before the haryana electricity regulatory … · a) the petitioner has established a coal based...

28
1 BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS No. 33-36, SECTOR-4, PANCHKULA- 134112, HARYANA Case No. HERC/PRO - 54 of 2017 DATE OF HEARING DATE OF ORDER 25.10.2018 15.11.2018 IN THE MATTER OF: Petition under section 86 of the Electricity Act, 2003 inter alia seeking approval of the Commission for installation of equipments (as detailed in the Petition) pursuant to the MoEFCC notification dated 07.12.2015, to enable the Petitioner to comply with the same and to in turn continue to supply power. Petitioner Lanco Amarkantak Power Ltd. (LAPL) Respondents 1. PTC India Ltd. (PTC) 2. Haryana Power Purchase Centre, Panchkula (HPPC) Present On behalf of the Petitioner (LAPL) 1. Shri Deepak Khurana, Advocate. 2. Shri Anil Sharma, Advocate. 3. Shri Vamsi Krishna Boppana, GM On behalf of the Respondent No. 2 (HPPC) 1. Ms. Sonia Madan, Advocate 2. Shri R.K. Sharma, CE/HPPC 3. Shri Randeep Singh, SE/HPPC. 4. Shri Ravi Juneja, AEE/HPPC. 5. Shri Vikrant Saini, AEE/HPPC. 6. Shri Pawan Bains, XEN/HPPC QUORUM Shri Jagjeet Singh, Chairman ORDER

Upload: others

Post on 04-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

1

BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS No. 33-36, SECTOR-4, PANCHKULA- 134112, HARYANA

Case No. HERC/PRO - 54 of 2017

DATE OF HEARING DATE OF ORDER

25.10.2018 15.11.2018

IN THE MATTER OF:

Petition under section 86 of the Electricity Act, 2003 inter alia seeking approval of the Commission for installation of equipments (as detailed in the Petition) pursuant to the MoEFCC notification dated 07.12.2015, to enable the Petitioner to comply with the same and to in turn continue to supply power.

Petitioner

Lanco Amarkantak Power Ltd. (LAPL)

Respondents

1. PTC India Ltd. (PTC) 2. Haryana Power Purchase Centre, Panchkula (HPPC)

Present

On behalf of the Petitioner (LAPL)

1. Shri Deepak Khurana, Advocate.

2. Shri Anil Sharma, Advocate.

3. Shri Vamsi Krishna Boppana, GM

On behalf of the Respondent No. 2 (HPPC)

1. Ms. Sonia Madan, Advocate

2. Shri R.K. Sharma, CE/HPPC

3. Shri Randeep Singh, SE/HPPC.

4. Shri Ravi Juneja, AEE/HPPC.

5. Shri Vikrant Saini, AEE/HPPC.

6. Shri Pawan Bains, XEN/HPPC

QUORUM

Shri Jagjeet Singh, Chairman

ORDER

Page 2: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

2

Brief Background of the Case

1. M/s. Lanco Amarkantak Private Limited (hereinafter referred to as LAPL or the

petitioner) has filed the present petition seeking approval of applicability of the MoEFCC

notification dated 07.12.2015 as change in law in accordance with Regulation 13 of the

HERC Tariff Regulations 2008 and to approve the resultant Capital Cost, increased

Auxiliary Energy Consumption and to consider shut down period of 60 days as deemed

availability.

2. The submissions of the petitioner herein i.e. M/s. LAPL is set out briefly below:-

a) The Petitioner has established a coal based thermal power plant having capacity of

300 MW i.e. Unit-II at Pathadi village, Korba District, Chhattisgarh.

b) The Respondent No. 1 (hereinafter referred to “PTC /Respondent No. 1”) is an

inter-state trader of electricity under the Act.

c) The Respondent No. 2 (hereinafter referred to as “HPPC/Respondent No. 2”) is the

entity responsible for procurement of power in the State of Haryana.

d) The Petitioner and the Respondent No. 1 had entered into a Power Purchase

Agreement (“PPA”) dated 19.10.2005 for sale of 273 MW (net power output) from the

Petitioner’s aforesaid 300 MW thermal Power Plant Unit – II in the State of Chhattisgarh

to Respondent No. 1 at a tariff which was to be determined as per the applicable CERC

Tariff Regulations, with a maximum cap of Rs.2.32 per unit as per the PPA.

e) The Respondent No. 1 entered into a Power Sale Agreement dated 21.9.2006

(“PSA”) with Haryana Power Generation Corporation Ltd. (presently represented by

Respondent No. 2 herein) for sale of the power purchased by the Respondent No. 1 from

the Petitioner under the PPA.

f) In view of the changed circumstances including force majeure events, introduction

of New Coal Distribution Policy and execution of Implementation Agreement by the

Petitioner with Government of Chhattisgarh, the Respondent No. 1 filed a petition before

this Commission seeking revision of tariff under the PSA. This petition of the Respondent

No. 1 for revision of tariff was opposed by the Respondent No. 2. The Petitioner objected

to the jurisdiction of this Commission.

g) Meanwhile, the Respondent No. 1 failed to fulfil its condition precedent of

obtaining and maintaining long term open access even after being issued a one year prior

notice by the Petitioner. Accordingly the Petitioner, during the pendency of the said

above-proceedings, was constrained to terminate the PPA on 11.01.2011.

Page 3: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

3

h) This Commission vide its order dated 02.02.2011 held that it had jurisdiction and

further restrained the Petitioner from revising its price for sale of power and further

restrained the Petitioner from selling the contracted power to a third party.

i) Aggrieved by the abovementioned Order dated 02.02.2011 passed by this

Commission, the Petitioner approached the Appellate Tribunal on 07.02.2011 by means

of an appeal being Appeal No. 15 of 2011. In the said Appeal, the Tribunal passed an

interim order dated 23.03.2011, whereby this Commission’s order dated 02.02.2011 was

partially stayed in terms of the following directions:

“11. Thus, we are inclined to grant interim stay of impugned order to the extent

indicated above. Accordingly, the Petitioner is permitted to supply 35% of

power to Chhattisgarh Government Company and is directed to supply the

balance power to the PTC (R-3) so that PTC (R-3) can discharge its obligation

to the Power Generation Corporation (R-2) in pursuance of the PSA entered

into between them.”

j) In terms of the interim order dated 23.03.2011, the Petitioner w.e.f. 07.05.2011

commenced 35% supply of power from its Unit-II to CSPTCL and balance to Respondent

No. 1. However, the price/tariff at which the power was to be supplied by the Petitioner

was not specified in the said Order.

k) The Hon’ble Tribunal dismissed the Appeal of the Petitioner i.e. Appeal No. 15 of

2011 on 04.11.2011 and upheld the jurisdiction of this Commission, while directing that

pending decision by the Hon’ble Appellate Tribunal on the contentions raised by CSTPCL

(the Petitioner in Appeal No.52/2011), “the interim order dated 23.03.2011 passed by us

will be in force till the final order is passed by the State Commission.”

l) The Petitioner challenged the said Order of the Hon’ble Tribunal by filing an

Appeal before the Hon’ble Supreme Court being Civil Appeal No. 10329/2011.

m) While issuing notice on the said appeal, the Hon’ble Supreme Court passed the

following interim order dated 16.12.2011:-

“(i) The Petitioner will continue to supply electricity as per the interim Order of

the Tribunal dated 23rd March, 2011;

(ii) Without prejudice to the rights and contentions of the parties and pending

further orders, the State Electricity Regulatory Commission, Haryana will

fix/approve the tariff for sale and purchase of power for the period in question about

which there is a dispute between the Petitioner and PTC.

