basic quality induction programme for welders`,fitters & engineers

Upload: laestat

Post on 09-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    1/54

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    2/54

    Project-overview

    IOCL VGM Spurline project , a venture in its pride to escalatetechnology in the Oil business to the next shift making CAIRNEnergy India Ltd.L&T`s construction contract for this project valued over Rs.10 Cr,

    where, both Pipeline & Piping activities included, Launcher in VGMTerminal and Receiver at IOCL Terminal.Project Pipeline spans for over 2.5km, bridging Cairn and IOCLterminal; Piping scopes over 2200inch-dia with 5 packages.This Projects construction with elevated measures in Safety, Quality

    & Stringent accomplishments with sophistication in each level of thisexecution.A Paramount in its possession, scope consists of Procurement,Fabrication, Construction, Installation, Pre-commissioning, Testing,Commissioning and Performance test run.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    3/54

    ROLLER COASTER RIDE ACCIDENTOne of the theories was due to the failure of a weld (car onto rollingmember). This speeds up more than 80kmph. It is reported that anaverage of 900 fatalities are reported each year in spite of constantinspection and most of theories were fatigue weld failures.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    4/54

    LEARNER INDUCTION PROGRAM

    Welders are to be taught about the WPS, explained to depths in themanner he understands;

    To ensure that he practices surface preparation; Fit-up checks like high-low, vertical/horizontal alignment and to re-

    ensure that he abides welding by the approved WPS; Qualified Filler wire/Electrode to be made to use and their storageconditions to be checked; Use of Owen for Low Hydrogen Electrodes(E-7018) and their effect on

    the weldments. Effect of Pre-heating & Stress Relieving on the weldments are to be

    defined in detail. Forbid multiple Fit-ups; Restrict Support tack-welds (over parent material) to a minimum; All welders must bear their ID`s on site.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    5/54

    Welding Procedure SpecificationThis directs the welder/welding operatorto weld by the rules/parameters as per

    the code requirements

    ESSENTIAL VARIABLES

    These variables are a must duringexecution and subject to changes/re-

    qualification of WPS/PQR, when thesevariables are changed. All that derive

    changes in the mechanical property areessential variables listed in the PQR

    SUPPLEMENTARY VARIABLES

    These are variables that are termed with

    specificity of their requirement, anychange in the variables will summon for

    re-qualification/re-certification of theWPS/PQR

    NON-ESSENTIAL VARIABLES

    Variables can be changed without re-qualifying the WPS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    6/54

    P number

    Assigned based on the BASE metalcharacteristics towards Weldability,Composition & Mechanical properties;

    G numberApplied for steel & steel alloys that

    belong to a group of P-numbers for thepurpose of procedure qualification,

    where, notch toughness requirementsare specified and metallurgical

    compatibilities should be considered;

    F numberApplied for grouping of electrodes

    based on their usability characteristics;Grouping done to reduce voluminous

    WPS/PQR and metallurgical

    compatibilities should beconsidered;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    7/54

    WELDING POSITIONS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    8/54

    CLASSIFICATION CURRENT ARC/PENETRATION ELECTRODE COATING

    E XXX0 DCEP DIGGING/DEEP CELLULOSE - Na

    E XXX1 AC/DCEP DIGGING/DEEP CELLULOSE - K

    E XXX2 AC/DCEN MEDIUM/SHALLOW RUTILE Ti & Na

    E XXX3 AC/DCEN/DCEP SOFT/SHALLOW RUTILE Ti & K

    E XXX4 AC/DCEN/DCEP SOFT/SHALLOW RUTILE Ti & Fe powder

    E XXX5 DCEP MEDIUM/SHALLOW BASIC LOW H 2 - Na

    E XXX6 AC/DCEP MEDIUM/SHALLOW BASIC LOW H 2 - K

    E XXX7 AC/DCEN/DCEP MEDIUM/SHALLOW IRON OXIDE - Fe powderE XXX8 AC/DCEP MEDIUM/SHALLOW BASIC LOW H 2 - Fe powder

    E XXX9 AC/DCEN/DCEP MEDIUM/SHALLOW RUTILE IRON OXIDE- Fe powder

    ELECTRODE CLASSIFICATION

    E (electrode) 70 (x1000 psi Tensile Strength) 1 (Welding Position) 8 (Coating, Penetration & Current)1 Flat, Horizontal, Vertical (up), Overhead

