basic design report · 11/11/2019  · b1.1: drainage failure + low tailwater. upstream water level...

305
BASIC DESIGN REPORT 115002924 11 November 2019 Rev 0 LUANG PRABANG POWER COMPANY LIMITED Luang Prabang HPP Structural Analysis Report Design Report For PNPCA only

Upload: others

Post on 29-Dec-2019

4 views

Category:

Documents


1 download

TRANSCRIPT

  • BASIC DESIGN REPORT

    11500292411 November 2019

    Rev 0

    LUANG PRABANG POWER COMPANY LIMITEDLuang Prabang HPP

    Structural Analysis ReportDesign ReportFor P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report i

    Copyright © Pöyry Energy Ltd.

    Contact

    Pöyry Energy Ltd. (Thailand)Vanit II Bldg, 22nd Floor, Room#2202 - 22041126/2 New Petchburi RoadMakkasan, RajchthewiTH-10400 BANGKOKThailandTel. +66 2 108 1000

    Robert Braunshofer, Business ManagerMobile: +66 92 264 [email protected]

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report ii

    Copyright © Pöyry Energy Ltd.

    “This report has been prepared by Pöyry Energy Ltd. (“Consultant”) for Luang PrabangPower Company Limited (“Client”, “LPCL”) pursuant to the Contract signed betweenthem (“Agreement”). This report is based in part on information not within Pöyry’scontrol. Surveys have been executed by subcontractors and information were providedto Poyry confirmed to be correct.While the information provided in this report is believed to be accurate and reliableunder the conditions and subject to the qualifications set forth herein Pöyry does not,without prejudice to Pöyry’s obligations towards the Client under the Agreement, makeany representations or warranties, expressed or implied, as to the accuracy orcompleteness of such information.

    Use of this report and any of the estimates contained herein by anyone else than theClient (“Third Party User”) shall therefore be at the Third Party User’s sole risk. Anyuse by a Third Party User shall constitute a release and agreement by the Third PartyUser to defend and indemnify Pöyry from and against any liability of Pöyry, whatsoeverin type or nature, in connection with such use, whether liability is asserted to arise incontract, negligence, strict liability or other theory of law.

    All information contained in this report is of confidential nature and may be used anddisclosed by the Client solely in accordance with the terms and conditions set forth inthe Agreement.”

    All rights are reserved. This document or any part thereof may not be copied orreproduced without permission in writing from Pöyry Energy Ltd.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report i

    Copyright © Pöyry Energy Ltd.

    Table of Contents

    1 PURPOSE AND SCOPE ................................................................................................... 1

    1.1 Introduction ......................................................................................................................... 11.2 Codes and Standards ............................................................................................................ 21.3 Other References ................................................................................................................. 21.4 Dam Safety – Performance Criteria ...................................................................................... 2

    2 POWERHOUSE ................................................................................................................ 3

    2.1 General ................................................................................................................................ 32.2 Structure Layout .................................................................................................................. 32.3 Performance Criteria ............................................................................................................ 42.4 Foundation ........................................................................................................................... 52.5 Material ............................................................................................................................... 52.6 Design Loads ....................................................................................................................... 52.6.1 Dead Load ........................................................................................................................... 52.6.2 Live Load ............................................................................................................................ 62.6.3 Water Levels ........................................................................................................................ 62.6.4 Seismic Load ....................................................................................................................... 62.7 Load Cases .......................................................................................................................... 62.8 Design Method .................................................................................................................... 92.8.1 Stability Analysis ................................................................................................................. 92.8.2 Structural Verification.......................................................................................................... 92.9 Stability Analysis ................................................................................................................. 92.9.1 Geometry ............................................................................................................................. 92.9.2 Calculation of Uplift Pressures ........................................................................................... 102.9.3 Rock Mass below Foundation ............................................................................................ 102.9.4 Upstream Hydrostatic Pressure .......................................................................................... 102.9.5 Permanent Sliding Calculations.......................................................................................... 112.9.6 Results of the Stability Analysis ......................................................................................... 112.9.7 Conclusion ......................................................................................................................... 132.10 Structural Verification of the Powerhouse Structure ........................................................... 132.10.1 General .............................................................................................................................. 132.10.2 Structural Model ................................................................................................................ 142.10.3 Results of the Structural Verification ................................................................................. 14

    3 SPILLWAY ...................................................................................................................... 15

    3.1 General .............................................................................................................................. 153.2 Structure Layout ................................................................................................................ 163.3 Performance Criteria .......................................................................................................... 173.4 Foundation ......................................................................................................................... 173.5 Material ............................................................................................................................. 173.6 Design Loads ..................................................................................................................... 183.6.1 Dead Load ......................................................................................................................... 183.6.2 Live Load .......................................................................................................................... 183.6.3 Water Levels ...................................................................................................................... 183.6.4 Seismic Load ..................................................................................................................... 193.7 Load Cases ........................................................................................................................ 193.8 Design Method .................................................................................................................. 21

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report ii

    Copyright © Pöyry Energy Ltd.

    3.8.1 Stability Analysis ............................................................................................................... 213.8.2 Structural Verification........................................................................................................ 223.9 Stability Analysis ............................................................................................................... 223.9.1 Geometry ........................................................................................................................... 223.9.2 Calculation of Uplift Pressures ........................................................................................... 233.9.3 Inclination of Sliding Surface ............................................................................................. 233.9.4 Rock Mass below Foundation ............................................................................................ 233.9.5 Siltation ............................................................................................................................. 243.9.6 Dynamic Excitation ........................................................................................................... 243.9.7 Results of the Stability Analysis ......................................................................................... 253.9.8 Conclusion ......................................................................................................................... 273.10 Structural Verification of the Spillway Structure ................................................................ 273.10.1 Structural Model ................................................................................................................ 273.10.2 Parameters ......................................................................................................................... 283.10.3 Temperature ....................................................................................................................... 283.10.4 Safety Evaluation Earthquake (SEE) .................................................................................. 293.10.5 Results ............................................................................................................................... 30

    4 NAVIGATION LOCK..................................................................................................... 31

    4.1 General .............................................................................................................................. 314.2 Structure Layout ................................................................................................................ 314.3 Performance Criteria .......................................................................................................... 324.4 Foundation ......................................................................................................................... 324.5 Material ............................................................................................................................. 324.6 Design Loads ..................................................................................................................... 334.6.1 Dead Load ......................................................................................................................... 334.6.2 Live Load .......................................................................................................................... 334.6.3 Water Levels ...................................................................................................................... 334.6.4 Backfill Loads ................................................................................................................... 344.6.5 Seismic Load ..................................................................................................................... 344.7 Load Cases ........................................................................................................................ 344.8 Design Method .................................................................................................................. 374.8.1 Stability Analysis ............................................................................................................... 374.8.2 Structural Verification........................................................................................................ 374.9 Stability Analysis ............................................................................................................... 374.9.1 Geometry ........................................................................................................................... 374.9.2 Calculation of Uplift Pressure ............................................................................................ 384.9.3 Backfill Water Level .......................................................................................................... 384.9.4 Results of the Stability Analysis ......................................................................................... 384.9.5 Conclusion ......................................................................................................................... 384.10 Structural Verification of the Navigation Lock Structure .................................................... 394.10.1 Structural Model ................................................................................................................ 394.10.2 Results of the Structural Verification ................................................................................. 39

    5 RCC CLOSURE STRUCTURE ...................................................................................... 40

    5.1 General .............................................................................................................................. 405.2 Structure Layout ................................................................................................................ 405.3 Performance Criteria .......................................................................................................... 415.4 Foundation ......................................................................................................................... 415.5 Material ............................................................................................................................. 415.6 Design Loads ..................................................................................................................... 41

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report iii

    Copyright © Pöyry Energy Ltd.

