before the haryana electricity regulatory …tribunal for electricity, new delhi. lanco amarkantak...
TRANSCRIPT
1 | P a g e
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO 33-36 SECTOR – 4 PANCHKULA – 134112, HARYANA
CASE NO: HERC/PRO – 05 OF 2014
DATE OF FINAL HEARING: 15.12.2014
DATE OF ORDER: 23.01.2015
IN THE MATTER OF:-
Filing of Generation Tariff Application by Lanco Amarkantak Power Ltd.
(LAPL) pursuant to the Judgment dated 03.01.2014 of the Hon’ble Appellate
Tribunal for Electricity, New Delhi.
Lanco Amarkantak Power Ltd. (LAPL) PETITIONER
AND IN THE MATTER OF
1. The Managing Director Haryana Power Generation Corporation Limited
(HPGCL), Panchkula.
2. The Chief Engineer Haryana Power Purchase Centre (HPPC)
3. PTC India Limited (PTC)
4. Chhattisgarh State Power Trading Company (CSPTC)
RESPONDENTS
Quorum Shri Jagjeet Singh, Chairman Shri M.S. Puri, Member
2 | P a g e
On behalf of HPGCL/HPPC
Shri M.G. Ramachandran, Advocate Shri U.K.Agarwal, SE/HPPC Shri Ravi Juneja, AEE/ HPPC Shri Pawan Bains, AEE/ HPPC
On behalf of LAPL On behalf of PTC India Ltd.
Shri Sanjay Sen, Sr. Advocate Shri Deepak Khurana, Advocate Shri V.Ravindran, CEO, LAPL Shri S.K. Bhardwaj, LAPL Shri Anil Sharma, LAPL
Ms. Pallavi Mohan, Advocate
ORDER
1. BRIEF FACTS OF THE CASE:-
1.1 PTC India Ltd (PTC) had filed Petition No. 12 of
2010 dated 12.05.2010 seeking directions from the
Commission to amend the Power Sale Agreement (PSA)
between them and Haryana Power Generation Company
Limited (HPGCL) on behalf of UHBVNL & DHBVNL (the
Distribution licensees in Haryana).
1.2 HPGCL had filed another petition dated 22.07.2010
seeking directions against the Applicant LAPL and PTC in
connection with supply of power from Lanco Amarkantak
Power Plant Unit – 2 (hereinafter referred to as LAPL).
1.3 The aforesaid petitions were disposed of by the
Commission vide Order dated 02.02.2011.
3 | P a g e
1.4 Aggrieved by the Order dated 2.02.2011 passed by
the Commission, LAPL filed an appeal bearing No.15 of
2011 before the Hon’ble Appellate Tribunal for Electricity
(hereinafter referred to as APTEL).
1.5 The Hon’ble APTEL, vide interim Order dated
23.03.2011 directed LAPL to supply 35% of the power
from LAPL Unit - 2 to the Chhattisgarh State Power
Trading Company and balance power to Haryana. The
appeal was disposed of by Order dated 04.11.2011. The
Hon’ble APTEL continued the interim Order while
remanding back the matter to the Commission for
deciding the rights of Chhattisgarh State Power Trading
Company. Aggrieved by the Order of the Hon’ble APTEL
dated 04.11.2011, LAPL filed civil appeal No. 10329 of
2011 in the Hon’ble Supreme Court.
1.6 The Hon’ble Supreme Court passed an interim
Order dated 16.12.2011 holding, inter-alia, as under:-
“…. Without prejudice to the rights and contentions of
the parties and pending further Orders, the State
Electricity Regulatory Commission, Haryana will
fix/approve the tariff for sale and purchase of power for
the period in questions about which there is a dispute
between the appellant and PTC. The State Electricity
4 | P a g e
Regulatory Commission, Haryana will decide the dispute
uninfluenced by the observations made in the impugned
Orders passed before today, by the Appellate Tribunal
and/or any other Authority in this case. All arguments
on both sides are kept open. Liberty is given to the
parties to make a proper application supported by
relevant documents before the State Electricity
Regulatory Commission, Haryana, within four weeks……”
In view of the Order of the Hon’ble Supreme Court
LAPL filed a petition in the Commission for tariff
determination i.e. fix/approve the tariff payable by PTC
for the sale of power by LAPL for the period in question
i.e. for the power supplied from 7.5.2011 uninfluenced by
the observations made in the impugned Orders passed by
the Hon’ble APTEL and/or any other Authority in this case.
Accordingly LAPL had sought tariff computed in
accordance with Central Electricity Regulatory
Commission (Terms & Conditions of Tariff ) Regulations,
2009 for the power supplied by them to Haryana as per
the Order dated 23.03.2011 of the Hon’ble APTEL and
continued by the Order dated 16.12.2011 of the Hon’ble
Supreme Court.
5 | P a g e
The Commission, after hearing the Petitioner and
the Respondents, passed Order dated 17.10.2012. The
operative part of the said Order is reproduced below:-
“The Commission is of the view that the entire project was
conceived on the basis of coal linkage available to LAPL
from SECL. However, the fact cannot be denied that there
are some temporary disruptions in coal supply which may
not continue in future. Additionally, during the prolonged
proceedings before the Commission the Petitioner could
not place on record any material that could establish the
fact that they made bona – fide efforts to secure coal
linkage as envisaged at the project planning stage that
formed the basis of the contracted levellised tariff also
approved by the Commission. Thus the Commission, for the
purpose of tariff determination for the disputed period, has
considered weighted average cost of SECL coal to the
extent of 71% as per the details filed by the Petitioner and
29% weightage to the cost of coal from other sources.
The consumption of secondary fuel oil has been considered
at 2.0 ml/kWh as per HERC Regulations, 2008 and the
same has been valued as per data provided by the
Petitioner which has been taken at the face value. Further
the GCV of coal has been considered as per the DPR despite
the fact that the Petitioner is also using imported coal with
6 | P a g e
significantly higher GCV which in effect would reduce the
coal requirement of the Petitioner. Further the Plant Load
Factor has been retained at 80% as per the DPR which is
also in line with HERC Regulations, 2008.
In view of the above, the tariff worked out by the
Commission at generator’s bus for the disputed period
beginning 7th May, 2011, for supply of LAPL Unit – 2 power
to Haryana, based on the norms approved in this Order is
as under:
I) Tariff 7th May, 2011 to 31st March, 2012:-
Rs. 2.52/kWh.
II) Tariff FY 2012-13:- Rs. 2.46/kWh.
However, as the tariff worked out as above is more than
the levellised capped tariff, the capped tariff of Rs.
2.32/kWh shall prevail. The benefit of any difference vis-
à-vis the capped tariff shall be passed on to the Consumers
through FSA mechanism. As the capped tariff does not
include Income Tax/MAT the same shall be paid to LAPL in
addition to the capped tariff on the ROE allowed by the
Commission in this Order.
7 | P a g e
The Commission notes that the levellised capped tariff of
Rs. 2.32/kWh is at the Generator’s bus bar, hence after
considering inter – state, intra – state transmission
charges and losses the landed cost of power to the
Discoms in Haryana, without statutory levies like MAT,
ED etc., would be in excess of Rs. 2.81/kWh”.
1.7 Aggrieved by the aforesaid Order of the
Commission LAPL preferred Interlocutory Application
dated 27.12.2012 in the Hon’ble Supreme Court. The
Hon’ble Supreme Court disposed of the said Interlocutory
Application vide its Order dated 19.02.2013 directing LAPL
to file statutory appeal in the Hon’ble APTEL against the
Order dated 17.10.2012 passed by this Commission.
Accordingly LAPL filed statutory appeal in the Appellate
Tribunal for Electricity, New Delhi (APTEL). The Hon’ble
APTEL, vide its judgment dated 03.01.2014 was pleased to
allow the appeal and set aside the Order dated October
17, 2012 passed by the Commission. The Hon’ble APTEL
vide its judgment dated January 03, 2014 further directed
the Commission to re-determine the tariff by way of
interim arrangement de hors the PPA, pending disposal of
the Civil Appeal No. 10329 of 2011 in Hon’ble Supreme
Court in the light of directions and finding given by the
Hon’ble APTEL in its aforesaid judgment within two
8 | P a g e
months from the date of communication of the aforesaid
judgment to the Commission. Further, LAPL was directed
by the Hon’ble APTEL to submit additional details and
documents for the consideration of the Commission for
fixing the interim adhoc tariff for supply of power by LAPL
pursuant to aforesaid Order of the Hon’ble Supreme Court
( Paras 63 and 69 of the APTEL judgment).
In compliance of the judgment dated January 03,
2014, LAPL submitted the details and documents for
consideration of the Commission for fixing the interim
tariff as directed by the Hon’ble Tribunal with a
disclaimer that the submission of the details and
documents does not amount to acceptance or
submission to the jurisdiction of this Commission and is
without prejudice to all rights and contentions in Civil
Appeal No. 10329 of 2011 pending before the Hon’ble
Supreme Court.
The Commission, in Order to have the benefit of
the views of the contesting parties on the details/data
submitted by LAPL, scheduled a hearing of the parties on
21.02.2014. Upon hearing the parties the Commission
passed the following interim Order:-
9 | P a g e
“The Ld. Counsel Shri Deepak Khurana submitted that they
have received a copy of the reply dated 18.02.2014 filed
by HPPC only yesterday i.e. 20.02.2014. Hence he sought
short adjournment to go through the reply filed by HPPC
and submit a rejoinder to the same. The representative of
the Respondent while agreeing to the adjournment sought
submitted that due to pre-occupation of their counsel the
case may be listed for hearing on 12.03.2014 afternoon
which was agreed to by the Petitioner. Upon hearing the
parties the Commission Orders that the Petitioner may file
a rejoinder by 3.03.2014 along with a copy to the
Respondent. In case this does not happen the Commission
may be informed accordingly. No further adjournment
shall be allowed in the matter”.
The case was listed for further hearing on 12th March,
2014, all parties were informed accordingly. The notice
of hearing was also posted on the website of the
Commission under heading “Schedule of Hearings”.
Upon hearing the parties following interim Order was
passed by the Commission.
“The Ld. Counsel for the Petitioner Shri Sanjay Sen
concluded his arguments including the issues raised by
the Respondent HPPC in their written reply. The Ld.
10 | P a g e
Counsel for the Respondent (HPPC) Shri Ramachandran
argued at length vehemently contesting the
completeness and credibility of the data/information
provided by the Petitioner in their petition as well as the
rejoinder for re-determination of interim adhoc tariff for
supply of power by Lanco Amarkantak Power Limited –
Unit 2 (LAPL) in terms of judgment dated 3.01.2014
passed by Hon’ble Appellate Tribunal for Electricity in
appeal bearing no. 65 of 2013. He also raised several
legal issues in the hearing. The Ld. Counsel for the
Petitioner replied at length to the issues raised in the
hearing and suggested that the Commission may give
him further opportunity to complete his reply on
25.03.2014 which was agreed to by the Respondent.
Acceding to the above request of the Petitioner and
agreed to by the Respondent the Commission posts the
case for further hearing on 25.03.2014 at 3.00 P.M”.
1.8 The case was called for hearing on
25.03.2014, after hearing the parties the Commission
passed the following Order:-
“In the hearing held on 25.03.2014 the parties again
made detailed submissions and there were wide
difference of opinion between the parties on the
information provided by the Petitioner regarding the
11 | P a g e
Capital Cost, apportionment of Capital Expenditure
between different Units of LAPL, infirm power and the
liability of the Petitioner regarding the increase in Capital
Cost on account of claimed Force Majeure events with
reference to the agreement of the Petitioner with the
Supplier.
Upon hearing the parties the Commission feels that the
Respondent must put up their demand for information
on the above issues in a highly specific manner and the
same should be provided by the Petitioner accordingly.
Moreover, it was felt that, with the consent of both
parties, external help shall be required to have an
unbiased verification of figures and cost apportionment
formula which may even require visit to the LAPL power
plant. Accordingly, after both the parties had given their
consent, the Commission Orders as under:-
i) Direction to the Petitioner (LAPL):
a. To file an affidavit certifying that the following
facilities/assets (include details of the assets) which were
created for LAPL Unit -1 and Unit – 2 and/or Unit -1 or
Unit – 2 are not being used or will not be used for LAPL
Unit – 3 or Unit – 4.
12 | P a g e
b) The following facilities/assets created for LAPL Unit
-1 and Unit – 2 or for Unit – 1 or Unit – 2 are being used
or shall be used for LAPL Unit – 3 or Unit – 4 jointly or
separately and the amount mentioned below against
each facilities/assets have been booked to LAPL Unit – 3
or Unit – 4 jointly or separately.
c) To submit the details of prudence in claiming and
recovery of Liquidated Damages (LD) in terms of contract
with the plant/machinery suppliers due to time over –
run in commissioning LAPL Unit – 2, if any. Further, in
case such claims were permissibly, the details of the
amount realized may be provided.
d) To submit the terms of agreement with the
auditors who have verified and certified the cost overrun
claimed.
ii) Direction to the Respondent (HPPC):
a) To submit a comprehensive list of additional
data/information required to the Petitioner along with a
copy to the Commission within three days (LAPL to
provide the details within a week).
13 | P a g e
Additionally, the Commission observes that given the
fact that certain key data i.e. project cost relevant to
LAPL Unit – 2, segregation/allocation of common service
cost, sale of infirm power, and realization of linkage coal,
submitted by LAPL which has significant bearing on
re – determination of tariff was vehemently contested by
the Respondent i.e. HPGCL/HPPC. Thus, all such data, as
agreed by both the parties, would have to be
independently verified and smoothened out by an
independent Chartered Accountant (including physical
verification) having exposure in power sector preferably
large power plants and not in any way connected to
either LAPL and/or Haryana Power Utilities. In this
regard the Commission shall identify an independent
Chartered Accountant (cost to be borne equally by both
the parties) and subject to acceptance of both the
parties appoint him to carry out the necessary
verification/segregation and submit a report to the
Commission within three weeks from the date of
additional data/details to be made available by LAPL.
The Chartered Accountant so appointed may visit the
power plant, if necessary, after informing both the
parties of the visit schedule”.
14 | P a g e
1.9 In compliance to the Order (supra) HPPC
filed an affidavit dated 1.04.2014 stating as under:-
“Pursuant to the directions give by the Hon’ble
Commission at the hearing on 25.03.2014, and without
prejudice to the rights and contention of HPGCL/HPPC
the following Interrogatories are served on Lanco, for
information and details with supporting documents”.
1.10 LAPL vide their letter dated 9.04.2014
provided their reply to the above mentioned
Interrogatories.
1.11 The Commission, after obtaining concurrence of HPPC and LAPL, appointed E&Y to undertake independent verification of the project cost and related matters of LAPL Unit – 2. The scope of assignment, including site visit, was as under:
Review of project cost: Review of project cost of Unit 2 of LAPL from audited accounts/EPC contracts/purchase Orders provided by LAPL.
Financial impact due to IDC: Financial Impact of delays in terms of Interest during Construction on the capital costs caused due to Force Majeure is to be ascertained.
Identification of common Assets: Identification of common use assets namely, coal handling &
15 | P a g e
transportation, water treatment plant, ash handling plant, auxiliaries and electrical switchgear.
Cost allocation of common assets: Cost allocation of such common use assets identified above, to Unit 2. The cost allocation of common use assets shall be done on the basis of the costs provided/certified by LAPL.
Land acquisition cost: Estimation of land acquisition costs as well as site development which shall be apportioned to Unit 2.
Estimation of cost of coal: Estimation of the cost of the coal used in LAPL (Unit 2) during FY 2011-12 and FY 2012-13 from the audited accounts/contracts, considering coal available from CIL, coal procured through e-auction, coal purchased from open market and imported coal. Cost shall be worked out on the basis of coal prices and GCV mentioned in the audited accounts/contracts.
Surplus generated from infirm power: The surplus generated from sale of infirm power from Unit 2 after accounting for fuel costs is to be determined.
1.12 On receipt of report dated 8.06.2014
from E&Y the Commission scheduled a hearing on
28.07.2014. In the hearing held on 28.07.2014 the Ld.
Advocate Shri M.G. Ramachandran, appearing for HPPC
raised the following issues:
Conflict of interest of E&Y with the Lanco Group,
16 | P a g e
No site visit undertaken by E&Y as per Order of
the Commission.
Lack of details on the issue of water intake
system of LAPL Unit -2, site plan including railway
siding, sub – stations etc.
After hearing the parties the Commission passed
an Order dated 28.07.2014. The operative part of the
said Order is reproduced below:-
“Upon hearing the arguments of the parties, the
Commission makes it clear that this Commission in the
hearing held on 22.07.2014 has adopted the draft report
dated 8.07.2014 submitted by E&Y. However, it is up to
this Commission what weightage is to be assigned to the
findings of E&Y on various issues keeping in mind the
arguments of the parties as well as the records available
in this Commission. The Commission has noted the reply
of the representative of E&Y to the various queries of the
Commission in the hearing held on 28.07.2014. The
same, in brief, is reproduced below:
i) Whether all details provided by LAPL to the
interrogatories of HPPC dated 1.04.2014 has been taken
into account while submitting the draft report. This was
17 | P a g e
replied to in affirmative by E&Y. It was further submitted
that only the information relevant for preparing the
report was finally considered.
ii) On the issue of verification of the details of Capital
Cost as submitted by LAPL it was submitted by E&Y that
the same have been cross – checked with EPC/PO.
iii) Whether the details of common assets and sharing
thereto was verified. This was also replied to in
affirmative and it was added that the same has been
cross –checked with the layout plan of the projects. It
was also submitted by the Consultant that none of the
common assets of Unit 1 and Unit 2 is being utilized for
Unit 3 and Unit –4 except railway line/siding to a minor
extent.
iv) On the issue of verification of IDC with regard to force
majeure, delay in commissioning and non –availability of
long term Open Access, it was submitted by E&Y that the
impact of the same shall be separately given.
v) on the issue of capitalizing A&G and other direct
expenses after February, 2010 i.e. the date of
capitalization, E&Y submitted that the same is
18 | P a g e
permissible given the fact that the HERC Regulations
provide that any revenue earned on account of sale of
infirm”.
Subsequent to the hearing held on 28.07.2014 E&Y
submitted an addendum to their report dated 8.07.2014
and also undertook cite visit along with the officials of
HPPC, LAPL and HERC. E&Y submitted their report on the
outcome of the site visit as well as provided an affidavit
on the issue of conflict of interest.
2.0 Previous Orders of the Commission:-
2.1 The Commission while considering the PSA
with PTC for 300 MW power from LAPL (with PPA as
annexure) filed by HPGCL for approval of the Commission
passed Order dated 31/10/2007 expressing its inability to
approve the same in the format submitted therein i.e.
levellised capped tariff with pool tariff mechanism as the
same was in violation of section 62(6) of the Electricity
Act, 2003.
2.2 A review petition was filed by HPGCL against
the Order dated 31.10.2007 passed by this Commission.
After hearing the parties i.e. HPGCL, PTC and LAPL and
after considering the fresh supporting documents
19 | P a g e
submitted by the parties, the Commission vide Order
dated 6/02/2008 approved the PSA with levellised
capped tariff of Rs. 2.32/kWh at the Generator’s bus for
the entire term of the agreement, the pooled tariff
mechanism was dispensed with.
2.3 Further, on petition filed by PTC dated 12th May,
2010 seeking appropriate directions from the
Commission to amend PSA and petition dated 22nd July,
2010 filed by HPGCL seeking directions from the
Commission to restrain LAPL from revising the agreed
tariff under PPA dated 19th October, 2005 and from
restraining LAPL from selling the contracted power in
favor of HPGCL to a third party, the Commission after
hearing the parties i.e. HPGCL, PTC and LAPL (WRLDC was
not present), passed Order dated 02/02/2011 as under:-
i) The Power Purchase Agreement dated 19th October,
2005 as amended by HERC Order dated 6th
February,2008 remains valid and in force and cannot
be revised at this stage.
ii) 300 MW of contracted power should go to HPGCL
and M/s Lanco Amarkantak Private Limited is
restrained from selling the same to a third party.
iv) WRLDC to make payment for infirm power since
the date of synchronization of LAPL Unit – II from the
20 | P a g e
UI pool to HPGCL instead of M/s Lanco Power Private
Limited. HPGCL and PTC should immediately take up
the matter with CERC for appropriate directions to
WRLDC regarding payment of UI charges to HPGCL
since in such cases only CERC has the competence to
issue directions.
2.4 An appeal (No. 15 of 2011) was filed by LAPL in the
Hon’ble APTEL against HERC Order dated 2.02.2011
wherein the Hon’ble APTEL vide judgment dated
4/11/2011 upheld the jurisdiction of the Commission.
2.5 Against the above Order of Hon’ble APTEL, LAPL
filed a CWP in the Supreme Court. The Hon’ble Supreme
Court in Civil Appeal No. 10329 of 2011 filed by LAPL
Ordered that the interim Order of APTEL would continue
and the Commission shall fix/approve the tariff
uninfluenced by the observations made in the impugned
Orders passed by APTEL and/or any other Authority in
this case. Further liberty was given to the parties to
make a proper application supported by relevant
documents before HERC within four weeks. Additionally,
the Hon’ble Supreme Court observed that “all
arguments on both sides are kept open”. Consequently,
all the proceedings in the matter were stayed by the
Commission.
21 | P a g e
3. LAPL Petition for Re-determination of Tariff :-
3.1 In pursuance of the Order of the Hon’ble Supreme
Court giving liberty to LAPL to make a proper
application supported by relevant documents before
HERC within four weeks, LAPL filed the present tariff
petition. As per the tariff petition LAPL has supplied
power during the period commencing 7th May, 2011
and is required to continue supplying power till the
disposal of the civil appeal No.10329 of 2011 by the
Hon’ble Supreme Court.
Accordingly the Petitioner has made the following
submission in their petition for determination of tariff.
3.2 FIXED COSTS:-
i. Capital Cost as at the end of 6.5.2011 is Rupees
1668.37 crores netted off for revenue earned on
account of UI the Capital Cost claimed by the Petitioner
is Rs. 1356.77 Crores.
ii. Project Loan: The loan drawn for the Project
claimed by the Petitioner is Rs. 1025.18 crores,
constituting 75.56% of the claimed capital cost.
22 | P a g e
iii. Return on Equity has been computed by the
Petitioner at 15.5% for the 24.44% equity based on
Regulation 15 of the CERC Regulations 2009.
iv. Income Tax has been proposed at the prevailing
MAT rate of 20.01% (18.50% base rate + 5% surcharge +
3% cess) based on Regulation 15(4) of the CERC
Regulations 2009.
v. Interest on Loan: has been claimed based on the
actual interest payments made to the lenders in line
with Regulation 16 of CERC Regulations 2009. Interest
on Loan for the balance period of 2011-12 and FY 2012-
13 has been estimated on the basis of prevailing
interest rates and in accordance with the terms of loan
agreements executed with the lenders.
vi. Depreciation: has been computed after excluding
the cost of margin money, expenses for start-up fuel,
training expenses etc. in accordance with Regulation 17
of CERC Regulations 2009. Rates for Depreciation have
been considered in accordance with the rates specified
in Appendix III of the CERC Regulations 2009.
23 | P a g e
vii. Operation and Maintenance expenses have been
claimed as Rs. 17.88 lakhs/MW and 18.91 lakhs/MW as
applicable for a 300 MW set for the years 2011-12 and
2012-13 respectively in accordance with Regulation
19(a) of CERC Regulations 2009.
viii. Interest on Working Capital has been computed
by the Petitioner in accordance with Regulation 18(3) of
CERC Regulations 2009 considering applicable SBI PLR
for the relevant period. The Working Capital covers the
following components in accordance with the CERC
Regulation 18(1)(a):
a. Cost of Coal for 2 months b. Cost of Secondary Fuel Oil for 2 months c. O&M expenses for 1 month d. Maintenance Spares at 20% of O&M expenses and e. Receivables for 2 months
ix. For the period May 2011 to December 2011, the
Interest on Working Capital has been computed based
on actual landed cost of fuel and Gross Calorific Value
(GCV) of fuel actually fired during the month. For the
period commencing from January 2012 onwards the
cost of fuel has been considered based on the landed
cost incurred and GCV of fuel actually fired during the
previous 3 months period of October 2011 to December
24 | P a g e
2011 and no fuel price escalation has been considered
as has been provided under Regulation 18(2) of CERC
Regulations 2009.
x. Secondary Fuel Oil expenses have been proposed
as a part of Fixed Costs in accordance with Regulation
14 of CERC Regulations 2009 and Normative Specific
Fuel Oil consumption of 1.0 ml/kWh has been
considered as provided under Regulation 26(iii)(a) of
CERC Regulations 2009. For the period May 2011 to
December 2011, the actual landed cost of secondary
fuel oil for the month has been considered. For the
period commencing from January 2012 onwards the
cost of secondary fuel oil has been considered based on
the actual average landed cost incurred during the
previous 3 months period of October 2011 to December
2011 has been considered as has been provided under
Regulation 20(2) of CERC Regulations 2009.
xi. The Petitioner has submitted that as per the
Implementation Agreement signed with Government of
Chhattisgarh, the Petitioner has submitted that they are
under an obligation to supply 5% of net power
generated at Energy Charges. Accordingly, the Fixed
25 | P a g e
Charge per kWh has been grossed up taking the above
5% power into consideration.
3.3 ENERGY CHARGES:-
3.3.1 The Petitioner has computed energy charges in
accordance with the formula specified in the Regulation
21(6)(a) of CERC Regulations 2009.
Normative Gross Station Heat Rate of 2401 Kcal/kWh
has been adopted as per Regulation 26(ii)(B) of CERC
Regulations 2009 applicable for Pressure Rating of 170
kg/cm2 as indicated below:
Max Design Unit Heat Rate : 2294 Kcal/kWh
Less 40 Kcal/kWh for electrical: 2254 Kcal/kWh Operated boiler feed pump (as per Regulation 26(B)(a)
Gross Station Heat Rate: 1.065 x Design Heat Rate: 1.065 x 2254 : 2401 Kcal/kWh
3.4.1 Auxiliary Energy Consumption:- In accordance with
Regulation 26(iv) of CERC Regulation 2009, the
Normative Auxiliary Consumption has been
considered by the Petitioner at 9% since the Unit has
electrically driven boiler feed pump and uses
induced draft cooling towers.
26 | P a g e
3.5.1 Landed cost and the GCV of coal for the period
commencing from May 2011 to December 2011 has
been considered by the Petitioner based on actual
receipts and consumption respectively. Landed cost
of coal has been computed in accordance with
Regulation 21(7) of CERC Regulations 2009 adopting
normative transit and handling loss of 0.8%.
3.6.1 Further the Petitioner has requested that Energy
Charges for the period January 2012 to March 2012
of 2011-12 and FY 2012-13 may be allowed to be
recovered in accordance with the CERC formula.
3.7.1 With regard to the tariff computed for the period
from 7th May 2011 to December 2011, the Petitioner
has submitted that the Letter of Assurance (LoA)
issued by South Eastern Coalfields Ltd.(SECL) vide
letter dated 18.9.2006 guarantees coal supply to the
extent of 1.445 Million Tons Per Annum (MTPA).
However, due to various directions issued by
Government of India pursuant to new coal
distribution policy, the actual coal supply has been
reduced progressively and stands at the current
allocation of 0.94 MTPA against the requirement of
about 1.62 MTPA for meeting 85% PLF.
27 | P a g e
3.8.1 A table indicating the progressive reduction in
coal allocation by SECL submitted by the Petitioner is
as follows:-
Reference Period Annual Quantity
MoU dated 15th Mar 2010
2009-10 18 lakh tons
MoU dated 27th Jul 2010
2010-11 13 lakh tons
MoU dated 30th Aug 2011
2011-12 (from September
2011 to December 2011)
9.4 lakh tons
The Petitioner has submitted that the current
allocation of coal from SECL would only be adequate
to operate the plant at about 45% to 50% PLF, which
would further depend upon the quality and quantity
of coal that may be actually supplied. Further they
have submitted that after the expiry of the MoU for
the FY 2010-11 in March 2011, the MoU for FY 2011-
12 was not executed/extended immediately, a fresh
MOU for FY 2011-12 was signed only on 30.08.2011
and the coal supply commenced from September
2011. No coal was supplied by SECL during the
period April 2011 to August 2011. Therefore, the
power plant had to be operated with the linkage
coal stocks whatever were available and
supplemented by procurement of costlier coal from
28 | P a g e
alternate sources like Imported Coal, e-auction coal
and coal procured from open market. It was
submitted that the cost of coal from alternate
sources is more than 3 times of the cost of linkage
coal supplied by SECL.
The following data was presented by the
Petitioner to show the availability of linkage coal
supply during the period May 2011 to December
2011:
Month Linkage Coal Supply from SECL (in MT)
May 11 - June 11 -
July 11 - August 11 -
Sept 11 59,169
Oct 11 76,926 Nov 11 72,421
Dec 11 88,680
The Petitioner further submitted that to
bridge the shortfall in domestic coal supply, the
Ministry of Power (MoP) has been directing various
power plants in the Country to procure imported
coal. In the process similar directions were also
issued to them vide Ministry of Power letter dated
11.6.2010 directing the Petitioner to procure 3
29 | P a g e
lakhs tons of imported coal. Further in the minutes
dated 18.04.11 of the Standing Linkage Committee
(Long Term) for Power under the Ministry of Coal,
Government of India, it was decided that the
model FSA formulated by CIL/SECL under New Coal
Distribution Policy envisages supply of 50%
domestic coal and balance 50% would be supplied
from imported coal, if available. From the
aforesaid minutes, it is thus evident that the
operation of power plant on purely domestic coal
is no more possible and procurement of imported
coal is inevitable which results in increase in cost of
generation.
3.9.1 That apart from the tariff claimed under the
present application, the Petitioner has submitted
that they are paying Electricity Duty & Cess to the
Government of Chhattisgarh for the Auxiliary
Consumption of the Project. LAPL has prayed that
they should be allowed to recover the Electricity
Duty & Cess paid to the Government of Chhattisgarh
in proportion to the power actually supplied to
Haryana.
a) In view of the above submissions LAPL has
prayed as under:-
30 | P a g e
The Commission may fix/approve the tariff in
accordance with the CERC Regulations 2009 for the
power supplied by the Applicant to PTC in terms of
the APTEL Order dated 23.03.2011 during the period
7th May 2011 to December 2011, in Rupees per unit,
as indicated below:-
Month May 11 June 11 July 11 Aug 11 Sep 11 Oct 11 Nov 11 Dec-11
Fixed Cost 1.85 1.86 1.87 1.96 1.90 1.88 1.87 1.85 Variable Cost 0.98 1.17 2.00 3.12 2.03 1.96 1.63 1.31
Total Cost 2.83 3.02 3.87 5.08 3.93 3.84 3.50 3.16
b) Fix/Approve tariff for the power proposed
to be supplied by the Applicant to PTC in terms of
Appellate Tribunal Order dated 23.3.2011 during the
balance period of FY 2011-12 and FY 2012-13 in
accordance with the regulations of CERC 2009, in
Rupees per unit, as indicated below:
Period Jan 12 to Mar 12 FY 2012-13
Fixed Cost 1.85 1.84
Variable Cost As per CERC Regulations 2009
c) Direct PTC to pay the difference in the tariff
paid by PTC for supply of power from 7th May, 2011
onwards at the tariff as per the CERC Regulations,
31 | P a g e
2009 within a period of two weeks from the date of
the Order.
d) Pass such Orders as the Commission may
deem fit and proper and necessary in the facts and
circumstances of the case.
4. The Commission, after considering the written as well as oral submissions of the parties and after perusing the records available in the Commission passed an Order dated 17.10.2014. The operative part of the said Order is as under:-
“ Based on the Submissions/arguments of the
parties the Commission has framed the following
issues for its consideration:-
A. Whether the Commission is competent to
adjudicate on the issue of allocation of power
from 300 MW LAPL Unit – 2 to CSPTC and
Haryana at this stage.
B. Whether capital cost as per Company’s Auditor’s
certificate has to be accepted by the Commission
for the purpose of tariff determination.
C. Whether performance parameters, both financial
and technical, has to be reckoned with as per
32 | P a g e
CERC 2004 Regulations or CERC 2009 Regulations
or some other norms.
D. Whether the Commission can determine the tariff
afresh irrespective of the fact that the tariff with
a levellised cap has already been agreed upon by
the parties for 25 years.
E. Whether the levellised cap tariff of Rs. 2.32/kWh
can be ignored.
8. In Order to find a reply to the issue framed at Para
9 ‘A’ The Commission has perused its own Order dated
02/02/2011 wherein it was held by us that 300 MW of
contracted power should go to HPGCL and M/s LAPL is
restrained from selling the same to a third party. The
Commission observes that this Order of the Commission
was subject matter of Appeal (No. 15 of 2011) before the
Hon’ble APTEL. The Commission has further considered the
submissions of CSPTC including their arguments in the
hearing before the Commission and is of the view that as
per the Hon’ble APTEL’s Interim Order the Petitioner was
directed to supply 65% power to Haryana and the balance
35% power to CSPTCL. The said interim Order has been
continued by the Hon’ble Supreme Court. Thus till further
Orders are passed by the Hon’ble Supreme Court of India
33 | P a g e
and/or till the disposal of C.A. 10329 of 2011, the
Commission is not going into the merits of allocation of
power based on the PPA/PSA or MOU/Implementation
Agreement signed between the parties.
Based on the above discussions the issue framed by us at
Para 9 ‘A’ is answered in negative i.e. at this stage the
Commission is not going into the merits of allocation of
power between CSTPC and Haryana. Further the
Commission agrees to the contention of CSPTC that the
tariff determined by this Commission shall be applicable
to the power supplied by LAPL Unit – 2 to Haryana only.
9. In Order to settle the issue framed by us at Para 9 ‘B’
the Commission has perused the arguments of the parties
as well as the case laws cited by them. After careful
perusal of the case laws the Commission observes that the
issue has been well settled by the Judgment of the Hon’ble
APTEL in Appeal No. 94 of 2008 as well as the decision of
the Hon’ble Supreme Court in West Bengal Electricity
Regulatory Commission Vs. CESC Ltd. (2002) (81) SCC 715.
Hence in view of the settled law the issue framed by us
at Para 9 ‘B’ is answered in negative i.e. prudence check
has to be applied in all instances irrespective of the fact
34 | P a g e
that the Company’s Auditor and or any other authority has
certified/approved the capital cost. The cost efficiency and
timeliness of executing the project by a developer has to
be examined by the Commission, more so, from the
perspective of protecting the interest of electricity
consumers who have to ultimately bear the burden of all
such costs if they were to be considered as a pass through.
10. On the issue of applicability of CERC norms the
Commission finds that the Petitioner has vehemently
argued for adoption of norms in accordance with CERC
2009 Regulations while the Respondents are pressing for
adoption of norms as per CERC 2004 Regulations. The
Commission observes that the tariff in dispute was agreed
upon by the parties prior to the provisions of National
Tariff Policy notified by the Ministry of Power, Government
of India in pursuance of the provisions of Electricity Act,
2003, came into force. Further, the said PPA (and by
default the PSA) which specified all the normative details
as well as the agreed upon tariff was unilaterally
terminated by LAPL. The Order of the Commission dated
02/02/2011 was challenged by LAPL in the Hon’ble APTEL
and subsequently the Order of Hon’ble APTEL dated
04/11/2011 in the aforesaid matter was challenged in the
Hon’ble Supreme Court, where the matter is still pending
35 | P a g e
final disposal. In view of this the Commission is of the
considered view that if CERC Regulations (which also finds
a mention in the PPA/PSA) were to be sacrosanct, the
matter could have been referred to the CERC. However, it
was not to be and the Hon’ble Supreme Court gave the
liberty to LAPL to file a petition for determination of tariff
for the disputed period in HERC and at the same time
continued with the allocation of power i.e. 65% to
Haryana and 35% to CSPTC. Thus given the peculiarity of
the case the Commission is of the opinion that for the
disputed period beginning 07th May, 2011 (the date from
which supply of power commenced) till the case is finally
settled by the Hon’ble Supreme Court, the Commission
shall apply its own benchmark norms wherever applicable
and for other parameters i.e. capital cost, cost of coal etc.
the same shall be reckoned with after applying prudence
check in reference to the original scheme of the project
that had formed the basis of arriving at the tariff agreed
upon by the parties for a period of 25 years.
In view of the above discussions the issue framed by us
at Para 9 ‘C’ is answered in favor of adopting HERC’s own
benchmarks and subject to prudence check wherever
applicable.
36 | P a g e
11. In Order to find an answer to the issue framed at
Para 9 ‘D’ the Commission has carefully gone through the
Judgment dated 16.12.2011 of the Hon’ble Supreme Court
i.e.
“…. Without prejudice to the rights and contentions of the
parties and pending further Orders, the State Electricity
Regulatory Commission, Haryana will fix/approve the tariff
for sale and purchase of power for the period in questions
about which there is a dispute between the appellant and
PTC. The State Electricity Regulatory Commission, Haryana
will decide the dispute uninfluenced by the observations
made in the impugned Orders passed before today, by the
Appellate Tribunal and/or any other Authority in this case.
All arguments on both sides are kept open. Liberty is given
to the parties to make a proper application supported by
relevant documents before the State Electricity Regulatory
Commission, Haryana, within four weeks……”.
In view of the fact that the main proceedings
before the Commission was triggered because the PPA for
supply of power from LAPL Unit – 2 to PTC was unilaterally
terminated by LAPL and hence PTC was unable to meet its
obligations for onward supply of power from LAPL Unit – 2
to Haryana under the Power Sale Agreement (PSA) signed
with the Respondent i.e. HPGCL. The proceedings initiated
37 | P a g e
in the Commission by HPGCL seeking directions to PTC and
LAPL to honor their commitment under the concluded
PPA/PSA was contested by LAPL on the issue of jurisdiction
wherein the Commission held that it has the jurisdiction to
proceed in the matter. This view of the Commission was
also upheld by the Hon’ble APTEL on the basis of the fact
that there is a clear nexus between PPA & PSA as the later
does not survive without the former and LAPL was also a
party before the Commission in the proceedings for
approval of PSA between HPGCL and PTC. However, this
finding of the Commission as well as the Hon’ble APTEL
was agitated before the Hon’ble Supreme Court leading to
the passing of the above mentioned interim Order by the
Supreme Court.
Thus as the fact stands today LAPL is supplying
power from the same Unit – 2 to more than one state i.e.
Haryana and Chhattisgarh. As the sale to more than one
State has been adjudicated upon by the Hon’ble APTEL and
continued by the Order dated 16/12/2011 of the Hon’ble
Supreme Court notwithstanding the merit of MOU &
Implementation Agreement (IA) signed by LAPL and
Chhattisgarh Government arguments on which is still to be
decided by the Hon’ble Supreme Court. Therefore, as the
sale of power as on date, is to more than one State that
38 | P a g e
matter could have been remanded to CERC. However, the
Hon’ble Supreme Court has directed this Commission to
“fix/approve the tariff for sale and purchase of power for
the period in questions about which there is a dispute
between the appellant and PTC”. Consequently, the
Commission has very carefully examined the aforesaid
direction of the Hon’ble Supreme Court and observes that
the said Order directs the Commission to fix/approve tariff.
Further, a perusal of the arguments of LAPL as well as
HPGCL/HPPC and PTC establishes the fact that all of them
agree that tariff for Haryana has to be fixed/approved. The
only point of dispute is on the norms to be adopted and
applicability of capped tariff.
Additionally as per the judgments of Hon’ble Supreme
Court and Hon’ble APTEL cited by the Petitioner, it is quite
clear that the Commission can go beyond the terms of PPA
while determining tariff under section 62 of the Act.
However, such situations could be as under:
i) When the terms of PPA are in violation of the provisions
of the Act or the Regulations framed thereto.
ii) When the terms of the PPA are detrimental to the
consumers’ interest, and result in unreasonable price of
39 | P a g e
electricity to the consumers as provided under section
62(1)(a).
The present case is somewhat unique i.e. it is a case of
negotiated tariff agreed upon between the generator and
buyer. This is neither covered by the provisions of Section
62 nor fully covered by the provisions of Section 63 of the
Act. This Commission had approved the negotiated tariff
keeping in view the fact that it more than protected the
consumers’ interest by ensuring a reasonable price of
electricity. Thus, this case can be considered closer to the
situation envisaged in Section 63 of the Act as the
Commission adopted the tariff, though no bidding had
taken place. In such an event the judgments cited by the
Petitioner are clearly distinguished on the facts as those
judgments relate to cases which are covered under Section
62 of the Act.
In view of the above discussions the issue framed by us
at Para 9 ‘D’ is answered in affirmative. However, as per
the judgment of the Hon’ble Supreme Court the tariff
determined by the Commission shall apply only to the
disputed period beginning 7th May, 2011 and for power
supplied to Haryana.
12. The last issue framed by us at Para 9 ‘E’ has been
examined at length. The Commission observes that the
40 | P a g e
judgment of the Hon’ble Supreme Court, under which the
instant tariff petition has been filed by LAPL, nowhere
mentions that the capped tariff voluntarily agreed upon by
the parties in the concluded PPA/PSA should be
disregarded. Thus the Commission finds no merit in the
contention of the Petitioner that the tariff capping
arrangement ought to be dispensed with. Further the
Commission agrees with the fact, also upheld by Hon’ble
APTEL in Appeal No. 29 of 2011, that if Power Purchase
Agreement is not in conformity with the Electricity Act,
2003 it loses its legal force. On this issue the Commission
observes that the Petitioner, at no stage, has contested
the fact that the concluded PPA is in violation of any of the
provisions of the Electricity Act, 2003 and hence the same
needs to be disregarded.
Further the Commission has examined the contention of
the Petitioner that the Discoms have already adopted
CERC tariff and HPGCL is already recovering the same from
the consumers and observes that the facts are somewhat
different. HPGCL does not come in the picture at all as the
power procurement as well as distribution and retail
supply of electricity is done by the two distribution
licensees in Haryana. The power purchase cost including
that of power supplied by LAPL/PTC is approved by the
41 | P a g e
Commission on a projected basis at the beginning of the
year on the basis of the rates as per the PPAs or in its
absence the recent invoices raised by the suppliers of
power with some adjustments for any anticipated change
in the rates. However, the source wise power purchase
cost so approved by the Commission is trued up through
FSA mechanism so that no additional burden is imposed
on the electricity consumers. In the case of the Petitioner,
the Commission observes that in the ARR of the Discoms
for FY 2012-13 the rate allowed for PTC/Lanco
Amarkantak power was Rs. 3.52/kWh based on the
average rate from May 2011 to December 2011 as against
Rs. 3.701/kWh proposed by the Discoms, subject to
adjustments through FSA mechanism as the actual tariff
within a cap of Rs. 2.32/kWh was still to be determined.
Consequently, the contention of the Petitioner that CERC
tariff was already adopted by the Discoms is not true.
In view of the above discussions the Commission answers
the issue framed at Para 9 ‘E’ in negative i.e. the capped
tariff agreed upon by the parties cannot be ignored.
13. In view of the above discussions the Commission
considers it appropriate to proceed with tariff
determination of the tariff for the disputed period as
42 | P a g e
directed by the Hon’ble Supreme Court and in accordance
with the provisions of the Electricity Act, 2003.
14. For the fixation of tariff, the Petitioner has
submitted that the Commission may consider capital cost
of Rs. 1356.77 Crore as at the end of 06.05.2011 i.e. Rs.
1668.37 Crore netted off for revenue earned on account of
UI, which is the actual capital cost incurred and verified by
the auditor. Per Contra HPGCL/HPPC has argued that the
capital cost for determination of tariff ought to be
determined by the Commission after applying prudence
check on the actual capital cost claimed to have been
incurred by the Petitioner. The Petitioner should be
directed to file all the relevant documents and audited
amounts in regard to capital expenditure pertaining to the
second unit of 300 MW.
The Commission observes that the levellised tariff
approved by this Commission was based on an aggregate
project cost as per the Detailed Project Report finalized in
accordance with CERC norms which was Rs. 1340.041
Crore as against Rs. 1356.77 Crore now claimed by the
Petitioner. Further, there is no audited account specifically
available for Unit – 2 of LAPL from where 300 MW power
was contracted to Haryana. Additionally, there is nothing
on record available to the Commission to establish the fact
43 | P a g e
that the project developer exercised sufficient prudence to
efficiently execute the project within the cost and timeline
as originally envisaged. On the contrary the
Commissioning of the project was un-necessarily lingered
on which also invited adverse comments from the CERC.
In view of the above the commission considers it
appropriate to consider project cost of Rs. 1007.731 Crore
for the purpose of tariff determination for the disputed
period i.e. Rs. 1340.041 Crore less Rs. 332.31 Crore
revenue earned on account of UI.
15. On the issue of financial structure the Petitioner
has submitted that the Debt drawn for the Project was Rs.
1025.18 Crores constituting 75.56% of Capital Cost and
the balance 24.44% is the equity capital. Per Contra
HPGCL/HPPC has submitted that Debt: Equity ratio of
80:20 should be considered in relation to the Petitioner’s
project.
The Commission observes that the Debt: Equity ratio
envisaged in the original scheme was 80:20. As the tariff is
estimated on normative basis the same has been
considered irrespective of the actual draw down of debt as
claimed by the Petitioner. Even otherwise the actual draw
down of debt as claimed by the Petitioner is Rs. 1025.18
Crore against the project cost of Rs. 1007.731 Crore now
44 | P a g e
considered by the Commission for the purpose of tariff
determination which works out to more than 100% of the
Project Cost. Consequently, a normative Debt: Equity ratio
of 80:20 is being considered by the Commission for the
purpose of computing interest cost of normative debt and
ROE.
16. Return on Equity (ROE) has been claimed by the
Petitioner at 15.5% for the 24.44% equity based on
Regulation 15 of the CERC Regulations 2009. While
objecting to this HPGCL/HPPC has submitted that the
approved financial package in this case is 80% debt and
20% equity. Accordingly, HPGCL/ HPPC has proposed that
the capital cost duly scrutinized subject to prudence check
and approved, should be apportioned in 80:20 ratio and
ROE should be restricted to 20% of the Capital Cost.
The Commission has considered the submissions of the
parties on the issue of ROE and observes that HERC
Regulations, 2008 provides as under:-
(iii) Return on Equity:
Return on equity shall be computed on the equity base
determined in accordance with regulation 15 @ 14% per
annum.
Hence, for the purpose of tariff determination the
Commission has considered 14% ROE on 20% of the capital
45 | P a g e
cost approved by the Commission as against 15.5% claimed
by the Petitioner as this also formed the basis of arriving at
a levellised tariff approved by the Commission.
17. Interest on Loan: has been claimed by the
Petitioner based on actual interest payments made to the
lenders in line with Regulation 16 of CERC Regulations
2009. Interest on Loan for the balance period of 2011-12
and FY 2012-13 has been estimated on the basis of
prevailing interest rates and in accordance with the terms
of loan agreements executed with the lenders. On this
issue HPGCL/HPPC has submitted that the interest on
working capital should be calculated on normative basis
hence the actual amount of capital employed by the
generating company from time to time in regard to coal
consumption etc. is irrelevant and the working capital
needs to be uniform throughout the tariff period of
2009-14.
The Commission has considered the above submission and
counter submissions on the issue of interest on working
capital and is of the view that the financial closure of the
project is attained prior to the actual implementation of
the project. Hence, the project loan including working
capital loans are agreed upon with lenders upfront.
46 | P a g e
Consequently, in line with the DPR that formed the basis of
arriving at the levellised capped rate voluntarily agreed
upon by the parties, the Commission has considered
12.10% interest on term loan and 13.10% interest on
working capital loan on the normative debt and working
capital requirement approved by the Commission.
18. Operating & Maintenance Expenses (O&M): The
Petitioner has claimed O&M expenses of Rs. 17.88
lakhs/MW and Rs. 18.91 lakhs/MW as applicable for a 300
MW set for the years 2011-12 and 2012-13 respectively in
accordance with Regulation 19(a) of CERC Regulations
2009. While contesting this claim HPGCL/HPPC has
submitted that O&M expenses need to be ascertained in
terms of CERC Regulations, 2004 based on the capital cost
finally determined by the Commission. They have further
submitted that under the Tariff Regulations, 2009, the
O&M Expenses are on normative basis and need to be
allowed only on that basis. Any claim on the part of the
Petitioner contrary to the above is wrong.
The Commission has considered the above submissions
and observes that while the Petitioner has considered
O&M expenses as per CERC Norms, 2009, HPGCL/HPPC
has proposed that the same should be as per
47 | P a g e
CERC Regulations, 2004. The Commission is of the view
that the DPR envisaged Rs. 1.265 Million/MW O&M
expenses in accordance with CERC Regulations, 2004, and
hence the same has been retained by the Commission for
working out tariff in the instant case despite the fact that
as per HERC Regulations, 2008 the O&M amount works
out on the lower side.
19. Energy Charges:-
The Petitioner has proposed Normative Gross Station Heat
Rate of 2401 Kcal/kWh as per Regulation 26(ii)(B) of CERC
Regulations 2009 applicable for Pressure Rating of 170
kg/cm2 , while HPGCL/HPPC has submitted that the same
ought to be in line with CERC Regulations, 2004.
The Commission observes that the Station Heat Rate
(Kcal/kWh) envisaged at the DPR stage which formed the
basis of contracted tariff was 2500 Kcal/kWh. The
Commission observes that the SHR, due to inherent
improvement in technology, has witnessed substantial
improvement in the case of 300 MW thermal powerhouses
which is also reflected in the actual performance reported
by the Petitioner in the case of their Unit – 2. Thus the
Commission, for the purpose of determining tariff for the
48 | P a g e
disputed period, in line with HERC Regulations, 2008, has
considered SHR at 2410 Kcal/kWh i.e. 2450 Kcal/kWh
minus 40 Kcal/kWh as the boiler feed pump in the instant
case is electrically operated.
20. Auxiliary Energy Consumption:- The Petitioner has
proposed auxiliary energy consumption in accordance with
Regulation 26(iv) of CERC Regulation 2009, the Normative
Auxiliary Consumption has been considered at 9% since
the Unit has electrically driven boiler feed pump and uses
induced draft cooling towers. As the same is in line with
the original scheme of things as well as HERC
Regulations, 2008, 9% auxiliary energy consumption has
been retained by the Commission for the purpose of
tariff determination.
21. Landed cost and the GCV of coal: for the period
commencing from May 2011 to December 2011 the
Petitioner has proposed landed cost of coal based on
actual receipts and consumption respectively. It was
submitted by the Petitioner that Landed cost of coal has
been computed in accordance with Regulation 21(7) of
CERC Regulations 2009 adopting normative transit and
handling loss of 0.8%. The Petitioner has requested that
Energy Charges for the period January 2012 to March
49 | P a g e
2012 of 2011-12 and FY 2012-13 may be allowed to be
recovered in accordance with the CERC formula.
With regard to the tariff computed for the period from 7th
May 2011 to December 2011, the Petitioner has submitted
that the Letter of Assurance (LoA) issued by South Eastern
Coalfields Ltd.(SECL) vide letter dated 18.9.2006
guarantees coal supply to the extent of 1.445 Million Tons
Per Annum (MTPA). However, due to various directions
issued by Government of India pursuant to new coal
distribution policy, the actual coal supply has been
reduced progressively and stands at the current allocation
of 0.94 MTPA against the requirement of about 1.62
MTPA for meeting 85% PLF. The Commission observes that
as per norms approved by the Commission including
normative PLF of 80% the coal requirement works out to
1.32 MTPA. Consequently, as per submissions of the
Petitioner on availability of the SECL link coal to the extent
of 0.94 MTPA, the percentage of linked coal works to the
coal requirement estimated by the Commission works out
to about 71%.
The Commission is of the view that the entire project was
conceived on the basis of coal linkage available to LAPL
from SECL. However, the fact cannot be denied that there
50 | P a g e
are some temporary disruptions in coal supply which may
not continue in future. Additionally, during the prolonged
proceedings before the Commission the Petitioner could
not place on record any material that could establish the
fact that they made bona – fide efforts to secure coal
linkage as envisaged at the project planning stage that
formed the basis of the contracted levellised tariff also
approved by the Commission. Thus the Commission, for
the purpose of tariff determination for the disputed
period, has considered weighted average cost of SECL coal
to the extent of 71% as per the details filed by the
Petitioner and 29% weightage to the cost of coal from
other sources.
The consumption of secondary fuel oil has been
considered at 2.0 ml/kWh as per HERC Regulations, 2008
and the same has been valued as per data provided by
the Petitioner which has been taken at the face value.
Further the GCV of coal has been considered as per the
DPR despite the fact that the Petitioner is also using
imported coal with significantly higher GCV which in
effect would reduce the coal requirement of the
Petitioner. Further the Plant Load Factor has been
retained at 80% as per the DPR which is also in line with
HERC Regulations, 2008.
51 | P a g e
22. In view of the above, the tariff worked out by the
Commission at generator’s bus for the disputed period
beginning 7th May, 2011, for supply of LAPL Unit – 2
power to Haryana, based on the norms approved in this
Order is as under:
Tariff 7th May, 2011 to 31st March, 2012: Rs. 2.52/kWh.
Tariff FY 2012-13: Rs. 2.46/kWh.
However, as the tariff worked out as above is more than
the levellised capped tariff, the capped tariff of Rs.
2.32/kWh shall prevail. The benefit of any difference vis-
à-vis the capped tariff shall be passed on to the
Consumers through FSA mechanism. As the capped tariff
does not include Income Tax/MAT the same shall be paid
to LAPL in addition to the capped tariff on the ROE
allowed by the Commission in this Order.
The Commission notes that the levellised capped tariff of
Rs. 2.32/kWh is at the Generator’s bus bar, hence after
considering inter – state, intra – state transmission
charges and losses the landed cost of power to the
Discoms in Haryana, without statutory levies like MAT,
ED etc., would be in excess of Rs. 2.81/kWh” .
52 | P a g e
Aggrieved by the aforesaid Order dated 17.10.2012
passed by the Commission, LAPL preferred an appeal
bearing number 65 of 2013 before the Hon’ble APTEL. The
Hon’ble APTEL, vide its judgment dated January 03, 2014
was pleased to allow the ibid appeal and set aside the
Order dated October 17, 2012 passed by the Commission.
The Hon’ble Tribunal vide its judgment dated January 03,
2014 directed the Commission to re-determine the tariff
by way of interim arrangement dehors the PPA, pending
disposal of the Civil Appeal No. 10329 of 2011 in Hon’ble
Supreme Court in the light of directions and finding given
by the Hon’ble Tribunal in its aforesaid judgement within
two months from the date of communication of the
aforesaid judgment to the Commission. Further, as
directed by the Hon’ble APTEL LAPL submitted additional
details and documents to the Commission for fixing the
interim adhoc tariff for supply of power by LAPL pursuant
to aforesaid Order passed by the Hon’ble Supreme Court.
In compliance of the judgment dated January 03,
2014, following details and documents were submitted
without prejudice to all rights and contentions in Civil
Appeal No. 10329 of 2011 pending before the Hon’ble
Supreme Court.
53 | P a g e
A. Documents containing details of actual Capital Cost
incurred up to the date of COD of the project for Unit 2
supported by Auditor’s Certificate.
B. A statement showing lender wise loans drawn and
their outstanding loans as on COD is enclosed and
supported by Auditor’s Certificate.
C. A note on the cost of common facilities of Unit 1 &
2 of LAPL.
D. Regarding detailed reasons for time and cost
overrun of the project, it is submitted that LAPL had duly
exercised prudence to efficiently execute the project
within the cost and timeline as originally envisaged.
However, we would like to place on record that there
were unequivocally agreed Force Majeure conditions
that caused delay in commissioning the project. We
respectfully submit that the commissioning of the Project
was delayed due to occurrence of Force Majeure events
which were not within our reasonable control and could
not be prevented by taking reasonable care. We had duly
informed PTC India Limited time to time in this regard.
We would like to draw your kind attention that M/s
Dongfang Electric Corporation, China (DEC), was our
supplier of main plant equipment and BTG component of
project and manufacturing units of DEC were severely
damaged due to earthquake in China and DEC could not
supply the machines and equipments and vis a vis could
not be received by us in time. Further, due to new Visa
Policy enforced by Government of India in
September/October 2009 all the Chinese Engineers of
DEC, who were supervising the erection, testing and
54 | P a g e
commissioning activities at the project site were forced
to leave the country on or before 31-10-2009 that caused
non availability of Chinese Experts for supervising the
erection, testing and commissioning activities and has
resulted in delay in said activities. We had duly informed
PTC India Limited vide our letter dated 28-05-2008 and
subsequently submitted a report vide letter dated 5-12-
2008 with respect of aforesaid Force Majeure events.
The above said Force Majeure events were duly
acknowledged and accepted by PTC and accordingly filed
Case no. HERC/PRO -12 dated 13.05.2010 before the
learned Commission. It was submitted by LAPL that even
the Commission duly appreciated and acknowledged as
well as accepted the aforesaid Force Majeure events in
its Order dated 02-02-2011 and held that “Force Majeure
Event as claimed by PTC/LAPL did happen and the same
were not disputed by HPGCL”. That our lead lender PFC
has approved the Project cost overrun. Further, it may be
noted that the reasons for delay in commissioning of the
project of LAPL were reasonable and appropriate which
were noted by the majority judgment dated 09.02.2012
passed by Central Electricity Regulatory Commission
(Para 40 of the judgment). It was further clarified that
some alleged adverse comments about the
commissioning of the Project of LAPL were made in the
minority judgment dated 13.02.2012 of CERC which has
no effect in the eyes of law as it is a trite principle of law
that only majority judgment is binding. The approval of
project cost over-run by our lead lender PFC Letter of
PTC India Limited dated 28-05-2008, LAPL letter dated 5-
12-2008 , Copy of case no. HERC/PRO-12 dated
13.05.2010 filled by PTC, HERC Order dated 02-02-2011,
CERC Order for majority judgment dated 09.02.2012
55 | P a g e
were also provided.