The State Electricity Regulatory Commission, Haryana will decide the dispute

uninfluenced by the observations made in the impugned orders passed before today,

by the Appellate Tribunal and/or any other Authority in this case. All arguments on

both sides are kept open. Liberty is given to the parties to make a proper application

Page 4: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

4

supported by relevant documents before the State Electricity Regulatory

Commission, Haryana, within four weeks.”

As such, the Hon’ble Supreme Court protected the Petitioner by directing this

Commission to fix the tariff to be paid by the Respondents for the mandated supply of

power by the Petitioner to the Respondents dehors the capped rate under the PPA.

n) The Petitioner approached this Commission to fix/approve the tariff for the period

in question i.e. for the power supplied from 07.05.2011 to 31.12.2011 and for the power

proposed to be supplied during the balance period of the year 2011-12 i.e. 01.01.2012 to

31.03.2012 and for the year 2012-13.

o) The said petition was disposed of by this Commission by it’s order dated

17.10.2012 holding that the capped tariff of Rs 2.32/kWh in the PPA shall prevail.

p) The Petitioner filed an Appeal before the Hon’ble Tribunal against the Order dated

17.10.2012 passed by this Commission being Appeal No. 65 of 2013.

q) The Hon’ble Tribunal allowed the said appeal being Appeal No.65/2013 vide its

order dated 03.01.2014 thereby directing this Commission to re-determine the tariff

within two months from the date of communication of the judgment dehors the PPA.

r) Accordingly, the Petitioner approached this Commission for re-determination of

tariff.

s) This Commission determined the tariff of Rs. 2.8875/kWh for FY 2011-12 and

Rs.2.9218/kWh for the FY 2012-13 comprising of capacity charges and variable charges

in accordance with HERC Tariff Regulations, 2008, vide order dated 23.01.2015.

t) The aforesaid determination of the tariff by the Commission was challenged by the

Respondent No. 2 before the Hon’ble Tribunal by way of Appeal No. 107/2015 and the

same is pending adjudication. Further, the Petitioner has also filed an appeal before the

Hon’ble Tribunal being Appeal No. 117 of 2015 seeking enhancement of the tariff

determined by this Commission, which is also pending adjudication.

u) It is pertinent to mention that currently, 95% power from Unit-II of the Petitioner

is being supplied to the Respondents at the tariff determined by this Commission vide

Order dated 23.01.2015 and the balance 5% power is being supplied to CSPDCL.

v) That the MoEFCC issued a Notification dated 07.12.2015 notifying the

Environment Protection Rules, 2015, which came into force from the date of their

publication in the Official Gazette i.e. from 08.12.2015. By way of the said notification, the

Central Government has specified certain standards to be met by thermal power plants

Page 5: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

5

on various parameters such as Water Consumption, Particulate Matter, Sulphur Dioxide

(SO2), Oxides of Nitrogen (NOx), Mercury (Hg) and Water Consumption.

w) That main plant & equipments of the Power Station (which came into commercial

operation w.e.f. 07.05.2011) were designed, engineered and procured in the year 2005-

06. The construction thereof had commenced during 2006-09, and as such the

designs/manufacturing of the equipments were based on the then prevailing norms for

environmental emissions. That being so, in view of the changed environmental norms as

notified by the MoEFCC vide its aforementioned notification dated 07.12.2015, the Power

Station requires upgradation and which in turn would lead to additional investment in

the plant and equipment. The said position was notified by Petitioner to the Respondent

No. 1 herein vide letter dated 05.05.2016, being a notice for Change in Law under

Regulation 13 of the Haryana Electricity Regulatory Commission (Terms and Conditions

for Determination of Generation Tariff) Regulations, 2008, which provides for additional

capitalization on account of Change in Law or compliance of an existing law.

x) That in pursuance of the aforementioned Notification dated 07.12.2015, a Special

TCC meeting of the ‘Western Regional Power Committee’ (‘WRPC’) was convened in

Mumbai to discuss the agenda of Phasing out thermal generating units in the Western

Region which did not have space for installation of FGD for compliance of new MoEFCC

Norms of SOx emissions. A perusal of the Minutes of the said meeting would show that

the Generators raised a concern that for installation of FGD they would have to incur

heavy expenditure, with the cost of power also to increase because of increase in

Auxiliary Power consumption and O & M Cost – to which the said generators were

advised to raise the said concerns with the CERC or the State commission, CEA, MoP. The

said Minutes also, inter-alia, enlisted the thermal generating Units which had been

planned to be phased out. The said List, however, inadvertently mentioned the Power

Station of Petitioner herein.

y) With reference to the aforesaid Minutes of Special TCC, the Petitioner herein vide

its letter dated 24.04.2017 brought to the attention of WRPC that the name of its Power

station had been wrongly mentioned in the list of units to be phased out. It was expressly

brought out therein that Petitioner’s Power Station had enough space available for

installation of the proposed FGD and other associated system. Accordingly, it was

requested to correct the same in the records.

z) That in the meantime, the Petitioner, in furtherance of its aforementioned Notice

dated 05.05.2016, once again brought to the aforesaid Change in Law to notice of the

Page 6: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

6

Respondents, vide its letter dated 26.04.2017. By the said letter, the Petitioner brought to

the notice of the Respondents, the changes brought out by the Amended Norms vis-à-vis

the Old Norms, and the upgradation of equipment required to comply with the

Environmental standards set out by the MoEFCC.

aa) That neither of the Respondents has replied to the aforesaid letters of the

Petitioner.

bb) That the Petitioner has conducted a detailed study of its current emissions from

the plant. Based on the baseline emissions of the plant, only SO₂ and NOx reduction is

required. Hg reduction is not required for Petitioner plant. A summary of the Pollutants

percentage reduction required is given below:

POLLUTANTS UNIT 2

CURRENT COAL

PM, % Reduction Required Not Required

SO2, % Reduction Required 66.41

NOx, % Reduction Required 20.42

Hg, % Reduction Required Not Required

In view of the above position, SO₂ and NOx control technology/ equipment needs to

be installed for plant of Petitioner.

cc) That the Petitioner has prepared a Detailed Project Report (“DPR”) on the impact

of installing and operating the aforesaid installations for its thermal power project

(2x300 MW). The said DPR provides a detailed analysis of the systems required to be

installed to comply with the revised norms, the process to be followed for installation and

other indicative capital cost & operating cost details for both the Units (Unit- I and Unit-

II) of the Petitioner. For the present Petition, the indicative capital cost and operating cost

for Unit-II have been considered at 50% of the overall cost indicated in the DPR for the

Project (2x300 MW). The timeline considered for completing the installation and

commissioning of FGD and SCR is planned to be carried out in a time span of 36 months

from the date of award of the contract.

i. A comparative analysis of the standards/norms existing prior to the

MoEFCC Notification dated 07.12.2015 vis-à-vis the revised norms

introduced by the said notification are briefly stated as under:

A. Sulphur Dioxide (SOx) Emissions

Page 7: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

7

I. As brought out above, prior to the MoEFCC Notification dated

07.12.2015, no norms was specified with regards to SOx

emission from the Thermal Power Plants. No such

requirement was specified in the environmental clearances

granted by MOEF for the Petitioner’s Project and accordingly

the Petitioner did not consider any cost towards the same in

the capital cost of the Petitioner’s Project. However, the

Amendment Rules stipulate that SOx Emissions from the

Project is to be kept below 600 mg/NM3. With the current

quality of domestic coal being fired at Petitioner project, the

SOx emission is expected to be higher than the norms

specified in the Amendment Rules.