    5.6.1 Dead Load ......................................................................................................................... 425.6.2 Live Load .......................................................................................................................... 425.6.3 Water Levels ...................................................................................................................... 425.6.4 Backfill load ...................................................................................................................... 435.6.5 Seismic Load ..................................................................................................................... 435.7 Load Cases ........................................................................................................................ 435.8 Design Method .................................................................................................................. 455.9 Stability Analysis ............................................................................................................... 455.9.1 Geometry ........................................................................................................................... 455.9.2 Calculation of Uplift Pressures ........................................................................................... 465.9.3 Inclination of Sliding Surface ............................................................................................. 475.9.4 Backfill Loads ................................................................................................................... 475.9.5 Results of the Stability Analysis ......................................................................................... 475.9.6 Conclusion ......................................................................................................................... 485.10 Stress Analysis of the RCC Closure Structure .................................................................... 49

    6 RIGHT PIER ................................................................................................................... 50

    6.1 General .............................................................................................................................. 506.2 Analogy Comparison ......................................................................................................... 506.3 Results ............................................................................................................................... 516.4 Conclusion ......................................................................................................................... 52

    7 LEFT PIER ...................................................................................................................... 53

    7.1 General .............................................................................................................................. 537.2 Analogy Comparison ......................................................................................................... 537.3 Results ............................................................................................................................... 547.4 Conclusion ......................................................................................................................... 55

    ANNEXES FOR STRUCTURAL ANALYSIS REPORT............................................................ 56

    ANNEX 1. LOAD CASES .................................................................................................. 57

    ANNEX 2-1 POWERHOUSE – STABILITY CALCULATION ........................................ 58

    ANNEX 2-2 POWERHOUSE – PERMANENT SLIDING CALCULATIONS ................. 59

    ANNEX 2-3 POWERHOUSE – STRUCTURAL VERIFICATION ................................... 60

    ANNEX 3-1 SPILLWAY – STABILITY CALCULATIONS .............................................. 61

    ANNEX 3-2 SPILLWAY – STRUCTURAL VERIFICATION .......................................... 62

    ANNEX 4-1 NAVIGATION LOCK – STABILITY CALCULATIONS ............................ 63

    ANNEX 4-2 NAVIGATION LOCK – STRUCTURAL VERIFICATION ......................... 64

    ANNEX 5-1 RCC CLOSURE STRUCTURE – STABILITY CALCULATIONS.............. 65

    ANNEX 5-2 RCC CLOSURE STRUCTURE – PERMANENT SLIDINGCALCULATIONS ........................................................................................................... 66

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report iv

    Copyright © Pöyry Energy Ltd.

    List of Figure

    Figure 1-1: Main Structures of Luang Prabang HPP ................................................................ 1Figure 2-1: Section through the Powerhouse ........................................................................... 3Figure 2-2: Earthquake designation at Powerhouse section 1-1 ............................................... 4Figure 2-3: LC A1.1 - Normal + low tailwater ........................................................................ 7Figure 2-4: LC A2 - Maintenance + low tailwater ................................................................... 7Figure 2-5: LC B1.1 – Drainage failure + low tailwater .......................................................... 7Figure 2-6: LC C1.1 - PMF ..................................................................................................... 8Figure 2-7: LC C3 – Seismic load case (SEE) ......................................................................... 8Figure 2-8: LC C5 –Surcharge ................................................................................................ 8Figure 2-9: Typical Powerhouse section ................................................................................. 9Figure 2-10: Rock mass below foundation .............................................................................. 10Figure 2-11: Hydrostatic water pressure .................................................................................. 11Figure 2-12: Permanent sliding displacements (Powerhouse founded on sediment- siltsone &shale) 13Figure 2-13: FE-model of the LP HPP Powerhouse ................................................................ 14Figure 3-1: Section through the Surface Spillway bay ........................................................... 15Figure 3-2: Section through the Low Level Outlet Spillway bay ........................................... 16Figure 3-3: Spillway boundaries ........................................................................................... 17Figure 3-4: LC A1.1 – Normal + low tailwater...................................................................... 19Figure 3-5: LC B1.1 – Maintenance + low tailwater .............................................................. 20Figure 3-6: LC B2.1 – Drainage failure + low tailwater ........................................................ 20Figure 3-7: LC C1.1 – PMF .................................................................................................. 20Figure 3-8: LC C3 – Seismic load case (SEE) ....................................................................... 21Figure 3-9: LC C4 – Surcharge ............................................................................................. 21Figure 3-10: Analysis section of the low level outlet ............................................................... 22Figure 3-11: Analysis section of the Surface Spillway ............................................................ 23Figure 3-12: Inclination of sliding surface............................................................................... 23Figure 3-13: Rock mass below foundation .............................................................................. 24Figure 3-14: Possible Siltation is front of the Spillway ............................................................ 24Figure 3-15: Right Spillway model ......................................................................................... 27Figure 3-16: Left Spillway model ........................................................................................... 28Figure 3-17: EC design spectrum parameter............................................................................ 29Figure 3-18: SEE Design Spectra compared with response spectra defined in SHA ................ 30Figure 3-19: Masses considered for the earthquake design analysis ......................................... 30Figure 4-1: Layout of the Navigation Lock ........................................................................... 31Figure 4-2: Backfill at the Navigation Lock .......................................................................... 34Figure 4-3: LC A1.1 – Normal + low lock level .................................................................... 35Figure 4-4: LC B1.1 – Maintenance (lock empty) ................................................................. 35Figure 4-5: LC B2.1 – Drainage failure + low lock level ....................................................... 35Figure 4-6: LC B4 – Construction ......................................................................................... 36Figure 4-7: LC C1.1 – PMF .................................................................................................. 36Figure 4-8: LC C3 – Seismic load case (SEE) ....................................................................... 36Figure 4-9: Analysis section of the upper lock chamber ........................................................ 37Figure 4-10: FE-model of the LP HPP Navigation Lock ......................................................... 39Figure 5-1: RCC-Dam Geometry Parameters ........................................................................ 40Figure 5-2: Backfill at the RCC Closure Structure ................................................................ 43Figure 5-3: LC A1.1 – Normal + low tailwater...................................................................... 44Figure 5-4: LC B1.1 – Drainage failure + low tailwater ........................................................ 44Figure 5-5: LC B2.1 – Sediment dredging failure + low tailwater ......................................... 44Figure 5-6: LC C1.1 – PMF .................................................................................................. 45Figure 5-7: LC C3 – Seismic load case (SEE) ....................................................................... 45

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report v

    Copyright © Pöyry Energy Ltd.

    Figure 5-8: Typical RCC Closure Structure section ............................................................... 46Figure 5-9: Hydrostatic Loads and Uplift Pressure ................................................................ 46Figure 5-10: Static Backfill Loads .......................................................................................... 47Figure 5-11: Permanent Sliding displacements (the RCC Closure Structure) ........................... 48Figure 6-1: Dimensions of the dam-safety relevant part of the Right Pier .............................. 50Figure 7-1: Dimensions of the dam-safety relevant part of the Left Pier ................................ 53

    List of Table

    Table 2-1: PH blocks and main elevations ............................................................................. 4Table 2-2: Shear strength parameters for sliding stability (Powerhouse) ................................ 5Table 2-3: Dead load ............................................................................................................. 5Table 2-4: Design elevations for the Upstream water levels ................................................... 6Table 2-5: Tailrace water levels ............................................................................................. 6Table 2-6: Seismic loads ........................................................................................................ 6Table 2-7: Results of the Stability Analysis for the Powerhouse – Sediment – Siltstone &Shale 12Table 2-8: Results of the Stability Analysis for the Powerhouse – Volcanic basaltic andesite

    12Table 3-1: Design Parameters of the Spillway of LP HPP .................................................... 15Table 3-2: SP parts and main elevations .............................................................................. 16Table 3-3: Shear strength parameters for sliding stability (Spillway) ................................... 17Table 3-4: Dead load ........................................................................................................... 18Table 3-5: Design elevations for the Upstream water levels ................................................. 18Table 3-6: Tailrace water levels ........................................................................................... 19Table 3-7: Seismic loads ...................................................................................................... 19Table 3-8: Calculation of the overall acceleration using the RSA for the FE model.............. 25Table 3-9: Results of the Stability Analysis for the Surface Spillway ................................... 26Table 3-10: Results of the Stability Analysis for the Low Level Outlet .................................. 26Table 3-11: FE model paramter ............................................................................................. 28Table 3-12: Parameters for the design response spectra used for the Spillway design ............. 29Table 4-1: Upper lock blocks ............................................................................................... 32Table 4-2: Shear strength parameters for sliding stability (Navigation Lock) ....................... 32Table 4-3: Dead load ........................................................................................................... 33Table 4-4: Design elevations for the reservoir water levels .................................................. 33Table 4-5: Tailrace water levels ........................................................................................... 34Table 4-6: Seismic loads ...................................................................................................... 34Table 4-7: Results of the Stability Analysis for the Navigation Lock ................................... 38Table 5-1: PC blocks and main elevations ........................................................................... 41Table 5-2: Shear strength parameters for sliding stability ..................................................... 41Table 5-3: Dead load ........................................................................................................... 42Table 5-4: Design elevations for the Upstream water levels ................................................. 42Table 5-5: Tailrace water levels ........................................................................................... 42Table 5-6: RCC Clousre Sturcture backfill elevations .......................................................... 43Table 5-7: Seismic loads ...................................................................................................... 43Table 5-8: Backfill properties .............................................................................................. 47Table 5-9: Results of the Stability Analysis for the Low Level Outlet .................................. 48Table 6-1: Analogy between the Right Pier and the right side of the Powerhouse ................ 51Table 7-1: Analogy between the Left Pier and the left side of the Powerhouse ..................... 54

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 1

    Copyright © Pöyry Energy Ltd.

