  • 7/30/2019 Besp Draft Evaluation Report 08

    1/50

    AN EVALUATION OF THE BASIC

    EDUCATION SUPPORT PROGRAMME II

    (BESP II: 2006-2008) IN THE TESO SUB-REGION

    FIRST DRAFT REPORT

    Submitted by:

    Henry Edison OkurutSchool of Education, Makerere University

    P.O.Box 7062, Kampala, Uganda.

    Tel. No. 0772 472 324E-mail:[email protected]/[email protected]

    October, 2008

    i

    mailto:[email protected]/[email protected]:[email protected]/[email protected]:[email protected]/[email protected]
  • 7/30/2019 Besp Draft Evaluation Report 08

    2/50

    ACKNOWLEDGEMENTS

    I would like to register my most sincere indebtedness to all categories of people who, in spite oftheir heavy duty schedules and many other odds, willingly spared their well budgeted time to

    engage me and my data collection team in a genuinely interactive and knowledge generating

    process.

    Indeed I was overwhelmed by the cooperation and understanding extended to us by the

    District/Municipal officials, the JAC and other core BESP staff, the church leadership, the headteachers, teachers, pupils, implementing partners and the satellite school communities located

    within the study area.

    Mr. J. Adweka, the executive secretary of the JAC and his co-secretary, Mr. J. Ojulun as well asFather Okurut merit special mention here for availing me most of the requisite documents and

    for expediting information gathering procedures through advance fixing of appointments with

    the key informants.

    I am also especially grateful to the entire staff in the BESP office for all the auxiliary support

    they readily gave us including the provision of transport within the study area andaccommodation in a favourable environment.

    i

  • 7/30/2019 Besp Draft Evaluation Report 08

    3/50

    ABSTRACT

    This report is an appraisal of the progress made in the 6 study districts and 1 municipal councilin the Teso sub-region to implement commitments to incremental access to quality primary

    school education as articulated in the vision and mission statements of the Basic Education

    Support Programme (BESP). It is informed by the documented district-specific experiences aswell as multi-stakeholder assessments and it draws on the background papers relating to the

    BESP initiative to help generate baseline information; highlight the existent achievements,

    prospects and challenges in the roll-out of the BESP process; establish linkages between theeducational gains made in the BESP schools and the programme reforms; map out the

    unfinished BESP agenda and propose a more tailored roadmap for advocacy in the lead up to a

    possible BESP III.

    ii

  • 7/30/2019 Besp Draft Evaluation Report 08

    4/50

    LIST OF ACRONYMS

    ADECs Archdeaconry Education CommitteeASEI Activity, Student, Experiment, Improvisation

    BERP Basic Education Rehabilitation Programme

    BESP Basic Education Support ProgrammeCCTs Centre Coordinating Tutors

    CEREDO Catholic Education Research and Development

    OrganizationCL Collaborative Learning

    COU Church of Uganda

    DEOs District Education Officers

    EMIS Education Information Management SystemHIV/AIDS Human Immunity Virus/Acquired Immunity

    Deficiency Syndrome

    JAC Joint Advisory Committee

    JICA Japan International Cooperation AgencyLCs Local Councils

    M&E Monitoring and EvaluationMoES Ministry of Education and Sports

    MoWLE Ministry of Water, Lands and Environment

    MS Media SupplementOVC Orphans and Vulnerable Children

    PCR Pupil Classroom Ratio

    PECs Parish Education Committees

    PLE Primary Leaving ExaminationsP/S Primary School

    PSDI Plan, Do, See and Improvise

    PTAs Parents Teachers AssociationsPTC Primary TeachersColleges

    PTR Primary Teachers Colleges

    ROM Results Oriented ManagementSMASSE Strengthening of Mathematics and Science in

    Secondary Education

    UNEB Uganda National Examinations Board

    iii

  • 7/30/2019 Besp Draft Evaluation Report 08

    5/50

    EXECUTIVE SUMMARY

    1.1 Background

    The BESP II is the culmination of a process that evolved from the operationalization of the BasicEducation Rehabilitation Programme (BERP: 1997 - 2002) in the then 3 districts of the Teso

    sub-region - Soroti, Kumi and Katakwi. It is the BERP which, in turn, begot Basic Education

    Support Programme I (BESP I: 2003 - 2005). This marked the beginning of a shift away from a

    focus on a rehabilitation concern to educational improvement mandate.

    1.2 Objectives of the evaluation

    (i) Review the progress made in basic education service delivery under the BESP II;

    (ii) Assess the relationship between the BESP and other actors in education;

    (iii) Gauge the relationship between the two partner churches which are jointly managingthe BESP;

    (iv) Critique the logic for the joint management of the BESP and present a case for the

    extension of a similar arrangement to the other sister church programmes; and(v) Recommend the way forward for BESP as well as other church programmes.

    1.3 Methodology

    The evaluation relied on a triangulated data collection strategy involving documentary analysis,

    key informant interviews, focus group discussions and non-participant observation that were

    employed in a mutually supportive manner.

    1.4 Findings of the BESP evaluation

    1.4.1 Implementation of the planned BESP activities

    The 2006-2008 BESP interventions can be broken down into the following performancecategories:

    Over performance (i.e. above 100%) 2006

    a) Training of trainers 113%

    b) Training of ADECs, PECs and the clergy 560%

    c) Mobilization of school community 1418%

    d) Holding scheduled inter-church meetings 119%e) Staff attendance of the scheduled national/regional meetings 200%

    High performance (51 100%) - 2006

    a) Development of materials for CL 70%

    b) Facilitation of school inspectors, ADECs, PECs 100%

    c) Holding school inspection review meetings 67%d) Collection and analysis of educational data 100%

    iv

  • 7/30/2019 Besp Draft Evaluation Report 08

    6/50

    e) Development of lobby/publicity materials 100%

    f) M&E in model schools 100%

    g) Timely payment of staff salaries 100%h) Purchase and maintenance of equipment/office stationery 100%

    i) Payment for utilities, bank charges and audit fees 100%

    Underperformance (0 50%) - 2006

    a) Taining of teachers 37%

    b) Holding radio talk shows 42%c) Training of key staff on advocacy skills 20%

    d) Training of community leaders on advocacy 44%

    It is noteworthy that, there were no worst case scenarios of non-performance throughout 2006.

    Save for the disturbance caused by the 2007 floods, a similar pattern in the roll out of the BESP

    implementation process was observable in the 2007 Financial Year and the first two quarters of

    2008.

    1.4.2 Contribution of the BESP to the improvement of access and quality as well as

    efficiency of basic education

    a) Access/equity indicators

    (i) Total primary school enrollment in the whole sub-region rose from 352,970 (.boys and

    .girls) in 2006 to 417,031 (.boys and .girls) in 2007, which translates into an

    enrollment growth rate of 10.8% and an improvement in the gender parity index

    fromin 2006 to in 2007.(ii) The number of schooling orphans in Teso has also risen from 19,252 (9,751 boys and

    9,501 girls) in 2006 to 57,706 (29,506 boys against 28,140 girls) in 2007,

    representing an increment of 300%.

    b) Quality indicators

    (i) Restoration of the degenerate professional status of the primary school teacher throughin-service training, with the head teachers giving the BESP sponsored in-service

    training programmes a performance rating of 81.3%

    (ii) Teachers are increasingly embracing the more interactive collaborative learning (CL)

    instructional approach which enjoys 100% popularity with the pupils.(iii) The number of pupils scoring Division 1 in PLE slightly rose from 414 (298 boys and

    116 girls) out of 19,329 candidates in 2006 to 449 (313 boys and 136 girls) out of

    55,622 candidates in 2007. In proportionate terms however, there was an overalldecline in Division 1 passes from 2.1% in 2006 to a paltry 0.8% in 2007. And in both

    cases, boys continue to dominate in the good grades.

    (iv) The PTR rose from 49.0 in 2006 to 66.2 in 2007, with the latter exceeding thenational PTR of 1:55 by 11.2 percentage points.

    (v) Similarly, the PCR rose from 70 in 2006 to 82.9 in 2007.

    v

  • 7/30/2019 Besp Draft Evaluation Report 08

    7/50

    c) Efficiency indicators

    (i) The number of primary school children repeating a grade in Teso dropped from 111,768(45,497 males and 66,271 females) in 2006 to 95,671 (48,770 males and 46,901

    females) in 2007 a 16.8% reduction.

    In addition, there have been significant reductions in teacher absenteeism, improved school

    attendance and upgraded school management capacity.

    1.4.3 The contribution of the BESP to the enhancement of managerial/technical capacities

    (i) Improvements in the church institutional structures as the BESP necessitated the adoption

    of a merger/unitary management structure that has improved operational efficiency atall levels through its contribution to:

    An enriched skills-mix;

    Improved scope for greater division of labour and specialization;

    Improved quality of decisions arrived at; The elimination of wasteful competition and duplication of service; and

    Greater economies of scale

    (ii) Stimulation of the urgency for training programmes and other capacity building back

    ups, especially because the BESP had effectively brought on board a wider variety of

    non-state actors (ADECs, PECs, the clergy, e.t.c.) to participate in schoolmanagement activities.

    (iii) Reduced reliance of the programme on external technical assistance. There is now

    adequate local expertise to undertake research, M&E, plan and draw up work plans.(iv) Firm placement of the school communities in the drivers seat and there is raised

    grassroots consciousness about school corruption and sharpened financial probity.

    Consequently, most school expenditures represent value for money. There isincreased prioritization and responsiveness to school community-led programmes and

    recognition of the need for greater flexibility to cater for differentiated school

    community concerns.