II. It is submitted that the Petitioner has conducted a detailed

study of the different technologies like Wet FGD, Ammonia

based FGD, SemiDry FGD, ReACT and the different technically

feasible combinations of aforementioned technologies and has

come to the conclusion that only Wet FGD would be the most

cost effective in meeting the category 2 limits i.e. 600

mg/Nm3. The Wet FGD life-cycle capital cost is significantly

below all the other SO₂ reduction system options that were

considered. Therefore, the Petitioner is required to install

Flue Gas Desulfurization (“FGD”) and associated equipments

as part of the Project to meet the MOEFCC compliance.

III. It is submitted that installation of the FGD will also lead to an

increase in auxiliary power consumption of the Unit in the

range of 1.8 % - 2.25% which needs to be considered by the

Commission for the purpose of computation of Tariff.

IV. It is submitted that an economic analysis of making technical

changes in the existing stack vis-a-vis the option of installing a

new stack was done in the detailed project report, in which it

was concluded that opting for a new stack for Wet FGD is

cheaper than making technical changes in the existing stack.

For the purpose of carrying out the interconnection, about 60

days of shutdown of the Unit is required for installation and

Page 8: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

8

commissioning of the FGD. It is submitted that non-

availability of the Unit due to installation activities of the FGD

System be considered as Deemed Availability for the purpose

of making payment of Fixed charges to Petitioner.

V. The indicative capital cost for the Wet FGD systems include

the following features:

(i) Flue Gas Desulfurization Vessels and Associated Equipment

(ii) Reagent preparation system and byproduct dewatering

system

(iii) Wastewater treatment system

(iv) New stack with borosilicate glass lining for acid corrosion

protection Flue Gas Ductwork

(v) Draft System Stiffening

(vi) Tanks, Pumps, and Interconnecting Piping

(vii) Bulk Material Handling Equipment for limestone and

byproduct

(viii) Raw Water Treatment System

(ix) New centrifugal ID fans, VFDs and supporting equipment

(x) Auxiliary Transformers and Electrical equipment

VI. The Annual O&M costs for the Wet FGD technologies consist

of the following cost categories:

(i) Operating labor costs

(ii) Maintenance materials and labor

(iii) Reagent

(iv) Byproduct disposal (including fly ash)

(v) Auxiliary power

(vi) ID or booster fan power costs

(vii) Service water costs

VII. The costs of reagent (limestone), byproduct disposal, and

auxiliary power are variable annual costs that differ with the

amount of SO₂ removed.

A Summary of Cost Estimates for Wet FGD Technology & Associated

Systems for Unit 2 (50% of total cost) is given in the table below:-

Page 9: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

9

Item Description Cost Estimate (50% of total cost) in Rs. Crores Capital Costs ₹ 191.13

O&M Costs per Annum ₹ 17.87

Note- The above cost is excluding Interest During Construction and

generation loss due to shut down required for construction.

B. Re: oxides of nitrogen emission limited to 300mg/NM3

I. It is submitted that the Amendment Rules stipulate that Oxides of

Nitrogen emission is to be kept below 300mg/NM3. It is submitted

that this is a new condition.

II. It is submitted that the Petitioner has conducted a detailed study

of different technologies like SNCR, SCR, Induct SCR, a new LNB

with OFA, ReACT and the different technically feasible

combinations of aforementioned technologies and has come to the

conclusion that only SCR would be the most cost effective in

meeting the category 2 limits i.e. 300 mg/Nm3. The SCR life-cycle

capital cost is significantly below all the other NOx reduction

system options that were considered. Therefore, in order to

comply with the MOEFCC changed norm, the Petitioner is required

to install SCR Systems.

III. It is submitted that for the purpose of carrying out the

interconnection, about 60 days of shutdown of the Unit is required

for installation and commissioning of the SCR. It is submitted that

non-availability of the Unit due to installation activities of the SCR

System be considered as Deemed Availability for the purpose of

making payment of Fixed charges to Petitioner. The outage of

about 60 days of the Unit shall be taken up for installation of FGD

and SCR systems.

IV. The indicative capital cost for the SCR systems include the

following features:

(i) Reactor / Selective catalytic reduction housing (ii) SCR Catalyst (iii) Ammonia dosing system (iv) Ducting (v) Ash hoppers

V. The Annual O&M costs for the SCR system consist of the following

cost categories:

Page 10: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

10

(a) Operating labor costs (b) Maintenance materials and labor (c) Catalyst (d) Anhydrous ammonia (e) Auxiliary power (f) Dilution water costs

VI. A Summary of Cost Estimates for the SCR systems for Unit 2 (50%

of the total cost) are given in the table below:

Item Description Cost Estimate (50% of total cost) in Rs. Cr. Capital Costs ₹ 150.18 O&M Costs per Annum ₹ 5.73

Note- The above cost is excluding Interest During Construction

and generation loss due to shut down required for construction.

C. Re: Mercury emission limited to 0.03mg/NM3

I. That the Amendment Rules stipulate that Mercury emissions are to

be limited to 0.03 mg/NM3.

II. That the Petitioner has conducted a preliminary assessment which

indicates that it is already in compliance with the aforesaid

condition.

III. That the Petitioner reserves its right to approach this Commission in

the event that any additional measures need to be implemented

involving additional installation cost and /or operating cost to

comply with the aforesaid condition.

D. Maximum specific water consumption of all existing Cooling Tower

bases plants to be reduced to 3.5M3/MWh

I. Prior to the MoEFCC Notification dated 07.12.2015, there was no

restriction on consumption of water. However, under the

Amendment Rules, the maximum water consumption for all existing

Cooling Towers based plants, such as that of the Petitioner is limited

to 3.5M3/MWh.

II. That the Petitioner has conducted a preliminary assessment which

indicates that it is currently in compliance with the aforesaid

condition. Further, upon installation of the wet FGD system

(required for meeting the SO₂ emission norms), the water

Page 11: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

11

consumption would continue to remain within the limit prescribed

in the Amendment Rules.

IV. That the Petitioner reserves its right to approach this Commission in

the event any additional measures need to be implemented

involving additional installation cost and /or operating cost to

comply with the aforesaid condition.

E. Re: Particulate Matter Emission limited to 50 mg/Nm3.

I. That the Amendment Rules stipulate that the particle matter

emissions is to be limited below 50 mg/Nm3.

II. That the Petitioner has conducted a preliminary assessment which

indicates that it is already in compliance with the aforesaid

condition.

dd) That in view of the above facts, the Petitioner is filing the present Petition to

obtain approval of the Appropriate Commission i.e. this Commission regarding the

applicability of Change in Law Provisions for the MoEFCC notification dated 07.12.2015,

to enable the Petitioner to comply with the same, and in turn continue to supply power.

ee) That the Petitioner reserves its right to approach this Commission in the event

that any additional measures need to be implemented involving additional installation

cost and /or operating cost to comply with the aforesaid condition.

