benefit-costanalysis forland-useplanning:acasestudy...summaryofbenefitsandcosts scenario1 scenario2...

18
Beneļ¬t-cost analysis for land-use planning: a case study Eric Marsden <[email protected]> Would this project provide a net beneļ¬t to society?

Upload: others

Post on 24-Apr-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Benefit-cost analysisfor land-use planning: a case study

Eric Marsden

<[email protected]>

Would this project provide a net benefit to society?

Page 2: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Warmup. Before reading this material, wesuggest you consult the associated slideson Benefit-cost analysis for risk-relateddecision-making.Available from risk-engineering.org &slideshare.net

2 / 18

Page 3: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Context

ā–· Land use planning raises numerous complex questions:ā€¢ which criteria should society use for alarp decisions?

ā€¢ which balance between different methods of reducing risk from a facilityshould be implemented?

ā–· Benefit-cost analysis: a decision-support tool which can helpdiscussion with stakeholders concerning these questions:ā€¢ structured framework for presenting all the components of a decision and

their different weightings

ā€¢ increasing the transparency of the decision-making processā€¢ provides a historical record of the elements considered in a decision

ā€¢ and the level of uncertainty existing at the time the decision was made

3 / 18

Page 4: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Case study

ā–· Study undertaken by the author and the Toulouse School of Economics,on behalf of the industrial operator (France, 2007)

ā–· Compared three scenarios for a maritime lpg importation and refillingsite:1 safety barriers proposed by plant operator (removal of one lpg sphere,

removal of railway wagons on site, reduction of quantity of gas stored on site)

2 mounding lpg spheres to protect from impinging ame (measure imposed bycompetent authorities)

3 closure of the facility, with current clients being supplied by truck fromanother facility

ā–· Relatively dense urbanization around the site:ā€¢ > 7ā€Æ000 people within a 900ā€Æm radius

ā€¢ potential domino effects towards neighboring facilities

4 / 18

Page 5: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Steps comprising a BCA

1 Specify the perimeter of the analysisā€¢ list of economic agents for whom we will estimate the consequences of the scenarios

2 List the consequences of the scenarios and choose ways of measuring them

3 Provide a quantitative prediction of the consequences for each scenario, over the projectlifetime

4 Monetize the consequencesā€¢ convert them into a monetary unit to allow comparison

5 Discount future benefits and costs, in order to obtain the net present value of each scenario

6 Analyze the robustness of the results obtained by undertaking an uncertainty analysis forthe main uncertain input parameters

7 Recommend a decision

5 / 18

Page 6: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Consequence estimation

ā–· 420 people (in addition to 22 workers on site)working or living within a radius of 360 m

ā–· 6ā€Æ700 people living between 360 and 900 m

ā–· 24ā€Æ500 people living between 900 and 1ā€Æ600 m

6 / 18

Page 7: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Hazards considered

ā–· Hazardous phenomena:ā€¢ unconfined vapour cloud explosion (UVCE), due to a leak of flammable gas to

the atmosphere which explodes some time after the time of release

ā€¢ jet fire, a large flame due to a leak of gas to the atmosphere which ignites closeto release point

ā€¢ BLEVE

ā–· Accidental scenarios considered:ā€¢ BLEVE of LPG transport trucks, railway wagons, or large LPG storage spheres

(envelope scenario)

ā€¢ pipe ruptures, for pipes of small and large diameter

ā€¢ the rupture of loading mechanisms for railway wagons or trucks

ā–· Probabilities and consequences taken from the safety case

7 / 18

Page 8: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Consequences excluded from study perimeter

ā–· Impact on firmā€™s image in case of an accidentā€¢ very difficult to estimate

ā€¢ would depend strongly on how the accident was reported in the media

ā–· Strategic value for France of an lpg importation location not monetized

ā–· Impact on productivity in each scenario is assumed to be negligible

8 / 18

Page 9: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Study assumptions: benefits