    However, from a purely M&E perspective, the school communities are too pre-occupied with

    only tracking school expenditures and monitoring staff behaviour and responsibilities rather than

    ascertaining the planned educational outcomes (i.e the downstream effects of the BESP).

    1.4.4 The role of the BESP in the promotion of inter-church cooperation and partnership

    with the other actors

    The BESP joint reviews have broadened the scope for:

    (i) Ensuring commonality of interest between the BESP and implementing partners becausesuch reviews provide a clear framework for their cooperation;

    (ii) Regular consultation among the partners;

    (iii) Transparency and accountability. This is being achieved through quarterly progress

    reporting, regular audits and joint decision-making;(iv)Expedited implementation of jointly planned activities e.g M&E;

    vi

  • 7/30/2019 Besp Draft Evaluation Report 08

    8/50

    (v) Strengthened process of dialogue, coordination and support for basic education;

    (vi)Putting the school communities in the drivers seat; and reduction of transactional

    costs(vii) Increased rapport between the Catholic and Protestant churches of Teso.

    1.5 Constraints and challenges

    (i) The BESP still has limited service reach;

    (ii) It has remained confined to the primary sub-sector and is largely invisible at postprimary level;

    (iii) The BESP logic and philosophy is sometimes at odds with contradictory policy

    pronouncements made by some government officials;(iv) The programme is getting overwhelmed with its self-created enrollment bulge;

    (v) There is an acute shortage of instructional materials suitable for delivering the new

    thematic curriculum;

    (vi) The BESP agenda is silent about the special learning needs of children with

    disabilities;(vii) There is a persistent problem of school drop outs, high repetition rates and poor

    performance in the UNEB examinations particularly among the girls;(viii) Teso sub-region is prone to the destabilizing effects of the wars, cattle rustling and

    natural hazards (e.g. 2007 floods);

    (ix) It is difficult to rectify the trauma and psycho-social damage visited on the localpopulation within a relatively short time frame. Consequently, there are still pockets

    of community indifference to the BESP and generalized apathy;

    (x) BESPs resource envelope is relatively limited leading to underperformance or non-

    performance of some planned programme activities;(xi) It is being accused of placing disproportionate emphasis on in-service Primary

    Teacher Training at the expense of the pre-service training programme;(xii) Its continued dependence on outside financial assistance undermines independentdecision-making and the future sustainability of the BESP;

    (xiii) The presence of overage pupils in some primary schools, especially in Kobuin sub-

    county complicates the enforcement of school discipline, elimination of bullying, thefight against HIV/AIDS, e.t.c;

    (xiv) The two sister churches are hesitant about extending the cost-efficient BESP

    experiment to cover their other projects/programmes and instead continue to operateless cost-efficient parallel management structures;

    (xv) The BESP is said to suffer from too much localization and context-specificity and

    this compromises the prospects for its roll out and replication in the other areas of the

    country; and(xvi) Under-representation of the female teachers in the total primary school teaching

    workforce in the Teso sub-region denies the girl child the benefits arising from the

    role model image which they would provide.

    vii

  • 7/30/2019 Besp Draft Evaluation Report 08

    9/50

    1.6 The way forward for the BESP III (2009 - 2011)

    The recommendations for the design of BESP III are derivatives of the constraints andchallenges highlighted above. Accordingly, they mainly relate to the educational access and

    quality concerns, the education of the girl child, capacity enhancement and the streamlining of

    managerial structures.

    viii

  • 7/30/2019 Besp Draft Evaluation Report 08

    10/50

    TABLE OF CONTENTS

    CHAPTER ONE: INTRODUCTION..............................................................................................1

    1.0 Historical context-------------------------------------------------------------------------------------1

    1.1 Evolution of the BESP process----------------------------------------------------------------------1

    1.2 Broad objectives of the BESP II---------------------------------------------------------------------11.3 Specific objectives of the BESP II------------------------------------------------------------------1

    1.4 Implementation strategy------------------------------------------------------------------------------2

    1.5 Objectives of the evaluation--------------------------------------------------------------------------21.6 Methodology-------------------------------------------------------------------------------------------2

    1.7 Rationale for the BESP II evaluation---------------------------------------------------------------3

    CHAPTER TWO: THE SUB-REGIONAL CONTEXT.................................................................42.0 Introduction---------------------------------------------------------------------------------------------4

    2.1 Location-------------------------------------------------------------------------------------------------4

    2.2 Vegetation----------------------------------------------------------------------------------------------4

    2.3 Climate--------------------------------------------------------------------------------------------------4

    2.4 Soils-----------------------------------------------------------------------------------------------------42.5 The socio-economic profile--------------------------------------------------------------------------4

    CHAPTER THREE: IMPLEMENTATION OF THE BESP ACTIVITIES (2006-2008)..............53.0 Introduction---------------------------------------------------------------------------------------------5

    3.1 The roll-out and outputs of the BESP II in 2006--------------------------------------------------5

    3.2 Implementation and outputs of BESP II in 2007--------------------------------------------------6CHAPTER FOUR: EFFECTIVENESS AND EFFICIENCY OF THE BESP.............................12

    4.0 Introduction-------------------------------------------------------------------------------------------12

    4.1 Improvement in access/equity indicators---------------------------------------------------------124.2 Improvement in quality indicators-----------------------------------------------------------------14

    4.2.1 Quality of teaching........................................................................................................14

    4.2.2 Pupils performance results...........................................................................................154.2.3 Pupil Teacher Ratios.....................................................................................................184.2.4 Pupil Classroom Ratios (PCRs)....................................................................................19

    4.3 Improvement in relevance and effectiveness-----------------------------------------------------20

    4.4 Improvement in efficiency indicators-------------------------------------------------------------20CHAPTER FIVE: AN APPRAISAL OF BESPs INSTITUTIONAL ARRANGEMENTS,

    CAPACITY BUILDING AND PARTNERSHIPS.......................................................................24

    5.0 Introduction-------------------------------------------------------------------------------------------245.1 Establishment of the BESP management structures---------------------------------------------24

    5.1.1 A Joint Top Executive..................................................................................................24

    5.1.2 The Joint Advisory Committee (JAC)..........................................................................24

    5.1.3 The Joint Programme Secretariat..................................................................................255.2 Evaluation of BESPs management structures---------------------------------------------------26

    5.2.1 Strengths.......................................................................................................................26

    5.2.2 Limitations....................................................................................................................275.3 Contribution of the BESP to Efficiency/Institutional and Human Capacity Building------27

    5.3.1 Stimulation of training programmes and other human capacity back-ups...................28

    5.3.2 Reduced reliance on external technical assistance .......................................................28

    ix

  • 7/30/2019 Besp Draft Evaluation Report 08

    11/50

    5.3.3 The contribution of the BESP to increased partnership and cooperation between the

    stakeholders............................................................................................................................29

    5.4 Analysis of BESPs Good Practice----------------------------------------------------------------29CHAPTER SIX: LESSONS LEARNT, CHALLENGES AND RECOMMENDATIONS..........30

    6.0 Introduction-------------------------------------------------------------------------------------------30

    6.1 Lessons Learnt----------------------------------------------------------------------------------------306.2 Conclusions-------------------------------------------------------------------------------------------30

    6.3 Challenges---------------------------------------------------------------------------------------------31

    6.4 Opportunities-----------------------------------------------------------------------------------------326.5 The Recommendations for the BESP III (2009 - 2011)-----------------------------------------33

    6.5.1 Relating to access/equity...............................................................................................33

    6.5.2 To address education quality issues..............................................................................33

    6.5.3 Concerning efficiency and managerial capacity...........................................................346.5.4 Pertaining to the education of the girl child..................................................................34

    REFERENCES..............................................................................................................................35

    x

  • 7/30/2019 Besp Draft Evaluation Report 08

    12/50

    LIST OF TABLES

    Table 1: Over performance (i.e. above 100%).................................................................................5Table 2: High performance (51 100%).........................................................................................5

    Table 3: Underperformance (0 50%)............................................................................................6

    Table 4: Over Performance (over 100%) - 2007.............................................................................6Table 5: High Performance (51-100%) - 2007................................................................................7

    Table 6: Underperformance (0-50%) - 2007...................................................................................7

    Table 7: Non-performance (0%) - 2007...........................................................................................8Table 8: Over Performance (over 100%) - 2008.............................................................................9

    Table 9: High Performance (51 100%) - 2008..............................................................................9

    Table 10: Underperformance (0 50%) - 2008.............................................................................10

    Table 11: Non-performance (0%) - 2008.......................................................................................11Table 12: Percentage number of pupils with adequate sitting and writing space in Teso sub-

    region 2006-2007...........................................................................................................................13

    Table 13: Number of orphans in Teso sub-region by gender 2006-2007......................................13

    Table 14: Table..: Head teachers assessment of the BESP interventions.....................................14Table 15: Table: Pupils assessment of the classroom performance of their class teachers......15

    Table 16: Table..: PLE results by district and gender in Teso sub-region, 2006...........................16Table 17: Table: PLE results by district and gender in the Teso sub-region, 2007...................16

    Table 18: Table: Summary of PLE results by gender in Teso region, 2006-2007....................17

    Table 19: Pupil Teacher Ratios (PTRs) in Teso sub-region, 2006-2007.......................................18Table 20: Pupil Classroom Ratios in the Teso sub-region, 2006-2007.........................................19

    Table 21: Number of primary school repeaters by class in Teso sub-region, 2006.......................20

    Table 22: Number of primary school repeaters by class in Teso sub-region, 2007.......................21

    Table 23: Consolidated summary of the number of primary school repeaters in Teso sub-region,2006-2007......................................................................................................................................21