    1 PURPOSE AND SCOPE

    1.1 IntroductionThe purpose of the present document is to summarize the performed civil basic designof the water retaining structures of the Luang Prabang Hydroelectric Power Project (LPHPP). The civil design includes the stability analysis and the structural verification ofimportant structural members for the following structures:

    · Powerhouse (PH)

    · Spillway (SP)

    · Navigation Lock (NL)

    · RCC Closure Structure (RC)The stability of the Right Pier (RP) and the Left Pier (LP) has been proven by analogyconclusion to the Powerhouse.It is understood that the basic design summarized in the present report is based on thedata and general requirements known in September 2019, and may be subject toadjustments as new information and updated requirements will become available. Theboundary conditions, design requirements, design principles and the applicable loads aredefined in the Design Criteria report. The civil design is performed according tointernational standards and the Lao Electric Power Technical Standard (LEPTS) asfurther defined in the Design Criteria report.

    The design of the cofferdams, the foundation treatment as well as the design of theexcavation and slopes is presented in other reports.

    Figure 1-1: Main Structures of Luang Prabang HPP

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 2

    Copyright © Pöyry Energy Ltd.

    1.2 Codes and StandardsThe LP HPP shall be designed in accordance with the most recognized internationalstandards and complies with the Lao Electric Power Technical Standard (LEPTS).Further information is given in the Design Criteria.

    · ICOLD: International Commission on Large Dams: Guidelines

    · USACE: United States Army Corps of Engineers: Engineering Manuals

    · ACI: American Concrete Institute: ACI 318

    · ASCE: American Society of Civil Engineers: ASCE 7

    · FEMA: Federal Emergency Management Agency: Guidelines

    · LEPTS: Lao Electric Power Technical Standard

    · MRC: Mekong River Commission

    1.3 Other ReferencesReference is made to the Design Criteria report where the basic design assumptions andloads are summarized. The findings and parameters from other studies such as theseismic hazard assessment or the geotechnical report are also summarized in the DesignCriteria report.

    · Luang Prabang HPP, Design Criteria (Revision 0 dated on 04.10.2019)

    1.4 Dam Safety – Performance CriteriaThe structures dealt with in this report are dam-safety relevant structures. The SafetyGuidelines issued by the International Committee on Large Dams (ICOLD) give thefollowing performance criteria under the probable maximum flood (PMF) and the safetyevaluation earthquake (SEE) loading:

    · The structures are flood-safe during the probable maximum flood (PMF).Therefore the access to the interior of the structures (i.e. Powerhouse and allgalleries) is above the PMF level in the LP HPP.

    · Following the 475 years’ Operating Basic Earthquake (OBE), there should eitherbe no damage or minor repairable damage.

    · During and after the Safety Evaluation Earthquake (SEE), damage is allowable,but it must not lead to catastrophic failure or uncontrolled release of thereservoir. According to the USACE, damage also includes permanent slidingdisplacements in the stability analysis and inelastic deformations in the structuraldesign considered with the demand capacity ratio (DCR) approach.

    Further details are given in the seismic design approach presented in the Design Criteriareport.For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 3

    Copyright © Pöyry Energy Ltd.

    2 POWERHOUSE

    2.1 GeneralThe Luang Prabang Powerhouse (PH) is located within the Mekong mainstream andforms part of the water retaining structures. Therefore, the Powerhouse must fulfil allrequirements that are applicable to a dam at that location. This includes the ProbableMaximum Flood (PMF) and the Safety Evaluation Earthquake (SEE) which is thegoverning load case for the stability analysis and the structural design.The principal arrangement of the Powerhouse comprises of a central part formed by thePowerhouse structure with the seven (7) vertical Kaplan units (main units, 200 MW and765 m3/s each) and the auxiliaries, and an erection bay at each end of the Powerhouse(including unloading bays above the erection bay at each end). The erection bay conceptallows simultaneous assembly of three (3) rotors.

    Bridges and access platforms over the entire length of the Powerhouse will be provided.Further the upstream and downstream fish migration system is integrated in thePowerhouse structure, with the collector system on the upstream side (downstreammigration) and downstream (upstream migration).

    Figure 2-1: Section through the Powerhouse

    2.2 Structure LayoutThe Powerhouse is a reinforced Conventional Vibrated Concrete (CVC) structurefounded on solid rock. All forces, mainly horizontal forces in flow direction, aretransmitted within the structure to the bottom of the foundation where they will betransmitted to the rock.The section of the Powerhouse can be roughly divided into three main sections:upstream with the trashrack, maintenance stoplogs and the intake gates, central with theturbines and generator and downstream with the BoP rooms and the draft tube. Themachine hall is covered with a steel roof.The Powerhouse is separated with flow parallel contraction (movement) joints into threeblocks, not counting the two erection bays.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 4

    Copyright © Pöyry Energy Ltd.

    Table 2-1: PH blocks and main elevations

    Block number and units Width xlengthfoundation

    Foundation

    Block 1: unit 1 & 2 71.5m x 95.7m Volcanic basaltic andesite

    Block 2: unit 3, 4 & 5 99.0m x 95.7m Sediment-siltstone & shale

    Block 3: unit 6 & 7 67.0m x 95.7m Sediment-siltstone & shale

    Main elevations

    Foundation 238.0 m asl

    Draft tube sill 246.0 m asl

    Intake slab 265.0 m asl

    Unit axis 266.92 m asl

    Machine Hall 283.20 m asl

    Downstream deck 310.0 m asl

    Upstream deck 317.0 m asl

    2.3 Performance CriteriaThe Powerhouse is a dam-safety relevant structure and must resist the SEE earthquakewithout uncontrolled release of reservoir. This is given when the red marked area inFigure 2-2 does not fail and the upstream power intake gate remains operational.

    For the stability analysis, permanent sliding displacements are allowed but shall remainin reasonable range, which is defined in the Design Criteria. For the structural design,the deformations must not remain in the elastic range and the demand capacity ratioconcept is permitted.

    For the civil design, the Powerhouse can be divided as follows:

    · Dam safety relevant: SEE

    · Non-dam safety relevant: MDE

    Figure 2-2: Earthquake designation at Powerhouse section 1-1

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 5

    Copyright © Pöyry Energy Ltd.

    2.4 FoundationThe resistance against sliding is determined for the LEPTS load cases considering thefriction angle and the cohesion, whereas for the USACE the cohesion has beenneglected, except for the SEE load case.Table 2-2: Shear strength parameters for sliding stability (Powerhouse)

    PowerhouseRock type in contact zone

    c [MPa] φs [°]1 φd [°]2

    Volcanic – Basaltic Andesite 0.19 50 30*

    Sediment - Siltstone & Shale 0.08 42 25*

    * assumption c=0 for τ(φd) residual, 1 σ1=750 kPa; 2 average value

    2.5 MaterialThe Spillway consists of C25 Conventional Vibrated Concrete (CVC) with fc’=25 MPa.Other concrete classes are not considered for the basic design stability analysis andreinforcement verification.

    2.6 Design LoadsReference is made to the Design Criteria report for a more detailed definition of thedesign requirements, design principles and the loads. This chapter only summarizes themain loads.The following loads have been considered for the structural design of the spillway:

    · Dead Load of the Concrete Structure and water

    · Live loads

    · Equipment Loads

    · Hydrostatic Loads

    · Uplift

    · Seismic Loads

    2.6.1 Dead LoadThe weight of the concrete is considered as indicated below for the stability analysis.For the structural verification, the weight is considered in the FE model.

    Water dead loads within the limits of the structural wedge depend on the load case(water level) and are not listed herein but considered in the calculations.Table 2-3: Dead load

    Concrete dead load Value

    Concrete volume (unit 2) 104’480 m3

    Unit weight concrete (stability analysis) 24 kN/m3

    Unit weight concrete (structural verification) 25 kN/m3

    Equipment load (Turbine, Generator) 18’335 kN

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 6

    Copyright © Pöyry Energy Ltd.

    2.6.2 Live LoadNot considered for the stability analysis.

    For the structural verification according to the Design Criteria report.