ā–· Averted fatalities and injuries:ā€¢ 2.5ā€ÆMā‚¬ per statistical fatality (upper value recommended by eu)ā€¢ 300ā€Ækā‚¬ for severe industrial injury (uk hse)ā€¢ 225ā€Ækā‚¬ for severe road accident, 33ā€Ækā‚¬ minor road accident (French ministry)

ā–· Avoided material damages:ā€¢ value of industrial facility is estimated at 25ā€ÆMā‚¬

ā€¢ nearby industrial installations: 67.5ā€ÆMā‚¬

ā€¢ lpg tankers and cargo boats potentially at port: 60ā€ÆMā‚¬

ā€¢ lost production of firms in nearby industrial zone: 5ā€ÆMā‚¬

ā€¢ house in potentially affected area: average 150ā€Ækā‚¬, apartments 120ā€Ækā‚¬

ā€¢ replacing window frames and windows: 5.5ā€Ækā‚¬ per household

ā€¢ average household has 1.5 vehicles, each worth 15ā€Ækā‚¬

9 / 18

Page 10: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Study assumptions (scenario 3)

ā–· Site closure ā†’ estimated increase in 475ā€Æ000 km/year in road traffic

ā–· 400ā€Æ000 km of trucks with small lpg bottles

ā–· 75ā€Æ000 km for lpg tankers

ā–· Annual consequences of extra traffic [accident statistics concerninghazardous materials transport]:ā€¢ 366 Ā· 10āˆ’5 statistical deaths

ā€¢ 2ā€Æ928 Ā· 10āˆ’5 severe injuries

ā€¢ 5ā€Æ124 Ā· 10āˆ’5 light injuries

ā–· Environmental impact (external cost of COā‚‚ emissions) ā‰ˆ 0.6ā‚¬/km

ā–· Dismantling the facility is assumed to have a zero net costā€¢ sale of scrap metal from the installations would compensate for labour costs

10 / 18

Page 11: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Study assumptions: costs

ā–· Investment for scenario 1: 1.5ā€ÆMā‚¬

ā–· Investment for scenario 2: 10ā€ÆMā‚¬

ā–· Extra operating costs for scenario 3: 1.1ā€ÆMā‚¬ per yearā€¢ higher lpg purchasing costs at other importation sites on the French west coast

ā€¢ additional road transport

ā–· Investment horizon: 15 years

ā–· Social discount rate of 4%

ā–· Cost of lost employment on the site (both direct and indirect) over 4 years(scenario 3): 1.2ā€ÆMā‚¬

11 / 18

Page 12: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Summary of benefits and costs

Scenario 1 Scenario 2 Scenario 3BenefitsAverted fatalities 6 275 6 400 -1 169Averted injuries 2 745 2 817 -5 060Material damage avoided

On site 950 675 4 000Off site 1 045 1 016 1 087

Sum of benefits 11 015 10 908 -1 142Direct costs

Investment 129 723 864 818 0Distribution overheads 0 0 1 100 000Other direct costs 0 0 43 241

Indirect costsEnvironmental costs 0 0 2 850Lost indirect employment 0 0 103 778

Sum of costs 129 723 864 818 1 249 869

Net annual benefit -118 708 -853 910 -1 251 011

Note all scenarios havea negative

net benefit (BCA recommends

against these decisions)

12 / 18

Page 13: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Interpretation

ā–· Closure of site would lead to an increase in the level of risk to whichinhabitants of the region are exposed

ā–· Scenarios 1 and 2 would result in levels of technological risk which arewithin the same confidence intervalā€¢ cost of the second scenario is 7 times greater than the first

ā–· Alternative presentation: net cost to society of each statistical deathaverted by implementing the safety measure is 50ā€ÆMā‚¬ for scenario 1 and332ā€ÆMā‚¬ for scenario 2ā€¢ 1.5ā€ÆMā‚¬ for public investment in road safety projects in France

ā€¢ 2.5ā€ÆMā‚¬ for regulatory impact assessment of EU legislation on air quality

ā–· Suggests that scenarios 1 and 2 are inefficient : larger number of fatalitiescould be avoided if spending were allocated to other classes of risks