    LIST OF FIGURES

    Figure 1: The criteria for evaluating the contribution of the BESP to the improvement inaccess/equity and quality/efficiency of primary education in Teso...............................................12

    xi

  • 7/30/2019 Besp Draft Evaluation Report 08

    13/50

    Figure 2: UNEB figures for Teso region 2006-2007.....................................................................17

    Figure 3: PTR in Teso region 2006-2007......................................................................................18

    Figure 4: PCR in Teso region 200-2007........................................................................................19Figure 5: Number of repeaters in Teso region 2006-2007.............................................................22

    Figure 6: Repeaters in Teso region by class 2006.........................................................................22

    Figure 7: Repeaters in Teso region by class 2007.........................................................................22Figure 8: BESP Implementation and Management structure........................................................25

    Figure 9: Criteria for evaluating the contribution of the BESP to Institutional Capacity Building

    ........................................................................................................................................................27

    xii

  • 7/30/2019 Besp Draft Evaluation Report 08

    14/50

    LIST OF ANNEXES

    Annex 1: Terms of Reference (ToT)

    Annex 2: The Interviewees

    xiii

  • 7/30/2019 Besp Draft Evaluation Report 08

    15/50

    CHAPTER ONE: INTRODUCTION

    1.0 Historical context

    The impact of two decades of devastating civil strife and war in northern and north eastern

    Uganda (Teso sub-region inclusive) was evident in the near total breakdown of the physicalinfrastructure and social services in the conflict areas. With regard to education provision, there

    was massive vandalization of school infrastructure and equipment, depletion of vital human

    resources, traumatization of school children and the inevitable downturn in all the key indicatorsof access, equity, quality and efficiency (BESP Secretariat : 2008. 4).

    The enormity and complexity of the challenges of resuscitating education service delivery insuch a post-conflict setting called for a different type of response, which the Ministry of

    Education and Sports (MoES) alone was incapable of providing. It is within that context that

    other non-government actors including NGOs, civil society organizations, faith-basedorganizations and international agencies decided to help mitigate the existent educational

    problems (MoES : 2008. 27).

    The Basic Education Support Programme (BESP) is one such intervention with coverage of theTeso sub-region. It is a collaborative initiative by the Catholic Church and Church of Uganda

    Soroti Dioceses.

    1.1 Evolution of the BESP process

    The BESP II (2006 - 2008) is the culmination of a process that evolved from theoperationalization of the Basic Education Rehabilitation Programme (BERP: 1997 - 2002) in the

    then 3 districts of the Teso sub-region - Soroti, Kumi and Katakwi. It is the BERP which, in turn,

    begot Basic Education Support Programme I (BESP I: 2003 - 2005). This marked the beginningof a shift away from a focus on a rehabilitation concern to educational improvement mandate.

    1.2 Broad objectives of the BESP II

    The BESP II has the twin purpose of:

    (i) Scaling up equitable access to quality as well as cost-efficient basic education in the

    target sub counties.(ii) Enhancing the capacity of the Joint Advisory Committee-JAC- (BESPs highest

    management organ), implementing partners and other education stakeholders to

    effectively manage educational interventions in the Teso sub-region (BESP : 2007. 2).

    1.3 Specific objectives of the BESP II

    More pointedly, the BESP II agenda seeks to enhance the quality and cost-effectiveness of

    educational investments in the sub-region by achieving greater:

    (i) School community ownership;

    (ii) Poverty reduction focus;

    1

  • 7/30/2019 Besp Draft Evaluation Report 08

    16/50

    (iii) Alignment of the BESP interventions with the national educational/development

    policy frameworks;

    (iv) Shift away from donor generated stand alone educational project modality toparticipatory programming, networking and pooling of resources;

    (v) Gender parity in education and sensitivity to the educational needs and concerns of

    the vulnerable children;(vi) Mutual accountability for the educational outcomes; and

    (vii) Higher job performance ratings for the head teachers, teachers, the core BESP

    staff, implementing partners and the church leadership through training and othercapacity building back-ups.

    1.4 Implementation strategy

    The operational approach for the accomplishment of the stipulated objectives involves:

    (i) Promotion of strategic partnerships, advocacy and networking;

    (ii) Capacity building initiatives particularly for the members of the School Management

    Committees (SMCs), selected district staff, the JAC, and other implementing partnersas well as stakeholders;

    (iii) In-service training for teachers;(iv) Performing an oversight role - supervising, inspecting and monitoring school

    activities;

    (v) Strengthening core-decision making and planning through establishment of moredependable school data banks and an integrated Education Management Information

    System (EMIS);

    (vi) The pooling of resources and expertise through multi-actor participation; and

    (vii) The localization or geographical concentration of effort for maximum effect.

    1.5 Objectives of the evaluation

    (i) Review the progress made in basic education service delivery under the BESP II;

    (ii) Assess the relationship between the BESP and other similar educational initiatives in

    the area;(iii) Gauge the relationship between the two partner churches which are jointly managing

    the BESP;

    (iv) Critique the logic for the joint management of the BESP and present a case for theextension of a similar arrangement to the other sister church programmes; and

    (v) Recommend the way forward for BESP as well as other church programmes.

    1.6 Methodology

    Actual data collection was largely pursued along two triangulated fronts, namely:

    (i) An extensive and intensive literature search and review process; and(ii) Direct field-based sourcing of primary data using semi-structured questionnaires for head

    teachers, teachers and P7/P6 pupils; an unstructured discussion guide for the client

    communities; semi-structured interview schedules for the JAC, SMCs, churchleaders, district staff and representatives of the other sister agencies. Additional

    2

  • 7/30/2019 Besp Draft Evaluation Report 08

    17/50

    information was tapped through informal discussions with stakeholders and non-

    participant observation.

    1.7 Rationale for the BESP II evaluation

    While the BESP II has almost run its full course, its performance has hitherto not beenindependently audited to:

    (i) Have an inventory of its impact on the teaching/learning activities thus far;

    (ii) Ascertain the prospects for rolling it out to all areas within the sub-region and beyond;(iii) Generate baseline data for projecting future requirements; and

    (iv)Feed into a possible BESP III (2009 - 2011) by suggesting its priority areas as well as

    better ways of harmonizing and boosting the efficiency of the church structures andprogramme activities.

    The findings of this evaluation are therefore meant to close such knowledge deficits and provide

    a platform for the formulation and adoption of BESP III as a more tailor-made response.

    3

  • 7/30/2019 Besp Draft Evaluation Report 08

    18/50

    CHAPTER TWO: THE SUB-REGIONAL CONTEXT

    2.0 Introduction

    This section examines the underlying contextual factors that inform effective programming and

    which have a direct bearing on the design, implementation, achievements and shortcomings ofthe BESP in Teso.

    2.1 Location

    The traditional geographic or ecological Teso sub-region covers the districts of Amuria,

    Katakwi, Soroti, Kumi, Bukedea and Kaberamaido located in North Eastern Uganda. However,since it also suffered under the 20 year period of insurgency (1986 - 2006), it is simultaneously

    considered to be part of the political definition of Northern Uganda.

    2.2 Vegetation

    This is mainly of the savannah grassland variety with dotted trees and shrubs and swampyenclaves.

    2.3 Climate

    The sub-region is characterized by a bimodal type of rainfall with peak periods falling in the

    months of May-June and September-October with an annual average of 1,300 mm (MoWLE :

    2007). However, the sub-region is prone to pronounced erratic weather conditions withsometimes excessive rainfall leading to water clogging or lack of rainfall resulting in aridity.

    2.4 Soils

    The soils throughout the sub-region are predominantly ferralitic sandy loams which can support

    agricultural production of fast maturing cereals, leguminous and tuber crops. However, the soilsgradually change to a patchy sandy category and clay loams as you move towards swamps.

    2.5 The socio-economic profile

    The main economic activities include peasant agriculture, livestock farming and some fishing.

    However, two decades of armed conflict and cattle rustling disturbed the economy of the area

    leading to a complex situation of human deprivation in the Teso sub-region. Peoples livingconditions are pathetic especially in the insecurity-prone districts of Amuria and Katakwi

    (Uganda Humanitarian Situation Report: 1 30 th June, 2008).

    4

  • 7/30/2019 Besp Draft Evaluation Report 08

    19/50

    CHAPTER THREE: IMPLEMENTATION OF THE BESP

    ACTIVITIES (2006-2008)

    3.0 Introduction

    This section presents an appraisal of the progress made in the implementation of the BESP II

    activities during the two and half year period (2006-2008) against the backdrop of the planned

    performance targets.