    2.6.3 Water LevelsThe following upstream water levels have been considered.Table 2-4: Design elevations for the Upstream water levels

    Upstream water level Value Type

    Design Full Supply Level (FSLD) 312.50 m a.s.l. Normal

    PMF Level (Q=41’400 m3/s) 314.20 m a.s.l. Extreme

    Maximum considered surcharge 317.00 m a.s.l. Extreme

    The tailrace water level which have been considered for the stability analysis areTable 2-5: Tailrace water levels

    Tailrace water level Tailwater Level Type

    Minimum Operating Level (MOL, Q=745 m3/s) 275.50 m a.s.l. Normal

    Coincident pool / median flow (Q=2’100 m3/s) 278.80 m a.s.l.

    10-year flood (Q=18’200 m3/s) 292.60 m a.s.l. Normal

    1000-year flood (Q=23’800 m3/s) 295.30 m a.s.l.

    PMF level (Q=41’400 m3/s) 300.50 m a.s.l. Extreme

    2.6.4 Seismic LoadThe following seismic loads have been considered.Table 2-6: Seismic loads

    Design Earthquake Return Period PGA [g]

    Horizontal Vertical

    SEE Safety Evaluation Earthquake --- (DSHA) 0.49 0.40

    OBE Operating Basis Earthquake 145 years 0.13 0.10

    The three scaled accelerograms (time histories) show horizontal accelerations in twoorthogonal directions: hor.360° and hor.90° resulting in 3×2=6 seismic combinations forboth foundation types for the SEE load case. All 2×6=12 combinations wereinvestigated for the SEE load case.

    2.7 Load CasesThe detailed load cases are defined in Annex 1. The below figures show some of theapplied load cases.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 7

    Copyright © Pöyry Energy Ltd.

    Figure 2-3: LC A1.1 - Normal + low tailwater

    Figure 2-4: LC A2 - Maintenance + low tailwater

    Figure 2-5: LC B1.1 – Drainage failure + low tailwater

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 8

    Copyright © Pöyry Energy Ltd.

    Figure 2-6: LC C1.1 - PMF

    Figure 2-7: LC C3 – Seismic load case (SEE)

    Figure 2-8: LC C5 –Surcharge

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 9

    Copyright © Pöyry Energy Ltd.

    2.8 Design Method

    2.8.1 Stability AnalysisThe stability analysis calculation for the Powerhouse has been carried out using Excel,resulting in forces and safety factors for static and pseudo-static load combinations.

    Two sections with different foundation properties according to chapter 2.4 representingthe two main bedrock types were analysed. The load cases and the applied loads are thesame for both investigated sections. The applied forces and the dead loads are for oneentire unit from the contraction joint till the limit with the next unit with a width of33.50 m.To evaluate the permanent sliding displacements, the computer program RS-DAM hasbeen used. The RS-DAM uses the scaled accelerograms (time histories) as input andone set of foundation properties

    2.8.2 Structural VerificationFor the structural verification, a FE-model has been used. The governing SEE load casehas been calculated with a time-history analysis.

    2.9 Stability Analysis

    2.9.1 GeometryThe concrete volume for the 33.50 m wide unit 2 block is given in chapter 2.6.1.

    Figure 2-9: Typical Powerhouse section

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 10

    Copyright © Pöyry Energy Ltd.

    2.9.2 Calculation of Uplift PressuresFor the uplift pressures the effect of the grout curtain and drainage gallery is considered.The reduction in uplift pressures is estimated with a drainage efficiency of 35% asdefined in the Design Criteria. A separate unusual load case for drainage failure isconsidered in the stability analysis as well.Only for the SEE load case, the drainage efficiency was assumed with 50%.

    2.9.3 Rock Mass below FoundationTwo rock mass volumes that are completely surrounded by the CVC structure areconsidered as additional mass for the sliding stability analysis. In the earthquake loadcases the rock mass below foundation is also subjected to horizontal and verticalaccelerations.Horizontal bearing resistance of the rock mass in the tailrace excavation downstream ofthe Powerhouse and at the steep slope below the draft tube is not considered.The rock parameters for the additional rock weight are as follows:

    · Rock mass volume (total): V = 4’236 m3

    · Rock mass buoyant unit weight g = 16 kN/m3

    Figure 2-10: Rock mass below foundation

    2.9.4 Upstream Hydrostatic PressureThe upstream hydrostatic pressure acting towards downstream has been applied fromthe corresponding reservoir water level till the lowest point of the foundation which is inthe centre part of the Powerhouse, below the draft tubes. A considerable portion of thatpressure however lies downstream of the grout curtain and the drainage holes thatreduce the uplift pressure as defined in chapter 2.9.2. The same reduction also applies tothe horizontally acting hydrostatic water pressure between the bottom of the upstreamgallery at elevation +254.0 m asl and the deepest point of the Powerhouse at elevation+238.0 m asl.For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 11

    Copyright © Pöyry Energy Ltd.

    Figure 2-11: Hydrostatic water pressure

    2.9.5 Permanent Sliding CalculationsThe permanent sliding displacements were calculated with the computer program RS-DAM that calculates the displacements for each time step in a time-history analysis.

    Because of the characteristic of the program that jumps back to the static friction angleas soon as the sliding safety factor is above 1.0, the residual friction angle has been usedas static friction angle as well. The cohesion is set by default as c=0 kPa. This approachoverestimates the sliding displacements because the initial sliding starts much earlierthan with the static foundation shear parameter. For this reason, an additionalverification with the static shear parameter has been done.

    Further information is given in Annex 2-2.

    2.9.6 Results of the Stability AnalysisThe civil structures shall be designed to be safe against sliding, floatation, overturningand foundation bearing. The results of stability analysis are presented below:

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 12

    Copyright © Pöyry Energy Ltd.

    Table 2-7: Results of the Stability Analysis for the Powerhouse – Sediment –Siltstone & Shale

    Table 2-8: Results of the Stability Analysis for the Powerhouse – Volcanic basalticandesite

    Safe

    ty fa

    ctor

    , exi

    stin

    g

    Safe

    ty fa

    ctor

    , req

    uire

    d

    Req

    urie

    d co

    hesi

    on (i

    n pe

    rcen

    t of

    the

    exis

    ting

    coh

    esio

    n)

    Max

    imum

    exc

    entri

    city

    Bas

    e in

    com

    pres

    sion

    , exi

    stin

    g

    Bas

    e in

    com

    pres

    sion

    , req

    uire

    d

    Safe

    ty fa

    ctor

    , exi

    stin

    g

    Safe

    ty fa

    ctor

    , req

    uire

    d

    Max

    imum

    bas

    e pr

    essu

    re

    Min

    imum

    bas

    e pr

    essu

    re

    All

    owab

    le b

    ase

    pres

    sure

    [-] [-] [%] [-] [%] [%] [-] [-] [kPA] [kPA] [kPA]

    A1.1_normal situation_USUAL 2.42 2 0.00 Middle third = L/6= 100 100 2.21 1.3 865 183 9000

    A1.2_normal situation_USUAL + HQ10 3.27 2 0.00 Middle third = L/6= 100 100 1.75 1.3 620 197 9000

    A2_maintainance_USUAL + low waterlevel 2.08 2 0.00 Middle third = L/6= 100 75 2.04 1.3 730 172 9000

    B1.1_drainage failure_UNUSUAL + low waterlevel 2.16 1.5 0.00 Middle half = L/4= 100 75 1.96 1.2 860 76 9000

    B1.2_drainage failure_UNUSUAL + HQ10 2.58 1.5 0.00 Middle half = L/4= 100 75 1.65 1.2 581 176 9000

    B2.1_OBE_UNUSUAL 1.59 1.5 0.00 Middle half = L/4= 94 75 2.02 1.2 1026 -61 9000

    C1.1_PMF_EXTREME 3.98 1.1 0.00 In the Base = L/2= 100 >0 1.65 1.1 550 227 9000

    C3_SEE_EXTREME 0.39 1.1 0.00 In the Base = L/2= 20 >0 1.88 1.1 1606 -711 9000

    C4_post SEE_EXTREME 1.20 1.1 0.00 In the Base = L/2= 100 >0 1.89 1.1 809 93 9000

    C5_surcharge_317,00_EXTREME 2.25 1.1 0.00 In the Base = L/2= 100 >0 2.14 1.1 895 127 9000

    C6_maintanance_EXTREME + HQ100 2.22 1.1 0.00 In the Base = L/2= 100 >0 1.49 1.1 447 137 9000

