  • 7/31/2019 Bend Tolerances 2

    1/15

    PIPE 3D- PROJECTIONS

    The line parallel to the respective axis is the direction of the bend. So is

    the direction of the branches coming on those pipes.

    Y-axis

    X-axis

    Z-axis

    20

  • 7/31/2019 Bend Tolerances 2

    2/15

    FACE OUT

    Pipe face out -1mm max.for GTAW and

    3.0mm for other joints

    Flange face out -1.0mm per 25mm or

    1.0mm whichever is greater

    Rotation of flanges from the indicated

    position-2.0mm max.

  • 7/31/2019 Bend Tolerances 2

    3/15

    BEND ANGLE

    Reference

    Bend Angle 0.5 deg. -Acceptable

  • 7/31/2019 Bend Tolerances 2

    4/15

    WRINKLES

    1. The depth of valley / OD (d/D) shall be < or = 3%2. Pitch of valley / Depth (A/d) shall be > or = 12

    3. Wrinkles beyond acceptable limits shall be corrected. Alloy steel

    pipes shall be checked by LPI/MPI after correction.

    Depth d=(D1+D2)/2-D3

  • 7/31/2019 Bend Tolerances 2

    5/15

    OVALITY

    1. IBR: < or = 20D/R

    2. ANSI: 8% max. for bends of R/D > 5

    Where R= Radius of bend & D = Diameter of the Pipe

    % of Ovality = {(Dmax Dmin)/ D nominal }x 100

    Dnominal

    Dmax

    Dmin

  • 7/31/2019 Bend Tolerances 2

    6/15

    LINEAR DIMENSIONS

    Tolerance on straight portionencompassing bends : 10mm

    Tolerance on straight portion for endlimbs of multiplane bends : + 15/-5mm

    Bend Radius:5.0mm

  • 7/31/2019 Bend Tolerances 2

    7/15

    NOZZLE LOCATIONS ON PIPES

    Pitch and Height

    Upto OD 273mm- 3.0mm

    From OD 323.9mm to 609.6mm -5.0mm

    From OD 609.6mm to OD 914mm

    Over OD 914-6.0mm+2.0mm for each 305mm increasein OD

    Circumferential shifting-3.0mm.However maintainverticality.Face out shall be within the limits.

  • 7/31/2019 Bend Tolerances 2

    8/15

    TOLERANCE FOR BENDS

    a) For single Offset & single plane bends 5 mm 5 mm

    b) For Compound Offset/ Multi plane bends: 10 mm

    10 mm

    10 mm

  • 7/31/2019 Bend Tolerances 2

    9/15

    U-SHAPED BENDS

    10 mm

  • 7/31/2019 Bend Tolerances 2

    10/15

    PIPE LENGTH

    Arm Length: +5/-2mm

    Pipe Length(DC pipes):+3/-1mm

    Other pipes:+/-3mm

  • 7/31/2019 Bend Tolerances 2

    11/15

    U-SHAPED BENDS (Cont.0

    5 mm

  • 7/31/2019 Bend Tolerances 2

    12/15

    STRAIGHTNESS

    Tolerance on Pipe Straightness

    For every one meter length 1 mm bow is acceptable

    Overall bow shall not be more than 6 mm over the

    entire length

  • 7/31/2019 Bend Tolerances 2

    13/15

    90 BEND

    Tangent

    Tangent R

    Tangent = R x tan 2

    Diagonal = 2R

  • 7/31/2019 Bend Tolerances 2

    14/15

    OTHER THAN 90BEND

    Tangent

    Tangent

    R

    Diagonal

    Tangent = R x tan2

    Diagonal = 2R x sin 2

  • 7/31/2019 Bend Tolerances 2

    15/15

    List of tools required to mark and check the bends

    1)Combination set -2 nos.2)Channel spirit level -2 nos.3)Protractor -2 nos.4)Straight edge 5 metres -2nos.5)Straight edge 3 metres -2 nos.6)Straight edge 2 metres -2 nos.7)1 lb.Hammer -2 nos.8)2 lb.Hammer - 2nos.9)30M measuring tape -2 nos.10)3M measuring tape -2 nos.

    11)Centre Punch -2 nos.12)Number punch(0 to 9) -2 set13)Letter punch (A to Z) -2 sets14)Marking Table 5M x 5M -1 No.15)300mm Try square -2 nos.16) Marking Scriber -2 nos.17) Marking pencil -2 nos.18) Plumb set -2 nos.19)Twine20) Piano wire -1 bundle