basic assessment report - gibbprojects.gibb.co.za/portals/3/projects/201208 eskom tombo...

88
BASIC ASSESSMENT REPORT 1 (For official use only) File Reference Number: DEAT/EIA/0000521/2011 Application Number: 12/12/20/2421 Date Received: Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended. Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for. 2. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing. 3. Where applicable tick the boxes that are applicable in the report. 4. An incomplete report may be returned to the applicant for revision. 5. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations. 6. This report must be handed in at offices of the relevant competent authority as determined by each authority. 7. No faxed or e-mailed reports will be accepted. 8. The report must be compiled by an independent environmental assessment practitioner. 9. Unless protected by law, all information in the report will become public information on receipt by the competent authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process. 10. A competent authority may require that for specified types of activities in defined situations only parts of this report need to be completed.

Upload: phungthuy

Post on 29-Mar-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

1

(For official use only)

File Reference Number: DEAT/EIA/0000521/2011

Application Number: 12/12/20/2421

Date Received:

Basic assessment report in terms of the Environmental Impact Assessment Regulations, 2010, promulgated in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998), as amended. Kindly note that: 1. This basic assessment report is a standard report that may be required by a competent authority in terms of the EIA

Regulations, 2010 and is meant to streamline applications. Please make sure that it is the report used by the particular competent authority for the activity that is being applied for.

2. The report must be typed within the spaces provided in the form. The size of the spaces provided is not necessarily

indicative of the amount of information to be provided. The report is in the form of a table that can extend itself as each space is filled with typing.

3. Where applicable tick the boxes that are applicable in the report. 4. An incomplete report may be returned to the applicant for revision. 5. The use of “not applicable” in the report must be done with circumspection because if it is used in respect of material

information that is required by the competent authority for assessing the application, it may result in the rejection of the application as provided for in the regulations.

6. This report must be handed in at offices of the relevant competent authority as determined by each authority. 7. No faxed or e-mailed reports will be accepted. 8. The report must be compiled by an independent environmental assessment practitioner. 9. Unless protected by law, all information in the report will become public information on receipt by the competent

authority. Any interested and affected party should be provided with the information contained in this report on request, during any stage of the application process.

10. A competent authority may require that for specified types of activities in defined situations only parts of this report

need to be completed.

Page 2: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

2

SECTION A: ACTIVITY INFORMATION

Has a specialist been consulted to assist with the completion of this section?

YES NO ����

If YES, please complete the form entitled “Details of specialist and declaration of interest”

for appointment of a specialist for each specialist thus appointed: Any specialist reports must be contained in Appendix D. 1. ACTIVITY DESCRIPTION Describe the activity, which is being applied for, in detail1:

1 Please note that this description should not be a verbatim repetition of the listed activity as contained in the relevant Government Notice, but should be a brief description of activities to be undertaken as per the project description.

Page 3: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

3

1.1 GENERAL PROJECT DESCRIPTION The proposed project (Tombo-Mafini) entails the construction of approximately 16.5 km of Chickadee 132 kV power line on guyed steel monopole structures. The proposed power line takes off from the Dumasi-Zimbane 132 kV power line, approximately 2 km east of the village of Cibeni and extends to the proposed Tombo substation near the village of Tombo. The proposed Tombo-Mafini power line joins up with the previously authorised Dumasi-Tombo 132 kV powerline and follows the same lineation for approximately 2 km where it joins up to the Tombo substation. The Tombo substation and Dumasi-Tombo powerline formed part of an EIA undertaken in 2010, of which received Environmental Authorisation on the 20th of September, 2010 (authorisation register number 12/12/20/1493; attached in Annexure G). The new Tombo-Mafini 132 kV overhead power line is required to strengthen the electricity grid supply to the northern areas of the Port St Johns Local Municipality and the North-eastern areas of the Nyandeni Local Municipality within OR Tambo District Municipality, Eastern Cape. The proposed project will involve the construction of:

• 16.5 km of 132 kV overhead Chickadee power line

• 65 guyed steel monopole structures. The study area is predominantly located within the Port St Johns Local Municipality, with a small portion of the line (near the take-off point) falling within the Nyandeni Local Municipality. The study area fall outside the urban edge within either the River Valley Zone or High Lying Hinterland development zones, as identified in the Port St Johns Local Municipality Spatial Development Framework. Motivation to improve network:

• Provides capacity for existing and future developments in the area

• Improves reliability of supply

• Increased revenue

• De-loads existing substations which will help to maintain firmness within the study area.

The Spatial Development Framework of the Port St Johns Local Municipality identifies Tombo as having the potential to develop into the second largest nodal point within the municipal area. Tombo currently serves an important administrative node to the surrounding rural communities since it provides, amongst others, a post office, clinic, government offices, an art centre, community hall and training centre. The proposed Tombo-Mafini powerline would therefore assist in facilitating the objectives of the Port St John Local Municipality Spatial Development Framework.

Page 4: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

4

Need and Desirability of the Project The reliable provision of electricity by Eskom is critical for industrial development and related employment and sustainable development in South Africa. As electricity cannot be stored, power is generated and delivered over long distances at the very instant that it is required. In South Africa, thousands of kilometres of high voltage Transmission lines (i.e. 765 kV, 400 kV and 275 kV Transmission lines) transmit this power, which is predominantly generated at the power stations located outside the Eastern Cape Province, to Eskom’s major substations. At these major substations, the voltage is down-rated and distributed to smaller substations all over the country via distribution lines (e.g. 132 kV, 88 kV and 66 kV power lines). Here the voltage is down-rated further for distribution to industry, businesses, farms and homes. In order to maintain a reliable power supply within the entire network, the voltages at all substations are required to be within certain desired limits. If the network is operated at voltages which are below these limits, voltage collapse problems and power outages may be experienced which will in turn adversely impact on the economic growth potential of the area. Environmental Authorisation This report represents the Basic Assessment Report (BAR) and has been prepared in accordance with the EIA Regulations published in Government Notice No. R543. These regulations fall under Section 24(5) read with Section 44 of the National Environmental Management Act, 1998 (Act No. 107 of 1998 as amended in 2010) (NEMA).

The NEMA Section 24(5) stipulates that “listed activities” require environmental authorization by way of a Basic Assessment or full Environmental Impact Assessment. The Background Information Document initially only identified one listed activity as being relevant to this project, however further assessment has identified a number of additional activities of which are activated by the proposed development. The proposed activity is listed under Government Notice R544 and Government Notice R546, promulgated in terms of the National Environmental Management Act, Act 107 of 1998 (NEMA), amended in 2010, as:

ACTIVITY DESCRIPTION REASON

Listing Notice 1 Activity No. 10

The construction of facilities or infrastructure for the transmission and distribution of electricity – (i) outside urban areas or industrial complexes with a

capacity or more than 33 but less than 275 kilovolts; or

(ii) Inside urban areas or industrial complexes with a capacity of 275 kilovolts or more.

The construction of 16.5 km of 132 kV power line

Listing Notice 1 Activity No. 11

The construction of: (i) canals; (ii) channels; (iii) bridges; (iv) dams; (v) weirs; (vi) bulk storm water outlet structures; (vii) marinas;

The construction of 132 kV powerline within 32 metres of the Mngazi River.

Page 5: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

5

(viii) jetties exceeding 50 square metres in size; (ix) slipways exceeding 50 square metres in size; (x) buildings exceeding 50 square metres in size; or (xi) infrastructure or structures covering 50 square metres or

more where such construction occurs within a watercourse or within 32 metres of a watercourse, measured from the edge of a watercourse, excluding where such construction will occur behind the development setback line.

Listing Notice 1 Activity No. 22

The construction of a road, outside urban areas, (i) with a reserve wider than 13.5 metres or, (ii) where no reserve exists where the road is wider than 8

metres, or (iii) for which an environmental authorisation was obtained

for the route determination in terms of activity 5 in Government Notice 387 of 2006 or activity 18 in Notice 545 of 2010.

Possible construction of new access roads

Listing Notice 1 Activity No. 47

The widening of a road by more than 6 metres, or the lengthening of a road by more than 1 kilometre – (i) where the existing reserve is wider than 13.5 metres; or (ii) where no reserve exists, where the existing road is wider

than 8 metres- excluding widening or lengthening occurring inside urban areas.

Possible expansion of access roads

Listing Notice 3

Activity No. 4

The construction of a road wider than 4 metres with a reserve less than 13.5 metres (a) In Eastern Cape

ii. Outside urban areas, in: (ee) Critical biodiversity areas as identified in systematic biodiversity plans adopted by the competent authority or on bioregional plans

Possible construction of new access roads falling within a terrestrial CBA 1 and CBA 2 area

Listing Notice 3

Activity No. 12

The clearance of an area of 300 square metres or more of vegetation where 75% or more of the vegetative cover constitutes indigenous vegetation. (a) Within any critically endangered or endangered

ecosystem listed in terms of section 52 of the NEMBA or prior to the publication of such a list, within an area that has been identified as critically endangered in the National Spatial Biodiversity Assessment 2004;

(b) Within critical biodiversity areas identified in bioregional plans.

The proposed power line falls within both a terrestrial CBA 1 and CBA 2 area

Listing Notice 3

Activity No. 16

The construction of: (iv) Infrastructure covering 10 square metres or more

Where such construction occurs within 32 metres of a watercourse, measured from the edge of a watercourse excluding where such construction occur behind the development setback line.

(a) In Eastern Cape ii. Outside urban areas, in:

The construction of approximately 16.5 km of 132 kV power line within a terrestrial CBA 1 and CBA 2 area

Page 6: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

6

(aa) A protected area identified in terms of NEMPAA, excluding conservancies (ff) critical biodiversity areas or ecosystem service areas as identified in systematic biodiversity plans adopted by the competent authority or in bioregional plans (hh) Areas within 10 kilometres from national parks or world heritage sites or 5 kilometres from any other protected areas identified in terms of NEMPAA or from the core area of a biosphere reserve.

Listing Notice 3

Activity No. 19

The widening of a road by more than 4 metres, or the lengthening of a road by more than 1 kilometre

(b) In Eastern Cape iii. Outside urban areas, in:

(aa) A protected area identified in terms of NEMPAA, excluding conservancies (ee) critical biodiversity areas or ecosystem service areas as identified in systematic biodiversity plans adopted by the competent authority or in bioregional plans. (gg) Areas within 10 kilometres from national parks or world heritage sites or 5 kilometres from any other protected areas identified in terms of NEMPAA or from the core area of a biosphere reserve.

Possible widening of existing access roads falling within a terrestrial CBA 1 and CBA 2 area

Details of Proponent

Applicant: ESKOM: Distribution

Contact Person: Ms. Lusanda Maqaqa

Environmental Advisor

Address: Land Development Private Bag X 01 Beacon Bay 5205

Telephone Number: 043 703 2561 Fax Number: 043 703 2392 E-mail: [email protected]

Details of Environmental Assessment Practitioner

Name: Mr. Richard Judge Address: PO Box 19844 East London 5214 Telephone Number: 043 706 3638 Fax Number: 043 706 3647 E-mail: [email protected]

Page 7: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

7

Expertise of the EAP

Richard Judge (BSc honours) is an Environmental Consultant with four years experience. Richard specialises in Environmental Impact Assessments, including scoping studies, public participation and co-ordination of specialist studies as well as the compilation of Environmental Management Programmes, applications to the Department of Mineral Resources, Department of Water Affairs Water Use License Applications, environmental management planning, monitoring and control and geotechnical analysis including physical, structural, chemical and groundwater components.

1.2 DESCRIPTION OF PROPOSED ACTIVITY Location and site description of the proposed development The study area is located approximately 70 km to the southeast of Mthatha and falls within the Port St Johns Local Municipality and Nyandeni Local Municipality. The take-off point will be from the existing Dumasi-Zimbane 132 kV power line at a point within the Nyandeni Local Municipality. The new Tombo-Mafini 132 kV powerline will travel in a south-easterly direction where it links up with a previously authorised Dumasi-Tombo powerline where it travel for approximately 2 km to the Tombo substation, located adjacent to the road that feeds Mpande and is near the R61 road intersection some 20 km from Port St Johns on the R61 to Mthatha. The Dumasi-Tombo power line and Tombo substation formed part of an EIA undertaken in 2010, of which received Environmental Authorisation on the 20th of September, 2010 (authorisation register number 12/12/20/1493).

Table 1: GPS Co-ordinates for the Tombo-Mafini 132 kV powerline

Take-off p oint (Dumasi -Zimbane 132 kV power line) 31º 31’ 29.40”S 29º 17’ 3.41”E

Proposed Tombo substation 31º 37’ 56.59”S 29º 22’ 29.78”E

Page 8: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

8

Figure 1: Locality map indicating the location of t he preffered alternative (indicated with blue) and minor alternative (indicated with black). Construction Phase The actual construction activities associated with the power line follow: 1. Building of foundations for the towers 2. Tower assembly and erection 3. Conductor stringing 4. Final inspection of the line and taking over from contractor 5. Rehabilitation of disturbed areas. The foundations are constructed first, followed by the assembly of the towers on the ground, then the erection of the towers and finally the stringing and regulation of the conductors. a) Construction of ~16.5 km of 132 kV overhead line from the existing Zimbane-Dumasi

132 kV power line to the proposed Tombo substation

For proposed overhead power lines, an area with a strip width of 6 m will be cleared along the entire route. Holes will then be drilled for each supporting pole or blasting may be employed. Small amounts of concrete will be mixed for the site stabilizing towers (~ 0.5 cubes per strain tower / 1 every 1.5 km). The internal towers will generally be placed on pre-cast foundations (~ 0.5 x 0.5 x 0.5 m). b) Construction of access roads Minor vehicle access roads may be created during the construction phase where these are not already available.

Minor Alternative

Preferred Alternative

Take-off point

Tombo Substation

Portion of the Tombo-Mafini 132 kV power line that follows the

previously authorized Dumasi-Tombo 132 kV power line lineation

Page 9: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

9

Earthmoving equipment may be required to establish access roads. All areas that will be disturbed such as construction camps, access roads and the construction area around the towers will have the topsoil stripped and stockpiled for use during the rehabilitation phase. Eskom estimates that it takes approximately 1 month for every 12 km. The construction for this project should thus be completed after approximately 2 months.