E. It was submitted that bonafide efforts to secure
coal linkage from SECL as envisaged right from the project
planning stage was made by LAPL which is evident from
the various correspondences exchanged with South
Eastern Coal Limited/Ministry of Power/Central Electricity
Authority &Ministry of Coal which are annexed herewith
for your perusal and marked as Annexure – D. A
continuous effort is being made on regular basis for
getting the linkage coal supply from SECL. The
correspondence clearly shows that, LAPL had made
utmost efforts on their part to secure linkage coal for
operating the plant as was initially planned. However, on
account of circumstances beyond control and owing to
nationwide coal shortage being faced, LAPL had to
procure coal from sources other than linkage coal.
F. Details with respect of Cost of Coal, Secondary Fuel
Oil and Chemist certificates of “as fired GCV” of coal for
determining of variable charges were provided.
G. Auditor’s Certificate for Actual O&M Cost incurred
was enclosed.
H. Details and documents with respect to additional
inputs including documents in support of procurement of
Secondary fuel oil, Primary fuel was provided.
56 | P a g e
5. REPLY FILED BY HPPC:-
HPPC vide their memo no.Ch-10/HPPC/SEC&R-I/LTP-
II/LAK/Loose dated 18.02.2014. The same is as follows:
5.1 “At the outset, the Respondent No. 2 wish to
submit that the Respondent No. 2 (HPPC) intend to file
second appeal from the judgment and Order dated
3.1.2014 passed by the Hon’ble Appellate Tribunal in
Appeal No. 65 of 2013 under section 125 of the Electricity
Act, 2003 to the Hon’ble Supreme Court.
5.2 The present submissions made by the Respondent
No. 2 in response to the petition filed by Lanco are
without prejudice to the claims, rights and contentions of
the Respondent No. 2 in the second appeal against the
Order dated 3.1.2014 as well as in Appeal No. 15 of 2011
filed by Lanco and pending before the Hon’ble Supreme
Court.
5.3 In the Order dated 3.1.2014, the Hon’ble Appellate
Tribunal has held as under in regard to the capital cost
and other elements of tariff of the power generating unit
to be considered for the purpose of determination of
tariff and other tariff elements in Paras 58 to 64:-
57 | P a g e
“58. The Tariff Regulations, 2008 of the State
Commission specify the following norms:-
i) Capital Cost: Regulation 12 specifies
that the actual expenditure incurred on
the date of completion of the Project
shall form the basis for fixation of final
tariff.
ii) Target Availability/Plant Load Factor:
Target Availability/PLF shall be as per
Regulations 11(2).
iii) Sale of inform power. Any revenue
earned by the generating company from
sale of infirm power, shall be taken as
reduction in capital cost and shall not
be treated as revenue.
iv) Debt equity ratio: As per Regulations
15, in case of generating stations where
investment approval was accorded prior
to 1.4.2008 and which are to be
declared under Commercial Operation
during the period from 01.4.2008 to
31.3.2011 or the projects where the
investment approval is accorded on or
after 01.4.2008, debt equity ratio of
70:30 shall be considered. However, if
the deployment of equity is less than
30%, the actual debt and equity shall be
considered for determination of tariff.
v) Interest on loan: As per Regulation
16(i), the interest on loan capital shall
58 | P a g e
be computed loan wise on the loans
arrived at in the manner indicated in
Regulation 15.
vi) Depreciation: As per Regulation 16(ii),
the depreciation shall be calculated
annually, based on straight line method
over the useful life of the asset and the
rates prescribed in Appendix-II to the
Regulations. The residual life of the
asset shall be considered as 10% and
depreciation shall be allowed up to 90%
of the historical cost of the asset.
vii) Return on equity: Return on equity
shall be computed on the equity base
determined in accordance with
regulation 15 @ 14% per annum.
viii) Operation and maintenance expenses:
In case of generating station which has
not been in existence for three years,
or has been commenced after the
commencement of the Regulations of
2008, the O&M expenses shall be
considered at 1% of the capital cost as
admitted by the State Commission with
escalation factor of 4% per annum to
arrive at the allowable O&M expenses
for the relevant year.
ix) Interest on Working Capital: The norms
for working capital and interest thereon
shall be as per Regulation 16(vi).
x) Income Tax: The tax on income streams
of the generating Company from its
59 | P a g e
core business, shall be computed as
expense at rates applicable from time
to time and shall be recovered from the
beneficiaries as per Regulation 16(vii).
xi) Energy charges: Regulation 17 specifies
the method for calculation of energy
charges based on actual price and heat
value of fuel.
59. Let us now examine the findings of the State
Commission regarding various parameters of
tariff.
60. The Appellant had claimed capital cost of
Rs.1356.77 crores i.e. Rs.1668.37 crores
netted off for revenue earned on account of
UI as actually incurred and verified by the
auditors. The State Commission, however,
allowed net capital cost of Rs.1007.731 crores
i.e. capital cost of Rs.1340.041 crores as pear
the Detailed Project Report less Rs.332.31
crores earned on account of UI. The State
Commission has made the following
observation in this regard.
“The Commission observes that the levellised
tariff approved by this Commission was based
on an aggregate project cost as per the
Detailed Project Report finalized in
accordance with CERC norms which was
Rs.1340.041 Crore as against Rs.1356.77
Crore now claimed by the Petitioner.
Further, there is no audited account
specifically available for Unit-2 of LAPL from
where 300 MW power was contracted to
60 | P a g e
Haryana. Additionally, there is nothing on
record available to the Commission to
establish the fact that the project developer
exercised sufficient prudence to efficiently
execute the project within the cost and
timeline as originally envisaged. On the
contrary the Commissioning of the project
was unnecessarily lingered on which also
invited adverse comments from the CERC.”
61. The State Commission has deviated from its
own Regulations for determination of the
capital cost based on the actual expenditure
as no audited account was made available for
Unit-2 from which power was contracted to
Haryana. Further, there was nothing on
record to establish that the Appellant
exercised sufficient prudence to efficiently
execute the Project within the cost and time
line as originally envisaged.
62. Of course, we agree with the Haryana Power
(R2) that the State Commission has to apply
prudence check in determining the capital
cost based on the audited accounts. We find
from the impugned Order that adequate
materials were not available before the State
Commission to verify the capital cost
incurred on Unit No.2 of the Appellant and to
examine that the time and cost overrun was
not due to reasons attributable to the
Appellant and in the absence of the requisite
materials the State Commission approved the
capital cost as per the Detailed Project
Report.
61 | P a g e
63. Therefore, we direct the Appellant to submit
the necessary details of capital cost for unit
No.2 including apportionment of cost of
common facilities and detailed reasons for
time and cost overrun of the Project before
the State Commission to enable the State
Commission to apply prudence check and
determine the capital cost according to its
own Tariff Regulations. The State
Commission in turn shall determine the
capital cost as per its Regulations after the
requisite details are furnished by the
Appellant.
64. The State Commission has allowed debt
equity ratio of 80:20 as envisaged in the
original scheme. Further, the debt as claimed
by the Appellant was 1025.18 cores as against
the project cost of Rs.1007.737 crores as
approved by the State Commission. Thus, the
debt was in excess of the capital cost. As
held above, the State Commission has to
re-determine the capital cost based on the
details to be furnished by the Appellant.
Accordingly, the debt equity ratio is also
required to be re-fixed according to the
Tariff Regulations of 2008.”
The Respondent (HPPC) submitted that In terms of
the above Order, in the previous proceedings, Lanco
admittedly had defaulted in not placing adequate
material before the Commission to verify the capital cost
related to Unit No. 2 of the generating station at
62 | P a g e
Amarkantak. The Hon’ble Appellate Tribunal has directed
the Petitioner to submit necessary details of the capital
cost for Unit No. 2 including the apportionment of the
cost of common facilities as well as detailed reasons for
time and cost overrun of the project to enable the
Hon’ble Commission to apply prudent check as per the
applicable Regulations.
The Respondent further submitted that despite specific
directions of the Hon’ble Tribunal, the Petitioner has not
furnished the requisite details relating to the capital cost
of Generating Unit No. 2 along with the Auditor’s
Certificate as well as the basis of apportionment of the
common assets and facilities. In the absence of the
above details, it is respectfully submitted that the
capital cost and other related tariff elements cannot be
effectively determined by the Commission as per
directions of the Hon’ble Appellate Tribunal due to
deliberate failure on the part of the Petitioner to give
the requisite details with supporting Auditor’s
Certificate.
In the written submissions filed by the Respondent
No.2 in Case No. 1 of 2012 on 24.7.2012, the answering
Respondent had clearly raised various defects in the
Tariff Petition then filed by the Petitioner. At Para 11 of
63 | P a g e
the written submissions, it was stated by Respondent
No.2 as under:
1. At the hearing it was specifically pointed out that there are defects in the tariff petition filed. The Hon’ble Commission had also specifically observed the absence of particulars in regard to common facilities. Even after the above, the reply filed by Lanco on the last date of the hearing i.e. on 19.7.2012 does not give all the requisite formats. In the circumstances Lanco is in serious default in filing the tariff petition and could be called upon to file all the requisite formats. It is not open to Lanco to selectively choose some format and that too in such modified form as it considers and require the Hon’ble Commission to determine the tariff based thereon.
The Respondent No.2 submitted that even in the
present petition filed by Lanco in pursuance to the Order
passed by the Hon’ble Appellate Tribunal on 3.1.2014,
Lanco has not furnished the requisite details to enable
the Hon’ble Commission to properly apply prudence
check and decide on the appropriate capital cost.
The Respondent No.2 submitted that the generating
station of Lanco planned to be established at Amarkantak
consist of two units of 300 MW each and two Units of 660
MW each aggregating to 1920 MW. The answering
Respondents have to get power from only the Generating
64 | P a g e
Unit No-2 of 300 MW. The Generating Unit No-2
constitutes only 15.62% of the total capacity of the
generating station. There are number of common
facilities including the Land, Service Buildings, MGR
Workshop Buildings, Off Site buildings, Administrative
buildings, Field Hostel, Residential and Service Buildings,
Township, Boundary Wall, Sewerage and Efficient
Treatment Plants, Power Station Switchyard, Air-
conditioning System, Coal Handling System, Permanent
Roads, Drains, Rain Water Harvesting, Fire Station and
related expenditure, Fuel Oil and Ash Handling System
and various other assets which are related to all the
generating units and is not restricted to Unit No. 2 or for
that matter Units 1 and 2 alone. Since these and other
common facilities relate to the entire project of 1920
MW, the cost of which common facilities to the extent of
15.62% alone can be apportioned to Unit No. 2 as per the
practice prevalent including the terms of the Tariff
Regulations notified by the Central Commission.
In the petition filed, Lanco has not furnished the
requisite details in regard to the common facilities.
Lanco has only apportioned the common facilities
amongst Units 1 and 2 without considering the impact of
such common facilities qua Units 3 and 4 of 660 MW
each. The apportionment between Units 1 and 2 is also
65 | P a g e
in an arbitrary manner undertaken at the whims of
Lanco. There is no Auditor’s Certificate verifying the
apportionment or the basis of apportionment.
The Auditor’s Certificate dated 12.1.2014 attached to
the petition, in fact, is not a Certificate approving the
apportionment of capital cost but a disclaimer by the
auditor who is suppose consider to the capital cost. The
Letter stipulated stipulating clearly the following:
“............the Capital Cost given in the
‘Annexure I”, which is prepared by the
management of the company..........”
“e) We have checked the underlying arithmetical
computation of the amounts included in the
‘Annexure I”, as prepared by the management of
the Company.”
“f) In view of the procedures do not constitute
either an audit or a review made in accordance
with generally accepted auditing standards in
India, we do not express any assurance on the
information.”
“g) Had we performed additional procedures or
had we performed an audit or review of the
financial statements in accordance with generally
accepted auditing standards in India, other matters
might have come to our attention that would have
been reported.”
“h) We have no responsibility to update this report
for events and circumstances occurring after the
date of this report.”
66 | P a g e
“i) Our report is solely for the purpose as set forth
in the paragraph 2(a) of this report and for your
information and is not to be used for any other
purpose or to be distributed to any other parties.”
In view of the above specific stipulation in the
Auditor’s Certificate which are in the nature of
disclaimer and not authenticated verification, the
apportionment of capital cost etc cannot be considered
as certified by the authority. The authenticity of the
apportionment or even the methodology of the
apportionment has not been certified by the Auditor.
The answering Respondents submits that there are no
details of the total capital expenditure incurred on
common facilities/shared facilities duly supported by
Auditor’s Certificate confirming such capital expenditure
and there are no details as to why the common facilities
cannot be related to the entire 1920 MW capacity of the
generating station. All the four units are being
established at the same place and as per the Project
Report developed by Lanco. The expenditures are
incurred for common facilities in respect of the entire
generating station.
In terms of Regulation 4 of the Tariff Regulations,
2009, the Commission has to determine the tariff in
respect of Unit No. 2 and for the above purpose the
capital cost of the project need to be broken into
67 | P a g e
distinctive units and to the extent on common facilities.
There has to be an appropriate apportionment on the
basis of the installed capacity of the four generating
units. The petition filed by Lanco is not in accordance
with the above Regulation. The answering Respondents
further submit that in terms of Regulation 7 the capital
cost need to be determined after the Hon’ble
Commission has applied the prudent check. This is
specifically provided for in Regulation 7 (1) of the Tariff
Regulations, 2009. It is, therefore, not correct on the
part of Lanco to seek that whatever capital cost has been
disclosed by Lanco need to be accepted based on the
auditors’ certificate. There is need to go into the
details.
The Commission is fully empowered to and has the
statutory function to undertake the prudence check.
Such exercise of powers by the Hon’ble Commission
notwithstanding any approval of the capital cost by the
Central Electricity Authority or by the Auditors etc have
been now well settled. In the case of West Bengal
Electricity Regulatory Commission v CESC (2002) 81 SCC
715 the Hon’ble Supreme Court held as under:-
“96.The High Court further came to the conclusion that in view of the fact that there is no challenge to the accounts of the Company by the consumers, the said accounts of the Company should be
68 | P a g e
accepted by the Commission. Here again we are not in complete agreement with the High Court. There may be any number of instances where an account may be genuine and may not be questioned, yet the same may not reflect good performance of the Company or may not be in the interest of the consumers. Therefore, there is an obligation on the Commission to examine the accounts of the Company, which may be genuine and unchallenged on that count still in the light of the above requirement of Section 29(2)(g) to (h). In the said view of the matter admitting that there is no challenge to the genuineness of the accounts, we think on this score also the accounts of the Company are not ipso facto binding on the Commission. However, we hasten to add that the Commission is bound to give due weightage to such accounts and should not differ from the same unless for good reasons permissible in the 1998 Act.”
Similarly, in the case of Kerala State Electricity
Board v Kerala State Electricity Regulatory Commission,
Appeal No. 177 of 2009 dated 13.1.2011the Hon’ble
Appellate Tribunal for Electricity has held as under:-
“20. At the outset, it shall be stated that the State Commission while examining the accounts is not bound by the audited accounts. The accounts may be genuine as per the Auditor’s Report. But, it is the State Commission which has to examine the accounts to ascertain the performance of the licensee in relation to the desirability of the expenditure in the interest of the consumers. This point has already decided by the Judgment of this Tribunal in Appeal No. 94 of 2008 as well as the decision of Hon’ble Supreme Court in West Bengal
69 | P a g e
Electricity Regulatory Commission vs. CESC Ltd. (2002) (8)SCC 715.
21. Let us refer to the relevant observations made
by this Tribunal in Appeal No. 94 of 2008:
“In the truing up process the actual expenditures are examined and the expenditure with various heads are trued up. So far as the effect of audit is concerned, it establishes the genuineness of accounts and expenditure incurred. The Commission has to allow only as much expenditure as pass through as meets the targets set by it or is found to be prudent and necessary”
22. This decision was given by this Tribunal on the strength of the ratio decided by Hon’ble Supreme Court. We will now refer to the relevant observations made by the Hon’ble Supreme Court in the decision referred in (2002) (8) SCC 715.
“In this process, the Commission, in our opinion, is not bound by the Auditors’ Report….. There may be any number of instances where an amount may be genuine and may not be questioned, yet the same not reflect good performance of the company or may not be in interest of the consumers. Therefore, there is an obligation on the Commission to examine the accounts of the company which may be genuine and unchallenged on that count still in the light of the above requirements of Section 29(2) (g) to (h). In the said view of the matter admitting that there is no challenge to the genuineness of the accounts, we think on this score also the accounts of the company are not ipso facto binding on the Commission.”
70 | P a g e
23. The above observations would reflect the ratio
decided by Hon’ble Supreme Court. What is to be
seen in this Appeal where each item of expenses
allowed or disallowed by the State Commission is
correct or not in the facts of the case and the
materials placed before of the Commission.”
Accordingly, the mere fact that the auditor has
given a letter as per the books of account or even when
the Auditor duly certifies the account does not mean that
the Commission will not exercise prudence check. The
prudence check need to be applied by the Commission is
to be in detail as higher capital cost would increase the
tariff for the consumers at large. The Commission
exercises the prudence check in all cases in Order to
ascertain not only the veracity of the claim of the
Petitioner/Generating Company but also to seek whether
all such capital expenditure have been incurred
reasonably or prudently. If the Commission comes to the
conclusion after applying the prudence check that any
such capital expenditure, though actually incurred was
not prudent or expedient, such part of the capital
expenditure will have to be rejected. The scrutiny of the
capital expenditure by the Commission is, therefore, an
absolute necessity which cannot be avoided by Lanco by
not giving the requisite particulars and satisfying the
claim. The Commission as well as the other Regulatory
71 | P a g e
Commissions has been exercising such prudence checks
including by appointment of consultants and through
verification by the staff of the Commission. It is,
therefore, not correct on the part of Lanco to seek
admission of the capital expenditure incurred only on the
basis of the auditor’s certificate.
The prudence check is also required to be
undertaken by the Commission in Order to determine
whether any part of the capital expenditure involve
minor assets or assets not relevant for the generation of
electricity. Accordingly, the expenditure being
supported by accounting vouchers for the purpose of the
Companies Act is not sufficient. The Generating
Company is required to establish to the satisfaction of
the Commission the need for capital expenditure,
incurring of such capital expenditure in a structured
manner and the total expenditure being reasonable and
just.
After the Commission undertakes complete scrutiny
of the capital expenditure, the Commission could come
to the decision as to what part of the capital expenditure
should be admitted as capital cost of Unit 2 including by
appropriate apportionment of the common/shared
facility in the proportion of MW capacity of Unit 2
72 | P a g e
vis-a-vis the total capacity of the power station. The
above is also a direction of the Hon’ble Tribunal in the
judgment dated 3.1.2014 passed in Appeal No. 65 of
2013.
While deciding the capital cost, the entire infirm
power including the power sold under Unscheduled
Interchange prior to the Commercial Operation Date i.e.
the date from which the Petitioner is supplying power,
the answering Respondents in pursuance to the earlier
Order dated 02.02.2011 passed by this Commission need
to be deducted. As per the financial statements of Lanco
filed for the year ended 31.03.2009, for the period 2009-
10 and for the period 2010-11, the sale of power from
Units 1 and 2 before the declaration of the date of
commercial operation aggregate to Rs. 1889.10 crores. In
addition, there has been sale of infirm power during the
period 01.04.2011 to 06.05.2011 the details of the same
have not been disclosed by Lanco. In the Financial
Statements providing for the income from sale of
electrical energy. Lanco has not given the details of the
breakup of the above, namely, what part of the sales
pertain to Unit -1 and what part pertains to Unit - 2.
It is, therefore, incumbent for Lanco to provide
details of the sale of infirm power and sale of power
under unscheduled interchange changes, namely, the
73 | P a g e
aggregate quantum of such sale both from Units 1 and 2
and out of the above, the amount realized from the sale
of infirm power and unscheduled interchange Charges
considered for reduction of the capital cost of Unit No. 1.
The balance after adjustment for Unit 1 held to be
accounted as pertaining to Unit No. 2. This revenue need
to be adjusted for reduction in the capital cost for the
purpose of determining the cost to be considered for
tariff. The deduction of revenues from infirm power/UI
Charges from the capital cost is a significant aspect of
capital cost determination and the benefit of the same
should go to the consumers in the State of Haryana. The
Commission may, therefore, direct a detailed
investigation into the quantum of infirm power sold by
Lanco from Amarkantak Project, verification of the above
quantum vis-a-vis Unit 2 and then determine the
reduction in the capital cost pertaining to Unit 2. In the
facts and circumstances of the case the submissions of
Lanco on the quantum of sale of infirm power at Rs.
311.60 crores is erroneous.
The approved financial package of the project
admittedly, is 80% debt and 20% equity. Accordingly, the
capital cost duly scrutinized subject to prudence check
and approved, will have to be apportioned in the form of
debt to the extent of 80% and equity to the extent of
74 | P a g e
20%. It is not open to Lanco to claim equity to be at
24.52% when the approved financial plan for equity is
only 20%. The excess of equity above 20% should be
treated as notional loan and not as equity. Accordingly,
the tariff filing made by Lanco on the basis of
apportionment the debt and equity in the ratio of 75% -
25% is wrong. The entire tariff calculation based on the
above wrong differentiation and equity ratio assumed by
Lanco is defective and need to be rejected. Once the
capital cost determined as per prudence check and
infirm power and UI revenues are deducted, the cost is
apportioned in the debt equity ratio of 80% - 20%, the
return of equity is to be restricted to 20% of the capital
cost. The balance 80% will have to be serviced as
borrowings/loan.
In terms of the Tariff Regulations, 2009 of the
Central Commission the servicing of the loan is equated
with the depreciation amount and on a normative basis.
The actual repayment of loan or the terms and conditions
entered into by Lanco with its Lenders on repayment of
loan are not relevant. What is, however, relevant is the
interest to be calculated on the normative repayment
i.e. on reducing balance as per the normative repayment
at the weighted average of the actual interest paid to
the Lenders. Accordingly, Lanco is required to give the
75 | P a g e
details of the depreciation claimed by Lanco, its
apportionment to the capital cost of Unit 2 from the
beginning. Any depreciation taken by Lanco on or after
1.4.2009 will be treated as normative repayment to the
banks. The interest for the subsequent period will have
to be determined after adjusting the normative
repayment. Lanco has not given such particulars in Order
to determine the normative loan, depreciation adjusted
and the balance to be serviced from time to time.
In the Order dated 2.2.2011 this Commission while
dealing with the Force Majeure pleaded by the Petitioner
specifically rejected the claim for compensation in terms
of tariff hike i.e. IDC and IEDC specifically holding as
under:-
“A perusal of the above provision makes it clear
that in an event of Force Majeure the parties are
entitled for some relief in terms of extension in
time for carrying out their respective contractual
obligations. As far as the issue of compensating (in
terms of tariff hike) for any consequential
appreciation in Capital Cost is concerned, the
Commission could not find any enabling provision
in the PSA/ PPA. Hence the second issue of
whether any relief other than extension in time
due to any Force Majeure event is admissible is
answered in negative i.e. no relief other than
extension in time as explicitly provided in the
PSA/PPA is admissible”.
76 | P a g e
The above decision of this Commission was not
interfered with by the Hon’ble Appellate Tribunal for
Electricity in the judgment dated 3.1.2014. In view of
the above, the Petitioner cannot claim either IDC or IEDC
or any other compensatory payment by way of cost
overrun or time overrun on account of the delay resulting
from the alleged Force Majeure Event of earthquake in
China or the Visa Policy of the Government of India. This
issue stands settled and cannot be re-opened at this
stage. It is, however, submitted that the alleged
reasons, namely, earthquake in China and Visa Policy of
the Government of India are not Force Majeure making it
impossible for Lanco to complete the construction of Unit
No. 2. In particular, the Visa Policy of the Government
of India cannot be construed as Force Majeure as
sufficient manpower has been available in India for
commissioning Unit No. 2. The claim for IDC and IEDC
i.e. time overrun and cost overrun can be considered
only in regard to the matters other than those resulting
from the alleged Force Majeure Event. The allegations
to the contrary are wrong and are denied.
A perusal of the documents on record, as filed by
the Petitioner, clearly shows that the claim of the
Petitioner for the delay in the commissioning is only on
77 | P a g e
account of Force Majeure Event of earthquake in China in
May 2008. The other reason given for the delay in the
Lenders Engineers Report is that the commissioning was
delayed due to the usage of rotor of Unit No. 2 in Unit
No. 1 allegedly to optimize the commissioning time of
the unit. This cannot be a ground for claiming the cost
overrun in respect of Unit No. 2. Any claim on account of
excess expenditure should be entirely to the account of
Unit No. 1 and no part of such expenditure should be
added on to Unit no. 2. Furthermore, the allegations of
Force Majeure of Visa Policy of the Government of India
not permitting the Chinese workforce have been raised as
an afterthought.
The Fixed Charges as per the Tariff Regulations,
2009 determined based on the capital cost will be on an
annual basis and thereafter apportioned 1/12th for each
month. The fixed charges claimed by Lanco in the
petition are varying from month to month and that also
significantly. This is not in accordance with the Tariff
Regulations, 2009. The annualized fixed charges need to
be determined and then divided into monthly fixed
charges on mathematical basis for recovery purposes.
The scheme adopted by Lanco in determining the fixed
charges on month-wise basis is completely contrary to
the Tariff Regulations, 2009.
78 | P a g e
The interest on working capital to be determined is
on normative basis. The reference to the period to be
taken for the purpose of actual consumption, coal price
etc is January 2009 to March 2009. Once the interest on
working capital is determined on a normative basis, the
actual amount of capital employed by the generating
company from time to time in regard to the coal
consumption etc is totally irrelevant. The interest on
working capital is not dependent on the actual working
capital incurred by the generating company irrespective
of whether the generating company incurs the working
capital or not, the normative working capital as
determined under the Regulations is alone admissible. In
the present case, the claim of Lanco of different working
capital every month or on the basis of coal value being
more in certain months are contrary to the Tariff
Regulations, 2009.
In addition, Lanco has not given details as to why
the coal consumption in a particular month is of higher
value. In any event, the Tariff Regulations, 2009 having
provided for the interest on working capital to be
determined on a normative basis, it is not open to Lanco
to claim interest on working capital allegedly on the
actual working capital incurred by it and that too on
79 | P a g e
month to month basis. The interest on working capital
need to be uniform throughout the tariff period of 2009-
14.
The Operating and Maintenance Expenses need to
be ascertained in terms of Tariff Regulations, 2004 based
on the capital cost finally determined by the
Commission. Under the Tariff Regulations, 2009, the O &
M Expenses are on normative basis and need to be
allowed. Any claim on the part of Lanco contrary to the
above is wrong.
As regards the coal, the Respondent had agreed to
purchase power from the second unit of Lanco Project
based on the coal linkage which Lanco had from Coal
India and/or its subsidiary. It is the obligation of Lanco
to arrange for the above coal. Lanco cannot demand
energy charges based on any coal used by it other than
through procurement of coal under a regular Fuel Supply
Agreement with Coal India and/or its subsidiary.
The Respondent craves leave to refer to make
further submissions on the documents on record at the
time of the hearing. The Respondent also submits that
this Hon’ble Commission should direct the Petitioner to
80 | P a g e
furnish all the requisite details before dealing with
various aspects.
6. REJOINDER FILED BY LAPL:
In response to the above reply filed by HPPC, LAPL filed a
rejoinder, the same are as under:-
The contents of para no.1 of the reply need no response being
matters of record. 2. The contents of para no.2 of the reply merit no response by the Petitioner. 3. The contents of para no. 3 of the reply need no reply being reproduction of certain paras of the judgment dated 03.01.2014 of the Hon’ble Appellate Tribunal for Electricity (‘Hon’ble APTEL’) passed in the Appeal no. 65 of 2013. 4. The contents of para no. 4 of the reply are denied as wrong, incorrect, baseless and misleading. It is denied that the Petitioner defaulted in placing on record the adequate material before this Hon’ble Commission to verify the capital cost related to the Unit-II. In this regard, the Petitioner craves leave to refer to the judgment of Hon’ble APTEL at the time of hearing of the matter. It is submitted that the Petitioner had placed adequate materials before this Hon’ble Commission to verify the capital cost relating to Unit-II. There was no Order/direction of this Hon’ble Commission directing the Petitioner to file any other document in support of cost overrun and time overrun during the hearing of the tariff petition CASE NO: HERC/PRO – 1 OF 2012 apart from the materials already placed by the Petitioner. Therefore, there was no occasion for the Petitioner to provide any additional documents to verify the capital cost related to Unit-II of the Petitioner. In any event, the allegation of the Respondent No. 2 is
81 | P a g e
irrelevant in view of the judgment dated 03.01.2014 of the Hon’ble APTEL. The Petitioner has complied with the said directions of the Hon’ble APTEL and has submitted the necessary details of the capital cost and is willing to provide any other necessary document/information which this Hon’ble Commission may deem fit and necessary for determining the tariff. 5. The contents of para no. 5 of the reply are denied as incorrect, false and misleading. It is denied that the Petitioner has not furnished the requisite details relating to the capital cost of the generating Unit-II along with the Auditor’s certificate. It is denied that the Hon’ble APTEL has directed the Petitioner to submit details of basis of apportionment of the common assets and facilities and what has been directed by the Hon’ble APTEL is necessary details of capital cost for Unit-II including apportionment of cost of common facilities only. In this regard, it is submitted that the Petitioner along with its letter dated 13.01.2014 has already filed:- (a). The filled up tariff filing formats containing detailed breakup of capital cost incurred upto the date of COD of Unit-II supported by the Auditor’s certificate in accordance with Haryana Electricity Regulatory Commission (Terms and Conditions for Determination of Generation Tariff) Regulations, 2008 (‘HERC Tariff Regulations, 2008’) along with other documents; [page no. 254 to 284 of Vol.-I along with letter dated 13.01.2014] (b). Statement showing lender wise loans drawn and their outstanding loans as on COD certified by the Auditor; and [page no. 74 to 75 of Vol.-I along with letter dated 13.01.2014]. (c). Note giving details of the cost incurred on common facilities of Unit-I & Unit-II of the Petitioner [page no. 76 of Vol.-I along with letter dated 13.01.2014]. It is submitted that the cost incurred on Unit-II on common facilities is for the augmentation/ modification/addition to the existing facilities of Unit-I. The cost incurred on the common facilities of Unit-II has been included in the total capital cost which is duly certified by the Auditor of the Petitioner [page no. 71 to 73 of Vol.-I along with letter dated 13.01.2014]. However, to avoid any
82 | P a g e
unnecessary objections from the Respondent No.2 a duly certified cost incurred on common facilities of the Unit-I & Unit-II of the Petitioner by its Auditor is being filed with this Rejoinder. It is denied that there is any failure on part of the Petitioner to provide any document and/or requisite details as alleged. It is wrong and denied that the capital cost and other related tariff elements cannot be effectively determined by this Hon’ble Commission as alleged. The Auditor certificate dated 18.02.2014 certifying the costs incurred on the common facilities of Unit-I and Unit-II of the Petitioner is annexed hereto and collectively marked as Annexure-P-1. 6. The contents of para no. 6 of the reply are denied being wrong, incorrect, false and misleading, save and except being matters of record. It is submitted that alleged defects raised by the Respondent No.2 has no relevance in the present proceedings more specifically after passing of the judgement dated 03.01.2014 of the Hon’ble APTEL which sets aside the Order dated 17.10.2012 of this Hon’ble Commission passed in CASE NO: HERC/PRO – 1 OF 2012. 7. The contents of para no. 7 of the reply are denied being wrong, incorrect, false and misleading. It is wrong and denied that the Petitioner has not furnished the requisite details to enable this Hon’ble Commission to properly apply prudence check and decide on the appropriate capital cost. It is submitted that the application has been filed duly adopting the Tariff formats in accordance with HERC Tariff Regulations, 2008. All the relevant information has been furnished in the applicable filled up tariff formats supported by Auditor’s certificates. Thus, the Petitioner submits that it has furnished all the details to the Hon’ble Commission for the purpose of re-determination of tariff as per the directions of the Hon’ble APTEL in Appeal no. 65 of 2013 and the Petitioner is ready to furnish any further information/document as per the direction of this Hon’ble Commission. 8. The contents of para no. 8 of the reply are denied being wrong, incorrect, false, baseless and misleading. It is incorrect and denied that the common facilities/common assets are for the entire project
83 | P a g e
of the 1920 MW of the Petitioner. It is submitted that the present tariff re-determination to be carried out by the Hon’ble Commission is for a generating station consisting of a single unit (1x300 MW) i.e. Unit-II. It is denied that there are any common facilities (including the ones alleged to be common para-8 of the reply) between Unit-I and Unit-II on the one hand and Unit-III & Unit-IV on the other hand. It is submitted that Unit III & IV (2X660MW) are being set up separately from Unit-I & Unit-II and the said Units are in construction phase and are expected to be commissioned in FY 2014-15 whereas Unit-I & Unit-II are already operational In relation to Unit-I and Unit-II, it is stated that Unit-I was conceptualised, planned and achieved financial closure on 20.09.2005 much prior to financial closure of Unit-II. Further, Unit-II has been appraised separately by the lenders and its financial closure happened on 15.09.2006 i.e. about one year after the financial closure of Unit I. It is noteworthy that the two Units i.e. Unit-I & Unit-II were separately conceptualized, appraised and executed by augmentation/ modification/ addition to the existing facilities of Unit-I. The details of the common facilities of Unit-I and Unit-II and their respective cost incurred along with a brief explanation note has already been filed vide its letter dated 13.01.2014. It is denied that any common facility relate to all the units adding upto 1920 MW. It is denied that the proportion of Unit-II works out to 15.62%. It is denied that the tariff regulations notified by the Central Commission are applicable to the present proceedings. The Petitioner craves the leave to refer to and rely upon the judgment dated 03.01.2014 passed by the Hon’ble APTEL as well as the CERC Tariff Regulations, 2009 at the time of hearing of the present matter. The Petitioner submits that the capital cost incurred on Unit-II which was conceptualized, appraised and executed independently is available and the details of the same have already been provided by the Petitioner. Without prejudice to any of the contentions of the Petitioner if CERC Tariff Regulations, 2009 are to be applied then the apportionment of capital cost towards common facilities of Unit-II would be higher than what is claimed by the Petitioner, which according to the Respondent No.2 is acceptable to it.
84 | P a g e
9. The contents of para no. 9 of the reply are denied being wrong, incorrect, false, baseless and misleading. It is denied that the Petitioner has not furnished the requisite details in regard to the common facilities as alleged. It is denied that there are any common facilities between the Unit-I & Unit-II on one hand and the Unit-III & Unit-IV on the other hand. It is submitted that Unit-III & Unit-IV (2x660MW) of the Petitioner Company are under construction phase and are yet to be commissioned. It is wholly misleading and mischievous on the part of the Respondent No.2 to state that the common facilities are related to the entire 1920 MW. It is denied that the apportionment between the Unit-I & Unit-II is undertaken in arbitrary manner at the whims of the Petitioner as alleged or otherwise. In this regard, it is submitted that the cost incurred on common facilities is true and correct and as per the books and records of Petitioner Company. In so far as the objection of the Respondent No.2 as regards auditor’s certificate verifying the apportionment is concerned, as stated above the Petitioner is filing the certificate along with the rejoinder which is already marked as Annexure-P-1. It is incorrect on the part of the Respondent No.2 to state that the auditor’s certificate will verify the basis of apportionment. The Petitioner has given requisite details of the apportionment in accordance with the judgment dated 03.01.2014 passed by the Hon’ble APTEL. 10. The contents of para no. 10 of the reply are denied being wrong, incorrect, baseless and misleading, save and except being matters of record. It is submitted that the Auditor’s certificate dated 12.01.2014 is for certification of Capital Cost of Unit II and is not a Certificate for apportionment of Capital Cost as alleged. It is submitted that the Auditor’s Certificate dated 12.01.2014 issued by the Auditor contains, inter alia, the terms of reference and the work that had been carried out by them. The certificate is issued in accordance with the Regulations of Institute of Chartered Accountants of India (ICAI). Para 1 of the Auditor’s Certificate clearly states that Capital Cost given in the Annexure-I which is prepared by the management of the Petitioner Company as per the HERC Tariff Regulations, 2008 is in accordance with the books and records
85 | P a g e
maintained by the Petitioner Company. Further, it has been very clearly stated in Para 2(a), that the said Certificate has been issued at the request of the Petitioner for submission to Hon’ble Haryana Electricity Regulatory Commission (HERC) for re-determination of interim tariff for supply of power from Unit-II of the Petitioner. In Para 2(b), the Auditor has clearly stated that it has verified the books of accounts and other relevant records and documents of the Petitioner while certifying the Capital Cost in Annexure-I. It is submitted that the certificate issued by the Auditor certifying the capital cost, was an engagement performed in accordance with the Standard on Related Service (SRS) 4400 on “Engagements to Perform Agreed-upon Procedures regarding Financial Information” issued by the Institute of Chartered Accountants of India (ICAI). In terms of the engagement, the Auditor was required to certify the capital cost as given in the 'Annexure I' of the certificate dated 12.01.2014 in accordance with the books and records maintained by the Petitioner, verify the amounts pertaining to components of capital cost and to identify exceptions, if any and report in accordance with the SRS 4400 issued by the ICAI. Accordingly, the Auditor has issued the certificate dated 12.01.2014. As regards para (f) and para (g) of the certificate dated 12.01.2014, it is submitted that the said paragraphs are in accordance with Para 5 of SRS 4400 issued by the ICAI. The objective of the engagement is to report on factual findings of agreed upon procedures and therefore the Auditor has expressly stated this fact in Para (f). The reporting format has been adopted as per Para 18 of SRS 4400. Accordingly, the Auditor has mentioned para (f) of the certificate which is extracted from Para 18(i) of SRS 4400 and Para (g) of the certificate is extracted from Para 18(j) of SRS 4400. In this regard, it is submitted that the para (f) & para (g) of the Auditor’s Certificate dated 12.01.2014 has to be read as a whole and not in isolation. Similarly, with regard to para (i) of the certificate dated 12.01.2014, it is an extract from Para 6 of SRS 4400 which specifies that the certificate is also restricted to those parties that have agreed to the procedures to be performed since others, unaware of the reasons for the procedures may misinterpret the results which accordingly the Auditor has stated the fact in Para (i) of the Certificate. In sum and substance, the disclaimers as alleged by the
86 | P a g e
Respondent No.2 in the Auditor’s Certificate dated 12.01.2014 are strictly in accordance with the said ICAI Regulations. It is thus submitted that the said certificate is a certificate verifying and certifying the capital cost of the Unit-II and is not a disclaimer as alleged by the Respondent No.2. The alleged objection to the Auditor’s Certificate dated 12.01.2014 are misconceived as well as mischievous. The Standard on Related Service (SRS) 4400 on “Engagements to Perform Agreed-upon Procedures regarding Financial Information” issued by the Institute of Chartered Accountants of India (ICAI) is annexed herewith and marked as Annexure-P-2. 11. The contents of para no. 11 of the reply are denied being wrong, incorrect, false, baseless and misleading, save and except being matters of record. It is denied that the alleged stipulations in the auditor’s certificate are not authenticated verification as alleged by the Respondent No.2. The alleged objections raised by the Respondent No.2 are frivolous and mischievous in nature. In this regard the contents of para 10 above are reiterated and reaffirmed. In so far as the objection of the Respondent No.2 pertaining to the capital expenditure incurred on common facilities is concerned the Petitioner reiterates and reaffirms the contents of para 8 above. The Petitioner further reiterates that there are no common facilities between Unit-I& Unit-II on the one hand and Unit-III & Unit-IV on the other hand. The mere fact that all the four units are established/being established at the same place does not ipso facto mean than there would be common facilities amongst all the units. The contention of the Respondent No.2 that all the four units are established as per the Project Report developed by Lanco is vague and ambiguous and therefore denied. It is reiterated that Units-III & IV (2X660MW) of the Petitioner Company are being constructed and are yet to be commissioned and therefore it is misleading to state that the common facilities are related to the entire 1920 MW. It is denied that the expenditures are incurred for common facilities in respect of the entire generating station as alleged.
87 | P a g e
12. The contents of para no. 12 of the reply are denied being wrong, incorrect, false, baseless and misleading and irrelevant. It is submitted that as per the judgement dated 03.01.2014 of the Hon’ble APTEL, the Hon’ble Commission is required to apply HERC Tariff Regulations, 2008. Without prejudice to the fact that the CERC Tariff Regulations, 2009 is not applicable to the Petitioner in the present proceedings in so far as capital cost is concerned, it is submitted that the Regulation 4 of the CERC Tariff Regulations, 2009 is only applicable in case of an on-going project as well as in the event when the break-up of capital cost of a project being executed in different stages or units is not available. In the present case firstly Unit-II of the Petitioner is a completed project and not an on-going project. Secondly, it is submitted that the break-up of completed capital cost of Unit-II is available in present case. In this regard, it is reiterated that the Unit-II of the Petitioner was conceptualized, appraised and executed independently. Without prejudice to any of the contentions of the Petitioner if CERC Tariff Regulations, 2009 are to be applied then the apportionment of capital cost towards common facilities of Unit-II would be higher than what is claimed by the Petitioner, which according to the Respondent No.2 is acceptable to it. It is denied that the petition filed by the Petitioner is not as per the HERC Tariff Regulations, 2008. It is incorrect to state that the capital cost of the Unit-II of the Petitioner needs to be determined as per Regulation 7 of the Tariff Regulations, 2009. This contention of the Respondent No.2 is contrary to the judgement of the Hon’ble APTEL and therefore needs to be rejected.. 13-14 The contents of para no. 13-14 of the reply merits no response being extracts of judicial pronouncements. The Petitioner craves leave to refer to and rely upon the said judgments at the time of hearing for their true scope and effect. 15.The contents of para no. 15 of the reply are denied being wrong, baseless and misleading and irrelevant. It is submitted that undoubtedly the Hon’ble Commission is empowered to conduct prudence check in accordance with the applicable regulations. It is wrong on the part of the Respondent No.2 to state that the Petitioner
88 | P a g e
is avoiding any scrutiny or the Petitioner has not given any requisite particulars. Further the contentions raised in the para under reply are completely vague and ambiguous. The contention that the Petitioner is seeking admission of the capital expenditure incurred only on the basis of auditors’ certificates is incorrect and false. 16-17.The contents of para no. 16-17 of the reply are vague and ambiguous and therefore denied. It is correct that prudence check is to be conducted by the Hon’ble Commission in accordance with the regulations. However, the scope of the prudence check as projected by the Respondent No.2 is completely vague and absurd. The Petitioner has given all the requisite details in respect of all the capital expenditure. The Respondent No.2, apart from raising general objections, has failed to point any specific component of the capital cost in which, according to it, prudence check is required to be conducted. It is denied that the apportionment of common/shared facilities is to be in the proportion of MW capacity vis-a vis the total installed capacity. In this regard, the contents of para 8 above are reiterated. It is wholly misleading on the part of the Respondent No.2 to state that the above is a direction of Hon’ble APTEL. It is submitted that the completed capital cost of Unit-II computed in accordance with HERC Tariff Regulations, 2008 is Rs. 1356.11 crores as on 06.05.2011 (upto COD) which translates to Rs. 4.52 crore per MW which is fairly reasonable for a 300 MW coal based thermal power project. 18.The contents of para no. 18 of the reply are denied being wrong, incorrect, false, baseless and misleading. The averment of the Respondent No. 2 that as per financial statements of the Petitioner filed for the year ended 31.03.2009, for the period 2009-10 and for the period 2010-11, the sale of power from Unit I and Unit-II before the declaration of the date of commercial operation aggregate to Rs. 1889.10 crores is irrelevant for the computation of infirm power revenue generated from Unit II. The Petitioner submits this very objection was raised by the Respondent No.2 in the proceedings in CASE NO: HERC/PRO – 1 OF 2012 and was dealt it by the Petitioner. The said objection was rejected by the Hon’ble Commission in its
89 | P a g e
Order dated 17.10.2012. The Respondent No.2 admittedly has not challenged the same and therefore the Respondent No.2 is estopped from raising this objection. Without prejudice to the above, it is submitted that the Respondent No.2 is trying to mislead this Hon’ble Commission by quoting the consolidated financials of the Company, which includes gross revenue from sale of power from Unit-1 before and after COD of Unit I in addition to the sale of infirm power from Unit-2 before its COD 07.5.2011.It is submitted that Unit I was synchronized on 01.05.2009 and its COD was declared on 09.04.2010 whereas Unit II was synchronized on 22.02.2010 and its COD was declared on 07.05.2011. The net revenue generated from sale of infirm power after fuel expenses of Unit-II is (Rs. 311.28 Crores) from date of synchronization (22.02.2010) upto the declaration of COD (07.05.2011) which is reflected in the certificate issued by Auditor certifying the capital cost of Unit II. It is submitted that complete details in relation to Energy Export and Amount of infirm power solely pertaining to Unit 2 has been already submitted by the Petitioner before this Hon’ble Commission in CASE NO: HERC/PRO – 1 OF 2012 vide its tariff petition dated 12.01.2012 and the same are already on record as Annexure-4 of the tariff petition dated 12.01.2012. It is submitted that the benefit of reduced capital cost has been clearly passed on to the consumers of State of Haryana as the revenue generated from sale of infirm power from Unit-II has been deduced from the capital cost of Unit-II in accordance with HERC Tariff Regulations, 2008. Therefore, the submission of the Respondent No.2 that the sale of infirm power during the period from 01.04.2011 to 06.05.2011 has not been disclosed by the Petitioner is totally incorrect and baseless. It is submitted that on 25.03.2010 i.e. the day when the Unit-II touched full load the assets of Unit-II of the Petitioner were capitalized in the book of accounts. The financial statements-as at March 31, 2011 along with auditor’s report and financial statements-as at March 31, 2010 along with auditor’s report of the Petitioner have already been submitted by the Petitioner before this Hon’ble Commission vide its reply dated 19.07.2012 to the objections filed by the Respondent No.2 in CASE NO: HERC/PRO – 1 OF 2012 and the same are already on record as Annexure-B of the reply dated 19.07.2012. The financial statements as at
90 | P a g e
March 31, 2012 along with Auditor’s report is annexed herewith and marked as Annexure-P-3. The standalone financials of Unit II certified by the Auditor for the period as on 25.03.2010, as on 31.03.2010, as on 31.03.2011 and as on 07.05.2011 is annexed herewith and marked as Annexure-P-4 (Colly). 19.The contents of para no. 19 of the reply are denied being wrong, incorrect, false, baseless and misleading. It is reiterated that the Petitioner has given details of the revenue generated by the Petitioner from the sale of infirm power and sale of unscheduled interchange charges. It is denied that it is incumbent upon the Petitioner to give details of aggregate quantum of the sale of infirm power and sale of power under unscheduled interchange of Unit-I & Unit-II. It is wrong and denied that any revenue generated from sale of infirm power and unscheduled interchange charges under the Unit-I need to be adjusted for reduction in the capital cost for the purpose of determining the cost to be considered for the tariff. It is reiterated that the capital cost of the Unit-II as certified by the Auditor in the certificate along with the letter dated 13.01.2014 excludes the sale of infirm power and unscheduled interchange charges under the Unit-I. It is submitted that the contention of the Respondent No.2 regarding a detailed investigation into the quantum of infirm power sold by the Petitioner under the Unit-II is totally misconceived, mischievous and is a ploy to delay the present proceedings. It is denied that the quantum of sale of infirm power at Rs. 311.28 crores is erroneous as alleged or otherwise. 20. The contents of para no. 20 of the reply are denied being wrong, incorrect, false, baseless and misleading. The averment of the Respondent No.2 that debt-equity ratio should be as per the alleged approved financial package is incorrect and misconceived and is contrary to the judgment dated 03.01.2014 of the Hon’ble APTEL. As per which the debt-equity ratio has to be fixed according to the HERC Tariff Regulations, 2008. It is wrong and denied that the Petitioner cannot claim the actual debt and equity. In this regard, it is submitted that the HERC Tariff Regulations, 2008 clearly provides that where equity actually employed is less than 30%, the actual debt and equity
91 | P a g e
shall be considered for the determination of tariff. The actual debt outstanding in the books of accounts of the Petitioner as on COD is Rs. 968.402 crores duly certified by the Auditor vide its certificate dated 12.01.2014 and accordingly the Petitioner has considered the actual net outstanding loan as on COD as the debt for the project and the balance amount of the capital cost of the project is considered as equity. It is submitted that the Petitioner has commenced repayment of the term loan for the project before the COD and based on actual debt outstanding as on COD, the debt –equity ratio stands at 71.41%:28.59% which has been claimed by the Petitioner. It is denied that in the present case the capital cost will have to be apportioned in the form of debt to the extent of 80% and equity to the extent of 20%. It is denied that it is not open to the Petitioner to claim equity at more than 20%. It is submitted that the claim of the Petitioner is strictly as per the HERC Tariff Regulations, 2008. It is denied that the tariff petition made by the Petitioner on the basis of apportionment of the debt and equity in the ratio stated therein is wrong. It is denied that the tariff calculation is based on any wrong differentiation and equity ratio assumed by the Petitioner. It is denied that the tariff calculation based on above stated debt-equity ratio is defective and need to be rejected. It is submitted that the Regulation 15 (3) of the HERC Tariff Regulations 2008 clearly stipulates that the debt-equity ratio shall be based on actual deployment of funds subject to the condition that the equity deployed in excess of 30% of the capital cost shall be treated as normative loan. It is denied that the once the capital cost determined as per prudence check and infirm power and UI charges are deducted the cost is to be apportioned in the debt-equity ratio of 80%-20%. It is wrong and denied that the return of equity is to be restricted to 20% of the capital cost. It is wrong and denied that the balance 80% will have to be serviced as borrowing/loan. 21. The contents of para no. 21 of the reply are denied being wrong, incorrect, false, baseless, misconceived and misleading. It is submitted that as per the judgement dated 03.01.2014 of the Hon’ble APTEL the Tariff Regulations, 2009 of the Central Commission is of no relevance in the present proceedings in so far as interest on loan is concerned. It is submitted that the Respondent No.2 is trying to mislead the
92 | P a g e
Hon’ble Commission by referring to the Tariff Regulations, 2009 of the Central Commission for Interest on Loan component of the Tariff as against the applicable HERC Tariff Regulations, 2008. The Petitioner states that it has claimed interest on loan after COD on the actual loan outstanding as on COD after duly taking into account the normative repayment for the respective tariff periods. The objections raised by the Respondent No.2 are misconceived as the Petitioner has not claimed any depreciation before COD, which is in line with the HERC Tariff Regulations, 2008. It is denied that the Petitioner has not given any particulars in Order to determine the normative loan, depreciation adjusted and balance to be serviced from time to time. The Petitioner reiterates that it has already submitted all the necessary and relevant details in the applicable Formats required for determination of Interest on Loan, Depreciation and Advance against Depreciation in accordance with the applicable provisions of HERC Tariff Regulations, 2008. 22-23.The contents of para no. 22-23 of the reply are incorrect, false, misconceived, misleading and irrelevant. It is submitted that this Hon’ble Commission vide its Order dated 02.02.2011 had specifically held that the Force Majeure events as claimed by Petitioner therein i.e. PTC India Limited did happen which were not disputed by PTC and the Respondent No.2. The said findings were not challenged by the Respondent No.2 or Respondent No.1 and thus became final and binding on the said parties. Therefore, it is not open to the Respondent No.2 now to state that the reasons namely earth quake in China and the visa policy of the Government of India are not Force Majeure events as contended or otherwise. In so far as the contention of the Respondent No.2 that this Hon’ble Commission vide Order dated 02.02.2011 rejected the claim of compensation in terms of the tariff hike is concerned, it is submitted that admittedly the said finding of the Hon’ble Commission was based on the premise that there was no enabling provision for the same in the PSA/PPA. The said finding of the Hon’ble Commission cannot be considered at all as the Hon’ble APTEL vide its judgement dated 03.01.2014 has directed re-determination of tariff dehors the PPA.. As per the said judgment of the Hon’ble APTEL the tariff is to be determined in accordance with
93 | P a g e
the HERC Tariff Regulations, 2008. Without prejudice to the above, the second appeal arising out of the Order dated 02.02.2011 passed by this Hon’ble Commission being C.A. No. 10329 of 2011 is pending before the Hon’ble Supreme Court and therefore the above finding in respect of tariff hike is sub-judice. It is important to note that the present proceedings for determination of interim tariff originally arise out of the Order dated 16.12.2011 passed by the Hon’ble Supreme Court in the said Civil Appeal. It is thus incorrect and misconceived to state that the Petitioner cannot claim either IDC or IEDC or any other compensatory payment by way of cost overrun or time overrun on account of the delay resulting from the Force Majeure Event of earthquake in China or visa policy of the Government of India. It is also incorrect to state that the said issue stands settled and cannot be opened at this stage as alleged. It is denied that the reason of earthquake in China, visa policy of the Government of India etc are not Force Majeure events as alleged by the Respondent No.2. In any event the Respondent No.2 is estopped from raising the above contention. It is denied that the claim for IDC and IEDC i.e. time overrun and cost overrun can be considered only in regard to the matters other than those resulting from the Force Majeure Event. It is pertinent to mention that IDC is dependent on hard cost of the project which is decided along with the time duration of the Project and the applicable interest rate. It is submitted that the actual capital expenditure incurred upto the COD has to be considered as the completed capital cost in accordance with Regulation 12 of the HERC Tariff Regulations, 2008. Therefore, the Petitioner is entitled to the actual capital cost incurred by it. As stated above the increase in capital costs were on account of the reasons which were beyond the reasonable control of the Petitioner. It is submitted that the reasons of increase in capital cost have been duly explained in Para-B of its letter dated 13.01.2014 and the documents filed along with the same and the contents of which may be treated as part and parcel of the para under reply. It is further submitted that as per Regulation 12 of the HERC Tariff Regulations, 2008 the Petitioner is entitled to increase in capital cost since the same has been actually and bonafidely incurred by the Petitioner in executing the project.