    A1.3_LEPTS-usual 3 3 100.00 Middle third = L/6= 100 100 2.2 865 183

    B3.2_LEPTS-seismic (OBE) 2 2 100.00 Middle half = L/4= 94 75 2.0 1026 -61

    C1.2_LEPTS-flood (PMF) 5 2 100.00 Middle half = L/4= 100 75 1.7 550 227

    Rotation Flotation Bearing capacitiy

    Load case

    Sliding

    Safe

    ty fa

    ctor

    , exi

    stin

    g

    Safe

    ty fa

    ctor

    , req

    uire

    d

    Req

    urie

    d co

    hesi

    on (i

    n pe

    rcen

    t of

    the

    exis

    ting

    cohe

    sion

    )

    Max

    imum

    exc

    entri

    city

    Bas

    e in

    com

    pres

    sion

    , exi

    stin

    g

    Bas

    e in

    com

    pres

    sion

    , req

    uire

    d

    Safe

    ty fa

    ctor

    , exi

    stin

    g

    Safe

    ty fa

    ctor

    , req

    uire

    d

    Max

    imum

    bas

    e pr

    essu

    re

    Min

    imum

    bas

    e pr

    essu

    re

    Allo

    wab

    le b

    ase

    pres

    sure

    [-] [-] [%] [-] [%] [%] [-] [-] [kPA] [kPA] [kPA]

    A1.1_normal situation_USUAL 3.20 2 0.00 Middle third = L/6= 100 100 2.21 1.3 865 183 9000

    A1.2_normal situation_USUAL + HQ10 4.33 2 0.00 Middle third = L/6= 100 100 1.75 1.3 620 197 9000

    A2_maintainance_USUAL + low waterlevel 2.76 2 0.00 Middle third = L/6= 100 75 2.04 1.3 730 172 9000

    B1.1_drainage failure_UNUSUAL + low waterlevel 2.86 1.5 0.00 Middle half = L/4= 100 75 1.96 1.2 860 76 9000

    B1.2_drainage failure_UNUSUAL + HQ10 3.42 1.5 0.00 Middle half = L/4= 100 75 1.65 1.2 581 176 9000

    B2.1_OBE_UNUSUAL 2.10 1.5 0.00 Middle half = L/4= 94 75 2.02 1.2 1026 -61 9000

    C1.1_PMF_EXTREME 5.27 1.1 0.00 In the Base = L/2= 100 >0 1.65 1.1 550 227 9000

    C3_SEE_EXTREME 0.48 1.1 0.00 In the Base = L/2= 20 >0 1.88 1.1 1606 -711 9000

    C4_post SEE_EXTREME 1.49 1.1 0.00 In the Base = L/2= 100 >0 1.89 1.1 809 93 9000

    C5_surcharge_317,00_EXTREME 2.98 1.1 0.00 In the Base = L/2= 100 >0 2.14 1.1 895 127 9000

    C6_maintanance_EXTREME + HQ100 2.93 1.1 0.00 In the Base = L/2= 100 >0 1.49 1.1 447 137 9000

    A1.3_LEPTS-usual 4 3 100.00 Middle third = L/6= 100 100 2.2 865 183

    B3.2_LEPTS-seismic (OBE) 3 2 100.00 Middle half = L/4= 94 75 2.0 1026 -61

    C1.2_LEPTS-flood (PMF) 7 2 100.00 Middle half = L/4= 100 75 1.7 550 227

    Rotation Flotation Bearing capacitiy

    Load case

    Sliding

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 13

    Copyright © Pöyry Energy Ltd.

    Figure 2-12: Permanent sliding displacements (Powerhouse founded on sediment-siltsone & shale)

    2.9.7 ConclusionAs it can be expected, the safety factors for the Powerhouse units founded on sediment-siltstone & shale are considerably lower than for the Powerhouse units founded on thevolcanic basaltic andesite.

    The floatation safety factor and the overturning in term of percent of base oncompression and location of resultant are greater than requirement for all load cases.The maximum base pressure is well below the allowable pressure for all load cases.The pseudo-static sliding stability of the Powerhouse is fulfilled for all load casesexcept for the SEE earthquake, which consequences were investigated in the permanentsliding calculations (see Annex 2-2).

    Permanent sliding displacements have been estimated to be in the range of 50 cm with aconservative approach. In an optimistic evaluation applying the static shear properties,the permanent sliding displacements tend to zero (range of 2 mm or less). The stabilityrequirements after the SEE event (C4, post SEE) is fulfilled. Because even theoverestimated displacements of 50 cm are acceptable and the effective displacementsare expected to the significantly lower (or even not present), the performance criteria forthe LP HPP Powerhouse are fulfilled.

    2.10 Structural Verification of the Powerhouse Structure

    2.10.1 GeneralMost of the forces apply at the intake walls from where they are transmitted via theintake slab and the mass concrete around the draft tube to the foundation, or via theMachine Hall floor and the generator barrel to the downstream side of the Powerhouse.A considerable force, also due to the high downstream water level fluctuations, act onthe downstream side of the Powerhouse, which is the reason for the regular pattern ofthe stiffening shear walls within the facility and equipment section of the Powerhouse.Forces at the semi spiral case and the generator foundation remain mainly in the massconcrete in the middle section of the Powerhouse but may lead to high and partiallycomplicated reinforcement arrangements. The design of the different floors of thedownstream BoP rooms, especially the floor below the transformer slab, is governed bythe construction stages, i.e. the fresh concrete weight of the subsequent floor.

    C:\ Users\ kch053\ Desktop\ Permanent_Sliding\Sediment_2019_10_02\ LPH

    0 5 10 15 20 25 30 35 40 45 50Time (sec)

    0.000.05

    0.10

    0.150.20

    0.25

    0.30

    0.350.40

    0.450.50

    Block relative displacement (m)

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 14

    Copyright © Pöyry Energy Ltd.

    2.10.2 Structural ModelA finite-element (FE) analysis has been performed for the structural verification of thePowerhouse. Calculations were done either static or as a time-history analysis for theSEE load case. For the time-history analysis, no response modification factor (R-factors) and for the SEE load case, no importance factors Ic are applied.The three sets of time history accelerograms from the seismic hazard assessment areused in the dynamic calculations. For each set of time histories, the 360° orientation wasapplied once into flow direction with the 90° orientation perpendicular to the flow, andonce applied perpendicular to the flow direction with the 90° orientation in flowdirection. These 6 separate calculations were done for both foundation conditions,resulting in 12 separate calculations.

    Figure 2-13: FE-model of the LP HPP Powerhouse

    2.10.3 Results of the Structural VerificationThe FE-model calculates the required reinforcement for the analyzed load cases.Following the demand capacity ratio (DCR) approach, the reinforcement requirementscalculated in the FE-model can be reduced (manually) because the DCR approach is notpart of the structural building codes and therefore not implemented in the FE analyzingtool.

    The results are presented in Annex 2-3.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 15

    Copyright © Pöyry Energy Ltd.

    3 SPILLWAY

    3.1 GeneralDuring flood operation the excess water (water not used for generation of electricityand/or operation of the navigation lock and fish migration Facilities) will be spilledthrough the Spillway (SP). The Spillway structure includes:

    · 6 Surface Spillway Bays

    · 3 Low Level Outlet BaysThe Spillway is arranged in two main blocks, the first block comprises four (4) SurfaceSpillway Bays and the second block comprises the three (3) Low Level Outlet bays withone Surface Spillway bay on each side (1+1).

    The main dimensions of the Spillway bays are given in the following table:Table 3-1: Design Parameters of the Spillway of LP HPP

    Surface Spillway Low Level Outlet

    Clear width of gate 19.0 m 12.0 m

    Clear height of gate 25.0 m 16.0 m

    Spillway ogee / LLO sill level 289.0 m asl 275.0 m asl

    Capacity per bay (at FSL) 4,850 m3/s 3,530 m3/s

    The operation of the Spillway will be such that the first bays in operation will be theLow Level Outlets in order to route “turbidity currents” through the Spillway and tominimize sedimentation in the reservoir area. When the capacity of the Low LevelOutlets is reached the Surface Spillway will start operation. All gates of the SurfaceSpillway will be equipped with flap gates to allow spill of floating debris in front of theSpillway into the tailwater area.

    Figure 3-1: Section through the Surface Spillway bay

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 16

    Copyright © Pöyry Energy Ltd.