Operational Phase: 1. Maintenance of Infrastructure The 132 kV power line will require routine maintenance work using access roads. Existing roads will be used as far as possible to avoid constructing new roads. 2. Corrosion Corrosion of structures is frequently found where the protective system, either galvanizing or a protective organic coating, has weathered, exposing the steel substrate. With routine maintenance, this form of corrosion can be avoided. 1.3 SURROUNDING LAND USE The land use of the areas of which the proposed power line transverse is restricted largely to rural villages and subsistence farming including low intensity subsistence livestock grazing and food plots. The area consists mainly of un-alienated state-owned land under the jurisdiction of the Department of Land Affairs. Land tenure is primarily communal, with chiefs and headmen responsible for the allocation of land-use rights. The Majola Tea Estate, one of the largest tea plantations in South Africa, can be found approximately 3.5 km to the east of the new power line take-off point. Majola is an interesting example of agricultural black empowerment in as much that its workers own the estate. 1.4 DESCRIPTION OF THE ENVIRONMENT Local Economy Port St Johns is a small coastal town in South Africa that owes most of its revenue to tourism. It is the hub of the Eastern Cape. The economy is largely subsistence-based. Most families live off social grants and pensions, as job-seekers tend to leave the rural areas and migrate to the larger cities such as Durban, East London and Johannesburg where there are more employment opportunities. Port St Johns offers a unique blend of cultural richness, as the Xhosa culture; both modern and traditional is always present. Many of the local population rely on tourism as an opportunity to make an income, selling curios and other memorabilia, as well as providing tours and other initiatives to offer tourists a taste of local culture. Port St Johns also provides an overnight rest place for those travelling through the area, a place where businessmen can stay when working in the area, as well as a beautiful holiday destination. The Port St Johns area lays claim to the Majola Tea Estate, which is a 450 ha tea plantation, situated on the rolling hills of Port St Johns and owned by its workers. The tea plantation provides the people of

Page 10: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

10

this area a means of generating an income by means of international trade.

Demographics Statistics from the 2001 Census indicate that the Port St Johns Local Municipality, in which the study area lies, has a total population of 146 967. The number of households is said to be in the order of 28 869 and is divided into 13 Wards. Port St Johns Municipality constitutes approximately 8.7% of the total population of O.R. Tambo District Municipality (ORTDM). Households contain average family sizes of six people. The majority of the population are below 30 years old and, due to the migrant labour system, women head the majority of households. Unemployment levels are high. The lack of energy resources within rural areas of South Africa is recognised as a major factor retarding socio-economic development. According to StatsSA Census 2001, less than half of the population in the Eastern Cape have electricity for lighting purposes, while 28% and 24% of the Eastern Cape population utilise electricity for cooking and heating respectively. It is made evident from the above information that network strengthening in terms of electricity distribution in the Eastern Cape is greatly needed. Climate The Port St Johns area is characterised by a sub-tropical climate with rainfall occurring mainly in the summer months. The area has a comparatively high rainfall, with the coastal and mountain regions receiving over 1000 mm per annum. Rainfall occurs all year round with summer peaks (October to April). In the winter months, snow has been known to occur in the high altitude regions. Extreme wind events have been recorded in Transkei, and could impact negatively on power lines. Geology and Soils Sandstones of the Beaufort Group of the Karoo Supergroup dominate the area of Port St Johns. The northern coastal region is located on the Horst of the Table Mountain Group around which sediments of the younger Ecca Group are deposited. The area is characterised by fairly resistant sandstones, which form the prominent topography. The coastline of Port St Johns comprises mostly of Ecca and Dwyka sediments with many intrusions therein. The route of the proposed 132kV powerline is underlain by Ecca Group sandstones and mudstones, dolerite intrusions and recent alluvium. According to the Palaeontological Impact Assessment undertaken by Rob Gess Consulting, the Ecca Group strata are potentially palaeontological sensitive. The Ecca Group sediments transverse by the powerline include corse and finer grained sediments, both of which contained only fragmented plant material. The palaeontologist has therefore indicated that it would e extremely unlikely that significant palaeotological material will be disturbed during the development of the proposed powerlines. Soils are generally highly erodible and, with the poor veld management and mismanagement of riparian areas, erosion dongas and gullies may develop. Heritage This section is dealt with in more detail in section 6 of this report. In conclusion the Cultural Heritage Specialists have recommended that the development proceed with the following heritage mitigation:

−−−− That tower placements should be negotiated with residents to ensure that no ancestral graves

are affected.

Page 11: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

11

−−−− Any observed archaeological remains should be reported as per SAHRA protocol.

Vegetation Three main vegetation types, namely the Ngongoni Veld, Eastern Valley Bushveld and the Southern Mistbelt Forest, dominate the study area and all three are classified as being Least Threatened or Vulnerable. The Eastern Valley Bushveld characterises the flanks of most rivers, where Acacias and Euphorbias dominate. The Ngongoni Veld borders the coastal strip. The Eastern Valley Bushveld is dominated by species such as: Coastal Buffalo grass (Stenotaphrum secundatum), Ngongoni or Wire grass (Aristida junciformis), and Giant Turpentine grass (Cymbopogon validis), Bitter Aloe (Aloe ferox), Sweet Thorn (Acacia karoo), and the common Umzimbeet (Millettia grandis). Most of the forests in the study area are demarcated as “State Forests” and are protected for the benefit of the local inhabitants. Typical trees of the forest biome include Giant Umzimbeet (Millettia sutherlandii), Forest Mahogany (Trichilia dregeana), Forest Ironplum (Drypetes gerrandii), Forest Fever Berry (Croton sylvaticus), Forest Bushwillow (Combretum krausii), and Small-leaved Jackal-berry (Disopyros natalensis). Rare and threatened trees found in the forests are Transvaal Stinkwood (Ocotea kenyensis), Forest Potato Bush (Phyllanthus macnaughtonii), and Forest Canary-berry (Suregada procera) (www.portstjohns.org.za). The proposed power line falls within both a terrestrial CBA 1 and CBA 2 area (refer to Figure 2). The construction of the power line will require mitigation measures to ensure the impact on vegetation is kept at a minimum.

Figure 2: Terrestrial CBA areas The proposed power line falls within an aquatic CBA 1 area. Construction within the aquatic environments, such as within river valleys must be undertaken such that the impacts on these areas are kept to a minimum.

Take-off point

Preferred Alternative

Minor Alternative

Tombo Substation

Page 12: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

12

Figure 3: Terrestrial CBA areas Current Landuse The current land-use includes mostly subsistence farming, including low intensity subsistence livestock grazing and maize food plots. FEASIBLE AND REASONABLE ALTERNATIVES “alternatives”, in relation to a proposed activity, means different means of meeting the general purpose and requirements of the activity, which may include alternatives to— (a) the property on which or location where it is proposed to undertake the activity;

Preferred Alternative

Minor Alternative

Tombo Substation

Take-off point

Page 13: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

13

The study area is located approximately 70 km to the southeast of Mthatha and falls within the Port St Johns Local Municipality and Nyandeni Local Municipality. Two route alignment options are being considered, a preferred route and a minor deviated route. Both options take off from the existing Dumasi-Zimbane 132 kV power line at a point within the Nyandeni Local Municipality. The preferred option, indicated in blue in Figures 2 and 3, will travel in a south-easterly direction over the Mngazi River where it links up with the previously authorised Dumasi-Tombo 132 kV power line and follows the same lineation for approximately 2 km where it links up with the Tombo substation, located adjacent to the road that feeds Mpande and is near the R61 road intersection some 20 km from Port St Johns on the R61 to Mthatha. The minor alternative, indicated in black in Figures 2 and 3, follows the same route as the preferred alternative but deviates in an easterly direction approximately 1.1 km north of the Mngazi River. The minor alternative travels for approximately 3.5 km where it crosses the Mngazi River and again joins the preferred alternative route. In both cases the surrounding vegetation have been heavily impacts from surrounding agricultural activities including extensive overgrazing. The proposed works all fall within un-alienated state land. Wayleave are entered into between ESKOM and the relevant tribal authority regarding access to land for servitudes. The department of Land Affairs compensates communities financially where relevant. The Department of Land Affairs (DLA), through a community resolution process will undertake the site transfer process, should an Environmental Authorisation (EA) be issued. The community leaders have signed a letter of no objection to the project proposal (Refer to Appendix G) (b) the type of activity to be undertaken;

ESKOM are proposing to construct approximately 16.5km of new 132kV overhead powerline (Tombo-Mafini) taking off from the existing Dumasi-Zimbane 132kV powerline to the Tombo substation.

(c) the design or layout of the activity;

Pylo n Alternatives No. Alternative type , either

alternative: site on property, properties, activity, design,

technology, operational or other (provide details of “other”)

Description

1. Technology Alternative (Monopole structure)

• Monopoles are single structures used to minimize impact on land use, wildlife and scenic views.

• The multitude of elbows and joints of lattice structures make ideal raptor perches which, in tandem with wide, clear-cut rights-of-way, create measurable negative impacts on wildlife.

• Some monopoles are single, self-supporting, vertical poles with no guy wire anchors. They can be as tall as lattice towers, but their single stem makes them less obtrusive, and they require only an eight-foot base.

• Monopoles offer aesthetic benefits and definitely require a smaller servitude for adequate placement. The monopole designs include rounded edges, which eliminates raptor perches and protects them

Page 14: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

14

from accidental electrocution.

In terms of design, various support towers or “pylons” were considered. These included a 5-pole wooden tower, concrete monopole tower or a steel monopole tower. The 5-pole wooden tower is no longer considered feasible due to the excessive maintenance requirements where poles require regular replacement. The two feasible alternatives are therefore concrete monopole towers or steel monopole towers with guides.

Figure 5: Alternative Towers to be considered (Concrete Monopole (left) and a Steel Monopole with Guides (Right).

2. Technology Alternative (Lattice structure)

• Lattice structures mostly four-legged structures.

• Lattice structures require guy wire anchors for support. They are also tall and obtrusive.

• The pylon design will be in accordance with the OHS Act which stipulates the clearance levels to ground, road, building etc., and also by taking into account the local area in terms of birds and animals.

(d) the technology to be used in the activity;

Monopole and lattice structures have been considered. However due to the maintenance requirements, negative impacts on wildlife, vegetation clearing requirements and visual impacts associated with lattice structures, monopole structures are preferred. Due to the high weights associated with the concrete monopole structures, it is likely that steel monopoles will be utilised for the proposed powerline construction.

(e) the operational aspects of the activity; and

There are no feasible or reasonable alternatives.

Page 15: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

15

(f) the option of not implementing the activity.

No-Go Alternative Due to the planned growth in the Port St Johns area an upgrade of the existing ESKOM distribution infrastructure is required. The new 132kV overhead powerline is therefore required to strengthen the grid supply in the Eastern Cape in response to planned growth. In terms of providing stable electricity supply in the Port St Johns area, the no-go alternative is not a practical or feasible project alternative. By not increasing the supply to the greater area, development will be constrained as the existing networks are at capacity. New electricity connections will not be viable and households will continue using alternative sources of energy for cooking, heating and lighting. These sources are mostly from non-renewable sources of electricity such as paraffin, gas, candles and fire-wood. Such forms of energy deplete fertile sources of fossil fuels. In addition, many are considered unsafe (e.g. paraffin and wood fires) and create safety risks to communities. Economic benefits related to the development, include job opportunities during construction and operation, contribution to infrastructure and development of the area. The no-go alternative will therefore have a direct impact on the provision of electricity and development in the area. The No-Go alternative may prevent the occurrence of negative environmental impacts such as construction associated risks (fires, spills of hazardous materials), impacts on ground and surface water quality with particular respect to Mngazi River; impacts on air quality and noise generation during construction; potential soil erosion from earthworks. Describe alternatives that are considered in this application. Alternatives should include a consideration of all possible means by which the purpose and need of the proposed activity could be accomplished in the specific instance taking account of the interest of the applicant in the activity. The no-go alternative must in all cases be included in the assessment phase as the baseline against which the impacts of the other alternatives are assessed. The determination of whether site or activity (including different processes etc.) or both is appropriate needs to be informed by the specific circumstances of the activity and its environment. After receipt of this report the competent authority may also request the applicant to assess additional alternatives that could possibly accomplish the purpose and need of the proposed activity if it is clear that realistic alternatives have not been considered to a reasonable extent. Paragraphs 3 – 13 below should be completed for each alternative.

Page 16: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

16

3. ACTIVITY POSITION Indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection. List alternative sites, if applicable. Alternative:

Latitude (S):

Longitude (E):

Alternative S12 (preferred or only site alternative)

o ‘ o ‘

Alternative S2 (if any) o ‘ o ‘

Alternative S3 (if any) o ‘ o ‘

In the case of linear activities: Alternative: Latitude (S): Longitude (E): Alternative S1 (preferred route alternative)

• Starting point of the activity 31o 31.491‘ 29o 17.102‘

• Middle/Additional point of the activity 31o 34.802‘ 29o 19.901‘

• End point of the activity 31o 37.946‘ 29o 22.503‘

Alternative S2 (Minor Alternative)

• Starting point of the activity 31o 33.366‘ 29o 18.364‘

• Middle/Additional point of the activity 31o 33.913‘ 29o 19.258‘

• End point of the activity 31o 34.712‘ 29o 19.764‘

Alternative S3 (if any)

• Starting point of the activity o ‘ o ‘

• Middle/Additional point of the activity o ‘ o ‘

• End point of the activity o ‘ o ‘

For route alternatives that are longer than 500 m, please provide an addendum with co-ordinates taken every 250 meters along the route for each alternative alignment – Please refer to Appendix G. 4. PHYSICAL SIZE OF THE ACTIVITY Indicate the physical size of the preferred activity/technology as well as alternative activities/technologies (footprints): Alternative: Size of the activity:

Alternative A13 (preferred activity alternative) m2

Alternative A2 (if any) m2

Alternative A3 (if any) m2

or, for linear activities:

2 “Alternative S..” refer to site alternatives. 3 “Alternative A..” refer to activity, process, technology or other alternatives.