94 | P a g e
24. The contents of para no. 24 of the reply are incorrect, false, misconceived, misleading. It is denied that the claim of the Petitioner for the delay in the commissioning is only on account of Force Majeure Event of earthquake in China in May, 2008. It is denied that the reasons stated for delay in commissioning of the Unit-II cannot be ground for claiming cost overrun in respect of Unit-II. It is submitted that on 12.05.2008, the manufacturing facilities of M/s Dongfang Electric Corporation, China (DEC), supplier of main plant equipment and BTG component of project were severely damaged due to a powerful earthquake rated at Richter scale 8.0 in China and DEC could not supply the machines and equipments to the Petitioner. This was admittedly a Force Majeure event. It is denied that the event of Force Majeure of Visa Policy of the Government of India not permitting the Chinese workforce has been raised as an afterthought. The force-majeure notices were issued by the Petitioner to the Respondent No.1 i.e. PTC India Limited immediately after the occurrence of the force majeure event in the year 2009 itself and therefore the allegation of the Respondent No.2 that it has been raised as an afterthought is patently wrong. It is denied that the delay in commissioning due to the usage of the rotor of Unit-II in Unit-I cannot be a ground for claiming the cost overrun in respect of Unit-II. It is submitted that the delay on this account was caused during the period of Force Majeure events. The Petitioner craves the leave of this Hon’ble Commission to treat the contents of para-B of the letter dated 13.01.2014 as part and parcel of the para under reply and the same are not repeated herein for the sake of brevity. 25.The contents of para no. 25 of the reply are incorrect, false, misconceived, misleading. It is reiterated that as per the judgment dated 03.01.2014 of the Hon’ble APTEL, the Tariff Regulations, 2009 of the Central Commission in so far as fixed charges is of no relevance in the present proceedings. As per the judgment dated 03.01.2014 of the Hon’ble APTEL, fixed charges are to be computed as per the HERC Tariff Regulations 2008. It is evident from the Tariff Formats filed by the Petitioner on 13.01.2014 which are in accordance with HERC Tariff Regulations, 2008 that the Petitioner has claimed annual fixed charges for FY 2011-12, FY 2012-13, FY 2013-14 and FY 2014-15. It seems
95 | P a g e
that the Respondent No.2 has raised these objections without going into the details submitted by the Petitioner. 26. The contents of para no. 26 of the reply are incorrect, false, misconceived, misleading. It is reiterated that as per the judgment dated 03.01.2014 of the Hon’ble APTEL the Tariff Regulations, 2009 of the Central Commission is of no relevance in the present proceedings in so far as interest on working capital is concerned. In the para under reply, the Respondent No.2 is again trying to mislead the Hon’ble Commission by referring to period of actual consumption, coal price etc. of January 2009 to March 2009. It is submitted that it commenced supply of power to the Respondent No.1 i.e. PTC India Limited w.e.f. 07.05.2011 pursuant to the interim Order dated 23.03.2011 passed by the Hon’ble APTEL. The Petitioner had been running its Unit II and supplying power to Respondent No.1 i.e. PTC India Limited by procuring the linkage coal supplied by SECL under MoU route and meeting its balance requirements of coal from alternate sources. That the linkage coal supplied by South Eastern Coalfields Limited (SECL) during the above period was widely varying and it was sufficient for only 27% PLF and hence the additional coal was procured from alternate sources which is much costlier than the linkage coal which had caused additional working capital expenditure and further the payment was not fully realized at par with the cost of generation from PTC India Limited. The tariff was to be determined based on the directions of the Hon’ble Supreme Court by its Order dated 16.12.2011 and now by the direction of Hon’ble APTEL for the power which had already been supplied based on costs actually incurred. The Petitioner submits that it is seeking reimbursement of the actual costs incurred by it in accordance with directions of Hon’ble APTEL. It is relevant to submit that to comply with the Order dated 16.12.2011 of the Hon’ble Supreme Court, the Petitioner was receiving widely varying quantum of linkage coal under MoU route from SECL, the coal procured from alternate sources also widely varied to run the Unit-II and supply power to the Respondent No.1 i.e. PTC India Limited . It is submitted that in the instant case, the Petitioner had to spend additional working capital to procure the coal from alternate sources varying on month to month basis based on the
96 | P a g e
quantum of linkage coal supplied. The tariff application containing the tariff filing formats filed on 13.01.2014 is based on the actual working capital expenditure incurred for the power already supplied for the past period and for the future period, the Petitioner has considered the normative working capital requirements in the computation of the tariff. It is further important to state that in the present facts and circumstances where the tariff is determined for a past and concluded period for which the data in respect of actual consumption of coal price, operation and maintenance expenses, cost of secondary fuel etc are already available then the interest of working capital is required to be determined on the said available data. It is denied that the actual amount of capital employed from time to time in regard to the coal consumption etc. is irrelevant as alleged. It is incorrect to state that the interest on working capital is not dependent upon the actual working capital incurred by the generating company irrespective of whether the generating company incurs the working capital or not. It is denied that the claim of the Petitioner of actual working capital every month or on the basis of coal value is contrary to HERC Tariff Regulations, 2008 or any other regulations. 27. The contents of para no. 27 of the reply are incorrect, vague, false, misconceived and misleading. The averment of the Respondent no.2 in relation to alleged coal consumption being higher in a particular month is completely vague. The Petitioner in its Tariff Filing Formats has given monthly as well yearly figures of coal consumption. The Petitioner submits that in certain months during the power supply period, the Petitioner did not receive any linkage coal as SECL had not supplied any linkage coal and the Petitioner had to procure the entire coal required for running the Unit-II from alternate sources including imported coal. In certain other months, the Petitioner had to depend entirely on procurement of coal from alternate sources including imported coal which led to higher outflow of working capital. It is reiterated that as per the judgement dated 03.01.2014 of the Hon’ble APTEL the Tariff Regulations, 2009 of the Central Commission is of no relevance in the present proceedings in so far as coal consumption is
97 | P a g e
concerned. It is denied that it is not open for the Petitioner to claim actual interest on working capital on month to month basis. 28. The contents of para no. 28 of the reply are incorrect, false, misconceived, misleading. It is denied that the operating and maintenance expenses need to be ascertained in terms of the Tariff Regulations, 2004 based on the capital cost determined by this Hon’ble Commission as alleged. In the para under reply, the Respondent No.2 is again trying to mislead the Hon’ble Commission by initially referring to the Tariff Regulations, 2004 and then referring to Tariff Regulations, 2009 pertaining to O&M expenses. It is reiterated that as per the judgement dated 03.01.2014 of the Hon’ble APTEL the Tariff Regulations, 2004 of the Central Commission is of no relevance in the present proceedings. Further, even otherwise the Tariff Regulations, 2004 cannot be made applicable to the tariff determination of the Petitioner since the said Regulations ceased to be effect from 01.04.2009 whereas O&M expenses in respect of the Petitioner case is for the year 2011-12. It is submitted that on 03.02.2014, the Petitioner has filed an application under Regulation 33 of the HERC Tariff Regulations, 2008 before this Hon’ble Commission inter alia seeking relaxation of Regulation 16(iv)(c) of the HERC Tariff Regulations, 2008 regarding O&M expenses and grant of O&M expenses as per CERC Tariff Regulations, 2009. In this regard, it is relevant to submit that the O&M expenses as per HERC Tariff Regulations, 2008 are much lower and practically not feasible for a generating station or Unit generating power. It is further submitted that the Respondent No.2 has also admitted that the O&M expenses needs to be paid to the Petitioner under CERC Tariff Regulations, 2009 on normative basis. It is further submitted that this Hon’ble Commission vide its Order dated 18.04.2011 passed in CASE No: HERC/PRO– 1 OF 2011 for generation tariff for the Respondent No.2 has noted that the HERC Tariff Regulations, 2008 in relation to Operation and maintenance expenses are outdated and not updated. Further, this Hon’ble Commission vide the said Order has not only deviated from the applicability of HERC Tariff Regulations, 2008 but has also allowed O & M Expenses as per CERC Tariff Regulations, 2009 for the generation tariff of the generating stations of the Respondent
98 | P a g e
No.2. In this regard, it is submitted that the Petitioner is therefore entitled to parity and is entitled to relaxation/variation of HERC Tariff Regulations, 2008 while re-determination of the interim tariff for its Unit-II. The relevant potion of the Order dated 18.04.2011 of this Hon’ble Commission is reproduced herein below: The Commission is of the considered view that adequate amount of O&M expenses is essential for deriving optimum efficiency from the plant and machinery. Hence, in the absence of updated HERC generation tariff regulations, CERC norms for unit size of 200 MW & above have been adopted for FY 2011-12. For the remaining generating stations of lower than 200 MW capacity, where CERC norm does not exist, the basis of estimating O&M expenses is the O&M expenses allowed by the Commission in FY 2009-10 escalated by 5.72% per annum to arrive at O&M expenses to be allowed in FY 2011-12. The escalation factor considered is as per CERC notification. Accordingly, the Commission allows O& M expenses @ Rs. 2.94 million/MW for PTPS (1-4), Rs. 2.034 million/MW for PTPS (5 to 8), Rs. 1.788 million/MW for DCRTPS and Rs. 1.308 million /MW for RGTPS (1&2). While the O&M expenses allowed by the Commission in the case of WYC & Kakroi have been approved as proposed by HPGCL. It is also important to state that pursuant to the passing of Order dated 18.04.2011, this Hon’ble Commission has passed similar tariff Orders for the Respondent No. 2 generating stations for the subsequent years wherein O&M expenses has been allowed in accordance with CERC Tariff Regulations, 2009 containing reference of Order dated 18.04.2011. Copy of relevant extract of the Order dated 18.04.2011 passed by the Hon’ble Commission in CASE No: HERC/PRO– 1 OF 2011 is annexed hereto and marked as Annexure P-5. 29. The contents of para no. 29 of the reply are incorrect, false, misconceived, misleading, save and except being matters of record. It is denied that the Petitioner cannot demand energy charges based on any coal used by it other than through procurement of coal under a regular Fuel Supply Agreement with coal India/its subsidiary is
99 | P a g e
contrary to the judgment dated 03.01.2014 of the Hon’ble APTEL. In terms of the said judgment the energy charges are to be calculated as per the HERC Tariff Regulations, 2008. Further, as per the directions of the Hon’ble APTEL the Petitioner has submitted the materials showing that it made bonafide efforts to secure coal linkage from SECL as envisaged at the project planning stage, along with the letter dated 13.01.2014. The Petitioner submits that since 07.05.2011 when the Petitioner commenced supply to the Respondent No.1 i.e. PTC India Limited, there have been frequent downward revisions in the supply of linkage coal by SECL. The Petitioner inspite of financial hardships had tried its best to operate its Unit-II and supply power to the Respondent No.1 i.e. PTC India Limited by procuring the ever increasing balance requirement of coal from alternate sources (where the cost of coal was at least 3 to 4 times higher than the cost of linkage coal) without realization of a just and equitable tariff which was not even meeting its generation cost. It is an admitted position that the Petitioner was facing severe hardship on account of the increasing burden due to coal costs (in view of the reduced quantities of coal being supplied by the government undertakings in light of the New Coal Distribution Policy). It is submitted that the coal linkage from the SECL to the Petitioner had decreased from what was originally envisaged with the SECL i.e. 100% linkage coal which is evident from the following: Letter of Assurance dated 18.09.2006 issued by SECL guaranteeing coal supply to the extent of 1.445 MTPA; MoU dated 15.03.2010 with SECL for the period 2009-2010 for coal supply of an annual quantity of 18 lakh tons; Letter dated 11.06.2010 by the Ministry of Power directing the Petitioner to procure 3 lakh tons of imported coal. MoU dated 24.07.2010 for the period 2010-2011 for coal supply of an annual quantity of 13 lakh tons with SECL; Minutes dated 18.04.2011 of SLC, Ministry of Coal envisaging supply of only 50% of domestic coal.
100 | P a g e
MoU dated 30.08.2011 for the year 2011-2012 for coal supply of an annual quantity of 9.4 lakh tons. Letter dated 10.07.2012 from SECL by which SECL had reduced the coal supply to 91% of 0.94 MTPA (i.e. 71,283 per month). Copy of the Letter of Assurance dated 18.09.2006, MoU dated 15.03.2010, MoU dated 24.07.2010, MoU dated 30.08.2011, Letter dated 11.06.2010 & Minutes dated 18.04.2011 of SLC have already been submitted by the Petitioner vide its tariff petition 12.01.2012 before this Hon’ble Commission in CASE NO: HERC/PRO – 1 OF 2012 and the same are already on record at page nos. 224-250 of the tariff petition dated 12.01.2012. Copy of the letter dated 10.07.2012 from SECL have already been submitted by the Petitioner vide its reply dated 19.07.2012 to the objection of the Respondent No.2 before this Hon’ble Commission in CASE NO: HERC/PRO – 1 OF 2012 and the same is already on record as Annexure-G of the reply dated 19.07.2012 of the Petitioner. As a matter of fact, there was no coal supply during the period from May 2012 to June 2012 and the coal allocation vide SECL letter dated 10.7.2012 was further reduced to an annual quantity equivalent to 0.86 million tons per annum (MTPA) from 0.94 MTPA. It is further submitted that, the coal supply was further reduced by SECL to 46216 metric tonnes per month (equivalent to 0.55 MTPA) vide letter dated 28.09.2012. The month wise supply of Linkage Coal from SECL was as under:
Month
Linkage Coal Supplied from SECL (in MT)
Coal Requirement for 100% PLF (in MT) @3300 kCal/kg
Supplied Coal Sufficient for % PLF
Weighted Average GCV (Kcal/Kg)
May-11 0 1,61,719 0% 3146
Jun-11 0 1,56,502 0% 3273
101 | P a g e
Jul-11 0 1,61,719 0% 3127
Aug-11 0 1,61,719 0% 3295
Sep-11 59,169 1,56,502 38% 3,348
Oct-11 76,926 1,61,719 48% 3,132
Nov-11 72,421 1,56,502 46% 3,321
Dec-11 88,680 1,61,719 55% 3,354
Jan-12 76,780 1,61,719 47% 3,487
Feb-12 74,172 1,51,285 49% 3,411
Mar-12 76,648 1,61,719 47% 3,350
Apr-12 74,601 1,56,502 48% 3,181
May-12 3,800 1,61,719 2% 3,265
Jun-12 0 1,56,502 0% 0
Jul-12 66,090 1,61,719 41% 2,952
Aug-12 63,847 1,61,719 39% 3,176
Sep-12 0 1,56,502 0% 3167
Oct-12 39,739 1,61,719 25% 2,976
Nov-12 44,809 1,56,502 29% 3,023
Dec-12 43,999 1,61,719 27% 2,929
Jan-13 44,439 1,61,719 27% 3,270
Feb-13 41,151 1,46,069 28% 3,581
Mar-13 39,961 1,61,719 25% 3,421
Total/ Average
9,87,232 36,56,934 27% 3,256
102 | P a g e
It is further relevant to submit that the cost of imported coal is about five times the cost of linkage coal after proportionally adjusting the benefit of higher GCV. That in the absence of the 100% linkage coal the Petitioner had to resort to procurement of the imported coal and therefore the Petitioner is entitled to actual cost incurred in procuring coal for generating the power at Unit-II. 30. In response to para no. 30 the Reply it is reiterated that the Petitioner has furnished all details as per the directions of the Hon’ble APTEL and is willing to provide any other information and/or document in the event the Hon’ble Commission directs so. The Petitioner prays that the re-determination of tariff be done at its earliest convenience of this Hon’ble Commission keeping in view the fact that the Petitioner had been supplying power since 07.05.2011 to the Respondent No.1 i.e. PTC India Limited as per the Orders passed by the Hon’ble APTEL and the Hon’ble Supreme Court of India, however, the Petitioner has so far not been able to recover its cost of generation. The total outstanding for power supplied upto March, 2013 is approximately Rs. 195 crores (approx) (without interest). Further, the Petitioner is facing severe financial hardship in meeting the interest and loan repayment obligations to various banks and financial institutions and the assets/project is likely to be treated as Non Performing Asset (NPA) by the Lenders and financial Institutions. In this regard, it is significant to submit that the financial position of Petitioner has become precarious over time by erosion of more than 70% of net worth of the Project. It is relevant to submit that as per the statement of accounts of Unit-II of the Petitioner, the accumulated losses since the date of commencement of sale of power to the Respondent no.1 upto 31.12.2013 is Rs. 317.73 Crores considering billed tariff in accordance with CERC Tariff Regulations, 2009. The Petitioner states that a just and equitable viable tariff as decided by this Hon’ble Commission shall allow the Petitioner to supply power on continuous basis to the Respondent No.1 PTC India Limited.
103 | P a g e
As per the directions of the Commission HPPC submitted a detailed
interrogatories seeking details from LAPL which was duly provided.
Additionally, LAPL provided the detailed site plan map, water intake
system as well as the details of the railway drawings. A copy of the
plant outlay and railway drawing was also made available to the
officials of HPPC who had undertaken the site visit
An affidavit dated 9.04.2014 was also filed by LAPL, on the directions
of the Commission, stating as under:
“2. I say that the following facilities/assets which were created for the
Unit -1 and Unit - 2 and/or Unit -1 or Unit - 2 of the Petitioner
Company (LAPL) are not being used or will not be used for the Unit -
3 or Unit - 4 of the Petitioner Company (LAPL).
a) Service building including MGR Workshop
b) Off Site Building
c) Administrative Building
d) Field Hostel, Residential and Service Building Township
e) Sewerage & Effluent Treatment Plant
f) Power Station Switchyard
g) Air Conditioning System
h) Coal Handling System
i) Permanent Road, Drain, Rain Water Harvesting, Fire Station
and Related
j) Fuel Oil Handling System
104 | P a g e
k) Ash Handling System
l) Cooling Water System Including Cooling Tower
m) Water Treatment Plant
n) Compressed Air System
o) Work Shop Equipment's
p) Laboratory Equipment's
q) Transmission Lines
r) Ventilation System
s) Emergency D.G Sets
t) Interior Communication Equipment's
u) Permanent Railway Siding
v) River Water Intake System
w) Weather Monitoring/Recording System and High Masts
Lighting
x) Land - Unit-I : 566.89 Acres, Unit-2: 200 Acres, Unit-3&4 :
570.71 Acres
3. I say that the following facilities/assets created for the Unit -1 and
Unit-2 or for Unit - 1 or Unit - 2 of the Petitioner Company (LAPL)
are being used or shall be used for the Unit - 3 or Unit - 4 of the
Petitioner Company (LAPL) jointly or separately and the amount
mentioned below against each facilities/assets have been booked to
the Unit - 3 or Unit - 4 of the Petitioner Company (LAPL) jointly or
separately:
105 | P a g e
a) Cost of Boundary Wall Separately booked: - Unit -1: Rs. 5.567
Crs., Unit-2: Rs. 2.56 Crs., Unit 3&4: Rs. 6.93 Crs. (cost
envisaged).
4. I say that facts stated above have been derived from the records of
the Petitioner Company maintained in the normal course of
business and believed by me to be true and correct”.
The above statement was verified by the officials of HPPC and E&Y
including officer/Technical Consultant of the Commission, who had
undertaken site visit of the power plants on 16th and 17th August,
2014. The outcome of the site visit as submitted by E&Y is as under:
“Following points stand clearly established: 1. Balance of Plant (BOP) facilities of the existing 2x300MW plant is shared between Units 1 & 2. These are as follows: i. Coal Handling Plant ii. Fuel Handling System iii. Ash Handling Plant iv. Fire Detection & Fire Fighting System v. Raw Water Intake Station vi. Clarified Water System vii. DM Water Plant viii. 400kV Switchyard ix. Miscellaneous auxiliary units not specifically listed above. 2. The capacities of existing facilities designed for 2x300 MW generation capacity does not allow them to be used for a much larger 2x660MW capacity of the new plant. The layouts of the existing plant
106 | P a g e
(Units 1&2) and that of the new plant (Units 3&4) also do not allow the existing BOP facilities for units 1&2 to be used for units 3&4. 3. The only physical connection between electrical/mechanical /coal/water systems of the existing plant and the new plant is the planned interconnection between the two 400kV switchyards, which are separated by a fence and have their own control rooms and evacuation arrangements. This connection gives a flexibility of operation and does not amount to sharing the assets of the existing plant (Units 1&2) with the new plant (Units 3&4). 4. Land: Unit 2 has been built partly on the green belt area for Unit 1. Additional land has been acquired to leave mandatory green belt for units 1&2 taken together. Since 200 acres has been attributed to Unit 2 and 566.89 acres to Unit 1, the cost of land considered for Unit 2 is less than half of the total for Units 1& 2 taken together. It is our understanding that in a similar manner, part of the green belt earmarked for Unit 2 hasbeen used for Units 3&4.Later an equal amount of the land which was taken from Unit 2 green belt area for Units 3&4 was transferred back to unit 2 from the land acquired for Units 3&4. Hence, total land allocated to Unit 2 remained 200 acres and no part of that was used by Units 3&4. 5. Boundary Wall: It is understood that additional boundary wall created for Unit 2 has been charged to it. Part of this boundary wall has been dismantled to enlarge the plant area to include Units 3&4. It is also learnt that the boundary wall for the enlarged plant has been charged to the Units 3&4. Hence there is no case for reduction in cost of assets charged to Unit 2 on this account. 6. Railway tracks and marshalling yards: The layout of tracks (except a small portion which is described separately in point no 6) and that of the coal unloading facilities is such that the existing facilities (Units 1&2) cannot be used for the new facilities (Units 3&4).
107 | P a g e
Land required for railway track for Units 3&4: There is a very small section of railway track where the railway track for units 3&4 is laid in parallel with that of existing units 1&2. It is possible that laying tracks in that section did not require additional land if the land earlier acquired was in excess of what was actually used to lay tracks for units 1&2. However, if land for this section of the track has been acquired for Unit 1 and has not been charged to Unit 2, the question of transferring the cost from Unit 2 to Units 3&4 does not arise. In other words, laying these tracks on the land in question does not impact the cost of Unit 2. 7. Quantity, cost and GCV of coal: LAPL shared some information on Coal GCV during the site visit. However, all the necessary information had been provided to us earlier too in soft copy format. We have already done necessary diligence and the same has been shown in the Addendum to the draft report dated 8th July (point no 4). No additional finding has been observed during the site visit and hence not reported here”.
A copy of the above site visit report was also provided to HPPC and
LAPL . Further, the Commission vide memo no. memo no. 1924-
27/HERC/Tariff/LAPL dated 20.08.2014 requested HPPC and LAPL as
under:
“All facilities of the power plants (Unit – 1 to Unit – 4) including water
intake system, ash dyke, coal handling, railway line/sidings etc. were
visited. A copy of the plant outlay and railway lines/sidings/drawings
was provided by LAPL to the representatives of HPPC and E&Y. Coal
and freight invoices for coal supplied by SECL, E-auction/Open Market
were produced by LAPL for verification. The manner of assessing
108 | P a g e
GCV of coal received at LAPL Unit – 1 and 2 including the sampling
method was explained and daily report was provided for inspection.
In view of the above HPPC may submit their observations/comments regarding common assets etc. and sharing of the same.
E&Y shall also submit a report including their revised assessment of
sharing of the common assets between various Units of LAPL,
quantity, cost and GCV of coal etc. for LAPL Unit – 2 at the site. The
said report shall be submitted as an addendum to the report already
submitted by E&Y to the Commission. On receipt of the same a copy
shall be forwarded to HPPC and LAPL for their
comments/observations, if any”.
Meanwhile LAPL filed another petition dated 26.08.2014
submitting that in terms of Order dated 28.07.2014 passed by this
Commission, HPPC was given two weeks time to file its
comments/objections from the date of receipt of addendum dated
4.08.22014. Accordingly, the time period for filing the
comments/objections by HPPC expired on 18.08.2014. It was further
submitted that, on the contrary, HPPC has written a letter dated
11.08.2014 claiming that the time period for HPPC to file their
comments/objections would commence on after an affidavit
regarding conflict of interest is filed by E&Y and layout plan of the
project is received from LAPL.
109 | P a g e
Additionally, LAPL submitted that as per the judgment dated
03.01.2014 passed by the Hon’ble APTEL in Appeal No. 65/2013, the
tariff was required to be determined by this Commission was within
two months from the date of receipt of the said judgment. Thereafter,
vide Order dated 13.05.2014 the Hon’ble APTEL had extended the
said time period up till 25.06.2014 and had made it clear that no
further extension will be given at any cost. Despite the said Order
being passed by the Hon’ble APTEL, HPPC is delaying the present
proceedings on one pretext or another.
It was submitted that in the hearing held on 20.05.2014 in
which representatives of HPPC were also present, the Commission
had specifically asked E&Y to clarify whether it has any conflict of
interest with any of the parties. E&Y had clarified during the hearing
that there was no conflict of interest with any of the parties. That
after the receipt of report from E&Y pursuant to the Order dated
25.03.2014 passed by this Commission, the same was forwarded to
the parties vide e mail dated 08.07.2014 to file their
comments/objections positively by 15.08.2014 and a hearing was
scheduled on 22.07.2014. In the said communication sent by this
Commission, it was specifically made clear that in case comments/
objections are not received within the time period prescribed, it will
be presumed that the party has no objection to the draft report. HPPC
did not file its objections within the time period prescribed by this
Commission and on the date of hearing made a request to defer the
hearing on the purported ground that the sufficient time was not
110 | P a g e
given for filing the objections. Prior to that on 15.07.2014, HPPC made
a request to defer the hearing on the ground that its counsel was not
available, which request was rejected by this Commission. Therefore,
it is apparent that the request made for deferment on the ground that
time was not sufficient to file objections was nothing but an
afterthought to ensure that the hearing does not happen. It is further
submitted that HPPC also filed written objections on 22.07.2014
wherein a frivolous ground that E&Y has conflict of interest with the
Petitioner was raised. It is important to note that E&Y was appointed
as consultant by this Commission with consent of both the parties.
Therefore, the objection of HPPC evidently was to delay the matter.
The next hearing was scheduled on 28.07.2014 when a direction was
given by this Hon'ble Commission to E&Y to file an addendum to the
report.
It was submitted that the Order dated 28.07.2014 passed by
this Commission is clear that HPPC was required to file its
comments/objections to the addendum to the report within 2 weeks
from the date of receipt, which it has failed to do. Instead, it has filed
a mischievous letter claiming that the time period to file its
comments/ objections would start from the date of receipt of the
affidavit regarding conflict of interest from E&Y. It is pertinent to
mention here that in spite of specific and unambiguous direction by
the Commission vide its Order dated 28.07.2014 HPPC is deviating
from the same. It is clear from the conduct of HPPC that it has nothing
specific to object in the matter and is finding ways and means to
111 | P a g e
somehow delay the conclusion of the present proceedings not only in
Order to cause irreparable harm and injury to the Applicant but also
disregard to the aforementioned Order passed by the Hon'ble APTEL
and the Commission.
The Applicant submitted that the time period to conclude the
present proceedings was fixed by Hon'ble APTEL keeping in mind the
continuous irreparable harm and injury being caused to the Applicant
as its plant is shut. HPPC has been relentlessly, on one pretext or
another, delaying the matter with malafide objective. The letter dated
11.08.2014 written by HPPC claiming that the time period to file
comments/objections to the addendum filed by E&Y has not even
begun is in teeth of the directions given by this Commission vide
Order dated 28.07.2014 and is contumacious (sic) in nature. HPPC is
crossing all limits to somehow ensure that the present proceedings
are not concluded despite being conscious that its conduct is contrary
to the Orders passed by the Hon'ble APTEL. It is also evident that
HPPC has nothing substantial to raise in the matter as all its queries
and questions raised vide memorandum of interrogatories have been
satisfactorily replied to by the Applicant as far back on 09.04.2014.
Therefore, it is raising ex-facie frivolous and misconceived issues to
scuttle the proceedings. The Applicant submits that the conduct of
HPPC amounts to abuse of process of law and this Commission ought
to take serious note of the same and pass appropriate Orders in the
matter.
112 | P a g e
In view of the above submissions LAPL has prayed that the
Commission may pass an Order treating the right of HPPC t file their
comments/objections to the addendum dated 4.08.2014 to the report
dated 08.07.2014 filed by E&Y in the present matter as closed.
HPPC’s Submissions:-
The Ld. Counsel appearing Shri M.G. Ramachandran,for HPPC, argued
at length in the hearing held on 19.09.2014. The gist of averments
made by him is as under:-
It was submitted that reports submitted by E & Y Consultants,
including the addendum report forwarded to the Respondent No. 2
on or about 23.08.2014, subsequent to the site visit undertaken on 16
– 17th August 2014 has several inconsistencies in the claim made by
the Petitioner including with regard to the capital cost and other
aspects and the Petitioner is deliberately concealing facts and
misleading the proceedings.
It was argued that E & Y Consultants have not undertaken the
requisite study and investigation in a professional manner in Order to
verify the admissible project cost for the Petitioner’s Generating Unit
No. 2 of 300 MW at Amarkantak. The E & Y Consultants have
proceeded in a mechanical manner to approve the claims made by
the Petitioner without investigating into the veracity of the claim by
comparing it with other projects and also applying prudence check.
The E & Y Consultants have not considered the Memorandum in the
113 | P a g e
form of Interrogatories in writing given by Respondent No. 2 on 1st
April 2014. Further, there was no consultation of any nature
whatsoever by the E & Y Consultants with Respondent No. 2. The
Petitioner had also purported to have given materials such as Site
Plan to E & Y Consultants without giving copies of the same to
Respondent No. 2. The E & Y Consultants proceeded to consider all
these materials without any notice to Respondent No. 2.
The cursory manner in which the reports have been prepared
by E&Y Consultant is clear from the fact that E&Y Consultant had
proceeded on the basis of the claim of the Petitioner that there is no
Common Asset at all between Units 1 & 2 with Units 3 & 4; Whereas,
the site visit clearly establishes the falsity of the claim on the part of
the Petitioner.
Further, despite specific representation made by Respondent
No. 2 in the letter dated 29th April 2014 addressed to the Director
(Tariff) of the Commission to ensure that E & Y Consultants should not
be associated in any form with Lanco Group for taking up the work of
verification of the project cost, E & Y Consultants did not file any
affidavit before taking up the work on its ability to undertake the
work without such conflict.
114 | P a g e
E&Y Consultants filed an affidavit only on 25.08.2014. However,
vide this affidavit; E&Y Consultants have failed to declare that they
were not associated in any form with Lanco Group for taking up the
work of verification of the project cost. E&Y Consultants have not
made adequate disclosure of conflict of interest. Instead, their
affidavit contrary to the requirement is limited to conflict of interest
with Lanco Amarkantak Power Limited at the time of signing of the
contract with this Hon’ble Commission i.e. on 09.06.2014. The said
affidavit cannot be relied upon as E&Y Consultants have failed to
discharge their obligation of full disclosure regarding conflict of
interest with Lanco Group. In the circumstances, it will not be
appropriate for the Commission to proceed on the basis of the reports
submitted by E&Y Consultants. The meaningful reading of the
Affidavit shows that E&Y Consultants are in fact hiding behind
technicalities and concealing the conflict of interest it has. In this
regard, E&Y Consultants have deliberately not dealt with the
documents filed by the Respondents along with affidavit dated
25.07.2014.
Without prejudice to the above during the site visit on 16th and
17th August 2014, the representatives of Respondent No. 2 became
aware of serious inconsistencies in the claim made by the Petitioner
that there are no common or shared assets whatsoever in regard to
Units 1 and 2 with Units 3 and 4 of Amarkantak Power Project.
115 | P a g e
Some of these inconsistencies cited by the Respondent are as
under:
a) Layout Plan: It was submitted that the Petitioner provided
the representatives of the Respondent No. 2 with a
combined layout plan of Unit Nos. 1 to 4. However, the said
Layout Plan has not been properly marked/labelled.
b) Land: Land of Unit Nos. 1 to 4 was not properly demarcated.
Further, land of Unit Nos. 3 & 4 could not even be separately
identified. It is submitted that part of the land of Unit Nos. 1
& 2 has been used for Unit Nos. 3 & 4 and there are no
separate boundary walls. This is evident from the fact that
the geographical coordinates for main plant area of Unit
Nos. 3 & 4, in terms of the layout plan, lies inside the land
Unit 1 & 2.
c) Switchyard: Switchyard of Unit Nos. 3 & 4 has been made
adjacent to existing switchyard of Unit Nos. 1 & 2 on the
land meant for Unit Nos. 1 & 2. During the site visit, the
representatives of Respondent No. 2 have been informed by
the Petitioner that in lieu thereof a separate patch of green
belt has been earmarked for Unit Nos. 1 & 2. However,
sufficient information towards the same was not provided.
Accordingly, it is submitted that as the Petitioner failed to
furnish necessary details, adverse inference needs to be
drawn against the Petitioner inasmuch as it has utilized land
116 | P a g e
meant for Unit Nos. 1 & 2 for Unit Nos. 3 & 4. Further it is
imprudent practice to have separate switchyard for different
generating units located at the same place. The costs of
switchyard ought to be proportioned and this Commission
must approve the project cost only after prudence check.
d) Ash Pond: As per Environment Clearance dated 31/12/2007
granted by MoEF for Unit No. 3, it has been, inter-alia,
stated that:
“Fly ash shall be collected in dry form and its utilization
shall be ensured in accordance with the provisions of the
notification of September, 1997 on fly ash Utilization and
its amendment of August, 2003. The unutilized fly ash
and bottom ash shall be disposed in the existing ash
pond.”
e) It is apparent from the above that the Petitioner is
mandated to use the existing ash pond for unutilised fly ash
and bottom ash. However, when the same was brought to
the notice of the Petitioner by the representatives of the
Respondent No. 2, it was informed that separate Ash pond
would be made for Unit No. 3 & 4. The above position is
completely contrary to the conditions stipulated by the
MoEF and also establishes that the ash pond is required to
be shared between the Unit No. 1 & 2 and Unit No. 3 & 4.
Further, and in any event, location of a separate ash pond
was not provided in the layout plan of Unit Nos. 1 to 4.
117 | P a g e
Further, the Respondent No. 2 was also informed by the
Petitioner that they have acquired separate land for ash
pond where high concentrated ash of Unit Nos. 3 & 4, will be
disposed off. However no details were provided. It is also
imprudent to have such separate ash dyke and ash disposal
facilities
f) Boundary wall: No boundary wall separating Unit 1 & 2 with
Unit 3 & 4 has been constructed. In the circumstances, as
the land is contiguous, cost of land ought to be apportioned
in terms of the capacity of each unit.
g) Colony: During the site visit, the Respondent No. 2 was
informed by the Petitioner that it has acquired separate land
for colony of Unit Nos. 3 & 4, which shall be built towards
the water intake side; however, no construction has started
yet and cannot be verified at this stage.
h) Water Intake system: During the site visit, the Respondent
No. 2 was shown a separate construction site and was
informed that a separate raw water pump house is being
constructed on the said site. However, at present, after
some initial construction, the entire construction work on
the said site for the Water Intake System is at stand still. It is
also not verifiable as to whether the Petitioner will use
existing pipeline or provide a separate one for Unit No. 3 &
4. It is submitted that having a totally separate water Intake
118 | P a g e
System, Raw Water Pump House and Water Pipelines for
respective units is imprudent on the part of the Petitioner.
i) Raw Water Reservoir: No separate raw water reservoir could
be seen. It has been informed that they are constructing an
anicut in the river (Hasdeo river) before raw water intake
pump house with the permission of Chhattisgarh
Government. Though, same cannot be verified at this stage
as construction was at very initial stage. It is submitted that
having separate Raw Water Reservoir for respective units is
imprudent on the part of the Petitioner.
j) Railway siding: During the site visit, the Respondent No. 2
was informed that a separate railway siding is being
proposed for Unit Nos. 3 & 4. However, at present, there is
no separate railway siding for Unit Nos. 3 & 4 and it would
be rather imprudent on the part of the Petitioner to use
separate sidings for Unit 3 & 4, instead of the existing one.
Further and in any event, the proposed railway siding for
Unit Nos. 3 & 4 is bound to be made on the land presently
used for the existing railway siding of Unit 1 & 2.
Accordingly, this Commission should apportion the costs
between the units in terms of the generation capacity of
each unit.
k) Coal handling plant (CHP): The CHP of Unit Nos. 3 & 4,
shown to the Respondent No. 2, is already constructed
119 | P a g e
adjacent to existing CHP of Unit Nos. 1 & 2. However, in the
layout plan provided for Unit Nos. 1 – 4, it is to be
constructed behind the ash pond of Unit Nos. 1 & 2. It would
therefore mean that the Petitioner would use the Wagon
Tipler Area identified in the layout plan for Unit No. 1 & 2 for
Unit Nos. 3 & 4. In the circumstance, it is evident that the
cost for Coal handling Plant (CHP) would be shared between
Units 1 & 2 and Units 3 & 4. In this regard, it is also
submitted that the Petitioner has sought approval of an
amount of Rs. 151.47 Cr. and Rs. 115.74 Cr. as cost for the
Coal Handling Plant for unit 1 and unit 2, respectively.
Clearly, the cost of the Coal Handling Plant of the Petitioner
is significantly higher, as compared to other power plants,
details of which have been provided in the subsequent
paragraphs.
l) It is further submitted that the in addition to the above
assets, the following assets are also common and/or are
likely to be shared between Units 1 & 2 and Units 3 & 4:
i. Existing Roads within the power project of the Petitioner.
ii. Administrative Building
iii. Service building
iv. Fire station
v. Field hostel
vi. Drainage System
120 | P a g e
During the site visit a specific inquiry was made about the
expansion of Units Nos. 5 & 6 of 660 MW each. The details of
the said units are given hereunder. There was no satisfactory
answer given in regard to the location of such units 5 & 6. From
the Layout plant, the said units it seems will be constructed
within the map disclosed as in the case of Units 3 and 4
integrated with Units 1 and 2
It be stated that the Lanco Amarkantak Power Project consist of
several generating units, namely, Units 1 and 2 with 300 MW
capacity each, Units 3 and 4 with 660 MW capacity each and
further Units 5 and 6 being an expansion of the project again
with a capacity of 660 MW each. Thus, the generating station
as was originally considered was with 2 x 300 MW each and 2 x
660 MW each and subsequently there has been a proposal to
expand the generating station by another 2 x 660 MW each.
Unit No. 2 of 300 MW, the subject matter of the present
proceedings before the Commission, has therefore been a part
of a large capacity generating station of 1960 MW, which has
now increased to 3240 MW. All the above generating stations
are contiguous in Korba in the State of Chhattisgarh.
Accordingly, the generating units have been established with
the intent to have sharing of various common assets and
facilities and to achieve economies in the scale of operation.
121 | P a g e
In regard to the above, it is relevant to mention that the
Petitioner had offered to sell electricity to Respondent No. 2
from the 300 MW Unit No. 2 at a ceiling tariff of Rs 2.32 per
kwH. Reference in this connection may be made to the
Schedule E of the Power Purchase Agreement dated 19.10.2005
entered into by the Petitioner with PTC India Limited,
Respondent No. 1, which, inter alia, provides as under:
“Schedule E 2.1 The capped Tariff Rate (in Rupees per kWh), levelised over the relevant Tariff Years, using a discounting factor of 12% per annum, shall be as set out in the following table:
Tariff Year Capped Tariff Rate (Rs./kWh)
Tariff Year 1 – 25 2.32 For the avoidance of doubt, it is clarified that the Capped Tariff Rate shall be Rs. 2.32/kWh and would be considered from the 1st Tariff Year onwards until the 25th Tariff Year for the purpose of Tariff Pool account calculation.”
The Respondent no. 2 submits that there should have
been some basis for the Petitioner to agree to the above tariff
of Rs 2.32 per KwH. The Petitioner’s proposal to agree to the
ceiling tariff of Rs 2.32 per KwH clearly indicates its intention to
develop the generating stations with various generating units
including the opportunity available for expansion, namely,
122 | P a g e
Units 1 to 6 with a large aggregate capacity and thereby taking
advantage of economies of scale of operation including and in
particular the use of various facilities in a shared and common
manner. There is otherwise, no explanation whatsoever from
the Petitioner in regard to its decision to offer power to
Respondent No. 2 with a ceiling tariff of Rs 2.32 per KwH.
Neither, the Petitioner had disclosed the same nor the E & Y
Consultants appointed by this Commission as an expert has
even made an attempt to make any inquiry on the aspect of the
basis on which the Petitioner had agreed to the ceiling tariff of
Rs 2.32 per KwH and incorporated the same in the Power
Purchase Agreement dated 19.10.2005. The E & Y Consultants
has, therefore, failed to conduct proper inquiry as an
independent Consultant appointed by the Commission to go
into the prudent check of the project cost admissible for the
tariff purpose and has mechanically adopted whatever the
Petitioner had stated in its financial statements and that too
without any opportunity to Respondent no. 2 to contest the
same.
Admittedly, when a generating station is established with
number of units and on land contiguous to each other, there
are opportunities available to economies the scale of
investments and use of various assets in a common/shared
manner thereby reducing the cost for each unit. In this regard
123 | P a g e
many of the assets relating to the above generating stations of
the Petitioner with six units, namely, 2 x 300 MW each and 4 x
660 MW each can be effectively used as a common asset. The
layout plan now made available fortifies the same. Despite the
above, the Petitioner has been alleging wrongly that there are
no common assets as between Units 1 and 2 on the one hand
and Units 3 and 4 or other units on the other hand. In this
regard, the Petitioner has referred to various approval granted
by the authorities including environmental approval, approval
for drawing water, railway authorities approval etc to allege
that there are no common assets/shares assets. The grant of
specific approval for each unit cannot be an indication of the
fact that each of the unit will have an independent and
separate asset and there will be no common assets. The
attempt made by the Petitioner is to mislead this Commission
by referring to consents and approval with regard to each of
the generating unit and concealing that the physical assets will
be common. The site visit has exposed the falsity of the claim of
the Petitioner and the attempt made by the Petitioner to
mislead the Commission.
The line for the railway siding from the main trunk line of
Indian Railways to the Korba Station for transportation of coal
etc. This railway line is not being established and ought not to
be established separately for each unit, namely, for Units 1 and
124 | P a g e
2 separately from Units 3 to 6. This ought to be a common line
to be used for transportation of coal for all the generating units
with an aggregate capacity of 3240 MW. In such an event, the
capacity of 300 MW pertaining to the Generating Unit No. 2
would proportionately work out to less than 10% of the use of
the railway line and railway siding. It is, therefore, not
appropriate to load the entire cost of the railway line and
railway siding on Units 1 and 2.
Without prejudice to the above, it is further submitted that the
Petitioner has submitted the total common cost of “Permanent
Railway Sidings” to be Rs. 35.33 Cr. The Respondent No. 2 has
undertaken a comparison of costs for such Railway Sidings with
other generating plants and it was found that the cost of
railway sidings of the Petitioner are on the higher side. The
comparison of the railway line was carried out with the
following thermal power plants:
a) Chabbra Thermal Power Plant, Phase 1 (Unit 1 & Unit 2) in
Rajasthan.
b) Parli Thermal Power Plant (Unit-6) in Maharashtra
S. No. Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
1 Lanco 35.33 600 0.059
2 Chabbra (Unit 1 & 2)
25.00 500 0.050
3 Parli (Unit 6) 13.35 250 0.053
125 | P a g e
Thus, from the above, it is clear that the cost of railway
sidings as submitted by the Petitioner (LAPL) is around 10% to
18% higher than the plants selected for comparison. Moreover,
since the railway sidings once commissioned would also be useful
to the subsequent units, the cost of construction of railway sidings
should be shared between the subsequent units in proportion to
the capacity of the respective units.
In this regard, reference may also be placed on the Order
passed by the Rajasthan State Electricity Regulatory Commission.
The Rajasthan State Commission vide its tariff Order dated 6th
June 2013 while approving the capital cost for Chabbra Thermal
Power Plant (Unit-I & II), has shared the cost of railway sidings
between phase –I (Unit-I and Unit-II) and phase – II (Unit-III and
Unit-IV) of the project. The relevant extract of the Order dated 6th
June 2013, has been provided below:
“5.30 As already discussed in detail vide para no. 3.7 of
Order dt. 13.06.2011, half of the cost of railway siding
amounting to Rs.25 cr., which is common to phase-1 & 2
is reduced from the capital cost.”
Further, in the case of Parli Thermal Power Plant, the
generating company had initially submitted Rs. 26.69 Cr. as the
cost of railway sidings for Unit - 6. However, upon a direction by
the Maharashtra Electricity Regulatory Commission, it was
required to segregate the aforementioned cost into Unit - 6 and
126 | P a g e
Unit – 7, in the equal proportion. Relevant extract of the Order
passed by the Maharashtra State Commission dated 21.10.2009 is
provided below:
“38. The Commission asked MSPGCL to clarify whether
the actual cost for Parli Unit includes come common
facilities for the other Unit yet to be commissioned at
Parli and directed MSPGCL to segregate costs for such
shared facilities amongst various Units. MSPGCL, in
responses, submitted the details of sharing of common
costs as under:………”
Similarly, the water intake for all the Units 1 to 6 will be
from Hasdeo River at a distance of 4 Km from the Korba
Generating Station of the Petitioner. While, the approval from
the authorities for such water intake is to be obtained
separately for many of the units, the water pumping and water
intake system can be commonly used for all the generating
units. It is imprudent on the part of the Petitioner to have
independent water intake and water pumping system as well as
water pipeline from the Hasdeo River for each of the generating
units.
Without prejudice to the above, it is further submitted
that the Petitioner has submitted that the cost of water supply
system to be Rs. 102.90 Cr. for both the units taken together.
However, the Respondent No. 2 would like to place for
127 | P a g e
consideration of this Hon’ble Commission a comparative
analysis undertaken by it with the power project of the
Petitioner and other generating plants, namely, (a) Sagardighi
Thermal Power Plant in West Bengal; and (b) Chabbra Thermal
Power Plant in Rajasthan:-
S. No.
Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
1 LAPL Unit -1 62.07 300 0.207
2 LAPL Unit -2 40.83 300 0.136
3 Sagardighi Unit 1 & 2
87.60 600 0.146
4 Chabbra Unit 1 24.73 250 0.099
5 Chabbra Unit 2 24.92 250 0.100
From the above, it is apparent that the cost of water
treatment facility in the Petitioner’s power project is
significantly higher than other projects and thus the
Commission ought to conduct a detailed prudence check on the
same. Further, it may also be noted that in the case of Chabra
Thermal Power Plant, the initial cost of water system was
stated to be Rs. 70.92 Cr.
The Rajasthan State Commission had, inter-alia, observed
that the same could be used in the subsequent units i.e. Units 3
& 4, as well. Accordingly, the Rajasthan State Commission
directed sharing the aforesaid cost in the ratio of 70:30 and
based thereon it finally arrived at the cost of Rs. 49.65 Cr for
128 | P a g e
Units 1 & 2. The relevant extract of the Order dated 6th June
2013 is reproduced herein below:
“5.31 Regarding the cost of water conductor system, which is
common for Phase-1&2, the Commission has considered
sharing of the cost in the ratio of 70:30 between Phase-1 and
Phase-2.”
Further, as the generating units are being established on
a contiguous land, the Switchyard for Interconnection and
evacuation of power from all the generating units can be the
same. It is imprudent for the Petitioner to establish a separate
Switchyard for Units 3, 4, 5 and 6 independent of the existing
Switchyard for Units 1 and 2. There will be an increase in the
Bay for the existing Switchyard for the purpose of Units 3, 4, 5
and 6. There is no need for the Petitioner to establish a
separate Switchyard. Again, the facilities such as residential
colonies, maintenance of such facilities, township facilities,
road, street lighting, security etc are to be commonly
maintained for all the generating units thereby reducing the
cost of each generating unit in the proportion to their
generation capacity. Unit No. 2 with 300 MW capacity out of
3240 MW can be related to not more than 10% of such overall
cost for all the generating units. The same would be the
position in regard to other facilities such as ash dyke, ash
disposal system, administrative and other general buildings,
129 | P a g e
coal handling system, air conditioning and ventilation system,
compressor system, fire fighting system, repair and
maintenance workshop, cooling towers, rain water harvesting,
roads and drainage etc.
The Petitioner has submitted the cost of Switchyard to be
Rs. 59.31 Cr. and Rs. 63.33 Cr. for unit-I and unit-II, respectively.
The comparison of the same has been done with the following
plants, namely, (a) Paras Thermal power plant (unit-3) in
Maharashtra; and (b) Parli Thermal power plant (unit-6) in
Maharashtra
S. No.
Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
1 LAPL Unit -1 59.31 300 0.198 2 LAPL Unit -2 63.33 300 0.211
3 Paras Unit 3 28.15 250 0.113 4 Parli Unit 6 48.35 250 0.193
Thus, it is apparent that the cost of switchyard for unit-2
of the Petitioner is also substantially higher than the other
plants.
Accordingly, it is wrong on the part of the Petitioner to
allege that there are no shared or common facilities and each of
the facilities mentioned herein above established for Units 1
and 2 are totally independent and separate for the facilities to
130 | P a g e
be established for Units 3, 4, 5 and 6. In any event, such an
action on the part of the Petitioner is totally imprudent and
contrary to the practice adopted in establishing the generating
units. Respondent No. 2 and the consumers in the State of
Haryana cannot be called upon to pay for such imprudent act
on the part of the Generating Company.
The Respondent No. 2 would also like to place for the
consideration of this Commission a comparative analysis with
respect to the costs for Ash Handling System, Switchyard, Land
and Coal Handling Plant submitted by the Petitioner and other
generating stations to bring out the inconsistencies and higher
costs assumed by the Petitioner. The Petitioner has submitted
the cost of ash handling plant to be Rs. 151.81 Cr. in aggregate
for unit-1 and unit-2 of the power plant. This comes out to be
Rs. 0.253 Cr. per MW. The comparison of the same has been
done with the other plants and it was observed that the cost for
Ash Handling System is much lower in other thermal power
plants. Following plants have been selected for the comparison:
a) Sagadighi Thermal Power Plant in West Bengal (Unit 1
& 2)
b) Paras Thermal Power Plant (Unit-3)
c) Parli Thermal Power Plant (Unit-6)
131 | P a g e
S. No.
Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
1 LAPL Unit -1 80.69 300 0.269
2 LAPL Unit -2 71.12 300 0.237
3 Sagardighi Unit 1 & 2 10.00
600 0.017
4 Paras Unit 3 21.30 250 0.085
5 Parli Unit 6 47.21 250 0.189
It is therefore apparent that the cost of ash handling
plant is substantially higher than the corresponding cost of
other generating stations. Thus this Commission ought to
conduct the prudence check in Order to arrive at the
reasonable cost of this component. It is further submitted that
in the case of Paras Thermal Power Plant, the cost of ash
handling system for unit – 3 was stated to be Rs. 29.11. Cr.
However, upon the direction of the Maharashtra State
Electricity Regulatory Commission vide Order dated 15.12.2009,
the aforementioned cost was segregated into unit-3 and unit-4
and finally the approved cost for Unit – 3 came to Rs. 21.30 Cr.
In so far as the cost of land is concerned, it is submitted
that the Petitioner has submitted the cost to be Rs. 62.05 Cr. for
both the units taken together. The Respondent No. 2 has
undertaken a comparison of the cost of land with that of
Sagardighi Thermal Power Plant in West Bengal. The
comparison is as given below:-
S. No.
Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
132 | P a g e
1 LAPL Unit -1 33.11 300 0.110
2 LAPL Unit -2 28.94 300 0.096
3 Sagardighi Unit 1 & 2 48.00
600 0.080
On the instant issue of cost of land, it is submitted that as
the land would be useful to the subsequent units as well, the
cost of construction of land should be shared between the units
in proportion of the capacity of each unit.
It is further submitted that the Petitioner has submitted
the cost of coal handling plant to be Rs. 151.47 Cr. and Rs.
115.74 Cr. for unit 1 and unit 2. The Respondent No. 2 has
undertaken a comparison of the same with the following plants:
a. Sagardighi Thermal power plant in West Bengal
b. Paras Thermal power plant (unit-3) in Maharashtra
c. Parli Thermal power plant (unit-6) in Maharashtra
S. No.
Name of the Plant
Cost (Rs. Cr.)
Capacity (MW)
Per MW Cost (Rs. Cr.)
1 LAPL Unit -1 151.47 300 0.505 2 LAPL Unit -2 115.74 300 0.386
3 Sagardighi (Unit 1 & 2)
211.09 600 0.352
4 Paras Unit 3 53.30 250 0.213 5 Parli Unit 6 34.69 250 0.139
133 | P a g e
From the above comparison, it is apparent that the cost
of coal handling plant of the Petitioner/Lanco is substantially
higher than the other power plants.
It is further submitted that the Report submitted by E&Y
has not verified the coal and secondary fuel purchase bills for
the verification of sources as well as the cost of the landed coal
and secondary fuel oil. Moreover, the consultant has not
verified the laboratory report for verification of GCV of the
landed coal. The Petitioner ought to be directed to submit the
aforementioned documents forthwith.
The Coal Handling Plant is common for Units 1 & 2.
However, no information or details have been provided for the
quality and quantity of coal used in Unit 1 and Unit 2,
separately. Only upon such information being provided, it
would be clear as to the amount of coal required for achieving
the station heat rate, which in-turn would have revealed the
impact on the cost of coal. It is further submitted that the
Petitioner has not given any details or information with regard
to the excessively high transportation cost of Rs. 570/metric
cube for e-auction coal. Accordingly, the Petitioner should be
directed to give the necessary details forthwith.
134 | P a g e
The Consultants E & Y has not examined any of the above
aspects despite the Memorandum filed by Respondent No. 2
before this Commission on 1st April 2014. The E & Y
Consultants have also not gone into the comparison of the
project cost claimed by the Petitioner with other projects in a
proper manner.
In the proceedings on 25th March 2014 also this
Commission had specifically referred to the aspects of railways
siding, railway lines etc being common to the entire station of
1920 MW. If so, the proportionate share of Unit 2 of Lanco
Power Station would work out only to approximately 14.6% and
the common assets cannot be considered for Unit 2 beyond the
above percentage. The table of apportioning common assets in
the report is also on assumption and presumptions etc and not
by verification of the data by an independent financial
consultant for which purpose E & Y was appointed.
The capital cost determination would include the
apportionment of the cost of shared assets (assets commonly
used for other and all units) and also an adjustment to be given
for sale revenue pertaining to Unit 2 prior to the COD.
The in-principle capital cost approved, as per DPR for unit
2 was Rs 1340.041 Crore. It is incumbent on the Petitioner to
establish to the satisfaction of the Commission for allowance of
135 | P a g e
an increase over the in-principle DPR cost of Rs 1340.041
Crores. A comparison of the original cost as per the DPR along
with the revised estimated capital cost submitted by the
Petitioner is being given below:
Sl No Particulars Original Cost as per DPR
Revised Project Cost
Variation of original DPR and revised
cost
Audited Project Cost as on 06 May 2011
1 Land 12 12 -
1,311,89
2 EPC Cost -
Off shore CIF supplies 470.2 448.39 (21.81)
On shore ex works supplies
226 231.93 5.93
Engg, transport., testing and Comm.
110.8 113.31 2.51
Civil and construction work
198 267.53 69.53
3 Non EPC Cost (Including land development)
92 112.36 20.36
4
design, engineering, construction, supervision & pre-operative expenses
28.5 58.32 29.82
5 Tools and spares 2 2 -
6 Preliminary expenses 2.5 1.14 (1.36)
7 Start up fuel 11 11 -
8 Training of O&M staff 1.2 1.2 -
9 Financial charges including up-front fees
11.7 14.28 2.58
10 Interest during construction
138.82 224.29 85.47
11 Physical contingencies
11.1 0 (11.10)
12 Margin money for working capital
24.22 24.22 - 24.22
Total 1,340.04 1,521.97 181.93 1,356.11
In case of on-shore ex works supplies, the variation of Rs.
5.93 has been on account of the extra spares for critical spares
and special tools & plants for maintenance. However, it is
136 | P a g e
submitted that the above spares should be part of O&M
expenses as they are meant for maintenance of plants. In any
event, this Commission ought to allow maintenance spares
strictly in accordance with the applicable regulations.
The Petitioner has increased the scope of the civil and
construction works by Rs. 69.53 Cr. The Petitioner has also
increased the scope of non EPC contract by Rs. 20.35 Cr.
However, there has been no cross-verification and this
Commission ought to cross-verify the extended scope in Order
to ascertain that they were not originally part of the actual DPR.
Moreover, necessary prudence check may also be carried out
by this Hon’ble Commission to ascertain whether the additional
scope of work is actually required. The Respondent No. 2 would
further submit that the Petitioner should be directed to submit
the copies of contract/work Order awarded to different
agencies for this work.
The Petitioner has also increased the design, engineering,
construction, supervision & pre-operative expenses by Rs. 29.82
Cr. on account of increase in price levels. The Respondent
submits that the same ought to be disallowed as the increase in
price was principally due to the delay in CoD, solely attributable
to the Petitioner.
137 | P a g e
Further, as per the certificate by the statutory auditor, the
Petitioner had submitted that the actual capital cost as on 06th
May 2011 was Rs. 1356.11 Cr. However, no detailed breakup of
the capital cost is provided. Thus, the Respondent No. 2 would
further submit that the Petitioner be directed to submit the
detailed capital cost as on CoD so that the variation in the
estimated and actual capital cost can be understood.
In the earlier proceedings leading to the passing of the
Order dated 17.10.2012, the Commission had taken the total
capital cost as Rs 1340.04 Crores only, in view of the failure and
default on the part of the Petitioner to give particulars of the
capital cost in spite of the specific objections taken by the
Respondent and in spite of the opportunity given by the
Commission.
In the Order dated 3rd January 2014, the Hon’ble
Appellate Tribunal has decided that the Petitioner can furnish
the particulars with necessary documents in support of its claim
for the capital expenditure claimed in excess of Rs 1340.041
Crores. The claim now made by the Petitioner is for a capital
cost of Rs 1668.37 Crores. This is to be justified by the
Petitioner with satisfactory evidence and details to be given.
The Petitioner has still not given the proper details and
evidence in support of Rs 1668.37 Crores.
138 | P a g e
In addition to the above, the Petitioner was to give
details of the Sale of Power prior to COD pertaining to Unit 2.
The annual accounts of the Petitioner indicate a total sale of Rs
1889.10 Crores during the period 2009-10 to 2010-11. In
addition, there was a sale of infirm power from 1st April 2011
to 6th May 2011 for which details have not been provided. This
includes revenue from infirm power and UI charges from Unit 1
and 2. Admittedly, the Petitioner has accounted for a specified
amount to be adjusted for Unit 1 in the proceeding before the
Madhya Pradesh Electricity Regulatory Commission.
Accordingly, the balance pertains to Unit 2. Despite
opportunities given, the Petitioner has not provided the break-
up of Rs 1889.10 Crores. In view of the failure of the Petitioner
to provide such details, adverse inference needs to be drawn
against the Petitioner to the effect that much more than Rs 311
Crores proposed by the Petitioner, needs to be adjusted in the
capital expenditure for revenue from infirm power and UI
Charges. As mentioned herein above, the adverse inference
needs to be drawn against the Petitioner to the above effect for
not furnishing the details of infirm power.
It is further submitted that the O&M Expenses for Unit
No. 1 have been approved by the Madhya Pradesh Electricity
Regulatory Commission and therefore O&M Expenses towards
salaries to staff, maintenance of common auxiliaries’ etc need
to be apportioned between Unit Nos. 1 and 2.
139 | P a g e
The Petitioner is not entitled to any IDC and IEDC or cost
overrun on account of any alleged Force Majeure conditions.
The Petitioner has to either accept the Order dated 2nd
October 2011 in toto wherein the Commission has considered
the China earthquake, Visa issues of the Chinese Personnel as
Force Majeure, mainly in view of the Respondent not replying
to the notice of Force Majeure given by the Petitioner and at
the same time holding that no cost implications will be there
and the Petitioner is entitled only to time overrun. It is not now
open to the Petitioner to seek cost implications. If the
Petitioner wishes to dispute the finding contained in the Order
dated 2nd October 2011, then the entire claim on Force
Majeure for China Earthquake or Via etc need to be examined
on merits, as the Power Purchase Agreement is not applicable
and accordingly the condition of the Respondent disputing the
condition of Force Majeure will not be applicable.
Even otherwise, in the absence of a Power Purchase
Agreement, the only applicable provision is Section 56 of the
Contract Act which relieves the performance of the obligation
during the period of the Force Majeure. There is no higher cost
implication to the non-affected party. The affected party gets
released of the obligations to perform during the period of
Force Majeure. The China earthquake or the visa problems
cannot be a Force Majeure as it did not affect the Petitioner. It
140 | P a g e
was not impossible for the Petitioner to perform the obligations
through alternate means. The issue of Force Majeure or
section 56 would arise only if the performance had become
impossible and not merely onerous or difficult or expensive.
This proposition is well settled and the Respondent No. 2 craves
leave to refer to the same at the time of hearing.
As regards the debt equity, the approved financial
package provided for 80:20. The debt equity ratio to be
adopted is, therefore, 80: 20. The Petitioner cannot be allowed
to claim higher equity of 24.52% instead of 20%.
The repayment of loan should be considered as minimum
amount of depreciation.
The Annual Capacity Charges applicable for 2011-12,
2012-13 and 2013-14 on the above basis, after adjusting for the
infirm power and shared assets need to be considered for the
purpose of the Capacity Charges. Such capacity charges need
to be adjusted in a proportionate manner for PLF as per
Regulations 10 and 11 of the Haryana Electricity Regulatory
Commission Tariff Regulations. In other words, if the Plant
Load Factor achieved is say 40% as against 80% Target
Availability, the above annual capacity charges will be adjusted
by half. In other words, the Petitioner is not entitled to per unit
141 | P a g e
tariff based on Annual Capacity Charges for 80% Plant Load
Factor.
For example, in the petition filed for the FY 2011-12, the
annual capacity charges had been worked out at Rs 318.07
Crores. The Plant Load Factor achieved during this period
including auxiliary consumption is 56%. The annual capacity
charges payable need to be adjusted to Rs 224.12 Crores. The
per unit charge to be paid will be to the tune of Rs 1.30. Similar
would be the calculation for the FY 2012-13, where the annual
capacity charges is Rs 344.31 Crores, the Plant Load Factor
including auxiliary consumption is 40.77% and the per unit tariff
would be Rs 0.90.
