Foundation of ZSOIL.PCPile element
Mechanical Features of Pile element Pile element contains pile (structure
element ), lateral skin shear interface and toe compaction/tension interface
The interaction between pile and surrounding soil can be modeled with skin and toe interface, which comply with Mohr-Coulomb strength criterion
Pile (structure element ) inherits all the properties of beam element
Raft or trip foundation
Compaction/tension interface
Shear interface
Pile/Beam
Functions related to Pile Foundation of ZSOIL.PCPile element
Modeling of Pile element Hundreds of pile elements can be
generated “on objects” within several seconds, which usually imported from DXF files
Pile head can be automatically “link to” raft or trip foundation smartly, which can save us many hours to “merge” pile head and nodes of solid element
Axial force, moment and shear force can transfer from piles to raft , and vice versa
The length of each segment of pile should be compatible with the length of the soil element, not too large nor too small
If layout of piles change, import the modified DXF file again
Raft foundation
Pile head
Pile element
Functions related to Pile Foundation of ZSOIL.PCPile element
Parameters of pile element Parameters of pile (structure) is easy to
determine when the style of pile is selected
Parameters of skin and toe interface can inherit from surrounding soil. Default settings of the program can cope with most of the situation, however, accuracy is not too high
In-site test, like pile static load test with strain gauge set in different depth of pile, is necessary for “fine” analysis of pile foundation. We can gain strength and stiffness of skin interface though diagraph of shear displacement vs. skin force
To comply with design code, zero friction angle of pile skin interface is necessry
0
20
40
60
80
100
120
140
160
180
0 2 4 6 8 10 12 14
桩身位移(mm)
侧摩阻力(kPa)
C1013
C1354
C1882
S22
Skin force of pile
Shear displacement
Ultimate Strength
Average stiffness
Determine the strength and stiffness of skin interface
Functions related to Pile Foundation of ZSOIL.PCBorehole
Complex spatial distribution of soil “Borehole” function helps to generate
complex spatial distribution of soil material easily without 3D surface generated.
It is convenient to add boreholes any time to update spatial distribution, which can save us many hours too
Functions related to Pile Foundation of ZSOIL.PCBorehole + Pile element
All for the sake of Engineers Step 1: hide all the soil above the
bearing layer of pile Step 2: “select visible faces”, then all
the face of bearing layer is selected Step 3: “Macro model\Point\Project\On
selected faces in direction”, then all the pile toes stand on the bearing layer
Step 4: move the pile toes some distance into the bearing layer if necessary
It is very convenient to “stick” hundreds of piles on the bearing layer
Functions related to Pile Foundation of ZSOIL.PCNodal link
Set the mind free Super structure can be connected to
the foundation by nodal link, without compatible mesh
Very fine structure model can be avoided, which will significantly increase the number of the elements of the whole model
Structure model can be established in another file .It can be assembled with soil and foundation when necessary.
