best%practice%approaches% to%contamination

31
BEST PRACTICE APPROACHES TO CONTAMINATION INVESTIGATION AND REMEDIATION IN AUSTRALIA 2nd China Sustainable Environmental Remediation Conference Ian Brookman 09 June 2018

Upload: others

Post on 18-Dec-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

BEST  PRACTICE  APPROACHES  TO  CONTAMINATION  INVESTIGATION  AND  REMEDIATION  IN  AUSTRALIA

2nd  China  Sustainable  Environmental  Remediation  Conference

Ian  Brookman

09  June  2018

PRESENTATION  OUTLINE

1. Ventia  history  and  experience

2. Remediation   in  Australia

3. The  remediation   process

4. Key  challenges

Ventia - Remediation ServicesIndustry Leading position

Unrivalled track record

§ Australasia’s oldest and most experienced remediation contractor

§ Successfully completed over 145 of Australasia’s largest and most complex environmental projects over last 30 years including: – The Hunter River Remediation Project ($405M)– Union Carbide and Allied Feeds sites including

Homebush Bay ($140M)– Barangaroo Gasworks Project – Sydney ($125M –Current)

– Cheoy Lee Shipyards – Hong Kong ($65M)– Botany Carpark Waste Encapsulation Project

($63M)

REMEDIATION  IN  AUSTRALIA

AUSTRALIAN  REMEDIATION  MARKET  DRIVERS

The  current  Australian   environmental  services  market  is  largely  driven  by  • Land  redevelopment• Regulatory   compliance  • Major  infrastructure  projects

Community  pressures  help  drive  demand  for  quality   remediation

Emerging  contaminants   such  as  Per-­ and  Polyfluoroalkyl   Substances   (PFAS)  are  causing  national   problem  for  Commonwealth  agencies.

LARGE  REMEDIATION  PROJECTS   IN  AUSTRALIA    (AUD  $20M+    /    ¥100,000,000+)

Project Type Reason Value  ($M  AUD) Value  ¥  CNY

Hunter  River  Remediation   Project  (sediment) Industrial   FacilityRegulatory   Compliance   and  Resource  infrastructure 405 1,967,363,946

Barangaroo   (in  progress) Gasworks Urban  Renewal 121 587,780,339Former  Union   Carbide Site,   (Lednez)  Rhodes Chem Facility Urban  Renewal 81 393,476,344Cheoy Lee  Shipyards  -­ Penny's   Bay  Remediation,  Hong  Kong   Industrial  Facility Disneyland   HK 65 315,752,622West  Melbourne   Gasworks Gasworks Urban  Renewal 63 306,031,360Orica  Carpark Waste  Encapsulation Chem Facility Regulatory   Compliance 63 306,031,360Dandenong  Waste   Treatment   Plant Landfill   &  Hazwaste Regulatory   Compliance 50 242,882,031AGL  Mortlake  Gasworks Gasworks Urban  Renewal 47 228,309,110Allied   Feeds  Site,   Rhodes Chem Facility Urban  Renewal 47 228,309,110

Varsity  Lakes  Creek  Station Landfill   &  HazwasteRegulatory   Compliance   &  Transport  Infrastructure 44 213,736,188

Newstead   RiverPark Gasworks Urban  Renewal 38 184,590,344

Cape  Lambert   Landfill   Relocation Landfill   &  hazwasteRegulatory   Compliance   and  Resource  infrastructure 31 150,586,859

RANAD  Newington,   Silverwater Landfill   &  hazwaste Urban  Renewal   (Sydney  Olympics) 27 131,156,297Macdonaldtown   Gasworks  Remediation Gasworks Regulatory   Compliance 27 131,156,297

Cox  Peninsula   Remediation   Project  (Stages   1&2) Industrial   Facility Regulatory   Compliance 27 131,156,297Point   Cook  FTA Defence Regulatory   Compliance 27 131,156,297HMAS   Platypus Gasworks Regulatory   Compliance 24 116,583,375Homebush   Bay  Dioxin  Remediation Chem Facility Regulatory   Compliance 22 106,869,576

BASICS  OF  THE    ASSEMENT  AND  REMEDIATION  PROCESS  

SITE  ASSESSMENT  AND  REPORTING  

• Generally  undertaken  by  Environmental  consultants

• Normally  a  minimum  of  two  stages,  desk  top  and  sampling  if  site  history  indicates  the  potential  for  contamination.  

• A  good  assessment  will  include  • Site  history• Future  use    • Geology  and  hydrogeology• Contamination   (type,  concentration  and  distribution)

• Applicable   standards/criteria• Preliminary  quantities• Adequate   sampling  upfront  saves  time  and  money  in  the  long  run.    

REMEDIATION  DESIGN  

• Generally  completed  by  an  Environmental  consultant• Early  contractor  involvement  reduces  the  risk  of  rework• The  future  land  use  needs  to  be  agreed  prior  to  

moving  forward  with  the  remediation  design  • Various  approaches  should  be  considered  • Approvals  should  be  obtained  after the  remediation  

design  is  completed  • Approvals  should  be  outcome  based• A  good  remediation  design  will  consider  the  potential  

impact  of  the  works  and  include  mitigating  measures.  