The above calculation has been made as an illustration in
regard to the Annual Capacity Charges assuming all the other
claims but not admitted. The other claims need to be adjusted,
namely, total project cost, debt equity ratio, repayment of loan,
interest on working capital, operation and maintenance
expenses etc.
The mere fact that the auditors’ have given a letter as per
the books of account or even when the Auditor duly certifies
the account does not mean that the Commission will not
exercise prudent check. The prudent check need to be applied
by the Commission is to be in detail as higher capital cost would
142 | P a g e
increase the tariff for the consumers at large. The Commission
exercised prudent check in all cases in Order to ascertain not
only the veracity of the claim of the Petitioner/Generating
Company but also to seek whether all such capital expenditure
have been incurred reasonably or prudently. If the Commission
comes to the conclusion after applying the prudent check that
any such capital expenditure, though actually incurred was not
prudent or expedient, such part of the capital expenditure will
have to be rejected. The scrutiny of the capital expenditure by
the Commission is, therefore, an absolute necessity which
cannot be avoided by Petitioner by not giving the requisite
particulars and satisfying the claim. The Regulatory
Commissions have been exercising such prudence checks
including by appointment of consultants and through
verification by the staff of the Commission. It is, therefore, not
correct on the part of the Petitioner to seek admission of the
capital expenditure incurred only on the basis of auditor’s
certificate.
The prudence check is also required to be undertaken by
the Commission in Order to determine whether any part of the
capital expenditure involve minor assets or assets not relevant
for the generation of electricity. Accordingly, the expenditure
being supported by accounting vouchers for the purpose of the
Companies Act is not sufficient. The Generating Company is
143 | P a g e
required to establish to the satisfaction of the Commission the
need for capital expenditure, incurring of such capital
expenditure in a structured manner and the total expenditure
being reasonable and just.
While deciding the capital cost, the entire infirm power
including the power sold under Unscheduled Interchange prior
to the Commercial Operation Date i.e. the date from which the
Petitioner is supplying power to the answering Respondents in
pursuance to the earlier Order dated 2.2.2011 passed by this
Commission need to be deducted. As per the financial
statements of Lanco filed for the year ended 31.3.2009, for the
period 2009-10 and for the period 2010-11, the sale of power
from Units 1 and 2 before the declaration of the date of
commercial operation aggregate to Rs. 1889.10 crores. In
addition, there has been sale of infirm power during the period
1.4.2011 to 6.5.2011 the details whereof has not been disclosed
by Lanco. In the Financial Statements providing for the income
from sale of electrical energy, Lanco has not given the details of
the break-up of the above, namely, what part of the sales
pertain to Unit 1 and what part pertains to Unit 2.
It is, therefore, incumbent for Lanco to give details of the
sale of infirm power and sale of power under Unscheduled
Interchange Charges, namely, the aggregate quantum of such
sale both from Units 1 and 2 and out of the above, the amount
144 | P a g e
realised from the sale of infirm power and Unscheduled
Interchange Charges considered for reduction of the capital
cost of Unit No. 1. The balance after adjustment for Unit 1 held
to be accounted as pertaining to Unit No. 2. This revenue needs
to be adjusted for reduction in the capital cost for the purpose
of determining the cost to be considered for tariff. The
deduction of revenues from infirm power/UI Charges from the
capital cost is a significant aspect of capital cost determination
and the benefit of the same should go to the consumers in the
State of Haryana. The Hon’ble Commission may, therefore,
direct a detailed investigation into the quantum of infirm power
sold by Lanco from Amarkantak Project, verification of the
above quantum vis-a-vis Unit 2 and then determine the
reduction in the capital cost pertaining to Unit 2. In the facts
and circumstances of the case the submissions of Lanco on the
quantum of sale of infirm power at Rs. 311.60 crores is
erroneous.
The approved financial package of the project
admittedly, is 80% debt and 20% equity. Accordingly, the
capital cost duly scrutinised subject to prudent check and
approved, will have to be apportioned in the form of debt to
the extent of 80% and equity to the extent of 20%. It is not
open to Lanco to claim equity to be at 24.52% when the
approved financial plan for equity is only 20%. The excess of
145 | P a g e
equity above 20% should be treated as notional loan and not as
equity. Accordingly, the tariff filing made by Lanco on the basis
of apportionment of the debt and equity in the ratio of 75% -
25% is wrong. The entire tariff calculation based on the above
wrong differentiation and equity ratio assumed by Lanco is
defective and needs to be rejected. Once the capital cost
determined as per prudent check and infirm power and UI
revenues are deducted, the cost is apportioned in the debt
equity ratio of 80% - 20%, the return of equity is to be
restricted to 20% of the capital cost. The balance 80% will have
to be serviced as borrowings/loan.
In terms of the Tariff Regulations, 2009 of the Central
Commission the servicing of the loan is equated with the
depreciation amount and on a normative basis. The actual
repayment of loan or the terms and conditions entered into by
Lanco with its Lenders on repayment of loan are not relevant.
What is, however, relevant is the interest to be calculated on
the normative repayment i.e. on reducing balance as per the
normative repayment at the weighted average of the actual
interest paid to the Lenders. Accordingly, Lanco is required to
give the details of the depreciation claimed by Lanco, its
apportionment to the capital cost of Unit 2 from the beginning.
Any depreciation taken by Lanco on or after 1.4.2009 will be
treated as normative repayment to the banks. The interest for
146 | P a g e
the subsequent period will have to be determined after
adjusting the normative repayment. Lanco has not given such
particulars in Order to determine the normative loan,
depreciation adjusted and the balance to be serviced from time
to time.
In the Order dated 2.2.2011 this Commission while
dealing with the Force Majeure pleaded by the Petitioner
specifically rejected the claim for compensation in terms of
tariff hike i.e. IDC and IEDC specifically holding as under:
“A perusal of the above provision makes it clear that in
an event of Force Majeure the parties are entitled for
some relief in terms of extension in time for carrying out
their respective contractual obligations. As far as the
issue of compensating (in terms of tariff hike) for any
consequential appreciation in Capital Cost is concerned,
the Commission could not find any enabling provision in
the PSA/ PPA. Hence the second issue of whether any
relief other than extension in time due to any Force
Majeure event is admissible is answered in negative i.e.
no relief other than extension in time as explicitly
provided in the PSA/PPA is admissible.”
The above decision of this Commission was not
interfered with by the Hon’ble Appellate Tribunal for
Electricity in the judgment and Order dated 3.1.2014. In
view of the above, the Petitioner cannot claim either IDC or
147 | P a g e
IEDC or any other compensatory payment by way of cost
overrun or time overrun on account of the delay resulting
from the alleged Force Majeure Event of earthquake in
China or the Visa Policy of the Government of India. This
issue stands settled and cannot be re-opened at this stage.
It is, however, submitted that the alleged reasons, namely,
earthquake in China and Visa Policy of the Government of
India are not Force Majeure making it impossible for Lanco
to complete the construction of Unit No. 2. In particular,
the Visa Policy of the Government of India cannot be
construed as Force Majeure as sufficient manpower has
been available in India for commissioning Unit No. 2. The
claim for IDC and IEDC i.e. time overrun and cost overrun
can be considered only in regard to the matters other than
those resulting from the alleged Force Majeure Event. The
allegations to the contrary are wrong and are denied.
A perusal of the documents on record, as filed by
the Petitioner clearly show that the claim of the Petitioner
for the delay in the commissioning is only on account of
Force Majeure Event of earthquake in China in May 2008.
The other reason given for the delay in the Lenders
Engineers Report is that the commissioning was delayed
due to the usage of rotor of Unit No. 2 in Unit No. 1
allegedly to optimise the commissioning time of the unit.
This cannot be a ground for claiming the cost overrun in
respect of Unit No. 2. Any claim on account of excess
expenditure should be entirely to the account of Unit No. 1
and no part of such expenditure should be added on to Unit
no. 2. Furthermore, the allegation of Force Majeure of Visa
Policy of the Government of India not permitting the
Chinese workforce has been raised, as an afterthought.
148 | P a g e
The Fixed Charges as per the Tariff Regulations,
2009 determined based on the capital cost will be on an
annual basis and thereafter apportioned 1/12th for each
month. The fixed charges claimed by Lanco in the petition
are varying from month to month and that also significantly.
This is not in accordance with the Tariff Regulations, 2009.
The annualized fixed charges need to be determined and
then divided into monthly fixed charges on mathematical
basis for recovery purposes. The scheme adopted by Lanco
in determining the fixed charges on month-wise basis is
completely contrary to the Tariff Regulations, 2009. Further,
in terms of the Tariff Regulations 2009 the fixed charges
need to be proportionately reduced for the targeted plant
load factor not achieved. It is further submitted that
pursuant to the site visit undertaken on 16-17th August
2014 and as recorded in the letter dated 20.08.2014 issued
by the Director, Tariff of this Commission, it was noted that
Long Term Open Access and connectivity for evacuation of
power from Petitioner’s Unit – 2 was still not in place. In the
circumstances, it is submitted that the implemented
schedule of power shall be taken as per availability at the
State’s Periphery and not on declared availability of the
Petitioner’s plant for payment/billing purposes. Suitable
directions in this regard need to be issued by on this by the
Commission.
The interest on working capital to be determined is
on normative basis. The reference to the period to be taken
for the purpose of actual consumption, coal price etc is
January 2009 to March 2009. Once the interest on working
capital is determined on a normative basis, the actual
amount of capital employed by the generating company
from time to time in regard to the coal consumption etc. is
149 | P a g e
totally irrelevant. The interest on working capital is not
dependent on the actual working capital incurred by the
generating company irrespective of whether the generating
company incurs the working capital or not, the normative
working capital as determined under the Regulations is
alone admissible. In the present case, the claim of Lanco of
different working capital every month or on the basis of coal
value being more in certain months is contrary to the Tariff
Regulations, 2009.
In addition, Lanco has not given details as to why the
coal consumption in a particular month is of higher value.
In any event, the Tariff Regulations, 2009 having provided
for the interest on working capital to be determined on a
normative basis, it is not open to Lanco to claim interest on
working capital allegedly on the actual working capital
incurred by it and that too on month to month basis. The
interest on working capital needs to be uniform throughout
the tariff period of 2009-14.
The Operating and Maintenance Expenses need to
be ascertained in terms of Tariff Regulations, 2004 based on
the capital cost finally determined by the Commission.
Under the Tariff Regulations, 2009, the O & M Expenses are
on normative basis and need to be allowed. Any claim on
the part of Lanco contrary to the above is wrong.
As regards the coal, the Respondent had agreed to
purchase power from the second unit of Lanco Project
based on the coal linkage which Lanco had from Coal India
and/or its subsidiary. It is the obligation of Lanco to arrange
for the above coal. Lanco cannot demand energy charges
based on any coal used by it other than through
150 | P a g e
procurement of coal under a regular Fuel Supply Agreement
with Coal India and/or its subsidiary.
In the circumstances mentioned herein above, the
claim of the Petitioner for the project cost needs to be
rejected. In view of the conduct of the Petitioner of
concealing various facts and not approaching this
Commission in a clean and transparent manner, adverse
inference needs to be drawn against the Petitioner and
there should not be any change in the project cost as
determined by the Commission in the earlier Order dated
17.10.2012.
In addition to the above the Ld. Counsel raised the
issue that the officers of the Commission also undertook
site visit along with HPPC and E&Y hence in terms of HERC
Regulations, they should have filed a report along with a
copy to the parties.
Per Contra, the Ld. Advocate for LAPL Shri Sanjay Sen argued at length rebutting the averments made by the Respondent (HPPC). At the outset he reiterated that E&Y was appointed by the Commission after obtaining consent of HPPC and after hearing the parties. Hence he has no further submissions to make in this regard. On the issue of Officers of this Commission filing a report regarding the site visit undertaken by them, he brought to the notice of the Commission Clause 97 of the Electricity Act, 2003 i.e. “97. The Appropriate Commission may, by general or special Order in writing, delegate to any Member, Secretary, Officer of the Appropriate Commission or any other person subject to such conditions, if any, as may be specified in the Order, such of its powers and functions under this Act (except the powers to adjudicate disputes under Section 79
151 | P a g e
and Section 86 and the powers to make regulations under section 178 or section 181) as it may deem necessary”. Thus, this Commission having once delegated the work of independent capital cost verification to E&Y cannot delegate the same task again to the officers of the Commission. In reply to the affidavit of objection dated 08.09.2014 filed on behalf
of the Respondent No.2 (‘HPPC’), the Petitioner, by way of a written
reply, submitted that the same ought not to be taken on record
inasmuch as the affidavit of objection dated 08.09.2014 has been filed
in utter violation of the Order dated 28.07.2014 of this Commission. It
was submitted that this Commission vide its Order dated 28.07.2014
had given HPPC the liberty to file their comments/objections to the
addendum dated 04.08.2014 to the report dated 08.07.2014 filed by
Ernst and Young (‘E&Y’) whereas HPPC mischievously have given their
alleged comments/objections even to the report dated 08.07.2014
filed by E&Y. The limited liberty to file comments/objections to the
addendum dated 04.08.2014 to the report dated 08.07.2014 filed by
E&Y was given by this Commission because this Commission had
already adopted the draft report dated 08.07.2014 filed by E&Y during
the hearing held on 22.07.2014, which is clear from para-4 of the
Order dated 28.07.2014. Accordingly, any comment/objection in
relation to report dated 08.07.2014 filed by E&Y cannot be taken on
record at a later stage when the time for filing the
objections/comments had already expired and is liable to be rejected.
152 | P a g e
“PARAWISE REPLY ON MERITS
1. The contents of para no. 1 are denied being incorrect and misleading,
save and except being matters of record. It is completely misleading to state
that the interest during construction is inadmissible as alleged or otherwise.
2. The contents of para no. 2 are denied being incorrect, false and
misleading. It is wrong and denied that the time period of two weeks given to
HPPC for filing comments/objections to the addendum report dated 04.08.2014
commenced from 23.08.2014 as alleged or otherwise. It is reiterated that the
period of two weeks given to HPPC for filing comments/objections to the
addendum report dated 04.08.2014 commenced from 04.08.2014 since the said
report was submitted by E&Y on 04.08.2014 and was forwarded by Hon’ble
Commission to HPPC on the same date and said period of two weeks ended on
18.08.2014. HPPC has mischievously stated two weeks for filing of their
comments/objections commenced from 23.08.2014 when E&Y submitted its
addendum report pursuant to site visit on 16-17.08. 2014 which was forwarded
on 23.08.2014 whereas as per Order dated 28.07.2014 of this Hon’ble
Commission period of two weeks commenced from 04.08.2014 when E&Y filed
its addendum report, copy of which was provided to HPPC on the said date
itself. The report submitted by E&Y pursuant to site visit on 16-17.08.2014 was
as per the Order dated 28.07.2014 passed by this Hon’ble Commission. The
contents of the preliminary objections in this regard may be treated as part and
parcel of the para under reply.
3. The contents of para no.3 are denied being incorrect, false and
misleading. It is submitted that the contents of the affidavit of objections dated
08.09.2014 to the extent of alleged objections in relation to report dated
08.07.2014 and 04.08.2014 are in teeth of directions given by this Hon’ble
Commission to HPPC vide its Order dated 28.07.2014. Accordingly, it is
submitted that the contents of the affidavit dated 08.09.2014 ought not to be
153 | P a g e
considered for the purpose of adjudication of the present tariff proceedings. It
is wrong and denied that there is any inconsistency in any claim made by
Lanco in regard to capital cost or other aspect as alleged or otherwise. It is
wrong and denied that Lanco is concealing any fact or misleading the
proceedings as alleged or otherwise.
4. The contents of para no.4 are denied being incorrect, false, baseless and
misleading. It is wrong and denied that that E&Y has not undertaken the
requisite study and investigation in a professional manner in Order to verify
the admissible project cost for Lanco’s Unit-II as alleged or otherwise. It is
wrong and denied that E&Y have proceeded on a mechanical manner to
approve the claims made by Lanco without investigating into the veracity of
claims as alleged or otherwise. As per the mandate of HERC given vide Order
dated 25.03.2014, E&Y was required to verify the data submitted by Lanco to
HERC and not to compare the said data with other projects, which is apparent
from the ‘scope of services’ detailed in page-6 in the report dated 08.07.2014
of E&Y. It is also wrong and denied that E&Y as an independent chartered
accountant have not applied prudence check while preparing the report dated
08.07.2014. It is wrong and denied that E&Y has not considered the
Memorandum in the form of interrogatories given by HPPC on 01.04.2014.
The fact that E&Y has duly considered the Memorandum in the form of
interrogatories given by HPPC is reflected even in the Order dated 28.07.2014
passed by this Hon’ble Commission. Lanco submitted all documents, data and
information including plant layout to Hon’ble Commission as and when
required for independent cost verification. Admittedly, no direction was given
by HERC to provide any document or information to HPPC. The remaining
contents of the para under reply are denied for want of knowledge.
5. The contents of para no.5 are denied being incorrect, false, baseless and
misleading. It is wrong and denied that E&Y prepared any report in a cursory
manner. It is reiterated that there are no common facilities between Unit-1 and
154 | P a g e
Unit-2 on the one hand and Unit-3 & Unit-4 on the other hand. The basis of
reports of E&Y that there are no common facilities between Unit-1 and Unit-2
on the one hand and Unit-3 & Unit-4 on the other hand is absolutely correct. It
is submitted that there was a site visit Unit-2 of Lanco on 16.08.2014 -
17.08.2014 which was attended by representatives of HPPC, this Hon’ble
commission, E&Y and Lanoc, during which all the members visited each and
every facility of operational Unit 1 &Unit 2 and under construction Unit 3 &
4. The site visit report dated 23.08.2014 of E&Y and the site photographs of
various facilities as enclosed by HPPC as Annexure-7 in their affidavit of
objection dated 08.09.2014 clearly establish the fact that Unit 1 &Unit 2 on
the one hand and Unit 3 & 4 on the other hand have no common facilities. It is
wrong and denied that site visit establishes any falsity of any claim of Lanco
much less the claim in relation to claim of common facilities between Unit-1
and Unit-2 on the one hand and Unit-3 & Unit-4 on the other hand.
6. The contents of para no.6 are denied being incorrect, false and
misleading. That with a sole intention to delay the tariff adjudication process of
Unit-II, HPPC has been deliberately raising the alleged issue of conflict of
interest whereas there exists none at such a late stage when the Hon’ble
Commission had already decided to adopt the draft report of E&Y in its
hearing held on 22.07.2014. In this regard, it is important to note that as per
the Order dated 25.03.2014 of this Hon’ble Commission, the Independent
Chartered Accountant was supposed to be one neither connected to Lanco
Amarkantak Power Limited nor to HPPC. Admittedly, E&Y was in no manner
connected either to Lanco Amarkantak Power Limited or to HPPC. Further,
admittedly no direction was given to E&Y to file any affidavit to that extent.
The letter dated 29.04.2014 of HPPC was addressed to the Hon’ble
Commission which in its wisdom chose E&Y on the condition that it had no
conflict of interest with Lanco Amarkantak Power Limited.
155 | P a g e
The relevant portion of the Order dated 25.03.2014 is reproduced herein
below:
“Thus, all such data, as agreed by both the parties, would have to be
independently verified and smoothened out by an independent Chartered
Accountant (including physical verification) having exposure in power
sector preferably large power plants and not in any way connected to
either LAPL and/or Haryana Power Utilities.”
It is submitted that on 20.05.2014, a hearing was called by this Hon’ble
Commission vide its notice by its e-mail dated 16.05.2014, wherein the
representatives of E&Y, Lanco and HPPC unequivocally agreed that they do
not have any objection in the engagement of E&Y as an independent chartered
accountant for verification of the data submitted by Lanco. Also vide same e-
mail dated 16.05.2014, the Hon’ble Commission forwarded the Proposal of
Assignment of E&Y dated 07.05.2014 which contained certification by E&Y
(Before the commencement of the Assignment) stating that “we hereby certify
that none of the team members whose names are mentioned below are currently
associated in any consultancy assignment with the Lanco Group, and hence
there is no conflict of interest with the current assignment. The names of the
team members are:
A. Mayank Bhardwaj B. Amit Kumar Das”
Thereafter, this Hon’ble Commission had engaged E&Y and E&Y commenced
the work as per the assignment. Lanco submitted all the requisite documents
and data as directed by this Hon’ble Commission from time to time. E&Y
submitted its draft report on 08.07.2014 to this Hon’ble Commission which was
subsequently forwarded to both HPPC and Lanco. This Hon’ble Commission
gave sufficient time of one week to Lanco and HPPC to file its
objections/comments, if any to E&Y directly. HPPC did not file its objections
on the E&Y draft report. Thereafter, hearing was held on 22.07.2014, wherein
the Hon’ble Commission had adopted the E&Y draft report and fixed the next
hearing as final hearing on 28.07.2014. In the hearing held on 22.07.2014,
156 | P a g e
HPPC did not raise the issue the issue of conflict of interest of E&Y with
Lanco. Later on, HPPC raised the issue of conflict of interest for the first time
only in their objection dated 25.07.2014 and during the hearing held on
28.07.2014. This clearly shows the dilatory tactics adopt by HPPC to delay the
process of re-determination of tariff.
7. The contents of para no.7 are denied being incorrect, false and
misleading, save and except being matters of record. Apparently, the record of
proceedings dated 28.07.2014 does not contain any direction to E&Y as being
alleged by HPPC in the para under reply. Significantly, the Hon’ble
Commission vide its letter dated 20.08.2014 directed E&Y to file an affidavit
that at the time of award of the assignment there were no conflict of interest.
Admittedly, affidavit to the extent of direction of this Hon’ble Commission
given in its letter dated 20.08.2014 has been filed by E&Y on 25.08.2014.
8. The contents of para no.8 are denied being incorrect, false and
misleading, save and except being matters of record. It is wrong and denied
that E&Y failed to file any affidavit as alleged or otherwise. It is wrong and
denied that E&Y has not made adequate disclosure of conflict of interest. In
this regard, it is important to note that as per the Order dated 25.03.2014 of
this Hon’ble Commission, the Independent Chartered Accountant was supposed
to be one neither connected to Lanco Amarkantak Power Limited nor to HPPC.
Accordingly, E&Y filed an affidavit dated 25.08.2014 stating that it had no
conflict of interest with Lanco Amarkantak Power Limited at the time of
awarding of assignment by this Hon’ble Commission. It is wrong and denied
that the affidavit of E&Y is contrary to the requirement of this Hon’ble
Commission. The contents of para no. 7 of the present reply is re-affirmed
herein which are not repeated for the sake brevity and prolixity. It is wrong and
denied that the affidavit dated 25.08.2014 cannot be relied upon by this
Hon’ble Commission as alleged or otherwise. It is reiterated that the affidavit
157 | P a g e
dated 25.08.2014 of E&Y is in complete consonance with the direction given by
this Hon’ble Commission. It is wrong and denied that it will not be appropriate
for the Hon’ble Commission to proceed on the basis of reports submitted by
E&Y as alleged or otherwise. It is wrong and denied that any reading of the
affidavit dated 25.08.2014 shows that E&Y is hiding behind any technicality or
is concealing any conflict of interest as alleged or otherwise. It is submitted
that E&Y themselves in their affidavit has categorically clarified that there is
no conflict of interest with Lanco Amarkantak Power Ltd. It is wrong and
denied that E&Y have deliberately not dealt with documents filed by HPPC
along with affidavit dated 25.07.2014. There is no mandate of this Hon’ble
Commission to E&Y to consider the documents filed by HPPC on 25.07.2014,
which admittedly is objection to the report dated 08.07.2014 of E&Y. HPPC is
raising false, frivolous, meaningless and unsustainable objections with a sole
intention to delay the re-determination process which act is completely
contrary to the mandate of the Hon’ble APTEL given vide judgment dated
03.01.2014 in Appeal No. 65 of 2013.
9. The contents of para no.9 are denied being incorrect, false and
misleading, save and except being matters of record. It is wrong and denied
that there is any inconsistency in the claim of Lanco in relation to no common
or share assets between Unit-I&II on one hand Unit-3 & 4 on the other hand.
a). Layout- The contents of para no.9 (a) are denied being incorrect, false
and misleading, save and except being matters of record. It is submitted that a
coloured copy of Combined Layout Plan was handed over to HPPC during
their site visit in which the facilities of Unit 1 & 2 and Unit 3 & 4 are
demarcated. Also the representatives of HPPC, Hon’ble commission, E&Y and
Lanco together during the site visit on 16-17.08.2014, had physically verified
the facilities of the entire plant and it was established that there are no common
facilities between Unit 1 & Unit 2 on one hand and Unit 3 & 4 on the other
hand. A site visit report of the independent chartered accountant, E&Y also
158 | P a g e
clearly establishes the facts that common facilities of Unit 1&2 in Operation
and Unit III&IV under construction are separate and not common in any
manner whatsoever. It is wrong and denied that layout plan has not been
properly marked/labelled as alleged or otherwise.
b). Land- The contents of para no.9 (b) are denied being incorrect, false,
baseless and misleading. It is wrong and denied that that the land of Unit-1 &2
is not properly demarcated as alleged or otherwise. It is wrong and denied that
the land of Unit 3 & 4 cannot even be separately identified as alleged or
otherwise. It is wrong and denied that any part of land of Unit-3 & 4 has been
used for Unit 3 & 4 as alleged or otherwise. It is denied that geographical
coordinates of main plant lies inside the land of Unit 2. It is submitted that
Unit II has been built partly on the green belt area for Unit 1. Additional land
has been acquired to leave mandatory green belt for Units 1&2 taken together.
Since 200 acres have been attributed to Unit II and 566.89 acres to Unit 1, the
cost of land considered for Unit 2 is less than half of the total for Units 1 & 2
taken together. In a similar manner, part of the green belt earmarked for Unit 2
has been used for Units 3 & 4. Later an equal amount of the land which was
taken from Unit 2 green belt area for Units 3&4 was transferred back to unit 2
from the land acquired for Units 3&4. Hence, total land allocated to Unit 2
remained 200 acres and no part of that was used by Units 3&4. The same has
been verified by E&Y team during their site visit as per their report dated
23.08.2014
c). Switchyard- The contents of para no.9 (c) are denied being incorrect,
false, baseless and misleading It is submitted that the Switchyard for Unit 1&2
and 3&4 are completely separate. It is denied that the Switchyard of Unit 3&4
is in Unit-2 land. As regard to contention of HPPC for imprudent practice of
different Switchyard in a generating station, it is submitted that Unit 1
(300MW) , Unit-2 (300 MW) and Unit 3&4 (2X660 MW) were conceptualised,
159 | P a g e
appraised and executed at different period of times and are of different
capacities, hence they were not planned and constructed simultaneously. There
was a gap of 4-6 years between Planning and Execution of Unit 1&2 and Unit
3&4. HPPC has accepted in its objections filed before the Hon’ble Commission
that the switchyard and transmission lines for operational Unit 1&2 are
separate from the proposed switchyard and transmission lines of under
construction Unit 3 & 4. Hence the contention of HPPC that Lanco has not
applied/exercised proper prudence is wrong, baseless and misleading.
d&e) Ash Pond: The contents of para no.9 (d & e) are denied being incorrect,
false, baseless and misleading It is submitted that the Ash Pond of Unit-I&II
and Unit III&IV are separate and accordingly it has been located in the layout
plan of Unit I&II and Unit III&IV and the same was clarified/shown in the
layout as well as physically to the representatives of HPPC during the site visit.
It is contrary to the fact that location of a separate Ash Pond was not provided
in the layout plan of Unit I&II and Unit III&IV. As regards the statement
mentioned by HPPC in its objection, from the MoEF issued Environment
Clearance of Unit-III related to Ash Disposal, it is submitted that the same was
issued in line with the disposal of bottom ash in lean slurry form and fly ash in
dry form. It is clarified that the State Pollution Control Board while issuing the
Consent to Establish of Unit- III&IV had imposed the condition of High
Concentration Disposal System (HCSD). Accordingly, HCSD is proposed to be
adopted for Unit III&IV. The Ash disposal System of Unit-I&II (Lean Slurry
System) and Unit III&IV (High Concentration Slurry Disposal System) being
different in nature/specifications, the ash generated from Unit I&II and that
from Unit III&IV cannot be disposed in one pond. Hence, it would be grossly
incorrect to state that Unit III&IV Ash will be used in Unit-I&II Ash Pond and
accordingly the allegation of HPPC is denied as baseless and misleading.
160 | P a g e
f) Boundary Wall: The contents of para no.9 (f) are denied being incorrect,
false, baseless and misleading It is submitted that additional boundary wall
created for Unit II has been charged to it. Part of this boundary wall has been
dismantled to enlarge the plant area to include Units III&IV. Boundary wall for
the enlarged plant has been charged to the Units III&IV. Hence there is no
case for reduction in cost of assets charged to Unit II on this account. The same
has been verified by E&Y during their site visit on 16/17.08. 2014 and reflected
in their site visit report dated 23.08.2014.It is also stated that the total land
allocated to Unit II is 200 acres and cost of the same land is charged in Unit-
II.
g) Colony: The contents of para no.9 (g) are denied being incorrect, false,
baseless and misleading It is submitted and that there are sseparate colonies
for Unit-I&II and Unit III&IV. The colony of Units I&II is at the land of Unit I.
Separate land has been identified at different location for the Colony of Units
III&IV, which is Govt. Land and currently is in the process of transfer to
Lanco.
h) Water Intake System: The contents of para no.9 (h) are denied being
incorrect, false, baseless and misleading During the site visit, it was
established that there is a separate Water Intake System for Unit-II (under
service) and Unit III&IV (under construction) at different locations. Being
different Unit sizes and location of intake system, there is no possibility of
having common pipeline for Units-I&II ( under service) and Units III&IV
(under construction). Also it would be misleading to state that it is imprudent
to have separate reservoir, separate raw water pump house and separate
water-pipeline for respective Units although HPPC is aware of the fact that
respective Units are of different sizes and also they were conceived, planned,
appraised and executed at different periods of time. The separate raw water
intake system for Units-I&II and Units III&IV are clearly indicated in
161 | P a g e
Annexure-7 (Page No. 69 and 70) of site photographs as enclosed by HPPC in
its affidavit of objection dated 08.09.2014
i) Raw Water Reservoir: The contents of para no.9 (i) are denied being
incorrect, false, baseless and misleading. There is a raw water reservoir for
Unit-I&II inside the plant. It is submitted that as per the water allocation
approval for Unit III&IV from Water Resources Department, Govt. of C.G, it
was mandated that River intake System is to be made by Govt. of C.G to meet
the water requirement in lean season with 3 months water storage capacity.
HPPC during the site visit had physically observed that the same is under
construction at an altogether different location. Also it is misleading to state
that it is imprudent to have separate reservoir for respective Units, in view of
the admitted position that Units having different size were conceived , planned
and executed at different periods of times with a gap of 4-7 years .
j) Railway Siding:- The contents of para no.9 (j) are denied being incorrect,
false, baseless and misleading. From the site visit and the evidence of railway
siding layout submitted by Lanco to the Hon’ble Commission and provided to
HPPC, it is clearly established that there is a separate railway siding for Unit
II and Units III&IV. As far as land utilisation is concerned , it is reiterated that
railway siding of Unit III&IV will not be built in Unit II land. Hence the
question of apportionment based on capacity does not arise at all.
k) Coal Handling Plant (CHP): The contents of para no.9 (k) are denied being
incorrect, false, baseless and misleading. HPPC has clearly stated that the
Coal Handling Plant of Unit III&IV is separate and independent of Units-I&II.
As far as layout is concerned, it is denied that Lanco would use Wagon Tippler
area of Unit II in Units III&IV. It is worth to mention that no wagon tippler
were envisaged for Units-I&II in the coal handling plant scheme. HPPC is
knowingly creating confusion and misleading with the statement of use of
162 | P a g e
Wagon Tippler area of Units-I&II in Units III&IV. Regarding cost of coal
handling plant for Unit I and Unit II. It is admitted position that actual cost as
incurred in the coal handling system of Unit I and Unit II has been booked
separately and comparison of the cost with other power plant is not
appropriate as it depends on various factors such as complete scope of the
system, Plant Layout, make of the equipment manufacturers, quality of coal,
supplier of systems, date of award of contract etc. which varies from plant to
plant.
l) It is denied that the assets mentioned in the objection filed by HPPC are
common or likely to be shared between Units-I&II and Units III&IV. In this
regard, Lanco has already submitted an affidavit as per the direction of
Hon’ble Commission on 09.04.2014, wherein it has been submitted that the
facilities built for operational Units I&II will not be used for under
construction Units III&IV. There is separate Plant entry and roads, drains,
Administrative Building, Service Building, Fire Station for the under
construction Units III&IV. It is submitted that the following facilities will not be
shared with Unit I and Unit II:
i) Existing Roads within the Power Projects of the Petitioner
ii) Administrative Building
iii) Service Building
iv) Fire Station
v) Field Hostel
vi) Drainage System
10. The contents of para no.10 are denied being incorrect, false and
misleading. It is wrong and denied that no satisfactory answer was given in
relation to location of Unit-V & VI. It is wrong and denied that from the layout
plan or even otherwise it seems that the Unit-V & VI will be constructed with
163 | P a g e
Unit-I & II. It is wrong and denied that from the layout plan or even otherwise
it seems that Unit-III &IV is constructed with or is integrated with the Unit-I
&II as alleged or otherwise. It is once again reiterated that 200 Acres of land
allocated for Unit-II has been charged under Unit II. The same has been
verified and confirmed in the site visit report of E&Y dated 23.08.2014. HPPC
is misleading the Hon’ble Commission by making wrong statements. It would
be absurd to state that land currently acquired for Unit I&II and Unit III&IV
can be used for the construction of Unit V&VI.
11. The contents of para no.11 are denied being incorrect, false and
misleading, save and except being matters of record. It is submitted that there
are no common facilities between Units-I & II on the one hand and Units-
III&IV on the other hand. Further, there will be no common facilities between
Units-I & II on the one hand and Units-V & VI (in case planned in future) on
the other hand. The contention of HPCC that generating station of Lanco was
conceived with 1920 MW capacity is completely baseless and misleading. It is
submitted that Units III & IV (2X660MW) are being set up separately from
Unit-I & Unit-2 and the said Units are in construction phase and are expected
to be commissioned in FY 2014-15 whereas Unit-I & Unit-III are already
operational. In relation to Unit-I and Unit-II, it is stated that Unit-I was
conceptualised, planned and achieved financial closure on 20.09.2005 much
prior to financial closure of Unit-II. Further, Unit-II has been appraised
separately by the lenders and its financial closure happened on 15.09.2006 i.e.
about one year after the financial closure of Unit I. It is noteworthy to state that
the two Units i.e. Unit-I & Unit-II were separately conceptualized, appraised
and executed by augmentation/ modification/ addition to the existing facilities
of Unit-I. It is wrong and denied that Unit-II of Lanco has been part of 1960
MW at any point of time as alleged or otherwise. It is wrong and denied that
Unit-II of Lanco will be part of 3240 MW as alleged or otherwise. Though all
the four Units would eventually be established on contiguous land with
164 | P a g e
common boundaries but land was not acquired as a whole for all the Units
together instead it was acquired at different periods of time for different units
when the unit wise project appraisals got firmed up. The details of the land
acquired are: Unit No. I (300 MW): 566.89 Acres, Unit No. II (300 MW): 200
Acres; and Unit No. III & IV (2x660 MW): 570.71 Acres. Land required for
Unit-II was lesser than the land required in Unit-I. Further part of land
acquired for Unit-I was used for Unit-II as a result of which the cost of land
incurred for Unit-II is less in comparison to Unit-I. Land for Unit-II was leased
by the State Government vide lease deed dated. 19.09.2007 [Ref: page nos. 19-
47 of Reply dated 09.04.2014 to the memorandum of interrogatories]. Land for
all Units were acquired in different periods details whereof are already on
record [page nos. 48-105 of Reply dated 09.04.2014 to the memorandum of
interrogatories]. The site visit report dated 23.08.2014 of E&Y clearly
established that the capacities of existing facilities designed for 2x300 MW
generation capacity do not allow them to be used for a much larger 2x660MW
capacity of the new under construction plant. The layouts of the existing plant
(Units I&II) and that of the new plant (Units III&IV) also do not allow the
existing BOP facilities for units I&II to be used for Units III&IV. It is wrong
and denied that that all the generating stations have been established with the
intent to have sharing of various common assets or facilities or to achieve
economies in the scale of operation as alleged or otherwise.
12. The contents of para no.12 are denied being incorrect, false and
misleading, save and except being matters of record. It is wrong and denied
that Lanco had offered to sell the electricity to HPPC from its Unit-II as
alleged or otherwise. In this regard, admittedly the PPA dated 19.10.2005 was
between Lanco and PTC (Respondent No.1) and not with HPPC. The said PPA
stands terminated and the said termination has not been stayed by any forum or
court.
165 | P a g e
13. The contents of para no.13 are denied being incorrect, false, misleading
and irrelevant. The basis for arriving at the capped tariff of Rs. 2.32 per kWh is
completely irrelevant in the context of re-determination of tariff. It is wrong
and denied that Lanco’s proposal to agree to said capped tariff indicates its
intention to develop the generating stations with various generating Units i.e.
from Unit-I to Unit-VI as alleged or otherwise. The said conclusion of HPPC is
completely absurd besides being illogical. It is wrong and denied that there is
no explanation from Lanco in regard to its decision to offer power to PTC with
a capped tariff of Rs. 2.32 kWh. As per the mandate of the Hon’ble APTEL vide
judgment dated 03.01.2014, the re-determination of tariff has to be done
de hors the PPA dated 19.10.2005. Therefore any kind of purported reliance on
the PPA shall be in contravention of the said judgment. Since the re-
determination of tariff is to be done dehors the PPA dated 19.10.2005 therefore
there was no occasion for Lanco to disclose any basis for arriving at the
capped tariff. It is wrong and denied that E&Y as an independent chartered
accountant has failed to conduct proper inquiry as an independent consultant
as alleged or otherwise. It is wrong and denied that E&Y failed to go into the
prudent check of the project cost admissible for tariff purpose or has
mechanically adopted whatever Lanco had stated in its financial statement. The
detailed report covering various aspects of prudence check of project cost,
apportionment of common assets and land, interest during construction,
estimation of coal cost and surplus generated from infirm power as submitted
by E&Y on 08.07.2014 , 04.08.2014 and 23.08.2014 is self explanatory as to
the extent the check was carried out and all desired documents were submitted
to Hon’ble commission on this aspect as and when required. The allegations
are absolutely false and frivolous with a sole intention to delay the re-
determination of tariff for Unit-II of Lanco.
14. The contents of para no.14 are denied being incorrect, false,
speculative and misleading, save and except being matters of record. It is
166 | P a g e
wrong and denied that different units of Lanco established at Korba, Pathadi is
one generating station as being suggested. It is reiterated that Units III & IV
(2X660MW) are being set up separately from Units-I & II and the said Units
are in construction phase and are expected to be commissioned in FY 2014-15
whereas Unit-1 & Unit-II are already operational. In relation to Unit-1 and
Unit-II, it is stated that Unit-I was conceptualised, planned and achieved
financial closure on 20.09.2005 much prior to financial closure of Unit-II.
Further, Unit-II has been appraised separately by the lenders and its financial
closure happened on 15.09.2006 i.e. about one year after the financial closure
of Unit I. It is noteworthy to state that the two Units i.e. Unit-I & Unit-II were
separately conceptualized, appraised and executed by augmentation/
modification/ addition to the existing facilities of Unit-I. It is wrong and denied
that just because several independent generating units are being on land
contiguous to each other there are opportunities available to economise the
scale of investments or use of various assets in a common/ shared manner as
alleged or otherwise. It is wrong and denied that any of the assets relating to
Units-I & II on one hand and Units-III & IV on the other can be effectively
used as common assets as alleged or otherwise. It is wrong and denied that that
any of the assets relating to Units-I&II can be used as a common asset for any
proposed unit as alleged or otherwise. It is wrong and denied that any layout
plan made available to HPPC fortifies the said alleged contention of HPPC. It
is wrong and denied that Lanco has been wrongly alleging that the there are no
common assets as between operational Units-I & II on one hand and under
construction Units-III & IV on the other hand. Grant of specific approval for
each Unit at different periods of time (gap of 4-7 years) is an indication and is
a matter of fact that each of the Unit will have an independent and separate
asset and there will be no common assets. It is wrong and denied that any
physical asset between Units-I & II on one hand and Units-III & IV on the
other hand will be common as alleged or even otherwise. It is wrong and
denied that Lanco is concealing any fact as alleged or even otherwise. It is
167 | P a g e
wrong and denied that Lanco has made any attempt to mislead this Hon’ble
Commission by referring to consents and approval with respect to each of the
generating units. It is wrong and denied that there is any falsity in the claim of
Lanco. It is wrong and denied that site visit has exposed anything as alleged or
even otherwise. It is wrong and denied that Lanco had made any attempt to
mislead this Hon’ble Commission as alleged or even otherwise.
15. The contents of para no.15 are denied being incorrect, false, and
misleading, save and except being matters of record. It is wrong and denied
that the railway line for Units-1 & 2 on one hand and Units-3 & 4 on the other
is not being established separately as alleged or even otherwise. It is wrong
and denied that railway line for Units-I&II on one hand and Units-III&IV on
the other hand ought not to have been established separately. The said two
statements are mutually contradictory. It is wrong and denied that railway line
ought to have been a common line to be used for transportation of coal for all
generating units with an aggregate capacity of 3240 MW. Till now HPPC has
been deliberately making false and baseless statement that all generating
station of Lanco were conceived with 1920 MW capacity. In the present
objections, HPPC is now alleging that the same was conceived with 3240 MW,
which allegation is completely baseless and misleading. It is reiterated that
Units-I&II on one hand and Units-III&IV on the other were conceptualized,
planned separately at different time period, hence there was no question of a
establishing a common railway line/siding. It is submitted that the necessary
approvals for railway siding for Units I&II and that for Units III&IV were
received in different periods of time with gap of 7 years. It has been clearly
established from the railway siding layout submitted by Lanco to Hon’ble
Commission and HPPC, that there is a separate railway siding for Unit-II and
Units III&IV. The Site Visit report of E&Y dated 23.08.2014 clearly
establishes that the layout of tracks of the coal unloading facilities is such that
the existing facilities of Unit-II in operation cannot be used for the new
168 | P a g e
facilities. Therefore it is wrong and denied that that capacity of 300 MW
pertaining to Unit-II would work out to less than 10% of the use of the railway
line and railway siding as alleged or even otherwise. It is wrong and denied
that any cost of railway line or railway siding of Unit III&IV is being
appropriated cost of the railway line and railway siding on Units-I&II as
alleged or even otherwise.
16. The contents of para no.16 are denied being incorrect, false, and
misleading, save and except being matters of record. It is denied that cost of
railway siding incurred by Lanco is on the higher side as alleged or otherwise.
The alleged attempt of HPPC to compare the common cost incurred in
establishing “permanent railway siding’ by different power plants is absolutely
incorrect and has been made to mislead this Hon’ble Commission.
It is also submitted that the arbitrary comparison of the cost of a
System/Equipment with other power plant is not appropriate as it depends on
various factors such as complete scope of the system, plant layout, make of the
equipments, supplier of system, cost components etc. which varies from plant
to plant. Hence any allegation of HPPC that per MW cost of Railway Siding
of Amarkantak is more than Chhabra (Unit 1&2 ) and Parli (Unit 6) is wrong
and baseless. The sole purpose of HPPC is to mislead the Hon’ble
Commission by showing irrelevant data. What is most relevant is the total
project cost which has an impact on the tariff passed on to the consumers of
the state. As per the RERC Order dated 20.09.2012 enclosed by HPPC, the
capital cost of the projects commissioned during 2007-2010 as approved by
CERC/SERCs along with other projects whose capital cost has been approved
by CERC/SERCs is tabulated below, it can be seen that capital cost of Rs. 4.52
crore/MW of Lanco Unit-II is quite reasonable. (Ref: Page 120 of Affidavit of
Objection dated 08.09.2014).
169 | P a g e
S.
No.
Plant Name Approved
Capital Cost
in Rs. Crore
Capacity in
MW
Capital
Cost (in
Rs. Crore
Per MW)
Commercial
Operation Date
(COD)
1 Reliance Rosa
(Unit 1&2)
3112.81 600 5.31 Unit 1: 12.03.2010
Unit 2: 30.06.2010
2 Korba Stage 3 2588.28 500 5.18 Unit1: 21.03.2011
3 Chabra(Unit
1&2)
2416.00 500 4.83 Unit 1: 11.06.2010
Unit 2: 15.10.2011
4 Parli (Unit 6) 1155.35 250 4.62 Unit 6: 01.11.2007
5. Sagardighi
(Unit2&3)
2672.25 600 4.45 Unit 1: 07.09.2008
Unit 2: 06.11.2008
6 Lanco (Unit 2) 1356.11 300 4.52 Unit 2: 07.05.2011
It is also to be noted that the cost of Permanent Railway Siding of Lanco and
other plants as tabulated in Para 16 are not comparable. In case of Lanco,
EDC/IDC is included in the cost whereas the cost of Chhabra (Unit 1&2) and
Parli (Unit 6) does not include EDC/IDC.
In addition to the above said, HPPC has mischievously stated that the total
common cost of ‘permanent railway siding’ as Rs. 35.33 crores and has
deliberately not stated that only Rs. 8.7 Crores (approx) has been incurred
towards the cost of ‘permanent railway siding’ for Unit-II which is the subject
matter of this petition, which admittedly is less than comparative cost of other
thermal plants. Further, it is relevant to submit that comparison of cost in
relation to ‘permanent railway siding’ from Chhabra Thermal Power Plant
(Unit-1 & Unit-2) and Parli Thermal Power Plant (Unit-6) is misconceived
inasmuch as case of facts and circumstances of Chhabra & Parli are ex-facie
inapplicable to that of Unit I & II of Lanco. In this regard, it is submitted that
apparently Unit-1 & Unit-2 of Chhabra Thermal power plant were
simultaneously conceived, planned and expenditures were booked. [Ref: pg-
170 | P a g e
115-para-5.5, 117-para-5.19, 121-para-5.37 of affidavit dated 08.09.2014 of
HPPC] Similarly, it is apparent that Unit-6 & Unit-7 of Parli Thermal were
simultaneously conceived and planned. However, it is an admitted position in
the present case Unit-I & Unit-II of Lanco were separately conceptualized,
appraised and executed by augmentation/ modification/ addition to the existing
facilities of Unit-I.
17. The contents of para no.17 are denied being incorrect, false, and
misleading. It is submitted that Lanco has prudently incurred the expenses on
setting up of ‘permanent railway siding’ and is not higher or imprudent as
being alleged by HPPC. The alleged figures of cost in setting up ‘permanent
railway siding’ cannot be applied by a straitjacket formula as being suggested
by HPPC. It is wrong and denied that railway sidings once commissioned
would be useful to the subsequent units as alleged or even otherwise. It is
wrong and denied that cost of construction of railway sidings should be shared
between the subsequent units in proportion to the capacity of the respective
units as alleged or otherwise. In this regard, it is relevant to submit that E&Y in
its addendum report dated 23.08.2014 after due scrutiny has categorically
stated that the following “The layout of tracks (except a small portion which is
described in point no 6) and that of the coal unloading facilities is such that the
existing facilities (Unit I&II) cannot be used for the new facilities (Unit
III&IV).
18. The contents of para no.18 are denied being incorrect, false, and
misleading, save and except being part of record. The Order dated 06.06.2013
passed by the Hon’ble Rajasthan State Electricity Regulatory Commission is
not applicable to the present facts and circumstances. It is relevant to note that
apparently Unit-1 & Unit-2 of Chhabra Thermal power plant were
simultaneously conceived, planned and expenditures were booked jointly. [Ref:
-para-5.-pg-115, para-5.19-pg-117, para-5.37-pg-121 of affidavit dated
171 | P a g e
08.09.2014 of HPPC]. Whereas it is the specific case of Lanco that it’s two
Units i.e. Unit-I & Unit-II were separately conceptualized, appraised and Unit-
II was executed by augmentation/ modification/ addition to the existing
facilities of Unit-I. The said fact is established by report dated 08.07.2014 of
E&Y as well as by the addendum report dated 04.08.2014. This independence
of Unit 1 & 2 has been clearly established during the site visit on 16-
17.08.2014 which was admittedly attended by the team of E&Y Consultant,
HPPC and representative of this Hon’ble Commission.
The relevant portion of the report dated 08.07.2014 of E&Y is reproduced
hereinbelow:
3.1 Identification of common assets
There are total 4 thermal power units (2x300 MW and 2x660 MW) of
LAPL at Korba, Chhattisgarh. While, Unit 1 & 2 (2x300 MW) are
already operational, units 3 & 4 (2x660 MW) are presently under
construction. The common assets considered here are utilised only by
Unit 1 and Unit 2.
4.2 Key Observation
► Cost of land for Unit 2 was acquired at a slightly higher rate (Rs
5.75 lakh/acre) than Unit 1 (Rs 5.48 lakh/acre)
► Total cost of land for Unit 2 is much lower than the cost of land
incurred for Unit 1, although both the Units are of same capacity.
► The cost of land incurred for common facility has been largely
included in the project cost of Unit 1 as land for Unit 1 was acquired
earlier and only incremental cost incurred for Unit 2 has been included
in the project cost of Unit 2.
8. Summary of Findings
Apportionment of common assets
► The cost of common assets allocated to Unit 2 by LAPL is the
incremental expenditure incurred due to expansion of the common
facilities between Unit 1 and Unit 2
2 Apportionment
of land/common
1. Review of
1. The layout provided
172 | P a g e
assets apportionment of
common assets/land
through
layouts/maps/drawings
etc.
by LAPL is for Unit 1
and Unit 2 only.
Common facilities have
been marked
separately for both the
units in the layout. As
per our understanding
from the railway track
arrangement layout,
the existing track in
operation for Unit 1
and Unit 2 is
represented by black
lines, and the red lines
show planned track
which is to be extended
for Unit 3 and Unit 4.
However, the same can
be verified along with
HPPC officials during
site visit
19. The contents of para no.19 are denied being incorrect, false, and
misleading, save and except being part of record. The Order dated 21.10.2009
passed by the Hon’ble Maharashtra State Electricity Regulatory Commission is
not applicable to the present facts and circumstances. In this regard, it is
submitted that Order dated 21.10.2009 of MERC has been passed in respect of
capital cost determination of Unit-6 of Parli Thermal power plant wherein the
both units i.e. Unit-6 &Unit-7 of the said power plant was simultaneously
conceived, planned and Unit-7 was being executed so as to utilize the common
facilities of Unit-6. Further, the common facilities built at Unit-6 were to be
utilized by Unit-7 which was yet to be commissioned and cost was apportioned
accordingly. It was in this circumstances MERC had Ordered for
apportionment of cost of common facilities between an existing unit and a
proposed unit [Ref: para-70-71-pg-174 & para-89-pg-180 of affidavit dated
173 | P a g e
08.09.2014 of HPPC]. Whereas, it is the specific case of Lanco that there is no
common facility between operational Unit-II&II on the one hand and under
construction Unit III&IV on the other hand. Further, no common facility of
Units 1 & 2 will be used for Unit 3 & 4. In this respect contents of para 18 of
the present reply is reiterated and re-affirmed, which are not repeated herein
for the sake of brevity. In so far as apportionment of cost between Units-1 & 2
is concerned admittedly there is no dispute that the same has been apportioned.
20. The contents of para no.20 are denied being incorrect, false, and
misleading, save and except being matters of record. It is mischievous on part
of HPPC to contend that water intake and water pumping system can be
commonly used for all the generating units. It is noteworthy to state that the
two Units i.e. Unit-I & Unit-II of Lanco were separately conceptualized,
appraised and executed by augmentation/ modification/ addition to the existing
facilities of Unit-I. Unit 3 & 4 (2X660MW) which is under construction were
conceptualized, planned and achieved financial closure much later in 2011.
The approvals of water supply system also were obtained at different periods of
time with a gap of 7 years. In light of the above facts and circumstances, it is
wrong and denied that that it is imprudent on part of Lanco to have
independent water intake and water pumping system as well as water pipelines
from the Hasdeo river for Units-I&II on one hand and Units-III& IV as alleged
or otherwise.
21. The contents of para no. 21 are denied being incorrect, false, and
misleading, save and except being matters of record. It is denied that cost of
water supply system incurred by Lanco is on the higher side as alleged or
otherwise. The alleged attempt of HPPC to compare the common cost incurred
in establishing “water supply system’ by different power plants is absolutely
incorrect and has been made to mislead this Hon’ble Commission. HPPC is
misleading the Hon’ble Commission by comparing the cost of both Units
174 | P a g e
together i.e. Unit 1 and Unit-II which is not a subject matter of petition .
Without prejudice to above, it is submitted that Rs. 102.90 Crs water supply
system cost of Lanco Unit-II includes cost of Water Treatment Plant, Intake
water System along with its proportionate IDC/EDC and civil construction
cost. HPPC has compared this cost with Sagardighi Unit 1&2 and Chabra Unit
1&2 which has no rationale due to following reasons:
a) Both Units of Sagardighi and Chhabra were conceptualized,
appraised and executed simultaneously whereas Units 1 & Unit-II of
Lanco was conceptualized, appraised and executed independently at
different periods of time.
b) The Scope of Work of Water System of Units of Sagardighi and
Chhabra are different as compared to Lanco. In case of Chhabra only
the cost of Water Storage and transportation is considered and it
excludes the Water Treatment Plant Cost, Civil cost and proportionate
EDC/IDC cost which is a major part. Similarly, in the case of
Sagardighi project, where cost of Plant water System is only considered
which excludes Civil construction cost and even this cost is higher than
Lanco Unit-II cost.
c) The Cost depends upon the plant layout, distance of source of water
from generating plant, make of system equipment, Technology Selected,
Source of Water etc., which cannot be same for all the three plants.
22. The contents of para no.22 are denied being incorrect, false, and
misleading. It is submitted that Lanco has prudently incurred the expenses on
setting up of ‘water supply system’ and the cost is not higher or imprudent as
alleged by HPPC. The alleged figures of cost in setting up ‘water supply
system’ are not applicable in a straitjacket manner as being suggested by
HPPC due to different facts and circumstances as referred in previous para.
175 | P a g e
23. The contents of para no.23 are denied being incorrect, false, and
misleading, save and except being part of the judicial record. The Order dated
06.06.2013 passed by the Hon’ble Rajasthan Electricity Regulatory
Commission (“RERC”) is not applicable to the present facts and
circumstances. In this regard, it is relevant to submit that the observation of
Hon’ble RERC reproduced in the para under reply is ex-facie inapplicable to
the present case inasmuch as admittedly Units-III&IV are of different capacity
i.e. 660x2 MW as against 300x2 and therefore the water treatment facility
and/or water supply system of power plant of lesser capacity cannot be made
applicable to power plant of higher capacity. The site visit by team members of
E&Y Consultant, HPPC and Hon’ble Commission and subsequent Report of
E&Y specifying that the layouts of the existing plant (Units I&II) and that of the
under construction Units III&IV) also do not allow the existing BOP facilities
for Units I&II to be used for Units III&IV, clearly establish the fact that there
is no common sharing and thus the case of apportionment does not arise.
Additionally, in the case of Chhabra Thermal power plant it is apparent that
the water conductor system was common for all the four units i.e. for Phase-
I&II. Whereas, it is an established case of Lanco that there is no common
facilities between Unit-I&II on the one hand and Unit III&IV on the other [Ref:
Affidavit dated 09.04.2014 on behalf of Lanco as Per directions of the Hon’ble
Haryana Electricity Regulatory Commission given vide Order dated
25.03.2014].
24. The contents of para no.24 are denied being incorrect, false, and
misleading. It is incorrect to suggest that since the generating Units are being
established on a contiguous land therefore the switchyard for interconnection
and evacuation of power for all generating units can be the same. It is incorrect
to suggest that that it is imprudent for Lanco to establish a separate switchyard
for Units-III,IV,V & VI independent of the existing switchyard for Units-I&II. It
is wrong and denied that there will be an increase in the bay for the existing
176 | P a g e
switchyard for the purpose of Units III, IV, V and VI. It is wrong and denied
that there is no need for Lanco to establish a separate switchyard. From the
date of approvals, clearances and land acquisitions, it is clearly established
that Unit I, Unit-II and Units III&IV were conceptualised, planned and
executed at different periods of time with a gap of 4-7 years, hence there is no
case of planning and constructing the switchyard of Units I&II and Units
III&IV together. Similarly, it is wrong and denied that the facilities such as
residential colonies or maintenance of such facilities or township facilities or
road or street lighting or security etc., are to be commonly maintained for all
the generating units as alleged or otherwise. It is wrong and denied that Unit-II
cannot be related to more than 10% of overall cost of all generating units i.e.
3240 MW as alleged or otherwise. It is wrong and denied that Unit-II cannot be
related to more than 10% of overall cost of other facilities as detailed in para
under reply. In this regard, it is submitted that HPPC has carried out physical
verification of the site and it is an admitted fact that the Units-III&IV are being
constructed independently and separately from the existing Units-I&II, which is
evident from Annexure-R-7 filed by HPPC. Further, residential colony,
maintenance of such facilities, township facilities, road, street lighting,
security, ash dyke, ash disposal system, administrative building, coal handling
system, air conditioning system, compressor system, fire fighting system,
maintenance workshop, cooling tower, rain water harvesting, roads, drainage
etc for Unit-III&IV are being established independently and separately from
that of the existing Units-I&II.