Page 17: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

17

Alternative:

Length of the activity:

Alternative A1 (preferred activity alternative) 1650 m

Alternative A2 (if any) 3530 m

Alternative A3 (if any) m

Indicate the size of the alternative sites or servitudes (within which the above footprints will occur): Alternative:

Size of the site/servitude:

Alternative A1 (preferred activity alternative) m2

Alternative A2 (if any) m2

Alternative A3 (if any) m2

5. SITE ACCESS

Does ready access to the site exist? � YES NO

If NO, what is the distance over which a new access road will be built m

Describe the type of access road planned:

Existing access roads will be utilised where possible and all new access roads to the powerlines will be built according to the Eskom requirements and approved management plans for this project. Access tracks will be limited to single tracks as close to the servitude as possible or within the servitude.

Include the position of the access road on the site plan and required map, as well as an indication of the road in relation to the site. 6. SITE OR ROUTE PLAN

A detailed site or route plan(s) must be prepared for each alternative site or alternative activity. It must be attached as Appendix A to this document. The site or route plans must indicate the following: 6.1 the scale of the plan which must be at least a scale of 1:500; 6.2 the property boundaries and numbers of all the properties within 50 metres of the site; 6.3 the current land use as well as the land use zoning of each of the properties adjoining the site or

sites; 6.4 the exact position of each element of the application as well as any other structures on the site; 6.5 the position of services, including electricity supply cables (indicate above or underground), water

supply pipelines, boreholes, street lights, sewage pipelines, storm water infrastructure and telecommunication infrastructure;

6.6 all trees and shrubs taller than 1.8 metres; 6.7 walls and fencing including details of the height and construction material; 6.8 servitudes indicating the purpose of the servitude; 6.9 sensitive environmental elements within 100 metres of the site or sites including (but not limited

to): � rivers;

Page 18: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

18

� the 1:100 year flood line (where available or where it is required by DWA); � ridges; � cultural and historical features; � areas with indigenous vegetation (even if it is degraded or infested with alien species);

6.10 for gentle slopes, the 1 metre contour intervals must be indicated on the plan and whenever the slope of the site exceeds 1:10, the 500 mm contours must be indicated on the plan; and

6.11 the positions from where photographs of the site were taken. 7. SITE PHOTOGRAPHS Colour photographs from the centre of the site must be taken in at least the eight major compass directions with a description of each photograph. Photographs must be attached under Appendix B to this form. It must be supplemented with additional photographs of relevant features on the site, if applicable. 8. FACILITY ILLUSTRATION A detailed illustration of the activity must be provided at a scale of 1:200 as Appendix C for activities that include structures. The illustrations must be to scale and must represent a realistic image of the planned activity. The illustration must give a representative view of the activity. 9. ACTIVITY MOTIVATION 9(a) Socio-economic value of the activity

What is the expected capital value of the activity on completion? Unknown

What is the expected yearly income that will be generated by or as a result of the activity?

Not yet known – reliant on demand and growth.

Will the activity contribute to service infrastructure? ���� YES NO

Is the activity a public amenity? ���� YES NO

How many new employment opportunities will be created in the development phase of the activity?

Due to the expertise required, an Eskom contractor and his permanent staff will do the work. Casual labourers from the local communities will be employed where there is a need.

What is the expected value of the employment opportunities during the development phase?

It is not yet known

Page 19: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

19

What percentage of this will accrue to previously disadvantaged individuals? It is not yet known – Eskom is a state owned entity

How many permanent new employment opportunities will be created during the operational phase of the activity?

It is not yet known

What is the expected current value of the employment opportunities during the first 10 years?

It is not yet known – Eskom is a state owned entity

What percentage of this will accrue to previously disadvantaged individuals? It is not yet known – Eskom is a state owned entity

9(b) Need and desirability of the activity Motivate and explain the need and desirability of the activity (including demand for the activity):

NEED:

1. Was the relevant provincial planning department involved in the application?

YES ���� NO

2. Does the proposed land use fall within the relevant provincial planning framework?

YES ���� NO

3. If the answer to questions 1 and/or 2 was NO, please provide further motivation / explanation:

Stakeholders will be consulted during the Public Participation Process where they will provide comments with regards to this project. Certain stakeholders were identified based on their potential interest in the project. These organisations were contacted directly for comment and were sent a Letter of Notification and a Background Information Document – BID (refer to Section 6.1.3 below).

DESIRABILITY:

1. Does the proposed land use / development fit the surrounding area? ���� YES NO

2. Does the proposed land use / development conform to the relevant structure plans, SDF and planning visions for the area?

���� YES NO

3. Will the benefits of the proposed land use / development outweigh the negative impacts of it?

���� YES NO

4. If the answer to any of the questions 1-3 was NO, please provide further motivation / explanation:

N/A

5. Will the proposed land use / development impact on the sense of place? ����YES NO

6. Will the proposed land use / development set a precedent? YES ���� NO

7. Will any person’s rights be affected by the proposed land use / development?

YES ���� NO

8. Will the proposed land use / development compromise the “urban edge”? YES ���� NO

Page 20: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

20

9. If the answer to any of the question 5-8 was YES, please provide further motivation / explanation.

N/A

BENEFITS:

1. Will the land use / development have any benefits for society in general? ���� YES NO

2. Explain:

The proposed construction of the powerline will provide additional electricity supply within the country and will therefore provide capacity for future load growth, acceptable voltage levels and quality supply to the project area.

3. Will the land use / development have any benefits for the local communities where it will be located?

���� YES NO

4. Explain:

The increased electrification capacity will allow for more households to become electrified and hence will reduce their requirement on local fossil fuels as an energy source. Many houses in the study area currently rely on fossil fuels as an energy source e.g. candles, paraffin, gas. The provision of electricity will promote local economic development and investment in the area through the provision of undisturbed electricity to local communities. Economic benefits related to the development, include job opportunities during construction and operation, contribution to infrastructure and development of the area.

10. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES List all legislation, policies and/or guidelines of any sphere of government that are applicable to the application as contemplated in the EIA regulations, if applicable:

Title of legislation, policy or guideline:

Administering authority:

Date:

National Environmental Management Act (NEMA) No. 107 0f 1998 (as amended)

DEA 1998

Environmental Impact Assessment Regulations (Government Notice No. R. 543 and 544)

DEA 2009

Constitution of the Republic of South Africa Act No. 108 of 1996

South African Government

1996

The Environment Conservation Act (ECA) No. 73 of 1989

DEA 1989

National Heritage Resources Act (NHRA) No. 25 of 1999

SAHRA 1999

Occupational Health and Safety Act (OHSA) No. 85 of 1993

Department of Labour 1993

National Water Act (NWA) No. 36 of 1998 DWAF 1998

Conservation of Agricultural Resources Act (43 of DoA 1983

Page 21: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

21

1983)

National Environmental Management: Air Quality Act 39 of 2004

Local February 2005

National Environmental Management: Biodiversity Act 10 of 2004

Provincial & National June 2004

National Environmental Management: Waste Act 59 of 2008

Provincial & National April 2009

Hazardous Substances Act 15 of 1973

Provincial & National March 1973

Noise Control Regulation PN 627 of 1998

Provincial & National November 1998

SANS 10103: The measurement and rating of Environmental noise with respect to annoyance and to speech communication

South African Bureau of Standards (SABS)

2008

National Health Act 61 of 2003

Provincial & National May 2005

Electricity Regulations Act (4 of 2006)

Provincial & National 2006

Eastern Cape Biodiversity Conservation Plan

Provincial

National Forest Act (NFAA) No. 84 of 1998 DWAF 1998

11. WASTE, EFFLUENT, EMISSION AND NOISE MANAGEMENT 11(a) Solid waste management

Will the activity produce solid construction waste during the construction/initiation phase?

���� YES NO

If yes, what estimated quantity will be produced per month? Unknown

How will the construction solid waste be disposed of (describe)?

Waste that will be produced on site include plastic bags and other domestic waste that the contractors may bring on site. This waste should be collected weekly and disposed of in a safe manner at the landfill utilised by the Local Municipality.- The management of this waste is to be addressed in the Environmental Management Programme (EMP).

Where will the construction solid waste be disposed of (describe)?

Construction solid waste and general waste produced during construction will be disposed at a landfill as utilised by the Local Municipality.

Will the activity produce solid waste during its operational phase? YES ���� NO

If yes, what estimated quantity will be produced per month? N/A

How will the solid waste be disposed of (describe)?

N/A

Where will the solid waste be disposed if it does not feed into a municipal waste stream (describe)?

N/A

Page 22: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

22

If the solid waste (construction or operational phases) will not be disposed of in a registered landfill site or be taken up in a municipal waste stream, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

Can any part of the solid waste be classified as hazardous in terms of the relevant legislation?

YES ���� NO

If yes, inform the competent authority and request a change to an application for scoping and EIA.

Is the activity that is being applied for a solid waste handling or treatment facility?

YES ���� NO

If yes, then the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA. 11(b) Liquid effluent

Will the activity produce effluent, other than normal sewage, that will be disposed of in a municipal sewage system?

YES ���� NO

If yes, what estimated quantity will be produced per month? N/A

Will the activity produce any effluent that will be treated and/or disposed of on site?

Yes ���� NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

Will the activity produce effluent that will be treated and/or disposed of at another facility?

YES ���� NO

If yes, provide the particulars of the facility:

Facility name:

Contact person:

Postal address:

Postal code:

Telephone: Cell:

E-mail: Fax:

Describe the measures that will be taken to ensure the optimal reuse or recycling of waste water, if any:

Although no effluent will be disposed on site, adequate measures have to be put in place to ensure that construction workers use portable toilets supplied by contractor. The open veld may not be used for ablutions. The EMP must address the management of this issue.

11(c) Emissions into the Atmosphere

Will the activity release emissions into the atmosphere? YES ���� NO

If yes, is it controlled by any legislation of any sphere of government? YES NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

If no, describe the emissions in terms of type and concentration:

Page 23: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

23

During the construction phase, it is expected that there will be short-term dust generation and emissions from vehicles and machinery. However, the dust and emissions will have a medium- to short-term duration and have a limited impact on the very immediate surrounding rural areas. Where appropriate, dust suppression measures will be implemented to reduce the impacts. It is recommended that construction vehicles be serviced and kept in good mechanical condition to minimise possible exhaust emission.

11(d) Generation of Noise

Will the activity generate noise? ���� YES NO

If yes, is it controlled by any legislation of any sphere of government? YES ���� NO

If yes, the applicant should consult with the competent authority to determine whether it is necessary to change to an application for scoping and EIA.

If no, describe the noise in terms of type and level:

Noise control regulations and SANS 10103 Short term noise impacts are anticipated during the construction phase of the project caused by construction vehicles and drilling machines. It is, however, anticipated that the noise will be localised and contained within the construction site. In order to minimise the impacts of noise during the construction phase, construction activities should be restricted to between 07H00 and 17H00, Monday to Friday, and 08H00 - 13H00 on Saturdays. This is required to avoid noise disturbances outside normal working hours. All construction equipment must be maintained and kept in good working order to minimise associated noise impacts. The noise level is anticipated to be less than 50dBA as required by SANS 10103 and thus authorisation will not be required for the noise. 12. WATER USE Please indicate the source(s) of water that will be used for the activity by ticking the appropriate box(es)

municipal water board groundwater river, stream, dam or lake

���� Other - water tanker

the activity will not use water

If water is to be extracted from groundwater, river, stream, dam, lake or any other natural feature, please indicate

the volume that will be extracted per month: N/A

Does the activity require a water use permit from the Department of Water Affairs?

YES ���� NO

If yes, please submit the necessary application to the Department of Water Affairs and attach proof thereof to this application if it has been submitted. 13. ENERGY EFFICIENCY Describe the design measures, if any, that have been taken to ensure that the activity is energy efficient:

Page 24: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

24

N/A as the project entails the construction of powerlines for the distribution of electricity. However, the contractor will be advised to transport all construction materials on site at the same time where possible and the collection of waste material conducted simultaneous with other activities to reduce the amount fuel usage for such transportation.

Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any:

N/A as the project entails the construction of powerlines for the distribution of electricity. Diesel fuel will be used on site instead of electricity.

SECTION B: SITE / AREA / PROPERTY DESCRIPTION Important notes:

1. For linear activities (pipelines etc.) as well as activities that cover very large sites, it may be necessary to complete this section for each part of the site that has a significantly different environment. In such cases please complete copies of Section C and indicate the area, which is covered by each copy No. on the Site Plan.

Section C Copy No. (e.g. A):

A

2. Paragraphs 1 - 6 below must be completed for each alternative.

3. Has a specialist been consulted to assist with the completion of this section?

YES ���� NO

If YES, please complete the form entitled “Details of specialist and declaration of interest”

for each specialist thus appointed: All specialist reports must be contained in Appendix D. Property description/physical address:

The take-off point is from the existing Dumasi-Vuyani 132kV powerline situated between the villages of Cibeni and Rawutini. The powerline will run in a south easterly direction over the Mngazi River (31º 33,89’ S; 29º 18.79’ E) and the R61 at (31º 37.44’ S; 29 22.08’ E) between the villages of Lugaqweni and KwaRela to the proposed Tombo substation located adjacent to the Mpande access road. The proposed works all fall within un-alienated state land or communal land. Wayleaves are entered into between ESKOM and the relevant tribal authority regarding access to land for servitudes. The department of Land Affairs compensates communities financially where relevant. The Department of Land Affairs (DLA), through a community resolution process will undertake the site transfer process, should an Environmental Authorisation (EA) be issued. The community leaders have signed a letter of no objection to the project proposal. The properties on which the powerline extend are classified as: RE/35, RE/36, RE/38; RE/39; RE/40.

(Farm name, portion etc.) Where a large number of properties are involved (e.g. linear activities), please attach a full list to this application.

In instances where there is more than one town or district involved, please attach a list of towns or districts to this application.

Page 25: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

25

Current land-use zoning: Un-alienated state owned land or communal land

In instances where there is more than one current land-use zoning, please attach a list of current land use zonings that also indicates which portions each use pertains to, to this application.

Is a change of land-use or a consent use application required? YES ���� NO Must a building plan be submitted to the local authority?