    3.1 The roll-out and outputs of the BESP II in 2006

    A summary of the progress made in the execution of the 2006 BESP II activities reveals at leastfour identifiable performance ratings, namely: the over performance, high performance, under

    performance and non performance categories. This is as depicted in the log frames below:

    Table 1: Over performance (i.e. above 100%)SN Programme Activity Planned Output Actual Output Estimated

    Performance Rating

    (%)

    1 ToT workshop 60 Inspectors, CCTs 68 Inspectors, CCTs 113

    2 Training of ADECs, PECs

    and clergy on supervision

    40 APECs, PECs and

    clergy

    264 APECs, ADECs and

    clergy

    560

    3 Mobilization of school

    community leaders

    60 school community

    leaders

    851 school community

    leaders

    1418

    4 Holding JAC and inter-

    church meetings

    4 JAC meetings and 12

    inter church meetings

    8 JAC meetings and 11

    inter church meetings

    119

    5 Staff to attend 3 national

    meetings

    2 people to attend 3

    national meetings

    4 people attended 3

    national and 3 regional

    meetings

    200

    Table 2: High performance (51 100%)

    SN Programme Activity Planned Output Actual Output Performance

    Rating (%)

    1 Development of materials for CL 1000 copies 700 copies 70

    2 Facilitation of Inspectors,

    ADECs, PECs

    100 persons 100 persons 100

    3 School supervision review

    meetings

    3 review meetings 2 review

    meetings

    67

    4 Collection and analysis of

    educational data

    60 schools 60 schools 100

    5 Development of brochures,calendars, media supplement

    2000 brochures, 500 calendars,1MS

    Fullyaccomplished

    100

    6 Termly planning, M&E in modelschools

    60 model schools Fullyaccomplished

    100

    7 Timely payment of salaries forBESP staff

    10 BESP staff Fullyaccomplished

    100

    8 Purchase and maintenance ofequipment

    1 vehicle, 2 motorcycles, 2computers, 2 projectors and 2

    digital cameras

    Fullyaccomplished

    100

    5

  • 7/30/2019 Besp Draft Evaluation Report 08

    20/50

    SN Programme Activity Planned Output Actual Output Performance

    Rating (%)

    9 Purchase of office stationery An assortment Fully

    accomplished

    100

    10 Payment for utilities All available utilities Fullyaccomplished

    100

    11 Payment of bank charges andaudit fees All bank charges and audit fees Fullyaccomplished 100

    Table 3: Underperformance (0 50%)

    SN Programme Activity Planned Output Actual Output Performance Rating (%)

    1 Training of teachers 2000 747 37

    2 Holding radio talk shows 12 times 5 times 42

    3 Training key staff on advocacy 10 persons 2 persons 20

    4 Training community leaders on advocacy 600 leaders 264 leaders 44

    While, on the whole, the BESP performance during 2006 was commendable, a weighted analysis

    of the data entries above reveals that, the majority of the over performance and high performanceratings were on activities that indirectly contribute to pupils learning achievement.

    Conversely, the training of teachers which directly impacts the outcomes of classroom processes

    underperformed at 37%. And even among the high performance category of the BESP activities,

    some similarly critical interventions including the development of instructional materials forinteractive learning fell short of the target output level (67% instead of 100%).

    Such a resource allocation formula that appears to prioritize implementation of auxiliary asopposed to core support services undermines the cost-effectiveness of the BESP.

    It is noteworthy that, there were no worst case scenarios of non-performance throughout 2006.

    3.2 Implementation and outputs of BESP II in 2007

    With regards to 2007, the graded performance of the BESP is as follows:

    Table 4: Over Performance (over 100%) - 2007

    SN Activities Planned Outputs Actual Output Performance

    Rate

    1 Attending National

    meetings.

    2 people to attend 3 national

    meetings

    3 national and 3 regional

    meetings attended by 4

    people

    200%

    2 Conduct skills trainingfor ADECs and PECs to

    provide technical support

    and support supervision

    40 ADECs and PECs to betrained on technical support and

    supervision of primary school

    teachers.

    11 parishes have beencovered, 40 ADECs and

    99 PECs have been trained

    on provision of technical

    support and supervision in

    primary schools

    More than300%

    6

  • 7/30/2019 Besp Draft Evaluation Report 08

    21/50

    Table 5:High Performance (51-100%) - 2007

    SN Activities Planned Outputs Actual Output Performance Rate

    1 Conducting ToT

    workshop for school

    inspectors and CCTs

    on curriculum

    interpretation and CLlearning approach

    ToT workshop to be conducted

    for 60 school inspectors and

    CCTs on curriculum

    interpretation and CL learning

    approach.

    20 school inspectors and

    40 CCTs trained on

    curriculum

    interpretation, CL

    learning approaches

    66%

    2 Purchase of bicycles

    to support school

    supervision

    monitoring

    40 bicycles to be purchased for

    PECs and ADECs to support

    monitoring and supervision

    40 bicycles were

    purchased and

    distributed to 40 selected

    parishes and

    archdeaconries

    100%

    3 Conducting joint

    termly reviews ofschool inspection

    and supervision

    3 Joint termly reviews of school

    inspection and supervision to beheld

    3 Joint termly reviews of

    school inspection andsupervision held

    100%

    4 Mobilizing the

    school communitiesto actively

    participate in

    governance issues

    300 local school community

    leaders (SMCs, PTAs and LCs)from 6 sub-counties were to be

    trained on development and

    implementing school plans,

    budget and expenditure

    tracking, monitoring and

    evaluation of school activies,

    research, lobby and advocacy

    and policy dialogue

    256 local school

    community leaders (51female and 205 male)

    were trained.

    85%

    5 Payment of staff

    salaries

    Payment of salaries for14 BESP

    staff

    Salaries for 14 BESP

    Staff were regularly and

    promptly paid

    100%

    6 Purchase of Office

    stationery and

    equipment

    Office stationery/equipment

    were to be purchased and

    regularly maintained

    Assorted stationery was

    purchased and 3

    vehicles, 2 motorcycles,2 LCD projectors, 2

    digital cameras,2 photo-

    copiers, computers and

    other accessories were

    regularly maintained

    100%

    7 Office Maintenance 2 offices regularly maintained Both offices were

    regularly maintained

    100%

    8 Installation of

    computers for DEOs

    2 computers 2 computers were

    purchased and

    distributed to Amuria

    and Bukedea

    100%

    Table 6: Underperformance (0-50%) - 2007SN Activities Planned Outputs Actual Output Performance Rate

    1 Organize JAC meeting for

    reviewing and up dating of

    BESP activities and Programmesadvocacy and policy

    3 JAC meeting to

    up date operational

    policies.

    A JAC staff training

    workshop on

    OrganizationDevelopment and

    Corporate Imaging.

    44%

    2 Training 600 local school

    community leaders on research,

    600 local school

    community leaders

    264 school community

    leaders trained on

    7

  • 7/30/2019 Besp Draft Evaluation Report 08

    22/50

    SN Activities Planned Outputs Actual Output Performance Rate

    lobby, advocacy and Monitoring

    and Evaluation

    trained on research,

    lobby, advocacy

    and Monitoring

    and Evaluation

    research, lobby,

    advocacy and

    Monitoring and

    Evaluation

    3 Holding 36 radio talk shows to

    sensitize 60 primary schools toactively participate in

    educational governance issues

    12 radio talk shows

    held targeting 60community schools

    5 radio talk shows were

    conducted on Voice ofTeso FM radio station

    targeting 60 schools

    communities mobilized.

    33%

    4 Develop training content and

    materials

    4000 teachers

    trained on

    curriculum

    interpretation and

    CL approach

    474 teachers in 34

    selected schools in

    Kumi, Kaberemaido

    Bukedea and Soroti

    Districts were trained onCL

    12%

    5 Training of 10 key staff of BESP

    on methods of conducting lobby,

    10 staff trained on

    methods of

    conducting lobby,advocacy and

    policy dialogue

    Two staff are currently

    persuing master degrees

    in the areas ofManagement and

    Development Studies

    20%

    6 Payment of Financial services Prompt payment of

    bank charges and

    audit fees was to

    be done

    Bank charges were

    regularly met but

    audit exercise is yet to

    be carried out

    50%

    7 Facilitating inspectors, CCTs,

    ADECs and PECs to carry out

    termly school inspection and

    supervision

    20 inspectors, 40

    CCTs, 40 ADECs

    and PECs to be

    provided with fuel,

    SDA and

    stationery to carry

    out school

    inspection

    BESP facilitated 35

    inspectors, CCTs, and

    BESP staff with fuel,

    Safari-day allowances

    and stationery

    Underperformed

    Table 7:Non-performance (0%) - 2007

    SN Activities Planned Outputs Actual Output Performance

    Rate

    1 Organize a workshop to developa holistic M and E plan for JAC-

    BESP to monitor and evaluate

    their activities

    Workshop conducted in2006

    2 Conduct review meeting forstrategic plan

    A meeting toreview the

    strategic plan was

    to be held

    The review meeting forthe strategic plan was

    not conducted

    0%

    Compared to the 2006 outturns, the BESP performance in 2007 was a little wanting as a goodnumber of the intended interventions were underperformed or not implemented altogether. The

    reasons advanced to explain this shortfall ranged from ambitious planning and failure by some

    parties to fulfill their financial commitments to the devastating aftermath of the 2007 floods.

    8

  • 7/30/2019 Besp Draft Evaluation Report 08

    23/50

    As for the 2008 Financial Year, a partial evaluation of the BESP implementation process relating

    to the first two quarters is as follows:

    Table 8: Over Performance (over 100%) - 2008

    SN Activities Planned Outputs Actual Output Performance

    Rate1 Facilityating PECs &

    ADECs to carry out school

    monitoring

    30 PECs & ADECs to be

    facilitated

    40 PECs & ADECs were

    facilitated to carry out

    school monitoring

    133%

    2 Holding radio talk shows 15 radio talk shows to be

    held

    17 radio talk shows held.

    2 radio spot messages run

    on two radio stations for 3

    months.

    113% achieved

    3 Supporting school

    community leaders to

    monitor government

    expenditure in schools

    Leaders from 12 school

    communities to be

    supported

    30 community leaders

    from 30 schools did the

    monitoring

    250%

    Table 9:High Performance (51 100%) - 2008

    SN Activities Planned Outputs Actual Output Performance

    Rate

    1 Support to school

    community initiated projects

    6 school community

    initiated projects to be

    supported

    6 school community

    initiated projects

    supported (Madera P/S

    Classroom renovation,

    kumi Boys Classroom

    completion, Serere P/S-

    Teacher & Amuria

    Primary schools

    100%

    2 Training of teachers on CL

    (module 2)

    2000 teachers to be trained

    in CL (module 2)

    1,237 teachers trained on

    CL

    61%

    achievement.