25. The contents of para no. 25 are denied being incorrect, false, and
misleading, save and except being matters of record. It is denied that cost of
switchyard incurred by Lanco is on the higher side as alleged or otherwise. The
alleged attempt of HPPC to compare the common cost incurred in establishing
“switchyard” by different power plants is absolutely incorrect and has been
made to mislead this Hon’ble Commission. It is submitted that the cost of
177 | P a g e
Switchyard for Unit-II alone is Rs. 63.33 Crs. HPPC has compared this cost
with the cost of Total BOP Electrical in the case of Paras Unit 3 and Parli Unit
6 power plants, which represents a different category and nature of
equipments. (Ref:-page no. 169 and 233 of Objection of HPPC dated
08.09.2014) HPPC without noting the content of the system has erroneously
made inference that the cost of switchyard of Unit-II is substantially higher
than Parli Unit 6 and Paras Unit 3 power plants. Without prejudice to the
above, it is also stated that the arbitrary comparison of the cost of a
System/Equipment with other power plant is not appropriate as it depends on
various factors such as Complete Scope of the System, Plant Layout, Make of
the equipments, date of award of Contract, Make of System, cost components
etc., which vary from Plant to Plant. Hence the contention of HPPC that per
MW cost of Switchyard of Lanco Unit-II is more than Paras (Unit 3) and Parli
(Unit 6) is not correct and is totally irrelevant. The sole purpose of HPPC is to
mislead the Hon’ble Commission by projecting irrelevant data. What is most
relevant is the total project cost/MW which is least in case of Lanco as
compared to other power plants even without the mega power benefit.
26. The contents of para no. 26 are denied being incorrect, false, and
misleading. It is denied that cost of switchyard incurred by Lanco is on the
higher side as alleged or otherwise.
27. The contents of para no. 27 are denied being incorrect, false, and
misleading. Admittedly, there are no common facilities between the Unit 1 & 2
on one hand and Unit 3 &4 on the other hand. Similarly, it is wrong and denied
that there will be any shared or common facilities between Unit I&II on one
hand and Unit V&VI (if planned in future) on the other hand as alleged or
otherwise. It is wrong and denied that any action of Lanco in establishing
separate and independent facilities for Unit-I&II one hand and Unit III&IV on
the other hand is imprudent or contrary to the practice adopted in establishing
the generating units. It is wrong and denied that HPPC or consumers of the
178 | P a g e
State of Haryana is being called upon to pay for any imprudent act of Lanco as
alleged or otherwise.
28. The contents of para no. 28 are denied being incorrect, false, and
misleading, save and except being matters of record. The alleged comparison
of costs incurred for ash handling system, switchyard, land or coal handling
system between Lanco and other generating station is misleading. It is wrong
and denied that there is any inconsistency with the cost incurred by Lanco as
alleged. HPPC is misleading the Hon’ble Commission by comparing the cost of
both Units together i.e. Unit 1 and Unit-II which is not a subject matter of
petition in view of the fact that the tariff determination process is for Unit-II
only which is a separate business Unit and all the inputs related to Unit-II have
been submitted to Hon’ble Commission and HPPC. Without prejudice to the
above, it is stated that comparison of Cost of Ash Handling System tabulated in
para 28 is misleading as the system considered for comparison are of different
nature and existence. With the detailed review of the Order quoted by HPPC, it
is submitted that the Cost of Ash Handling System of Lanco Unit-II includes the
cost of Ash Handling Equipments, Ash Pond and cost associated with it such as
Civil and proportionate EDC/IDC etc. However in case of Sagardighi Unit
1&2, only the cost of Ash Pond is considered which contains only a part of Ash
Handling System. In a similar manner in Case of Paras Unit 3 and Parli Unit 6
the scope of the system is different from the scope of Lanco Unit-II. (Ref:-page
no. 169, 233 and 280 of Objection of HPPC dated 08.09.2014). It can be seen
from the tabulated data that there is a major difference in the Cost of Ash
Handling System among Sagardighi Unit 1&2, Parli Unit 6 and Paras Unit 3
where Lanco is no way connected and it clearly indicates that the sole purpose
of HPPC is to mislead the Hon’ble Commission with absurd data and not to
compare with the facts and figures at par. Hence arbitrary comparison of the
cost of a System/Equipment with other power plant is not appropriate as it
depends on various factors such as Complete Scope of the System, Plant
179 | P a g e
Layout, Make of the equipments, Date of Contract award, Make of System,
Specification of Equipments, cost components and Selection of Technology etc.,
which vary from, Plant to Plant. Hence the contention of HPPC that per MW
cost of Ash Handling System of Lanco Unit-II is more than Sagardighi Unit
1&2, Paras (Unit 3)and Parli (Unit 6) is wrong and baseless. The sole
purpose of HPPC is to mislead the Hon’ble Commission by projecting
irrelevant data analysis. It is wrong and denied that Lanco has incurred any
cost imprudently as being alleged by HPPC.
29. The contents of para no. 29 are denied being incorrect, false, and
misleading. The alleged comparison of costs incurred for ash handling system,
switchyard, land or coal handling system between Lanco and other generating
station is misleading. With the facts and circumstances referred in previous
para, it is wrong to suggest that the cost of ash handling plant is higher than
the corresponding cost of other generating stations. Also the observation of the
Hon’ble Maharashtra State Electricity Regulatory Commission in the Order
dated 15.12.2009 in the case of Paras Thermal Power plant is not applicable to
the present facts and circumstances. It is pertinent to note that the Hon’ble
MSERC passed the Order dated 15.12.2009 on a specific admitted case of
Maharashtra State Power Generation Company Limited (‘MSPGCL’) that the
common facilities constructed for Unit-3 shall be shared with proposed Unit-4
passed the Order dated 15.12.2009 [Ref: para-90-pg-238 & para-108-pg-243].
Whereas, it is reiterated that it is the specific as well as an established case of
Lanco that there is no common facilities between Unit-I&II on the one hand
and Unit III&IV on the other [Ref: Affidavit dated 09.04.2014 on behalf of
Lanco as Per directions of this Hon’ble Commission given vide Order dated
25.03.2014].
180 | P a g e
30. The contents of para no. 30 (wrongly numbered as para 26) are denied
being incorrect, false, and misleading, save and except being matters of record.
The alleged attempt of HPPC to compare the common cost incurred in for land
by different power plants is absolutely incorrect and has been made to mislead
this Hon’ble Commission. It is submitted that cost incurred for land depends on
various factors namely cost of land depends upon the Quantity, Rate (which
varies from State to State), Date of Purchase etc. which cannot be uniformly
applied for acquiring/purchasing land of each power plant. Hence comparing
the cost of Land with Lanco Unit-II is not correct. It is to clarify that the land
has been handed over by the State Govt, to Lanco through lease deed at a state
notified rate and has not been purchased directly from the villagers, hence any
allegation over the cost of land which is beyond the purview/control of Lanco is
baseless and denied. Also in the case of Sagardighi Plant, the COD happened
in the year 2008 which is much prior to the COD of Unit-II on 07.05.2011. The
cost incurred for acquiring/purchasing land for Sagardighi cannot be yardstick
for contending that cost incurred by Lanco in acquiring/purchasing land for
Unit-I &II is higher or imprudent.
31. The contents of para no. 31 (wrongly numbered as para 27) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is submitted that cost of purchasing land for Unit-II has been separately
booked and accounted for while determining the capital cost of Unit-II. It is
wrong and denied that the land acquired/purchased for Unit-I&II would be
useful to the subsequent Units as alleged or otherwise. It is wrong and denied
that the cost of construction of land should be shared between the units in
proportion of capacity of each unit. It is reiterated that there is no common
land or common construction on land between Unit-II&II on one hand and
Unit-III&IV on the other hand. HPPC is deliberately raising the issue to
mislead this Hon’ble Commission. In this regard, it is submitted that Lanco has
filed an affidavit dated 09.04.2014 as per directions of this Hon’ble
181 | P a g e
Commission given vide Order dated 25.03.2014 wherein Lanco has
categorically stated that no part of the land for Unit-II shall be used for Unit-
III&IV. The relevant extract of Site Visit report of E&Y dated 23.08.2014 which
is reproduced below clearly establishes the fact that 200 Acres is completely
utilised in Unit-II and no part of it is used in subsequent Units.
“ 4. Hence total land allocated to Unit 2 remained 200 Acres and no
part of that was used by Unit III&IV.”
32. The contents of para no. 32 (wrongly numbered as para 28) are denied
being incorrect, false, and misleading, save and except being matters of record.
The alleged attempt of HPPC to compare the common cost incurred for
establishing ‘coal handling plant’ by different power plants is absolutely
incorrect and has been made to mislead this Hon’ble Commission. In para no.
32, HPPC has undertaken a comparison of the cost of Coal Handling Plant of
Sagardighi, Paras Unit 3 and Parli Unit 6 with Unit No.1 & Unit No. II of
Lanco. It is submitted that HPPC had failed to appreciate that the cost of 300
MW Unit No. II of Lanco is very much in line with the 300 MW cost of Coal
Handling Plant of Sagardighi. It is submitted that the hard cost of 300 MW
Unit No. II of the Petitioner is 91.77 Crs (Excluding EDC/IDC) where as the
hard cost of Coal Handling Plant of Sagardighi thermal power plant is Rs.
184.22/2=92.11 Crs (Ref:-Page 279 of Objection of HPPC dated 08.09.2014)
although it’s COD was in the year 2008 much prior to COD of Unit No. II of
Lanco. HPPC also failed to analyse as to why there is a huge gap in per MW
cost of Coal Handling Plant of Sagardighi, Paras Unit 3 and Parli Unit 6.
Under these circumstances, it is appropriate to refer to the justification given in
previous paras that the cost of a System depends on various factors such as
scope of the System, Plant Layout, Make of the equipments, Date of contract
award, Make of System, cost components, Technology etc. which varies from
Plant to Plant and cannot be applied uniformly. In accordance with the
justification given in above para, it is submitted that the sole purpose of HPPC
182 | P a g e
is to mislead the Hon’ble Commission by projecting irrelevant, and baseless
data analysis The cost incurred for establishing ‘coal handling plant’ for
Sagardighi, Paras or Parli Thermal power plant cannot be yardstick for
contending that cost incurred by Lanco in establishing ‘coal handling plant’ for
Unit-I &2 is higher or imprudent.
33. The contents of para no. 33 (wrongly numbered as para 29) are denied
being incorrect, false, and misleading. With the facts and figures described in
previous para, it is denied that cost incurred for establishing ‘coal handling
system by Lanco is on the higher side in comparison with other power plant as
alleged or otherwise.
34. The contents of para no. 34 (wrongly numbered as para 30) are denied
being incorrect, false, and misleading. It is wrong and denied that report
submitted by E&Y has not verified the coal and secondary fuel purchase bills
for the verification of sources as well as the cost of landed coal or secondary
fuel as alleged or otherwise. In this regard, it is submitted that Lanco has
provided all necessary details in relation to coal and secondary fuel purchase
bills for verification to E&Y which have been duly verified and the same has
been shown at point 4 of the addendum report dated 04.08.2014. It is wrong
and denied that E&Y has not verified the laboratory report for verification of
GCV of the landed coal. In this regard, it is submitted that E&Y vide its email
dated 29.07.2014 requested Director, Tariff, HERC to ensure the documents in
relation to determining GCV of coal such as lab report, sampling mix etc.
Lanco vide its email dated 31.07.2014 provided the documents as sought by
E&Y to both E&Y and to the Director, Tariff of this Hon’ble Commission,
which have been duly considered by E&Y in validation of Coal Quantity and
Quality at point no. 7 of its site visit report submitted to Hon’ble Commission
on 23.08.2014. In addition to it as per the requirement during site visit, all the
invoices of coal were produced, which were verified without any
inconsistencies by representatives of both the Hon’ble Commission and that of
183 | P a g e
the HPPC. All the Invoices and Lab reports were also submitted to this Hon’ble
commission and HPPC on 12.01.2012 and 13.01.2014. It is therefore incorrect
to allege that Lanco ought to be directed to submit any document in relation to
lab report for determining GCV of landed coal. Without prejudice to the
foregoing, it is apparent from the proceedings dated 20.08.2014 issued by this
Hon’ble Commission that Lanco during the site visit provided manner of
assessing of GCV of coal of Unit I&II as well explained the sampling method
and provided the daily report for inspection to the satisfaction of the team
undertaking the site visit.
35. The contents of para no. 35 (wrongly numbered as para 31) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is submitted that HPPC should be concerned only about Unit-II of Lanco in
as much as the present proceeding is confined to re-determination of tariff of
Unit-II pursuant to the Order dated 03.01.2014 of the Hon’ble Tribunal. It is
strange that HPPC is not aware that the Station Heat Rate is a fixed/normative
parameter specified in the HERC Tariff Regulations, 2008, as such the quality
and quantity of coal used in Unit-II are not used to work out the station heat
rate as alleged by HPPC. The details of month wise weighted average GCV as
well as the supporting lab reports which are a measure of the quality of coal
used were submitted by Lanco to both E&Y and to Hon’ble Commission on
31.07.2014. The month wise data pertaining to coal stock at the beginning of
the month, the coal receipts during the month, transportation cost of coal, coal
consumption during the month and the closing stock of coal at the end of month
along with necessary documents have already been submitted as per Form 15
to this Hon’ble Commission as well as to E&Y. It is submitted that to meet the
shortfall of coal due to insufficient linkage coal quantity, Lanco had to resort to
procurement of coal from alternate sources i.e. e-auction/open
market/imported coal. The coal procured from e-auction sources was
transported by trucks from the coal mines located at to and fro distance of 100
184 | P a g e
to 240 km from the plant and therefore, the transportation cost incurred during
the supply period varied from Rs. 185/ton to Rs. 710/ton with average
transportation cost during the supply period was Rs. 480/ton. The
transportation cost incurred was through finalization of transparent
competitive bidding offers invited from the transporters. HPPC has not
specified how it has arrived at the figure of Rs. 570/metric cube stated in its
objection. Accordingly, from the above, it is clear that HPPC is mischievously
alleging the wrong figures and analysis related to the coal quality, coal
quantity and station heat rate.
36. The contents of para no. 36 (wrongly numbered as para 32) are denied
being incorrect, false, and misleading. It is wrong and denied that E&Y has not
examined any aspect as being alleged by HPPC or even otherwise. It is
reiterated that inter alia E&Y has examined and verified the quantity and
quality of coal for Unit-II, GCV of coal for Unit-II as well as coal cost
incurred. There was no occasion for E&Y to compare project cost claimed by
Lanco with other projects as alleged or otherwise inasmuch as the mandate of
E&Y as per this Hon’ble Commission was to verify the data furnished by Lanco
and not to compare the said data with other projects which is apparent from
the ‘scope of services’ detailed in page-6 in the report dated 08.07.2014 of
E&Y. Without prejudice to any right and contentions of Lanco, it is submitted
that admittedly the project cost of Parli (Unit-6), Paras Unit-3, Korba Stage –
III, Simdhari Stage-II is over and above Rs. 5 crore/MW which is much higher
than what Lanco’s Unit-II of Rs. 4.52 crore/MW being claimed in the present
tariff re-determination process.
37. The contents of para no. 37 (wrongly numbered as para 33) are denied
being incorrect, false, and misleading. It is completely wrong and denied that
this Hon’ble Commission in the proceedings dated 25.03.2014 had specifically
or otherwise referred to the aspects of railway siding, railway line etc., being
common to entire station to 1920 MW. HPPC is making false statement before
185 | P a g e
this Hon’ble Commission which is apparent from the record of proceedings
dated 25.03.2014. It is wrong and denied that the proportionate share of Unit-
II of Lanco works out to 14.6% (approx). It is wrong and denied that common
assets of Unit-II cannot be considered beyond 14.6% as alleged or otherwise. It
is wrong and denied that the table of apportioning common assets in the report
is also an assumption or presumptions as alleged or otherwise. It is wrong and
denied that the table of apportioning common assets in the report is not by
verification of the data furnished by Lanco as alleged or otherwise instead the
statement of cost of common facilities submitted by Lanco are based on actual
expenditure incurred for augmentation/ modification/ addition to the existing
facilities of Unit-I which has also been duly certified by its Statutory Auditors..
38. The contents of para no. 38 (wrongly numbered as para 34) are denied
being incorrect, false, and misleading. HPPC is deliberately and with malafide
intent is delaying process of re-determination of tariff of Unit-II inasmuch as
this Hon’ble Commission has given enough opportunities to HPPC to file its
objections/comments to the report which admittedly have not been availed by
HPPC and therefore it is humbly submitted that no further opportunity/liberty
should be given HPPC.
39. The contents of para no. 39 (wrongly numbered as para 35) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that, except that with Unit-I, there are shared
assets/common facilities between Unit-II and other units. It is wrong and
denied that capital cost determination of Unit-II would include apportionment
of the cost of shared assets other than shared assets between Unit-I&II.
40. The contents of para no. 40 (wrongly numbered as para 36) are denied
being incorrect, false, and misleading, save and except being matters of record.
Lanco has duly explained reason for increase in the capital cost in its details
submitted to Hon’ble Commission [ref: pg-77-80 of Vol-I-letter dated
186 | P a g e
13.01.2014, pg-2-3of rejoinder dated 03.03.2014 on behalf of Lanco; pg-1-
para-2-reply dated 09.04.2014on behalf of Lanco to memorandum of
interrogatories].
41. The contents of para no. 41 (wrongly numbered as para 37) are denied
being incorrect, false, and misleading, save and except being matters of record.
42. The contents of para no. 42 (wrongly numbered as para 38) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is submitted that the increase in cost of Rs. 69.53 Crores was on account of
increase in span of mill and bunker in Order to match with the requirement of
traverse of the hoist, and also to provide operational ease, deck sheeting in TG
building for construction of roof slabs to expedite construction activities,
requirement of pile foundation for stacker, re-claimer hopper entailing
additional expenditure towards manpower and material, price escalation
towards re-enforcement steel, structural steel and cement. The said increase in
cost has been duly approved by lenders engineer vide letter dated 23.04.2010,
which is already on record. Further, increase in scope of non-EPC contractor
to tune of Rs. 20.35 crores has also been duly approved by lenders engineer
vide letter dated 23.04.2010, which is already on record. Apparently, the said
figures have been cross-verified by E&Y. It is evident from the lender’s
engineer report dated 23.04.2010 that increase in scope of non-EPC cost was
on account of works carried out in accordance with directives of state
authorities and local state bodies. HPPC with a sole motive to delay the re-
determination of tariff is seeking documents time and again. In this regard, it is
submitted that HPPC has filed its reply dated 10.02.2014, memorandum of
interrogatories dated 01.04.2014 and preliminary objection dated 21.07.2014,
which have been duly responded by Lanco. However, HPPC never requested
for copies of the contract/work Order awarded to different agencies, which
clearly shows that HPPC is requesting for more documents only to delay the
proceedings, which is liable to rejected.
187 | P a g e
43. The contents of para no. 43 (wrongly numbered as para 39) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that cost of Rs. 29.82 Crores on account of change in
the design, engineering, construction, supervision & pre-operative expenses. It
is wrong and denied that the said increased cost ought to be disallowed as
alleged or otherwise. It is wrong and denied that the delay in achieving COD
was solely attributable to Lanco as alleged or otherwise. It is reiterated that the
delay in COD was on account of reasons beyond reasonable control of Lanco,
which has been duly explained by Lanco in its written submission dated
25.07.2014 [Ref: pg-10-13-para-12-18].
44. The contents of para no. 44 (wrongly numbered as para 40) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is completely wrong and denied that no detailed breakup of the capital cost is
provided as alleged or otherwise. Lanco has given all requisite details in
relation to capital cost. HPPC is repeating its alleged objections which have
been dealt with by Lanco in its rejoinder dated 01.03.2014 [ref: pg-2-5 para-
5], reply to memorandum dated 09.04.2014 [ref: page-1 to 4 para-2].
45. The contents of para no. 45 (wrongly numbered as para 41) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that there was any default on the part of Lanco to give
particulars of capital cost as alleged or otherwise. It is submitted that the
Order dated 17.10.2012 does not record any finding of failure of Lanco in
submitting all documents as per the direction of this Hon’ble Commission. In
any event the Order dated 17.10.2012 is of no relevance in the present re-
determination of tariff since the same has been set aside by the Hon’ble APTEL
vide judgment dated 03.01.2014.
188 | P a g e
46. The contents of para no. 46 (wrongly numbered as para 42) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is denied that the Lanco has made a claim for capital cost as Rs. 1668.37 as
alleged. Lanco has claimed actual capital expenditure incurred upto the COD
which has been supported by a certificate from its Statutory Auditor as per
applicable HERC Tariff Regulations, 2008. The cost overrun in the project cost
was approved by Lender’s engineer (PFC) after a thorough independent
assessment and verification. Significantly, the net revenue generated from sale
of infirm power after fuel expenses of Unit-II is (Rs. 311.28 Crores) from date
of synchronization (22.02.2010) upto the declaration of COD
(07.05.2011),which is reflected in the certificate issued by Auditor certifying
the capital cost of Unit II [Ref: page-73 of Vol-I-letter dated 13.01.2014]. It is
submitted that the benefit of reduced capital cost has been clearly passed on to
the consumers of State of Haryana as the revenue generated from sale of infirm
power from Unit-II has been deduced from the capital cost of Unit-II in
accordance with HERC Tariff Regulations, 2008. It is wrong and denied that
Lanco has not given proper details and evidence in support of capital cost
claimed by it.
47. The contents of para no. 47 (wrongly numbered as para 43) are denied
being incorrect, false, and misleading, save and except being matters of record.
The contents of the para under reply is mere repetition of para-18 & 19 of reply
dated 10.02.2014, which have been dealt with by Lanco in its rejoinder dated
01.03.2014. The averment of HPPC that as per financial statements of Lanco
filed for the year ended 31.03.2009, for the period 2009-10 and for the period
2010-11, the sale of power from Unit I and Unit-II before the declaration of the
date of commercial operation aggregate to Rs. 1889.10 crores is irrelevant for
the computation of infirm power revenue generated from Unit-II. Lanco
submits this very objection was raised by HPPC in the proceedings in CASE
NO: HERC/PRO – 1 OF 2012 and was dealt it by Lanco. The said objection
189 | P a g e
was rejected by the Hon’ble Commission in its Order dated 17.10.2012. HPPC
admittedly has not challenged the same and therefore HPPC is estopped from
raising this objection. Without prejudice to the above, it is submitted that
HPPC is trying to mislead this Hon’ble Commission by quoting the
consolidated financials of Lanco, which includes gross revenue from sale of
power from Unit-I before and after COD of Unit I in addition to the sale of
infirm power from Unit-II before its COD 07.5.2011. It is submitted that Unit I
was synchronized on 01.05.2009 and its COD was declared on 09.04.2010
whereas Unit II was synchronized on 22.02.2010 and its COD was declared on
07.05.2011. The net revenue generated from sale of infirm power after fuel
expenses of Unit-II is (Rs. 311.28 Crores) from date of synchronization
(22.02.2010) upto the declaration of COD (07.05.2011) which is reflected in
the certificate issued by Statutory Auditor certifying the capital cost of Unit-II.
It is submitted that complete details in relation to Energy Export and Amount of
infirm power solely pertaining to Unit-II has been already submitted by Lanco
before this Hon’ble Commission in CASE NO: HERC/PRO – 1 OF 2012 vide
its tariff petition dated 12.01.2012 and the same are already on record as
Annexure-4 of the tariff petition dated 12.01.2012. It is submitted that the
benefit of reduced capital cost has been clearly passed on to the consumers of
State of Haryana as the revenue generated from sale of infirm power from
Unit-II has been deduced from the capital cost of Unit-II in accordance with
HERC Tariff Regulations, 2008. Therefore, the submission of HPPC that the
sale of infirm power during the period from 01.04.2011 to 06.05.2011 has not
been provided by Lanco is totally incorrect and baseless. It is submitted that on
25.03.2010 i.e. the day when the Unit-IItouched full load the assets of Unit-II of
Lanco were capitalized in the book of accounts. The financial statements-as at
March 31, 2011 along with auditor’s report and financial statements-as at
March 31, 2010 along with auditor’s report of Lanco have already been
submitted by Lanco before this Hon’ble Commission vide its reply dated
19.07.2012 to the objections filed by HPPC in CASE NO: HERC/PRO – 1 OF
190 | P a g e
2012 and the same are already on record as Annexure-B of the reply dated
19.07.2012. The financial statements-as at March 31, 2012 along with
Auditor’s report is already on record as Annexure-P-3 with the rejoinder dated
01.03.2014. The standalone financials of Unit-II certified by the Auditor for the
period as on 25.03.2010, as on 31.03.2010, as on 31.03.2011 and as on
07.05.2011 is already on record as Annexure-P-4 (Colly) with the rejoinder
dated 01.03.2014. It is wrong and denied that Lanco has not provided break up
as alleged or otherwise. It is wrong and denied that there is any failure of
Lanco to provide any detail. It is wrong and denied that any adverse inference
is to be drawn against Lanco to the extent that more than Rs. 311 crores needs
to be adjusted in the capital expenditure for revenue from infirm power and UI
Charges as alleged or otherwise. It is wrong and denied that any adverse
inference is to be drawn against Lanco.
48. The contents of para no. 48 (wrongly numbered as para 44) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that O&M expenses for Unit I as approved by MPERC
towards salaries of staff, maintenance of common auxiliaries etc., need to be
apportioned between Unit I & II as alleged otherwise. That no common cost
has been incurred towards salaries of staff or maintenance of common facilities
as alleged or otherwise. It is submitted that the claim of Lanco towards
capital cost in the present proceedings is the actual cost incurred by Unit-II
wherein no such alleged cost has been incurred and booked in the books of
accounts. Similarly, the capital cost incurred by Unit I of Lanco is
independently booked and incurred.
49. The contents of para no. 49 (wrongly numbered as para 45) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that Lanco is not entitled to any IDC and IEDC or cost
overrun on account of any alleged Force Majeure conditions. HPPC is
misconceived in stating that Lanco has to either accept the Order dated 2nd
191 | P a g e
October 2011 in toto i.e. finding of occurrence of force majeure events with no
cost implication. It is also wrong and denied that it is not now open to Lanco to
seek cost implications. In this regard, it is submitted that though Lanco has
challenged the said Order dated 02.02.2011 before the Hon’ble Supreme Court
but it is a fact on record that the said findings in the Order dated 02.02.2011
has not been assailed either by Lanco or HPGCL (HPPC) or for that matter by
PTC. Further, the said portion of the Order dated 02.02.2011 is fact finding
rendered by the Hon’ble Commission which will not change in any scenario. It
is misconceived on part of HPPC to contend that since PPA dated 19.10.2005
is not applicable therefore the fact that HPPC not disputing the condition of
Force Majeure will not be applicable.
50. The contents of para no. 50 (wrongly numbered as para 46) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that in the absence of PPA dated the only applicable
provision is Section 56 of the Contract Act as alleged or otherwise. It is wrong
and denied that there is no higher cost implication to the non-affected party in
the event of occurrence of Force Majeure events. It is wrong and denied that
the affected party only gets released of the obligations to perform during the
period of Force Majeure. It is wrong and denied that the China earthquake or
the visa problems cannot be a Force Majeure as it did not affect Lanco. It is
wrong and denied that it was not impossible for Lanco to perform the
obligations through alternate means. It is wrong and denied that performance
of the obligations of Lanco had become onerous or difficult or expensive as
alleged or otherwise. It is reiterated that the performance of Lanco was delayed
on account of factors beyond reasonable control which has been duly explained
by Lanco in its reply to memorandum of interrogatories dated 09.04.2014. It is
pertinent to mention herein that IDC is dependent on hard cost of the project
which is decided along with the time duration of the Project and the applicable
interest rate. It is submitted that the actual capital expenditure incurred upto
192 | P a g e
the COD has to be considered as the completed capital cost in accordance with
Regulation 12 of the HERC Tariff Regulations, 2008. Therefore, Lanco is
entitled to the actual capital cost incurred by it. As stated above the increase in
capital costs were on account of the reasons which were beyond the reasonable
control of Lanco. It is submitted that the reasons of increase in capital cost
have been duly explained in Para-B of its letter dated 13.01.2014 and the
documents filed along with the same and the contents of which may be treated
as part and parcel of the para under reply. It is further submitted that as per
Regulation 12 of the HERC Tariff Regulations, 2008 Lanco is entitled to
increase in capital cost since the same has been actually and bonafidely
incurred by Lanco in executing the project. In this regard, it is submitted that it
is a settled law that in case delay in execution of a generating project occurs
due to factors beyond the control of the generating company e.g. delay caused
due to force majeure then the generating company is entitled to benefit of the
additional cost incurred due to time over-run. In this respect reliance may be
placed on the judgment of APTEL passed in Appeal No. 72 of 2010. Lanco
craves the leave of this Hon’ble Commission to distinguish any alleged settled
legal position during the course of argument.
51. The contents of para no. 51 (wrongly numbered as para 47) are denied
being incorrect, false, and misleading. The averment of HPPC that debt-equity
ratio should be as per the alleged approved financial package is incorrect and
misconceived and is contrary to the judgment dated 03.01.2014 of the Hon’ble
APTEL. As per which the debt-equity ratio has to be fixed according to the
HERC Tariff Regulations, 2008. It is wrong and denied that Lanco cannot
claim the actual debt and equity. In this regard, it is submitted that the HERC
Tariff Regulations, 2008 clearly provides that where equity actually employed
is less than 30%, the actual debt and equity shall be considered for the
determination of tariff. The actual debt outstanding in the books of accounts of
Lanco as on COD is Rs. 968.402 crores duly certified by the Statutory Auditor
193 | P a g e
vide its certificate dated 12.01.2014 and accordingly Lanco has considered the
actual net outstanding loan as on COD as the debt for the project and the
balance amount of the capital cost of the project is considered as equity. It is
submitted that Lanco has commenced repayment of the term loan for the
project before the COD and based on actual debt outstanding as on COD, the
debt –equity ratio stands at 71.41%:28.59% which has been claimed by Lanco.
It is denied that in the present case the capital cost will have to be apportioned
in the form of debt to the extent of 80% and equity to the extent of 20%. It is
denied that Lanco cannot be allowed to claim equity at more than 20%. It is
submitted that the claim of Lanco is strictly as per the HERC Tariff
Regulations, 2008.
52. The contents of para no. 52 (wrongly numbered as para 48) are denied
being incorrect, false, and misleading. It is wrong and denied that the
repayment of loan should be considered as minimum amount of depreciation as
alleged or otherwise. It is submitted that the issue of repayment of loan as
raised by HPPC is irrelevant for current tariff re-determination as per HERC
Tariff Regulations, 2008 as it already provides for components of Depreciation
and Advance against Depreciation which shall take care of the requirements of
repayment of loan.
53. The contents of para no. 53 (wrongly numbered as para 49) are denied
being incorrect, false, and misleading. It is submitted that the Annual capacity
charges for 2011-2012, 2012-2013 and 2013-2014 has been computed after
adjusting infirm power as well as common facilities between Unit 1 & 2 for the
purpose of Capacity charges. Since there are no shared assets/facilities
between Unit 1 & Unit-II on one hand and Unit III&IV on the other hand
therefore there is no question for adjusting the same from the annual capacity
charges as alleged by HPPC. It is wrong and denied that as per regulations 10
& 11 of HERC Tariff Regulations, 2008 capacity charges need to be adjusted
194 | P a g e
as alleged or otherwise. It is wrong and denied that if the plant load factor is
achieved by say 40% as against 80% target availability the above capacity
charges will be adjusted by half. It is wrong and denied that Lanco is not
entitled to per unit tariff based on annual capacity charges for 80% plant load
factor. In this regard, it is submitted that the Lanco has claimed annual
capacity charges strictly as per HERC Tariff Regulations, 2008.
54. The contents of para no. 54 (wrongly numbered as para 50) are denied
being incorrect, false, and misleading, save and except being matters of record.
It is wrong and denied that plant load factor achieved by Lanco during the FY
2011-2012 including auxiliary consumption is 56%. It is wrong and denied that
annual capacity charges payable need to be adjusted to Rs. 224.12 crores. It is
wrong and denied that per unit charge to be paid will be to the tune of Rs. 1.30.
It is also wrong and denied that computation of annual capacity charges would
be as alleged by HPPC in the para under reply. It is wrong and denied that
plant load factor including auxiliary consumption for the FY 2012-2013 is
40.77% as alleged. It is wrong and denied that per unit charge for FY 2012-
2013 to be paid will be to the tune of Rs. 0.90. It is submitted that the HERC
Tariff Regulations, 2008 clearly provide for recovery of full annual capacity
charges at the Target Availability (80%) of Unit-II. In case the Availability is
less than the Target Availability on an annual basis, the recovery of annual
capacity charges shall be on pro-rata basis. Recovery of annual capacity
charges have nothing to do with the PLF of the plant. Therefore, the issue
raised by HPPC is irrelevant as annual capacity charges shall be determined
by the Hon’ble Commission as per the HERC Tariff Regulations, 2008.
55. The contents of para no. 55 (wrongly numbered as para 51) are denied
being incorrect, false, and misleading. It is wrong and denied that any other
claims of Lanco need to be adjusted as alleged or otherwise. It is denied that
total project cost or debt equity ratio or repayment of loan or interest on
195 | P a g e
working capital or operation and maintenance expenses etc., need to be
adjusted as alleged or otherwise.
56. The contents of para no. 56 (wrongly numbered as para 52) are denied
being incorrect, false, and misleading. It is not the case of Lanco that the
Hon’ble Commission should not exercise prudent check. It is wrong and denied
that Lanco has claimed any higher capital cost. It is reiterated that Lanco has
claimed capital cost prudently and actually incurred by it as per HERC Tariff
Regulations, 2008. It is wrong and denied that Lanco has not given any
requisite particulars in support of its claim. It is reiterated that Lanco has
provided all documents and information in support of claims as and when
sought to the Hon’ble Commission from time to time. It is incorrect to contend
that Lanco is seeking admission of capital expenditure incurred only on the
basis of auditor certificate.
57. The contents of para no. 57 (wrongly numbered as para 53) are denied
being incorrect, false, and misleading. Lanco has provided all requisite details
explaining the need for capital expenditure. Lanco has also provided the details
of actual capital expenditure incurred. It is reiterated that all expenditure
incurred by Lanco is reasonable and just.
58. The contents of para no. 58 (wrongly numbered as para 54) are denied
being incorrect, false, and misleading. It is wrong and denied that Lanco ever
supplied power to HPPC. It is submitted that Lanco has supplied power to PTC
which has in turn supplied the same to HPPC. It is reiterated that Lanco has
already deducted the revenue from infirm power while computing the capital
cost of Unit-II. The remaining contents of para under reply are mere repetition
of the contents of para no. 47 (wrongly number as para 43). Accordingly,
Lanco reiterates and reaffirms the contents of para no. 47 of this reply, which
are not repeated herein for the sake of brevity.
196 | P a g e
59. The contents of para no. 59 (wrongly numbered as para 55) are denied
being wrong, incorrect, false, baseless and misleading. It is reiterated that
Lanco has given details of the revenue generated by Lanco from the sale of
infirm power upto the COD of Unit-II, which has been duly certified by its
Statutory Auditor. It is submitted that based on the directions of Hon’ble
Commission, E&Y has also verified the same and found to be correct and in
Order. It is denied that it is incumbent upon Lanco to give details of aggregate
quantum of the sale of infirm power and sale of power under unscheduled
interchange of Unit-I & Unit-II. It is wrong and denied that any revenue
generated from sale of infirm power and unscheduled interchange charges
under the Unit 1 need to be adjusted for reduction in the capital cost for the
purpose of determining the cost to be considered for the tariff. It is reiterated
that the capital cost of the Unit-II as certified by the Statutory Auditor in the
certificate along with the letter dated 13.01.2014 excludes the sale of infirm
power and unscheduled interchange charges under the Unit I. It is submitted
that the contention of HPPC regarding a detailed investigation into the
quantum of infirm power sold by Lanco under the Unit-II is totally
misconceived, mischievous and is a ploy to delay the present proceedings. It is
denied that the quantum of sale of infirm power at Rs. 311.28 crores is
erroneous as alleged or otherwise.
60. The contents of para no. 60 (wrongly numbered as para 56) are denied
being wrong, incorrect, false, baseless and misleading. The averment of HPPC
that debt-equity ratio should be as per the alleged approved financial package
is incorrect and misconceived and is contrary to the judgment dated 03.01.2014
of the Hon’ble APTEL. As per which the debt-equity ratio has to be fixed
according to the HERC Tariff Regulations, 2008. It is wrong and denied that
Lanco cannot claim the actual debt and equity. In this regard, it is submitted
that the HERC Tariff Regulations, 2008 clearly provides that where equity
actually employed is less than 30%, the actual debt and equity shall be
197 | P a g e
considered for the determination of tariff. The actual debt outstanding in the
books of accounts of Lanco as on COD is Rs. 968.402 crores duly certified by
the Statutory Auditor vide its certificate dated 12.01.2014 and accordingly
Lanco has considered the actual net outstanding loan as on COD as the debt
for the project and the balance amount of the capital cost of the project is
considered as equity. It is submitted that Lanco has commenced repayment of
the term loan for the project before the COD and based on actual debt
outstanding as on COD, the debt –equity ratio stands at 71.41%:28.59% which
has been claimed by Lanco. It is denied that in the present case the capital cost
will have to be apportioned in the form of debt to the extent of 80% and equity
to the extent of 20%. It is denied that it is not open to Lanco to claim equity at
more than 20%. It is submitted that the claim of Lanco is strictly as per the
HERC Tariff Regulations, 2008. It is denied that the tariff petition made by
Lanco on the basis of apportionment of the debt and equity in the ratio stated
therein is wrong. It is denied that the tariff calculation is based on any wrong
differentiation and equity ratio assumed by Lanco. It is denied that the tariff
calculation based on above stated debt-equity ratio is defective and need to be
rejected. It is submitted that the Regulation 15 (3) of the HERC Tariff
Regulations 2008 clearly stipulates that the debt-equity ratio shall be based on
actual deployment of funds subject to the condition that the equity deployed in
excess of 30% of the capital cost shall be treated as normative loan. It is denied
that the once the capital cost determined as per prudence check and infirm
power and UI charges are deducted the cost is to be apportioned in the debt-
equity ratio of 80%-20%. It is wrong and denied that the return of equity is to
be restricted to 20% of the capital cost. It is wrong and denied that the balance
80% will have to be serviced as borrowing/loan.
61. The contents of para no. 61 (wrongly numbered as para 57) are denied
being wrong, incorrect, false, baseless and misleading. It is submitted that as
per the judgement dated 03.01.2014 of the Hon’ble APTEL the Tariff
Regulations, 2009 of the Central Commission is of no relevance in the present
198 | P a g e
proceedings in so far as interest on loan is concerned. It is submitted that
HPPC is trying to mislead the Hon’ble Commission by referring to the Tariff
Regulations, 2009 of the Central Commission for Interest on Loan component
of the Tariff as against the applicable HERC Tariff Regulations, 2008. Lanco
states that it has claimed interest on loan after COD on the actual loan
outstanding as on COD after duly taking into account the normative repayment
for the respective tariff periods. The objections raised by HPPC are
misconceived as Lanco has not claimed any depreciation before COD, which is
in line with the HERC Tariff Regulations, 2008. It is denied that Lanco has not
given any particulars in Order to determine the normative loan, depreciation
adjusted and balance to be serviced from time to time. Lanco reiterates that it
has already submitted all the necessary and relevant details in the applicable
Formats required for determination of Interest on Loan, Depreciation and
Advance against Depreciation in accordance with the applicable provisions of
HERC Tariff Regulations, 2008.
62-63. The contents of para no. 62-63 (wrongly numbered as para 58-
59) are denied being wrong, incorrect, false, baseless and misleading. It is
submitted that this Hon’ble Commission vide its Order dated 02.02.2011 had
specifically held that the Force Majeure events as claimed by Petitioner therein
i.e. PTC India Limited did happen which were not disputed by PTC and HPPC.
The said findings were not challenged by HPPC and thus became final and
binding on the said parties. Therefore, it is not open to HPPC now to state that
the reasons namely earth quake in China and the visa policy of the Government
of India are not Force Majeure events as contended or otherwise. In so far as
the contention of HPPC that this Hon’ble Commission vide Order dated
02.02.2011 rejected the claim of compensation in terms of the tariff hike is
concerned, it is submitted that admittedly the said finding of the Hon’ble
Commission was based on the premise that there was no enabling provision for
the same in the PSA/PPA. The said finding of the Hon’ble Commission cannot
199 | P a g e
be considered at all as the Hon’ble APTEL vide its judgement dated 03.01.2014
has directed re-determination of tariff dehors the PPA.. As per the said
judgment of the Hon’ble APTEL the tariff is to be determined in accordance
with the HERC Tariff Regulations, 2008. Without prejudice to the above, the
second appeal arising out of the Order dated 02.02.2011 passed by this
Hon’ble Commission being C.A. No. 10329 of 2011 is pending before the
Hon’ble Supreme Court and therefore the above finding in respect of tariff
revision is sub-judice. It is important to note that the present proceedings for
determination of interim tariff originally arise out of the Order dated
16.12.2011 passed by the Hon’ble Supreme Court in the said Civil Appeal. It is
thus incorrect and misconceived to state that Lanco cannot claim either IDC or
IEDC or any other compensatory payment by way of cost overrun or time
overrun on account of the delay resulting from the Force Majeure Event of
earthquake in China or visa policy of the Government of India. It is also
incorrect to state that the said issue stands settled and cannot be opened at this
stage as alleged. It is denied that the reason of earthquake in China, visa policy
of the Government of India etc are not Force Majeure events as alleged by
HPPC. In any event HPPC is estopped from raising the above contention. It is
denied that the claim for IDC and IEDC i.e. time overrun and cost overrun can
be considered only in regard to the matters other than those resulting from the
Force Majeure Event. It is pertinent to mention that IDC is dependent on hard
cost of the project which is decided along with the time duration of the Project
and the applicable interest rate. It is submitted that the actual capital
expenditure incurred upto the COD has to be considered as the completed
capital cost in accordance with Regulation 12 of the HERC Tariff Regulations,
2008. Therefore, Lanco is entitled to the actual capital cost incurred by it. As
stated above the increase in capital costs were on account of the reasons which
were beyond the reasonable control of Lanco. It is submitted that the reasons of
increase in capital cost have been duly explained in Para-B of its letter dated
13.01.2014 and the documents filed along with the same and the contents of
200 | P a g e
which may be treated as part and parcel of the para under reply. It is further
submitted that as per Regulation 12 of the HERC Tariff Regulations, 2008
Lanco is entitled to increase in capital cost since the same has been actually
and bonafidely incurred by Lanco in executing the project.
64. The contents of para no. 64 (wrongly numbered as para 60) are denied
being wrong, incorrect, false, baseless and misleading. It is denied that the
claim of Lanco for the delay in the commissioning is only on account of Force
Majeure Event of earthquake in China in May, 2008. It is denied that the
reasons stated for delay in commissioning of the Unit-II cannot be ground for
claiming cost overrun in respect of Unit-II. It is submitted that on 12.05.2008,
the manufacturing facilities of M/s Dongfang Electric Corporation, China
(DEC), supplier of main plant equipment and BTG component of project were
severely damaged due to a powerful earthquake rated at Richter scale 8.0 in
China and DEC could not supply the machines and equipments to Lanco. This
was admittedly a Force Majeure event. It is denied that the event of Force
Majeure of Visa Policy of the Government of India not permitting the Chinese
workforce has been raised as an afterthought. The force-majeure notices were
issued by Lanco to PTC immediately after the occurrence of the force majeure
event in the year 2008 itself and therefore the allegation of HPPC that it has
been raised as an afterthought is patently wrong. It is denied that the delay in
commissioning due to the usage of the rotor of Unit-II in Unit-I cannot be a
ground for claiming the cost overrun in respect of Unit-II. It is submitted that
the delay on this account was caused during the period of Force Majeure
events. Lanco craves the leave of this Hon’ble Commission to treat the contents
of para-B of the letter dated 13.01.2014 as part and parcel of the para under
reply and the same are not repeated herein for the sake of brevity.
65. The contents of para no. 65 (wrongly numbered as para 61) are denied
being wrong, incorrect, false, baseless and misleading. It is reiterated that as
per the judgement dated 03.01.2014 of the Hon’ble APTEL, the Tariff
201 | P a g e
Regulations, 2009 of the Central Commission in so far as fixed charges is of no
relevance in the present proceedings. As per the judgement dated 03.01.2014 of
the Hon’ble APTEL, fixed charges are to be computed as per the HERC Tariff
Regulations 2008. It is evident from the Tariff Formats filed by Lanco on
13.01.2014 which are in accordance with HERC Tariff Regulations, 2008 that
Lanco has claimed annual fixed charges for FY 2011-12, FY 2012-13, FY
2013-14 and FY 2014-15. It seems that HPPC has raised these objections
without going into the details submitted by Lanco. It is wrong and denied that
the implemented schedule of power shall be taken as per availability at the
State’s Periphery and not on declared availability of Lanco’s Plant for
payment/billing purposes as alleged or otherwise. It is denied that any suitable
directions in this regard need to be issued by this Hon’ble Commission.
66. The contents of para no. 66 (wrongly numbered as para 62) are denied
being wrong, incorrect, false, baseless and misleading. It is reiterated that as
per the judgement dated 03.01.2014 of the Hon’ble APTEL the Tariff
Regulations, 2009 of the Central Commission is of no relevance in the present
proceedings in so far as interest on working capital is concerned. In the para
under reply, HPPC is again trying to mislead the Hon’ble Commission by
referring to period of actual consumption, coal price etc. of January 2009 to
March 2009. It is submitted that it commenced supply of power to the PTC for
onward supply to HPPC w.e.f. 07.05.2011 pursuant to the interim Order dated
23.03.2011 passed by the Hon’ble APTEL. Lanco had been running its Unit II
and supplying power to PTC for onward supply to HPPC by procuring the
linkage coal supplied by SECL under MoU route and meeting its balance
requirements of coal from alternate sources. That the linkage coal supplied by
South Eastern Coalfields Limited (SECL) during the above period was widely
varying and it was sufficient for only 27% PLF and hence the additional coal
was procured from alternate sources which is much costlier than the linkage
coal which had caused additional working capital expenditure and further the
202 | P a g e
payment was not fully realized at par with the cost of generation from PTC. The
tariff was to be determined based on the directions of the Hon’ble Supreme
Court by its Order dated 16.12.2011 and now by the direction of Hon’ble
APTEL for the power which had already been supplied based on costs actually
incurred. Lanco submits that it is seeking reimbursement of the actual costs
incurred by it in accordance with directions of Hon’ble APTEL. It is relevant to
submit that to comply with the Order dated 16.12.2011 of the Hon’ble Supreme
Court, Lanco was receiving widely varying quantum of linkage coal under
MoU route from SECL, the coal procured from alternate sources also widely
varied to run the Unit-II and supply power to PTC for onward supply to HPPC
. It is submitted that in the instant case, Lanco had to spend additional working
capital to procure the coal from alternate sources varying on month to month
basis based on the quantum of linkage coal supplied. The tariff application
containing the tariff filing formats filed on 13.01.2014 is based on the actual
working capital expenditure incurred for the power already supplied for the
past period and for the future period, Lanco has considered the normative
working capital requirements in the computation of the tariff. It is further
important to state that in the present facts and circumstances where the tariff is
determined for a past and concluded period for which the data in respect of
actual consumption of coal price, operation and maintenance expenses, cost of
secondary fuel etc are already available then the interest of working capital is
required to be determined on the said available data. It is denied that the actual
amount of capital employed from time to time in regard to the coal
consumption etc. is irrelevant as alleged. It is incorrect to state that the interest
on working capital is not dependent upon the actual working capital incurred
by the generating company irrespective of whether the generating company
incurs the working capital or not. It is denied that the claim of Lanco of actual
working capital every month or on the basis of coal value is contrary to HERC
Tariff Regulations, 2008 or any other regulations.
203 | P a g e
67. The contents of para no. 67 (wrongly numbered as para 63) are denied
being wrong, incorrect, false, baseless and misleading. The averment of HPPC
in relation to alleged coal consumption being higher in a particular month is
completely vague. Lanco in its Tariff Filing Formats has given monthly as well
yearly figures of coal consumption. Lanco submits that in certain months
during the power supply period, Lanco did not receive any linkage coal as
SECL had not supplied any linkage coal and Lanco had to procure the entire
coal required for running the Unit-II from alternate sources including imported
coal. In certain other months, Lanco had to depend entirely on procurement of
coal from alternate sources including imported coal which led to higher
outflow of working capital. It is reiterated that as per the judgement dated
03.01.2014 of the Hon’ble APTEL the Tariff Regulations, 2009 of the Central
Commission is of no relevance in the present proceedings in so far as coal
consumption is concerned. It is denied that it is not open for Lanco to claim
actual interest on working capital on month to month basis.
68. The contents of para no. 68 (wrongly numbered as para 64) are denied
being wrong, incorrect, false, baseless and misleading. It is denied that the
operating and maintenance expenses need to be ascertained in terms of the
Tariff Regulations, 2004 based on the capital cost determined by this Hon’ble
Commission as alleged. In the para under reply, HPPC is again trying to
mislead the Hon’ble Commission by initially referring to the Tariff Regulations,
2004 and then referring to Tariff Regulations, 2009 pertaining to O&M
expenses. It is reiterated that as per the judgement dated 03.01.2014 of the
Hon’ble APTEL the Tariff Regulations, 2004 of the Central Commission is of
no relevance in the present proceedings. Further, even otherwise the Tariff
Regulations, 2004 cannot be made applicable to the tariff determination of
Lanco since the said Regulations ceased to be effect from 01.04.2009 whereas
O&M expenses in respect of Lanco case is for the year 2011-12. It is submitted
that on 03.02.2014, Lanco has filed an application under Regulation 33 of the
204 | P a g e
HERC Tariff Regulations, 2008 before this Hon’ble Commission inter alia
seeking relaxation of Regulation 16(iv)(c) of the HERC Tariff Regulations,
2008 regarding O&M expenses and grant of O&M expenses as per CERC
Tariff Regulations, 2009. In this regard, it is relevant to submit that the O&M
expenses as per HERC Tariff Regulations, 2008 are much lower and
practically not feasible for a generating station or Unit generating power. It is
further submitted that HPPC has also admitted that the O&M expenses needs
to be paid to Lanco under CERC Tariff Regulations, 2009 on normative basis.
It is further submitted that this Hon’ble Commission vide its Order dated
18.04.2011 passed in CASE No: HERC/PRO– 1 OF 2011 for generation tariff
for HPPC has noted that the HERC Tariff Regulations, 2008 in relation to
Operation and maintenance expenses are outdated and not updated. Further,
this Hon’ble Commission vide the said Order has not only deviated from the
applicability of HERC Tariff Regulations, 2008 but has also allowed O & M
Expenses as per CERC Tariff Regulations, 2009 for the generation tariff of the
generating stations of HPPC. In this regard, it is submitted that Lanco is
therefore entitled to parity and is entitled to relaxation/variation of HERC
Tariff Regulations, 2008 while re-determination of the interim tariff for its
Unit-II. The relevant potion of the Order dated 18.04.2011 of this Hon’ble
Commission is reproduced herein below:
“2.7.1...........
The Commission is of the considered view that adequate amount of
O&M expenses is essential for deriving optimum efficiency from the
plant and machinery. Hence, in the absence of updated HERC
generation tariff regulations, CERC norms for unit size of 200 MW &
above have been adopted for FY 2011-12. For the remaining generating
stations of lower than 200 MW capacity, where CERC norm does not
exist, the basis of estimating O&M expenses is the O&M expenses
allowed by the Commission in FY 2009-10 escalated by 5.72% per
annum to arrive at O&M expenses to be allowed in FY 2011-12. The
escalation factor considered is as per CERC notification. Accordingly,
the Commission allows O& M expenses @ Rs. 2.94 million/MW for
PTPS (1-4), Rs. 2.034 million/MW for PTPS (5 to 8), Rs. 1.788
million/MW for DCRTPS and Rs. 1.308 million /MW for RGTPS (1&2).
205 | P a g e
While the O&M expenses allowed by the Commission in the case of
WYC & Kakroi have been approved as proposed by HPGCL.
It is also important to state that pursuant to the passing of Order dated
18.04.2011, this Hon’ble Commission has passed similar tariff Orders for the
Respondent No. 2 generating stations for the subsequent years wherein O&M
expenses has been allowed in accordance with CERC Tariff Regulations, 2009
containing reference of Order dated 18.04.2011. Copy of relevant extract of the
Order dated 18.04.2011 passed by the Hon’ble Commission in CASE No:
HERC/PRO– 1 OF 2011 is already on record as Annexure P-5 with the
rejoinder dated 01.03.2014.
69. The contents of para no. 69 (wrongly numbered as para 65) are denied
being wrong, incorrect, false, baseless and misleading. It is denied that Lanco
cannot demand energy charges based on any coal used by it other than through
procurement of coal under a regular Fuel Supply Agreement with coal India/its
subsidiary is contrary to the judgment dated 03.01.2014 of the Hon’ble APTEL.
In terms of the said judgment the energy charges are to be calculated as per the
HERC Tariff Regulations, 2008. Further, as per the directions of the Hon’ble
APTEL Lanco has submitted the requisite materials showing that it made
bonafide efforts to secure coal linkage from SECL as envisaged at the project
planning stage, along with the letter dated 13.01.2014. Lanco submits that
since 07.05.2011 when Lanco commenced power supply to PTC for onward
supply to HPPC, there have been frequent downward revisions in the supply of
linkage coal by SECL. Lanco inspite of financial hardships had tried its best to
operate its Unit-II and supply power to PTC for onward supply to HPPC by
procuring the ever increasing balance requirement of coal from alternate
sources (where the cost of coal was at least 3 to 4 times higher than the cost of
linkage coal) without realization of a just and equitable tariff which was not
even meeting its generation cost. It is an admitted position that Lanco was
facing severe hardship on account of the increasing burden due to coal costs
206 | P a g e
(in view of the reduced quantities of coal being supplied by the government
undertakings in light of the New Coal Distribution Policy). It is submitted that
the coal linkage from the SECL to Lanco had decreased from what was
originally envisaged with the SECL i.e. 100% linkage coal which is evident
from the following:
a) Letter of Assurance dated 18.09.2006 issued by SECL
guaranteeing coal supply to the extent of 1.445 MTPA;
b) MoU dated 15.03.2010 with SECL for the period 2009-2010
for coal supply of an annual quantity of 18 lakh tons;
c) Letter dated 11.06.2010 by the Ministry of Power directing
Lanco to procure 3 lakh tons of imported coal.
d) MoU dated 24.07.2010 for the period 2010-2011 for coal
supply of an annual quantity of 13 lakh tons with SECL;
e) Minutes dated 18.04.2011 of SLC, Ministry of Coal envisaging
supply of only 50% of domestic coal.
f) MoU dated 30.08.2011 for the year 2011-2012 for coal supply
of an annual quantity of 9.4 lakh tons
g) Letter dated 10.07.2012 from SECL by which SECL had
reduced the coal supply to 91% of 0.94 MTPA (i.e. 71,283 per
month).
Copy of the Letter of Assurance dated 18.09.2006, MoU dated 15.03.2010,
MoU dated 24.07.2010, MoU dated 30.08.2011, Letter dated 11.06.2010 &
Minutes dated 18.04.2011 of SLC have already been submitted by Lanco vide
its tariff petition 12.01.2012 before this Hon’ble Commission in CASE NO:
HERC/PRO – 1 OF 2012 and the same are already on record at page nos. 224-
250 of the tariff petition dated 12.01.2012.
Copy of the letter dated 10.07.2012 from SECL have already been submitted by
Lanco vide its reply dated 19.07.2012 to the objection of HPPC before this
207 | P a g e
Hon’ble Commission in CASE NO: HERC/PRO – 1 OF 2012 and the same is
already on record as Annexure-G of the reply dated 19.07.2012 of Lanco.
As a matter of fact, there was no coal supply during the period from May 2012
to June 2012 and the coal allocation vide SECL letter dated 10.7.2012 was
further reduced to an annual quantity equivalent to 0.86 million tons per
annum (MTPA) from 0.94 MTPA. It is further submitted that, the coal supply
was further reduced by SECL to 46216 metric tonnes per month (equivalent to
0.55 MTPA) vide letter dated 28.09.2012. The month wise supply of Linkage
Coal from SECL was as under:
Month
Linkage Coal
Supplied from
SECL (in MT)
Coal
Requirement
for 100% PLF
(in MT)
@3300
kCal/kg
Supplied Coal
Sufficient for %
PLF
Weighted
Average GCV
(Kcal/Kg)
May-11 0 1,61,719 0% 3146
Jun-11 0 1,56,502 0% 3273
Jul-11 0 1,61,719 0% 3127
Aug-11 0 1,61,719 0% 3295
Sep-11 59,169 1,56,502 38% 3,348
Oct-11 76,926 1,61,719 48% 3,132
Nov-11 72,421 1,56,502 46% 3,321
Dec-11 88,680 1,61,719 55% 3,354
Jan-12 76,780 1,61,719 47% 3,487
Feb-12 74,172 1,51,285 49% 3,411
Mar-12 76,648 1,61,719 47% 3,350
Apr-12 74,601 1,56,502 48% 3,181
May-12 3,800 1,61,719 2% 3,265
Jun-12 0 1,56,502 0% 0
Jul-12 66,090 1,61,719 41% 2,952
Aug-12 63,847 1,61,719 39% 3,176
Sep-12 0 1,56,502 0% 3167
Oct-12 39,739 1,61,719 25% 2,976
Nov-12 44,809 1,56,502 29% 3,023
Dec-12 43,999 1,61,719 27% 2,929
208 | P a g e
Jan-13 44,439 1,61,719 27% 3,270
Feb-13 41,151 1,46,069 28% 3,581
Mar-13 39,961 1,61,719 25% 3,421
Total/
Average 9,87,232 36,56,934 27% 3,256
It is further relevant to submit that the cost of imported coal is about five times
the cost of linkage coal after proportionally adjusting the benefit of higher
GCV. That in the absence of the 100% linkage coal Lanco had to resort to
procurement of the imported coal and therefore Lanco is entitled to actual cost
incurred in procuring coal for generating the power at Unit-II.
70. The contents of para no. 70 (wrongly number as para 66) are denied
being wrong, incorrect, false, baseless and misleading. It is wrong and denied
that the claim of Lanco for the project cost needs to be rejected. It is wrong
and denied that Lanco has concealed any fact from this Hon’ble Commission
as alleged or otherwise. It is wrong and denied that Lanco has not approached
this Hon’ble Commission in a clean and transparent manner as alleged or
otherwise. It is wrong and denied that any adverse inference needs to be drawn
against Lanco as alleged or otherwise. It is wrong and denied that there should
not be any change in the project cost as determined by the Hon’ble Commission
in the earlier Order dated 17.10.2012 as alleged or otherwise.