YES ���� NO

Locality Map: An A3 locality map must be attached to the back of this document, as Appendix A. The scale of the locality map must be relevant to the size of the development (at least 1:50 000. For linear activities of more than 25 kilometres, a smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map. The map must indicate the following:

• an indication of the project site position as well as the positions of the alternative sites, if any;

• road access from all major roads in the area;

• road names or numbers of all major roads as well as the roads that provide access to the site(s);

• all roads within a 1 km radius of the site or alternative sites;

• a north arrow;

• a legend; and

• locality GPS co-ordinates (indicate the position of the activity using the latitude and longitude of the centre point of the site for each alternative site). The co-ordinates should be in degrees and decimal minutes. The minutes should have at least three decimals to ensure adequate accuracy. The projection that must be used in all cases is the WGS84 spheroid in a national or local projection.

1. GRADIENT OF THE SITE Indicate the general gradient of the site. Alternative S1:

Flat 1:50 – 1:20

1:20 – 1:15 1:15 – 1:10 ����

1:10 – 1:7,5 1:7,5 – 1:5

Steeper than 1:5

Alternative S2 (if any): Minor Alternative

Flat 1:50 – 1:20

1:20 – 1:15 1:15 – 1:10 ����

1:10 – 1:7.5 1:7.5 – 1:5

Steeper than 1:5

2. LOCATION IN LANDSCAPE Indicate the landform(s) that best describes the site: 2.1 Ridgeline 2.2 Plateau 2.3 Side slope of hill / mountain ���� 2.4 Closed valley 2.5 Open valley ���� 2.6 Plain 2.7 Undulating plain / low hills ���� 2.8 Dune 2.9 Seafront

Page 26: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

26

3. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE Is the site(s) located on any of the following (tick the appropriate boxes)? Alternative S1: Alternative S2:

Minor Alt. Alternative S3 (if any): N/A

Shallow water table (less than 1.5 m deep)

YES NO ����

YES NO ����

YES NO

Dolomite, sinkhole or doline areas

YES NO ����

YES NO ����

YES NO

Seasonally wet soils (often close to water bodies)

YES NO ����

YES NO ����

YES NO

Unstable rocky slopes or steep slopes with loose soil

YES NO ����

YES NO ����

YES NO

Dispersive soils (soils that dissolve in water)

YES ����

NO YES ����

NO YES NO

Soils with high clay content (clay fraction more than 40%)

YES NO ����

YES NO ����

YES NO

Any other unstable soil or geological feature

YES NO ����

YES NO ����

YES NO

An area sensitive to erosion

YES ����

NO

YES ����

NO

YES NO

If you are unsure about any of the above or if you are concerned that any of the above aspects may be an issue of concern in the application, an appropriate specialist should be appointed to assist in the completion of this section. (Information in respect of the above will often be available as part of the project information or at the planning sections of local authorities. Where it exists, the 1:50 000 scale Regional Geotechnical Maps prepared by the Council for Geo Science may also be consulted). 4. GROUNDCOVER Indicate the types of groundcover present on the site: The location of all identified rare or endangered species or other elements should be accurately indicated on the site plan(s).

Natural veld - good conditionE

����

Natural veld with scattered aliensE

Natural veld with heavy alien infestationE

Veld dominated by alien speciesE

Gardens

Sport field Cultivated land ����

Paved surface Building or other structure

Bare soil

Page 27: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

27

Much of the pristine indigenous vegetation has been transformed by agriculture (i.e. cultivated lands) and settlements in the vicinity of the project and thus the human impact levels on natural vegetation have been very high. Open grasslands that are grazed with domestic stock have been poorly managed in terms of high stocking density and the application of poor burning regimes. This has caused many of the highly palatable grass species (e.g. Themeda triandra) to become replaced with less desirable/ unpalatable grasses (e.g. Aristida sp). Remaining intact patches of indigenous vegetation are therefore of high conservation value as they provide habitat and refuge for the remaining indigenous fauna species in the study area. Three main vegetation types, namely the Ngongoni Veld, Eastern Valley Bushveld and the Southern Mistbelt Forest, dominate the study area and all three are classified as being Least Threatened or Vulnerable. The Eastern Valley Bushveld cover the majority of the study area (Mucina and Rutherford, 2006) and characterise the flanks of most rivers, where Acacias and Euphorbias dominate. The Ngongoni Veld borders the coastal strip. No indigenous mammals were observed during the site visit. Given the high level of anthropogenic disturbance, it is to be expected that populations of indigenous large mammals will be restricted to forests, secluded valleys, proclaimed and fenced protected areas. No such protected areas occur within the immediate study area. The Avifaunal Specialist Report indicated that the proposed route for the powerlines appears to have been well planned and is probably the best possible route in terms of avifaunal impacts.

Page 28: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

28

5. LAND USE CHARACTER OF SURROUNDING AREA Indicate land uses and/or prominent features that currently occur within a 500 m radius of the site and give description of how this influences the application or may be impacted upon by the application: The highlighted sections indicate the relevant landuse 5.1 Natural area �

Refer to Section B4

5.2 Low density residential �

The project will improve power supply to the communities within the study area and provide a number of jobs during the construction phase, thus stimulating the local economy. Non-maintenance of the powerlines may pose safety issue to the communities in terms of fire and electrocutions. The communities may lose land through the development of new servitudes as well as a loss of “sense of place.

5.3 Medium density residential 5.4 High density residential 5.5 Informal residentialA 5.6 Retail commercial & warehousing 5.7 Light industrial 5.8 Medium industrial AN 5.9 Heavy industrial AN 5.10 Power station 5.11 Office/consulting room 5.12 Military or police base/station/compound 5.13 Spoil heap or slimes damA 5.14 Quarry, sand or borrow pit 5.15 Dam or reservoir 5.16 Hospital/medical centre 5.17 School �

The school is located approximately 0.43 km west of the proposed take-off point and therefore the school should not affect the application negatively. The school will however benefit from improved power supplies to the area.

5.18 Tertiary education facility 5.19 Church 5.20 Old age home 5.21 Sewage treatment plantA 5.22 Train station or shunting yard N 5.23 Railway line N 5.24 Major road (4 lanes or more) N 5.25 Airport N 5.26 Harbour 5.27 Sport facilities 5.28 Golf course 5.29 Polo fields 5.30 Filling station H

Page 29: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

29

5.31 Landfill or waste treatment site 5.32 Plantation 5.33 Agriculture �

Agriculture in the region takes the form of low intensity subsistence agriculture. The proposed powerline will result in the reduction of arable land through the development of new servitudes. The proposed development may however result in improved economic conditions reducing the reliance on subsitance agriculture.

5.34 River, stream or wetland �

The proposed powerline crosses the Mthatha River at approximately 31° 33.886’ S ; 29° 18.764’ E. The proposed development may negatively impact the vegetation and banks of a river system, through disturbance, vegetation clearing, erosion and pollution. However, should ESKOMS “Standard for Bush clearance and maintenance within overhead powerline servitudes” together with the mitigation measures contained within this report be implemented, the impact on the Mthatha River is believed to be low.

5.35 Nature conservation area 5.36 Mountain, koppie or ridge 5.37 Museum 5.38 Historical building 5.39 Protected Area 5.40 Graveyard 5.41 Archaeological site 5.42 Other land uses (describe) If any of the boxes marked with an “N “are ticked, how will this impact / be impacted upon by the proposed activity? N/A If any of the boxes marked with an "An" are ticked, how will this impact / be impacted upon by the proposed activity? If YES, specify and explain: If YES, specify: If any of the boxes marked with an "H" are ticked, how will this impact / be impacted upon by the proposed activity. If YES, specify and explain: If YES, specify:

Page 30: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

30

6. CULTURAL/HISTORICAL FEATURES

Are there any signs of culturally or historically significant elements, as defined in Section 2 of the National Heritage Resources Act, 1999, (Act No. 25 of 1999), including

YES NO �

Archaeological or palaeontological sites, on or close (within 20 m) to the site?

NO �

If YES, explain:

N/A

If uncertain, conduct a specialist investigation by a recognised specialist in the field to establish whether there is such a feature(s) present on or close to the site.

Briefly explain the findings of the specialist:

Please see section below: PHASE 1 HERITAGE IMPACT ASSESSMENT

and PALAEOLOGICAL IMPACT ASSESSMENT

Will any building or structure older than 60 years be affected in any way? YES NO �

Is it necessary to apply for a permit in terms of the National Heritage Resources Act, 1999 (Act 25 of 1999)?

YES NO �

If yes, please submit or make sure that the applicant or a specialist submits the necessary application to SAHRA or the relevant provincial heritage agency and attach proof thereof to this application if such application has been made.

PHASE 1 HERITAGE IMPACT ASSESSMENT Findings of the Heritage specialist

eThembeni Cultural Heritage was appointed by GIBB as the Heritage specialist to undertake a

Phase 1 Heritage Impact Assessment (HIA) for this Basic Assessment, in terms of the National

Environmental Management Act 107 of 1998 as amended, in compliance with Section 38 of the

National Heritage Resources Act 25 of 1999, as amended.

The Heritage specialist observed no visually sensitive categories of heritage resource within the

proposed development corridor. However, they did notice various abandoned homesteads around and

between existing villages that probably date to before the establishment of the aforementioned villages

and may include ancestral graves.

Furthermore, the colluvial plain adjacent to the Mgazi River and its tributaries has potential to contain Early and Late Iron Age archaeological remains (Prins et al 1993). However, these have in all likelihood been largely removed from primary context by successive deep-disc ploughing episodes over the last 45 years. eThembeni Cultural Heritage recommended the following mitigation measures:

−−−− That tower placements should be negotiated with residents to ensure that no ancestral graves

are affected.

−−−− Any observed archaeological remains should be reported as per the protocol indicated below.

Protocol for the identification, protection and recovery of heritage resources during construction and operation

Page 31: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

31

It is possible that sub-surface heritage resources will be encountered during the construction phase of

this project. The Project Engineer, Environmental Control Officer (ECO) and all other persons

responsible for site management and excavation should be aware that indicators of sub-surface sites

could include:

− Ash deposits (unnaturally grey appearance of soil compared to the surrounding substrate);

− Bone concentrations, either animal or human;

− Ceramic fragments, including potshards;

− Stone concentrations that appear to be formally arranged (may indicate the presence of an

underlying burial); and

− Fossilised remains of fauna and flora, including trees.

In the event that such indicator(s) of heritage resources are identified, the following actions should be

taken immediately:

− All construction within a radius of at least 20m of the indicator should cease. This distance

should be increased at the discretion of supervisory staff if heavy machinery or explosives

could cause further disturbance to the suspected heritage resource.

− This area must be marked using clearly visible means, such as barrier tape, and all personnel

should be informed that it is a no-go area.

− A guard should be appointed to enforce this no-go area if there is any possibility that it could

be violated, whether intentionally or inadvertently, by construction staff or members of the

public.

− No measures should be taken to cover up the suspected heritage resource with soil, or to

collect any remains such as bone or stone.

− If a heritage practitioner has been appointed to monitor the project, s/he should be contacted

and a site inspection arranged as soon as possible.

− If no heritage practitioner has been appointed to monitor the project, Dr Mariagrazia Galimberti

at SAHRA’s Cape Town head office should be contacted (telephone 021 462 4502).

− The South African Police Services should be notified by a SAHRA staff member or an

independent heritage practitioner if human remains are identified. No SAPS official may

disturb or exhume such remains, whether of recent origin or not.

− All parties concerned should respect the potentially sensitive and confidential nature of the

heritage resources, particularly human remains, and refrain from making public statements

until a mutually agreed time.

Any extension of the project beyond its current footprint involving vegetation and/or earth clearance should be subject to prior assessment by a qualified heritage practitioner, taking into account all information gathered during this initial heritage impact assessment. Conclusion

eThembeni Cultural Heritage recommend that the development proceed with the proposed heritage

mitigation. They have submitted this report to SAHRA in fulfilment of the requirements of the NHRA.

Page 32: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

32

According to Section 38(4) of the Act the report shall be considered timeously by the Council which

shall, after consultation with the person proposing the development, decide –

− whether or not the development may proceed;

− any limitations or conditions are to be applied to the development;

− what general protections in terms of this Act apply, and what formal protections may be

applied to such heritage resources;

− whether compensatory action shall be required in respect of any heritage resources damaged

or destroyed as a result of the development; and

− whether the appointment of specialists is required as a condition of approval of the proposal.

If permission is granted for development to proceed, the client is reminded that the NHRA requires that a developer cease all work immediately and follow the protocol contained in the section above (Protocol for the identification, protection and recovery of heritage resources during construction and operation) should any heritage resources, as defined in the Act, be discovered during the course of development activities.

PALAEONTOLOGICAL IMPACT ASSESSMENT Findings of the Palaeological specialist

Rob Gess Consulting was appointed by GIBB as the Palaeontological Impact Assessment as part of

the Heritage Impact Assessment (HIA) for this Basic Assessment, in terms of the National

Environmental Management Act 107 of 1998 as amended, in compliance with Section 38 of the

National Heritage Resources Act 25 of 1999, as amended.

The Palaeontological Specialist identified that the proposed development would transverse land

underlain by strata belonging to the Karoo Supergroup. The Karoo Supergroup consist of mudstones

and sandy mudstones of the Ecca Group as well as dolerite intrusions emplaced during extrusion of

the Drakensberg Group. Due to the nature of the dolerites, no fossils are present. The alluvium

consisting of unconsolidated silt from large floodplains located adjacent to major rivers is also not

considered to be palaeontologically sensitive.

Course grained exposures of sandy Ecca Group was found to be exposed near Tombo. These

sediments were found to contain only small fragments of plants and are said to be of little

palaeontological importance. As the powerline descends northwards outcrops of resilient Ecca Group

rock were identified, of which were not found to be visually fossiliferous. The powerline then follows the

vally of the Mngazi River where outcrops were covered by thick deposits of Quaternary sand and silt

which are agin not considered to be palaeontologically sensitive. As the powerline leaves the Mnagzi

River valley towards Mafini it transverses a south facing slope characterised by weathered ridges of

resilient dolerite. A small out crop of Ecca Group sediments was again identified a short distance from

the north western end of the route. These sediments consisted of more fine grained mudstones then

the sediments encountered elsewhere along the study area and only fragmented plant remains were

observed.