    2 Flat, Horizontal4 Flat, Horizontal, Overhead, Vertical (down)WELDING POSITION

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    9/54

    WELDING ELECTRODES A STUDY

    CELLULOSE RUTILE BASIC

    MECHANICAL PROPERTY GOOD GOOD EXCELLENT

    WELD-ABILITY &PENETRATION EASY & DEEP MEDIUM & SHALLOW DIFFICULT & MODERATE

    ARC-STABILITY STRONGER & HARDER, MORESPATTERS, SPRAY-FORMLIGHTER & EASIER, LESSSPATTER, SPRAY-FORM

    LIGHTER & EASIER,REDUCED SPATTER, DROP-

    FORM

    COATING THICKNESS THIN / MEDIUM MEDIUM THICK & HYGROSCOPIC(BAKING NECESSARY)

    DE-SLAGGING MEDIUM DUE TO STRONGERARC INTENSITY EASY DIFFICULT-MORE VISCOUS

    WELDING POSITION &ANGLE

    DEEP-PENETRATION AT ALLPOSITIONS & 45to 60

    VERY GOOD AT VERTICAL-DOWN & 45to 60

    FLAT, HORIZONTAL &VERTICAL-UP & 75to 90

    WELD METAL DEPOSITION 85% 65% 115%

    PARAMETERS DC(-) & DC(+) for SHALLOW &DEEP PENETRATION AC / DCDC preferred for continuous

    ARC-STABILITY

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    10/54

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    11/54

    ARC WELDING - SAFETY CONCERNS

    Rays from Arc-Welding ranges from 2500C to 6500C, hence,direct eye-view would cause corneal aberration, IR heating- causingdistortion of cartilaginous lens;

    Sparks and molten spatters impinge on the skin with high velocity-causing burns & fire hazard;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    12/54

    Electrical Hazards In-sufficient safety-wears-gloves, goggles, shoes,un-insulated / damaged holders, bare live cables and proper earthingwith soil conductivity is also a factor;

    Fumes Confined areas, electrode certification through OSHAS/othersafety standards are a must, as toxicity is a major issue;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    13/54

    Equipment operation familiarity is a concern & Safety is a prioritymeasure; Use of Flash-back arrestors & tarpaulin overs which arenot fire-proof;

    Site Management-evaluating working / conditions of clothing and

    different areas of work-nature, Usage of safety-wears in the rightmanner; committing to provide thoughts to the fellow workers.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    14/54

    1. Make sure machine is properly grounded (earth-ing);

    2. Never permit live electric parts to touch bare skin;

    3. Do not cool electrode holders by immersing in water;4. Turn off power supply when welder is not in use;

    5. Do not stand on wet areas while welding;

    6. Wear leather gloves;7. Make sure that cables are not open-striped off making the inner bare

    wire naked;

    8. Make certain that electrode holders are properly insulated;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    15/54

    1. Protect eyes and face from flying particles of slag by use of safetyglasses or face shield.

    2. Wear adequate protective clothing.

    3. Always wear leather gloves.

    4. Wear high top shoes.

    5. Keep collar, shirt pockets, etc buttoned.

    6. Do not touch the electrode or metal where welding has taken place.

    7. Handle hot metal with pliers or tongs.

    8. Keep electrode stubs properly disposed of.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    16/54

    1. Use a welding helmet with the correct shade lens for each weldingprocess, in good condition.

    2. Wear suitable clothing do not leave bare skin exposed to the rays of the arc.

    3. Do not strike the arc without covering the face and eyes. Givewarning to others before striking the arc.

    4. Avoid looking directly at the arc where others are welding withoutproper eye protection.

    5. If administered seeing the arc with the naked eyes, immediately washeyes with water.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    17/54

    1. Work only in well-ventilated, clean areas.

    2. Use great care when working on metals covered with lead or zinc.

    3. If working in a confined area use respirator or other approvedbreathing devices.

    4. In confined spaces, presence of toxic gases and ventilation for gasesduring welding should be checked initially.

    5. Necessary precautions to be taken when welding near combustiblematerials of any kind.

    6. Never weld on covered containers which may have held combustiblematerials without first taking adequate safety precautions. For

    example, fill them with water, steam clean or fill with an inert gas.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    18/54

    1. Be familiar with location and types of fire extinguishers.

    2. Familiarity with the use of extinguishers;

    3. Report any unsafe conditions that might start a fire.4. Do not weld near inflammable materials.

    5. Do not weld on containers that has/had inflammable materials.

    6. Do not weld near electrical fittings or lines.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    19/54

    HEAT TREATMENT

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    20/54

    HEAT TREATMENT an Introduction

    Pre-heating:Localized heating of the parent

    material on either sides of the joint above theambient temperature before welding.