    3 Conduct joint termly review

    meetings (inspection

    reports)

    2 joint meetings to review

    termly inspection reports to

    be held

    2 joint meetings to review

    termly inspection reports

    were held

    100% achieved

    4 To facilitate PECs &

    ADECs to carry out school

    supervision

    40 PECs & ADECs to be

    facilitated

    40 PECs & ADECs were

    facilitated to carry out

    school monitoring

    100% achieved

    5 Conducting JAC meetings One JAC meeting to be

    held

    One finance committee

    meeting of the JAC washeld; 2 inter-church

    committee meetings wereheld

    100% achieved

    6 Staff salaries 12 staff to be paid salariesregularly

    All staff promptly paidtheir salaries

    100% achieved

    7 Maintenance of equipment 2 vehicles, 4 M/cycles, 4computers and pcopiers to

    be maintained

    Equipment from bothoffices were fairly

    maintained

    100%

    8 Purchase of office stationery Assorted stationery to be

    purchased

    Stationery was purchased

    for both offices but notadequate

    100%

    9 Payment for utilities Payments to be made for allutilities

    All utility (telephone,water & internet) expenses

    were promptly paid for

    100%

    9

  • 7/30/2019 Besp Draft Evaluation Report 08

    24/50

    SN Activities Planned Outputs Actual Output Performance

    Rate

    10 Payment for financial

    services

    Payment for all financial

    services to be made

    Financial services

    expenses were promptly

    paid for

    100%

    11 Office maintenance The 2 offices to be

    (CEREDO &COU) wellmaintained

    Both offices were fairly

    well maintained.CEREDO office expanded

    and needed more funds

    100%

    12 Conducting national

    meetings

    4 National meetings to be

    conducted

    3 National meetings were

    held

    75%

    14 Carrying out planning,

    monitoring and evaluation

    Effective M & E to be

    carried out monthly in the

    beneficiary schools

    14 M & E visits were done

    in the 60 schools by

    supervisors and

    programme officers

    100%

    15 Support to school

    community initiated projects

    6 school community

    initiated projects to be

    supported

    4 projects supported i.e.

    - Madera Boy P/S

    Classroom

    completion

    - Amuria P/S teachershouse constructionand supply of 20

    beds

    - Kumi BoysP/S

    Classroom

    completion

    67%

    16 Training of school

    community leaders on

    research lobby & advocacy.

    300 community leaders

    from 60 schools to be

    trained on lobby &

    advocacy

    284 people from 20

    schools trained i.e PECs,

    ADECs, SMCs and PTAs

    95%

    17 Conducting joint termly

    review meetings (inspection

    reports)

    2 joint meetings to review

    termly inspection reports

    were to be held

    2 joint meetings to review

    termly inspection reports

    were held

    100%

    18 Training of teachers on CL

    (module 2)

    2000 teachers to be trained

    in CL (module 2)

    1,237 teachers trained on

    CL

    61%

    Table 10: Underperformance (0 50%) - 2008

    SN Activities Planned Outputs Actual Output Performance

    Rate

    1 Facilitating inspectors,

    CCTs, ADECs and

    PECs to carry out

    inspection

    100 inspectors,CCTs,

    ADECs and PECs to be

    facilitated to carry out

    inspection.

    34 inspectors, CCTs,

    ADECs, PECs and

    BESP staff were

    facilitated to carry out

    inspection in the 60selected schools

    34%

    2 Collect and analyse datafrom DEOs offices

    (EMIS)

    Data to be collected andanalysed from all the

    study districts

    Finalization of data forAmuria &

    Kaberamaido districts

    was done

    33%

    10

  • 7/30/2019 Besp Draft Evaluation Report 08

    25/50

    Table 11:Non-performance (0%) - 2008

    SN Activities Planned Outputs Actual Output Performance

    Rate

    1 Facilitate 600 teachers with

    scholastic materials for

    effective implementation of CL

    600 teachers from 60

    schools to be facilitated

    Wasnt implemented 0%

    2 Mobilization of schoolcommunities to participate in

    school governance

    Mobilise the schoolcommunities in 60 schools

    to actively participate in

    school governance

    Activity not done.Shortage of funds 0%

    3 Facilitating inspectors, CCTs,

    ADECs

    100 inspectors,CCTs,

    ADECS and PECs to be

    facilitated

    Activity not done.

    Shortage of funds

    0%

    4 Effecting educational exchange

    visit for SMCs and PTAs

    One educational exchange

    visit for SMCs and PTAs to

    be carried out

    Activity not

    implemented

    0%

    5 Schools inspectors, PECs &

    ADECs report sharing and

    dissemination

    Inspection report to be

    shared and disseminated

    Activity not

    implemented

    0%

    6 Support school community

    leaders

    12 school community

    leaders to be supported

    Activity not

    implemented

    0%

    7 Supporting pupils leadership

    clubs for effective participation

    in school management

    10 pupils leadership clubs

    to be supported

    Activity not

    implemented

    0%

    8 End of term evaluation End of term evaluation to

    be conducted

    Activity not

    implemented

    0%

    9 Annual maintenance of BESP

    website for information

    dissemination

    JAC/BESP website to be

    maintained

    Activity not

    implemented

    0%

    Once again a similar pattern of performance, prioritization and resource allocation is applicable

    to the first half of 2008.

    Most of the activities that appear in the non-performance category were those that, owing to

    delays in the release of finances, were deferred to the fourth quarter of 2008. Theirimplementation is therefore ongoing.

    11

  • 7/30/2019 Besp Draft Evaluation Report 08

    26/50

    CHAPTER FOUR: EFFECTIVENESS AND EFFICIENCY OF

    THE BESP

    4.0 Introduction

    The effectiveness, relevance and efficiency of the BESP in revamping access to and the quality

    of basic education service delivery in the Teso sub-region was assessed using the criteria

    outlined in Boxbelow.

    There is evidence to suggest that, through its strategy of resource concentration, selective

    resource targeting, strengthening of partnerships, elimination of wasteful duplication of

    procedures and improvement of managerial capacities, the BESP has significantly contributedtowards:

    4.1 Improvement in access/equity indicators

    (i) Greater pupil participation in the schooling process as evidenced in higher enrolments,

    substantial reduction in gender disparities and increased cohort survival rates. While the data

    in Table..below is focused more on the issue of adequacy of sitting and writing space, it alsoindicates the district-specific trends for primary school enrollment in the Teso sub-region

    over the 2006-2007 period.

    12

    Figure 1: The criteria for evaluating the contribution of the BESP to theimprovement in access/equity and quality/efficiency of primaryeducation in Teso

    (i) Access/equity indicators

    a) Changes in total enrollment

    b) Changes in gender parity index

    (ii) Quality/effectiveness indicators

    a) Primary Leaving Examination (PLE) results

    b) Pupil to Teacher Ratios

    c) Pupil to Classroom Ratios

    (iii) Efficiency indicators

    a) Repetition rates

    b) School attendance

  • 7/30/2019 Besp Draft Evaluation Report 08

    27/50

    Table 12: Percentage number of pupils with adequate sitting and writing space in Teso sub-region2006-2007

    SN District

    2006 2007

    Enrolment

    Students with

    adequate

    space

    % of studentswith adequate

    space to total

    enrol Enrolment

    Studentswith

    adequate

    space

    % of

    students

    with

    adequatespace to

    total

    enrol

    1 Amuria 52,522 22,901 43.6 59,904 33,490 55.9

    2 Bukedea n/a n/a n/a 43,207 18,636 43.1

    3 Kaberamaido 48,215 30,269 62.8 51,259 32,879 64.1

    4 Katakwi 36,880 20,060 54.4 37,058 29,788 80.4

    5 Kumi 87,824 65,775 74.9 93,447 55,766 59.7

    6 Soroti 127,538 69,461 54.5 132,156 67,661 51.2

    Total 352,979 208,466 59.1 417,031 238,220 57.1Source: EMIS, Ministry of Education and Sports

    It is clear from the tabulations above that, there was a modest surge in enrollments in all the sixdistricts of Teso. Taking the sub-region as a whole, total primary school enrollment rose from

    352,979 in 2006 to 417,031 in 2007 which translates into an annual growth rate of 10.8%. This

    aggregative average however masks a lot of inter-district disparities. For example, the lowestpercentage increase was registered in Katakwi district where total enrollment crept up from

    36,880 in 2006 to 37,058 pupils in 2007 representing an incremental rate of only 0.5%, while the

    highest proportionate increment was in Amuria district where pupil participation rates climbed

    from 52,522 in 2006 to 59,904 in 2007, which converts into a growth rate of approximately 14%.

    (ii) The rise in school enrolments has also partially helped to resolve the problem of inequality of

    educational opportunity. There is now near gender parity in primary education in Teso and moreand more vulnerable children (especially orphans) are now able to access education in response

    to BESPs Orphans and Vulnerable Children (OVC) initiative as depicted in Table.. below.