In view of the above, it is submitted that the objections filed on behalf of HPPC
are frivolous, baseless and meritless.
The Petitioner, as directed by the Commission in the hearing held on
19.09.2014, submitted as under:
209 | P a g e
a) Use of Rotor of Unit-II in Unit-I as mentioned in the Lender’s
Engineer report regarding cost overrun dated 23.04.2010
The scheduled date of commissioning of Unit-II of Lanco was 15.09.2009.
Accordingly, the scheduled date for supply of Generator was 23.08.2008 and
the scheduled date of start of erection was 15.10.2008 and it was to be
completed by 30.04.2009. The scheduled date of start of supply of
connecting piping, heaters & valves was 12.08.2008, completion of supply
of the same was 04.10.2008 and erection of piping was scheduled from
19.11.2008 to 25.05.2009 to achieve steam blowing completion by
25.06.2009. Thus, the original schedule of generator erection was starting
from 15.10.2008 and was to be completed by 30.04.2009.
It is an admitted position that there was a powerful earth quake in China of
magnitude 7.8 on Richter scale on 12.05.2008. Consequently there was
delay in delivery of above said items and the same had been communicated
by Original Equipment Manufacturer (“OEM”) to Lanco. There was an
overall delay of 5 months in supply of connecting pipes, valves etc and
missing/damaged parts such as LP Diaphragm, HP –IP diaphragm etc. in
shipping. This 5 month delay in supply of connecting pipes, valves and
missing/damaged parts resulted in delay in start of erection of respective
systems. Accordingly, the supply of the above items was commenced by the
OEM and thereafter in April 2009, erection of the said items including HP-
210 | P a g e
IP diaphragms commenced, and was completed by November 2009 and
steam blowing was completed by December 2009.
It is also an admitted position that the Govt. of India vide its notification
dated 08.09.2009 and letter dated 25.9.2009 from Ministry of Home Affairs
introduced New and Specific Visa regime for foreign personnel coming to
India for execution of projects/contracts which restricted their deployment
for execution of the Project. All the Chinese engineers of OEM left the
project site of Unit-II of Lanco in September/October, 2009 and resumed
back in February, 2010 which added to the delay of 5 more months in
commissioning the Unit-II even after receipt of the materials.
On 31.01.2009, rotor of Unit-I of Lanco failed during its synchronization.
Accordingly, rotor of Unit-I was sent back to OEM, China in March, 2009.
As due to the factors i.e. earthquake in China and visa issues, the overall
construction and erection activities of Unit-II got delayed, the rotor of Unit-
II was used in Unit-I only for the month of April 2009 and Unit-I was
synchronised on 01.05.2009. At that time, Unit-II Turbine Generator
erection activities had just started after March 2009 after the effect of earth
quake in China had ceased and as per the project construction status of Unit-
II, generator rotor was not required to be used immediately and it was
expected to be used only after August 2009.
211 | P a g e
The Generator rotor of Unit-I for use in Unit-II was dispatched from China
on 04.06.2009 well in advance of its requirement for erection at site. I say
that there was delay in receipt of connecting pipes, valves and
missing/damaged parts as stated hereinabove.
The delay in commissioning of Unit-II due to delay in supply of connecting
pipes can be confirmed from the fact that the steam blowing completion as
per Original Schedule was 25.06.2009 which was delayed by around 6
months and was actually completed on 27.12.2009. That the steam blowing
process is directly related to supply and erection of piping and is in no way
connected with readiness of generator. Also it is reiterated that there was
further delay due to Visa issue after receipt of the materials. However the
turbine generator was ready for barring gear before completion of steam
system for steam blowing.
The mention of the use of Unit-II rotor in Unit-I in the lender’s engineer
report regarding cost overrun dated 23.04.2010 is general is nature. It is in
addition to the problems faced by the Project. It is important to mention that
the said lender’s engineer report regarding cost overrun dated 23.04.2010
does not indicate any specific delay attributable on account of the use of
rotor of Unit-II in Unit-I. This is for the reason that the said period overlaps
with the overall delay in the project on account of the above Force Majeure
212 | P a g e
events namely Earth Quake in China and Visa issues of Chinese workers
which were beyond the reasonable control of Lanco. This is clear from the
facts narrated above. Thus the use of rotor of Unit-II in Unit-I did not
contribute in any delay.
The final cost overrun approval was done by the Lender’s engineer report
dated 23.04.2010 and after the said approval no further approval was done
by the Lender’s Engineer. The Lender’s report regarding cost overrun
approval dated 23.04.2010 is already on record.
b) Separate Coal supplies for Unit-I & Unit-II
Lanco had signed a separate Coal Supply Agreement dated 25.06.2008 with
South Eastern Coalfields Ltd (SECL), Bilaspur for its Unit-I. As far as Unit-
II is concerned, Lanco had signed an MoU with SECL on 24.07.2010 for
supply of power to PTC for onward supply to Haryana.
The supply of coal under the above different arrangements for Unit-I and
Unit-II, on monthly basis and as per the Railway norms, Lanco had to
request for railway rake allotment Unit wise to SECL in the prescribed
format for approval, which Lanco used to submit Unit wise. SECL supplied
213 | P a g e
coal through rakes with Unit reference and Railway Receipt (RR) &
Invoices were raised separately for each of the Units. Therefore, say that the
month wise quantum of coal and its amount was separately accounted for
Unit-I and Unit-II.
During the course of hearing on 19.09.2014 Lanco was directed by this
Commission to furnish details in relation to capital costs of various projects
commissioned during the period 2007-2013, which have been approved by
various Appropriate Commissions. Lanco has prepared a chart giving
various relevant details in relation to capital costs of various projects
commissioned during the period 2007-2013. The said chart is prepared on
the basis of the Orders passed by various commissions (as mentioned in the
chart). The said Orders are available on the website of the respective
commissions. The said chart clearly shows that the capital cost claimed by
Lanco is lesser than the capital costs for other projects approved by the
various Commissions.
In the hearing held on 19.09.2014 the Respondent No.2 i.e. HPPC as a part
of its written submission filed a chart allegedly comparing the common
facilities of Unit-I & II on one hand and Unit-III & IV on the other as well
as comparing the cost of several other thermal power plants with that of
Lanco. The said chart handed over by HPPC is a mere repetition of
214 | P a g e
statements made by HPPC in its affidavit of objection dated 08.09.2014,
which have been duly responded by Lanco in its reply dated 17.09.2014.
7.0 Commission’s Analysis & Order:-
7.1 The Commission, while passing this Order, has taken into
account all the pleadings, written as well as oral, of the parties as well
as the report submitted by E&Y including addendum, outcome of the
site visit, subsequent clarifications furnished by E&Y in response to
various queries of the Commission, reply dated 30.10.2014 filed by
LAPL to furnish information sought vide letter dated 22.10.2014 by
the Commission, documents /information furnished by LAPL, PTC, and
HPGCL consequent to Commission’s interim Order dated 15.12.2014
and all other documents/data/information submitted by the
Petitioner/Respondent’s and on the record of the Commission.
7.2 As already stated, the Commission had appointed independent
consultants, M/S E&Y on 09.06.2014 with the consent of both the
parties to (i) review the capital cost (ii) ascertain impact due to IDC (iii)
identification and cost allocation of common assets (iv) ascertain land
acquisition cost (v) estimation of cost of coal and (vi) determine
surplus generated from infirm power in respect of Unit-II of LAPL. The
report was submitted by M/S E&Y on 08.07.2014. Subsequently E&Y
also submitted an addendum to the report and further, thereafter,
furnished clarifications to various queries of the Commission as
sought vide e-mail dated 31.10.2014 and note to the clarifications
furnished in response to the additional queries of the Commission.
215 | P a g e
7.3 The Commission notes that HPPC had filed preliminary
objections on the report dated 8th July, 2014 of E&Y. In brief, HPPC
had raised the issues of the Interrogatory/questionnaire submitted by
them not taken into account by E&Y, upteem number of disclaimers in
the said report, no independent cost verification done by E&Y etc. The
Commission had considered all the issues raised by the HPPC and
passed an Order dated 28.07.2014. Thus the issues that survived were
conflict of interest of E&Y and site visit. On this issue the Commission
observes that E&Y was appointed after obtaining confirmation from
both LAPL as well as HPPC during the meeting held on 20th May 2014
by the Commission wherein the Chief Engineer/HPPC, DY. CEO LAPL
and representatives of E&Y were present. However, to remove any
doubt on the issue of conflict of interest, E&Y was directed to file an
affidavit regarding the same. Accordingly, E&Y filed an affidavit dated
25th August, 2014 stating as under:
“I hereby declare to the best of my knowledge that EY LLP had not conflict of interest with Lanco Amarkantak Power Limited at the time of signing the contract with the Haryana Electricity Regulatory Commission i.e. on 9th June, 2014, in a manner so as to affect the independence of EY LLP in relation to performing services mentioned in the contract dated 09th June, 2014 with Haryana Electricity Regulatory Commission”. In this regard the Commission observes that E&Y and for that matter
any big consultancy firm may have handled some business/services
for a firm for consideration in the past but once all such transactions
216 | P a g e
are closed, there do not seem any justification to apprehend
existence of any conflict of interest. It is evident from the affidavit
now submitted by E&Y that that EY LLP had no conflict of interest with
Lanco Amarkantak Power Limited at the time of signing the contract
with the Haryana Electricity Regulatory Commission i.e. on 9th June,
2014.
7.4 In addition to the above E&Y submitted addendum to their
report as well as undertook site visit and submitted a report on the
same. Further, as already stated, E&Y also replied to various queries
of the Commission in respect of capital cost, coal cost etc made vide
e-mail dated 31.10.2014 and note to the clarifications furnished in
response to the additional queries of the Commission. In view of
above and to address the apprehension of HPPC in this regard, the
Commission would like to make it very clear that report submitted by
E&Y has been just another input for determination of tariff amongst a
large number of inputs received in the Commission in the form of
pleadings (both written & oral) in a number of hearings held in the
present case. Consequently, the Commission was bound to apply its
own mind including prudence check to all the claims of LAPL and
records available in the Commission rather than base its judgment
solely on the report submitted by E&Y. Further the Commission did
satisfy itself in the hearing held on 28.07.2014 that E&Y carried out
the assignment in accordance with the scope of work as per the
contract and further directed E&Y to submit an addendum in respect
217 | P a g e
whatever doubts/quarries that still remained as well as to undertake
site visit which was complied with by E&Y as already stated above.
7.5 Further, midway through the proceedings, HPPC submitted that
they are filing a second appeal before the Hon’ble Supreme Court
against the Order of Hon,ble APTEL dated 03.01.2014, in pursuance of
which the present Petition for re-determination of tariff has been filed
by LAPL. Considering the fact that filing an appeal is a statutory right
of the party but until any such appeal is admitted by a court of
competent jurisdiction and stay granted there is no legal embargo on
this Commission to proceed with the present case, the Commission
continued with the proceedings. Moreover, in a number of
proceedings/hearings held in the present case prior to that, HPPC
never mentioned a word about the intended second appeal or its
status thereto. In their submission in pursuance of Commission’s
interim Order dated 15.12.2014, HPPC again submitted that have filed
an appeal against the judgment dated 03.01.2014 of the Hon’ble
APTEL before the Hon’ble Supreme Court, being Civil Appeal No. 3800
of 2014 and that HPPC has also filed an application for interim Orders
on the said Civil Appeal and further that notice on interim application
and Civil Appeal has been issued by Hon’ble Supreme Court to LAPL
and others and matter is pending. As already stated Commission is
not estopped from proceeding in the matter/passing Order in view
thereof.
218 | P a g e
In view of the above discussions, the Commission finds no merit in the
preliminary objections of HPPC with regard to the report submitted by
E&Y and shall now proceed to examine the case on merit.
7.6 Before proceeding further, the Commission observes that the
time granted by the Hon’ble APTEL for passing the Order in the
present case was two months from the date of communication of the
said judgment. However, due to complexity of the case and disputes
raised by the HPPC on the details/data provided by LAPL for re-
determination of tariff in the present case, the Commission sought
some more time from the Hon’ble APTEL. The Hon’ble APTEL was
pleased to grant time till 25.06.2014. However, due to the need
subsequently felt by the Commission for independent verification of
the data/details, which was got done by appointing independent
consultant M/S E&Y, site visit as well as adjournments sought by the
parties, the matter got further delayed beyond the extended time
allowed to the Commission by the Hon’ble APTEL. It was, however,
essential for the Commission to first satisfy itself regarding the
authencity of the voluminous data/details running into several
hundred pages filed by the parties which formed the basis for tariff
determination and then only proceed further to avoid any
factual/computational error and further litigation, hence the delay.
Further, delay was also caused due to insufficient data furnished by
LAPL in their different fillings and certain other inconsistencies which
219 | P a g e
had to be got clarified/ascertained by the Commission before taking
up determination of tariff in the present case.
7.7 The Commission observes that as per Hon’ble APTEL’s Order
dated 03.01.2014, the generation tariff in the present case has to be
determined as under:-
“The interim tariff to be determined by the State Commission as per
the Order of the Hon’ble Supreme Court dated 16.11.2011 has to be in
accordance with the State Commission’s own tariff Regulations of
2008. However, where no specific operational or financial norms have
been specified in the State Commission’s Tariff Regulations, the
provisions of Central Commission’s Regulations of 2009 would be
considered for such parameters.
“The State Commission has to re-determine the interim tariff as per
the directions given in this judgment, pending disposal of the Appeal
before the Hon’ble Supreme Court”.
From the above it is evident that the norms to be reckoned for
determination of generation tariff has to be HERC Regulations, 2008
and where no norms have been specified in the HERC’s Tariff
Regulations then CERC Regulations, 2009 can be based upon.
7.8 The Commission, before proceeding further, would also like to
record certain facts which emerged after the Commission examined
various data/information furnished by LAPL on 30.10.2014 in
220 | P a g e
response to Commission letter dated 22.10.2014. It came out from
the information/data supplied by LAPL on 30.10.2014 that LAPL had
not conducted trial run to demonstrate maximum continuous rating
(MCR) before declaring COD of Unit-2 on 07.05.2011. This information
was held back by the Petitioner LAPL from the Commission until it was
specifically asked for by the Commission. The Commission expresses
its displeasure on the conduct of Petitioner LAPL in this regard.
This above fact first came to light after LAPL was directed vide
Commission letter dated 22.10.2014, besides furnishing other
information/data, to supply a copy of the trial run test (MCR)
conducted before declaration of COD of Unit-2. In reply to this, LAPL,
vide information furnished through affidavit filed on 30.10.2014,
submitted that “the trial run test (MCR) could not be conducted before
the declaration of COD of Unit-2 due to non-availability of
transmission facility; however the Unit running on continuous basis on
available capacity has been demonstrated before COD”. The reply
furnished by LAPL on this point is reproduced below:-
“The scheduling of power in terms of APTEL interim Order dated
23.03.2011 in Appeal No. 15/2011 to PTC for onward supply to the
Haryana Dicoms was commenced from 07.05.2011 i.e. the date from
which the scheduling was allowed by WRLDC, even though the long
term opened access (LTOA) for Unit-2 was not operationalized. The
responsibility of arranging LTOA for both Units was with PTC as it was
221 | P a g e
PTC who was the applicant for LTOA and had signed BPTA with CTU.
The power was being evacuated through the interim LILO
arrangement and based on grid/ transmission constraints. In
accordance with the CERC Tariff Regulations, 2009 which define the
date of commercial operation (COD) as the date from which the
scheduling process was fully implemented as per the Indian Electricity
Grid Code (IEGC), LAPL had declared 07.05.2011 as the commercial
operation date (COD) of Unit 2 as from that date the scheduling of
power to the beneficiaries had commenced. The trial run test (MCR)
could not be conducted before the declaration of COD of Unit 2 due to
non- availability of transmission facility. However the Unit running on
continuous basis on available capacity has been demonstrated before
COD. Further LAPL had considered the revenues generated from sale
of infirm power up to 06.05.2011 which have been deducted from the
capital cost for ascertaining the completed capital cost of the project
for determination of tariff”
Further, from the perusal of the letters exchanged by LAPL with
SECL, MoP, CEA regarding coal allocation (copies of which were
supplied by LAPL along with the affidavit dated 30.10.2014), it was
noted that whereas in the application dated 13.01.2014 filed by LAPL
with the Commission for tariff determination, the COD of Unit-2 had
been given as 07.05.2011, in a letter dated 15.12.2011 written by
LAPL to MoP LAPL expressed its inability to commission the Unit – 2
even up to 31.12.2011 and requested MoP to recommend to the
222 | P a g e
Ministry of Coal to ask SECL to continue coal supply beyond
31.12.2011 without insisting for compliance of achievement of COD
up to 31.12.2011. The relevant part of the letter is reproduced
below:-
“…. further we apprehend that in the pretext of not meeting the
special milestone related to achievement of COD by 31st December,
2011, SECL may stop supply of coal beyond 31st December, 2011 to
LAPL Unit – 2. …… as you are already aware, we have commissioned
the Unit - 2 of our project on 25th March, 2010 itself and due to
reasons beyond our control we could not declare COD”.
Besides in a letter dated 17.05.2012 of SECL addressed to Coal
India Limited, (CIL), it had been stated as under:-
“At present, supplies to above Unit are being continued under MOU.
However, since COD was not declared by the above Unit by
31.12.2011, the matter was referred by CIL to MOC and subsequently
deliberated in the SLC (LT) meeting held on 14.02.2012. Relevant
extracts of minutes of above SLC (LT) meeting…”
From this correspondence, it was absolutely clear that LAPL had not
declared COD of Unit-2 even until December, 2011.
In this context it would be relevant to refer to the definition of
COD as given in the HERC Tariff Regulations, 2008 and CERC Tariff
Regulations of 2009 which are reproduced below:-
Definition of COD as per HERC Tariff Regulations.
3(j) ‘Date of Commercial Operation’ (COD) In relation to a Unit mean
the date declared by the generator after demonstrating the Maximum
223 | P a g e
Continuous Rating (MCR) or Installed Capacity through a successful
trial run after notice to the beneficiaries and in relation to the
generating station the date of commercial operation means the date
of commercial operation of the last Unit or block of the generating
station;
Definition of COD as per CERC Tariff Regulations.
3(12) ‘date of commercial operation’ or ‘COD’ means (a) In relation to a Unit or block of the thermal generating station,
the date declared by the generation company after demonstrating the maximum continuons rating (MCR) or the installed capacity (CI) through a successful trial run after notice to the beneficiaries, from 0000 hour of which scheduling process as per the Indian Electricity Grid Code (IEGC) is fully implemented, and in relation to the generation station as a whole, the date of commercial operation of the last Unit or block of the generating station;
From the definitions of COD , it is evident that before
declaration of COD of a thermal generation station or Unit, it is
mandatory for the generation company to demonstrate continuous
maximum rating (MCR) of the station/Unit by conducting a successful
trial run with notice to the beneficiaries. But LAPL, as stated above
and as categorically admitted by them in their Affidavit dated
30.10.2014, had not conducted trial run of Unit 2 to demonstrate
MCR before declaration of COD. Thus LAPL had not complied with
the provisions regarding declaration of COD of neither HERC Tariff
Regulations, 2008 nor CERC Regulations of 2009 before declaration
of COD of Unit 2. In the given situation the issue which needed to be
decided by the Commission before preceding for tariff determination
was, whether, in view of factual position which had emerged as
224 | P a g e
stated above, COD of 07.05.2011 of Unit-2 declared by LAPL (without
conducting trial run) and stated as such in the application dated
13.01.2014 could be considered for Tariff determination or not?
The Commission devoted considerable time deliberating on this
issue as it was germane to the issue of the process of tariff
determination. LAPL on its part had submitted in their Affidavit dated
30.10.2014 that since the scheduling of power from Unit-2, in terms
of APTEL interim Order dated 23.03.2011, to PTC for onwards supply
to Haryana Discoms had commenced from 07.05.2011 i.e. the date
from which scheduling of power from Unit 2 was allowed by WRLDC,
LAPL, in line with CERC Tariff regulations which define the date of
commercial operation as the date from which the scheduling process
was fully implemented as per IEGC, had declared 07.05.2011 as the
COD of Unit- 2. This contention of LAPL was, however, without any
merit and was a misinterpretation of CERC Regulations, 2009.
Commission observed that in the first instance WRLDC should not
have allowed scheduling of power from Unit-2 without ascertaining
that LAPL has declared COD of Unit-2 after following the due
procedure as per CERC Regulations. Secondly, it was also incumbent
on the part of beneficiaries i.e. PTC and Haryana Discoms to
ascertain, before agreeing to schedule power from Unit-2 w.e.f.
07.05.2011, that LAPL had conducted successful trial run before
declaring COD. Commission further observed that had this fact, that
LAPL had not conducted trial run before declaration of COD, been
225 | P a g e
brought to the notice of the Commission in the application dated
13.01.2014 by LAPL or by Haryana Discoms/ LAPL in the initial stage
of the case, the commission could have considered to refer the
matter back to Hon’ble APTEL for directions. But at that point of time
(i.e. after it was disclosed by LAPL vide their filing dated 30.10.2014
that it had not conducted trial run before declaration of COD) when
the case had already been delayed due to the reasons earlier stated
in this Order, it would not had been appropriate for the Commission
to refer the matter back to Hon’ble APTEL at that stage. The point
was that the Commission had been directed to determine the Tariff
as per HERC Tariff Regulations and the first step for determination of
tariff under these Regulations was to determine the completed
capital cost on COD. Further the tariff determined under these
Regulations would be applicable from the date of commercial
operation (COD) onwards. So if COD of 07.05.2011 was not accepted,
the tariff determination process got stalled.
7.9 To have the views/submissions of Respondents PTC and HPPC
on the issue of COD as also on other information/clarifications
furnished by LAPL vide Affidavit dated 30.10.2014, copies of the
same were supplied to PTC and HPPC and hearing was held on
15.12.2014 which was attended by all the parties. Further based on
submission/arguments made in the hearing, Commission, vide
interim Order dated 15.12.22014, directed LAPL to submitted the
following documents/information.
226 | P a g e
i) Documentary evidence to establish the fact that LAPL
Unit-2 was capable of generating at the rated capacity.
ii) Performance Guarantee Test conducted by the EPC
contractor and details of LDs/penalties imposed if any.
iii) Documentary evidence in support of request(s) made for
making the Grid available for trial-run post
synchronization and response/replies received.
From perusal of the reply furnished by LAPL on the above points vide
their filing dated 19.12.2014, the Commission observed as under:-
a) Unit-2 was run continuously for 3 days from 11.08.2010 to
13.08.2010 when Unit-1 was stated to be under
shutdown. From the slot wise (15 minute) energy
generation data enclosed, it is seen that Unit was run at
an average PLF of 93.40% and the generation varied from
260 MW (approx.) to 294.50 MW (approx.). As stated by
LAPL, due to non-availability of LTOA, which was PTC’s
responsibility as per PPA, Unit-2 could not achieve full
capacity due to transmission constraints.
227 | P a g e
b) LAPL conducted Preliminary Acceptance Test for 7 days
continuous running during the period 04.10.2010 to
10.10.2010 which was witnessed by Lender’s engineer,
the EPC contractor and Lanco but PTC and beneficiaries
were not informed. From the copy of the load record and
CRT data for 7 days furnished by LAPL, it is seen that there
were large dips in the generation during 3 days as visible
from the load curve during 7 days running. The maximum
load touched is 297.296 MW on 04.10.2014. The Unit did
not touch the rated capacity of 300 MW even once during
these seven days.
c) Performance Guarantee Test was conducted from
04.01.2012 to 07.01. 2012 when Unit-1 was on shutdown.
Copy of Performance test report of Steam Generator and
Steam Turbine has been enclosed wherein it has been
shown that Steam Generator and Steam Turbine met the
design values during the test but test results in respect of
performance test on the turbo generator have not been
furnished. LAPL has stated that “based on above test on
achieving guaranteed performance and due to non-
availability of power evacuation capacity which was
beyond EPC contractor’s scope, no LD /penalty was
imposed on the EPC contractor”.
228 | P a g e
d) LAPL has again reiterated that (MCR) test could not be
conducted due to non-availability of downstream
transmission facilities which prevented simultaneously
running of both Units (2X300 MW) at peak load and in the
light of said circumstances, Lanco considered the date
w.e.f. which scheduling of power of Unit-2 was allowed by
WRLDC i.e. 07.05.2011 as the COD which is accepted by all
parties.
e) In response to directive of the Commission at (iii) above,
LAPL has stated that non-availability of downstream
transmission facilities had caused frequent grid
restrictions which prevented simultaneous running of
both the Units on peak load and therefore there was no
occasion for Lanco to have made the requests to
appropriate authorities like WRLDC as it was WRLDC itself
which was imposing restrictions on generation.
The Commission has perused the above submissions
(supra) and is not inclined to accept the arguments advanced by
LAPL, particularly in view of submissions made by WRLDC in the
proceedings before CERC in case of Petition no. 289 and 290 of
2010, as recorded in CERC Order dated 09.02.2014 (referred to in
the later part of this Order) wherein WRLDC stated that “considering
the delay in Commissioning schedule of WR pooling station near
229 | P a g e
Sipat, a System Protection Scheme (SPS) has been put in operation
progressively for both Units of LPL starting from 01.09.2010 to
ensure grid security as well as evacuation of power from both Units
of LPL” It is therefore apparent that it was only because of lack of
serious efforts on the part of LAPL that MCR test on Unit-2 could not
be conducted by LAPpL before declaration of COD.
7.10 Prior to the hearing held on 15.12.2014, the Commission
vide letter dated 01.12.2014, had asked LAPL to submit its reply
/clarification on the issue of ‘Declaration of COD of the project by
lanco viz-a-viz HERC Tariff Regulations’, in response to which LAPL
has submitted that “at the relevant time when COD for Unit-2
occurred, it was nobody’s case that HERC Tariff Regulations, 2008
would apply. It was only pursuant to APTEL’s judgment dated
03.01.014, it was decided that interim tariff of Unit-2 shall be
determined as per HERC Tariff Regulations, 2008. Accordingly, the
COD i.e. 07.05.2011 ought to be taken as the same for determination
of interim tariff as per the Hon’ble Supreme Court Order dated
16.12.2011 and as per the stand of the parties. It is significant to
state that no dispute has ever been raised by HPGCL or PTC in respect
of COD, which has also been recognized by the CEA”.
7.11 PTC, in respect of COD, has stated in their filing dated
30.12.2014 in compliance of Commission’s interim Order dated
15.12.2014, that PTC has not accepted COD of 07.05.2012 of Unit-2
230 | P a g e
as no evidence of any Commissioning or load test has been provided
by LAPL to PTC.
7.12 HPPC in their filing dated 02.01.2015, in response to the
interim Order dated 15.12.2014, has also stated that LAPL has not
undertaken proper performance test in regard to rated capacity of
the Unit, in particularly, commissioning test of running the Unit
continuously for a period of 72 hours to the extent of 95% of the
contracted capacity.
From the position brought out above it is apparent that irrespective
of the reasons the admitted position is that LAPL has not conducted
the trial run to demonstrate Maximum Continuous Rating of the Unit
before declaration of COD on 07.05.2011. This fact was first admitted
by LAPL in their submissions made vide affidavit dated 30.10.2014
and again vide their filing dated 19.12.22014. The main reason
advanced by LAPL is that trial run could not be conducted due to
non-operationalization of LTOA. But now that LTOA for Unit-2 has
been stated to be operationalized w.e.f. 01.01.2015, it would be
desirable as also essential that LAPL conducts trial run to
demonstrate MCR of 300 MW of Unit-2, to claim fixed charges as
determined vide this Order.
7.13 The commission, after careful consideration of
submissions of all the parties on the issue of COD, the material on
231 | P a g e
record of the Commission and all other aspects, has decided to
proceed with determination of tariff considering 07.05.2011 as the
commercial operation date (COD) of Unit-2 for the purpose of tariff
determination keeping in view that WRLDC had allowed scheduling
of power from Unit-2 w.e.f. 07.05.2011 and further Haryana Discom
had also started scheduling power from this Unit w.e.f. 07.05.2011
although in the opinion of the commission LAPL had not complied
with the provisions of relevant Regulations before declaration of
COD. The Commission at the same time directs LAPL to conduct trial
run of Unit-2 to demonstrate its Maximum Continuous Rating
(MCR) of 300 MW as per the Regulations within three months from
the date of this Order and in the event of failure of LAPL to conduct
MCR test within this period, the matter shall be brought before this
Commission by HPPC/PTC for taking appropriate action in the
matter.
The Commission has, accordingly, proceeded to determine
various cost components for determination of generation tariff in the
present case considering COD of LAPL Unit-2 as 07.05.2011.
8.0 Capital Cost:-
8.1 The Commission in its earlier Order dated 17.10.2012 had
approved the capital cost as Rs. 1007.731 cr. i.e original capital cost of
Rs. 1340.041 cr. estimated by PFC as per Detailed Project Report
232 | P a g e
(DPR) less Rs. 332.31 cr., the net earning by LAPL on account of sale of
infirm power from the date of synchronization to COD of UNIT-2 of
LAPL. The Hon’ble APPTEL in its Order dated 03.01.2014 with regard
to capital cost had observed as under:-
“61. The State Commission has deviated from its own Regulations for determination of the capital cost based on the actual expenditure as no audited account was made available for Unit-2 from which power was contracted to Haryana. Further, there was nothing on record to establish that the Appellant exercised sufficient prudence to efficiently execute the Project within the cost and time line as originally envisaged. 62. Of course, we agree with the Haryana Power (R2) that the
State Commission has to apply prudence check in determining the capital cost based on the audited accounts. We find from the impugned Order that adequate materials were not available before the State Commission to verify the capital cost incurred on Unit No.2 of the Appellant and to examine that the time and cost overrun was not due to reasons attributable to the Appellant and in the absence of the requisite materials the State Commission approved the capital cost as per the Detailed Project Report. 63. Therefore, we direct the Appellant to submit the necessary details of capital cost for Unit No.2 including apportionment of cost of common facilities and detailed reasons for time and cost overrun of the Project before the State Commission to enable the State Commission to apply prudence check and determine the capital cost according to its own Tariff Regulations. The State Commission in turn shall determine the capital cost as per its Regulations after the requisite details are furnished by the Appellant”.
The Commission, therefore, is required to determine the capital
cost of Unit-2 of LAPL as per HERC Tariff Regulations, 2008 i.e starting
from competed capital cost on COD claimed by LAPL, Commission
should apply prudence check keeping in view the reasons of time and
cost overrun submitted by LAPL and reasonableness of various cost
components to arrive at the capital cost that can be considered for
tariff determination. Regulation 12 and 14 of HERC Tariff Regulations
233 | P a g e
regarding capital cost and sale of infirm power as per which capital
cost is to be determined are reproduced below:-
“12 . Capital Cost. –
(1) The actual expenditure incurred on the date of completion of the
project shall form the basis for fixation of final tariff. Investments made
prior to 1/04/2008 in the case of the existing generating stations shall be
accepted for reckoning capital cost on the basis of audited accounts. The
final tariff shall be determined based on the capital expenditure allowed
by the Commission and the expenditure actually incurred up to the date
of commercial operation of the generating station and shall include
capitalized initial spares, subject to ceiling norms mentioned below, as a
percentage of plant and equipment cost:
(i) Coal based projects 2.5%
(ii) Gas Turbine/CCGT 4.0%
(2)The admissibility of the capital cost shall be subject to the prudence
check by the Commission. This shall, however, be limited to the
reasonableness of the capital cost, financing structure, interest during
construction, working capital margin, efficient technology and such other
matters. Any benefit from capital restructuring shall be passed on to the
beneficiaries.
Provided that where the power purchase agreement entered into between
the generating company and the beneficiaries provides a ceiling of actual
expenditure, the capital expenditure shall not exceed such ceiling for
determination of tariff;
Provided further that any person intending to establish, operate and
maintain a generating station may make an application before the
Commission for ' in principle' acceptance of the project capital cost and
financing plan before taking up a project through a Petition in
accordance with the procedure specified in the appendix – III to these
regulations, as applicable from time to time. The Petition shall contain
information regarding salient features of the project including capacity,
location, site specific features, fuel, beneficiaries, break up of capital cost
estimates, financial package, schedule of commissioning, reference price
level, estimated completion cost including foreign exchange component, if
234 | P a g e
any, consent of beneficiary licensees to whom the electricity is proposed
to be sold etc.;
Provided also that where the Commission has given ‘in principle’
acceptance to the estimates of project capital cost and financing plan, the
same shall be the guiding factor for applying prudence check on the
actual capital expenditure;
Provided also that in case of the existing generating stations, the capital
cost admitted by the Commission prior to 1.4.2008 shall form the basis
for determination of tariff.
14. Sale of Infirm Power:
Infirm power shall be accounted as Unscheduled Interchange (UI) and
paid for from the State UI pool account at the applicable frequency-
linked UI rates as may be determined by the CERC from time to time. Any
revenue earned by the generating company from sale of infirm power,
shall be taken as reduction in capital cost and shall not be treated as
revenue.”
As already stated the capital cost of Unit-2 of LAPL as
originally estimated by PFC as per DPR was Rs. 1340.041 crores. The
financial closure of Unit-2 was achieved by LAPL on 15.09.2006. The
construction period was estimated to be three years and the
scheduled COD of this Unit was 15.09.2009. But the synchronization
/commissioning of the Unit got delayed. The Unit was synchronized
for the first time on 22.02.2010 and achieved full load on 25.03.2010.
COD of Unit also got subsequently delayed and LAPL finally declared
Unit-2 on commercial operation on 07.05.2011, though without
conducting trial run almost 4 years and 8 months after financial
closure. The delay in COD impacted the capital cost primarily by way
of increase in IDC. The certified capital cost as on COD, as submitted
by LAPL in their Petition for determination of tariff supported with
Auditor’s certificate, is Rs. 1643.17 crores (gross) and Rs. 1331.89
235 | P a g e
crores, net of revenue earned (Rs. 311.28 crores) by LAPL from sale of
infirm power less fuel cost incurred for generation of infirm power
from the date of synchronization to COD. The certified capital cost on
COD as given in Annexure-1 enclosed with Auditor’s certificate
submitted by LAPL is as under:-
Particulars Amount
(Rs. In Crores)
Capital Cost as 31 March 2010 - As per Books (A) 1459.59
Expenses charged to Profit and Loss Account : (B)
Year: 2009-10
Administrative Expenses from 26 March 2010 to 31 March 2010
12.48
Finance Cost from 26 March 2010 to 31 March 2010 1.87
Year: 2010-11
Administrative Expenses 22.68
Other Direct Expenses 13.01
Finance Cost 119.05
Year: 2011-12 (01 April 2011 to 6 May 2011)
Administrative Expenses 1.56
Other Direct Expenses 0.78
Finance Cost 12.15
Total (B) 183.58
Total C=(A+B) 1643.17
Infirm Power: (D)
Year: 2009-10
Sales 1.35
Fuel Expenses (0.60) 0.75
Year: 2010-11
Sales 424.58
Fuel Expenses (142.41) 282.17
Year: 2011-12 (01 April 2011 to 06 May, 2011)
Sales 44.00
Fuel Expenses (15.64) 28.36
Total-Infirm Power (D) 311.28
Capital Cost on 06 May 2011 (C-D) 1,331.89
The following notes given in the Auditor’s certificate for the capital
cost are worth mentioning here.
236 | P a g e
a) Pursuant to the Order dated 03.01.2014 of the Hon’ble
Appellate Tribunal for Electricity, the Company is submitting
further information to Haryana Electricity Regulatory
Commission (HERC) for re-determination of interim tariff for
supply of power from Unit-II of LAPL, this certificate has been
issued at the request of the company for submission to HERC.
b) We have verified the books of account and other relevant
records & documents of M/s Lanco Amarkantak Power Limited
(LAPL), formerly Lanco Power Limited having its Registered
Office at LANCO House, Plot No.04, Software Units Layout,
Hitech City, Madhapur Hyderabad-500081 and Corporate office
at Plot NO. 3978, Udyog Vihar, Phase 3, Gurgaon 122016.
c) The capital cost certified does not include Margin Money
amounting to Rs. 24.22 crores which is part of project cost
appraised and approved by Power Finance Corporation Ltd.
(Lead Financial Institution).
d) The HERC Regulations contemplate that initial spares are
identified and capitalized as fixed assets and such value shall
not exceed 2.5% of the project cost. The value of initial spares is
included in the cost of respective machineries.
237 | P a g e
It need to be noted that certified capital cost does not include margin
money of Rs. 24.22 cr, which was part of project cost appraised and
approved by PFC. However, LAPL, in the claimed capital cost, has
included margin money of Rs. 24.22 cr. If the margin money is
included, the capital cost on COD works out to Rs. 1667.39 cr. and
after netting of the revenue earned from infirm power (less fuel cost),
the capital cost on COD works out to Rs. 1356.11 cr. as under:-
(Rs. Cr.)
i) Certified capital cost on COD 1643.17 ii) Margin money not included in
the certified cost
24.22
Total 1667.39
iii) Less revenue earned from infirm power (less fuel cost)
311.28
iv) Net capital cost on COD 1356.11
Although in the auditor’s certificate Rs. 1459.59 cr. has been
mentioned as the ‘capital cost as on 31.03.2010- As per Book’, in the
hearing held on 15.12.2014, in response to a query, it was informed
by LAPL that Rs. 1459.59 cr. is the capitalized cost as on the date of
synchronization i.e. 25.03.2010. It is observed that in the auditor’s
certificate, it has not been mentioned that the margin money of Rs.
24.22 cr. needs to be included in the capital cost.
238 | P a g e
The details of capitalized cost of Rs. 1459.59 cr.
(as on 25.03.2010) mentioned in the certified cost as per the Auditor’s
certificate are available in the break-up of the capital cost on COD
furnished by LAPL in the form 5-B enclosed with the Petition.
Summary of the same, package- wise is as under: -
Sr. No.
Description Amount (Rs. Millions)
1 Cost of land &development & RR charges including lease rentals
28.94
2 Total main plant and equipment
i) Total Main Plant (TG) 340.25
iI) Total BoP Mech. 114.84
iii) Total BoP Elect. 143.25
iv) C&I Package 14.63
Total Plant & Equipment excluding Taxes & Duties 612.97
Taxes & Duties 79.94
Total Plant & Equipment including Taxes & Duties 692.91
3 Initial Spares -
4 Total Civil Works 337.51
5 Construction & Pre Commissioning expenses
i) Erection Testing & Commissioning 110.75
ii) Insurance (Const.) 4.58
iii) Tools & Plants -
iv) Startup 8.14
v) Total construction & Pre Commissioning expenses 123.47
6 Overheads
Establishment 49.98
Audit & Accounts 1.20
Total overheads 50.10
7 Total excluding IDC & IC 1232.93
8 Total IDC including Finance charges (up to 25.03.2010 226.66
9 Total 1459.59
In brief, the certified capital cost on COD as submitted in the
Petition is Rs. 1667. 39 cr., gross and Rs. 1356.11 cr. net of earnings
239 | P a g e
from sale of infirm power as against Rs. 1340.04 cr. originally
appraised by PFC. There is a time overrun of 1 year and about 8
months. This has resulted into gross cost overrun of Rs. 327.35 cr. But
the net cost overrun after accounting for the earning from infirm
power is Rs. 16.07 cr. (1356.11- 1340.04) only.
The Petitioner has submitted that it is entitled to the actual
expenditure incurred as on the date of completion of the project which
is Rs. 1356.11 cr. to be considered as capital cost for the
determination of tariff as per Regulation 12 of HERC Tariff Regulations,
2012.
Regarding detailed reasons for time and cost overrun of the
project, the Petitioner has submitted as under:-
“LAPL had duly exercised prudence to efficiently execute
the project within the cost and timeline as originally envisaged.
There were unequivocally agreed Force Majeure conditions
that caused delay in commissioning the project. The
commissioning of the Project was delayed due to occurrence of
Force Majeure events which were not within reasonable
control of LAPL and could not be prevented by taking
reasonable care. LAPL had duly informed PTC India Limited
from time to time in this regard.
M/s Dongfang Electric Corporation, China (DEC), was
LAPL’s supplier of main plant equipment and BTG component of
the project. Manufacturing facilities of DEC were severely
damaged due to a powerful earthquake in China on 12.05.2008
and DEC could not supply the machines and equipments and
vis- a- vis the same could not be received by LAPL in time.
240 | P a g e
Due to new Visa Policy enforced by Government of India
in September/October 2009, all the Chinese Engineers of DEC,
who were supervising the erection, testing and commissioning
activities at the project site were forced to leave the country on
or before 31-10-2009 that caused non availability of Chinese
Experts for supervising the erection, testing and commissioning
activities. To ensure warranty and guarantee of the plant and
equipment, alternate arrangement for the work of erection
commissioning was not possible. Due to the said policy, 40
Chinese engineers/executives could not be deployed for a
period of about 4-5 months i.e. from September, 2009 to Feb,
2010 which resulted in delay in erection, testing and
commissioning. LAPL had duly informed PTC India Limited vide
letter dated 28-05-2008 and subsequently submitted a report
vide letter dated 5-12-2008 with respect to aforesaid Force
Majeure events. The above said Force Majeure events were
duly acknowledged and accepted by PTC and PTC accordingly
filed Case no. HERC/PRO -12 dated 13.05.2010 before the
learned Commission.
Due to non-availability of the long term open access
(which was purchaser’s obligation), the testing and
commissioning activities of Unit-2 could not be completed in
time. Though an interim LILO arrangement was made for
connecting Unit-2 to the 400 kV Korba-Sipat transmission line
for evacuation of power, continuous full load operation of the
Unit-2 was not possible in the absence of long term open access
which was the purchaser’s obligation. Due to non-
operationalization of long term open access, the transmission
constraints persisted throughout the period of generation of
infirm power which prevented the continuous full load
operation of Unit-2 and which was beyond the reasonable
241 | P a g e
control of Lanco. During the period up to the COD, (COD was
declared on 07.05.2011 when WRLDC allowed scheduling of
power), the Unit was running intermittently on “as and when
available basis” at part load and generating infirm power.
The Commission duly appreciated and acknowledged
as well as accepted the aforesaid Force Majeure event in its
Order dated 02-02-2011 and held that “Force Majeure Event as
claimed by PTC/LAPL did happen and the same were not
disputed by HPGCL”. Lanco had challenged the said Order dated
02.02.2011 before the Hon’ble Supreme Court but it is a fact on
record that the said finding in the Order dated 02.02.2011 has
not been assailed either by Lanco or HPGCL (HPPC) or for that
matter by PTC.
LAPL lead lender PFC has approved the Project cost
overrun. The reasons for delay in commissioning of the project
of LAPL were reasonable and appropriate which were noted by
the majority judgment dated 09.02.2012 passed by Central
Electricity Regulatory Commission (Para 40 of the judgment)”.
The Respondent HPGCL/HPPC in respect of capital
cost has submitted as under:-
i. In the previous proceedings Lanco admittedly had defaulted in
placing adequate material before the Commission. The Hon’ble
APTEL has directed the Petitioner to submit necessary details of
capital cost of Unit-2 including the apportionment of the cost of
common facilities as well as detailed reasons for the time and cost
overrun to enable the Commission to apply prudent check.
242 | P a g e
Despite specific directions of Hon’ble APTEL , the Petitioner has
not furnished the requisite details relating to capital cost of Unit-2
along with Auditor’s certificate as well as basis for apportionment
of the cost of common facilities. In the absence of same, capital
cost and other tariff elements cannot be effectively determined
by the Commission.
ii. The generating station of Lanco consists of two Units of 300 MW
and two Units of 600 MW each with aggregate capacity of 1920
MW. Respondent have to get power only from Unit-2 of 300 MW
which constitute only 15.62% of total capacity. There are number
of common facilities such as land, service buildings, administrative
buildings, field hostels, residential colonies, sewerage treatment
plant, drainage, air conditioning system etc. which are related to
all the Units and not restricted to Unit-2 alone. Cost of such
facilities to the extent of 15.62% alone can be apportioned to Unit
-2.
iii. Lanco has only apportioned the common facilities amongst Units
1 and 2 without considering the impact of such common facilities
qua Units 3 and 4 of 660 MW each. The apportionment between
Units 1 and 2 is also in an arbitrary manner undertaken at the
whims of Lanco. There is no Auditor’s Certificate verifying the
apportionment or the basis of apportionment.
iv. The Auditor’s certificate dated 12.01.2014 attached to the
Petition is not a proper certificate approving the apportionment
of cost of common facilities in view of number of disclaimers
mentioned in the certificate by auditors.
v. The Commission is fully empowered to and has the statutory
function to undertake the prudent check. Such exercise of powers
by the Commission, notwithstanding any approval of capital cost
by the CEA or by the auditors etc., have been now well settled as
243 | P a g e
held by Hon’ble Supreme Court in case of West Bengal Electricity
Regulatory Commission vs. CESC (2002) 81 SCC 715 and by
Hon’ble APTEL in case of Kerala State Electricity Board vs. Kerala
State Electricity Regulatory Commission, Appeal No. 177 of 2009
dated 13.01.2011.
vi. The prudence check is also required to be undertaken by the
Commission in Order to determine whether any part of the capital
expenditure involve minor assets or assets not relevant for the
generation of electricity. Accordingly, the expenditure being
supported by accounting vouchers for the purpose of the
Companies Act, is not sufficient. The Generating Company is
required to establish to the satisfaction of the Hon’ble
Commission the need for capital expenditure, incurring of such
capital expenditure in a structured manner and the total
expenditure being reasonable and just. The Petitioner was to give
details of sale of power prior to COD pertaining to Unit-2. The
annual accounts of the Petitioner indicate a total sale of Rs
1889.10 Crores during the period 2009-10 to 2010-11. In
addition, there was a sale of infirm power from 1st April 2011 to
6th May 2011 for which details have not been provided. This
includes revenue from infirm power and UI charges from Unit 1
and 2. Admittedly, the Petitioner has accounted for a specified
amount to be adjusted for Unit - 1 in the proceedings before the
Madhya Pradesh Electricity Regulatory Commission. Accordingly,
the balance pertains to Unit - 2. Despite opportunities given, the
Petitioner has not provided the break-up of Rs 1889.10 Crores. In
view of the failure of the Petitioner to provide such details,
adverse inference needs to be drawn against the Petitioner to the
effect that much more than Rs. 311/- Crores proposed by the
Petitioner, needs to be adjusted in the capital expenditure for
revenue from infirm power and UI Charges.
244 | P a g e
vii. In the Order dated 02.02.2011, the Commission while dealing with
the Force Majeure events pleaded by the Petitioner specifically
held that “…….no relief other than extension in time as explicitly
provided in the PSA/ PPA is admissible”.
In view of the above, the Petitioner cannot claim either IDC or
IEDC or any other compensatory payment by way of cost overrun
or time overrun on account of the delay resulting from the alleged
Force Majeure Event of earthquake in China or the Visa Policy of
the Government of India. This issue stands settled and cannot be
re-opened at this stage.
viii. The Petitioner has to either accept the Order dated 2nd October,
2011 (it should be 02.02.2011) in toto wherein the Commission
has considered the China earthquake, Visa issues of the Chinese
Personnel as Force Majeure, mainly in view of the Respondent not
replying to the notice of Force Majeure given by the Petitioner
and at the same time holding that no cost implications will be
there and the Petitioner is entitled only to time overrun. It is not
now open to the Petitioner to seek cost implications. If the
Petitioner wishes to dispute the finding contained in the Order
dated 2nd October, 2011, then the entire claim on Force Majeure
for China Earthquake or Visa issue etc need to be examined on
merits as the Power Purchase Agreement is not applicable and
accordingly the condition of the Respondent disputing the
condition of Force Majeure will not be applicable. In the absence
of a Power Purchase Agreement, the only applicable provision is
Section 56 of the Contract Act which relieves the performance of
the obligation during the period of the Force Majeure. There is no
higher cost implication to the non-affected party. The affected
party gets released of the obligations to perform during the
period of Force Majeure. The China earthquake or the visa
problems cannot be a Force Majeure as it did not affect the
245 | P a g e
Petitioner. It was not impossible for the Petitioner to perform the
obligations through alternate means.
The issue of Force Majeure or section 56 would arise only if the
performance had become impossible and not merely onerous or
difficult or expensive. This proposition is well settled.
ix. A perusal of the documents furnished by the Petitioner show that
the claim of the Petitioner for delay in commissioning is only on
account of Force Majeure event of earthquake in China. The other
reason for delay given in Lender’s Engineer report is diversion of
rotor of Unit-2 for Unit-1 which cannot be ground for claiming
cost overrun for Unit-2. Further allegation of Force Majeure event
of change in visa policy of GOI has been raised by the Petitioner as
an afterthought.
The Respondent has also submitted a comparative analysis with
respect to cost of Ash Handling System, Coal Handling System,
Switch Yard, Railway Siding as submitted by the Petitioner for
Unit- 2 with the cost of corresponding systems of the following
plants.
a) Sagadighi Thermal Power Plant in West Bengal Unit 1&2)
(2x300 MW).
b) Paras Thermal Power Plant (Unit -3 of 250 MW).
c) Parli Thermal Power Plant (Unit -6 of 250 MW).
It has been brought out that the per MW cost for ash handling
system, coal handling system, switch yard and railway siding is much
higher in case of LANCO Unit 1&2 as compared to the corresponding
per MW cost in case of above mentioned plants.
246 | P a g e
LAPL in response to the argument of the Respondent that per
MW cost of ash handling system etc. is higher in case of Unit - 2 as
compared to above plants, submitted that the arbitrary comparison of
the cost of a System/ Equipment with other power plants is not
appropriate as it depends on various factors such as compete scope of
the system, plant layout, make of the equipments, supplier of system,
cost components etc. which vary from plant to plant; What is most
relevant is the total project cost which has an impact on the tariff
passed on to the consumers of the State.
LAPL has submitted that capital cost of Rs. 4.52 crore/ MW of
Unit 2 based on completed capital cost of Rs. 1356.11 crore is quite
reasonable and in support of their contention has furnished the capital
cost of some other plants commissioned during 2007-2010 as
approved by CERC/ SERCs as under:-
S. No Plant Name Approved
Capital Cost in Rs. Crore
Capacity in MW
Capital Cost (in Rs. Crore Per MW)
Commercial Operation Date (COD)
1 Reliance Rosa (Unit 1&2)
3112.81 600 5.31 Unit1: 12.3.2010 Unit 2:30.06.2010
2 Kobra Stage 3 2588.28 500 5.18 Unit1: 21.03.2011
3 Chabra (Unit 1&2) 2416.00 500 4.83 Unit1: 11.06.2010 Unit2: 15.10.2011
4 Parli (Unit 6) 1155.35 250 4.62 Unit6: 01.11.2007
5 Sagardighi (Unit 2&3)
2672.25 600 4.45 Unit1: 07.09.2008 Unit2: 06.11.2008
6 Lanco (Unit 2) 1356.11 300 4.52 Unit2: 07.05.2011
247 | P a g e
Regarding arguments of HPGCL/ HPPC on apportionment of the cost of
common facilities, Petitioner has submitted that “there are no
common facilities between Units-I & II on the one hand and Units-III&IV
on the other hand; Further, there will be no common facilities between
Units-I & II on the one hand and Units-V & VI (in case planned in future)
on the other hand; The contention of HPCC that generating station of
Lanco was conceived with 1920 MW capacity is completely baseless
and misleading. Units III & IV (2X660MW) are being set up separately
from Unit-I & Unit-II and the said Units are in construction phase and
are expected to be commissioned in FY 2014-15 whereas Unit-I & Unit-
II are already operational; Unit-I was conceptualized, planned and
achieved financial closure on 20.09.2005 much prior to financial
closure of Unit-II ; Further, Unit-II has been appraised separately by the
lenders and its financial closure happened on 15.09.2006 i.e. about one
year after the financial closure of Unit-I; It is noteworthy to state that
the two Units i.e. Unit-I & Unit-II were separately conceptualized
appraised and executed by augmentation/ modification/ addition to
the existing facilities of Unit-I ; It is wrong and denied that Unit-II of
Lanco has been part of 1960 MW at any point of time as alleged or
otherwise; It is wrong to say that Unit-II of Lanco will be part of 3240
MW project.”
The issue of Capital Cost that could be considered by this
Commission for fixation of tariff including the apportionment of
common assets between Unit- 1 and Unit –2 and between Unit–1 & 2
248 | P a g e
on one hand and Unit-3 & Unit-4 on the other hand at the same site
was vehemently contested by the Petitioner as well as Respondents
during the course of number of hearings held by the Commission in
the matter. While the Petitioner argued that the Commission may
consider capital cost of Rs. 1356.11 Crore i.e. Rs. 1667.39 Crore netted
off for revenue earned on account of UI, which is the actual capital
cost incurred and verified by the auditor. Per Contra HPGCL/HPPC has
argued that the capital cost for determination of tariff ought to be
determined by the Commission after applying prudence check on the
actual capital cost claimed to have been incurred by the Petitioner.
The Respondent further submitted that the Capital Cost considered by
the Commission in its Order dated 17.10.2012 may only be considered
and the claims of IDC/IEDC due to force majeure ought not to be
allowed.
While the Commission agrees with the HPPC that prudence
check is essential and the Commission may not solely rely on the
audited accounts/auditor’s certificate, the Commission finds it difficult
to agree with HPPC that the details of cost of Ash Handling System,
Coal Handling System, Switch Yard, Railway Siding etc. of a few power
projects cited by them can in any manner be considered as the
benchmark to determine the reasonableness of the cost of these
common facilities as included in the completed capital cost of Unit-2 of
the Petitioner. Commission agrees with the contention of the
Petitioner that the arbitrary comparison of the cost of a System/
249 | P a g e
Equipment with other Power Plants would not be appropriate as it
depends on various factors which vary from plant to plant.
On the issue of apportionment of cost of common facilities,
Respondents HPGCL/HPPC had initially submitted that generating
station of LAPL comprise of four Units with a total capacity of 1920
MW; capacity of Unit- 2, from which Respondent have to get power,
constitute only 15.62% of the total capacity, there are a number of
common facilities [refer para 4 (ii)] which relate to all the four Units and
their use is not restricted to Unit-2 alone and as such cost of such
facilities to the extent of 15.62 % alone can be apportioned to Unit-2.
Subsequent to site visit, HPGCL/ HPPC submitted that as per the
feedback gathered by them during the site visit, there seems a proposal
to expand the generating station by another two Units of 660 MW each
and in that case, Unit-2 would become a part of still larger capacity of
3240 MW. Extending their above argument further, HPGCL/ HPPC
submitted that cost of such facilities which may relate to all the 6 Units
could be apportioned to Unit-2 only to the extent of not more than
10%. HPGCL/ HPPC further submitted that it would be imprudent on
the part of Petitioner to have independent railway siding, water intake
system, switch yard etc. for each of the generating Units.
The Commission finds no merit in the above arguments of the
Respondents. More so because Unit-3 and 4 which are still under
construction and Unit-5 and 6 which are reportedly at a planning stage,
250 | P a g e
is of much larger capacity i.e. 660 MW each as compared to Unit-1 and
2 of 300 MW each. The existing common facilities of Unit- 1 and 2 have
been designed for a capacity of 2x300 MW and the same, in all
probability, cannot be used/ shared for Unit-3 and 4 or Unit-5 and 6.
Further, as stated in the Petition by LAPL, Unit-1 was independently
conceptualized planned and executed and common facilities were
created for Unit-1 on standalone basis. Thereafter existing facilities of
Unit-1 were augmented to cater to the requirements of Unit-2. This
also lends credence to the inference that common facilities of Unit-1
and 2 would not be suitable for sharing with Unit-3 and 4 or Unit- 5 and
6. The Commission observed that the Respondent (HPPC) has taken
contradictory stands i.e. on the one hand they would argue that there
are common (shared) assets between various Units at LAPL site while
on the other hand they would argue that it is prudent practice to have
shared assets when several generating Units are planned at the same
site in Order to garner economies of scale.
The Commission has carefully perused the detailed objections/
submissions made by the Respondent HPGCL/HPPC on the
apportionment of cost of common facilities, the counter submissions/
clarifications submitted by Petitioner in respect of each of the
objections of Respondent HPGCL/ HPPC and after considering the same,
intend to agree with the Petitioner that common facilities of Unit- 1 and
2 are not in any way shared with Unit- 3 and 4 or for that matter with
Unit-5 and 6. LAPL also filed an Affidavit on 9.4.2014 stating that
251 | P a g e
facilities built for operational Unit- 1 and 2 will not be used for Unit-3
and Unit-4. Further with reference to the objection of HPGCL that
common facilities namely i) Existing Roads within the power project of
the Petitioner ii) Administrative Building iii) Service Building iv) Fire
Station v) Field Hostel and vi) Drainage System created for Unit-1 and 2
are likely to be used/shared for/with Unit - 3 & 4, LAPL has categorically
stated that “there is separate plant entry and roads, drains,
administrative building, service building, fire station for the under
construction Unit 3 and 4 and these will not be shared with Unit 1 & 2”.
The inference drawn as above by the Commission in respect of
sharing of common facilities is also supported by the Report furnished
by E&Y after the site visit on 16th and 17th August, 2014 along with
representatives of LAPL and HPGCL/HPPC. In this Report, E&Y has
stated that, after the site visit, following points stood clearly
established:-
“1. Balance of Plant (BOP) facilities of the existing 2x300MW
shared between Units 1& 2. These are as follows
i. Coal Handling Plant ii. Fuel Handling System iii. Ash Handling Plant iv. Fire Detection & Fire Fighting System v. Raw Water Intake Station vi. Clarified Water System vii. DM Water Plant viii. 400kV Switchyard ix. Miscellaneous auxiliary Units not specifically listed above.
252 | P a g e
2. The capacities of existing facilities designed for 2x300 MW
generation capacity does not allow them to be used for a much
larger 2x660MW capacity of the new plant i.e. Units 3 & 4. The
layouts of the existing plant (Units 1 & 2) and that of the new
plant (Units 3&4) also do not allow the existing BOP facilities for
Units 1 & 2 to be used for Units 3 & 4.