GROUNDS FOR CLAIMING RELIEFS:-

ff) That the notification dated 07.12.2015 issued by the MoEFCC has revised the

norms/parameters for emission of Particulate Matter as compared to the

norms/parameters existing on the COD of the Petitioner’s Project. Further, the said

notification has introduced additional limits for the Power Project as regards the

emission norms for Sulphur Dioxide, Oxides of Nitrogen, the amount of cooling water to

be used per unit, installation of Cooling Tower. It is thus clear that the notification issued

by the MoEFCC constitutes a Change in Law under the HERC Tariff Regulations and has

substantial impact on the capital cost and operational cost of the Project. In the light of

the above, the additional cost being incurred on account of the additions/modifications

etc. is to be added to the Capital Cost subject to approval by the Commission. The said

approval would be fundamental for determining the tariff recovery based on such

additional investment and for securing financing from financial institutions. In the

Page 12: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

12

absence of such approvals, the implementation and/ or compliance of the MoEFCC

Notification would be practically impossible.

gg) That the Amendment Rules issued by the MoEFCC has changed the very basis on

which the Petitioner had conceived and set up the aforementioned Power Project. The

applicable environment norms at the time of installation/commissioning of the

Petitioner’s Project have undergone a substantial change by virtue of MoEFCC’s

notification dated 07.12.2015, as detailed above, which require the Petitioner to

undertake substantial and major capital works and modifications in order to be continue

to operate its Project and continue to supply the power. Such capital works and

modifications would require substantial capital expenditure during the Operating Period

apart from recurring Operational expenditure. It would also lead to increase in cost due

to change in operational parameters. In this regard, the initial assessment of expenditure

required (capital expenditure and operational expenditure) for complying with the

revised norms prescribed in the MoEFCC Notification is quite substantial at approx. Rs.

365 crores for 300 MW Unit-II. To incur an expenditure of such magnitude, the Petitioner

would be required to arrange for funds from the lenders. It is in the aforesaid factual

backdrop, that the Petitioner herein has filed the present Petition under Section 86 of the

Electricity Act seeking regulatory certainty qua the treatment of such costs and in

principal approval of the capital cost to be incurred by the Petitioner for installation,

operation and maintenance of the FGD, SCR and associated Systems.

hh) That the expenditure to be incurred by the Petitioner in order to comply with the

MoEFCC notification ought to be allowed to be recovered as pass through in the tariff

inasmuch as the same is occasioned by a change in law and in the nature of a statutory

expense and therefore beyond the control of the Petitioner. The Petitioner has no option

but to incur the said cost. The objective behind the Electricity Act, 2003 and the Tariff

Policy also includes ensuring the viability of the generators and in order to maintain the

viability of the Petitioner. Non-recovery of cost incurred on the Project will make the

Project unviable thereby resulting in the asset becoming stranded. This would defeat the

objectives of the Electricity Act, 2003 and the Tariff Policy, inasmuch as substantial

expenditure is required to be incurred to undertake the works in compliance with the

MoEFCC notification to adhere to the revised norms. Not only would it require one time

capital expenditure, there would be impact on the recurring Operation and Maintenance

Costs as well as increase in Auxiliary Consumption etc. This in turn would lead to

increase in the cost of generation of power. Accordingly, it becomes important to have a

Page 13: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

13

regulatory certainty of the treatment to be given to such costs. Furthermore, in order to

arrange the funds from lenders to undertake the works, an in-principle approval from the

regulatory is required in order to ensure that the cost so incurred would be required

from the tariff. This is important to ensure funding from the lenders in the absence of

which, the compliances to be done in terms of the MoEFCC notification would be

rendered virtually impossible. Therefore, it is of utmost importance for the Petitioner to

approach this Hon’ble Commission with the present petition to have certainty in the

matter.

ii) That the Minutes of meeting of the WRPC, supports the case of the Petitioner

herein, in as much as, a bare of the same would show that the Generators raised a

concern that for installation of FGD they would have to incur heavy expenditure, with the

cost of power also to increase because of increase in Auxiliary Power consumption and O

& M Cost – to which the said generators were advised to raise the said concerns with the

CERC or the State commission, CEA, MoP.

jj) That the Petitioner is entitled to approval & consent with regards to applicability

of Change in Law for the MoEFCC notification dated 07.12.2015, to enable the Petitioner

to comply with the same, and to in turn continue to supply power. It is most respectfully

submitted that in case the Petitioner is not adequately secured in such manner, the same

would not only be gravely prejudicial to the Petitioner but would also defeat the object of

the Electricity Act, 2003.

kk) That the Petitioner shall be suffering on account of absence of approval & consent

with regards to applicability of Change in Law for the MoEFCC notification dated

07.12.2015.

ll) That the present Petition is being filed without prejudice to Petitioner’s rights and

contentions in the Civil Appeal No. 10329/2011 and Civil Appeal No. 3800/2014 pending

before the Hon’ble Supreme Court.

RELIEFS SOUGHT:-

(a) Approve the applicability of the MoEFCC notification dated 07.12.2015 as Change

in Law in accordance with Regulation 13 of the HERC Tariff Regulations 2008;

(b) Pass an Order granting in-principle approval to:

i) Capital Cost of approx. Rs 191.13 Crore along with O&M cost of approx. Rs.

17.87 Crore per annum expected to be incurred by the Petitioner’s Project

Page 14: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

14

towards installation & O&M of the FGD and associated system, apart from

the Cost incurred towards financing/interest and other incidental

expenditure thereto during the construction period.

ii) Capital Cost of approx. Rs 150.18 Crore along with O&M cost of approx. Rs.

5.73 Crore per annum expected to be incurred by the Petitioner’s Project

towards installation & O&M of the SCR and associated system, apart from

the Cost incurred towards financing/interest and other incidental

expenditure thereto during the construction period;

iii) Increase in Auxiliary Energy consumption of about 1.8-2.25% due to

installation & O&M of additional FGD & SCR systems for the purpose of

computation of tariff;

iv) Time period of about 60 days required for Shut down of the Unit required

for interconnection during the installation and commissioning of the FGD,

SCR and other associated systems which shall be considered as deemed

availability under the PPA for the purpose of payment of capacity charges;

Proceedings in the Case

3. The case was first heard on 18.09.2017, wherein the Petitioner mainly reiterated

the contents of its Petition, which for the sake of brevity, have not been reproduced here.

4. Per contra, Ld. Advocate for the Respondent No. 2 i.e. HPPC raised the issue of

Jurisdiction of this Commission to deal with any question of law as the power is being

supplied as per the Interim direction of the Hon’ble Supreme Court and Govt. of

Chhattisgarh is also recipient of 5% power from the project. HPPC submitted that the

Jurisdiction to decide whether the MoEFCC notification dated 07.12.2015 constitutes

Change in Law, is with the Hon’ble Central Electricity Regulatory Commission. The Ld.

Advocate Smt. Sonia Madan, appearing for HPPC, further argued that in any case relief

cannot be granted unless expenses have been actually incurred by the Petitioner. Further,

she argued that there is no provision in the statues/regulations regarding in-principle

approval of such expenses. The Ld. Advocate also argued at length on the status of the

Petitioner as a generator having composite scheme of supply to more than one State.

Regarding this she provided reliance on the Judgement dated 11.04.2017 passed by the

Hon’ble Supreme Court in Civil Appeal No. 5399-5400 of 2016 (Energy Watchdog Vs.

Page 15: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

15

CERC and Ors etc.). The Commission heard the arguments of Ltd. Advocate(s) appearing

for PTC and Lanco as well.