    Figure 3-2: Section through the Low Level Outlet Spillway bay

    3.2 Structure LayoutThe stilling basin is structurally divided by a concrete wall between the two blocks, andis detached from the Spillway by a contraction (movement) joint. The Spillway bridges(upstream and downstream) are embedded in the Spillway piers in order to reasonablylimit the deformations of the piers at the radial gates. To gain additional stiffness, theSpillway is structurally connected to the navigation lock on the right side and to theRight Pier on its left side. The stability analysis however does not rely on thisconnection to the navigation lock or the Right PierTable 3-2: SP parts and main elevations

    Block number and units Width x length Foundation

    Part 1: 4 Surface Spillways 101.0m x 79.6m Volcanic basaltic andesite

    Part 2: 3 LLO & 2 Surface Spillways 104.0m x 76.8m Volcanic basaltic andesite

    Main elevations

    LLO foundation (at gallery) 256.22 m asl (variable)

    Surface Spillway foundation 259.05 m asl (variable)

    Surface Spillway ogee 289.0 m asl

    Downstream deck 310.0 m asl

    Upstream deck 317.0 m aslFor P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 17

    Copyright © Pöyry Energy Ltd.

    Figure 3-3: Spillway boundaries

    3.3 Performance CriteriaThe Spillway structure is a dam-safety relevant structure and must resist the SEEearthquake without uncontrolled release of reservoir.

    For the stability analysis, permanent sliding displacements are allowed if not otherwiserestraint. Due to the latera stiffness requirements, the Navigation Lock and the RightPier are structurally connected to the Spillway block. This restrains the displacements inflow direction. Therefore (and considering the fact that the Spillway is located on goodrock), permanent sliding displacements are not permitted for the present configuration.The radial gate must be operational after an SEE event and the deformations of theSpillway piers shall remain elastic, following the limits of the radial gate supplier.Therefore the demand capacity ratio (DCR) approach is not applied to the Spillwaypiers.

    3.4 FoundationThe stability analysis design parameters used for the safety factor against sliding arelisted in the table below.

    The resistance against sliding is determined for the LEPTS load cases considering thefriction angle and the cohesion, whereas for the USACE the cohesion has beenneglected, except for the SEE load case.Table 3-3: Shear strength parameters for sliding stability (Spillway)

    Spillway

    Rock type in contact zone

    c [MPa] φs [°]1 φd [°]2

    Volcanic – Basaltic Andesite 0.17 50 30*

    * assumption c=0 for τ(φd) residual, 1 σ1=550 kPa; 2 average value

    3.5 MaterialThe Spillway consists of C25 Conventional Vibrated Concrete (CVC) with fc’=25 MPa.Other concrete classes are not considered for the basic design stability analysis andreinforcement verification.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 18

    Copyright © Pöyry Energy Ltd.

    3.6 Design LoadsReference is made to the Design Criteria report for a more detailed definition of thedesign requirements, design principles and the loads. This chapter only summarizes themain loads.

    The following loads have been considered for the structural design of the Spillway:

    · Dead Load of the Concrete Structure

    · Hydrostatic Loads

    · Uplift

    · Earthquake Loads

    3.6.1 Dead LoadThe weight of the concrete is considered as indicated below for the stability analysis.For the structural verification, the weight is considered in the FE model.Water dead loads within the limits of the structural wedge depend on the load case(water level) and are not listed herein but considered in the calculations.Table 3-4: Dead load

    Concrete dead load Value

    Concrete volume Surface Spillway (width 24m incl. pier) 34,195 m3

    Concrete volume LLO (width 17m incl. pier) 39,677 m3

    Unit weight concrete (stability analysis) 24 kN/m3

    Unit weight concrete (structural verification) 25 kN/m3

    Equipment load (radial gate, stoplog) Not considered

    3.6.2 Live LoadNot considered for the stability analysis.For the structural verification according to the Design Criteria report.

    3.6.3 Water LevelsThe following upstream water levels have been considered.Table 3-5: Design elevations for the Upstream water levels

    Upstream water level Value Type

    Design Full Supply Level (FSLD) 312.50 m a.s.l. Normal

    PMF Level (Q=41’400 m3/s) 314.20 m a.s.l. Extreme

    Maximum considered surcharge 317.00 m a.s.l. Extreme

    The tailrace water level which have been considered for the stability analysis are

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 19

    Copyright © Pöyry Energy Ltd.

    Table 3-6: Tailrace water levels

    Tailrace water level Tailwater Level Type

    Minimum Operating Level (MOL, Q=745 m3/s) 275.50 m a.s.l. Normal

    Median Annual Discharge (Q=2’100 m3/s) 278.80 m a.s.l. Normal

    PMF level (Q=41’400 m3/s) 300.50 m a.s.l. Extreme

    3.6.4 Seismic LoadThe following seismic loads have been considered:Table 3-7: Seismic loads

    Design Earthquake Return Period PGA [g]

    Horizontal Vertical

    SEE Safety Evaluation Earthquake --- (DSHA) 0.49 0.40

    OBE Operating Basis Earthquake 145 years 0.13 0.10

    3.7 Load CasesThe detailed load cases are defined in Annex 1. The below figures show some of theapplied load cases.

    Figure 3-4: LC A1.1 – Normal + low tailwaterFor P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 20

    Copyright © Pöyry Energy Ltd.

    Figure 3-5: LC B1.1 – Maintenance + low tailwater

    Figure 3-6: LC B2.1 – Drainage failure + low tailwater

    Figure 3-7: LC C1.1 – PMF

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 21

    Copyright © Pöyry Energy Ltd.

    Figure 3-8: LC C3 – Seismic load case (SEE)

    Figure 3-9: LC C4 – Surcharge

    3.8 Design Method

    3.8.1 Stability AnalysisThe stability analysis calculation for the Spillway was carried out using Excel, resultingin forces and safety factors for static and pseudo-static load combinations.For the response spectra analysis of the stability analysis, the dynamic excitation iscalculated with a FE model (see structural analysis) and its value inserted into the Excelsheet. For further details of the RSA applied for the stability analysis please refer to3.9.6. The finite element model is further explained in chapter 3.10.1.The following load case has been investigated and is only governing for buoyancy /floatation verification.

    · Earthquake load combination = +

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 22

    Copyright © Pöyry Energy Ltd.

    3.8.2 Structural VerificationFor the structural verification, a FE-model has been used. The governing SEE load casehas been calculated with a response-spectrum analysis.

    3.9 Stability Analysis

    3.9.1 GeometryTo prove the stability of the two Spillway blocks, two independent stability analyses forthe Surface Spillway and the LLO have been performed to prove that every section isstable for itself. The connection to the Navigation Lock on the right side and the RightPier on the left side of the Spillway were not taken into account.The analysis is based on one entire Surface Spillway or LLO block including two timeshalf of the pier and a width of 24.0 m (Surface Spillway) and 17.0 m (LLO)respectively. The analysis sections are presented below:

    Figure 3-10: Analysis section of the low level outlet

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 23

    Copyright © Pöyry Energy Ltd.

    Figure 3-11: Analysis section of the Surface Spillway

    3.9.2 Calculation of Uplift PressuresFor the uplift pressures the effect of the grout curtain and drainage gallery is considered.The reduction in uplift pressures is estimated with a drainage efficiency of 35% asdefined in the Design Criteria. A separate unusual load case for drainage failure isconsidered in the stability analysis as well.

    3.9.3 Inclination of Sliding SurfaceThe sliding surface below the rock has an inclination of 1.3° for the Surface Spillwaycross-section and 2.1° for the low level outlet cross-section. The respective inclinationshave been considered in the stability analysis for the sliding stability verification.

    Figure 3-12: Inclination of sliding surface

    3.9.4 Rock Mass below FoundationThe rock mass below the heel of the foundation has been considered as additional massfor the sliding stability. In the earthquake load cases the rock mass below foundation isalso subjected to horizontal and vertical accelerations.The rock parameters for the additional rock weight are as follows:

    · Rock mass volume (Surface Spillway): V = 8’640 m3

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 24

    Copyright © Pöyry Energy Ltd.

    · Rock mass volume (LLO): V = 2’910 m3

    · Rock mass buoyant unit weight g = 16 kN/m3

    Figure 3-13: Rock mass below foundation

    3.9.5 SiltationSiltation in front of the Spillway radial gates has been checked and is considered notcritical for the stability of the structure. This is caused by the favourable effect of the(stabilizing) vertical load in case of siltation providing additional weight for a length ofapproximately 30 m as shown in the sketch below.The favourable effect of stabilizing vertical loads compared to driving horizontal loadsis also valid for earthquake load cases with increased horizontal loads.