    Table 13: Number of orphans in Teso sub-region by gender 2006-2007

    SN District

    2006 2007

    Male Female Total Male Female Total

    1 Amuria 1,237 1,028 2,265 5,190 4,676 9,866

    2 Bukedea n/a n/a n/a 2,772 2,687 5,459

    3 Kaberamaido 1,015 968 1,983 3,506 3,303 6,809

    4 Katakwi 896 889 1,785 3,341 2,959 6,300

    5 Kumi 3,252 3,183 6,435 6,165 5,993 12,158

    6 Soroti 3,351 3,433 6,784 8,592 8,522 17,114

    Total 9,751 9,501 19,252 29,566 28,140 57,706

    Source: EMIS, Ministry of Education and Sports

    The percentage share of Tesos orphaned children in the national primary school age population

    is fairly high, averaging about 5% in 2006 but reduced to 4.5% in 2007 (MoES: 2007). It is

    13

  • 7/30/2019 Besp Draft Evaluation Report 08

    28/50

    however gratifying that, the total number of orphans accessing primary education in the sub-

    region, rose from 19,252 (9,751 boys and 9,501 girls) in 2006 to 57,706 (29,566 boys against

    28,140 girls) in 2007, representing an increment of 300%. Soroti and Kumi districts posted thehighest number of schooling orphans at primary level (6,435 3,252 boys with 3,183 girls - and

    6,784 - 3,351 with 3,433 - respectively in 2006; and 12,158 6,165 boys with 5,993 girls - and

    17,114 8,592 boys with 8,522 girls - respectively in 2007).

    However, in terms of the orphans enrolment growth rates, Amuria, Katakwi and Kaberamaido

    districts surpass the pace of incremental growth in Soroti and Kumi districts. For example,although the total enrollment of orphaned primary school pupils in Soroti district grew from

    6,784 in 2006 to 17,114 in 2007 (which translates into an annual growth rate of 267%), the

    number of orphaned primary school children in Amuria district increased from 2,265 in 2006 to

    9866 representing a percentage increment of 435.6%.

    There is near parity in the gender distribution of the enrolled orphaned primary school age

    population across the six districts of the sub region.

    Implication for the BESP III: Although the Orphans and Vulnerable Children (OVC)

    programme of the BESP is certainly yielding the desired impact, there is still a very big demand-supply gap which calls for a scaling up of the BESP process.

    4.2 Improvement in quality indicators

    4.2.1 Quality of teaching

    BESP has contributed towards the restoration of the previously degenerate professional andsocio-economic status of the primary school teacher, largely through the provision of continuous

    in-service training.

    While giving their own assessments regarding the effectiveness of the various interventions of

    the BESP in their schools, the majority of the 17 head teachers interviewed ranked its in-service

    teacher training and school inspection and supervision programmes as being the most cost-effective, with each receiving a performance rating of 81.3% (see Table below).

    Table 14: Table..: Head teachers assessment of the BESP interventions

    Area of analysis

    Effective Ineffective Not applicable Non-response

    Freq. % Freq. % Freq. % Freq. %

    In service teacher training 13 81.3 0 0 2 12.5 1 6.3

    Training of schoolmanagement committee 10 62.5 3 18.8 2 12.5 1 6.3

    HIV/AIDS support

    activities 11 68.8 1 6.3 3 18.8 1 6.3

    Construction of school

    buildings 5 31.3 6 37.5 4 25 1 6.3

    School feeding 3 18.8 6 37.5 6 37.5 1 6.3

    14

  • 7/30/2019 Besp Draft Evaluation Report 08

    29/50

    Area of analysis

    Effective Ineffective Not applicable Non-response

    Freq. % Freq. % Freq. % Freq. %

    School inspection and

    supervision 13 81.3 1 6.3 1 6.3 1 6.3

    Encouragement of local

    community participation inschool activities 11 68.8 2 12.5 2 12.5 1 6.3

    Source: Returns from the field

    Conversely, the visibility of the BESP process in the areas of school feeding and andinfrastructural development is relatively weak, with low performance ratings of 18.8% and

    31.3%, respectively;

    The employment of a more inclusive and collaborative learning has become quite popular withthe pupils. This was corroborated by the 36 pupils in the BESP schools who were asked to

    characterize the instructional approaches commonly used by their class teachers. Their tallies

    were heavily indicative of increased teacher professionalism and regular employment of pupil-centered methods as shown in Table.. below.

    Table 15: Table: Pupils assessment of the classroom performance of their class teachers

    Area of analysis TRUE FALSE

    Non-

    response

    Freq. % Freq. % Freq. %

    Explains points clearly 33 91.7 3 8.3 0 0

    Summarizes main points 26 72.2 10 27.8 0 0

    Introduces lesson at the beginning 32 88.9 8 8.3 1 2.8

    Uses local examples 31 86.1 5 13.9 0 0

    Encourages questions from pupils 36 100 0 0 0 0

    Uses different methods of teaching 27 75 9 25 0 0

    Encourages class discussions 28 77.8 8 22.2 0 0

    Gives and marks homework 27 75 9 25 0 0

    Source: Returns from the field

    The 100% rating relating to the teachers encouragement of questions from the students is a vivid

    proof that, the teachers in the BESP schools have shifted away from the use of the traditional

    teacher-dominated classroom discourse to more interactive pupil engagement in a learningprocess;

    4.2.2 Pupils performance results

    Tables 16 and 17 as well as Figure 2 below are a depiction of the trends in the performance of

    primary school pupils in PLE for 2006 and 2007.

    15

  • 7/30/2019 Besp Draft Evaluation Report 08

    30/50

    Table 16: Table..: PLE results by district and gender in Teso sub-region, 2006

    District Division 1 Division 2 Division 3 Division 4 Division U Division

    X

    Grand Totals

    M F M F M F M F M F M F M F

    Amuria15 2 626 252 271 243 154 75 30 48 50 32 1,146 652

    Kaberamaido37 5 799 349 242 199 109 85 33 23 67 41 1,287 702

    Katakwi

    24 4 461 289 281 222 150 100 71 71 56 49 1,043 735

    Kumi90 41 2,050 1,412 872 1,012 498 492 232 355 154 187 3,896 3,499

    Soroti

    132 64 1,709 1,061 863 834 575 470 316 438 271 236 3,866 3,103

    Bukedea n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a

    Total

    298 116 5,645 3,363 2,529 2,510 1,486 1,222 682 935 598 545 11,238 8,691

    Source: EMIS, Ministry of Education and Sports

    Table 17: Table: PLE results by district and gender in the Teso sub-region, 2007

    District Division 1 Division 2 Division 3 Division 4 Division U Division X Grand totals

    M F M F M F M F M F M F M F

    Amuria

    19 4 638 305 282 262 138 111 61 93 30 26 1,969 3,919

    Kaberamaido

    39 3 783 408 288 260 99 107 44 23 28 15 2,097 4,155

    Katakwi

    27 3 392 250 263 224 119 73 58 73 24 22 1,528 3,029

    Kumi

    90 56 1,235 875 558 651 246 293 161 268 86 94 4,613 9,136

    Soroti

    127 69 1,547 1,022 837 775 452 430 376 533 184 200 6,552 12,977

    Bukedea

    11 1 489 309 279 289 120 151 56 109 31 41 1,886 3,761

    Total

    313 13

    6

    5,084 3,169 2,507 2,461 1,17

    4

    1,16

    5

    756 1,099 383 398 18,645 36,977

    Source: EMIS, Ministry of Education and Sports

    Although the overall number of pupils passing in Division 1 in the whole sub-region rose from414 (298 males and 116 females, representing about 72% and 28% of the Division 1 cases

    respectively) to 449 (313 boys and 136 girls) in 2007, the pass rates continue to be skewed

    against the girls. The number of girls failing PLE rose from 935 in 2006 to1,099 in 2007.

    However, the number of children who registered but did not sit for the examination reduced by agood margin from 598 in 2006 to 383 in 2007 for the boys, and from 545 in 2006 to 398 in

    2007 for the girls.

    16

  • 7/30/2019 Besp Draft Evaluation Report 08

    31/50

    Table 18: Table: Summary of PLE results by gender in Teso region, 2006-2007

    Category 2006 2007

    M F M F

    Division 1 298116

    313 136

    Division 2 5,645 3,363 5084 3169

    Division 3 2,5292,510

    2507 2461

    Division 4 1,4861,222

    1174 1165

    Division U 682935

    756 1099

    Division X 598545

    383 398

    Total11,238 8,691 10,21

    7

    8,428

    Source: EMIS, Ministry of Education and Sports

    Figure 2: UNEB figures for Teso region 2006-2007

    Source: EMIS, Ministry of Education and Sports

    In proportionate terms, the number of pupils scoring Division 1 in Primary Leaving

    Examinations (PLE) in Teso declined from 414 (298 males as opposed to 116 females) out of a

    total number of 19,329 (11,238 males and 8,691 females) in 2006 (i.e. 2.1%) to 449 (313 malesand 136 females) out of a total number of 55,622 (18,645 males against 36,977 females) in 2007

    (i.e. 0.8%). In both cases, the performance rating was skewed against the girls. While therepresentation of girls among the PLE candidates rose from 8,691 in 2006 to 36,977 in 2007 (i.e.

    it more than quadrupled), the number obtaining Division 1 and 2 de

    clined sharply in percentage terms.

    17

  • 7/30/2019 Besp Draft Evaluation Report 08

    32/50

    Implications for the BESP III: The current trend in PLE results continues to present a very

    strong case for a continued policy of positive discrimination in favour of the girl child.

    4.2.3 Pupil Teacher Ratios

    As reflected in Table. And Figure, the Pupil Teacher Ratios have tended to rise during theperiod under review.