5. Upon hearing the parties, the Commission vide its Interim Order dated

25.09.2017, directed as under:-

a) All the parties should file their argument (in the hearing held on 18.09.2017)

in writing.

b) The Petitioner may file rejoinder to the reply filed by HPPC as well as issued

raised in the hearing held on 18.09.2017, within 7 days from the date of this

Order.

6. In pursuant to the Interim Order of the Commission dated 25.09.2017, M/s. LAPL

filed its reply on the objection raised by Respondent No. 2 (HPPC) regarding the

jurisdiction of this Commission. The Petitioner has submitted as under:-

a) That the present petition has been filed seeking approval of applicability of the

notification dated 07.12.2015 issued by MoEFCC whereby the Environment

(Protection Rules), 1986 were amended to set new emissions norms, inter alia, for

emission of oxides of Sulphur (SOx) and Oxides of Nitrogen (NOx) in Thermal

Power Plants as Change in Law within the meaning of HERC Regulations 2008. In

order to achieve the said revised norms, additional systems and more particularly

Flue Gas Desulphurizer (for SOx) and Selective Catalytic Reduction (for NOx) are

required to be installed in 300 MW Unit-II of the Petitioner’s Thermal Power Plant,

which would result in incurring capital expenditure. The Petitioner has also

sought in principle approval of this Commission to the capital cost required to be

incurred for installation of the said systems as well as the O & M cost to be

incurred on the said systems. The Petitioner has also sought in principal approval

for increase in auxiliary energy consumption resulting from installation and O&M

of the additional systems.

b) That the Respondent in its reply has raised an objection to the jurisdiction of this

Commission. The objection is raised on the basis that the Hon’ble Supreme Court in

its judgment dated 11.04.2017 in Civil Appeal No. 5399 – 5300 of 2016, titled

Energy Watch Dog Vs. Central Electricity Regulatory Commission & Ors. has laid

down that any issue / dispute with regard to generation and sale of power under a

composite scheme within the meaning of Section 79(1)(b) of the Electricity Act,

2003 confers exclusive jurisdiction on the CERC and, therefore, the issue raised in

the present Petition can only be adjudicated by CERC as the Petitioner has two

beneficiaries i.e. State of Haryana and State of Chhattisgarh from its Unit 2. The said

Page 16: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

16

objection is raised in para 4 of the reply, which is reproduced hereunder for ready

reference of the Commission:-

“4. That the instant petition is misconceived and without proper jurisdiction. It is

pertinent to note in this regard that the Petitioner has one more beneficiary other

than the Answering Respondent, i.e. State of Chhattisgarh, which has long term

arrangement with the Petitioner. In view of the law laid down by the Hon'ble

Supreme Court in Civil Appeal no. 5399/2016, for any issue/dispute with regard to

the generation and sale of power under a composite scheme within the meaning of

Section 79(1) (b) of the Act, the Hon'ble Central Commission alone has the

jurisdiction. The question as to whether the installation and commissioning of

FGD/SRC system in view of the MoEF notification dated 07.12.2015 falls under the

definition of 'Change in law' and can only be adjudicated by the Hon'ble Central

Commission as it affects two beneficiaries, i.e. State of Haryana and State of

Chhattisgarh.”

c) That the objection raised by the Respondent No. 2 is untenable. In the present

case, admittedly, the supply of power is taking place pursuant to and in terms

of interim directions issued by the Hon’ble Appellate Tribunal (vide Order

dated 23.03.2011) and continued by the Hon’ble Supreme Court (vide Order

dated 16.12.2011) and therefore the parties to the present proceedings are

governed solely by the said interim directions. In this regard, following

admitted facts are being submitted:-

i) In Appeals filed by the Petitioner and Chhattisgarh State Power Trading

Company Ltd. against the order dated 02.02.2011 passed by this Commission

whereby the Commission had held that it had jurisdiction to adjudicate upon

the disputes arising out of PPA between Petitioner and Respondent No. 1 and

PSA between Respondent No. 1 and Respondent No. 2, the Hon’ble Tribunal

passed an interim order dated 23.03.2011 directing the Petitioner to supply

35% power generated from its 300 MW Unit-II, to Chhattisgarh (as

Chhattisgarh was entitled to 35% power under Implementation Agreement

with the Petitioner) and the remaining power to Respondent No. 1 for onward

supply to Respondent No. 2,. The appeal of the Petitioner was dismissed, the

jurisdiction of this Commission was upheld vide Order dated 04.04.2011

passed by the Hon’ble Appellate Tribunal, however, the interim order dated

23.03.2011 qua supply of power was directed to be continued.

Page 17: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

17

ii) Pursuant to the said interim order, the supply of power from unit-II of the

Petitioner commenced on 07.05.2011.

iii) In Appeal being Civil Appeal No. 10329/ 2011 filed by the Petitioner against

the aforesaid order of the Appellate Tribunal, before the Hon’ble Supreme

Court, an interim order dated 16.12.2011 was passed whereby the direction

for supply of power by the Appellate Tribunal vide its order dated 23.03.2011

was continued. The Hon’ble Supreme Court issued further directions to this

Commission to fix / approve the tariff for sale and purchase of power. The

relevant portion of the order is reproduced hereunder:-

“… … …

Pending hearing and final disposal of the appeal, we issue following

directions:

(i) The appellant will continue to supply electricity as per the interim

order of the Tribunal dated 23rd March, 2011;

(ii) Without prejudice to the rights and contentions of the parties and

pending further orders, the State Electricity Regulatory

Commission, Haryana will fix / approve the tariff for sale and

purchase of power for the period in question about which there is

a dispute between the appellant and PTC.

The State Electricity Regulatory Commission, Haryana by

observations made in the impugned orders passed before today, by the

Appellate Tribunal and / or any other Authority in this case. All

arguments on both sides are kept open. Liberty is given to the parties

to make a proper application supported by relevant documents before

the State Electricity Regulatory Commissioner, Haryana, within four

weeks.”

iv) In terms of the aforesaid order passed by the Hon’ble Supreme Court, the

Petitioner applied to this Commission to determine the tariff. The Commission

vide its order dated 17.10.2012, determined the tariff. However, the

Commission came to a conclusion that as the PPA contains capped tariff of

Rs.2.32/kWh, the said capped tariff shall prevail.

v) The Petitioner challenged the said Order by filing an appeal before the

Appellate Tribunal being Appeal No. 65/ 2013. The said Appeal was allowed

vide judgment dated 03.01.2014 and the Appellate Tribunal directed this

Page 18: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

18

Commission to re-determine the tariff in accordance with HERC Regulations,

2008, de-hors the PPA.

vi) Pursuant to the said order, the Commission vide its order dated 23.01.2015

determined the tariff afresh.

d) The above undisputed facts make it evident that the supply of power from

Petitioner’s Unit-II is taking place pursuant to and in terms of the interim

order dated 16.12.2011 passed by the Hon’ble Supreme Court and at a tariff

determined by this Commission pursuant to the directions issued by the

Hon’ble Supreme Court/Hon’ble Appellate Tribunal. The jurisdiction of this

Commission is fixed by the Hon’ble Supreme Court and, therefore, cannot be

altered till as long as the Order dated 16.12.2011 passed by the Hon’ble

Supreme Court is in force. By way of an interim-ad-hoc mechanism, the Hon’ble

Supreme Court has chosen this Commission for fixing/ approving the tariff for sale

and purchase of power for the period in question about which there is a dispute

between the parties. Not only this Commission has determined the tariff

pursuant to the said order of the Hon’ble Supreme Court, it has also issued

appropriate order dated 12.07.2016 subsequently directing the

Respondents to pay the differential tariff (Rs 99 crores approx.) for the

power supplied by the Petitioner, as per the tariff determined vide order

dated 23.01.2015. Further, in its latest order dated 18.05.2017, this

Commission has allowed the Petitioner to source alternate coal for meeting

its coal requirements to continue optimum utilisation and efficient

operations of its Unit-II. Thus, this Commission continues to exercise

jurisdiction in the matters arising before it since 16.12.2011 (date of interim

order of Hon’ble Supreme Court) and consequently the jurisdiction to entertain

the present Petition lies only with this Commission. Any other contention or

view would be contrary to the Order passed by the Hon’ble Supreme

Court/Hon’ble Appellate Tribunal.

e) That, the tariff has been determined by this Commission as per HERC Regulations,

2008 and supply of power is taking place on the said basis. Therefore, the

jurisdiction to determine as to whether the amendment in the Environment

(Protection) Rules, 1986 amounts to Change in Law within the meaning of

HERC Regulations 2008 or not also lies with this Commission, as the

Regulations which fall for consideration are framed by this Commission.