    Figure 3-14: Possible Siltation is front of the Spillway

    3.9.6 Dynamic ExcitationThe input for the RSA used for the stability analysis is based on the FE model furtheroutlined in section 3.10 The natural frequencies, the mobilized mass per naturalfrequency (participation) and the modal reply of the system are calculated in the FEprogram.

    Based on the results obtained from the FE analysis the overall acceleration of thestructure considering its actual frequencies is calculated as shown in the table below asan example for the natural frequencies of the Low Level Outlet Structure. In this casethe natural frequency number 4 with a period of 0.275 seconds contributes a significantpart of the mobilized mass in x-direction (flow direction). The number of natural

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 25

    Copyright © Pöyry Energy Ltd.

    frequencies considered must be such, that at least 90% of the mass in the respectivedirection are mobilized. Finally the sum of the spectral accelerations for each mode willdetermine the overall acceleration of the structure considered in the stability analysis(here: 0.25g).Table 3-8: Calculation of the overall acceleration using the RSA for the FE model

    Mode ξ (sec) Mx (%) Sx (-) Mx * Sx *ag/ R

    1st 0.585 0 0.803 0.000

    2nd 0.393 0.2 1.196 0.000

    3 0.296 4.2 1.587 0.008

    4 0.275 25.7 1.71 0.054

    5 0.256 0.2 1.835 0.000

    6 0.242 0 1.942 0.000

    7 0.231 0.6 2.035 0.001

    8 0.226 3.4 2.084 0.009

    9 0.22 1.8 2.137 0.005

    ... 0.216 3.7 2.174 0.010

    n

    Sum >90% 0.250

    ξ... period of natural frequency n

    Mx... mobilized mass in flow direction for natural frequency nSx... Normalized response acceleration (modal reply)

    ag... Peak Ground Acceleration in the respective direction (here: 0.49)

    3.9.7 Results of the Stability AnalysisThe civil structures shall be designed to be safe against sliding, floatation, overturningand foundation bearing. The results of stability analysis are presented below while thedetailed calculation tables are attached in Annex 3-1:

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 26

    Copyright © Pöyry Energy Ltd.

    Table 3-9: Results of the Stability Analysis for the Surface Spillway

    Table 3-10: Results of the Stability Analysis for the Low Level Outlet

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 27

    Copyright © Pöyry Energy Ltd.

    3.9.8 ConclusionThe sliding safety factor, floatation safety factor, overturning in term of percent of basein compression and location of resultant, are greater than the requirement for all loadcases. The maximum base pressure is well below the allowable pressure for all loadcases.All the stability criteria are fulfilled.

    3.10 Structural Verification of the Spillway StructureThe structural resistance at ultimate limit state of the Spillway pier and Spillway Bridgehave been checked. The results are shown in Annex 3-2.

    3.10.1 Structural ModelThe horizontal deformation of the pillar during earthquake is a critical element whichwas investigated specifically in the structural analysis. In order to achieve acceptablepillar deformations perpendicular to the flow it is required to support the pillars of theSurface Spillway with the U/S Spillway Bridge and the D/S Spillway bridgerespectively.The Spillway structure is therefore consisting of two independent structural modelsoutlined below being separated by one deformation joint in the middle of the Spillwaybetween Surface Spillway bay S3 and S2:

    Right Spillway Model:Four Surface Spillway bays next to the Navigation Lock.

    Figure 3-15: Right Spillway model

    Left Spillway Model:Three low level outlet bays with one adjacent Surface Spillway bay on each side.For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 28

    Copyright © Pöyry Energy Ltd.

    Figure 3-16: Left Spillway model

    The bridge shall be fixed to each pillar forming a continuous beam which is leading to aframe-like structure perpendicular to flow direction subject to less deformation.

    3.10.2 ParametersThe parameters shown in the table below were applied for the structural analysis of theSpillway structure. The response modification factor (R-Factor) is depending on theseismic force-resisting system in the respective direction. The seismic force resistingsystem for the Spillway are as follows:

    · In Flow Direction: Ordinary Reinforced Concrete Shear Wall

    · Perpendicular to Flow: Ordinary Reinforced Concrete Moment Frame

    · Vertical Direction: Ordinary Reinforced Concrete Shear WallTable 3-11: FE model paramter

    Parameter Value

    Design modification factor (flow direction, perpendicular) 1.0

    Response Modification Coefficient (R-factor) in flow direction R = 4

    Response Modification Coefficient perpendicular to flow R = 3

    Response Modification Coefficient vertical R = 4

    3.10.3 TemperatureWith the upstream and downstream bridge being fixed to the Spillway pillars the entiresystem will be subjected to thermal movements perpendicular to flow direction. Athermal expansion and contraction equivalent to ±25°C has been considered in thestructural calculation.In case of thermal contraction the induced average tension stresses in the bridge arebelow the tensile strength of the concrete. The bending stresses induced in the pillar arenegligible.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 29

    Copyright © Pöyry Energy Ltd.

    3.10.4 Safety Evaluation Earthquake (SEE)The structural system described above has been investigated for the load casesconsidered critical. The governing load case for the Spillway pillars is the SEE loadcase with the ground motion accelerations defined in the Design Criteria.

    The SEE load case is investigated with a response spectra analysis (RSA). Since thefinite element program does not allow a direct input of the design spectra from theSeismic Hazard Analysis (SHA) the Eurocode Design Spectra was used to obtain asimilar design spectrum. The EC Design spectrum is defined by the followingparameters:

    Figure 3-17: EC design spectrum parameter

    The parameters used for the EC Spectra shown below were chosen as follows:Table 3-12: Parameters for the design response spectra used for the Spillway design

    Parameter of Design Response Spectra horizontal vertical

    Modal Damping D 0.05 0.05

    Rigid Acceleration SA 1 1

    Constant Acceleration SB 2.35 2.33

    Minimum Acceleration SMIN 0.1 0.05

    Time Value TB 0.08 0.05

    Time Value TC 0.2 0.15

    Time Value TD 4 4

    Cut-Off Time Value TE 0 0

    The figure below shows the response spectra for the SEE earthquake as defined in theSeismic Hazard Analysis (SHA) as well as the corresponding EC design spectrum usedfor the calculation.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 30

    Copyright © Pöyry Energy Ltd.

    Figure 3-18: SEE Design Spectra compared with response spectra defined in SHA

    The dynamic interaction between the water body in the reservoir and the Spillwaystructure is modelled by additional masses inserted in the structural model. Theadditional masses are calculated according to the Westergaard approach. The location ofadditional masses is indicated in the picture below as an example for the left Spillwaymodel.

    Figure 3-19: Masses considered for the earthquake design analysis

    3.10.5 ResultsThe dimensions of the main structural members are adequate. For the detailed results ofthe structural analysis of the Spillway structure please refer to the design report inAnnex 3.2.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 31

    Copyright © Pöyry Energy Ltd.

    4 NAVIGATION LOCK

    4.1 GeneralThe Luang Prabang Navigation Lock (NL) is located at the right abutment. It comprisestwo lock chambers with three mitre gates of which the middle mitre gate is the waterretaining gate when the lock is not in operation. The Navigation Lock can be dividedinto an upper lock from the reservoir till the middle mitre gate and a lower lock with thedownstream mitre gate. According to the MRC Guidance the Navigation Lock has to beoperated between a 30 years flood (Q=21’700 m3/s) and 95% flow duration of the riverin natural conditions (Q=1’100 m3/s).The maximum upstream water level is at elevation 312.50 m asl, equal to Design FullSupply Level (FSLD), and the minimum downstream water level (for navigation) is276.50 m asl. During impounding the Navigation Lock needs to be operational evenwhen the FSL is not reached; the minimum upstream water level for the operation of theNavigation Lock is 294.25 m asl (Lowest Operating Level, LOL).

    The filling of the chambers of the Navigation Lock is done via a gravity based feedingsystem from the headwater of the plant controlled by bonneted gates. The lockage timefor a two-step ship lock is expected to be shorter than the required 50 minutes.Due to its location along the right abutment, the Navigation Lock is also a backfillretaining structure for the platforms on the right abutment where also the upstream fishmigration upper channel with the intake / outlet structure is located.

    Figure 4-1: Layout of the Navigation Lock

    4.2 Structure LayoutThe Navigation Lock is a reinforced Conventional Vibrated Concrete (CVC) U-shapestructure founded on solid rock. All forces from the backfill at the right abutment andthe hydrostatic and hydro-dynamic forces are transmitted in the cantilevered walls of theU-shaped structure into the foundation.The upper lock consists of various independent blocks, divided by contraction joints.The block where the middle mitre gate is located is structurally connected to theSpillway (see chapter 3.2).