    Table 19: Pupil Teacher Ratios (PTRs) in Teso sub-region, 2006-2007

    SN District

    2006 2007

    Total

    Students

    Total

    Teachers PTR

    Total

    Students

    Total

    Teachers PTR

    1 Amuria 52,522 930 56.5 59,904 878 68.2

    2 Bukedea n/a n/a n/a 43,207 696 62.1

    3 Kaberamaido 48,215 812 59.4 51,259 694 73.9

    4 Katakwi 36,880 708 52.1 37,058 603 61.55 Kumi 87,824 2397 36.6 93,447 1465 63.8

    6 Soroti 127,538 2356 54.1 132,156 1965 67.3

    Total 352,979 7,203 49.0 417,031 6,301 66.2

    Source: EMIS, Ministry of Education and Sports

    Figure 3: PTR in Teso region 2006-2007

    56.5

    68.2

    0.0

    62.1 59.4

    73.9

    52.1

    61.5

    36.6

    63.8

    54.1

    67.3

    49.0

    66.2

    0.0

    20.0

    40.0

    60.0

    80.0

    100.0

    120.0

    140.0

    Figure*** showing the PTR in teso Region 2006-2007

    2007 PTR 68.2 62.1 73.9 61.5 63.8 67.3 66.2

    2006 PTR 56.5 0.0 59.4 52.1 36.6 54.1 49.0

    Amuria Bukedea Kaberamai

    do

    Katakwi Kumi Soroti

    Source: EMIS, Ministry of Education and Sports

    A district specific disaggregation of the data reveals that, PTRs have been rising but in varying

    degrees from district to district. For example, the biggest increase was in Kaberamaido (57.0 in

    2006 to 75.9 in 2007 i.e. an increase of 18.9 points in absolute terms), followed by Amuria (from

    54.1 in 2006 to 67.5 = 13.4 points differential), Soroti (from 55.1 in 2006 to 67.6 in 2007 = 12.5

    18

  • 7/30/2019 Besp Draft Evaluation Report 08

    33/50

    points gap), Kumi (from 53.6 in 2006 to 64.7 in 2007 = 11.1 points differential) and Katakwi

    (from 51.6 in 2006 to 61.4 in 2007 = 9.8 points difference).

    The rise in PTRs is partially attributable to the BESP-induced enrollment bulge.

    Implication for the BESP III: The training of teachers directed towards enhancing theirpedagogical competence in the employment of a collaborative teaching/learning strategy as a

    remedy in situations of high PTRs should be intensified in the worst hit areas especially

    Kaberamaido, Soroti and Amuria.

    4.2.4 Pupil Classroom Ratios (PCRs)

    Similarly, and as shown in Tableand Figurebelow, PCRs in the sub-region have tended toincrease as the pace of classroom construction is slower than the rate of BESP-stimulated

    enrolment growth.

    Table 20: Pupil Classroom Ratios in the Teso sub-region, 2006-2007

    SN District

    2006 2007

    Total

    Students

    Total

    Classrooms PCR

    Total

    Students

    Total

    Classrooms PCR

    1 Amuria 52,522 631 83.2 59,904 695 86.2

    2 Bukedea n/a n/a n/a 43,207 510 84.7

    3 Kaberamaido 48,215 655 73.6 51,259 694 73.9

    4 Katakwi 36,880 489 75.4 37,058 476 77.9

    5 Kumi 87,824 1,582 55.5 93,447 1,123 83.2

    6 Soroti 127,538 1,665 76.6 132,156 1,534 86.2

    Total 352,979 5,022 70 417,031 5,032 82.9Source: EMIS, Ministry of Education and Sports

    Figure 4: PCR in Teso region 200-2007

    83.2

    86.2

    0.0

    84.7

    73.6

    73.9

    75.4

    77.9

    55.5

    83.2

    76.6

    86.2

    70

    82.9

    0.0

    20.0

    40.0

    60.0

    80.0

    100.0

    120.0

    140.0

    160.0

    180.0

    Figure *****showing the PCR in teso region for the year 2006-2007

    2007 PCR 86.2 84.7 73.9 77.9 83.2 86.2 82.9

    2006 PCR 83.2 0.0 73.6 75.4 55.5 76.6 70

    Amuria

    BukedeaKabera

    maidoKatakwi

    Kumi Soroti

    Source: EMIS, Ministry of Education and Sports

    19

  • 7/30/2019 Besp Draft Evaluation Report 08

    34/50

    The upward trend assumed by the PCRs is applicable in all the 6 districts of the Teso sub-region

    with Bukedea and Soroti having the highest PCR values (86.5 for Soroti and 86.3 for Bukedea),

    followed by Amuria (84.8), Kumi (84.6), Katakwi (78.0) and Kaberamaido (72.7). With theexception of Katakwi and Kaberamaido, the entire district specific PCRs lie above the sub-

    regional average of 83.0

    4.3 Improvement in relevance and effectiveness

    With regards to the relevance of education to the learning/development needs of its beneficiaries,the BESP took this into account since it was developed after extensive and intensive consultation

    with a wide spectrum of stakeholders.

    Indeed, the Teso BESP provides a model example of good practice for multi-stakeholder

    ownership and management of basic education, whereby the school community has been firmly

    placed in the drivers seat. The school communities are directly consulted on matters relating

    to their priority needs and perceptions about the quality of education service delivery.

    The findings from such consultative efforts are factored into the work plans and are used to

    inform resource allocation decision-making. As a result, there is now increased prioritization ofschool community focused programmes and a recognition of the need for greater flexibility to

    cater for intra and inter-district differences.

    Undoubtedly, the sensitization programmes for the school communities have helped to raise

    grassroots consciousness about school corruption issues and enhanced their financial probity.

    However, from the M&E perspective, the school community still suffers some limitation as theirinterest is exclusively focused on tracking expenditures and personnel responsibilities rather than

    on the education outcomes and impacts that are being pursued.

    4.4 Improvement in efficiency indicators

    The existing internal efficiency measures for primary education provision in Teso, thoughimproving, are still disappointing. This is exemplified by the data about school repetition rates

    shown in Tables..,,..and given a pictorial illustration in Figuresandbelow.

    Table 21: Number of primary school repeaters by class in Teso sub-region, 2006

    SN DistrictPrimary

    1Primary

    2Primary

    3Primary

    4Primary

    5Primary

    6Primary

    7

    1 Amuria 3,783 1,511 1,532 1,432 1,186 896 4172 Bukedea - - - - - - -

    3 Kaberamaido 3,205 1,693 1,733 1,728 1,675 1,378 6144 Katakwi 2,088 1,128 1,202 1,214 1,038 685 362

    5 Kumi 6,600 3,936 5,292 4,887 4,709 3,313 1,5526 Soroti 7,241 24,986 4,319 4,590 4,549 3,501 1,793

    Total 22,91 33,25 14,07 13,85 13,15 9,773 4,738

    20

  • 7/30/2019 Besp Draft Evaluation Report 08

    35/50

    7 4 8 1 7

    National Total ofrepeaters

    293,719

    190,183

    175,817

    156,101

    141,825

    124,572 52,533

    % of repeaters in Tesoregion to Total ofrepeaters in the

    country 7.8 17.5 8.0 8.9 9.3 7.8 9.0Source: EMIS, Ministry of Education and Sports

    Table 22: Number of primary school repeaters by class in Teso sub-region, 2007

    SN District

    Primary

    1

    Primary

    2

    Primary

    3

    Primary

    4

    Primary

    5

    Primary

    6

    Primary

    7

    1 Amuria

    3,842 2,019 2,009 1,958 1,440 1,114 332

    2 Bukedea

    2,363 1,457 1,974 1,452 1,291 1,178 430

    3 Kaberamaido

    3,316 1,841 2,283 1,879 1,625 1,377 320

    4 Katakwi2,377 1,379 1,629 1,605 1,098 795 304

    5 Kumi

    5,126 2,796 3,369 3,404 3,243 2,566 852

    6 Soroti

    7,176 3,660 4,845 4,807 4,495 3,471 1,174

    Total 24,200 13,152 16,109 15,105 13,192 10,501 3,412

    National Total of

    repeaters

    294,614 170,091 182,698 160,374 141,024 122,126 43,916

    % of repeaters in

    Teso to Total of

    repeaters in the

    country 8.2 7.7 8.8 9.4 9.4 8.6 7.8Source: EMIS, Ministry of Education and Sports

    Table 23: Consolidated summary of the number of primary school repeaters in Teso sub-region, 2006-2007

    SN District

    2006 2007

    Male Female Total Male Female Total

    1 Amuria 5,524 5,233 10,757 6,420 6,294 12,714

    2 Bukedea - - - 5,244 4,901 10,145

    3 Kaberamaido 5,971 6,055 12,026 6,326 6,315 12,641

    4 Katakwi 3,969 3,748 7,717 4,932 4,255 9,187

    5 Kumi 15,143 15,146 30,289 10,949 10,407 21,3566 Soroti 14,890 36,089 50,979 14,899 14,729 29,628

    Total 45,497 66,271 111,768 48,770 46,901 95,671

    Source: EMIS, Ministry of Education and Sports

    Note:1. Generally, there was a tremendous reduction in the number of repeaters in Tesosub-region (i.e from 111,768 to 95,671 in total.

    21

  • 7/30/2019 Besp Draft Evaluation Report 08

    36/50

    2. The number of repeaters in the districts of Amuria and Katakwi howeverincreased in 2007 compared to 2006-an indication of a slump in theteaching and learning. Repeaters increased from 10,757 in 2006 to 12,714in 2007 in Amuria and 7,717 in 2006 to 9,187 in 2007.

    Figure 5: Number of repeaters in Teso region 2006-2007

    -

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    Figure***** showing the total number of repeaters in teso Region for the year 2006-

    2007.

    Total 14,890 36,089 50,979 14,899 14,729 29,628

    Male Female Total Male Female Total

    2006 2007

    Figure 6: Repeaters in Teso region by class 2006

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000

    Figure ***** showing the number of repeaters by class in teso region , 2006.