Page 33: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

33

Conclusion

The powerline route is underlain by Ecca Group sandstones and mudstones, dolerite intrusions and

recent alluvium. Only the Ecca Group strata are potentially palaeontologically sensitive, with only small

fragments of plant stems identified.

The palaeontologist believes it is extremely unlikely that significant paleontological material will be

disturbed during the erection of the powerline.

The following recommendations have been proposed:

1. Monitoring of the works by a palaeontologist is not required; and

2. The ECO should be notified to be on the lookout for any mudstone layers containing mats of

fossil plants, where Ecca Group rocks are disturbed, and should notify SAHRA and/ or a

qualified palaeontologist should such be exposed.

Page 34: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

34

SECTION C: PUBLIC PARTICIPATION 1. ADVERTISEMENT The person conducting a public participation process must take into account any guidelines applicable to public participation as contemplated in Section 24J of the Act and must give notice to all potential interested and affected parties of the application which is subjected to public participation by— (a) fixing a notice board (of a size at least 60 cm by 42 cm; and must display the required

information in lettering and in a format as may be determined by the competent authority) at a place conspicuous to the public at the boundary or on the fence of— (i) the site where the activity to which the application relates is or is to be undertaken; and

(ii) any alternative site mentioned in the application; (b) giving written notice to—

(i) the owner or person in control of that land if the applicant is not the owner or person in control of the land;

(ii) the occupiers of the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;

(iii) owners and occupiers of land adjacent to the site where the activity is or is to be undertaken or to any alternative site where the activity is to be undertaken;

(iv) the municipal councillor of the ward in which the site or alternative site is situated and any organisation of ratepayers that represent the community in the area;

(v) the municipality which has jurisdiction in the area; (vi) any organ of state having jurisdiction in respect of any aspect of the activity; and (vii) any other party as required by the competent authority;

(c) placing an advertisement in— (i) one local newspaper; or

(ii) any official Gazette that is published specifically for the purpose of providing public notice of applications or other submissions made in terms of these Regulations;

(d) placing an advertisement in at least one provincial newspaper or national newspaper, if the activity has or may have an impact that extends beyond the boundaries of the metropolitan or local municipality in which it is or will be undertaken: Provided that this paragraph need not be complied with if an advertisement has been placed in an official Gazette referred to in subregulation 54(c)(ii); and

(e) using reasonable alternative methods, as agreed to by the competent authority, in those instances where a person is desiring of but unable to participate in the process due to— (i) illiteracy; (ii) disability; or (iii) any other disadvantage.

Refer to Appendix for PP documentation 2. CONTENT OF ADVERTISEMENTS AND NOTICES A notice board, advertisement or notices must:

(a) indicate the details of the application which is subjected to public participation; and (b) state—

(i) that the application has been submitted to the competent authority in terms of these Regulations, as the case may be;

(ii) whether basic assessment or scoping procedures are being applied to the application, in the case of an application for environmental authorisation;

Page 35: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

35

(iii) the nature and location of the activity to which the application relates; (iv) where further information on the application or activity can be obtained; and (iv) the manner in which and the person to whom representations in respect of the

application may be made. Refer to Appendix for PP documentation 3. PLACEMENT OF ADVERTISEMENTS AND NOTICES Where the proposed activity may have impacts that extend beyond the municipal area where it is located, a notice must be placed in at least one provincial newspaper or national newspaper, indicating that an application will be submitted to the competent authority in terms of these regulations, the nature and location of the activity, where further information on the proposed activity can be obtained and the manner in which representations in respect of the application can be made, unless a notice has been placed in any Gazette that is published specifically for the purpose of providing notice to the public of applications made in terms of the EIA regulations. Advertisements and notices must make provision for all alternatives. Refer to Appendix for PP documentation 4. DETERMINATION OF APPROPRIATE MEASURES The practitioner must ensure that the public participation is adequate and must determine whether a public meeting or any other additional measure is appropriate or not based on the particular nature of each case. Special attention should be given to the involvement of local community structures such as Ward Committees, ratepayers’ associations and traditional authorities where appropriate. Please note that public concerns that emerge at a later stage that should have been addressed may cause the competent authority to withdraw any authorisation it may have issued if it becomes apparent that the public participation process was inadequate.

5. COMMENTS AND RESPONSE REPORT The practitioner must record all comments and respond to each comment of the public before the application is submitted. The comments and responses must be captured in a comments and response report as prescribed in the EIA regulations and be attached to this application. The comments and response report must be attached under Appendix E. 6. AUTHORITY PARTICIPATION Please note that a complete list of all organs of state and/or any other applicable authority with their contact details must be appended to the Basic Assessment Report. Authorities are key interested and affected parties in each application and no decision on any application will be made before the relevant local authority is provided with the opportunity to give input.

Page 36: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

36

List of authorities informed: Authority Stakeholder Responsible Person

Department of Economic Development, Environment and Tourism (Mthatha)

Mr. Qondile Paliso

Department of Rural Affairs and Land Reform Mr. Vuyisa Mdlalo-sifanele or Ms. Peliwe Njemla

O.R. Tambo District Municipality Mr. Siya Busi

South African Heritage Resource Agency Dr. Mariagrazia Galimberti

Nyandeni Local Municipality Mr. Mandlenkosi Zide

Port St Johns Local Municipality Mr. Sopela

Nyandeni Ward Councillor Cibeni Village Mr. Mtobela

Port St Johns Ward Councillor Montusini Village Ms. Tshitshiliza

Tombo Village Ms. Mtuku

List of authorities from whom comments have been received:

The SAHRA have requested that a Heritage Impact Assessment be undertaken (Please refer to Appendix E). No further comments received to date. Comments received during the Public Participation Process will be recorded in the Final BAR.

7. CONSULTATION WITH OTHER STAKEHOLDERS Note that, for linear activities, or where deviation from the public participation requirements may be appropriate, the person conducting the public participation process may deviate from the requirements of that subregulation to the extent and in the manner as may be agreed to by the competent authority. Proof of any such agreement must be provided, where applicable.

Has any comment been received from stakeholders? YES NO ����

If “YES”, briefly describe the feedback below (also attach copies of any correspondence to and from the stakeholders to this application):

No comments have yet been received. Any comments received during the Public Participation Process will be recorded in the final BAR

Page 37: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

37

SECTION D: IMPACT ASSESSMENT The assessment of impacts must adhere to the minimum requirements in the EIA Regulations, 2010, and should take applicable official guidelines into account. The issues raised by interested and affected parties should also be addressed in the assessment of impacts. 1. ISSUES RAISED BY INTERESTED AND AFFECTED PARTIES List the main issues raised by interested and affected parties.

No issues have been raised by I&APs thus far. Any comments received during the Public Participation Process will be recorded in the Final BAR.

Response from the practitioner to the issues raised by the interested and affected parties (a full response must be given in the Comments and Response Report that must be attached to this report as Annexure E):

N/A

2. IMPACTS THAT MAY RESULT FROM THE PLANNING AND DESIGN, CONSTRUCTION, OPERATIONAL, DECOMMISSIONING AND CLOSURE PHASES AS WELL AS PROPOSED MANAGEMENT OF IDENTIFIED IMPACTS AND PROPOSED MITIGATION MEASURES List the potential direct, indirect and cumulative property/activity/design/technology/operational alternative related impacts (as appropriate) that are likely to occur as a result of the planning and design phase, construction phase, operational phase, decommissioning and closure phase, including impacts relating to the choice of site/activity/technology alternatives as well as the mitigation measures that may eliminate or reduce the potential impacts listed. Alternative A (preferred alternative)

PLANNING AND DESIGN PHASE

DIRECT

Design of Power line may result in bird collision with the proposed overhead power line (-)

Visual impact on existing landscape (-)

INDIRECT

Planning the positions for pylons without taking into account the slope angles, geology and soil properties along the proposed power line may result in unnecessary soil erosion (-)

Planning of access roads may unnecessarily impact on private land, causing security issues and nuisance to surrounding Landowners. (-)

MITIGATION MEASURES

• Proposed monopole structure is preferred in terms of avifaunal impacts as opposed to 5-pole wooden towers.

• Pylons are to be fitted with perching brackets and the river crossing should be marked with suitable anti-collision marking devices to mitigate the impact of bird collision.

• Once the exact powerline tower positions have been surveyed and finalised, an avifaunal walk-through must be undertaken, thus identifying powerline spans requiring mitigation.

• Minimise impact by planting appropriate screening vegetation where feasible.

• Ensure that, as far as possible, pylons are sited to avoid areas of inappropriate geological or soil

Page 38: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

38

properties.

• Planning of access routes must be done in conjunction with the Contractor, Eskom and the Landowner.

• Existing access roads to be utilised as far as practically possible.

• All agreements reached will be documented in writing and no verbal agreements should be made.

• All Southern Mist Belt Forest should be demarcated as “no-go zones” and avoided by the powerline route.

• Eskom undertaking community resolution to avoid potential social disputes

CONSTRUCTION PHASE

DIRECT

Temporary job creation opportunities during the construction phase (+)

Compacting of soils during earthworks (-)

Onsite contamination of soil during concrete mixing (-)

Reduction in air quality as a result of construction activities (-)

Excessive noise pollution from the construction sites may impact on both the surrounding social and biophysical environment (-)

Impact watercourse beds and banks during pole erection and stringing operations (-)

Movement of trucks delivering construction material (-)

INDIRECT

New vehicle tracks and/or clearing of any vegetation may cause additional and unnecessary soil erosion (-)

Uncontrolled vehicular access to the site and to the surrounding servitudes could result in destruction of sensitive vegetation and unnecessary soil erosion and/or soil compaction (-)

Incorrect topsoil stripping and stockpile management can result in soil losses via erosion (wind and water) (-) This impact would apply for: • Site establishment • Pylon excavations

The digging of foundations for support structures and access tracks may result in exposure of soils to erosion (-)

Stormwater runoff may contaminate the surrounding environment (-)

Spillage of any stored hazardous substances such as fuel, chemicals, paint, etc. that can contaminate ground, groundwater and water column (-)

Inappropriate responses to petrochemical or hazardous spill (-)

Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environments and risk to surrounding communities (-)

Fires created within the construction sites may result in runaway veldfires (-)

Failure to provide adequate on-site sanitation and clean drinking water may result in runoff transferring contaminants into the surrounding environment (-)

Increase in dust generation during the movement of construction vehicles (-)

Construction rubble left onsite may attract vermin and encourage the growth of opportunistic alien vegetation (-)

The impact on habitats or on fauna directly (bird collisions and electrocutions) causing loss of species diversity. Bird collisions likely to have the highest impact (-)

Poaching of animals in the vegetation (-)

Temporary emigration of animals out of construction area (-)

Damage to roads by construction vehicles (-)

Increase in traffic and traffic congestion due to construction vehicles (-)

Cultural, heritage and palaeontological artefacts may be uncovered during the course of the construction

Page 39: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

39

site establishment, pylon excavations, etc. (-)

MITIGATION MEASURES

• Soils compacted during the construction of the power line should be deeply ripped to loosen compacted layers and regraded to even running levels.

• Topsoil should be spread over landscaped areas.

• According to specifications by Eskom’s landscape architect, the area should be re-vegetated upon completion of construction activities.

• Vehicle access to the power line servitude must as far as possible be limited to existing roads. If new access roads need to be constructed, they should follow cleared areas such as cattle pathways.

• The Contractor will properly mark all access roads.

• Markers will show the direction of travel as well as tower numbers to which the road leads.

• Roads not to be used will be marked with a "NO ENTRY" sign. Unnecessary traversing of land is discouraged. Where required, speed limits will be indicated on the roads (30 km). All speed limits will be strictly adhered to at all times.

• Strict control should be implemented over all activities during construction to ensure disturbance to social and ecological components is kept to a minimum.

• The full depth of topsoil should be stripped from areas affected by construction and related activities prior to the commencement of major earthworks. This should include the building footprints, working areas and storage areas.

• Topsoil must be reused where possible to rehabilitate disturbed areas.

• Care must be taken not to mix topsoil and subsoil during stripping.

• No soil stripping must take place on areas within the site that the contractor does not require for construction works, or on areas of retained vegetation.

• Subsoil and overburden should, in all construction and lay-down areas, be stockpiled separately to be returned for backfilling in the correct soil horizon order.

• Stockpiles should not be situated such that they obstruct natural water pathways and drainage channels.

• If stockpiles are exposed to windy conditions or heavy rain, they should be covered either by vegetation or cloth.

• Stockpiles may further be protected by the construction of berms or low brick walls around their bases.

• Stockpiles should be kept clear of weeds and alien vegetation growth by regular weeding.

• The site must be managed in a manner that prevents pollution of downstream watercourses or groundwater, due to suspended solids, silt or chemical pollutants.

• Temporary cut-off drains and berms may be required to capture stormwater and promote infiltration.

• Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Staff that will be handling hazardous materials must be trained to do so. Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time

• Depending on the nature and extent of the spill, contaminated soil must be either excavated or treated on-site.

• The ECO must determine the precise method of treatment of polluted soil.

• This could involve the application of soil absorbent materials or oil-digestive powders to the contaminated soil.

• If a spill occurs on an impermeable surface such as cement or concrete, the surface spill must be contained using oil absorbent materials.

Page 40: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

40

• Contaminated remediation materials must be carefully removed from the area of the spill so as to prevent further release of petrochemicals into the environment, and stored in adequate containers until appropriate disposal.

• The individual responsible for or who discovers the petrochemical spill must report the incident to the Project Co-ordinator, ECO and/or Contractor as soon as reasonably possible.

• Any spills are to be immediately assessed and the necessary actions undertaken to contain and remediate the spill.

• No vehicles transporting concrete to the site may be washed on site.

• If a batching plant is necessary, run-off should be managed effectively to avoid contamination of other areas of the site.

• Fire-fighting equipment should be present on site at all times as per the Occupational Health and Safety Act.

• All construction staff must be trained in fire hazard control and fire-fighting techniques.

• All flammable substances must be stored in dry areas which do not pose an ignition risk.

• No open fires will be allowed on site unless in a demarcated area identified by the ECO.

• Smoking may only be conducted in demarcated areas as agreed upon by the ECO and contractor.

• All cooking will be done in demarcated areas that are safe in terms of runaway or uncontrolled fires.