13 / 18

Page 14: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Uncertainty analysis

Parameter Best estimate (šœ‡) Std dev (šœŽ)Killed per billion road km 7.0 0.3Value of neighboring site A 50ā€ÆMā‚¬ 5ā€ÆMā‚¬Value of the studied site 25ā€ÆMā‚¬ 2ā€ÆMā‚¬Multiplier for accident consequences 1.0 5Value of a statistical life (VSL) 2.5ā€ÆMā‚¬ 1ā€ÆMā‚¬Cost of an injury (industrial accident) 300ā€Ækā‚¬ 30ā€Ækā‚¬Cost of a severe injury (road accident) 225ā€Ækā‚¬ 25ā€Ækā‚¬Cost of a light injury (road accident) 33ā€Ækā‚¬ 3ā€Ækā‚¬Interest rate 4% 1%Temporal horizon for investment 15 years 3 yearsCosts in scenario 1 1.5ā€ÆMā‚¬ 0.15ā€ÆMā‚¬Costs in scenario 2 10ā€ÆMā‚¬ 1ā€ÆMā‚¬Extra costs for alternative LPG sourcing 1.1ā€ÆMā‚¬ 110ā€Ækā‚¬Extra km in scenario 3 450ā€Ækā‚¬ 45ā€Ækā‚¬

The main uncertain input

variables, represented using

Gaussian probability

distributions

14 / 18

Page 15: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Robustness of the conclusions

Annual net social benefit (ā‚¬)āˆ’2e+06 āˆ’1.5e+06 āˆ’1e+06 āˆ’500000 0

Scenario 1Scenario 2Scenario 3

The figure shows the distribution of the annualnet social benefit of each scenario, comparedwith the status quo. The distribution isobtained using a Monte Carlo analysis whichrandomly samples the main uncertainquantities in the analysis (see previous slide)from their probability distributions.

This uncertainty analysis shows that theconclusions are robust: with most possiblecombinations of uncertain input variables, theordering of scenarios (in terms of social netbenefit) remains the same.

15 / 18

Page 16: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Sensitivity analysis

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8

Value of nearby site B

Value of site

Multiplier for accident consequences

Value of a statistical life (VSL)

Interest rate

Investment horizon

Scenario 1 investments

A global sensitivity analysis using the FASTmethod shows the relative contribution of theuncertainty of the main input parameters to theoverall output uncertainty (their sensitivityindex).

For scenario 1 (figure on left), the maincontribution to uncertainty in the net socialbenefit comes from the uncertainty in theprobability of the various accident scenarios.

For scenario 3 (not shown), the maincontribution to uncertainty is the additionalcost of sourcing LPG from another location.

16 / 18

Page 17: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

What results from this study?

ā–· Results were presented to the competent authorities by the site operator

ā–· Authorities required implementation of scenario 2ā€¢ risk-informed and cost-informed argument was rejected

ā–· Argument not judged sufficiently convincing to override a Best AvailableTechnology approachā€¢ national doctrine requiring flame-proof mounds

ā–· Argument based on concepts such as statistical value of life was judgeddifficult to defend politically

ā–· National doctrine concerning the management of technological risk isbased on uniform thresholds defining acceptable exposure to riskā€¢ little latitude for the integration of cost considerations

ā€¢ low impact of local preferences

17 / 18

Page 18: Benefit-costanalysis forland-useplanning:acasestudy...Summaryofbenefitsandcosts Scenario1 Scenario2 Scenario3 Benefits Avertedfatalities 6275 6400 -1169 Avertedinjuries 2745 2817 -5060

Feedback welcome!

Was some of the content unclear? Which parts were most useful toyou? Your comments to [email protected](email) or @LearnRiskEng (Twitter) will help us to improve thesecourse materials. Thanks!

@LearnRiskEng

fb.me/RiskEngineering

This presentation is distributed under the terms of theCreative Commons Attribution ā€“ Share Alike licence

For more free course materials on risk engineering,visit risk-engineering.org

18 / 18