Practice of Pile Foundation TreatmentGeneral informationChallengePile static load test3D FEM analysis
Practice of Pile Foundation treatmentGeneral information
Information of super structure Frame shear wall structure, 26F(105m),
basement 2F(16.5m depth)
This building will be discussed
Practice of Pile Foundation treatmentGeneral information
Information of pile Pre-stressed concrete pipe pile(PHC), diameter 500mm, thickness 125mm,
length 30.0m(segment I :15m + segment II :15m), bearing capacity 2500kN Static piling method is used to drive the pile
Ground surface ,+30.86m
Bottom of basement ,+13.86m
Bottom of pile ,-16.14m
Pile length, 30m
PHC500, 15m length per segment
Static driving machine
Practice of Pile Foundation treatmentGeneral information
Layout of piles 594 PHC piles are employed to support
the gravity of the building “grid” type layout is used, for the
bearing capacity of each pile is not high enough
The distance between two neighboring piles is 2.0m, which is the min. pile spacing according to the code for Chinese pile foundation
Practice of Pile Foundation treatmentGeneral information
Information of geology conditions The site is mainly composed of silty clay (N/SPT=10~12, Ps/CPT= 1.5~2.5Mpa)
and middle sand (N/SPT=22~30, Ps/CPT= 10.0~15.0Mpa)
pile
Pile head level
Pile toe level
Sand, hard to penetrate
gravel, hard to penetrate
silty clay
6.96.96.86.8
6 6.6
6.56.46.76.7
6.8
66
6.3 6.3 6.3
6.7
6.96.4
6.86.9
6
6.86.6
6.9 6.6 6.8 6.1
6.86.86.76.86.86.9
6.96.2
6.36.4 6.5 6.8 6.6
6.2
6.4
6.7 6.7 6.9 6.8 6.3
Practice of Pile Foundation treatmentChallenge
According to the construction records, 200+ piles are shorter than design length (30m)
Irregularly distributed “hard layer” may be the reason7.07.57.0
7.47.5
7.5
7.3 7.5 7.4 7.5 7.3
7.6 7.3 7.3 7.4 7.3
7.5 7.5 7.3 7.5 7.4 7.37.77.7
7.6 7.8 7.7 7 7.1
7.2
7.2
7.3
7.3
7.4
7.27.1
7.27.17.77.67.6
7.5 7.5 7 7.2 7.2
7.17.27.17.5
7.5
7.27.27.2
7.1 7 7 7 7 7.2 7.2
7.47777
7 7 7
77
7.17.17777.2
79 piles are 7~8m shorter than design length 49 piles are 6~7m shorter
than design length
Practice of Pile Foundation treatmentChallenge
28 piles are 5~6m shorter than design length
5.75.1
5.7
5.4 5.3
5.65.6
5.5 5.5 5.6 5.8 5.3
84.55.55.35.3
5.5 5.4
5.55.5
6.2
5.5
5.95.55.15.35.9
4.7
4.3
4.6 4.5 4.4 4.5 4.5
4.3
4.2
4
44.5
4.2
4.2 4.1
4.54.14.2
18 piles are 4~5m shorter than design length
Practice of Pile Foundation treatmentChallenge
39 piles are 3~4m shorter than design length
3 3
3.63.73.2
33.1
3.6 3.4 3.7 3.5 3.6 3.43.13
3.1 3.2
3.4 3
3.3
3.2 3.1
3.2
3
3.4 3.3
3.43.33.1
3.1
3.4
3.0 3.2
3.2
3.9
3.9
3.2
3.7 3.7
2.4 2.4 2.4 2.4 2.4
2.42.42.42.4 2.4 2.4 2.4 2.4 2.42.4 2.4
2.1
2.82.9
2.82.8
2.7
2.4 2.3 2.7
2.92.72.82.72.8
2.7 2.8 2.8
2.1
2.9
2.1
22.7
2.6
2.12.5
2.6 2.3 2.9
2.92.82.9
2.32.7
2.32.42.42.7
2.4
2.4 2.5 2.6 2.4 2.9
61 piles are 2~3m shorter than design length
Practice of Pile Foundation treatmentChallenge
It seems impossible to drive additional piles into the ground to compensate the lack of bearing capacity. There is no room left, even for only 1 pile.
It seems impossible to move to another site to construct the building. Kidding?
Maybe our client has to reduce the height of the building. maybe
With so many “short” piles, is the foundation safe enough to support the load of the building?
Practice of Pile Foundation treatmentChallenge
How to help our client? We need to know the exact load applied to each pile. Super structure-foundation-soil interaction theory can be employed to
calculate the load of each pile. Pile static load test can be used to determine the real bearing capacity of
piles with different length, especially the shortest piles. We can judge the safety factor of each pile. We can calculate the settlement of the building.