• The Contractor will have operational fire-fighting equipment available on site at all times. The level of fire-fighting equipment must be assessed and evaluated through a typical risk assessment process. It may be required to increase the level of protection, especially during the winter months.

• Adequate sanitary and ablutions facilities must be provided for construction workers and serviced regularly.

• The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.

• Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp will be collected and removed from the site for appropriate disposal at a licensed commercial facility.

• Heavy vehicle traffic should be routed away from noise sensitive areas, where possible.

• Noise levels must be kept within acceptable limits. All noise and sounds generated must adhere to SABS 0103 specifications for maximum allowable noise levels for residential areas. No pure tone sirens or hooters may be utilised except where required in terms of SABS standards or in emergencies.

• Noisy activities to take place during allocated construction hours only as per Section 25 of the Noise Control Regulations of the Environment Conservation Act, 1989 (Act No. 73 of 1989).

• Construction rubble will be disposed of in pre–agreed, demarcated spoil dumps that have been approved by the Municipality.

• Continued care should be taken to observe any sites of heritage significance during operation. Should any archaeological artefacts and palaeontological remains be exposed during operations, work on the area where the artefacts were found will cease immediately and the appropriate person will be notified as soon as possible.

• Any discovered artefacts will not be removed under any circumstances. Any destruction of a site can only be allowed once a permit is obtained from SAHRA and the site has been mapped and noted.

• Under no circumstances will archaeological or palaeontological artefacts be removed, destroyed or interfered with by anyone on the site during operations.

• The operator will advise its workers of the penalties associated with the unlawful removal of cultural, historical, archaeological or palaeontological artefacts, as set out in the National Heritage Resources Act (Act No. 25 of 1999), Section 51(1).

• The rehabilitation of the trenches and disturbed areas around the power line must be done with indigenous grasses local to the area and that require minimal horticultural maintenance.

• All weeds and invasive vegetation should be eradicated over a five year period.

• Dust suppression measures need to be implemented on site when necessary to reduce the dust

Page 41: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

41

impacts.

• Waste managed accordingly and collected regularly to prevent accumulation on site.

OPERATIONAL PHASE

DIRECT

Provision of uninterrupted power supply (+)

INDIRECT

Uncontrolled access to the power line servitude may result in an increase in illegal poaching on property surrounding the servitude (-)

Non-compliance to a power line maintenance schedule would result in the line becoming overgrown and perhaps incurring damage (-)

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply (+)

Consideration of local workforce will stimulate the local economy (+)

Failure to maintain the powerline and servitudes may lead to veld fires (-)

Loss of land with registration of a permanent servitude (-)

Loss of ‘sense of place’ (-)

CUMULATIVE

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply. (+)

Contribution to densification of the area. (-/+)

MITIGATION MEASURES

• Access to the power line servitude must be restricted. Ideally this should be done by fencing off and gating along the main access roads.

• Regular inspection of the power line must take place to monitor its operational status

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

• The development must be screened by vegetation where practically feasible to limit the visual impact

• Ensure all development takes place in accordance with relevant policies and guidelines

• During this phase it is essential that all maintenance personnel undertake general best practice environmental management including:

� Keeping to existing access roads and no “open bush” driving;

� No littering or disturbance to surface water features (where relevant); and

� Closing gates and general respect for property. NO-GO ALTERNATIVE

Failure to install the proposed power line may result in significantly longer power outages when failures in the supply network occur as it will not be possible to utilise remote switching control between circuits / substations. This option is not a feasible or reasonable alternative.

DECOMMISSIONING AND CLOSURE PHASE

The decommissioning and closure phase for the substation is anticipated to be within 25-30 years from development of the facility. Should the facility be decommissioned it is anticipated that the installation will be removed from the site or upgraded.

Page 42: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

42

Alternative B (minor alternative)

PLANNING AND DESIGN PHASE

DIRECT

Design of Power line may result in bird collision with the proposed overhead power line (-)

Visual impact on existing landscape (-)

INDIRECT

Planning the positions for pylons without taking into account the geology and soil properties along the proposed power line may result in unnecessary soil erosion (-)

Planning of access roads may unnecessarily impact on private land, causing security issues and nuisance to surrounding Landowners. (-)

MITIGATION MEASURES

• Proposed monopole structure is preferred in terms of avifaunal impacts as opposed to 5-pole wooden towers.

• Pylons are to be fitted with perching brackets and the river crossing should be marked with suitable anti-collision marking devices to mitigate the impact of bird collision.

• Once the exact powerline tower positions have been surveyed and finalised, an avifaunal walk-through must be undertaken, thus identifying powerline spans requiring mitigation.

• Minimise impact by planting appropriate screening vegetation.

• Ensure that, as far as possible, pylons are sited to avoid areas of inappropriate geological or soil properties.

• Planning of access routes must be done in conjunction with the Contractor, Eskom and the Landowner.

• Existing access roads to be utilised as far as practically possible.

• All agreements reached will be documented in writing and no verbal agreements should be made.

• All Southern Mist Belt Forest should be demarcated as “no-go zones” and avoided by the powerline route.

• Eskom undertaking community resolution to avoid potential social disputes

CONSTRUCTION PHASE

DIRECT

Temporary job creation opportunities during the construction phase (+)

Compacting of soils during earthworks (-)

Onsite contamination of soil during concrete mixing (-)

Reduction in air quality as a result of construction activities (-)

Excessive noise pollution from the construction sites may impact on both the surrounding social and biophysical environment (-)

INDIRECT

New vehicle tracks and/or clearing of any vegetation may cause additional and unnecessary soil erosion (-)

Uncontrolled vehicular access to the site and to the surrounding servitudes could result in destruction of sensitive vegetation and unnecessary soil erosion and/or soil compaction (-)

Incorrect topsoil stripping and stockpile management can result in soil losses via erosion (wind and

Page 43: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

43

water) (-) This impact would apply for: • Site establishment • Pylon excavations

The digging of foundations for support structures and access tracks may result in exposure of soils to erosion (-)

Stormwater runoff may contaminate the surrounding environment (-)

Spillage of any stored hazardous substances such as fuel, chemicals, paint, etc. that can contaminate ground, groundwater and water column (-)

Inappropriate responses to petrochemical or hazardous spill (-)

Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environments and risk to surrounding communities (-)

Fires created within the construction sites may result in runaway veldfires (-)

Failure to provide adequate on-site sanitation and clean drinking water may result in runoff transferring contaminants into the surrounding environment (-)

Construction rubble left onsite may attract vermin and encourage the growth of opportunistic alien vegetation (-)

The impact on habitats or on fauna directly (bird collisions and electrocutions) causing loss of species diversity. Bird collisions likely to have the highest impact (-)

Poaching of animals in the vegetation (-)

Temporary emigration of animals out of construction area (-)

Damage to roads by construction vehicles (-)

Increase in traffic and traffic congestion due to construction vehicles (-)

Cultural, heritage and palaeontological artefacts may be uncovered during the course of the construction site establishment, pylon excavations, etc. (-)

MITIGATION MEASURES

• Soils compacted during the construction of the power line should be deeply ripped to loosen compacted layers and regraded to even running levels.

• Topsoil should be spread over landscaped areas.

• According to specifications by Eskom’s landscape architect, the area should be re-vegetated upon completion of construction activities.

• Vehicle access to the power line servitude must as far as possible be limited to existing roads. If new access roads need to be constructed, they should follow cleared areas such as cattle pathways.

• The Contractor will properly mark all access roads.

• Markers will show the direction of travel as well as tower numbers to which the road leads.

• Roads not to be used will be marked with a "NO ENTRY" sign. Unnecessary traversing of land is discouraged. Where required, speed limits will be indicated on the roads (30 km). All speed limits will be strictly adhered to at all times.

• The full depth of topsoil should be stripped from areas affected by construction and related activities prior to the commencement of major earthworks. This should include the building footprints, working areas and storage areas.

• Topsoil must be reused where possible to rehabilitate disturbed areas.

• Care must be taken not to mix topsoil and subsoil during stripping.

• No soil stripping must take place on areas within the site that the contractor does not require for construction works, or on areas of retained vegetation.

• Subsoil and overburden should, in all construction and lay-down areas, be stockpiled separately to be returned for backfilling in the correct soil horizon order.

• Stockpiles should not be situated such that they obstruct natural water pathways and drainage channels.

Page 44: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

44

• If stockpiles are exposed to windy conditions or heavy rain, they should be covered either by vegetation or cloth.

• Stockpiles may further be protected by the construction of berms or low brick walls around their bases.

• Stockpiles should be kept clear of weeds and alien vegetation growth by regular weeding.

• The site must be managed in a manner that prevents pollution of downstream watercourses or groundwater, due to suspended solids, silt or chemical pollutants.

• Temporary cut-off drains and berms may be required to capture stormwater and promote infiltration.

• Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Staff that will be handling hazardous materials must be trained to do so. Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time

• Depending on the nature and extent of the spill, contaminated soil must be either excavated or treated on-site.

• The ECO must determine the precise method of treatment of polluted soil.

• This could involve the application of soil absorbent materials or oil-digestive powders to the contaminated soil.

• If a spill occurs on an impermeable surface such as cement or concrete, the surface spill must be contained using oil absorbent materials.

• Contaminated remediation materials must be carefully removed from the area of the spill so as to prevent further release of petrochemicals into the environment, and stored in adequate containers until appropriate disposal.

• The individual responsible for or who discovers the petrochemical spill must report the incident to the Project Co-ordinator, ECO and/or Contractor as soon as reasonably possible.

• The problem must be assessed and the necessary actions required will be undertaken.

• The immediate response must be to contain the spill.

• No vehicles transporting concrete to the site may be washed on site.

• If a batching plant is necessary, run-off should be managed effectively to avoid contamination of other areas of the site.

• Fire-fighting equipment should be present on site at all times as per the Occupational Health and Safety Act.

• All construction staff must be trained in fire hazard control and fire-fighting techniques.

• All flammable substances must be stored in dry areas which do not pose an ignition risk.

• No open fires will be allowed on site unless in a demarcated area identified by the ECO.

• Smoking may only be conducted in demarcated areas as agreed upon by the ECO and contractor.

• All cooking will be done in demarcated areas that are safe in terms of runaway or uncontrolled fires.

• The Contractor will have operational fire-fighting equipment available on site at all times. The level of fire-fighting equipment must be assessed and evaluated through a typical risk assessment process. It may be required to increase the level of protection, especially during the winter months.

• Adequate sanitary and ablutions facilities must be provided for construction workers.

• The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.

• Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp will be collected and removed from the site for appropriate disposal at a licensed commercial facility.

• Heavy vehicle traffic should be routed away from noise sensitive areas, where possible.

• Noise levels must be kept within acceptable limits. All noise and sounds generated must adhere to SABS 0103 specifications for maximum allowable noise levels for residential areas. No pure tone

Page 45: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

45

sirens or hooters may be utilised except where required in terms of SABS standards or in emergencies.

• Noisy activities to take place during allocated construction hours only as per Section 25 of the Noise Control Regulations of the Environment Conservation Act, 1989 (Act No. 73 of 1989).

• Construction rubble will be disposed of in pre–agreed, demarcated spoil dumps that have been approved by the Municipality.

• Continued care should be taken to observe any sites of heritage significance during operation. Should any archaeological artefacts and palaeontological remains be exposed during operations, work on the area where the artefacts were found will cease immediately and the appropriate person will be notified as soon as possible.

• Any discovered artefacts will not be removed under any circumstances. Any destruction of a site can only be allowed once a permit is obtained from SAHRA and the site has been mapped and noted.

• Under no circumstances will archaeological or palaeontological artefacts be removed, destroyed or interfered with by anyone on the site during operations.

• The operator will advise its workers of the penalties associated with the unlawful removal of cultural, historical, archaeological or palaeontological artefacts, as set out in the National Heritage Resources Act (Act No. 25 of 1999), Section 51(1).

• The rehabilitation of the trenches and disturbed areas around the power line must be done with indigenous grasses local to the area and that require minimal horticultural maintenance.

• All weeds and invasive vegetation should be eradicated over a five year period.

OPERATIONAL PHASE

DIRECT

Provision of uninterrupted power supply (+)

INDIRECT

Uncontrolled access to the power line servitude may result in an increase in illegal poaching on private property surrounding the servitude (-)

Non-compliance to a power line maintenance schedule would result in the line becoming overgrown and perhaps incurring damage (-)

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply (+)

Consideration of local workforce will stimulate the local economy (+)

Failure to maintain the powerline and servitudes may lead to veld fires (-)

Loss of land with registration of a permanent servitude (-)

Loss of ‘sense of place’ (-)

CUMULATIVE

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply. (+)

Contribution to densification of the area. (-/+)

MITIGATION MEASURES

• Access to the power line servitude must be restricted. Ideally this should be done by fencing off and gating along the main access roads.

• Regular inspection of the power line must take place to monitor its operational status

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

• The development must be screened by vegetation to limit the visual impact

Page 46: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

46

• Ensure all development takes place in accordance with relevant policies and guidelines

• During this phase it is essential that all maintenance personnel undertake general best practice environmental management including:

� Keeping to existing access roads and no “open bush” driving;

� No littering or disturbance to surface water features (where relevant); and

� Closing gates and general respect for property. NO-GO ALTERNATIVE

Failure to install the proposed power line may result in significantly longer power outages when failures in the supply network occur as it will not be possible to utilise remote switching control between circuits / substations. This option is not a feasible or reasonable alternative.

DECOMMISSIONING AND CLOSURE PHASE

The decommissioning and closure phase for the substation is anticipated to be within 25-30 years from development of the facility. Should the facility be decommissioned it is anticipated that the installation will be removed from the site or upgraded. 3. ENVIRONMENTAL IMPACT STATEMENT Taking the assessment of potential impacts into account, please provide an environmental impact statement that summarises the impact that the proposed activity and its alternatives may have on the environment after the management and mitigation of impacts have been taken into account, with specific reference to types of impact, duration of impacts, likelihood of potential impacts actually occurring and the significance of impacts.