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 32

    Copyright © Pöyry Energy Ltd.

    Table 4-1: Upper lock blocks

    Block number Width xlengthfoundation

    Foundation

    Block 2 (u/s mitre gate) 35m x 70.8m Volcanic basalticandesite

    Block 3 35m x 77.4m Volcanic basalticandesite

    Block 4 (middle mitre gate) 35m x 80.8m Volcanic basalticandesite

    Main elevations

    Foundation 280.25 m asl

    Bottom of lock 289.25 m asl

    Top of lock 317.0 m asl

    Lock height (concrete) 36.75 m

    Width (wall / lock / wall) 12.0m / 12.0m / 11.0m

    4.3 Performance CriteriaThe Navigation Lock with the middle mitre gate is a safety relevant structure and mustresist the SEE earthquake without uncontrolled release of water.

    The upper lock structure is only partially safety relevant because it is not a waterretaining structure. But due to its proximity to the Spillway approach, the upper lockshall not fail in a way that it obstructs the safe lowering of the reservoir after a SEEearthquake. For this reason, the upper lock will be designed as well for the SEEearthquake, permitting larger permanent sliding displacements and the maximumdemand capacity ratio (DCR).

    4.4 FoundationThe resistance against sliding is determined for the LEPTS load cases considering thefriction angle and the cohesion, whereas for the USACE the cohesion has beenneglected, except for the SEE load case.Table 4-2: Shear strength parameters for sliding stability (Navigation Lock)

    Navigation Lock

    Rock type in contact zone

    c [MPa] φs [°]1 φd [°]2

    Volcanic – Basaltic Andesite 0.19 50 30*

    * assumption c=0 for τ(φd) residual, 1 σ1=700 kPa; 2 average value

    4.5 MaterialThe Navigation Lock consists of C25 Conventional Vibrated Concrete (CVC) withfc’=25 MPa. Other concrete classes are not considered for the basic design stabilityanalysis and reinforcement verification.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 33

    Copyright © Pöyry Energy Ltd.

    4.6 Design LoadsThe following loads have been considered for the structural design of the NavigationLock:

    · Dead Loads of the Concrete Structure

    · Hydrostatic Loads

    · Uplift

    · Lateral Earth Pressure

    · Earthquake Loads

    4.6.1 Dead LoadThe weight of the concrete is considered as indicated below for the stability analysis.For the structural verification, the weight is considered in the FE model.Water dead loads within the limits of the structural wedge depend on the load case(water level) and are not listed herein but considered in the calculations.Table 4-3: Dead load

    Concrete dead load Value

    Concrete area 867 m2

    Unit weight concrete (stability analysis) 24 kN/m3

    Unit weight concrete (structural verification) 25 kN/m3

    Equipment load (mitre gate, stoplog, etc.) Not considered

    4.6.2 Live LoadNot considered for the stability analysis.For the structural verification according to the Design Criteria report.

    4.6.3 Water LevelsThe following upstream water levels have been considered.Table 4-4: Design elevations for the reservoir water levels

    Upstream water level Value Type

    Design Full Supply Level (FSL) 312.00 m a.s.l. Normal

    Rapid reservoir drawdown 297.00 m a.s.l.

    PMF Level (Q=41’400 m3/s) 314.20 m a.s.l. Extreme

    The water level inside the Navigation Lock can either be at the FSL or at the minimumoperating level for the navigation in the reservoir which is at elevation 294.25 m asl.

    As indicated in chapter 4.9.2, the water level in the backfill depends on the tailracewater level. The tailrace water levels which have been considered for the stabilityanalysis are:

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 34

    Copyright © Pöyry Energy Ltd.

    Table 4-5: Tailrace water levels

    Tailrace water level Tailwater Level Type

    Minimum Operating Level (MOL, Q=745 m3/s) Not relevant

    Median Annual Discharge (Q=2’100 m3/s) Not relevant

    PMF level (Q=41’400 m3/s) 300.50 m a.s.l. Extreme

    4.6.4 Backfill LoadsBackfill loads are considered with K0 at rest soil pressure from the first berm onelevation 289.25 m asl till the top of the platform on elevation 317.0 m asl.

    Figure 4-2: Backfill at the Navigation Lock

    4.6.5 Seismic LoadThe following seismic loads have been considered:Table 4-6: Seismic loads

    Design Earthquake Return Period PGA [g]

    Horizontal Vertical

    SEE Safety Evaluation Earthquake --- (DSHA) 0.49 0.40

    OBE Operating Basis Earthquake 145 years 0.13 0.10

    4.7 Load CasesThe detailed load cases are defined in Annex 1. The below figures show some of theapplied load cases.

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 35

    Copyright © Pöyry Energy Ltd.

    Figure 4-3: LC A1.1 – Normal + low lock level

    Figure 4-4: LC B1.1 – Maintenance (lock empty)

    Figure 4-5: LC B2.1 – Drainage failure + low lock level

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 36

    Copyright © Pöyry Energy Ltd.

    Figure 4-6: LC B4 – Construction

    Figure 4-7: LC C1.1 – PMF

    Figure 4-8: LC C3 – Seismic load case (SEE)

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 37

    Copyright © Pöyry Energy Ltd.

    4.8 Design Method

    4.8.1 Stability AnalysisThe stability analysis calculation for the Navigation Lock has been carried out usingExcel, resulting in forces and safety factors for static and pseudo-static loadcombinations.Because the structure fulfils the stability requirements, no further calculations weredone.

    4.8.2 Structural VerificationFor the structural verification, a FE-model has been used. The governing SEE load casehas been calculated with a time-history analysis.

    4.9 Stability Analysis

    4.9.1 GeometryThe Navigation Lock block where the middle mitre gate is located is structurallyconnected to the Spillway. The loads acting in flow direction, including all loads duringan SEE earthquake are not critical due to relatively narrow width of the lock (12 m)compared to the width of the structure (35 m).

    Perpendicular to the flow, the upper lock has a similar shape from block with the uppermitre gate till block 4 with the middle mitre gate. Section D-D from block 3 isconsidered representative to prove the stability of the entire upper lock. Compared withother sections, the concrete mass is slightly reduced in the upper part of both walls. Forthe analysis, a width of 1.0 m has been considered.

    Figure 4-9: Analysis section of the upper lock chamber

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 38

    Copyright © Pöyry Energy Ltd.

    4.9.2 Calculation of Uplift PressureThere is no drainage gallery and no drainage holes foreseen along the Navigation Lock.Therefore no abrupt uplift pressure reduction has been assumed. The uplift is consideredlinear between the water level in the reservoir and the assumed water level in thebackfill (see chapter 4.9.3).

    4.9.3 Backfill Water LevelThe upper lock is founded on elevation 280.25 m asl and the first berm in theNavigation Lock excavation is assumed on elevation 289.25 m asl. It is assumed that theconcrete is poured directly against rock up to the first berm. On top of this first berm, alayer of free draining material that connects to the tailrace area is foreseen. As a result,the water level within the backfill is significantly lower than the reservoir water level.Following assumptions were made:

    · Elevation of first berm plus 13.0 m = 302.25

    · Tailwater level plus 5.0 m

    4.9.4 Results of the Stability AnalysisThe civil structures shall be designed to be safe against sliding, floatation, overturningand foundation bearing. The results of stability analysis are presented below:Table 4-7: Results of the Stability Analysis for the Navigation Lock

    4.9.5 ConclusionThe sliding safety factor, floatation safety factor, overturning in term of percent of baseon compression and location of resultant, are quite high and greater than requirement for

    For P

    NPCA

    only

  • Luang Prabang HPP – Basic Design Report 1150002924Structural Analysis Report 39

    Copyright © Pöyry Energy Ltd.

    all load cases. The maximum base pressure is well below the allowable pressure for allload cases.

    All the stability requirements are fulfilled.

    4.10 Structural Verification of the Navigation Lock Structure

    4.10.1 Structural ModelFor the finite element (FE) model, the same section as described in chapter 4.9.1, alsowith a width of 1.0 m has been taken into account. Calculations were done either staticor as a time-history analysis for the SEE load case. For the time-history analysis, noresponse modification factor (R-factors) and for the SEE load case, no importancefactors Ic are applied.

    As outlined in the Design Criteria, the modulus of subgrade at both borders of thestructure is twice the modulus of subgrade in the rest of the model.

    The three sets of time history accelerograms from the seismic hazard assessment areused in the dynamic calculations. For each set of time histories either 360° orientationor