Page 19: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

19

f) Therefore, assuming without admitting and for the sake of argument that the

Petitioner is supplying power to State of Haryana and State of Chhattisgarh from

its Unit-II on interim basis till further orders are passed in this matter by Hon’ble

Supreme Court and thus having a composite scheme under Section 79(1)(b) of the

Act,, still this Commission’s jurisdiction, which is conferred by the Hon’ble

Supreme Court, cannot be taken away or altered. In fact, in view of the order of

the Hon’ble Supreme Court, contending that any other Commission can

exercise jurisdiction over the parties in question amounts to showing

disregard to the order of the Hon’ble Supreme Court.

g) It is submitted that in so far as the Petitioner, the Respondent No.1, the

Respondent No.2 and this Commission (who is Respondent No.1 in the Civil

Appeal pending before the Hon’ble Supreme Court) are concerned, the said

parties are bound by the order of the Hon’ble Supreme Court. Consequently, it

cannot be urged by the Respondent No. 2 that this Hon’ble Commission does not

have jurisdiction to entertain the present Petition. In view of the above position,

the objection raised by the Respondent No. 2 that the jurisdiction to

entertain the present petitioner lies with the CERC, is in teeth of the interim

Order dated 16.12.2011 passed by the Hon’ble Supreme Court, apart from

being misconceived and without any merit.

h) That without prejudice to the above and even otherwise, the Petitioner does not

fulfil the requirements of composite scheme of arrangement within the meaning of

Section 79(1)(b) of the Act and as laid down by the Hon’ble Supreme Court in

Energy Watchdog case (supra).

i) From Paras 20 to 29 of the said judgment in Energy Watchdog case (supra), the

Hon’ble Supreme Court has discussed and laid down the principles governing

jurisdiction of the CERC under Section 79(1)(b) of the Act. In Para 23 of the said

judgment the court has observed that “the PPA which deals with generation and

sale of electricity, will either will have to be governed by the State Commission or the

Central Commission. The State Commission’s jurisdiction is only where generation

and supply takes place within the state. On other hand, the moment generation and

sale takes place in more than one State, the central Commission becomes the

appropriate Commission under the Act.” It is important to note that in the both the

scenario i.e. generation and sale within the state and generation and sale in

more than one state, the court has qualified such generation and sale under

Page 20: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

20

the PPA. Therefore, it follows that in order to have a composite scheme of

generation and sale, PPA is a must. This becomes clear from Paras 28 and 29 of the

said judgment, wherein the Court relies upon the definition of composite scheme

given in Para 5.11 (j) of the tariff policy dated 06.06.2006 (as amended on

28.01.2016). As per the said definition, long term or medium term PPA with at

least 10% of the capacity of the project to a distribution licensee outside the

state in which the project is located is a condition precedent for composite

scheme.

j) That in the present case, only 5% power is being supplied to the State of

Chhattisgarh from Unit-II of the Petitioner, that too at variable charges only. The

Petitioner does not have any PPA with the State of Chhattisgarh for the said

supply. The remaining 95% power from Unit-II of the Petitioner is being supplied

to Respondent No. 1 for onward supply to Respondent No.2. Thus, it is clear that

neither the supply to Haryana nor to Chhattisgarh is a supply under PPA and

instead is in terms of the Hon’ble Supreme Court’s and APTEL’s order, de-hors the

PPA. Therefore, the condition precedent for composite scheme is not met in the

present case.

k) That in Para 4 of the reply, the Respondent No. 2 has raised another contention as

regards the jurisdiction of this Hon’ble Commission. The Respondent No. 2 has

stated that the jurisdiction for grant of approval to pass through the cost of

installation and commissioning of additional systems as regards Unit-I of the

Petitioner lies with Madhya Pradesh Electricity Regulatory Commission as power

from Unit-I is being supplied solely to Discoms of Madhya Pradesh. The

Respondent No. 2 has alleged that the Petitioner has not disclosed the status of

any similar reference filed by the Petitioner before the MPERC and has further

stated that view of MPERC is essential to be considered before this Commission

passes an order in the present Petition.

l) That it is submitted that a similar petition has been filed by the Petitioner before

the MPERC in respect of Unit-I of the Petitioner. The said petition was filed on

20.07.2017 i.e. after the filing of the present petition.

m) The contention of the Respondent No.2 that the view of MPERC on the said issue is

essential for this commission to consider the present petition is totally

misconceived. Admittedly, this Commission has determined tariff for supply of

power from Unit-II of the Petitioner to the Respondents. In such determination of

Page 21: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

21

tariff, this Commission has considered the capital cost incurred on Unit-II of the

Project alone. All other parameters in respect of tariff determination have been

considered exclusively of Unit-II. In so far as Unit-I is concerned, the tariff and

capital cost for the said Unit has been approved by MPERC. It is, thus, clear that the

tariff determination exercise for both the Units is separate and distinct and has

been conducted by two different Commissions. The pendency of the Petition

before the MPERC, thus, has no bearing on the present Petition which is to be

decided by this Commission separately. It is, thus, clear that the objection raised

by the Respondent No. 2 is untenable and meritless and, therefore, deserves to be

rejected.

n) This Commission had also enquired the outcome of similar Petitions filed before

other Regulatory Commissions. In this regard, the Petitioner has been able to

locate an Order dated 20.03.2017 passed by the CERC in Petition No. 72/MP/2016

(Maithon Power Limited v. Damodar valley Corporation and Ors.) and Order dated

27.04.2017 passed by UPERC in Petition No. 1132/2016 (Rosa Power Supply

Company Ltd.). The Petitioner submits that the said judgments are distinguishable

on facts and the Petitioner reserves its rights to refer to the said judgments for

their true scope and effect, at the time of hearing on merits of the present Petition.

7. The Respondent No. 1 i.e. M/s. PTC filed its reply as under:-

a) That Hon’ble Supreme Court, vide its interim order dated 16.12.2011 in Civil

Appeal No. 10329 of 2011 titled as Lanco Amarkantak Power Limited vs. Haryana

Electricity Regulatory Commission & Ors. was put in place an interim arrangement

relating to supply of power and directed determination of tariff by this

Commission. It is further submitted that pending adjudication of the said Civil

Appeal, this Commission may have jurisdiction on all tariff related matters

including change of law.

b) That Hon’ble Supreme Court in its judgment dated 11.04.2017 in Civil Appeal No.