    Post-heating:Localized heating of the welded joint

    and the HAZ.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    21/54

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    22/54

    Pre-Heating Decreases rate of thermal conductivity; Decreases the cooling rate after welding,

    thereby, susceptibility towards cracking &martensitic transformation is meagre;

    Reduces stress across the weld-parent metalinterface, thus, reduces distortion;

    Reduces shrinkage and increases parent metalsurface wettability; Moisture evacuation; Usually, ranging between 10 C to 400 C.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    23/54

    Pre-heat Temperature-Information Chiefly based on Carbon Equivalent values (Ceq) for carbon steels

    dependent on the weight percentage of carbon presence.Ceq = C + Mn /6 + (Cr + Mo + V) /5 + (Cu + Ni) /15

    Material thickness is a main factor to be considered in the evaluationof heat-treatments. Material with Large thickness dissipates heat orcools off sooner and Thinner materials tend to distort with largelinear/lateral variation and cools slowly as the volume for thermaldistribution is less.

    Upon pre-heating, hydrogen emissivity is increased, thereby,reducing prone to Weld-metal, HAZ hydrogen cracking.

    A welded joint on a high thickness job cools off immediately, as thevolume more is large to conduct/dissipate heat through the material.Therefore, pre-heating, will help the weld-puddle (molten weldbefore solidification) to cool at a slower rate. Therefore, shrinkage isminimized.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    24/54

    MILD STEEL MEDIUM CARBON &ALLOYED STEELHIGH CARBON &ALLOYED STEEL

    CARBONEQUIVALENT

    CeqC

    eq< 0.4 0.4< C

    eq0.5

    WELDABILITY EASY MEDIUM DIFFICULT

    PRE-HEAT

    10 C for thickness 1in as

    per ASME B31.3 andOptional by BS 5135

    150 C to 180 C as perASME B31.3 and 93 C

    to 204 C by BS 5135

    150 C to 400 C as perASME B31.3 and204 C to 370 C

    by BS 5135

    USE OF LOWHYDROGEN

    ELECTRODESOptional for Thicker sections

    Optional for Thinsections & Conditional

    for thicker sections

    Conditional for all size-dimensions

    POST-WELD

    HEATINGOptional for Thicker sections Conditional for thicker

    sections at 1 hr/in

    Conditional for all size-

    dimensions at 2 hr/in

    COOLING RATE AIR-COOLING SLOW VERY SLOW

    HEATAFFECTED

    ZONE (HAZ)Cracking

    Not susceptible , if lowhydrogen electrodes are

    used

    Less susceptible , iflow hydrogen

    electrodes are used

    Higher susceptibility .Mandatory use of LowHydrogen Electrodes

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    25/54

    Post-weld Heat Treatment Post weld heat treatment (PWHT), defined as

    any heat treatment after welding, is often used toimprove the properties of a weldment.

    This process is commonly referred to stressrelief , so called because it is carried out attemperatures below the critical range of thebase metal, followed by uniform cooling.

    PWHT-Stress Relieving: decreases hardness,increases ductility by decreasing yield strengthof the material.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    26/54

    Post Weld Heat Treatment Relaxes residual stresses; Recovers cold work-deformations; Improves toughness;

    Tempering to the required levels (softening), asin the case for Leaf springs used as suspensorin heavy vehicles ;

    Re-crystallization & Spherodization for specialpurpose applications .

    PWHT to be done within 14 days from the day ofwelding completion-as per ASME B31.3.