3. The only physical connection between electrical/mechanical
/coal/water systems of the existing plant and the new plant is the
planned interconnection between the two 400kV switchyards,
which are separated by a fence and have their own control rooms
and evacuation arrangements. This connection gives a flexibility of
operation and does not amount to sharing the assets of the
existing plant (Units 1 & 2) with the new plant (Units 3 & 4).
Land: Unit 2 has been built partly on the green belt area for Unit 1.
Additional land has been acquired to leave mandatory green belt
for Units 1&2 taken together. Since 200 acres has been attributed
to Unit 2 and 566.89 acres to Unit 1, the cost of land considered
for Unit 2 is less than half of the total for Units 1& 2 taken
together.
It is our understanding that in a similar manner, part of the
green belt earmarked for Unit 2 has been used for Units 3&4.
Later an equal amount of the land which was taken from Unit 2
253 | P a g e
green belt area for Units 3 & 4 was transferred back to Unit 2 from
the land acquired for Units 3 & 4. Hence, total land allocated to
Unit 2 remained 200 acres and no part of that was used by Units 3
& 4.
Boundary Wall: It is understood that additional boundary wall
created for Unit 2 has been charged to it. Part of this boundary
wall has been dismantled to enlarge the plant area to include
Units 3 & 4. It is also learnt that the boundary wall for the
enlarged plant has been charged to the Units 3&4. Hence there is
no case for reduction in cost of assets charged to Unit 2 on this
account.
Railway tracks and marshalling yards: The layout of tracks (except
a small portion which is described separately below) and that of
the coal unloading facilities is such that the existing facilities
(Units 1&2) cannot be used for the new facilities (Units 3&4).
Land required for railway track for Units 3&4: There is a very
small section of railway track where the railway track for Units
3&4 is laid in parallel with that of existing Units 1&2. It is possible
that laying tracks in that section did not require additional land if
the land earlier acquired was in excess of what was actually used
to lay tracks for Units 1&2. However, if land for this section of the
track has been acquired for Unit 1 and has not been charged to
254 | P a g e
Unit 2, the question of transferring the cost from Unit 2 to Units
3&4 does not arise. In other words, laying these tracks on the land
in question does not impact the cost of Unit 2.”
The Commission in view of the position brought out above
observes that there are no common facilities of Unit-1 & 2 which are
shared or will be shared with Unit- 3 &Unit- 4 or with Unit-5 & Unit- 6.
The cost incurred on the common facilities for Unit -1 & Unit-2
as given in the Petition dated 13.01.2014 was Rs. 635.13 Crore and
Rs. 544.60 Crore respectively i.e. total cost of common facilities of Unit-1
& 2 as per the information provided worked out to Rs. 1179.73 Cr. The
Auditor’s Certificate dated 18.02.2014 certifying the cost incurred on the
common facilities as above was provided by the Petitioner along with the
rejoinder filed on 03.03.2014.
In respect of apportionment of cost of common facilities,
Petitioner has submitted that Unit-1 was independently conceived,
planned and financial closure was achieved in 2005. EPC contracts of
Unit-1 were executed in May, 2005 exclusively for the facilities required
for Unit-1 on standalone basis, Expansion in the form of Unit-2 took place
subsequently, as such only the actual expenditure incurred for
augmentation of existing facilities of Unit-1 to cater the requirements of
Unit-2 have been included in arriving at the capital cost of Unit-2.
255 | P a g e
The apportionment of the cost of common facilities between
Unit-1 & Unit-2 was also reviewed by E & Y in their report. It has been
stated by E & Y that LAPL confirmed through e-mail dated 02.07.2014
that amount of cost considered for common assets for Unit-1 in the
MPERC Order is same as indicated in Annexure- B3 of the Petition dated
13.01.2014 i.e. Rs. 635.13 Cr. However, the total cost of common
facilities for Unit-1 and Unit-2, based on information provided by LAPL
to E & Y, has been given as Rs. 1162.30 Cr. in the E & Y report. Out of
this, based on e-mail dated 02.07.2014 of LAPL to E&Y referred to
above, Rs. 635.13 Cr. pertain to Unit-1 and has been included
accordingly in the capital cost of Unit-1 in the MPERC Order. Thus, the
cost of common facilities to be apportioned to Unit-2 works out to
Rs. 527.17 Cr. (1162.30-635.13) which is less by Rs. 16.85 Cr. as
compared to the cost (Rs. 544.60 Cr.) indicated in the Petition dated
13.01.2014 by LAPL. The difference, it is observed, is on account of the
reason that whereas in Annexure –B3 of Petition dated 13.01.2014, the
cost of land and land development for Unit-2 has been given as Rs.
28.94 Cr. but in the information provided to E & Y by LAPL, it has been
given as Rs. 11.51 Cr. The cost pertaining to land for Unit-2 was
subsequently also intimated by LAPL as Rs. 11.50 Cr. (Land cost Rs. 4.28,
Land development cost Rs. 7.22) in the reply filed by LAPL on 30.10.2014
in response to various queries of the Commission sought vide letter
dated 22.10.2014.
256 | P a g e
The Commission in Order to have further clarity on the issue of
cost of land apportioned to Unit-2, vide interim Order dated 15.12.2014,
directed LAPL to furnish clarification on the following:-
“Details of apportionment of cost of land and land development
cost: The land and development cost was earlier given as Rs. 28.94
cr. in the Petition dated 13.01.2014 but subsequently while
submitting reply to clarification sought by commission land and
development cost was indicated as Rs. 11.5 cr but corresponding
reduction in completed project cost was not made, this may be
clarified.”
In reply to the above, LAPL vide filing dated 19.12.2014,
submitted that all the costs including land development, Design,
Engineering, Supervision and other expenses towards land have been
grouped in the land cost of Rs. 28.94 cr. mentioned at Sr. No. (A) in the
Form 5B and the same is different from the land cost (Rs. 12.00 cr.)
mentioned under project appraisal by lenders. LAPL further submitted
that in the project appraisal, land development cost is covered in the
Non-EPC cost and other items i.e. Design, Engineering etc. are covered
under respective heads. The break-up of the land cost of Rs. 28.94 cr. as
given in the Form 5B has now been given as under:-
i) Land cost : Rs. 4.28 cr.
ii) Land development cost : Rs. 7.22 cr.
257 | P a g e
iii) Cost incurred towards Design Engineering : Rs.17.44 cr.
and other expenses.
The Commission, after careful consideration of the submissions
(supra), is not satisfied with the clarification given in respect of
difference of Rs. 17.44 cr. in the cost of land as intimated vide reply
furnished by LAPL on 30.10.2014 (Rs. 11.50 cr.) and the cost of Rs. 28.94
cr. mentioned in Form 5B in view of the following reasons:-
a) If LAPL’s explanation is accepted i.e. in the project appraisal
cost, the cost of land development (Rs. 7.22 cr.) is covered in
Non-EPC cost and the cost pertaining to Design Engineering etc.
(Rs. 17.44 cr.) is covered in the respective heads, then the cost
of land as given at Sr. No. 1 of the Project appraisal cost should
have been Rs. 4.28 cr. but it has been mentioned as Rs. 12.00 cr.
b) When LAPL was asked in the first instance vide Commission’s
letter dated 22.10.2014 to explain the different figures of cost of
land given in Annexure-B3 of Auditor’s certificate for
apportionment of cost (Rs. 28.938 cr.) and as mentioned in the
project appraisal (Rs. 12.00 cr.), LAPL in their reply furnished on
30.10.2014 had stated that cost of land and land development
was Rs. 11.51 cr. as already indicated in the E&Y report based on
information furnished by them. LAPL in their reply furnished on
30.10.2014 did not mention that the balance cost of Rs. 17.44 cr.
258 | P a g e
pertained to Design Engineering & other expenses in respect of
land. It is only when again questioned by the Commission, vide
above given query that if the cost of land and land development
was Rs. 11.51 cr., then why corresponding reduction (of Rs.
17.44 cr.) was not affected in the capital cost, that the LAPL has
come out with this explanation.
c) The total land and site development cost sought to be given by
the generation company against (A) in the prescribed Form 5B of
the HERC Regulations, 2008, lists following components to be
included under this head:-
Land including Lease Rental.
Rehabilitation & Resettlement (R&R).
Preliminary investigation & Site Development.
As clearly mentioned in the E&Y Report, LAPL had not
undertaken any Rehabilitation and Resettlement for land
acquired for Unit-2 as the land was leased by the State Govt. So
the cost indicated against Sr. No. (A) could have included only
cost of land, cost of site development and lease rentals. As there
is no mention of Design Engineering and other expenses under
this head, so there was no question that LAPL could have
included, as claimed, Design Engineering and other expenses
pertaining to land under this head.
259 | P a g e
d) Another reason to substantiate that clarification given is not
plausible is that, if Rs. 17.44 cr. of the total cost of land
(Rs. 28.94 cr.) pertained to Design Engineering and other
expenses for land, the same would not have been included in
the Auditor’s certificate for cost of common facilities pertaining
to Unit-2 as the Design Engineering and other expenses are
covered under different head and do not form part of common
facilities.
In view of above, Commission observes that LAPL has not been
able to satisfy the Commission regarding the difference of Rs. 17.44 cr.
in the cost of land as mentioned in the Annexure B-3 of the Petition
(Rs. 28.94 cr.) and as given by LAPL to E &Y (Rs. 11.51 cr.) and
mentioned as such by E&Y in their Report while working out the cost of
common facilities. The cost of land to the extent of Rs. 17.44 cr. included
in the cost of common facilities as also in the capital cost on COD is,
therefore, disallowed.
The Commission, therefore, has considered the cost of
common facilities apportioned to Unit-2 as Rs. 526.58 Cr. i.e.
apportioned cost as per Annexure–B3 in the Petition dated 13.01.2014
less excess cost of land & land development amounting to Rs. 17.44 Cr.
(28.94-11.5) booked to Unit-2 by LAPL but disallowed by the
Commission on account of reasons stated above. Necessary
260 | P a g e
adjustment to this effect has been made while approving the capital
cost. Regarding the apportionment of cost of various facilities between
Unit -1 & 2, E & Y, based on their review, has stated that the same is in
Order and the Commission has accepted their recommendations.
Having observed as above, the Commission has proceeded to
examine the completed project cost as on COD claimed by LAPL with a
view to apply prudence check, the reasons for time and cost overrun
and various components of cost overrun in the light of
submissions/counter submissions, relevant Regulations and relevant
judgments of APTEL etc.
The Commission observes that the completed project cost of
Rs. 1667.39 cr. broadly comprises of:-
Rs. in Crores
i) Capitalized cost as on date of synchronization i.e.
25.03.2010
1459.59
ii) Administrative and direct expenses incurred from
26.03.2010 to 06.05.2011
50.51
iii) IDC and finance charges from26.03.2010 to
06.05.2011
133.07
iv) Margin money 24.22
Total 1667.39
261 | P a g e
The Commission has examined the capital cost in two parts as
under:-
i) The capitalized cost on the date of synchronization (25.03.2010).
ii) Expenses incurred from date of synchronization to COD.
It has been submitted by the Petitioner that the project lead
Lender PFC had approved the revised project cost and project cost
overrun. In support of the same, the Petitioner has submitted a copy
of the Note on cost overrun funding prepared by PFC and forwarded to
the Petitioner vide PFC letter dated 23.04.2010. This Note, as stated
therein, was prepared by PFC based on the cost overrun report
received by PFC from M/s Development Consultants Pvt. Ltd. (DCPL),
the Lenders’ Engineer, vide letter dated 15.01.2010. In this Note, PFC
estimated revised project cost as Rs. 1521.97 cr. considering the
synchronization of the Unit on 22.03.2010 with the assumption that
Unit was planned to be put on commercial operation on 30th June,
2010. Expenditure incurred or to be incurred upto the date of
synchronization was considered and balance expenditure upto COD
(30.06.2010) was assumed to be met out of the revenue that would be
available from sale of infirm power. The revised project cost estimate
and the break -up /reasons of cost overrun as given by PFC in this Note
are reproduced below:-
Revised Project Cost Estimate (Rs. in Millions)
Particulars Original Project
Cost
Revised
Project Cost
Cost
Overrun
1 2 3 4 (4-3)
1 Land 120.00 120.00
262 | P a g e
2 EPC Cost
Off-shore CIF supplies 4,702.00 4,483.91 (218.09)
On-Shore Ex works Supplies 2,260.00 2,319.30 59.30
Engg., Transport, Testing & Comm. 1,108.00 1,133.03 25.03
Civil and Construction Works 1,980.00 2,675.30 695.30
3 Non –EPC cost (including Land Development 920.00 1,123.60 203.60
4 Design, Engineering Construction Supervision
& Pre4perative Expenses
285.00 583.20 298.20
5 Tools & Spares 20.00 20.00 -
6 Preliminary Expenses 25.00 11.40 (13.60)
7 Start-up Fuel 110.00 110.00 -
8 Training of O & M Staff 12.00 12.00 -
9 Financial Charges incl. up-front fee 117.00 142.81 25.81
10 Interest During Construction 1,388.20 2,242.95 854.75
11 Margin Money for working capital 242.21 242.21 -
12 Physical contingencies 111.00 - (111.00)
Total (Rs. in millions) 13,400.41 15,219.71 1,819.30
Break-up/reasons for cost overrun are listed below in brief:-
Particular Cost
overruns
(Rs. cr.)
Major reasons for overrun/Areas with increased /modified
scope of works
1 EPC Cost
Off –shore CIF
supplies
(21.81) Saving in the CIF contract in rupee terms due to forex
variation
On-shore Ex works
supplies
5.93 Supply (Ex-works) contract with ZPPL-Extra spares for
critical systems and special tools & plants for maintenance,
in Order to minimize downtime of plant
Engg., Trans, Testing
& Comm.
2.50 Services contract with ZPPL-Delay in supply of material
due to force majeure requiring extended hiring of cranes
and extra deployment of manpower for erection
Civil and construction
works
69.53 Civil contract with ZCIPL-Increase in span of mill and
bunker in Order to match with the requirement of traverse,
of the hoist, and also to provide operational ease; Deck
sheeting in TG building for construction of roof slabs to
expedite construction activities; requirement of pile
foundation for stacker re-claimer hopper entailing additional
expenditure towards manpower and material; price
escalation towards reinforcement steel, structural steel and
cement.
2 Non-EPC Cost
(including Land
Development)
20.36 Under no-EPC contract with LITL-Increase in plinth area. In
the residential colony; construction of road over bridge in
accordance with eh directives of the state authorities
miscellaneous and R & R works requested by local state
bodies and affected village people carried out by LITL
263 | P a g e
3 Design, Engineering,
Construction
Supervision &
Preoperative
Expenses
29.82 Increase in pre-operative expenses based on general
increase in price levels in view of expenditure already
incurred and balance to be incurred till Feb ’10.
4 Preliminary Expenses (1.36) Provision available against preliminary expenses
5 Financial charges incl.
up-front fee
2.58 Variation between estimated and actual expenditures
incurred/to be incurred on the project.
6 Interest During
Construction
85.48 Increase in IDC primarily due to extended period on
account of delay in commissioning and also increase in
interest rates during the construction period, estimated upto
Feb ‘2010.
7 Physical contingencies (11.1) Provision available against contingency provision.
8 Cost overrun 181.93
The actual expenditure upto the date of synchronization i.e.
25.03.2010 was, however, lower (1459.59+24.22=1483.81). It has been
mentioned by PFC in this Note that ‘the details of cost overrun have
also been reviewed by the Lenders’ Engineer M/S DCPL and have been
found to be in Order. Another important observation made by PFC in
this Order is that ‘the COD has been delayed due to force majeure event
of earth quake in China in May ‘08 and the commissioning has been
further delayed due to delay in delivery of generator rotor of Unit-1 for
use in Unit-II, subsequent to damage to the turbine generator of Unit-1
in Jan’09 and usage of Unit-II equipment in Unit-1to optimize the
commissioning time of the Units’.
The Commission observes that Lender’s Engineer report
submitted by LAPL is of December, 2009 and LAPL has failed to submit
Lender’s Engineer report in respect of completed cost of Rs. 1667.39 cr.
as on COD i.e. 07.05.2011 despite asking for the same by the
Commission.
264 | P a g e
As may be seen, the major components of cost overrun
listed/reviewed by PFC in their Note based on Lenders’ Engineer report
on cost overrun corresponding to revised cost estimate of Rs. 1521.71
cr. (which accounted for the expenses incurred or to be incurred up to
February, 2010) are as under:-
Sr. No.
Particulars Cost overrun (Rs. crores)
1. EPC cost
On-shore Ex works supplies 5.93
Civil and construction works 69.53
2. Non-EPC Cost (including Land Development) 20.36
3. Design, Engineering, Construction Supervision &
Preoperative Expenses
29.82
4. Interest During Construction 85.48
The break-up of actual cost overrun corresponding to the
completed project cost of Rs. 1667.39 cr. is given below in the following
table. For the sake of comparison, the break-up of the cost overrun as
given in the Note of PFC corresponding to revised cost of Rs. 1521.71
cr. is also depicted along side.
Particulars Initial appraised Project Cost (by PFC) in 2005 (Rs. Crore)
Revised Project Cost as approved by Lender (Rs. Crore
Cost overrun w.r.t Revised project cost
Completed Project cost (Rs. Crore)
Cost overrun w.r.t completed project cost
1 2 3 4 5 6
Land 12 12 0 4.28 -7.72
EPC & Non-EPC Cost 1,097.00 1173.51 76.51 1,152.90 55.9
Off-shore CIF Supplies 470.2 448.39 -21.81 430.34 -39.86
On Shore Ex works Supplies 226 231.93 5.93 231.93 5.93
Engg. Transportation, Testing, & Commissioning
110.8 113.3 2.5 110.75 -0.05
Civil and Construction Works 198 267.53 69.53 267.53 69.53
Non-EPC Cost (including Land 92 112.36 20.36 112.35 20.35
265 | P a g e
Development)
Design, Engineering Construction Supervision & Pre- Operative Expenses
28.5 58.32 29.82 58.32 29.82
Preliminary Expenses 16.7 15.34 -1.36 2.96 -13.74
Tools & Spares
Start-up fuel
Training of O&M Staff
Financial Charges incl. up-front fee
11.7 14.28 2.58 11.35 -0.35
Interest During Construction 138.82 224.3 85.48 229.78 90.96
Sub-Total (Capital cost incurred up to 25/03/10)
1,304.72 1497.75 193.03 1,459.59 154.87
Physical contingencies 11.1 0 -11.1 0 -11.1
Margin Money for working capital
24.22 24.22 0 24.22 0
Total Capital Cost up to synchroniszation 25/03/10 (A)
1,340.04 1521.97 181.93 1,483.81 143.77
Expenses charged to P & L before COD (26/03/10 to 06/05/11) during the infirm power period (Operating expenses & Admin.
0 0 - 50.51 50.51
IDC, & Financing Charges) (B) 0 0 - 133.07 133.07
Total Capital Cost up to COD 06/05/11 (C) = (A) + (B)
1,340.04 1521.97 181.93 1,667.39 327.35
Revenue from infirm power up to COD (D)
0 0 - 469.93
Less: Fuel Expenses (coal & sec. oil) incurred during infirm power period (E)
0 0 - 158.65
Net Revenue to be adjusted against capital cost during infirm power period (F) = (D) - (E)
0 0 - 311.28
Completed Capital Cost as on COD (G) =(C-) - (F)
1340.04 1521.97 181.93 1,356.11
As may be seen from the above table, cost overrun
corresponding to the actual capitalized cost of Rs. 1459.59 cr. as on
date of synchronization in respect of EPC cost (i.e. On-shore
266 | P a g e
ex - works supplies and Civil & Construction Works), Non-EPC cost
(including land development) and Design Engineering construction
supervision & preoperative expenses remained at the same level as
mentioned in the Lender’s Engineer report. Cost overrun on account
of IDC up to the date of synchronization increased to Rs. 90.96 cr.
against Rs. 85.48 cr. given in the Lender’s Engineer report. Besides
saving in On-Shore Ex works supplies increased to Rs. 39.60 cr. as
against Rs. 21.81 cr. mentioned in Lender’s Engineer report.
The total cost overrun up to COD after utilizing the
provision for contingencies, available fund on preliminary expenses
and saving in FOREX works out to Rs. 327.35 cr. comprising of cost
overrun of Rs. 143.77 cr. up to synchronization and Rs. 183.58 cr.
from synchronization to COD (Rs. 50.51 cr. + Rs. 133.07 cr., pre-
operative expenses and IDC & FC from synchronization to COD).
Major component of cost overrun is increase in IDC of Rs. 224.03 cr.,
Rs. 90.96 cr. up to synchronization and balance Rs. 133.07 cr.
thereafter upto COD . The balance cost overrun of Rs. 103/- cr.
(approx.), as stated in Lender’s Engineer report, is on account of
‘claims arising from EPC/ Non-EPC contractors and/ or their sub
contractors due to escalating market situations with regard to cost of
raw material and services, extra works claimed by EPC/Non-EPC
contractors including additional works undertaken by LAPL.
267 | P a g e
The various components of cost overrun which the
Commission shall hereinafter examine are listed in the table given
below for ready reference:-
Sr. No. Cost overrun component Cost overrun
1. EPC cost
On-shore Ex works supplies 5.93
Civil and construction works 69.53
2. Non-EPC Cost (including Land
Development)
20.36
3. Design, Engineering, Construction
Supervision & Preoperative
Expenses
29.82
4. IDC upto synchronization 90.96
5. IDC 133.07
6. Pre operative expenses from synchronization to COD
50.51
Before examining the various components of cost
overrun for their admissibility or otherwise, the Commission has
examined the reasons of time overrun i.e. reasons for delay in
synchronization and then delay in declaring COD after synchronization
of the Unit on 25.03.2010 so as to ascertain whether the delay was on
account of reasons attributable to LAPL or was it on account of
reasons beyond their reasonable control.
I) Reasons for delay in synchronization Unit:-
The Petitioner in their submissions/ arguments has stated that
synchronization of Unit was delayed due to Force Majeure events,
which were beyond their reasonable control, of (i) earthquake in
China on 12.05.2008 which damaged manufacturing facilities of DEC
resulting into delay in supply of main plant equipment and BTG
268 | P a g e
components and (ii) new visa policy enforced by GOI in
September/October, 2009 which resulted into non availability of
Chinese Engineers for erection and commissioning for some time and
that the Commission had in the Order dated 02.02.2011.
acknowledged the aforesaid events and held that Force Majeure
events did happen. The Respondent on the other hand has argued
that, in the Order dated 02.02.2011, the Commission had considered
the China earthquake and visa issue as Force Majeure mainly in view
of Respondent not replying to the notice of Force Majeure given by
the Petitioner which was required as per the PPA/PSA but at the same
time it was also held that no cost implication will be there and the
Petitioner is entitled only to the time overrun. The Petitioner,
therefore, cannot now seek cost implication on the reliance of said
Order. It has further been argued by the Respondent that in the
absence of PPA, the applicable provision is section 56 of the Contract
Act, which relieves the affected party from the performance of
obligation during the period of Force Majeure but there is no cost
implication to the other party.
E&Y in their report have stated that the delay in commissioning
can be attributed to two reasons i) earthquake in China and ii) visa
issue of Chinese workers. While Lender’s Engineer in his report of
December, 2009 on Cost Overrun has stated in respect of delay in
commissioning of the Unit.
269 | P a g e
‘in view of the delay in the execution of the project due to Force
majeure event of earthquake in China, and delay in delivery of
Generator rotor of Unit #1 (which was sent to China for repair and
reuse in Unit#2 to reduce the restoration period consequent to the
damage of Unit#1 steam turbine generator prior to oil
synchronization on 30.01.09), the COD targeted in September, 2009
could not be achieved.’
In this respect Commission observes that LAPL in their
submissions/arguments have entirely relied on Lender’s Engineer
report for acceptance of their cost overrun claims but when it
comes to acceptance of reasons of delay as mentioned in the
Lender’s Engineer report, it has been argued by the Petitioner that
reference of diversion of Rotor of Unit -2 for Unit-1 as reason of
delay in synchronization of Unit -2 in the Lender’s Engineer report is
of general nature and there has been no delay in synchronization of
Unit-2 on this account. Commission, however, differs with the
Petitioner and considers that diversion of Rotor of Unit -2 for Unit-1
as also usage of Unit-2 equipment in Unit-1 to optimize the
commissioning of the Units, as mentioned by PFC in their note on
cost overrun enclosed with the Petition, is also one of the reason
for delay in synchronization of Unit-2.
The other reason for delay in synchronization of the Unit
in Commission’s view is China earthquake because of which some
270 | P a g e
equipment of Unit -2 was delayed on account of damage to
manufacturing facilities of DEC during the earthquake. Commission
is not inclined to accept that visa issue has also been a reason of
delay in synchronization of the Unit because firstly, it does not find
mention as reason of delay in the Lender’s Engineer report which
was prepared in December, 2009 where as the Chinese Engineers,
as per the Petitioner, had left the site in September/October, 2009.
Had it been the reason for delay in synchronization, it must had
been mentioned in the Lender’s Engineer report. Secondly, in the
Lender’s Engineer report it has been recorded that “the overall
project progress achieved in October, 2009 is reported as 96%
…..and synchronization of the Unit is now targeted in February,
2010”. It can be inferred from the above that absence of some
Chinese Engineers from the site had not affected the pace of the
project.
The Commission after considering submissions/counter
submissions in this regard, agree with the Lender’s Engineer’s
report that synchronization of Unit-2 was delayed due to i) earth
quake in China ii) diversion of rotor of Unit-2 for Unit-1 and usage
of Unit-2 equipment in Unit-1 for optimizing commissioning of the
Units. Whereas the first reason was clearly beyond reasonable
control of the Petitioner, the second reason can only be attributed
to the Petitioner.
271 | P a g e
II) Reasons for delay in declaring COD:-
It has been submitted by the Petitioner that COD of the
Unit was primarily delayed due to non availability of Long Term
Open Access (LTOA) which was purchaser’s ie PTC’s obligation. It has
also been submitted that though an interim Loop in loop Out (LILO)
arrangement was made for connecting Unit-2 to the 400 KV Korba-
Sipat transmission lines for evacuation of power, continuous full
load operation Unit-2 was not possible in the absence of LTOA and
that due to non-operationalization of LTOA, transmission constraints
persisted throughout the period of generation of infirm power
which prevented the continuous full load operation of Unit-2 and
which (transmission constraints) were beyond reasonable control of
the Petitioner.
E&Y in the report have stated that delay in achieving COD
was mainly on account of non-availability of LTOA which prevented
full load operation of the Unit-2. However, E&Y in response to
Commission’s queries further stated, vide clarifications furnished
subsequent to their report, that most of the reasons advanced by
LAPL for delay in achieving COD as per CERC’s Order dated
09.02.2012 in case of Petition number 289 and 290 of 2010 and IA
8/2011 were technical in nature and analysis of the same was
beyond scope of their assignment. This implies that E&Y while
stating that COD was delayed due to non-availability of LTOA had
not kept in view various reasons advanced by LAPL in the
272 | P a g e
proceedings before CERC in the said case other than visa issue and
non-availability of LTOA.
LAPL, in response to Commission’s interim Order dated
15.12.2014, vide their filing dated 19.12.2014 in respect of delay in
COD has reiterated their earlier submission.
The additional submissions made by LAPL in this regard
are reproduced below:-
“it is a fact on record that Lanco could not declare COD as long term
open access (LTOA) for Unit-2 was not in place for Unit-2 due to
delay in operationlization of the PGCIL Bilaspur Pooling Station along
with delay in commissioning of various transmission system
strengthening schemes in Western Region as enumerated in the
BPTA for Unit-2 signed by PTC with PGCIL. The obligation for
obtaining and maintaining LTOA was of PTC under the PPA (now
terminated). The other operational/technical reasons as given in the
CERC Order dated 09.02.2012 relate to normal commissioning
problems that could have been overcome by running the Unit on
continuous full load. This was not in the case of Unit-2 because of
restrictions and non-availability of power evacuation capacity in the
grid due to the aforesaid reasons. It is submitted that had the long
term open access and power evacuation been arranged by the
beneficiaries on time, there would not have been any delay in
273 | P a g e
conducting the required testing and achieving the COD. The delay in
COD was on account of non availability of long term open access,
grid restrictions & non availability of the transmission system for full
power evacuation from Unit-2, which was admittedly the
responsibility of PTC.”
PTC in their written submissions filed on 30.12.2014 in
response to interim Order dated 15.12.2014, on the issue of delay in
COD after synchronization of Unit-2, has submitted that delay in
declaration of COD was solely on account of Lanco. It has been
stated that PTC’s obligation to evacuate power under open access
comes only after the unit is commissioned. PTC in support of their
argument has cited regulation 8(7) of the CERC Open Access
Regulations, 2009 wherein it has been provided that “ a generating
station including captive generating station which has been granted
connectivity to the grid shall be allowed to undertake testing
including full load testing by injecting its infirm power into the grid
before put into commercial operation, even before availing any type
of open access, after obtaining permission of the concerned Regional
Load Dispatch Centre….. “.
PTC, to emphasize their point, has further cited para 37
of the CERC Order dated 09.02.2012, referred to above, wherein it
has been held that “…… existence of LTOA for evacuation of power
from the generating station has no relevance before commercial
274 | P a g e
operation of the unit of the generating station”. In response to the
allegation of LAPL that commissioning was delayed due to non-
availability of sufficient transmission capacity, PTC has stated that in
terms of Article 4.1(v), the obligation to commission the project was
solely that of the Petitioner. PTC has further stated that it is because
of various technical issues involved that the commissioning of Unit-2
got delayed. In support of its argument, PTC has cited para 7(c) of
the above referred CERC Order wherein the reasons advanced by
LAPL in the proceedings before CERC for delay in achieving COD
(reproduced in the later part of the Order) have been given. PTC has
also cited para 40 of the said CERC Order wherein at the end of the
said para, CERC has held that “…….A summary of the problems is
mentioned at para 7(c) of this Order. We are of the view that both
the units of the generating stations had certain teething problems
which has contributed to some extent to the delay in declaration of
the commercial operation apart from the mater of termination of
the PPA being sub-judice before the Hon’ble Supreme Court.”
PTC has further stated that construction of dedicated 400
kV line from the project upto WR pooling station was part of LTOA
and was included in the scheme for evacuation of power from Unit-
2; Even though PGCIL had completed the WR pooling station on
04.04.2012 (correct date is 01.04.2012), Lanco did not construct
dedicated line until 09.06.2014 and therefore lanco was (also)
responsible for non availability of LTOA.
275 | P a g e
In this context Commission observes as under:-
a) WRLDC in its reply/submissions before CERC in the case referred to
above had stated that ‘considering the delay in Commissioning of
schedule of WR pooling station near Sipat, a System Protection
Scheme (SPS) has been put in operation progressively for both
Units of LPL starting from 01.09.2010 to ensure grid security as
well as evacuation of power from both Units of LAPL’.
It is therefore apparent that after 01.09.2010 as per
WRLDC, a system was in place to evacuate power from both Units.
There could be occasional transmission constraints but, it is felt, it
was very much possible for LAPL to manage through WRLDC and
CEA/WRPC to run Unit-2 on full load for requisite period for trial
run for declaration of COD. From the reply filed by LAPL on
19.12.2014, it is evident that LAPL never took up the matter on
these lines with WRLDC or any other appropriate authority.
b) LAPL’s argument for delay in declaration of COD after the
synchronization of Unit-2 on 25.03.2010 is that it could not declare
COD as LTOA for Unit-2 was not in place due to delay in
operationalization of the PGCIL Bilaspur (near Sipat) pooling
station along with delay in commissioning of various transmission
system strengthening schemes in the Western Region (WR). LAPL
276 | P a g e
further stated that obligation of obtaining and maintaining LTOA
was of PTC. But as stated by PTC in their reply filed on 30.12.2014,
the transmission scheme for evacuation of power from Unit-2 and
for operationalization of LTOA also included a dedicated 400 kV DC
line from the project to the WR Pooling Station, Bilaspur which was
to be constructed by LAPL itself. This line, as stated by PTC in their
reply, was not constructed by LAPL until 06.09.2014. From the
CERC Order dated 03.01.2014 enclosed with PTC’s reply, it is
observed that WR Pooling Station, Bilapsur, along with systems
covered under the scheme was put into commercial operation by
PGCIL w.e.f 01.04.2012 whereas the dedicated 400 kV line was not
constructed by LAPL until 06.09.2014 as already stated. So, LAPL
was equally responsible for non operationalization of LTOA.
c) The argument of PTC that LTOA was to come into force only after
commissioning of the Unit is not entirely true. Whereas the power
transfer from a generating station under LTOA commences only
after COD, the associated transmission system for evacuation of
power should be in place by the synchronization of the Unit i.e
connectivity as per the power to be evacuated is required to be
provided by the time of synchronization so that the station can
undertake testing including full load testing for trial run and inject
infirm power into the grid, the LTOA gets operationlized only after
COD. In this case though transmission system associated with
LTOA was not in place at the time unit was synchronized, but, as
277 | P a g e
already stated, LILO arrangement was there for evacuation of
power and as stated in para (a) a system was in place for
evacuation of power from both the units subject however to
occasional transmission constraints. Commission agrees that
without the transmission system required for operationalizing
LTOA it may not had been possible for LAPL to run the unit on full
load on sustained basis but Commission is not inclined to accept
that trial run for MCR was not possible without that.
d) PTC in their reply has stated that there were certain technical
issues with Unit-2 which delayed its commissioning and has cited
para 7 of the CERC Order dated 09.02.2012 in this regard. CERC in
para 7 (c) of the said Order has given the reasons that were
advanced by LAPL for delay in declaration of COD of Unit-2 during
the proceedings before CERC in the said case and the same are
reproduced below:-
i) Heavy steam leakage from the turbine side leading to
resynchronization on 07.04.2010;
ii) Tripping on 09.04.2010 and 10.04.2010 due to EH oil leakage
from the control valve;
iii) Shutdown from 26.05.2010 to 21.06.2010 due to
problems in the coal mills, gear box and coal mill motor;
278 | P a g e
iv) Time taken for rectification of the problems due to non-
availability of expert Chinese engineers on account of change
in VISA policy;
v) Heavy, leakage of flue gas in the duct leading to the chimney
due to faulty design at joint plane;
vi) Fire accident in coal mills and consequent failure of
grinding rolls;
vii) Problems in ash handling system due to choking of ash
evacuation from the ESP hoppers and problem in wetting
heads;
viii) Delay in commissioning of dry ash handling system and water
circulation system; and
ix) Overloading of transmission line and high frequency
conditions prevailing in the system and consequent grid
security issues affecting operation of the Unit continuously at
full load and completion of testing and achieving
stabilization.
From the above, it is apparent that transmission
constraints due to non-availability of LTOA cannot be said to be the
only reason for delay in declaration of COD, Unit-2 did face a number
of technical problems post synchronization and besides there was
delay in commissioning of ash handling and water circulation systems.
All these factors also caused delay in the commercial operation of the
Unit. These problems could be on account of faulty design, sub -
279 | P a g e
standard quality of equipment procured, poor workmanship during
construction etc. for which only the Petitioner can be held
responsible. The very fact that when LAPL declared COD, LTOA was
still not operationalized, clearly establishes that delay in declaration
of COD cannot be entirely attributed to non-availability of LTOA.
In view of position brought out above, Commission
concludes that delay of 14 months in declaration of COD after
synchronization cannot solely be attributed to the transmission
constraints due to non-availability of the transmission system
associated with LTOA, for which also LAPL is partially responsible,
but there were other reasons for the delay as given above which can
only be attributed to the Petitioner.
Now the Commission shall examine the various components of
cost overrun.
I. Increase in EPC cost:-
a) Increase in cost of on-shore Ex-works supplies: Rs. 5.93 cr.
As stated in the Lender’s Engineer report as also in the
PFC cost overrun report, the increase is on account of
procurement of extra spares for critical systems and special
tools & plants for maintenance in Order to minimize the down
time of the plant. The Respondents have submitted that the
extra spares were for maintenance and should be part of O&M
280 | P a g e
cost and further that the Commission should allow
maintenance spares as per applicable regulations.
The Petitioner in the reply filed on 30.10.2014 to
the query on extra spares have submitted that the cost of initial
spares included in the BTG package is Rs. 4.33 cr. and after
including additional cost of Rs. 5.93 cr. for extra spares, the
total cost of spares works out to Rs. 10.26 cr. i.e 1.47% of the
total plant & equipment cost. This, however, is not correct. The
cost of initial spares of Rs. 4.33 cr. as per the document
submitted is only for initial spares for Turbine-Generator Island.
The cost of initial spares for other packages has not been
shown separately.
The Commission observes that as per HERC Tariff
Regulations, 2008, initial spares to the extent of 2.5% of the
plant and equipment cost can be included in the capital cost. As
already stated above the cost of initial spares in respect of all
the packages other than Turbine-Generator Island have not
been separately mentioned and are included in the respective
packages. Further in the Auditor’s certificate submitted by the
Petitioner in respect of Capital cost on COD, it has been
mentioned that ‘the value of initial spares is included in the cost
of respective machineries’. PFC in its cost overrun report has
stated that extra spares were procured for critical system and
281 | P a g e
special tools & plants for maintenance and to minimize the
down time.
In view of above, Commission is of the considered
view that cost of extra spares of Rs. 5.93 cr. should form part
of O&M cost and cannot be booked to the Capital cost.
Accordingly, cost overrun of Rs. 5.93 cr. and towards extra
spares is disallowed.
b) Increase in cost of Civil and Construction Works: Rs. 69.53 cr.
As per lender’s engineer report, the increase has
occurred due to additional claims by LAPL’s civil contractor
Zelan Construction (India) Pvt. Ltd.(ZCIPL) as under:-
Sr. no.
Particular Additional claim (Rs. cr.)
i) Increase in Span of Bay of Mill and Bunker building from 12 m to 17 m in Order to match with the requirement of traverse of the hoist and also to provide operational ease
23.93
ii) Deck sheeting in TG building for construction of roof slabs to expedite construction activities.
8.18
iii) Requirement of pile foundation for stacker re-claimer hopper
9.27
iv) Price escalation towards reinforcement steel, structural steel and cement.
33.24
The Petitioner has submitted that these claims are on
account of change in scope and PFC have approved the same
after due diligence. Respondents have submitted that
282 | P a g e
Commission should cross verify the extended scope to
ascertain whether it was part of DPR and should also apply
prudent check.
The Commission observes that contract for civil and
construction works on Zelan Projects Pvt. Ltd. (ZPPL) and for
Engineering Transportation, Erection, Testing and
Commissioning on ZCIPL were turn- key contracts on firm price
basis, the responsibility of design, engineering, construction,
supply, erection, testing and commissioning was with turn-key
contractors and accordingly there was no question for any
additional claims.
In the correspondence enclosed with Lender’s Engineer
report, there is a letter from the Petitioner to ZPPL/ ZCPIL
wherein the Petitioner have written to ZPPL/ ZCPIL that under
the Agreement the responsibility for complete design for 300
MW Unit rested with ZPPL/ZCPIL and as such no additional
claims would be entertained. Further, from the correspondence
submitted, it is apparent that extension in the span of Mill and
Bunker building was done in Unit-1 also. Similarly, Deck
sheeting in TG building to expedite construction activities was
also done in Unit-1. Therefore, Petitioner should have taken
care of these changes while awarding contracts for Unit-2.
Further, Deck sheeting was used in T.G. building for saving time
in construction and expenses incurred should be considered to
have been paid back in the form of saving on account of
283 | P a g e
reduced time of construction and accordingly no additional
claim on this account should arise. Similarly, regarding
additional claim for requirement of pile foundation for stacker
reclaimer, it is observed that in a turn- key contract for
construction the terms and conditions of the contract should
necessarily provide that the foundation of the type required as
per site conditions shall be provided and accordingly, no
additional claim should arise for providing pile foundations for
stacker reclaimer.
In view of these observations, it is felt that these
additional claims have arisen on account of imprudence on the
part of LAPL in selecting the contractors/ sub-contractors, in
finalizing the terms and conditions of the contracts and in
handling the contracts. The Commission, therefore, is not
inclined to accept additional claims in respect of increase in span
of Mill & Bunker building, use of deck sheeting in TG Building
and requirement of pile foundation for Stacker Reclaimer.
Regarding the additional claim for price escalation
towards increase in prices of Steel and Cement, Commission
observes that it has been claimed by the Contractor ZCIPL that
prices of cement, reinforcing steel and structural Steel had
increased by 39%, 138% and 114% from Feb, 2006 to August,
2008 and an additional amount of Rs. 36.94 cr. had been
284 | P a g e
incurred by the Contractor on this account. LAPL on its part has
raised additional claim for Rs. 33.24 cr. stating that they have
asked the Contractor to absorb 10% increase. Commission
observes that in a firm price contract the risk of escalation in
prices has to be entirely with the Contractor. But considering
that the increase in prices was too steep, the Commission
considers that at best the increase beyond 10% can be shared by
LAPL and Contractor fifty- fifty. Accordingly, one half of the claim
on this account is accepted and the rest i.e. Rs. 16.62 cr. is
disallowed.
Therefore, out of cost overrun of Rs 69.53 cr. under this
heading, cost overrun of Rs. 16.62 cr. is accepted and the
balance Rs. 52.91 cr. is disallowed.
II. Increase in Non-EPC cost: Rs. 20.36 cr.
As per Lender’s Engineer report, the increase of Rs. 20.36
cr. in the Non-EPC cost has occurred on account of additional
claims raised by LAPL’s Non-EPC contractor Lanco Infratech Ltd.
(LITL) as under:-
Sr. No.
Particular Additional claim (Rs. cr.)
i Increase in plinth area in residential colony from 87800 Sq.ft. to 146200 sq.ft
6.38
ii Construction of road over bridge in accordance with the directives of the state authorities
14.95
iii Miscellaneous and R& R works requested by local state bodies and affected villages people
0.97
285 | P a g e
From perusal of the Lender’s Engineer report, it is
observed that additional claim for Residential colony/Township
has arisen on account of increase in number of dwelling Units
from 88 in the original contract placed on LITL to 124 Units and
increase in the plinth area from 87800 Sqft to 146200 Sqft.
Petitioner has neither furnished any justification for increase in
the number of dwelling Units/plinth area in the Residential
colony/Township nor this could be an essential requirement for
the project.
Regarding other two works i.e. Road over Bridge and
Misc. Civil and R&R works, it is obvious from the
documents/correspondence enclosed with the Lender’s Engineer
report that construction of Road over Bridge was carried out as
per requirement/directive of the district authorities and misc. Civil
Works and R&R works were also carried out as requested by local
authorities and affected villages people.
In view of above, Commission finds no justification for
allowing cost overrun of Rs. 6.38 cr. for additional work in the
Residential colony/Township. But the cost overrun in respect of
other two works is admitted considering that these were
unavoidable for LAPL and have been carried out as per
requirements of District/Local authorities. Therefore, out of cost
286 | P a g e
overrun in the Non-EPC cost, cost overrun of Rs. 14.95+0.97 i.e
Rs.15.92 cr. is admitted and balance cost overrun of Rs. 6.38 cr.
is disallowed.
III. Increase in Design, Engineering, Construction Supervision &
Preoperative Expenses: Rs. 29.82 cr.
It has been stated in the Lender’s Engineer report that
due to increase in general price level and inflation rate, there was
an increase in the pre-operative expenses from Rs. 28.50 cr. as
per approved cost to the level of Rs. 58.32 cr. resulting in cost
overrun of Rs. 29.82 cr. As per the details furnished, actual pre-
operative expenses up to the date of synchronization i.e. up to
25.03.2010 has also been at the same level i.e. Rs. 58.32 cr. as
estimated in the Lender’s Engineer report. The Commission
observes that the increase of Rs. 29.82 cr. in the pre-operative
expenses is not only on account of general price rise but is also
due to delay in commissioning of the Unit from September, 2009
to March, 2010. As per Commission’s estimate on the basis of
increase in WPI and CPI during the project construction schedule,
out of increase of Rs. 29.82 cr. in pre-operative expenses, increase
to the extent of Rs. 11.70 Crore is due to, increase in inflation i.e.
general price rise from September, 2006 to September, 2009 and
the balance increase of Rs. 18.12 Crore is on account of
cumulative effect of increase in price level and also due to
287 | P a g e
extension in the pre-operative period from Sept, 2009 to March,
2010 on account of delay in synchronization of the Unit.
Thus, the cost overrun of Rs. 29.82 cr. due to increase in
pre-operative expenses can be considered to be comprising of
two components i.e first component of Rs. 11.70 cr. which is
entirely on account of general increase in price level and second
component of Rs. 18.12 cr. which is on account of time overrun
from September, 2009 to March, 2010 i.e. due to delay in
synchronization of the Unit.
To examine the admissibility of each of these components, it
would be relevant to refer to the Hon’ble APTEL’s Order dated
27.04.2011 in case of Maharashtra State power Generation
Corporation Ltd. V/s MERC (Appeal no. 72 of 2010) wherein
Hon’ble APTEL has laid down principles for applying prudent
check on time overrun related costs. Relevant part of the Order is
reproduced below:-
“ 7.4 The delay in execution of a generating project could occur
due to following reasons:-
i) Due to factors entirely attributable to the generating
company, e.g., imprudence in selecting the
contractors/suppliers and in executing contractual
288 | P a g e
agreements including terms and conditions of the contracts,
delay in award of contracts, delay in providing inputs like
making land available to the contractors, delay in payments
to contractors/ suppliers as per the terms of contract,
mismanagement of finances, slackness in project
management like improper co-ordination between the
various contractors etc.
ii) Due to factors beyond the control of the generating
company e.g. delay caused due to force majeure like natural
calamity or any other reasons which clearly establish,
beyond any doubt, that there has been no imprudence on
the part of the generating company in executing the project.
iii) Situation not covered by (i) & (ii) above.
In our opinion in the first case the entire cost due to time
overrun has to be borne by the generating company.
However, the Liquidated Damages (LDs) and insurance
proceeds on account of delay, if any, received by the
generating company could be retained by the generating
company. In the second case the generating company could
be given benefit of the additional cost incurred due to time
overrun. However, the consumers should get full benefit of
the LDs recovered from the contractors/suppliers of the
generating company and the insurance proceeds, if any, to
reduce the capital cost. In the third case the additional cost
due to time overrun including the LDs and insurance
289 | P a g e
proceeds could be shared between the generating company
and the consumer. It would also be prudent to consider the
delay with respect to some benchmarks rather than
depending on the provisions of the contract between the
generating company and its contractors/ suppliers. If the
time schedule is taken as per the terms of the contract, this
may result in imprudent time schedule not in accordance
with good industry practices.
7.5. In our opinion, the above principles will be in
consonance with the provisions of Section 61 (d) of the Act,
safeguarding the consumers’ interest and at the same time,
ensuring recovery of cost of electricity in a reasonable
manner.”
If examined in the light of principles laid down in the
above Order of Hon’ble APTEL, the first component of Rs. 11.70
cr. of cost overrun in respect of pre-operative expenses becomes
admissible as the same was entirely due to general increase in
prices level i.e on account of reasons beyond the control of the
Petitioner.
The increase of Rs. 18.12 cr. in the pre-operative
expenses has occurred on account of delay in synchronization of
the Unit. The synchronization of Unit-2, as discussed in para (12)
(i), was delayed due to (a) earth quake in China and (b) due to
diversion of rotor and some other supplies of Unit -2 to Unit-1.
Whereas the first reason was beyond the control of the
290 | P a g e
Petitioner, the second reason is attributable to the Petitioner.
Accordingly 50% of the cost overrun component of Rs. 18.12 cr. is
disallowed in line with the principles laid down in the above
referred Hon’ble APTEL’s Order.
Therefore of the cost overrun of Rs. 29.82 cr. due to
increase in preoperative expenses, cost overrun of Rs. 20.76 cr.
(11.70 + 50% of 18.12) is admitted and the balance Rs. 9.06 cr. is
disallowed.
IV. Increase in IDC up to synchronization : Rs 90.96 cr.
i) As per the original project cost of Rs. 1340.04 cr. , the
Petitioner was to raise the debt of Rs. 1072.03 cr. and the
provision for IDC in the Project cost was Rs. 138.82 cr. As per
the details furnished in the Petition the gross loan drawn in
actual up to COD i.e. 07.05.2011 was Rs. 1025.54 cr. with a
repayment period of 12 years and with a floating rate of
interest.
ii) The IDC incurred as on the date of capitalization i.e.
25.03.2010 has been given as Rs. 229.78 cr. [Refer Table under
para (11)]. Thus the cost overrun due to increase in IDC up to
the date of capitalization or the date of synchronization of the
Unit, works out to Rs. 90.96 cr.
iii) The Petitioner has submitted that the delay in
synchronization of the Unit has occurred due to Force Majeure
events of China earthquake and Visa issue which were beyond
reasonable control of the Petitioner and as such actual IDC up
291 | P a g e
to synchronization should be considered in the capital cost.
Petitioner has submitted as under on the increase in IDC up to
synchronization.
“The interest rate on loan as per the original appraised
project cost of Rs. 1340.041cr. in year 2005 was 8.5% (as
mentioned in page no. 111 of 144 of DPR). By the time, the
financial closure of Unit-2 was achieved in September, 2006, the
interest rates had started increasing. The first disbursement of
term loan which commenced in September, 2006 was at interest
rate of 10.25%. By September 2009, when the disbursement were
continuing, the interest rate of the loan portfolio had become
12.09% which was much higher then the interest rate of 8.5 %
envisaged in the original appraised project cost.
The increase in IDC was about Rs. 41.09 cr. only on account of
increase in interest rates on loan from initial 8.5% to weighted
average of 12.09% during the construction period from year 2005
to September 2009. Additionally, an amount of Rs. 49.878 cr. was
the IDC which was the cumulative effect of time extension due to
force majeure events and also the increased weighted average
interest rate of the loan portfolio upto capitalization on
25.03.2010.
Thus, the increase in IDC from the originally appraised project
cost in year 2005 to the capitalized project cost in March 2010 was
Rs. 90.96 cr. for the above mentioned reason……”
292 | P a g e
The Respondents, on the other hand, submitted that the
Petitioner is not entitled to any IDC and IEDC or cost overrun on
account of any alleged Force Majeure conditions in terms of Order
dated 02.02.2011 of the Commission where it was held that the
Petitioner is entitled only to the time overrun on account of Force
Majeure conditions and no cost implications will be there.
iv) The Commission observes that the Hon’ble Supreme
Court in its Order dated 16.12.2011 has held that ‘the State
Electricity Regulatory Commission, Haryana will decide the
dispute uninfluenced by the observations made in the impugned
Orders passed before today by the Appellate Tribunal and/ or
any Authority in this case…’ As such the Commission cannot
rely on its Order dated 02.02.2011 to disallow overrun cost on
account of increase in IDC as argued by the Respondents.
v) As per the Petitioner, out of total increase of Rs. 90.96 cr.
up to synchronization, increase of about Rs. 41.09 cr. is on
account of increase in the interest rates on loans from 8.5% to
weighted average interest rate of 12.09% during the original
construction period from September, 2006 to September, 2009.
The balance increase of Rs. 49.87 cr. was due to cumulative
effect of time extension due to Force Majeure events and due
to increased weighted interest rate.
E&Y in their report has worked out IDC as per the
proposed debt scheduled for the original project cost at the
293 | P a g e
interest rates as prevailing during the original construction period
of September, 2006 to September, 2009, as Rs. 201.30 cr. The
increase in IDC due to increase in interest rates, therefore, works
out to Rs. 62.48 cr. (201.30-138.82). But E & Y in their calculations
have taken the total debt as Rs. 1072.03 cr. as proposed for the
original project cost where as actual loans raised by the Petitioner
up to COD add up to Rs. 1025.54 cr. only as already stated. The
Petitioner has, however, worked out the increase for the actual
loans drawn i.e. for Rs. 1025.54 cr. and as per the actual interest
rates prevailing from September, 2006 to September, 2009. The
Commission has considered the increase in IDC on account of
increased interest rates as per the calculations of the Petitioner.
vi) Thus, the Commission has considered that out of total
cost overrun of Rs. 90.96 cr., Rs. 41.09 cr. is on account of
increase in interest rates, which was beyond the reasonable
control of the Petitioner, and the balance Rs. 49.87 cr. is on
account of delay in the synchronization of the Unit. As already
held by the Commission earlier in para (12) (i), the
synchronization of Unit-2 was delayed due to the reasons partly
beyond control of the Petitioner and partly attributable to the
Petitioner.
Accordingly, in line with the principles laid down by the
Hon’ble APTEL in the Order referred to above, out of total cost
overrun of Rs. 90.96 cr. on account of increase in IDC up to
294 | P a g e
synchronization, increase of Rs. 41.09 cr. on account of increase in
interest rates and 50 % of Rs. 49.87 cr. on account of delay in
synchronization of the Unit is admitted and the balance 50% of Rs.
49.87 cr. is disallowed. In the nutshell, out of total cost of overrun
Rs. 90.96 cr. on account of increase in IDC upto synchronization, Rs.
66.03 cr. is admitted and the balance Rs. 24.93 cr. is disallowed.
V) IDC from date of synchronization to COD : Rs. 133.07 cr.
i. As per the Auditor’s certificate in respect of completed
Capital Cost furnished by the Petitioner, the project cost was
capitalized on the date of synchronization i.e 25.03.2010 at Rs
1459.59 cr. (exclusive of margin money of Rs.24.22 cr.) and
the expenses there after upto COD have been shown to be
booked to ‘Profit and Loss Account’. The IDC incurred during
this period add upto Rs. 133.07 cr.
ii. The Petitioner in respect of IDC of Rs. 133.07 cr. has submitted
as under:-
“Rs. 133 cr.: Interest up to COD from synchronization date
(26.03.2010 to 07.05.2011) is due to evacuation/transmission
constraints which were beyond the reasonable control of
Lanco as it was purchaser’s obligation to obtain long term
open access. During this period infirm power revenue was
295 | P a g e
much higher than the IDC which has been adjusted in Unit-II
capital cost and the same has been certified in the Auditor
Certificate as per the HERC Tariff Regulations, 2008”.
The Respondent, as already stated, has submitted that in
terms of Order dated 02.02.2011 of the Commission; the
Petitioner is not entitled to any IDC and IEDC or cost overrun
on account of any alleged Force Majeure conditions.
iii. E & Y in their report in response to the query of the
Commission that whether the O&M costs and IDC incurred
during the extended period of achieving COD should be
capitalized with the project cost, has given their opinion as
under:-
“It is our opinion that if the net revenue from sale of infirm
power is being taken into account for adjustment of project
capital cost, then the associated O&M cost incurred for
generating power as well as the IDC incurred during the
production of infirm power should be taken into account for
determination of project capital cost”.
iv. As already held in para (12) (ii), the delay of 14 months in
declaration of COD after synchronization cannot be solely
attributed to non-availability of LTOA as contended by the
296 | P a g e
Petitioner but there were other reasons for the delay which
are attributable to the Petitioner.
Going by the principles laid down in the ibid Order
of the Hon’ble APTEL, 50% of the IDC of Rs. 133.07cr. incurred
from synchronization of the Unit-2 to COD needs to be
disallowed. The Commission, however, feels that since the
benefit of net earnings from sale of inform power is being
passed on to the consumers by way of reduction of the
completed capital cost to that extent, the IDC of Rs. 133.07
cr., in all fairness and in line with the recommendations of
consultant E&Y, should be taken into account for
determination of capital cost on COD.
Therefore the IDC of Rs. 133.07cr. incurred from
synchronization of the Unit-2 to COD is admitted for
including in the capital cost on COD and no part of the same
is disallowed.
VI Pre-operative expenses from synchronization to COD: Rs.
50.51cr.
i) the details of Pre-operative expenses incurred from the
date of synchronization to COD as per the audited
financial statements submitted by the Petitioner are as
297 | P a g e
under. The Normative O&M expenses as per CERC
Regulations, 2009 for the corresponding period as
worked out by E&Y are also depicted for comparison:-
26.03.2010 to 31.03.2010 (6 days)
01.04.2010 to31.03.2011 (365 days)
01.04.2011 to 06.05.2014 (36 days)
Total (Rs. in Crores)
Administrative Expenses
12.48 22.68 1.56 36.72
Direct Expenses 0.0 13.01 0.78 13.79
Total 12.48 35.69 2.34 50.51
CERC Normative O&M Cost
0.79 50.76 5.29 56.84
ii) The Commission observes that the administrative
and direct expenses claimed by the Petitioner are
nothing but the O&M expenses incurred by the Petitioner
in generating the infirm power from date of
synchronization to COD. E&Y have compared the O&M
expenses claimed by the Petitioner with normative O&M
expenses for 300 MW Units as per CERC Regulations,
2009 and have found that the expenses claimed are on
lower side as is apparent from the Table given above. It
has also been stated in the E&Y report that O&M
expenses incurred from 26.03.2010 to 31.03.2010 i.e
Rs. 12.48 cr. are exceptionally high and that the one
major component considered in this O& M cost of Rs.
12.48 cr. is the net exchange fluctuation during the
construction which is Rs 7.17 cr. Commission observes
298 | P a g e
that even after taking into account the said adjustment of
Rs. 7.17 cr., the balance O&M cost of Rs.5.31 cr. is much
higher considering that it is only for 6 days and the actual
O&M expenses for the full FY 2010-11 are Rs. 35.69 cr.
The Commission further observes that the Hon’ble
APTEL have directed this Commission to determine the
tariff for the disputed period which commences from
07.05.2011 as per HERC Tariff Regulation, 2008. The
normative O&M cost as per HERC Tariff Regulations for
300 MW Unit-2 of LAPL works out to Rs. 13.40 cr. for FY
2010-11, Rs. 0.22 cr. for 6 days of FY 2009-10 (on prorata
basis) and Rs. 1.32 cr. for 36 days of FY 2011-12. Thus,
the normative O& M cost for the period of generation of
infirm power works out to Rs. 15.01 cr. only against
actual expenses of Rs. 50.51 cr. The Commission,
however, is of the view that the normative O&M cost as
per tariff regulations should apply only after COD and it
may not be appropriate to restrict the O&M expenses
during the period of generation of infirm power to
normative O&M cost.