    Total 22,917 33,254 14,078 13,851 13,157 9,773 4,738

    Primar

    Primar

    Primar

    Primar

    Primar

    Primar

    Primar

    Figure 7: Repeaters in Teso region by class 2007

    22

  • 7/30/2019 Besp Draft Evaluation Report 08

    37/50

    -

    5,000

    10,000

    15,000

    20,000

    25,000

    Figure ***** showing total number of repeaters in teso region by class , 2007

    Total 24,200 13,152 16,109 15,105 13,192 10,501 3,412

    Primar

    Primar

    Primar

    Primar

    Primar

    Primar

    Primar

    The number of children repeating a class in the Teso sub-region varies by grade and gender. For

    instance, while as depicted for P1 in Tablethe number rose averagely from 22,917 in 2006 to

    24,200 in 2007, the number of P2 repeaters fell sharply from 33,254 in 2006 down to 13,152 in2007. However, with Tesos percentage share of the total national primary school repetitionsstanding at an average of nearly 9%, this trend remains unacceptable.

    The positive side to it is that, overall, the number of primary school repeaters in the Teso sub-region declined from 111,768 (45,497 males and 66,271 females) in 2006 to 95,671 (48,770

    males and 46,901 females) in 2007 (a reduction of repetition rate by 16.8%).

    Implications for the BESP III: It would appear that, BESPs pro-girl child resource targeting

    policy is paying off and it should therefore be sustained to avoid a relapse into the pre-BESP

    scenario.

    Other contributory factors of the BESP

    In addition to the innovations already alluded to, the other BESP-led initiatives which havebrought about a reversal in the downward trend of the education access, equity, quality and

    efficiency indicators are:

    (i) The creation and facilitation of a standby stock of specially trained and inducted cadre ofteacher educators (Coordinating Center Tutors - CCTs), who are conversant with both

    pre-service and in-service teacher training delivery modalities;

    (ii) The upgrading of the managerial skills among primary school head teachers, members ofthe School Management Committees (SMCs), and some district level staff using a multi-

    faceted strategy involving study tours, short face to face training, e.t.c.(iii) Increasing the responsiveness of the satellite school communities to educational

    initiatives and endeavours within their localities;(iv) Improvement in the quality of primary school/ Primary Teacher College (PTC)

    infrastructural facilities, equipment and accessories which have had a strong motivational

    effect on the teaching learning process;

    23

  • 7/30/2019 Besp Draft Evaluation Report 08

    38/50

    (v) Equipping the JAC and its implementing partners with the skills for effective

    performance of their planning, policy analysis, management, implementation,

    information processing, M&E responsibilities;

    CHAPTER FIVE: AN APPRAISAL OF BESPs INSTITUTIONALARRANGEMENTS, CAPACITY BUILDING AND

    PARTNERSHIPS

    5.0 Introduction

    This chapter discusses the effectiveness of the management structures that define the nature of

    the working relationship between the Church of Uganda and the Catholic ChurchSoroti

    dioceses. It also examines the efficacy of the attendant capacity building efforts and partnerships.

    5.1 Establishment of the BESP management structures

    As a jointly managed programme, the BESP necessitated a shift away from a bi-modal church

    management structure in which each of the two churches independently ran its educational

    initiatives to a merger/unitary administrative set up with a twining approach to decision makingand control.

    As a result, the full operationalization of the BESP process is a shared responsibility between thefollowing hybrid management organs:

    5.1.1 A Joint Top Executive

    This is comprised of the two Diocesan Bishops, who are the first authority over the BESP, key

    signatories to all the programme documents/agreements and the originators of any new policy

    thrusts. Their main role therefore is policy assurance and monitoring of the overall programmeimplementation.

    5.1.2 The Joint Advisory Committee (JAC)

    24

  • 7/30/2019 Besp Draft Evaluation Report 08

    39/50

    This is composed of 8 members appointed by the two Bishops in accordance with the principle

    of equal representation. The JAC is the engine room for the BESP implementation. Its specific

    work assignments, among others, include:(i) Refining and synthesizing outputs and progress reports from the Joint Programme

    Secretariat;

    (ii) Monitoring and evaluating the programme implementation process and providing the TopExecutive with an early alert mechanism in cases where the planned output targets are

    not met;

    (iii) Reviewing progress reports and making recommendations to the Top executive;(iv)Providing a forum/an avenue for continuous feedback between Top Executive and the

    donors as well as stakeholders; and

    (v) Supervising the secretariat and providing institutional liaison.

    5.1.3 The Joint Programme Secretariat

    This is the programme implementation team made up of the education departments of the twochurches. Each of the education departments is headed by an education secretary. They are

    responsible for the day to day planning, administration and operations of the programme.

    A diagrammatic representation of the power and authority relationships and pattern of

    communication flow is as shown in Figurebelow:

    Figure 8: BESP Implementation and Management structure

    This three-tier management structure is founded on the efficacy of a joint as opposed to a

    fragmented approach to human development issues. Joint management structures and

    25

    4 1

    23

    The Secretariat (The Two

    Education Departments)

    Top Executive (The Two

    Bishops)

    The Joint AdvisoryCommittee (JAC)The Two Secretaries ofEducation

  • 7/30/2019 Besp Draft Evaluation Report 08

    40/50

    partnerships are particularly viewed as essential in addressing issues such as education that

    require a multi-dimensional, holistic response.

    Core to this, is the conviction about a collaborative advantage, through which the collective

    response of partners is greater than the sum of their individual contributions (Paton and Vangen,

    2004: 2).

    5.2 Evaluation of BESPs management structures

    5.2.1 Strengths

    Various evaluation studies have actually found out that, collaborative working contributes tooperational efficiency through:

    (i) An enriched skills-mix;

    (ii) Improved scope for greater division of labour and specialization;

    (iii) Improved quality of the decisions arrived at;

    (iv)Greater economies of scale; and(v) Increased fit between the services offered and what is required by the clientele

    In overall, administrative mergers benefit from the sharing of expertise, ideas, resources good

    practice and improved referrals (Wiggins, et al 2005: 23).

    This was corroborated by the BESP staff who expressed their desirability for the joint venture

    because:

    (i) It accords them a higher level of job satisfaction;

    (ii) They derive a sense of liberation from the traditional bureaucratic organizations;(iii) There is increased flexibility for staff and enhanced career development opportunities;

    (iv)There are demonstrable improvements in staff retention, recruitment and workload;(v) It creates greater scope for cross-fertilization of ideas and experiences;(vi) It broadens opportunities for strengthened partnership, as well as a deeper and mutually

    informed relationship between the two churches since all the actors in the BESP have

    one point of reference.

    It was all summed up by one BESP official who remarked thus:

    We benefit from having the experience of working with people from other backgrounds we

    pick other perspectives and others ways of doing things

    And from the perspective of the donors, jointly managed interventions of the BESP type with a

    strong anchorage to the local government structures have a strong appeal because they:(i) Minimize on the amount of capital commitments and risk;

    (ii) Facilitate the incorporation of local knowledgeable talent into the jointly run

    project/programme;(iii) Promote the cultivation of a healthy working relationship with the local authorities;

    (iv)Allow for a broader access to local supplies of the needed goods and services; and

    (v) Deter expropriations (Yerbury, 1997: 85).

    26

  • 7/30/2019 Besp Draft Evaluation Report 08

    41/50

    All these improve the prospects for the future sustainability of the project or programme after the

    gradual withdrawal of external assistance.

    5.2.2 Limitations

    Conversely, there were a few reservations expressed about the continued survival of the BESP asa collaborative venture and they center on the fact that:

    (i) While joint funding and budgeting arrangements are good, they can also be problematic

    where differences in prioritization develop;(ii) Contrary to the usual expectations, the BESP could have brought about an increase rather

    than a decrease in the transaction costs. This is because of the initial specific

    administrative changes which were needed to kick-start and support the BESP

    including the establishment of the JAC as an inter-agency strategic planning forum; therecruitment of a team leader to coordinate activities and the regular operation of joint

    reviews;

    (iii) Collaborative working has increased the administrative workload of the core staff and it

    therefore places additional demands on staff time. The BESP staff could be gettingoverstretched with the new burden of managing the partnership, preparing quarterly and

    annual progress reports and arranging for the regular joint reviews;(iv)Jointly managed programmes work best when they are also co-located. By their very

    nature therefore, jointly managed ventures remain localized with limited service reach

    (Chandan : 1999.217);(v) Although the BESP is in principle being run under a fused administrative model, the staff

    is still conscious of their ultimate accountability to the separate church hierarchies.

    There is therefore the difficulty of divided management which can lead to dual

    loyalties; and(vi) The existence of the conventional church management structure alongside the BESP

    model could lead to less efficient decision-making and to difficulty in the enforcement

    of obligations.

    5.3 Contribution of the BESP to Efficiency/Institutional and Human Capacity

    Building

    27

    Figure 9: Criteria for evaluating the contribution of the BESP to Institutional Capacity

    Building

    (i) Improvements in organizational structures including evidence of organizational

    restructuring;(ii) Stimulation of training programmes and other human capacity development

    initiatives;

    (iii) Reduced reliance on external technical assistance;

    (iv) Enhanced planning and management competencies;

    (v) Strengthened M&E functions; and

    (vi) Adequate supply of the requisite physical resources.

    (vii)Whether the expenditure of the planned activities represent value for money

  • 7/30/2019 Besp Draft Evaluation Report 08

    42/50

    5.3.1 Stimulation of training programmes and other human capacity back-ups

    The nature of the BESP process itself necessitated a renewal of interest in human resourcetraining principally because; it deliberately increased the participation of non-state actors (the