5399 – 5300 of 2016, titled Energy Watch Dog Vs. Central Electricity Regulatory

Commission & Ors. has held that in any issue/ dispute with regard to generation

and sale of power under a composite scheme within the meaning of Section

79(1)(b) of the Electricity Act, 2003, Hon’ble CERC will have jurisdiction.

c) That keeping in view of the position of law and also interim order dated

16.12.2011 and pendency of Civil Appeal No. 10329 of 2011 before Hon’ble

Page 22: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

22

Supreme Court, the Commission may pass appropriate orders and the Respondent

No. 1 will abide by such decision.

8. The Respondent No. 2 i.e. HPPC filed its reply as under:-

a) That the instant petition is misconceived and without proper jurisdiction. It is

pertinent to note in this regard that the Petitioner has one more beneficiary other

than the Answering Respondent, i.e. State of Chhattisgarh, which has long term

arrangement with the Petitioner through Implementation Agreement. In view of

the law laid down by the Hon'ble Supreme Court in Civil Appeal no. 5399/2016,

for any issue/dispute with regard to the generation and sale of power under a

composite scheme within the meaning of Section 79(1) (b) of the Act, the Hon'ble

Central Commission alone has the jurisdiction. It is relevant here to reproduce the

operative part of the judgment, which is a under -

" ...................... Jurisdiction of the Central Commission

20. The appellants have argued before us that the expression “composite scheme” mentioned in Section 79(1) must necessarily be a scheme in which there is uniformity of tariff under a PPA where there is generation and sale of electricity in more than one State. It is not enough that generation and sale of electricity in more than one State be the subject matter of one or more PPAs, but that something more is necessary, namely, that there must be a composite scheme for the same. 21. In order to appreciate and deal with this submission, it is necessary to set out Section 2(5) of the Act which defines appropriate Government as follows: “2. Definitions. In this Act, unless the context otherwise requires, (5) "Appropriate Government" means, - (a) the Central Government, - (i) in respect of a generating company wholly or partly owned by it; (ii) in relation to any inter-State generation, transmission, trading or supply of electricity and with respect to any mines, oil-fields, railways, national highways, airports, telegraphs, broadcasting stations and any works of defence, dockyard, nuclear power installations; (iii) in respect of the National Load Despatch Centre; and Regional Load Despatch Centre; (iv) in relation to any works or electric installation belonging to it or under its control ; (b) in any other case, the State Government, having jurisdiction under this Act;” Sections 25 and 30 also have some bearing and are set out as under : “25. Inter-State, regional and inter-regional transmission. For the purposes of this Part, the Central Government may, make region-wise demarcation of the country, and, from time to time, make such modifications therein as it may consider necessary for the efficient, economical and integrated transmission and supply of electricity, and in particular to facilitate voluntary interconnections and co-

Page 23: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

23

ordination of facilities for the inter-State, regional and inter-regional generation and transmission of electricity. 30. Transmission within a State. The State Commission shall facilitate and promote transmission, wheeling and inter-connection arrangements within its territorial jurisdiction for the transmission and supply of electricity by economical and efficient utilisation of the electricity.” 22. The scheme that emerges from these Sections is that whenever there is inter-State generation or supply of electricity, it is the Central Government that is involved, and whenever there is intra-State generation or supply of electricity, the State Government or the State Commission is involved. This is the precise scheme of the entire Act, including Sections 79 and 86. It will be seen that Section 79(1) itself in sub-sections (c), (d) and (e) speaks of inter-State transmission and inter-State operations. This is to be contrasted with Section 86 which deals with functions of the State Commission which uses the expression “within the State” in sub-clauses (a), (b), and (d), and “intra-state” in sub-clause (c). This being the case, it is clear that the PPA, which deals with generation and supply of electricity, will either have to be governed by the State Commission or the Central Commission. The State Commission’s jurisdiction is only where generation and supply takes place within the State. On the other hand, the moment generation and sale takes place in more than one State, the Central Commission becomes the appropriate Commission under the Act. What is important to remember is that if we were to accept the argument on behalf of the appellant, and we were to hold in the Adani case that there is no composite scheme for generation and sale, as argued by the appellant, it would be clear that neither Commission would have jurisdiction, something which would lead to absurdity. Since generation and sale of electricity is in more than one State obviously Section 86 does not get attracted. This being the case, we are constrained to observe that the expression “composite scheme” mean anything more than a scheme for generation and sale of electricity in more than one State. 23. This also follows from the dictionary meaning [(Mc-Graw-Hill Dictionary of Scientific and Technical Terms (6th Edition), and P.Ramanatha Aiyar’s Advanced Law Lexicon (3rd Edition)] of the expression “composite”: (a) ‘Composite’ – “A re-recording consisting of at least two elements. A material that results when two or more materials, each having its own, usually different characteristics, are combined, giving useful properties for specific applications. Also known as composite material.” (b) ‘Composite character’ – “A character that is produced by two or more characters one on top of the other.” (c) ‘Composite unit” – “A unit made of diverse elements.” The aforesaid dictionary definitions lead to the conclusion that the expression “composite” only means “consisting of at least two elements”. In the context of the present case, generation and sale being in more than one State, this could be referred to as “composite”. 24. Even otherwise, the expression used in Section 79(1)(b) is that generating companies must enter into or otherwise have a “composite scheme”. This makes it clear that the expression “composite scheme” does not have some special meaning – it is enough that generating companies have, in any manner, a scheme for generation and sale of electricity which must be in more than one State.

Page 24: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

24

25. We must also hasten to add that the appellant’s argument that there must be commonality and uniformity in tariff for a “composite scheme” does not follow from the Section. 26. Another important facet of dealing with this argument is that the tariff policy dated 6th June, 2006 is the statutory policy which is enunciated under Section 3 of the Electricity Act. The amendment of 28th January, 2016 throws considerable light on the expression “composite scheme”, which has been defined for the first time as follows: “5.11 (j) Composite Scheme: Sub-section (b) of Section 79(1) of the Act provides that Central Commission shall regulate the tariff of generating company, if such generating company enters into or otherwise have a composite scheme for generation and sale of electricity in more than one State. Explanation: The composite scheme as specified under section 791) of the Act shall mean a scheme by a generating company for generation and sale of electricity in more than one State, having signed long-term or medium-term PPA prior to the date of commercial operation of the project (the COD of the last unit of the project will be deemed to be the date of commercial operation of the project) for sale of at least 10% of the capacity of the project to a distribution licensee outside the State in which such project is located.” 27. That this definition is an important aid to the construction of Section 79(1)(b) cannot be doubted and, according to us, correctly brings out the meaning of this expression as meaning nothing more than a scheme by a generating company for generation and sale of electricity in more than one State. .............."

The law laid down by the Hon'ble Apex Court is explicit from a plain reading of the

Judgment. The only test laid down by the Hon'ble Supreme Court for upholding

jurisdiction of the Central Commission in case of Composite Scheme is sale of electricity in

more than one State.

b) The question as to whether the installation and commissioning of FGD/SRC

system in view of the MoEF notification dated 07.12.2015 falls under the

definition of 'Change in law' can only be adjudicated by the Hon'ble Central

Commission as it affects two beneficiaries, i.e. State of Haryana and State of

Chhattisgarh. Further, Unit-1 of the Petitioner's Project is dedicated to Madhya

Pradesh.

c) That the issues raised by Petitioner in the present petitions has implications on all

the beneficiaries (State of Haryana, State of Chattisgarh and State of Madhya

Pradesh).

d) That the Order passed by Madhya Pradesh Electricity Regulatory Commission in a

Petition filed by the Petitioner in respect of Unit-1 of the Project seeking

Page 25: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

25

declaration that the shifting of delivery point is on account of Change in Law

within the meaning of Article 12.1.1(i) of the PPA dated 11.05.2005 and Article

12.1 of PSA dated 30.05.2005. The petitioners had also sought declaration of their

entitlement for tariff adjustment payment as per the PPA and PSA read with the

respective Implementation Mechanism. The Hon'ble MPERC in its order dated

24.08.2017 in Petition number 19 of 2017 titled as PTC India Ltd. and anr. v M.P.