Practice of Pile Foundation treatmentPile static load test
We select 7.0~8.0m shorter piles to implement pile static load test. If the bearing capacity of the shortest piles is OK, of course ,the capacity of other piles will be OK. Pile static load test
Steel beam
Hydraulic jacks
Practice of Pile Foundation treatmentPile static load test
0 1000 2000 3000 4000 500040
30
20
10
0
settl
emen
t (m
m)
Load (kN)
7m shorter
Three 7.0m shorter piles are selected to test. We select the shortest piles to
represent the whole piles. According to the diagraph of load vs.
settlement, the max. load of the test is about 4750kN.
The current bearing capacity of the tested pile is 4750/2=2375kN. The design bearing capacity is
2500kN. The current bearing capacity is about
5% smaller than the design value. Is the current bearing capacity
enough ? What the 3d FEM analysis tell us?
Practice of Pile Foundation treatment3D FEM analysis
Some details should be considered in the analysis The effective length of the piles ,bearing layer and the depth into the
bearing capacity are very different. The distribution of stiffness of the super structure will affect the settlement
value. The distribution of stiffness of the super structure will affect distribution of
the settlement of the foundation. The thickness of the raft will play the positive role of the settlement
compatibility between raft and piles.
Practice of Pile Foundation treatment3D FEM analysis
We implement the below when establish FEM model Pile element is used to model PHC pile. Pile skin and toe interface are
considered. The length of pile is set according to the construction record. For the
convenience of modeling, piles are classified to 7m, 5m and 3m shorter than design value.
Borehole method is used to determine the spatial distribution of soil layer. Mohr-coulomb model is used to descript soil mechanical behavior. The geometry of frame column and shear wall is set strictly according to
the structural design. The load applied to frame column and wall is set strictly according to the
structural analysis result.
Practice of Pile Foundation treatment3D FEM analysis
Load applied on wall and Frame column according to structural calculation result
Practice of Pile Foundation treatment3D FEM analysis
Frame columnwall
Shear wall
floor
floor
Frame column and wall are
connected to floor with “nodal link”
Practice of Pile Foundation treatment3D FEM analysis
Raft
Piles with different length(7m,5m,3m
shorter than design length)
Bearing layer of piles
Practice of Pile Foundation treatment3D FEM analysis
Max. settlement is about 5.85cm, which occurs at the corner of the shear wall core tube. This maybe the result of piles of
different length and irregularly spatial distribution of bearing layer.
Min. settlement is about 2.90cm. Max. settlement difference is about
2.95cm. Taking into account the width of the
raft(30m), the inclination of the building is about 0.1%.
The max. settlement and the inclination of the building meet the requirements of the standard(GB50007-2002).
Practice of Pile Foundation treatment3D FEM analysis
Axial force of pile head range from 520 to 2200kN. The average value is about 950kN. According to the pile static load test,
the calculated axial force of pile head (working load) is below the bearing capacity(2375kN).
The distribution of axial force of pile head is very different from our experience. According to our experience, max.
axial force of pile head usually occurs at corner and edge of the raft.
This maybe the result of piles of different length and irregularly spatial distribution of bearing layer.
Practice of Pile Foundation treatment3D FEM analysis
Analysis Summary According to 3D Fem analysis, the bearing capacity of short piles, the
settlement and inclination of the building can meet the requirement of Chinese foundation standard (“code for design of building foundation” GB50007-2002).
It is necessary to conduct super structure-foundation-soil interaction analysisfor irregularly spatial distributed soil layer and piles with different length. Sometimes, experience from horizontally stratified ground can not be transplanted
to irregularly spatial distributed soil layer. It is too conservative to design pile foundation without consideration of the
contribution of raft. With the help of the method mentioned above, we can optimize the design of pile
foundation.
Acknowledgements
Thanks to the development team of ZSOIL.PC help from ZACE since 2011/01/03
YIN JI
Email:[email protected]
For some reasons, not all of the details is published in the PPT. Ideas maybe important than numbers for geotechnical engineers.