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    27/54

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    28/54

    HEATTREATMENT PROCESS

    COOLINGRATE

    MECHANICALPROPERTIES

    ANNEALINGHeated above UCT & soaked for1Hr for every 1in.Then, cooled in Furnace

    SLOW

    DUCTILITY TOUGHNESS

    STRENGTH COARSE GRAINED

    SUB-CRITICAL orSTRESS-RELIEF

    ANNEALING

    Heating around LCT (~635 C),depending on the steel and locality SLOW

    ONLY RESIDUAL STRESSRELIEVED; NO CHANGE INGRAIN STRUCTURE

    NORMALIZINGHeated above UCT & soaked for1Hr for every 1in.Then, cooled in Air

    MEDIUM

    DUCTILITY TOUGHNESS STRENGTH FINE GRAINED

    TEMPERING(DRAWING)

    Re-Heated(220 C to 723 C) toconvert the remaining Hardness intoToughness

    MEDIUM

    DUCTILITY

    TOUGHNESS STRENGTH FINE GRAINED

    HARDENINGHeated above UCT & soaked for1Hr for every 1in.

    Then, cooled in QuenchingRAPID

    DUCTILITY HARDNESS TOUGHNESS STRENGTH FINE GRAINED

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    29/54

    HEAT INPUT - INFORMATION Heat Input (H) is a relative measure of the amount of

    Energy transferred during welding. Any change in values from the WPS will call for re-

    qualification. Welding with High Q will weaken the HAZ due to its

    high temperature & Slower cooling rate-coarser grainstructure.

    H = Power / Velocity of motionduring welding, Watt-sec/mm ;

    One Joule = One Watt-sec; Cooling Rate is conversely

    proportional to the Pre-heattemperature and the Heat Input;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    30/54

    If the HEAT-INPUT is large,

    MECHANICALPROPERTIES

    Reduced Tensile & Yield StrengthIncreased Ductility, Reduced Hardness

    Notch Toughness for 1550 kJ/in for SMAW

    Notch Toughness for 50110 kJ/in for SMAW

    if S , Blow Hole, In-complete penetration, Porosity, Improper Beadsize, Ir-regular weave profile

    if V A, Complex & profuse melting of electrode, localized weldlumps, reinforcement, under-cuts, pressurized-gouging arc,weak HAZ, forced slag entrapment

    HAZLarge & Weak-HAZ/oxidation of the parent material,precipitation in some steels

    COOLINGRATE

    Lower cooling rate, Large metallurgical changes, Pre-heatrequired for some metals with low heat-input (faster cooling)

    DISTORTION Depends on thickness & large variation-angular/linear

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    31/54

    Post Heating Method

    Flexible Ceramic Pads (FCP) heatingelements- desired temperature up to 1150C

    Burners- Infrared gas burners - smaller

    sized objects.

    - Oil burners or High Velocity gasburners- larger objects

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    32/54

    Heat Treatment Furnaces

    Temporary furnaces Permanent furnaces High temperature

    furnaces

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    33/54

    BASIC FIT-UP REGULATIONS Inside cleaning, Surface Buff, Paint/stain & foreign material removal; Groove-design, Face-width, Bevel taper & Angle-made as per the

    approved procedure; Check for the appropriate material & thickness in use;

    Material for tack-supports shall be the same as the parent materialmade in use & be restricted to 4 at each 90 of 10mm max; Wedge/Bridge inserts tacked between the grooves are better

    preferred & After welding, De-tacks shall not be hammered out; Suspended pipings/Sand-bag supports tend to deviate, hence, mitre

    possibilities are to be checked & counter alignment has to be made;; RF pads shall be drilled for a hole before welding onto pipes; Use of machining wheels-GRINDING/CUTTING for appropriate

    applications; Punching/Tracing shall be made out before welding;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    34/54

    Improper BEVEL-ANGLE ,Insufficient GAP and

    DIS-QUALIFIED Branch Fit-up

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    35/54

    UN-REGULATED GAP(7mm) /MIS-MATCH FOUND, THIS

    INVOLVES SUPPORT PIPE RE-LENGTHING & WELDING

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    36/54

    JOINT INVOLVING MORE THAN 4FIT-UP SPOTS; PARENT METALELECTRODE-STROKED; POOR

    BEVEL & GROOVE DESIGN

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    37/54

    RESTRICT TACK WELDS TO AMINIMUM & EACH SHOULD

    CONTAIN STITCH WELDS/ DROPSNOT TO EXCEED 10 mm

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    38/54

    De-LINEAR ALIGNMENT

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    39/54

    IMPROPER BRANCH CUTS FORWELDING OF OLETS INNER

    DIAMETER DOEST NOT MATCH THE`OLET in FIG A; SQUARE CUTTING

    BY GRINDING WHEELas in FIG B & C;