Criteria for Ranking Severity of Environmental Impacts

LOW (L) MEDIUM (M) HIGH (H) DEFINITE

Intensity Ecological functions may continue undisturbed, no rare or endangered species affected, no objection from I&APs

Ecological functioning temporarily affected, no rare or endangered species affected, some concern from I&APs

Ecological functioning permanently altered, rare or endangered species impacted, major concern from I&APs

N/A

Spatial Scale Immediate area of impact

Beyond site boundary; Local

Far beyond site boundary; Regional/National

N/A

Duration Quickly reversible; Less than the project life; Short Time

Reversible over time; Life of the project; Medium term

Permanent; Beyond Closure; Long term

N/A

Probability Unlikely Possible Likely Highly Likely/ Definite

Page 47: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

47

Alternative A (preferred alternative)

Option 1 is preferred route alignment because it presents Low environmental impacts with mitigation. According to the Avifaunal specialist study the preferred alternative appears to have been well planned and is probably the best possible route in terms of avifaunal impacts. In terms of ecological factors, the preferred alternative is favoured as it avoids the patches of indigenous forests and other sensitive micro habitats that exist within the study area. According to the Heritage Impact Assessments, including Archaeological and Palaeontological aspects, it is unlikely that the preferred alternative will disturb any significant palaeontological or archaeological material.

Alternative B (Minor alternative)

The minor alternative has very little bearing on the anticipated impacts. The impacts are therefore envisaged to be the same as the preferred alternative.

No-go Alternative (compulsory)

The provision of a non-interrupted power supply is essential for economic development of the area. The no-go alternative is not a viable option.

Page 48: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

48

Alternative A (preferred alternative)

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

PLANNING AND DESIGN PHASE

AVI-FAUNA Bird collision with the proposed overhead power line (-)

M L H M H L • Pylons are to be fitted with perching brackets and the river crossing should be marked with suitable anti-collision marking devices to mitigate the impact of bird collision.

VISUAL IMPACT Impact on existing landscape (-)

L L H M M M • The development must be screened by vegetation where practically feasible to limit the visual impact. Absolute screening will however not be practically feasible and will impact the sense of place.

• Monopole structures are to be utilised due to their reduced visual impact

GEOLOGY AND SOILS

Installation of pylons and construction of substation without taking into account the geology and soil structure along the proposed line may result in unnecessary soil erosion and/or damage to geological formations (-)

M L M M H M • Ensure that as far as possible, infrastructure is sited to avoid areas of inappropriate geological or soil structure.

ACCESS ROADS

Access roads may unnecessarily impact on social and ecological components (-)

L L H M L L • Planning of access routes must be done in conjunction with the Contractor, Eskom and the Landowner.

• All access to private or communal land must be negotiated in advance with land-owners.

• All agreements reached will be documented in writing and no verbal agreements should be made.

• The condition of existing access roads to be used will be documented with photographs.

CONSTRUCTION PHASE

JOB CREATION Temporary job creation opportunities during the construction phase (+)

M L H H M M • No mitigation required.

SOIL MANAGEMENT

Compacting of soils during earthworks (-) M L H H M L • Soils compacted during the construction of the power line should be deeply ripped to loosen compacted layers and regarded to even running levels.

• Topsoil should be spread over landscaped areas. • According to specifications by Eskom’s landscape architect, the area

should be re-vegetated upon completion of construction activities. New vehicle tracks and/or clearing of any vegetation may cause additional and unnecessary soil erosion (-)

M L H M H M • Vehicle access to the power line servitude must as far as possible be limited to existing roads. If new access roads need to be constructed, they should follow cleared areas such as cattle pathways.

Page 49: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

49

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

Uncontrolled vehicular access to the site and to the surrounding servitudes could result in destruction of sensitive vegetation and unnecessary soil erosion and/or soil compaction (-)

M L M M M L • The Contractor will properly mark all access roads. • Markers will show the direction of travel. • Roads not to be used will be marked with a "NO ENTRY" sign.

Unnecessary traversing of agricultural and natural open land is discouraged.

• Where required, speed limits will be indicated on the roads. All speed limits will be strictly adhered to at all times.

Incorrect topsoil stripping and stockpile management can result in soil losses via erosion (wind and water) (-). This impact would apply for:

• Site establishment • Pylon excavations

M S H M M L • The full depth of topsoil should be stripped from areas affected by construction and related activities prior to the commencement of major earthworks. This should include all working areas and storage areas.

• Topsoil must be reused where possible to rehabilitate disturbed areas.

• Care must be taken not to mix topsoil and subsoil during stripping. • No soil stripping must take place on areas within the site that the

contractor does not require for construction works, or on areas of retained vegetation.

• Subsoil and overburden should, in all construction and lay-down areas, be stockpiled separately to be returned for backfilling in the correct soil horizon order.

• Stockpiles should not be situated such that they do not obstruct natural water pathways and drainage channels.

• If stockpiles are exposed to windy conditions or heavy rain, they should be covered either by vegetation or cloth.

• Stockpiles may further be protected by the construction of berms or low brick walls around their bases.

• Stockpiles should be kept clear of weeds and alien vegetation growth by regular weeding.

• Stockpiles should be protected from erosion.

The removal of vegetation cover for the digging of foundations for support structures and access tracks may result in exposure of soils to erosion (-)

M S H H H M

STORMWATER MANAGEMENT

Stormwater runoff may contaminate the surrounding environment (-)

M L H M M L • The site must be managed in a manner that prevents pollution of downstream watercourses or groundwater, due to suspended solids, silt or chemical pollutants.

• Temporary cut-off drains and berms may be required to capture stormwater and promote infiltration and protect from erosion.

HAZARDOUS MATERIAL

Spillage of any stored hazardous substances such as fuel, chemicals, paint etc. that can

M L H M H L • Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS

Page 50: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

50

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

MANAGEMENT contaminate ground, groundwater and water column (-)

Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Staff that will be handling hazardous materials must be trained to do so. Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Depending on the nature and extent of the spill, contaminated soil must be either excavated and disposed of at a hazardous waste disposal or treated on-site.

• The ECO must determine the precise method of treatment of polluted soil.

• This could involve the application of soil absorbent materials or oil-digestive powders to the contaminated soil.

• If a spill occurs on an impermeable surface such as cement or concrete, the surface spill must be contained using oil-absorbent materials.

• Contaminated remediation materials must be carefully removed from the area of the spill so as to prevent further release of petrochemicals into the environment, and stored in adequate containers until appropriate disposal.

Inappropriate responses to petrochemical or hazardous spill (-)

M L M M M L • The individual responsible for or who discovers the petrochemical spill must report the incident to the Project Coordinator, ECO and/or Contractor as soon as reasonably possible.

• The problem must be assessed and the necessary actions required will be undertaken.

• The immediate response must be to contain the spill.

On-site contamination of soil during concrete mixing (-)

M S M M M L • No vehicles transporting concrete to the site may be washed on site. • If a batching plant is necessary, batching is to take place on an

impermeable surface and run-off should be managed effectively to avoid contamination of other areas of the site.

FIRE MANAGEMENT

Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environments and surrounding agricultural activities (-)

M L M M M L • Fire-fighting equipment should be present on site at all times as per Occupational Health and Safety Act.

• All construction staff must be trained in fire hazard control and fire-fighting techniques.

Page 51: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

51

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

• All flammable substances must be stored in dry areas which do not pose an ignition risk.

• No open fires will be allowed on site unless in a demarcated area identified by the ECO.

• Smoking may only be conducted in demarcated areas as agreed upon by the ECO and contractor.

Fires created within the construction sites may result in runaway veldfires (-)

M M L M H L • All cooking will be done in demarcated areas that are safe in terms of runaway or uncontrolled fires

• The Contractor will have operational fire-fighting equipment available on site at all times. The level of fire-fighting equipment must be assessed and evaluated through a typical risk assessment process. It may be required to increase the level of protection, especially during the winter months.

PROVISION OF PORTABLE TOILETS

Failure to provide adequate on-site sanitation and clean drinking water may result in run-off transferring contaminants into the surrounding environment (-)

M M M M M L • Adequate sanitary and ablutions facilities must be provided for construction workers.

• The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.

• Toilet facilities must be available within walking distance of all working areas.

• Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp will be collected and removed from the site for appropriate disposal at a licensed commercial facility.

NOISE

Excessive noise pollution from the construction sites may impact the surrounding environment (-)

L L M H M L • Heavy vehicle traffic should be routed away from noise-sensitive areas, where possible.

• Noise levels must be kept within acceptable limits. All noise and sounds generated must adhere to SABS 0103 specifications for maximum allowable noise levels for residential areas. No pure tone sirens or hooters may be utilised except where required in terms of SABS standards or in emergencies.

• Noisy activities to take place during allocated construction hours only as per Section 25 of the Noise Control Regulations of the Environment Conservation Act, 1989 (Act No. 73 of 1989).

BUILDING RUBBLE Construction rubble left on-site may attract vermin and encourage the growth of

M L M M M L • Construction rubble will be disposed of in pre–agreed, demarcated spoil dumps that have been approved by the relevant Municipality.

Page 52: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

52

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

opportunistic alien vegetation (-)

AIR QUALITY Reduction in air quality as a result of construction activities (-)

M L L M M L • All vehicles and equipment are to be maintained in an acceptable condition. Vehicles are to maintain vehicle speed limits to avoid dust generation. Dust suppression measures need to be implemented on site when necessary to reduce the dust impacts.

FAUNA Poaching of animals in the vegetation (-)

M L L M M L • No poaching of fauna is allowed.

Temporary emigration of animals out of construction area (-)

L L L M L L • No mitigation. Short term nature of the project and rehabilitation of disturbed areas

INFRASTRUCTURE Damage to roads by construction vehicles (-) M L H M M L • Construction vehicles are to maintain vehicle speed limits and are to

utilise roads approved by the Engineer or ECO

TRAFFIC Increase in traffic due to construction vehicles (-)

M L M M M M • Construction vehicles to utilised roads approved by the Engineer or ECO.

CULTURAL HERITAGE

Cultural, heritage and palaeontological artefacts may be uncovered during the course of the construction site establishment, pylon excavations, etc. (-)

M S H M M L • Continued care should be taken to observe any sites of heritage significance during operation. Should any archaeological artefacts and palaeontological remains be exposed during operations, work on the area where the artefacts were found will cease immediately and the appropriate person will be notified as soon as possible.

• Any discovered artefacts will not be removed under any circumstances. Any destruction of a site can only be allowed once a permit is obtained from SAHRA and the site has been mapped and noted.

• Under no circumstances will archaeological or palaeontological artefacts be removed, destroyed or interfered with by anyone on the site during operations.

• That tower placements should be negotiated with residents to ensure that no ancestral graves are affected.

• The operator will advise its workers of the penalties associated with the unlawful removal of cultural, historical, archaeological or palaeontological artefacts, as set out in the National Heritage Resources Act (Act No. 25 of 1999), Section 51(1)

VEGETATION

Ineffective vegetation rehabilitation measures could result in excessive soil erosion and encroachment of alien vegetation (-)

M M H M M L • The rehabilitation of the trenches and disturbed areas around the power line must be done with indigenous grasses local to the area and that require minimal horticultural maintenance.

• All weeds and invasive vegetation should be eradicated over a five year period.

Page 53: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

53

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

• Indigenous forest areas are to be completely avoided by the powerline and labour teams.

• Vehicle and machinery movement in and around the river crossing and grassland should be kept to a minimum.

• As little as possible of the natural vegetation should be removed for the purpose of construction.

OPERATIONAL PHASE

POWER SUPPLY Provision of uninterrupted power supply (+) M R H H N/A N/A • No mitigation required.

ACCESS CONTROL Uncontrolled access to the power line servitude may result safety hazards

M L H M M L • Access to the power line servitude must be restricted. Ideally this should be done by fencing off and gating along the main access roads.

LINE MAINTENANCE

Non-compliance to a power line maintenance schedule would result in the line becoming overgrown and perhaps incurring damage (-)

M R M M M L • Regular inspection of the power line must take place to monitor its operational status.

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

FAUNA

The impact on habitats or on fauna directly (bird collisions and electrocutions) causing loss of species diversity. Bird collisions likely to have the highest impact (-)

M S LT M M L • Adhere to Eskom guidelines for construction. • Bird perching brackets are to be used on every powerline pole. • High risk section of the powerline as identified in the Avifaunal

Specialist report must be fitted with suitable Eskom approved anti-bird collision line marking devices on the earth wire to increase visibility of the cables.

• Once the exact tower positions are surveyed and finalised, an avifaunal walk-through must done on the line, thus identifying the exact spans of powerline requiring mitigation.

• Indigenous forest areas are to be completely avoided by the powerline and labour teams.

• Vehicle and machinery movement in and around the river crossing and grassland should be kept to a minimum.

SOCIO-ECONOMIC IMPACTS

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply (+)

M R M H N/A N/A • No mitigation required.

Consideration of local workforce will stimulate the local economy (+)

M L H H N/A N/A • No mitigation required.

Failure to maintain powerline and servitudes may lead to veld fires (-)

M L M M H M • Regular inspection of the power line must take place to monitor its operational status.

Page 54: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

54

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

Loss of land with registration of a permanent servitude (-)

M L H M M M • No mitigation

Loss of ‘sense of place’ (-) M L H M M L • The guyed monopole structures are designed such to have to lease

visual impact on the environment. The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply. (+)

M L L H N/A N/A • No mitigation required.

Contribution to densification of the area. (-/+) M L L M M M • Ensure all development takes place in accordance with relevant

policies and guidelines.

Alternative B (Minor alternative)

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure In

tens

ity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

PLANNING AND DESIGN PHASE

AVI-FAUNA Bird collision with the proposed overhead power line (-)

M L H M H L • Pylons are to be fitted with perching brackets and the river crossing should be marked with suitable anti-collision marking devices to mitigate the impact of bird collision.

VISUAL IMPACT Impact on existing landscape (-)

L L H M M M • Proposed mitigation measures provided in this report and the Environmental Management Programme should be implemented thus reducing cumulative impacts. The overall project will result in a positive impact.

GEOLOGY AND SOILS

Installation of pylons and construction of substation without taking into account the geology and soil structure along the proposed line may result in unnecessary soil erosion

M L M M H M • Ensure that as far as possible, infrastructure is sited to avoid areas of inappropriate geological or soil structure.

Page 55: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

55

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

and/or damage to geological formations (-)

ACCESS ROADS

Access roads may unnecessarily impact on social and ecological components (-)

L L H M L L • Planning of access routes must be done in conjunction with the Contractor, Eskom and the Landowner.