However, as already stated above, the O&M
expenses for 6 days period of FY2009-10 are very high
even after considering the adjustment of Rs. 7.17 cr.
299 | P a g e
Commission, therefore, restrict the O&M expenses for
the period 26.03.2010 to 31.03.2010 to Rs. 0.59 cr.
(worked out on prorata basis from actual expense of Rs.
35. 69 cr. for the FY 2010-11) plus Rs. 7.17 cr. on account
of the said adjustment i.e. to Rs. 7.76 cr. and balance
amount of Rs. 4.72 cr. is disallowed.
Therefore, out of pre-operative expenses of Rs. 50.51 Crore for
the period 26.03.2010 to 06.05.2011, an amount of Rs. 4.72 Crore. is
disallowed on account of reasons stated above.
The project cost on COD prior to netting off the net earnings
from sale of infirm power works out as under:-
(Rs. in Cr.)
i)
Project cost on COD as per Auditor’s certificate 1667.39
ii)
Less cost overrun disallowed as per paras (13) I to (13) VI.
103.93
iii)
Less excess cost of land and land development booked to apportioned cost of common facilities as per para (9)
17.44
iv) Approved project cost on COD 1546.56
Therefore, the approved project cost on COD prior to netting
of the net earnings from sale of infirm power works out to Rs. 1546.56
Crore.
300 | P a g e
Infirm Power:-
i) In its previous tariff Order this Commission had considered
Rs. 332.31 Cr. as net revenue earned on account of sale of infirm power.
The Commission, in view of the further details provided by LAPL for
Unit–1, has revisited the entire gamut of sale of infirm power, fuel and
other costs etc.
The details of revenue earned from sale of infirm power in respect of
Unit-2 from 22.03.2010 to 06.05.2011 as also the details of fuel
expenses have been provided in the Auditor’s Certificate dated
12.01.2014 for capital cost on COD as under:
(Rs. in Cr.)
Year Revenue from sale of infirm power
Fuel expenses Net earnings
FY 2009-10
(26.03.2010 to
31.03.2010)
1.35 0.60 0.75
FY 2010-11 424.58 142.41 282.17
FY 2011-12
(1.04.2011 to
06.05.2011)
44.00 15.64 28.36
Total 469.93 158.65 311.28
Thus, the net earnings from the sale of infirm power from
22.03.2010 to 06.05.2011 as per details furnished by the Petitioner have
been given as Rs. 311.28 cr.
ii) The Respondent HPPC have submitted /argued that as per financial
statements of Lanco filed for the year 2009-10 and 2010-11, the sale of
301 | P a g e
infirm power from Unit 1 & Unit 2 before declaration of commercial
operation aggregate to Rs 1889.10 cr. and in addition there has been
sale of infirm power during the period 01.04.2011 to 06.05.2011 the
details of which have not been furnished.
iii) Commission observes that requisite details have been provided by the
Petitioner. The break-up of total sales of Rs. 1889.12 cr. from Unit-1
and Unit-2 during the year FY 2009-10 and FY 2010-11 have been
furnished as under:-
a) Sales Revenue Unit-1- Infirm power : 629.63 cr.
(Before COD 09.04.2010)
b) Sale Revenue Unit-1-short term : 869.32 cr.
(After COD 09.04.2010)
c) Sale Revenue Unit-1 –UI : (-) 35.76 cr.
(After COD) in the year 2010-11
d) Sales Revenue from Unit-2- infirm power : 425.93 cr.
(Before COD 07.05.2011) for FY 2010-11
Total 1889.10 cr.
Further, sales revenue from infirm power from Unit-2 from
01.04.2011 to 06.05.2011 has also been furnished as Rs. 44.00 cr.
Commission also observes that MPERC in its Order on Unit-1 has taken
the revenue from sale of infirm power from Unit-1 as Rs. 629. 63 cr.
302 | P a g e
iv) The net earnings from sale of infirm power from Unit-2 have also
been examined by E& Y in their report and have been found to be in
Order. The recommendations given by E&Y in their report in this
regard are reproduced below:
“The total revenue from Unit-2 as per statutory auditor
from sale of infirm power during the period from
26.03.2010 to 06.05.2011 is Rs. 469.93 cr. which is higher
than total UI charges Rs. 425.26 cr. considering Unti-2 on
standalone basis during the same period.
Actual coal consumption during infirm power sale
is slightly lower than EY estimated figures. Similarly, oil
consumption is also lower than regulatory allowable
consumption during infirm power sale but the difference
in case of oil consumption is significant to the tune of
66.92%.”
In view of the above, Commission has considered Rs. 311.28
cr. as the net earnings from sale of infirm power generated from Unit-2
from 22.03.2010 to 06.05.2011.
The capital cost on COD for determination of tariff accordingly
works out as under:-
(Rs. in Cr.)
Approved project cost on COD 1546.56 Net earnings from sale of infirm power 311.28
Net capital cost on COD 1235.28
The Commission has, therefore, considered (admitted) Capital
Cost of Unit-2 of LAPL for the purpose of tariff determination as per
303 | P a g e
Order of Hon’ble APTEL as Rs. 1235.28 cr. The Commission observes
that the net capital cost on COD as determined by the Commission for
Unit-2 is comparable with the net capital cost for Unit-1 for LAPL
(Rs. 1236.40 cr.) determined by Hon’ble Madhya Pradesh Electricity
Regulatory Commission in its Order dated 27.04.2011.
The Commission observes that against Rs. 1,356.11 Crore
claimed by LAPL and Rs. 1007.73 cr. considered by this Commission in its
previous Order dated 17.10.2012, the net capital cost for determination
of tariff after applying prudence check works out to Rs. 1235.28 cr.i.e.
4.11 cr. per MW.
The above Capital Cost i.e. Rs. 4.11 cr./MW compares well with
the Capital Cost of coal based power plant of similar capacity and
vintage including the Capital Cost of 2 X 300 MW DCR TPS Yamunanagar
Power Plants commissioned in Haryana by the State owned power
generating company i.e. HPGCL . Thus, after applying the aforesaid
prudence check to each item of cost overrun, the Commission is of the
considered view that there is no need to further go into micro details of
allocation of common costs between LAPL Unit – 1 & Unit – 2.
9.0 Financial Structure (Debt: Equity):-
The Petitioner has submitted that the debt drawn for the
Project was Rs. 1025.18 Crore constituting 75.56% of Capital Cost and
the balance 24.44% is the equity capital. Per Contra the Respondent
304 | P a g e
(HPPC) argued that the Debt:Equity ratio of 80:20 as originally envisaged
for the project should be considered in relation to LAPL Unit – 2.
The Commission observes that the Debt: Equity ratio envisaged
in the original scheme was 80:20. As the tariff in the present case is to
be determined in accordance the HERC Regulations, 2008, the debt –
equity ratio has been considered in accordance with the regulation 15 of
the said Regulations which provides that “provided further that where
deployment of equity is less than 30%, the actual debt and equity shall
be considered for determination of tariff”. As per the information
provided by the Petitioner the debt as on COD i.e. 7.05.2011 was Rs.
968.403 Crore. Accordingly, the Commission has considered the debt
as Rs. 968.403 Crore and the balance part of the approved Capital Cost
i.e. 266.877 Crore as Equity which translates into a debt: equity ratio of
78.39 : 21.61 i.e. 3.6 : 1 as against 4:1 in the approved financial package
and 2.5:1 proposed by the Petitioner.
Return on Equity (ROE) has been claimed by the Petitioner at
15.5% for the 24.44% equity corresponding to the project cost of
1356.11 Crore as submitted by the Petitioner based on Regulation 15 of
the CERC Regulations, 2009. While objecting to this HPGCL/HPPC has
submitted that the approved financial package in this case was 80% debt
and 20% equity. Accordingly, HPGCL/HPPC has proposed that the capital
cost duly scrutinized subject to prudence check and approved, should be
apportioned in 80:20 ratio and ROE should be restricted to 20% of the
approved Capital Cost.
305 | P a g e
The Commission has considered the submissions of the
parties on the issue of ROE and observes that HERC Regulations, 2008
provides as under:-
(iii) Return on Equity:
Return on equity shall be computed on the equity base
determined in accordance with regulation 15 @ 14% per
annum.
As the Commission is mandated to determine the tariff as per
HERC Tariff Regulations, 2008 hence, for the purpose of tariff
determination the Commission has considered 14% ROE in line with
the ibid Regulations as against 15.5% claimed by the Petitioner.
Interest on Loan has been claimed by the Petitioner based on
actual interest payments made to the lenders in line with Regulation
16 of CERC Regulations 2009. Interest on Loan for the balance period
of 2011-12 and FY 2012-13 has been estimated on the basis of
prevailing interest rates and in accordance with the terms of Loan
Agreements executed with the lenders. On this issue HPGCL/HPPC has
submitted that the interest on working capital should be calculated on
normative basis and that the actual amount of capital employed by
the generating company from time to time in regard to coal
consumption etc. is irrelevant and the working capital needs to be
uniform throughout the tariff period of FY 2009-10 to FY 2013-14.
The Commission has considered the above submissions of the
contesting parties on the issue of interest on term loan and working
306 | P a g e
capital loan and in line with HERC Regulations, 2008, has considered
12.76% interest on term loan worked out on the basis of actual
interest on loan drawl by LAPL and 13% interest on working capital
loan arrived at on the basis of SBI Prime Lending Rate as applicable for
the relevant year. The above interest rates have been applied on the
normative debt and working capital requirement approved by the
Commission.
Operating & Maintenance Expenses (O&M): The Petitioner has
claimed O&M expenses of Rs. 17.88 lakhs/MW and 18.91 lakhs/MW
as applicable for a 300 MW set for the years 2011-12 and 2012-13
respectively in accordance with Regulation 19(a) of CERC Regulations,
2009. While contesting this claim, HPPC has submitted that O&M
expenses need to be ascertained in terms of CERC Regulations, 2004
based on the capital cost finally determined by the Commission. They
have further submitted that under the Tariff Regulations, 2009, the
O&M Expenses are on normative basis and need to be allowed only
on that basis. Any claim on the part of the Petitioner contrary to the
above is wrong.
The Commission has considered the above submissions and
observes that while the Petitioner has considered O&M expenses as
per CERC Norms, 2009, HPGCL/HPPC has proposed that the same
should be as per CERC Regulations, 2004. In this regard the
Commission observes that the Hon’ble APTEL in its Order dated
3.01.2014 has clearly said that the O&M expenses should be
307 | P a g e
determined as per the Tariff Regulations of the State Commission.
Hence, for the purpose of tariff determination in the present case
O&M expenses @ 1% of the Capital Cost as admitted by the
Commission in accordance with HERC Regulations, 2008, has been
considered for FY 2011-12. Further, for FY 2012-13 the same has
been escalated @ 4% to arrive at the allowable O&M expenses.
Additionally, the Commission observes that the Petitioner had
filed a separate application under Regulation 33 of the HERC Tariff
Regulations, 2008 praying for relaxation of Regulation 16 (iv)(c) of the
said Regulations concerning O&M expenses in view of the higher
actual O&M expenses incurred by them in LAPL Unit – 2. They have
submitted that the actual O&M expenses now being claimed by them
are lower than the normative O&M expenses admissible as per CERC
Tariff Regulations, 2009 whereas the same are higher than the
normative O&M expenses as per HERC Tariff Regulations, 2008. This
application/petition of LAPL was also heard along with the main
petition. The prayer of the Petitioner was vehemently opposed by the
Respondent HPGCL/HPPC. The Commission has considered the
submissions of the parties and is of the considered view that the tariff
in the present case is determined as per the remand Order of the
Hon’ble APTEL, wherein, on the issue of O&M expenses the Hon’ble
APTEL has specifically said that “O&M expenses should be determined
as per the Tariff Regulations of the State Commission”. In view of the
same the Commission finds no merit in the prayer of the Petitioner.
Hence, petition no. HERC/PRO - 5 of 2014 is accordingly disposed of.
308 | P a g e
10. Energy Charges:-
The Petitioner has proposed Normative Gross Station Heat Rate
of 2410 Kcal/kWh as per Regulation 26(ii)(B) of CERC Regulations
2009, while HPGCL/HPPC has submitted that the same ought to be in
line with CERC Regulations, 2004.
The Commission observes that the Station Heat Rate
(Kcal/kWh) envisaged at the DPR stage which formed the basis of
contracted tariff was 2500 Kcal/kWh. The Commission observes that
the SHR, due to inherent improvement in technology, has witnessed
substantial improvement in the case of 300 MW thermal
powerhouses which is also reflected in the actual performance
reported by the Petitioner in the case of their Unit – 2.
However, the Commission, for the purpose of determining
tariff for the disputed period, has considered SHR of 2410 Kcal/kWh
i.e. 2450 Kcal/kWh prescribed for 300 MW thermal units, minus 40
Kcal/kWh as the boiler feed pumps in the case of LAPL Unit - 2 are
electrically operated, in line with HERC Regulations, 2008.
Auxiliary Energy Consumption: The Petitioner has proposed
auxiliary energy consumption in accordance with Regulation 26(iv) of
CERC Regulation 2009, the Normative Auxiliary Consumption has
been considered at 9% since the Unit has electrically driven boiler
feed pump and uses induced draft cooling towers. As the same is in
line with regulation 11 (5) of the HERC Regulations, 2008, 9%
309 | P a g e
auxiliary energy consumption has been considered by the
Commission for the purpose of tariff determination in the present
case.
Landed cost and the GCV of coal:-
Regulation 17 (4) of the HERC Regulations, 2008 provides as under:
“(4) Landed Cost of Coal: The landed cost of coal for the purpose of
computation of energy charges shall be arrived at after considering 0.8%
normative transit and handling losses of the quantity of coal dispatched
by the coal supply company. The cost shall be considered as per the
notifications of the Central Government or Coal Companies. In the
absence of any recent notification, the weighted annual average cost of
the current year adjusted for known changes shall be considered as the
cost while computing generation tariff. The Commission may relax the
norm in the light of achievability of the norm and circumstances specific
to the generating station”.
For the period commencing from May, 2011 to December, 2011
the Petitioner has proposed landed cost of coal based on actual
receipts and consumption respectively. It was submitted by the
Petitioner that landed cost of coal has been computed in accordance
with Regulation 21(7) of CERC Regulations, 2009 adopting normative
transit and handling loss of 0.8%. The Petitioner has submitted that
Energy Charges for the period January, 2012 to March, 2012 of 2011-
12 and FY 2012-13 may be allowed to be recovered in accordance
with the CERC formula.
With regard to the tariff computed for the period from 7th May,
2011 to December, 2011, the Petitioner has submitted that the Letter
310 | P a g e
of Assurance (LoA) issued by South Eastern Coalfields Ltd.(SECL) vide
letter dated 18.9.2006 guaranteed coal supply to the extent of 1.445
Million Tons Per Annum (MTPA). However, due to various directions
issued by Government of India pursuant to new coal distribution
policy, the actual coal supply was reduced progressively and stands at
the current allocation of 0.94 MTPA against the requirement of about
1.62 MTPA for meeting 85% PLF.
The Commission observes that as per the month wise details of
coal procured by LAPL Unit – 2 from SECL (linked coal mines),
Imported coal and coal procured through e–auction and open market
in FY 2011-12 and FY 2012-13, the weighted average cost of landed
coal as per LAPL works out to Rs. 2063/MT for FY 2011-12 and
Rs. 2323/MT for FY 2012-13 and the weighted average GCV of coal
from all sources works out to 3293 and 3144 Kcal/Kg respectively. As
far as cost of coal is concerned the Commission observes that a mix of
coal with varying costs have been used at LAPL Unit-2 i.e. SECL
(Linkage Coal), e-auction coal, open market coal and imported coal.
The landed cost of coal including transit & handling loss and cost of
transportation of the same ranges from Rs. 1172/MT (SECL Linkage
Coal), Rs. 3812/MT (Open Market Coal) Rs. 6050/MT for the imported
coal. The pricing of coal for the purpose of tariff determination
became complex as the power generated from LAPL Unit – 2 was
being supplied to Haryana, Chattisgarh as well as accounted for under
UI mechanism even after the claimed COD in May, 2011. The
311 | P a g e
Petitioner has submitted that the Commission may consider allowing
the energy charges based on month wise weighted average landed
cost of the coal computed after considering the opening stock of coal
at the beginning of the month, coal received during the month, coal
consumed during the month and the closing stock of coal at the end
of the month as per the details submitted by them in the petition. It
was further submitted that month wise GCV of coal as on fired basis
may be considered for determining variable/energy charges.
While objecting to the cost of coal and GCV as claimed by the
Petitioner, the Respondent i.e. HPPC/HPGCL submitted that as the
entire project LAPL Unit – 2 was conceived on the basis of linkage coal
from SECL hence, it was the responsibility of LAPL to arrange coal
from SECL and there should not be any obligation on the part of HPPC
to pay for the energy charges in excess of price that would be
applicable for the supply of coal by SECL. It was further submitted that
coal procured by LAPL through other means including e – auction,
direct purchases, imported coal etc. should be entirely at the risk and
cost of LAPL. Additionally, it was submitted that entire quantum of
supply from SECL should be accounted for generation and sale of
electricity to HPPC.
The Commission observes that allocation of coal supply
to LAPL was as per the Memorandum of Understanding (MoUs)
between SECL and LAPL dated 24.07.2010 and dated 30.08.2011.
From the documents/details placed on record by LAPL it is observed
312 | P a g e
that the coal supply was stopped in the beginning of FY 2011-12,
despite direction from CIL (letter dated 30.03.2011) to continue
supply to all developers till June 2011 with allocation quantity as per
previous MOU dated 24.07.2010. Supply of coal was, however,
resumed from September 2011 with the signing of MoU dated
30.08.2011. Further, the reason behind the delay of five months (April
to August 2011) in resuming the coal supply could not be ascertained.
LAPL, however, has furnished copy of its letters dated 11.05.2011 to
CEA, letter dated 04.07.2011 to SECL, and letter dated 19.07.2011 to
the Ministry of Coal asking for resumption of coal supply on
immediate basis in support of their contention that they have made
sufficient efforts to secure linkage coal from SECL.
Additionally, the Commission observes that the coal supply was
stopped from May 2012 through a letter dated 17.05.2012 in the
absence of valid PPAs with DISCOMs of Haryana and Chhatisgarh.
However, LAPL had one PPA dated 12.01.2011 with Chhattisgarh State
Power Trading Company Ltd. and also, as per the directions of the
Hon’ble Supreme court, power was to be supplied to Haryana
Discoms. Subsequently, the coal supply was restored in July 2012 on
the direction of Ministry of Coal. SECL vide their letter dated 20th Sep
2012 reduced the coal supply to 65% of the LAPL Unit-2 and this
curtailment became effective from 1st July 2012, due to which
adjustments in coal supply were made in subsequent months. It is
also noted that power from Unit-2 was supplied to CSPTCL till 1st
313 | P a g e
October 2012. However, as evident from the submissions dated
24.12.2014 made by PTC , from 21.03.2013 LAPL indicated its inability
to supply power to Haryana as well on account of fuel shortages.
Further w.e.f 21.08.2014 LAPL started issuing day-ahead availability
without providing any details regarding availability of fuel, source or
cost of fuel which would be used to generate and supply of power.
It has been observed that on many coal invoices which are
provided as Unit-2 coal procurement invoices there is mention of
Unit – 1 instead of Unit - 2. On this LAPL submitted that only one FSA
was in place with SECL for Unit-1 at that time and coal for Unit-2 was
being supplied by SECL under MOU route. However all the invoices
raised by SECL for both Unit-1 (under FSA) and for Unit-2 (under
MOU) had the recipient’s address as “Urga Unit-I, Korba (CG)”. It is
further observed that ‘Unit-II’ appeared in the invoices only when
SECL resumed coal supply to Unit-2 from July 2012 onwards. It was
mentioned by LAPL that the difference between allocated quantity
and actual received quantity is due to usage of different coal wagons
from the accounted one (BOBRN vis a vis BOXN wagons). Similar
difference is observed for Unit-1 as well.
The Commission observes that substantial quantum of power
sent out from LAPL Unit 2 after COD till March 2013, was under
Unscheduled Interchange (UI) mechanism. Thus the Commission was
required to take a view whether the cost of coal procured from other
314 | P a g e
sources at a much higher price and used for UI should be passed on to
the consumers of Haryana or not and further whether month wise
GCV of coal or weighted average GCV of coal for the year should be
considered for tariff determination.
The HERC Tariff Regulation, 2008, does not provide details/
methodology for adjustment of the capital cost after accounting for
revenue from UI after COD, and hence, a mechanism had to be
devised wherein the landed cost of coal for supply of power to
Haryana could be calculated considering the coal from other sources
namely, imported, open market, e-auction etc. to be first allocated for
UI and remaining coal to be considered for Haryana.
In this regard E&Y suggested the following methodology
for working out the coal cost for supply of power to Haryana
Discoms:-
i) The cost of coal procurement for power supply to Haryana is
adjusted for 0.8% normative transit and handling losses since
the coal considered for power supply to Haryana is primarily
linkage coal.
ii) To calculate the landed cost of coal each month, weighted
average yearly rate is used for coal from different sources.
315 | P a g e
iii) Rate of coal from different sources is calculated from the
quantity and value of coal procured and is as per form-19 Fuel
Summary, provided by LAPL.
iv. In Order to calculate the cost of coal for supplying power to
Haryana Discoms, the following broad methodology was
adopted,
a. First, required coal used for generation of UI power is
allocated in the Order of imported, open market, e-auction and
then linkage. Coal used for generation of UI is fulfilled at the
end of each month.
b. Second, the remaining required coal required for
generation of power supplied to Haryana & CG Discoms is
allocated in the Order of remaining amount of linkage,
remaining amount of e-auction, remaining amount of open
market and finally remaining amount of imported coal. Coal
with respect to Haryana & CG is not sufficient for the months of
Jun, Jul & Aug’11 and May’12 and, hence, coal transferred from
Unit 1 is assumed to have fulfilled the shortfall.
c. Third, as per LAPL submissions, certain amount of
coal was transferred to unit -2 from unit-1 and for the purpose
of this analysis, this transferred coal is assumed to be kept in a
transfer account. Coal from this transfer account is considered
to have been used for meeting the shortfall for the months of
Jun, Jul & Aug’11 and May’12, as mentioned above. The transfer
316 | P a g e
of coal stock from Unit-1 to Unit-2 is considered at the actual
rate as provided by LAPL in form-19 Fuel Summary. It is
pertinent to mention that transfer of coal to unit-2 from unit-1
has only been considered to the tune of fulfilling the shortfall for
the months mentioned above.
d) GCV for various types of coal is different, but for the
purposed of this analysis, coals from all sources are considered
to have the same GCV”.
On the above methodology suggested by E&Y, LAPL vide their
reply/clarification furnished vide affidavit dated 18.12.2014 submitted
that the methodology of E&Y considering the supply of coal from
other sources i.e. imported, open market, e-auction etc. to be first
allocated for UI and the remaining coal to be considered for the
Discoms for computation of energy charges is not correct. The main
reasons given by LAPL are as under:-
a) That the linkage coal was sufficient to meet only 46%
average PLF in FY 2011-12 (up to April 2012). Further the
linkage coal supplied from July 2012 to March 2013 was
sufficient to meet only 26% average PLF and thus sufficient
linkage coal was not available even to run the plant at technical
minimum limit of 50% PLF.
317 | P a g e
b) There was progressive reduction of linkage coal
supplied by SECL over a period of time which necessitated
procurement of coal from available alternate sources i.e. e-
auction/open market/imported coal during the period of supply
of power to PTC for Haryana.
c) During the period July 2012 to March 2013, LAPL was
forced to run the Unit at minimum technical loads due to grid
restrictions, at times with steam bypass valve in open mode
with average PLF of around 52.7%. Under these circumstances
LAPL had no option but to inject power as UI.
On the issue of same GCV of coal taken for coal
procured from different sources, LAPL submitted that, “any
analysis which considers the same GCV of coal procured from
different sources will give wide variations in the month wise
cost of coal”.
In response to the observations of LAPL on the
methodology of coal cost computation and GCV, E&Y further
clarified as under:-
“With regard to GCV of coal:-
In this regard, we would like to explain that in
light of limited information on GCV obtained from the
318 | P a g e
coal invoices provided to EY, GCV of Linkage coal and
e-Auction coal are same (Grade F as mentioned in
most of the invoices). For Open market coal, as per
some of the invoices GCV of coal is found to be in the
range of 2856-3322 kcal/kg which is similar to the GCV
of Linkage and e-Auction coal. No mention of GCV is
found in case of imported coal invoices. Considering
the higher rate of imported coal and general industry
knowledge, the GCV of imported coal would have been
higher than coal from other three sources. However
quantum of imported coal is only 0.73% of the entire
coal used from COD to 31st Mar’13 as per our cost of
coal calculation. Therefore, the impact of considering
same GCV irrespective of sources of procurement
would not be significant.
With regard to Sale of power under UI mechanism
after COD:-
As per latest submission filed by LAPL dated
19.12.2014 pursuant to the case no HERC/PRO-05 of
2014, LAPL mentioned, “During certain months,
especially from July 2012 to March 2013, due to grant
of partial open access or complete rejection of open
access applications, the schedule of PTC (Haryana)
was not sufficient to run the coal based Unit even at
319 | P a g e
minimum technical loads (50%). There were times
when Lanco had to run the Unit at technical minimum
loads by opening the steam bypass valve. Under these
circumstances, Lanco had no option but no inject
power as UI.”
It is agreed that at times Lanco had to inject UI
power so as to maintain certain economical minimum
PLF. However the extent of sale of UI power has to be
considered especially in a situation wherein there was
a shortage of cost effective Linkage coal. The monthly
actual PLF is calculated based on no of days of
declared availability/Quantum requested to
NRLDC/WRLDC in the following table. As observed in
the following table, there are certain months
(highlighted) when considerable UI power was sold
with the Unit run at high PLF even when the
availability of Linkage coal was less.
Haryana
Sent out (MUs)
Chhattisgarh
Sent out (MUs)
UI (MUs) Percentage
of UI
No of days
of declared availability
*
Actual PLF
considering only
available days
Percentag
e of Linkage
coal procured
May-11 77.94 75.34 49.15% 25 94.28% 0%
Jun-11 57.71 9.60 75.45 52.85% 30 73.13% 0%
Jul-11 34.53 21.12 12.23 18.02% 11 95.42% 0%
Aug-11 85.17 42.17 33.12% 28 69.80% 0%
Sep-11 97.98 32.51 24.91% 29 68.93% 35%
Oct-11 95.63 49.38 23.63 14.01% 31 82.83% 34%
320 | P a g e
Nov-11 87.00 45.60 18.66 12.34% 30 76.82% 54%
Dec-11 81.37 43.48 15.05 10.76% 31 68.96% 100%
Jan-12 85.56 44.63 19.20 12.85% 31 76.48% 100%
Feb-12 80.04 41.76 10.44 7.89% 29 70.09% 100%
Mar-12 95.16 44.64 17.50 11.13% 31 77.89% 100%
FY12 878.09 300.21 342.18
Apr-12 100.80 45.00 18.22 11.11% 30 84.00% 53%
May-12 74.36 39.99 4.71 3.96% 24 76.65% 4%
Jun-12 0 NA
Jul-12 22.03 11.76 12.82 27.50% 9 85.88% 56%
Aug-12 66.31 27.19 45.15 32.56% 31 70.29% 80%
Sep-12 73.50 27.04 28.59 22.14% 30 66.69% 0%
Oct-12 57.50 1.92 62.99 51.46% 31 61.51% 44%
Nov-12 23.37 86.66 78.76% 30 57.73% 47%
Dec-12 33.23 61.38 64.88% 29 51.38% 49%
Jan-13 90.08 26.07 22.45% 31 57.77% 46%
Feb-13 70.48 27.57 28.12% 28 54.66% 47%
Mar-13 25.11 38.65 60.62% 21 47.55% 78%
FY13 636.77 152.90 412.81
* Source: Annexure-E- PTC(Haryana) Availability Summary as submitted by LAPL dated 19.12.2014 In absence
of the revenue details from sale of UI power and any relevant HERC regulation detailing out the treatment of the surplus earning from sale of UI power after adjusting for the fuel
In absence of the revenue details from sale of UI
power and any relevant HERC regulation detailing out
the treatment of the surplus earning from sale of UI
power after adjusting for the fuel charges after COD, it
cannot be assessed whether there should be any
impact of UI surplus on the determination of tariff of
the power sold to Haryana. EY is of the opinion that
excess sale of UI power has no bearing on the tariff of
321 | P a g e
power sold to Haryana Discoms as long as no unjust
fuel charges is loaded on the consumers of Haryana
Discoms. However in this case LAPL had to resort to
expensive sources of coal procurement because of
shortage of Linkage supply from SECL. On one hand,
LAPL had to procure expensive coal in Order to run the
plant at above the minimum economical PLF. On other
hand, LAPL, being aware of the 150 MW scheduling
cap as mentioned by PTC, could have reduced the PLF
to the extent possible so as to avoid the excess usage
of uneconomical coal.
In this context, since no optimum justifiable
quantum of UI revenue can be estimated, the best
possible course of settlement would be by using the
landed cost of coal for supply of power to Discoms in
such a way so that the coal from other sources
namely, imported, open market, e- auction etc. is first
allocated for UI and remaining coal along with Linkage
coal is considered for Discoms”.
Accordingly, as per E&Y methodology the
weighted average coal cost for supply of power to Haryana for
322 | P a g e
FY 2011-12 and FY 2012-13 works out as under:-
Power scheduled to Haryana
Coal quantity used for generating power for Hry
Value of coal used for generating power for Hry.
Weighted average rate
(MUs) (MT) (Rs.) (Rs./MT)
FY 2011-12 878.09 706,270.01 1,24,67,59,71 1,765.27 FY 2012-13 636.77 539,840.20 89,64,75,73 1,660.63
The Commission has carefully considered the
methodology adopted by E&Y for working out weighted
average coal cost as well as the submissions of LAPL on the
same. The Commission, from the generation data/details of
energy sold to Haryana, Chhattisgarh and injected as UI,
provided by LAPL and as analyzed by E&Y observes that LAPL
has been generating power in excess of minimum technical
limit despite the admitted shortage of linkage coal. Thus, the
argument of LAPL that they had to inject UI in Order to
maintain minimum technical limit of generation does not hold
any ground. The Commission is, therefore, of the view that the
methodology adopted by E&Y for working out the weighted
average cost of coal is the only just and fair mechanism to
ensure that higher cost incurred by LAPL on procurement of
costlier coal for generation of UI is not passed on to the
consumers of Haryana. However, there are certain aberrations
in the ibid methodology.
323 | P a g e
They are as under:-
i) The normative coal transit & handling loss of 0.8 has been
applied by E&Y for coal consumption worked out for Haryana
from all sources including imported coal.
ii) Coal from the transfer account was considered to
have been used for meeting the shortfall for the months of
June, July & August, 2011 and May, 2012 after exhausting the
coal available from all other sources. Consequently, in some of
the months costlier imported coal and open market coal was
assigned for generation with reference to Haryana schedule
despite the availability of cheaper transferred coal.
iii) E&Y while computing weighted average cost of coal
has not taken into account 6156.82 MT of Coal, which as per
LAPL clarification, was attributed to accounting adjustments in
the month of November, 2012.
iv) After July, 2012, SECL vide letter dated 28th
September, 2012, restricted the supply of linkage coal up to
65% of 273 MW or 59% of 300 MW i.e. corresponding to the
capacity of LAPL Unit – 2 covered under PPA with Discoms of
Haryana through PTC and accordingly supply of linkage coal for
Chattisgarh stood discontinued. However, E&Y in their
324 | P a g e
calculations of weighted average cost of coal have considered
linkage coal for Chattisgarh even beyond July, 2012.
In view of the deficiencies (supra) in the E&Y calculations
of weighted average cost of coal the Commission adopted the
methodology for computation of weighted average cost of coal for
determination of fuel/variable cost. The methodology adopted by
the Commission is in line with the E&Y calculations except that the
aberrations as mentioned above have been appropriately addressed.
In these calculations, the Commission has used the data regarding
month wise coal consumption, source wise coal receipts and
corresponding rates as provided by LAPL. The coal transportation
charges and un–loading charges as provided by LAPL have been
considered for the purpose of tariff determination. Before proceeding
further on the methodology of computation of coal cost, the
Commission notes that to a specific query that ‘what was the process
followed for procurement of coal other than SECL coal and whether
any approval of Haryana/PTC was sought for procurement of e-
auction/open market/imported coal’ LAPL replied vide their filing
dated 19.12.2014 as under:-
“The power was supplied to PTC for onwards supply to
HPGCL/HPPC pursuant to APTEL’s interim Order dated 23.03.2011
which was continued by the Hon’ble Supreme Court Order dated
16.12.2011. There was no specific direction of the Court in respect of
fuel to be used for supply of power. In absence or shortage of linkage
325 | P a g e
coal Lanco had to make good the shortage by procuring coal from e-
auction tenders from SECL, tendering process for open market
domestic coal and imported coal to get the lowest prices of coal, for
supply of power generated from Unit – 2 under the above said
direction of APTEL ad the Hon’ble Supreme Court”.
It has been further submitted by LAPL that “PTC/HPGCL (HPPC)
has never raised objection on the usage of the type of Coal for
Unit – 2”.
The Commission has considered the above submissions of LAPL
and observes that the LAPL should have sought specific approval of
PTC/HPPC for procurement of Coal from costlier sources like open
market or imported coal.
The methodology adopted by the Commission for
computation of weighted average cost of coal for determination of
fuel/variable cost is as under:-
Step 1:-
The opening stock of quantum of coal from all sources i.e. SECL, E-
auction, Open Market, Import) has been considered along with its
value (as per LAPL at the time of CoD) for the gross generation for the
power supplied to Haryana, Chhattisgarh and that injected under UI
Mechanism.
326 | P a g e
Step 2:-
Source wise procurement of coal is taken along with its value. Transit
& handling loss (0.8%) for coal supplied through linkage (SECL) is also
taken into account white computing the final quantity of coal received
through linkage. Further the cost of coal Transportation and
unloading charges as supplied by LAPL, as already stated, have also
been considered while computing the cost of coal received by LAPL
during the month.
Step 3:-
By adding to the source wise monthly opening stock of coal the
source wise monthly procurement of coal, the total quantity of coal
(sources wise) along with its value has been arrived at for the month.
Step 4:-
From the source wise quantity/value of coal for the month arrived at
in Step – 3, the Coal from the costlier sources, starting with the
costliest, has been considered to have been used for power
accounted through UI mechanism after CoD. Accordingly the value of
coal considered to have been used for power accounted through UI
mechanism has been worked out. Month wise balance quantity of
coal along with its value in respect of each source has been computed
after off-setting the coal used for UI Power.
327 | P a g e
Step 5:-
From the balance source wise and month wise coal stock as computed
above, the Coal from cheaper sources, starting with the cheapest has
been considered for generation of power for supply to Haryana &
Chhattisgarh Discoms. The sources wise coal used for generation of
power supplied to Haryana and Chhattisgarh has been computed
along with its value. From the same, the weighted average value of
coal used for generation of power supplied to Haryana and
Chhattisgarh is computed month wise (up to June, 2012).
SECL vide their letter dated 28th September, 2012, reduced the coal
supply to 65% of the LAPL Unit-2 capacity and this curtailment
became effective from 01st July 2012. This restriction was imposed
considering that 177 MW (65% of 273 MW or 59% of 300 MW)
capacity of Unit – 2 is covered under PPA with Discoms of Haryana
through PTC. The Commission therefore w.e.f. July, 2012 has
considered that of the source wise balance coal in each month after
off-setting the coal used for UI Power, the costlier Coal has been
considered to have been used for generation of power for Chattisgarh
and the balance from each source to have been used for supply of
power to Haryana.
Step 6:-
The source wise balance coal, after accounting for as above for
generation during the month, is the closing stock for the month and is
328 | P a g e
transferred to the next month along with its value in source wise
manner.
In certain months, the coal has been transferred from Unit-1 to Unit-
2. The weighted average cost of transferred coal is computed. If the
same turns out to be the cheapest, the same is considered to be used
for generation of power supplied to Haryana & Chhattisgarh. The
transfer of coal stock from LAPL Unit – 2 back to Unit – 1 has been
done at the same value as considered by LAPL in their petition.
The details of coal cost computation are placed at Annexure – E
and the summary of the weighted average cost of coal arrived on the
basis of the methodology mentioned above is presented in the table
that follows:-
Computation of Weighted Average Rate of Coal
Power scheduled to Haryana
Coal quantity used for generating power for Haryana.
Value of coal used for generating power for Haryana
Weighted average rate for Haryana
FY
(MUs) (MT) (Rs. Millions) (Rs./MT)
2011- 12
878.09 706,270.01 1169.61 1656.03
2012-13
636.77 539,840.20 915.54 1695.95
In view of the fact that LAPL has not followed any mutually
agreed procedure for procurement of Coal other than linkage Coal,
the Commission directs that for future supply of power by LAPL from
Unit – 2 to PTC/HPPC a mutually agreed procedure shall be evolved
329 | P a g e
and followed for procurement of Coal other than linkage Coal till
further Order is passed in the matter by the Hon’ble Supreme Court.
Secondary Fuel Oil Consumption:-
The consumption of secondary fuel oil has been considered at 2.0
ml/kWh as per regulation 11 (4) of the HERC Regulations, 2008 and
the same has been valued as per the invoices from the oil companies
provided by the Petitioner.
Target Availability/Plant Load Factor:-
The Target Availability/Plant Load Factor, for the purpose of tariff
determination in the present case, has been considered at 80% in line
with regulation 11 (2) (a) of the HERC Regulations, 2008.
Depreciation:-
The regulation 16 (ii)(a) of the HERC Tariff Regulations, 2008 provides
as under:-
“(a) Depreciation For the purpose of tariff, depreciation shall be
computed in the following manner, namely:
(i) the value base for the purpose of depreciation shall be the historical
cost of the asset;
(ii) depreciation shall be calculated annually, based on straight line
method over the useful life of the asset and at the rates prescribed in
Appendix II to these regulations.
The residual life of the asset shall be considered as 10% and depreciation
shall be allowed up to maximum of 90% of the historical capital cost of
the asset. Land is not a depreciable asset and its cost shall be excluded
330 | P a g e
from the capital cost while computing 90% of the historical cost of the
asset. The historical capital cost of the asset shall include additional
capitalisation on account of Foreign Exchange Rate Variation up to
31.3.2008 already allowed by the Commission.
(iii)on repayment of entire loan, the remaining depreciable value shall be
spread over the balance useful life of the asset.
(iv) depreciation shall be chargeable from the first year of operation. In
case of operation of the asset for part of the year, depreciation shall be
charged on pro rata basis”.
The depreciation, in the present case, has been accordingly
computed on the project cost i.e. Rs. 1235.28 Crore admitted by the
Commission less land cost of Rs. 11.51 Crore and margin money of Rs.
24.22 Crore i.e. on a value of Rs. 1199.55 Crore at the weighted
average rate of 3.59% computed by LAPL.
In addition to the above, the Commission, in line with HERC
Regulations, 2008, has also considered Advance Against Depreciation
(AAD). The calculations for AAD are given in Annexure – D.
Income Tax:-
On the issue of Income Tax, for the purpose of tariff
determination regulation 16 (vii) of HERC Regulations, 2008 provides
as under:
“Income Tax:
(a) Tax on the income streams of the generating company from its core
business, shall be computed as an expense at the rates applicable from
time to time and shall be recovered from the beneficiaries.
331 | P a g e
(b) Any under-recovery or over-recovery of tax on income shall be
adjusted every year on the basis of income-tax assessment under the
Income-Tax Act, 1961, as certified by the statutory auditors. Provided
that tax on any income stream other than the core business shall not
constitute a pass through component in tariff and tax on such other
income shall be payable by the generating company.
Provided further that the benefits of tax-holiday as applicable in
accordance with the provisions of the Income-Tax Act, 1961 shall be
passed on to the beneficiaries.
Provided also that in the absence of any other equitable basis the credit
for carry forward losses and unabsorbed depreciation shall be given in
the proportion as provided in the second proviso to this regulation.
Provided also that income-tax allocated to the generating station shall be
charged to the beneficiaries in the same proportion as annual fixed
charges.
(c)Recovery of income tax shall be done directly by the generating
company from the beneficiaries without making any application before
the Commission.
Provided that incase of any objections by beneficiaries to the amounts
claimed on account of income tax the generating company may make an
application before the Commission for its decision.
Provided further that in case the objections of the beneficiaries are found
to be invalid by the Commission then they shall make payment of the
amount claimed by the generating company alongwith late payment
surcharge at the rates as applicable from time to time”.
332 | P a g e
Accordingly, the amount of tax paid/to be paid by LAPL- 2 has
been considered as per actual for FY 2011-12 and FY 2012-13 i.e. Rs.
7.68 Crore and Nil respectively. For FY 2013-14 onwards the Income
Tax shall be payable as actually paid by LAPL in respect of Unit – 2.
In view of the above, the tariff worked out by the Commission
at generator’s bus for the disputed period beginning 7th May, 2011,
for supply of power from LAPL Unit – 2 to Haryana based on the
norms approved in this Order is as under (till further Order is passed
in the matter by the Hon’ble Supreme Court).
Tariff Tariff (Rs./kWh)
7th May, 2011 to 31st
March, 2012.
2.8875
FY 2012-13 2.9218
Implementation of the Tariff Order:-
This Order shall be reckoned to have come into effect from the
date of commencement of supply from LAPL Unit – 2 in compliance of
the Interim Order dated 03.01.2011 of the Hon’ble APTEL for the
period FY 2011-12 and FY 2012-13. For the subsequent period of
dispute, tariff shall be worked out based on cost parameters and
norms approved in this Order till further Order is passed in the matter
by the Hon’ble Supreme Court.
333 | P a g e
The details of tariff calculations are given in Annexure A to E
of this Order.
The tariff petition filed by LAPL in pursuance of the Hon’ble APTEL’S
judgment dated 3.01.2014 is accordingly disposed of.
This Order is signed, dated and issued by the Haryana Electricity
Regulatory Commission on 23rd January, 2015.
Date: 23.01.2015 (M.S. Puri) (Jagjeet Singh) Place: Panchkula Member Chairman
334 | P a g e
ANNEXURE - A
Parameters Unit Derivation LANCO AMARKANTAK UNIT - 2
7
th May11 to
March 2012 1
st April 12 to
31st March 2013
329 days 365 days
Capacity (MW) MW 300 300
Target Availability/PLF (Normative) % 80 80
Capital Cost Rs. Million 12352.8 12352.8
Equity Rs. Million 2668.77 2668.77
Equity % 21.6 21.6
Debt Rs. Million 9684.0 9684.0
Debt % 78.40 78.40
D/E Ratio 3.62:1 3.62:1
Return on Equity % 14.00 14.00
Interest on Term Loan % 12.76 12.76
Interest working Capital % 13.00 13.00
Depreciation Rate (weighted average) % 3.59 3.59
Gross Generation at normative PLF MU A 1895.04 2102.40
Auxiliary Energy Consumption % 9% 9%
Generation (Ex-bus) MU A1 1724.49 1913.18
Station Heat Rate (SHR) Kcal/kwh B 2410 2410
Specific Oil Consumption ml/kwh C 2 2
Gross Calorific Value of Oil Kcal/litre D 10200 10200
Gross Calorific Value of Coal K.cal/Kg E 3293 3144
Overall Heat G.cal F=(A*B) 4567046.40 5066784.0
Heat from Oil G.cal G=(A*C*D)/1000 38658.82 42888.96
Heat from Coal G.cal H= (F-G) 4528387.58 5023895.04
Oil Consumption KL I=G*1000/D=A*C 3790 4205
Coal Consumption MT J=(H*1000/E) 1375155.66 1597930.99
Cost of Oil per KL Rs/KL K 56582.00 54608.00
Landed Cost of Coal (weighted average) # Rs/MT L 1656.03 1695.95
Total Cost of Oil Rs .Mln M=(K*I)/10^6 214.45 229.62
Total Cost of Coal Rs.Mln N=(J*L)/10^6 2277.30 2710.01
Total Fuel Cost Rs.Mln O=M+N 2491.75 2939.63
Fuel Cost Rs./kWh P=O/A1 1.4449 1.5365
Fixed Cost Rs./kWh 1.4426 1.3853
Tot al Cost Rs./kWh 2.8875 2.9218
# including normative coal transit and handling loss of 0.8% on linkage coal from SECL.
Specific Coal Consumption (725.66 gms/kWh)
335 | P a g e
ANNEXURE – B
FIXED COST COMPUTATION (Rs. Millions)
EXPENSES 7 May 11 to 31 March 2012 FY 2012-13 FY 2013-14 FY 2014-15
No. of Days 329 No. of Days 365 No. of Days 365 No. of Days 365
Operation & Maintenance (O&M) 111.34 128.47 133.61 138.95
Depreciation @ weighted avg rate of 3.59% 388.16 430.64 430.64 430.64
Interest & Finance Charges @ 12.76% 1071.96 1143.86 1068.19 958.08
W/C Interest @ 13 % 160.60 194.35 194.35 194.35
ROE @ 14% 339.46 376.60 376.60 376.60
Fixed Cost 2071.52 2273.92 2203.38 2098.62
Advance Against Depreciation 339.44 376.36 376.36 376.36
Income Tax (MAT) @ 20.01% 76.80 0.00 as per actual as per actual
Total Fixed Cost (Rs. Millions) 2487.76 2650.28 2579.74 2474.98
Fixed Cost (Rs./kWh) 1.4426 1.3853 1.3484 1.2936
ANNEXURE – C
WORKING CAPITAL COMPUTATION (Rs. Million) HERC Regulations 16 (vi) of 2008
ITEMS DERIVATION LAPPL 7 May to 31 March
2012 LAPPL 1 April to 31
March 2013
Coal Stock 2 months 421.08 451.67
Oil Stock 2 months 39.65 38.27
O&M Expenses 1 months 10.29 10.71
Spares (P&E) 1% of historical cost 69.29 72.06
Receivables 2 months 830.21 922.28
W/C Requirement 1370.53 1494.98
Int (@13% 160.60 194.35
ANNEXURE – D
Advance Against Depreciation (AAD) Rs. Millions
Particulars 2011-12 2012-13
1 1/10th of the Loans 968.403 895.64
2 Repayment of the loans as considered for working out interest on loan
727.6 807.00
3 Minimum of the above 727.6 807.00
4 Less : Depreciation during the year 388.16 430.64
5 (A)1 Balance amount (3-4) 339.44 376.36
6 Cumulative repayment of the loans 727.60 1534.60
7 Less : Cumulative Depreciation 388.16 818.80
8 (B) Balance amount (6-7) 339.44 715.80
9 Advance Against Depreciation (minimum of A & B) 339.44 376.36
ANNEXURE - E
336 | P a g e
COAL COST COMPUTATION
Month
Coal quantity used for Haryana Schedule (MT)
Coal quantity used for Chhattisgarh Schedule (MT)
Coal quantity used for UI Power (MT)
Linkage Coal E-auction Coal
Qty. used for Haryana Schedule (MT)
Rate (Rs. /MT)
Qty. used for Chhattisgarh Schedule (MT)
Rate (Rs. /MT)
Qty. used for UI Power (MT)
Rate (Rs. /MT)
Qty. used for Haryana Schedule (MT)
Rate (Rs. /MT)
Qty. used for Chhattisgarh Schedule (MT)
Rate (Rs. /MT)
Qty. used for UI Power (MT)
Rate (Rs. /MT)
May-11 65,820.46 - 63,624.75 65,820.46 1,172.39 - - 63,624.75 1,172.39 - - - - - -
Jun-11 46,871.69 7,797.06 61,280.01 46,871.69 1,172.39 7,797.06 1,172.39 26,280.01 1,172.39 - - - - - -
Jul-11 29,548.77 18,073.27 10,465.72 - - - - - - - - - - - -
Aug-11 68,670.16 - 34,000.48 4,841.86 1,172.39 - - - - 31,093.06 3,060.00 - - - -
Sep-11 76,481.43 - 25,376.72 47,563.86 949.85 - - - - 28,917.57 3,184.07 - - - -
Oct-11 80,597.70 41,617.84 19,915.55 50,324.93 1,012.35 25,986.04 1,012.35 - - 30,272.77 2,942.29 15,631.80 2,942.29 - -
Nov-11 69,123.85 36,230.43 14,825.87 47,135.41 967.94 24,705.46 967.94 - - 21,988.44 2,865.48 11,524.98 2,865.48 - -
Dec-11 64,154.28 34,280.79 11,865.82 57,334.30 998.77 30,636.54 998.77 - - 6,819.99 2,865.48 3,644.25 2,865.48 - -
Jan-12 67,302.48 35,106.47 15,102.94 50,055.84 1,351.72 26,110.24 1,351.72 - - 17,246.65 2,865.48 8,996.23 2,865.48 14,695.60 2,865.48
Feb-12 62,405.30 32,559.29 8,139.82 48,351.93 1,067.72 25,227.10 1,067.72 - - 14,053.37 2,865.48 7,332.19 2,865.48 8,139.82 2,865.48
Mar-12 75,293.88 35,320.71 13,846.60 51,756.04 1,077.83 24,279.00 1,077.83 - - 23,537.84 2,865.48 11,041.71 2,865.48 13,846.60 2,865.48
Apr-12 83,618.29 37,329.59 15,114.34 51,163.21 1,086.17 22,840.72 1,086.17 - - 32,455.08 2,817.38 14,488.87 2,817.38 15,114.34 2,817.38
May-12 60,868.69 32,734.52 3,855.45 2,451.47 1,079.39 1,318.38 1,079.39 - - 11,926.28 2,791.52 6,413.82 2,791.52 - -
Jun-12 - - - - - - - - - - - - - - -
Jul-12 21,481.25 11,467.07 12,500.66 17,725.68 1,079.24 - - - - - - - - - -
Aug-12 56,778.12 23,281.51 38,659.81 56,778.12 1,093.02 - - - - - - - - - -
Sep-12 62,158.72 22,867.64 24,178.47 6,557.44 1,093.02 - - - - 21,485.93 2,987.63 - - - -
Oct-12 52,084.94 1,739.18 57,057.92 39,420.75 1,099.37 - - - - 3,664.19 2,980.77 1,739.18 2,980.77 12,695.00 2,980.77
Nov-12 21,059.67 - 78,092.89 21,059.67 1,101.31 - - 20,905.83 1,101.31 - - - - 176.58 2,980.77
Dec-12 30,923.19 - 57,119.03 30,923.19 1,091.73 - - - - - - - - - -
Jan-13 73,600.39 - 21,300.65 58,717.23 1,088.74 - - - - - - - - - -
Feb-13 56,157.03 - 21,967.22 40,822.14 1,098.93 - - - - - - - - - -
Mar-13 21,109.91 - 32,492.95 21,109.91 1,091.20 - - 9,159.64 1,091.20 - - - - - -
ANNEXURE - E
337 | P a g e
Month
Open Market Coal Imported Coal Transferred Coal
Qty. used for Haryana Schedule (MT)
Rate (Rs. /MT)
Qty. used for Chhattisgarh Schedule (MT)
Rate (Rs. /MT)
Qty. used for UI Power (MT)
Rate (Rs. /MT)
Qty. used for Haryana Schedule (MT)
Rate (Rs. /MT)
Qty. used for Chhattisgarh Schedule (MT)
Rate (Rs. /MT)
Qty. used for UI Power (MT)
Rate (Rs. /MT)
Qty. used for Haryana Schedule (MT)
Rate (Rs. /MT)
May-11 - - - - - - - - - - - - - -
Jun-11 - - - - - - - - - - - - - -
Jul-11 - - - - 6,638.95 3,812.90 - - - - 3,826.77 6,122.33 29,548.77 985.40
Aug-11 30,357.29 3,633.01 - - - - - - - - 34,000.48 6,056.40 2,377.96 985.40
Sep-11 - - - - 13,633.00 3,298.59 - - - - 11,743.72 6,056.40 - -
Oct-11 - - - - 19,915.55 3,237.69 - - - - - - - -
Nov-11 - - - - 14,825.87 3,208.28 - - - - - - - -
Dec-11 - - - - 11,865.82 3,208.28 - - - - - - - -
Jan-12 - - - - 407.35 3,208.28 - - - - - - - -
Feb-12 - - - - - - - - - - - - - -
Mar-12 - - - - - - - - - - - - - -
Apr-12 - - - - - - - - - - - - - -
May-12 14,789.58 3,375.33 7,953.68 3,375.33 3,855.45 3,375.33 - - - - - - 31,701.36 1,123.88
Jun-12 - - - - - - - - - - - - - -
Jul-12 3,755.56 3,459.72 11,467.07 3,459.72 12,500.66 3,459.72 - - - - - - - -
Aug-12 - - 23,281.51 3,453.40 38,659.81 3,453.40 - - - - - - - -
Sep-12 34,115.35 3,445.36 22,867.64 3,445.36 24,178.47 3,445.36 - - - - - - - -
Oct-12 - - - - 44,362.93 3,405.56 - - - - - - 9,000.00 1,221.77
Nov-12 - - - - 40,853.66 3,402.71 - - - - - - - -
Dec-12 - - - - 57,119.03 3,561.25 - - - - - - - -
Jan-13 14,883.16 3,708.17 - - 21,300.65 3,708.17 - - - - - - - -
Feb-13 15,334.90 3,569.86 - - 21,967.22 3,569.86 - - - - - - - -
Mar-13 - - - - 23,333.31 3,495.57 - - - - - - - -
ANNEXURE - E
338 | P a g e
Month
Transferred Coal Haryana Schedule Chhattisgarh Schedule UI Power
Qty. used for Chhattisgarh Schedule (MT)
Rate (Rs. /MT)
Qty. used for UI Power (MT)
Rate (Rs. /MT)
Total quantity of coal used (MT)
Total Cost (Rs.) Weighted Average rate (Rs./MT)
Total quantity of coal used (MT)
Total Cost (Rs.) Weighted Average rate (Rs./MT)
Total quantity of coal used (MT)
Total Cost (Rs.) Weighted Average rate (Rs./MT)
May-11 - - - - 65,820.46 77,166,952.23 1,172.39 - - - 63,624.75 74,592,740.33 1,172.39
Jun-11 - - 35,000.00 2,136.26 46,871.69 54,951,698.29 1,172.39 7,797.06 9,141,159.31 1,172.39 61,280.01 105,579,554.22 1,722.90
Jul-11 18,073.27 985.40 - - 29,548.77 29,117,245.65 985.40 18,073.27 17,809,331.83 985.40 10,465.72 48,742,420.78 4,657.34
Aug-11 - - - - 68,670.16 213,452,581.56 3,108.37 - - - 34,000.48 205,920,380.93 6,056.40
Sep-11 - - - - 76,481.43 137,254,043.73 1,794.61 - - - 25,376.72 116,094,274.64 4,574.83
Oct-11 - - - - 80,597.70 140,018,071.68 1,737.25 41,617.84 72,300,453.62 1,737.25 19,915.55 64,480,375.88 3,237.69
Nov-11 - - - - 69,123.85 108,631,679.71 1,571.55 36,230.43 56,937,983.85 1,571.55 14,825.87 47,565,535.44 3,208.28
Dec-11 - - - - 64,154.28 76,806,078.90 1,197.21 34,280.79 41,041,272.10 1,197.21 11,865.82 38,068,863.37 3,208.28
Jan-12 - - - - 67,302.48 117,081,229.38 1,739.63 35,106.47 61,072,174.70 1,739.63 15,102.94 43,416,746.33 2,874.72
Feb-12 - - - - 62,405.30 91,896,064.76 1,472.57 32,559.29 47,945,772.92 1,472.57 8,139.82 23,324,458.60 2,865.48
Mar-12 - - - - 75,293.88 123,231,434.68 1,636.67 35,320.71 57,808,440.99 1,636.67 13,846.60 39,677,102.31 2,865.48
Total FY 2011-12
706,270.01 1,169,607,080.57 1,656.03 240,985.87 364,056,589.30 1,510.70 278,444.30 807,462,452.82 2,899.91
Apr-12 - - - - 83,618.29 147,010,433.13 1,758.11 37,329.59 65,629,657.65 1,758.11 15,114.34 42,582,873.56 2,817.38
May-12 17,048.64 1,123.88 - - 60,868.69 121,486,726.34 1,995.88 32,734.52 65,334,241.35 1,995.88 3,855.45 13,013,422.08 3,375.33
Jun-12 - - - - - - - - - - - - -
Jul-12 - - - - 21,481.25 32,123,419.48 1,495.42 11,467.07 39,672,808.46 3,459.72 12,500.66 43,248,758.88 3,459.72
Aug-12 - - - - 56,778.12 62,059,714.41 1,093.02 23,281.51 80,400,332.59 3,453.40 38,659.81 133,507,724.03 3,453.40
Sep-12 - - - - 62,158.72 188,899,152.05 3,038.98 22,867.64 78,787,311.65 3,445.36 24,178.47 83,303,596.16 3,445.36
Oct-12 - - - - 52,084.94 65,255,915.55 1,252.87 1,739.18 5,184,105.09 2,980.77 57,057.92 188,921,337.23 3,311.04
Nov-12 - - 16,156.82 1,800.06 21,059.67 23,193,317.63 1,101.31 - - - 78,092.89 191,646,815.27 2,454.09
Dec-12 - - - - 30,923.19 33,759,740.93 1,091.73 - - - 57,119.03 203,414,993.78 3,561.25
Jan-13 - - - - 73,600.39 119,116,723.90 1,618.43 - - - 21,300.65 78,986,330.11 3,708.17
Feb-13 - - - - 56,157.03 99,604,213.65 1,773.67 - - - 21,967.22 78,419,813.37 3,569.86
Mar-13 - - - - 21,109.91 23,035,218.79 1,091.20 - - - 32,492.95 91,558,187.72 2,817.79
Total FY 2012-13
539,840.20 915,544,575.87 1,695.95 129,419.52 335,008,456.78 2,588.55 362,339.39 1,148,603,852.18 3,169.97