    FLOW OBSTRUCTION & SHOCKTURBULENCE MAY BE OBSERVED IN

    DUE SERVICE

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    40/54

    `OLETS WELDED WITHFLANGES BEFORE WELDING

    ONTO PIPES; HIGH RATEDFLANGES ARE HEAVY, WOULDPOSE A MIS-FIT IN ALIGNMENT

    SIMULTANEOUS FIT-UPS-NOTADVICED; CAUSES RESTRAINT

    AMONG THE MEMBERS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    41/54

    FIG A & B : SUPPORTCHANNELS DIRECTLYWELDED TO THE PARENTMATERIAL WITHOUT ANYSANDWICH(SIMILAR TOPARENT METAL);FIG C : CS SUPPORTS AREGIVEN TO SS PIPINGS-REGRETTED;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    42/54

    PRE/POST WELD REGULATIONS Welder ID/Qualification to be checked; Electrode-baking, Amperage controls, Pre-heat are to be checked; Earthing to be tight, blunt, insulated & clamped and should not be placed

    over the parent metal; Welding cleats for fit-ups to be made by approved welder for the right

    material; Conductivity check of the electrode be made over a scrap piece; For Socket welds, minimum 2 runs required & the start point shall not

    coincide with the end point;

    Post weld De-slagging, Re-capping be made if convex peeks, Under-cuts& removal of welded cleats are observed;

    Arc-strikes must be restricted and if made should be filed-off; Weaving width shall not exceed 2.5D;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    43/54

    OBSERVATION : RF PAD WELDED ONTO PIPE JOINT;CONSEQUENCE : HAZ WEAKENING or PRECIPITATION

    SEGREGATION, JOINT INSPECTION IN-ABILITY, SERVICE LOADIMBALANCE;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    44/54

    CLEATREMOVALUN-DONE

    CRATERS ASSISTED WITH ELECTRODE DRAG &PENETRATED ARC-STRIKE

    IN-COMPLETECAPPING,

    UN-REGULATEDWEAVING

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    45/54

    DAMAGED-PIPE TACK WELD SPOTS

    DAMAGES MADE BYFIT-UP TACKS &

    GRINDING

    POOR AMPERAGE CONTROLS & PARAMETERS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    46/54

    POOR AMPERAGE CONTROLS & PARAMETERS

    IN-COMPLETE PENETRATION

    EXCESSPENETRATION

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    47/54

    ARC-STRIKES & INAPPROPRIATE EARTHING SPOTS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    48/54

    NO SURFACE PREPARATION-WELDED OVERCOATING, RESULTING IN HEAVY OXIDATION DUE TO

    HIGH HEAT INPUT & PIPE DAMAGE

    SUPPORTPENETRATING

    THRO` THE PIPE

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    49/54

    INSUFFICIENT OVERLAPPING OF BEADS

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    50/54

    LEAKS OBSERVED DUE TO ELECTRODEPENETRATION THROUGH THE THICKNESS OFTHE PIPE, INDISCIPLINED WELD LEAKSWITNESSED

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    51/54

    OBSERVATION: Leak during hydro-test, a 7 mmprotrusion (thro` thickness) found;REASON: Pipe welded with R-pad support, but, waspoorly welded with the electrode penetrating thro` thethickness;

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    52/54

    Stainless steel - AWARENESSAwareness:Heat Input (H) parameters to be checked as per the approved WPS, as

    they vary from CS to SS (H,usually lower than CS);Pipes/Tubes 2 & below are to be welded by GTAW for shallowpenetration;

    Inter-pass time delay for Distortion control in SS;Purging for SS avoids OXIDATION;Use of low/no chloride markers for markings on SS, as punching &materials/tools used in CS are regretted for use in SS;Use of the appropriate electrodes for SS;

    Use of the appropriate SS materials for supports, fit-up cleats,grinding/buffing tools;

    THERMAL BEHAVIOUR CS SSThermal Conductivity

    Thermal Expansion & Distortion

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    53/54

    CRATER STROKES

    UNDERCUT

    OXIDIZATION of impurities present in thefiller / foreign material interference

  • 8/8/2019 Basic Quality Induction Programme for Welders`,Fitters & Engineers

    54/54

    THANK U