Power Management Company Ltd, Jabalpur, has dismissed the petition on the

ground of jurisdiction.

e) it is further humbly submitted that this Commission is the appropriate authority

to assess tariff in accordance with HERC Tariff Regulations, 2008 in terms of Order

of the Hon'ble Supreme Court dated 16.12.2011. However, any other issue which

affects all the beneficiaries of the Petitioner's project can only be adjudicated by

the Hon'ble CERC as it has the residual authority on all issues impacting more than

one beneficiary. In that view, once the issue raised by the petitioner is adjudicated

by the Hon'ble CERC, this Commission can assess the resultant impact on tariff

after the expenditure has been incurred as per decision of the Hon'ble Supreme

Court taking into consideration actual expenditure incurred or the cost approved

by Hon'ble CERC, if any, whichever is lower. Thus, the Central Commission alone

had the necessary jurisdiction to embark upon the issues raised by the petitioner

in present case.

MAIN ARGUMENTS ADVANCED BY THE CLAIMANT

During the course of arguments, the claimant made the following submissions:

The Hon'ble Commission has the appropriate jurisdiction in view of the Supreme Court

Order dated 16.02.2011.

The scheduling of power by the Respondent no.2 does not fall under the Composite

Scheme as the power is being scheduled as per interim arrangement made by order of

Hon'ble Supreme Court and there is no long term PPA in operation.

The respondent submits that the contention of the claimant on both counts is devoid of

merit and deserves dismissal. The submissions of the respondent refuting the above

stated submissions are as under:

Page 26: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

26

1. The Hon'ble Commission has the appropriate jurisdiction in view of the Supreme

Court Order dated 16.02.2011.

The said contention of the Petitioner is incorrect and denied. As stated above, the

Hon'ble Supreme Court in its interim order dated 16.02.2011 has conferred a

limited jurisdiction on this Hon'ble Commission, i.e. for the purpose of

determination of tariff in accordance with HERC Tariff Regulations, 2008. The

operative part of the interim order reproduced hereinabove evince that there is

nothing in the order that authorize this Hon'ble Commission to adjudicate issues

for which statutory power under Section 79 is conferred to Hon'ble CERC.

It is further reiterated that this Hon'ble Commission is the appropriate authority

only to assess tariff in accordance with HERC Tariff Regulations, 2008 in terms of

Order of the Hon'ble Supreme Court dated 16.12.2011. However, any other issue

which affects all the beneficiaries of the Petitioner's project can only be

adjudicated by the Hon'ble CERC as it has the residual authority on all issues

impacting more than one beneficiary. In that view, once the issue raised by the

petitioner is adjudicated by the Hon'ble CERC, this Hon'ble Commission can

assess the resultant impact on tariff after the expenditure has been incurred as per

decision of the Hon'ble Supreme Court taking into consideration actual

expenditure incurred or the cost approved by Hon'ble CERC, if any, whichever is

lower.

2. The scheduling of power by the Respondent no.2 does not fall under the

Composite Scheme as the power is being scheduled as per interim arrangement

made by order of Hon'ble Supreme Court and there is no long term PPA in

operation.

This contention of Petitioner is incorrect and denied. At the outset, the

submissions raised above are reiterated to assert that the Petitioner is supplying

power to more than one state and the issue raised by the Petitioner in this Petition

affects all the beneficiaries. Therefore, in terms of Section 79 (1) (b) of the

Electricity Act, 2003, Hon'ble CERC alone has the jurisdiction to adjudicate this

issue.

The contention of the petitioner regarding there being no long term PPA in

Operation, it is humbly submitted that in view of the interim order of the Hon'ble

Supreme Court dated 18.09.2015 in Civil Appeal no. 10389/2011, the interim

Page 27: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

27

supply of power to the answering respondent has been recognized as equivalent

to supply of power in terms of having a subsisting long term PPA. The relevant

part of the said order is reproduced hereunder for the kind consideration of this

Hon'ble Commission.

"..........

The learned counsel for respondent no. 8 submitted that the power generating plants

for the supply of coal fall into two categories specified in the office memorandum of

the Government of India, MInistry of Coal dated 30th June, 2015. The first category is

of the generating companies which have subsisting long term power purchase

agreements and the second which do not have such agreements. In view of the fact

that the application chose to terminate his existing power purchase agreement with

respondent no. 3, the applicant is not entitled to clam supply of coal under the first

category. In response to a specific query, the learned counsel for respondent no. 8

made a clear statement that they have enough coal to supply to the application

herein subject to the various legal objections of the respondent.

Shri Harish Salve, learned senior counsel appearing for the appellant

submitted that though the legal obligations to open a Letter of Credit for an amount

Rs. 13.82 crores in favour of respondent no. 9 is that of respondent no. 3 in view of

the predicament in which the application is placed, the respondent no. 3 without

prejudice to the applicant's legal rights in this behalf.

In the circumstances mentioned above, in view of the interim order dated

16.12.2011 of this Court under which the application is obliged to continue to supply

of power we deem it appropriate to direct respondent No.8 to supply coal to the

appellant treating the appellant to be falling under category no. 1 referred to earlier

during the pendency of this appeal without prejudice to the legal right of respondent

no. 8 which can be determined at the time of the disposal of the appeal."

From the foregoing, it would be seen that the issues raised by the Petitioner in the instant

petition cannot be adjudicated by this Hon'ble Commission for want of Jurisdiction.

Commission’s Analysis & Order 9. The case was finally heard on 25.10.2018, wherein the parties mainly re-iterated

their earlier submissions, which for the sake of brevity has not been reproduced here.

Page 28: BEFORE THE HARYANA ELECTRICITY REGULATORY … · a) The Petitioner has established a coal based thermal power plant having capacity of 300 MW i.e. Unit-II at Pathadi village, Korba

28

The Commission has examined the contents of the Petition filed/ additional submissions

made by the parties and observed that the contention of the Respondent i.e. HPPC

regarding the jurisdiction of this Commission to decide the issue, has some force. The

Commission has earlier determined tariff for the supply of power by the Petitioner to the

Respondents in compliance to the directions of Hon'ble Supreme Court vide its interim

order dated 16.12.2011 which was limited to the determination of tariff in accordance

with HERC Tariff Regulations, 2008 only. When the power is being supplied under the

interim arrangement and tariff is determined de-hors the PPA, the existence of PPA, its

terms & conditions including its period are to be determined afresh. Till all these issues

are settled, the Commission finds itself unable to decide the issue of jurisdiction.

10. In view of the above and without going into the merits of the case, the petition is

disposed of for want of jurisdiction of the Commission in the matter.

This order is signed, dated and issued by the Haryana Electricity Regulatory

Commission on 15.11.2018.

Date: 15.11.2018 (Jagjeet Singh) Place: Panchkula Chairman