Remediation  Technologies  and  solutions    

REMEDIATION  TECHNOLOGIES  &  SOLUTIONS  

• Containment  • Biological  • Chemical  /  physical

• Immobilisation• Chemical   oxidation

• Thermal

• Insitu  and  Exsitu

CONTAINMENT  /  ENCAPSULATION  • Appropriate   for  both  Inorganics  and  

organics• Onsite  encapsulation   utilising   Clay  and  

synthetic   liners,  drainage   layers,  capping.• landfilling   off  site  at  a  licenced   facility• Regulatory   limits  determine   if  treatment  is  

requirement• Does  not  destroy  contaminants  and  can  

limit  the  future  land  use  if  done  onsite.  

BIOREMEDIATION

• From  landfarming  through  to  engineered  cell• Simple  organics  to  moderately  complex  organics  – TPHs,  PAHs• Sensitive  to  contaminant  concentration  and  complexity• Duration  and  cost  variable

IMMOBILISATION

• Physical  or  chemical  treatment• Organics  and  inorganics• Immobilises,  does  not  destroy

THERMAL

• Organics  • Insitu or  exsitu,  batch  or  continuous• Direct  or  Indirect  • Destroys  or  condense  and  collect  

SUMMARY  REMEDIATION  APPROACHES

• Various   strategies  should  be  considered  

• Generally   the  “do  nothing”  approach  is  considered   the  cheapest,  however  be  aware  of  “consultant  creep”  

• “Dig  and  Dump”  is  quick  but  can  be  costly  

• “Contain”  can  be  more  cost  effective  but  could   limit  future  development  

• Treatment  is  generally   costly  but  deals  with  the  “legacy  of  contamination”

• “Bio”  is  inexpensive   but  can  be  unreliable

CHALLENGES  IN  REMEDIATION

ENVIRONMENTAL  (ODOUR  /  VOLATILES  CONTROL)    

• One  of  the  biggest  issues  with  community  and  stakeholder  is  odour

• Odour control  enclosures  are  common  on  projects  in  Australia

• Buildings  are  often  constructed  from  a  series  of  steel  trusses  covered  in  a  weather  proof  fabric  envelope

• Negative  pressure  

EMISSIONS  CONTROL  SYSTEM

• Removes  contaminated  air  from  within  Environmental  Control  Enclosures  (and  replaces  with  clean  air  from  the  outside)

• Treats  contaminated  air  through  particulate  and  activated  carbon  filters

ENVIRONMENTAL  MONITORING  (REAL  TIME)  

GEOTECHNICAL  • Often  overlooked  • Material  properties  key  in  treatment  selection  

• Could  decrease  or  increase  volumes  significantly  

OCCUPATIONAL  HEALTH  &  HYGIENE

• Appropriate  exposure  limits  established  

• Medical  assessments  for  workers  

• Comprehensive   inductions• Real-­time  Monitoring  for  chemicals  of  concern

• Biological  monitoring

COMMUNITY  ENGAGEMENT

Remediation  project  examples

THERMAL  DESORPTION  OF  HEXACHLOROBUTADIENE,  NSW

http://www.orica.com/Locations/Australia--Pacific-and-Indonesia/Australia/Botany-Remediation-Projects/Projects/Completed-Projects/Car-Park-Waste/remediation-works#.Whwu4VVsZ0w

LANDFILL  RELOCATION  –VARSITY  LAKES,  QLD.

Excavation, screening and relocation of 1,000,000m3 of domestic and hazardous waste

THERMAL  DESORPTION  OF  DIOXINS  – RHODES  PENINSULA,  NSW.  

$160m dioxin clean-up of former Union Carbide/ Allied Feeds sites and Homebush BayProject involved dredging and thermal treatment of bay sedimentsExtensive pollution control measures

REMEDIATION  OF  PENNY’S  BAY  (FORMER  CHEOY  LEE  SHIPYARDS)  HONG  KONG

Thermal treatment of 75,000t of dioxin-contaminated soilstabilisation of 130,000t of heavy metal wastebioremediation of 16,000t of hydrocarbon waste

CONCLUSION

• Improper  or  limited  site  characterization  is  the  cause  of  great  uncertainty  and  generally  leads  to  claims.  

• The  future  use  of  the  site  needs  to  be  agreed  prior  to  developing  the  remediation  strategy  

• Approvals  should  be  outcome  based  • Allocate  risk  appropriately  • Early  contractor  involvement  is  critical• Adequate  environmental  controls  can  save  you  money  and  time  in  long  run  

CONTAMINATED  LAND  INDUSTRY  CONFERENCE

• Sydney,  Australia.    October  02-­05  2018

• http://landandgroundwater.com/conference/2018-­ecoforum-­conference-­exhibition

IAN  BROOKMANMANAGER  – STRATEGY    ENVIRONMENTALSERVICES

M:  +61  418  524  671E  [email protected]    

谢谢