• All access to private or communal land must be negotiated in advance with land-owners.

• All agreements reached will be documented in writing and no verbal agreements should be made.

• The condition of existing access roads to be used will be documented with photographs.

CONSTRUCTION PHASE

JOB CREATION Temporary job creation opportunities during the construction phase (+)

M L H H M M • No mitigation required.

SOIL MANAGEMENT

Compacting of soils during earthworks (-) M L H H M L • Soils compacted during the construction of the power line should be deeply ripped to loosen compacted layers and regarded to even running levels.

• Topsoil should be spread over landscaped areas. • According to specifications by Eskom’s landscape architect, the area

should be re-vegetated upon completion of construction activities. New vehicle tracks and/or clearing of any vegetation may cause additional and unnecessary soil erosion (-)

M L H M H M • Vehicle access to the power line servitude must as far as possible be limited to existing roads. If new access roads need to be constructed, they should follow cleared areas such as cattle pathways.

Uncontrolled vehicular access to the site and to the surrounding servitudes could result in destruction of sensitive vegetation and unnecessary soil erosion and/or soil compaction (-)

M L M M M L • The Contractor will properly mark all access roads. • Markers will show the direction of travel. • Roads not to be used will be marked with a "NO ENTRY" sign.

Unnecessary traversing of agricultural and natural open land is discouraged.

• Where required, speed limits will be indicated on the roads. All speed limits will be strictly adhered to at all times.

Incorrect topsoil stripping and stockpile management can result in soil losses via erosion (wind and water) (-). This impact would apply for:

• Site establishment • Pylon excavations

M S H M M L • The full depth of topsoil should be stripped from areas affected by construction and related activities prior to the commencement of major earthworks. This should include all working areas and storage areas.

• Topsoil must be reused where possible to rehabilitate disturbed areas.

• Care must be taken not to mix topsoil and subsoil during stripping. • No soil stripping must take place on areas within the site that the

The removal of vegetation cover for the digging of foundations for support structures

M S H H H M

Page 56: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

56

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

and access tracks may result in exposure of soils to erosion (-)

contractor does not require for construction works, or on areas of retained vegetation.

• Subsoil and overburden should, in all construction and lay-down areas, be stockpiled separately to be returned for backfilling in the correct soil horizon order.

• Stockpiles should not be situated such that they do not obstruct natural water pathways and drainage channels.

• If stockpiles are exposed to windy conditions or heavy rain, they should be covered either by vegetation or cloth.

• Stockpiles may further be protected by the construction of berms or low brick walls around their bases.

• Stockpiles should be kept clear of weeds and alien vegetation growth by regular weeding.

• Stockpiles should be protected from erosion.

STORMWATER MANAGEMENT

Stormwater runoff may contaminate the surrounding environment (-)

M L H M M L • The site must be managed in a manner that prevents pollution of downstream watercourses or groundwater, due to suspended solids, silt or chemical pollutants.

• Temporary cut-off drains and berms may be required to capture stormwater and promote infiltration and protect from erosion.

HAZARDOUS MATERIAL MANAGEMENT

Spillage of any stored hazardous substances such as fuel, chemicals, paint etc. that can contaminate ground, groundwater and water column (-)

M L H M H L • Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Staff that will be handling hazardous materials must be trained to do so. Hazardous Chemical Substances Regulations promulgated in terms of the Occupational Health and Safety Act 85 of 1993 and the SABS Code of Practise must be adhered to. This applies to solvents and other chemicals possibly used in the construction time.

• Depending on the nature and extent of the spill, contaminated soil must be either excavated and disposed of at a hazardous waste disposal or treated on-site.

• The ECO must determine the precise method of treatment of polluted soil.

• This could involve the application of soil absorbent materials or oil-digestive powders to the contaminated soil.

• If a spill occurs on an impermeable surface such as cement or

Page 57: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

57

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

concrete, the surface spill must be contained using oil-absorbent materials.

• Contaminated remediation materials must be carefully removed from the area of the spill so as to prevent further release of petrochemicals into the environment, and stored in adequate containers until appropriate disposal.

Inappropriate responses to petrochemical or hazardous spill (-)

M L M M M L • The individual responsible for or who discovers the petrochemical spill must report the incident to the Project Coordinator, ECO and/or Contractor as soon as reasonably possible.

• The problem must be assessed and the necessary actions required will be undertaken.

• The immediate response must be to contain the spill.

On-site contamination of soil during concrete mixing (-)

M S M M M L • No vehicles transporting concrete to the site may be washed on site. • If a batching plant is necessary, batching is to take place on an

impermeable surface and run-off should be managed effectively to avoid contamination of other areas of the site.

FIRE MANAGEMENT

Inadequate attention to fire safety awareness and fire safety equipment could result in unsafe working environments and surrounding agricultural activities (-)

M L M M M L • Fire-fighting equipment should be present on site at all times as per Occupational Health and Safety Act.

• All construction staff must be trained in fire hazard control and fire-fighting techniques.

• All flammable substances must be stored in dry areas which do not pose an ignition risk.

• No open fires will be allowed on site unless in a demarcated area identified by the ECO.

• Smoking may only be conducted in demarcated areas as agreed upon by the ECO and contractor.

Fires created within the construction sites may result in runaway veldfires (-)

M M L M M L • All cooking will be done in demarcated areas that are safe in terms of runaway or uncontrolled fires

• The Contractor will have operational fire-fighting equipment available on site at all times. The level of fire-fighting equipment must be assessed and evaluated through a typical risk assessment process. It may be required to increase the level of protection, especially during the winter months.

PROVISION OF PORTABLE

Failure to provide adequate on-site sanitation and clean drinking water may result in run-off

M M M M H L • Adequate sanitary and ablutions facilities must be provided for construction workers.

Page 58: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

58

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

TOILETS transferring contaminants into the surrounding environment (-)

• The facilities must be regularly serviced to reduce the risk of surface or groundwater pollution.

• Toilet facilities must be available within waliking distance of all working areas.

• Contaminated wastewater must be managed by the Contractor to ensure existing water resources on the site are not contaminated. All wastewater from general activities in the camp will be collected and removed from the site for appropriate disposal at a licensed commercial facility.

NOISE

Excessive noise pollution from the construction sites may impact the surrounding environment (-)

L L M H M L • Heavy vehicle traffic should be routed away from noise-sensitive areas, where possible.

• Noise levels must be kept within acceptable limits. All noise and sounds generated must adhere to SABS 0103 specifications for maximum allowable noise levels for residential areas. No pure tone sirens or hooters may be utilised except where required in terms of SABS standards or in emergencies.

• Noisy activities to take place during allocated construction hours only as per Section 25 of the Noise Control Regulations of the Environment Conservation Act, 1989 (Act No. 73 of 1989).

BUILDING RUBBLE Construction rubble left on-site may attract vermin and encourage the growth of opportunistic alien vegetation (-)

M L M M M L • Construction rubble will be disposed of in pre–agreed, demarcated spoil dumps that have been approved by the relevant Municipality.

AIR QUALITY Reduction in air quality as a result of construction activities (-)

M L L M M L • All vehicles and equipment are to be maintained in an acceptable condition. Vehicles are to maintain vehicle speed limits to avoid dust generation. Dust suppression measures need to be implemented on site when necessary to reduce the dust impacts.

FAUNA Poaching of animals in the vegetation (-)

M L L M M L • No poaching of fauna is allowed.

Temporary emigration of animals out of construction area (-)

L L L M L L • No mitigation. Short term nature of the project and rehabilitation of disturbed areas

INFRASTRUCTURE Damage to roads by construction vehicles (-) M L H M M L • Construction vehicles are to maintain vehicle speed limits and are to

only utilise roads approved by the Engineer or ECO.

TRAFFIC Increase in traffic due to construction vehicles (-)

M L M M M M • Construction vehicles to utilised roads approved by the Engineer or ECO.

CULTURAL HERITAGE

Cultural, heritage and palaeontological artefacts may be uncovered during the course

M S H M M L • Continued care should be taken to observe any sites of heritage significance during operation. Should any archaeological artefacts

Page 59: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

59

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

of the construction site establishment, pylon excavations, etc. (-)

and palaeontological remains be exposed during operations, work on the area where the artefacts were found will cease immediately and the appropriate person will be notified as soon as possible.

• Any discovered artefacts will not be removed under any circumstances. Any destruction of a site can only be allowed once a permit is obtained from SAHRA and the site has been mapped and noted.

• Under no circumstances will archaeological or palaeontological artefacts be removed, destroyed or interfered with by anyone on the site during operations.

• That tower placements should be negotiated with residents to ensure that no ancestral graves are affected.

• The operator will advise its workers of the penalties associated with the unlawful removal of cultural, historical, archaeological or palaeontological artefacts, as set out in the National Heritage Resources Act (Act No. 25 of 1999), Section 51(1)

VEGETATION

Ineffective vegetation rehabilitation measures could result in excessive soil erosion and encroachment of alien vegetation (-)

M M H M M L • The rehabilitation of the trenches and disturbed areas around the power line must be done with indigenous grasses local to the area and that require minimal horticultural maintenance.

• All weeds and invasive vegetation should be eradicated over a five year period.

• Indigenous forest areas are to be completely avoided by the powerline and labour teams.

• Vehicle and machinery movement in and around the river crossing and grassland should be kept to a minimum.

• As little as possible of the natural vegetation should be removed for the purpose of construction.

OPERATIONAL PHASE POWER SUPPLY Provision of uninterrupted power supply (+) M R H H N/A N/A • No mitigation required.

ACCESS CONTROL Uncontrolled access to the power line servitude may result in safety hazards

M L H M M L • Access to the power line servitude must be restricted. Ideally this should be done by fencing off and gating along the main access roads.

LINE MAINTENANCE

Non-compliance to a power line maintenance schedule would result in the line becoming overgrown and perhaps incurring damage (-)

M R M M M L • Regular inspection of the power line must take place to monitor its operational status.

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

Page 60: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

60

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

FAUNA

The impact on habitats or on fauna directly (bird collisions and electrocutions) causing loss of species diversity. Bird collisions likely to have the highest impact (-)

M S LT M M L • Adhere to Eskom guidelines for construction. • Bird perching brackets are to be used on every powerline pole. • High risk section of the powerline as identified in the Avifaunal

Specialist report must be fitted with suitable Eskom approved anti-bird collision line marking devices on the earth wire to increase visibility of the cables.

• Once the exact tower positions are surveyed and finalised, an avifaunal walk-through must done on the line, thus identifying the exact spans of powerline requiring mitigation.

• Indigenous forest areas are to be completely avoided by the powerline and labour teams.

• Vehicle and machinery movement in and around the river crossing and grassland should be kept to a minimum.

SOCIO-ECONOMIC IMPACTS

The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply (+)

M R M H N/A N/A • No mitigation required.

Consideration of local workforce will stimulate the local economy (+)

M L H H N/A N/A • No mitigation required.

Failure to maintain powerline and servitudes may lead to veld fires (-)

M L M M H M • Regular inspection of the power line must take place to monitor its operational status.

• Once built and commissioned, periodic maintenance will be undertaken repairing faults, and broken infrastructure.

Loss of land with registration of a permanent servitude (-)

M L H M M M • No mitigation

Loss of ‘sense of place’ (-) M L H M M L • The guyed monopole structures are designed such to have to lease

visual impact on the environment. The impact of power provision on the socio-economic structure of the region. Improved reliability of power supply. (+)

M L L H N/A N/A • No mitigation required.

Contribution to densification of the area. (-/+) M L L M M M • Ensure all development takes place in accordance with relevant

policies and guidelines.

NO-GO ALTERNATIVE Landscape remains as is M L M M N/A N/A N/A No additional job opportunities created M L M M H L • Construct proposed power line.

Page 61: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

61

Environment Description of Environmental Impact

Criteria

Significance

Mitigation Measure

Inte

nsity

Spa

tial S

cale

Dur

atio

n

Pro

babi

lity

With

out

Miti

gatio

n

With

Miti

gatio

n

Vegetation remains intact, however erosion due to grazing might occur (-)

M L M M M L N/A

No construction associated risks (fires, spills of hazardous materials etc.) (+)

L L N/A

M N/A N/A N/A

Site may become overrun by invasive plant species due to grazing (-)

M L M M M L N/A

No impact on air quality (+) L L N/A

M N/A N/A N/A

No contribution to infrastructure and economic development of the area (-)

M M M M H L • Construct proposed power line.

Overloading of other substations and powerline may result in voltage collapse problems and impact on provision of electricity in the area (-)

H M M H H L • Construct proposed power line.

Page 62: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

62

SECTION E. RECOMMENDATION OF PRACTITIONER

Is the information contained in this report and the documentation attached hereto sufficient to make a decision in respect of the activity applied for (in the view of the Environmental Assessment Practitioner)?

YES �

NO

If “NO”, indicate the aspects that should be assessed further as part of a Scoping and EIA process before a decision can be made (list the aspects that require further assessment):

N/A

If “YES”, please list any recommended conditions, including mitigation measures that should be considered for inclusion in any authorisation that may be granted by the competent authority in respect of the application:

• All mitigation measures proposed in the report form part of the EMPr and adherence to the specifications of the EMPr should form part of the conditions of the environmental authorisation, should this be granted

• An Independent Environmental Control Officer (ECO) must be appointed for the construction of the proposed development to monitor compliance to EMPr

• The EMPr must be adhered to by the contractor under, the supervision of the engineer and an ECO.

• the ECO audits must include: � A monthly compliance audit - with the first audit being conducted no later than

one month after construction commences on site; and � A post construction (rehabilitation) compliance audit is to be conducted no

later than two weeks before the contractor hands over the completed project. • Pylons are to be fitted with perching brackets and the sensitive areas identified in the

avifaunal report. • Valley areas including the river crossing, should be marked with suitable anti-collision

marking devices. • An avifaunal walk-through should be undertaken once the exact tower positions are

surveyed and finalised. • Indigenous forest areas are to be completely avoided by the powerline and labour teams. • Soils compacted by construction activities are to be ripped. • Topsoil is to be stripped from all areas affected by construction and related activities prior

to the commencement of major earthworks and conserved for rehabilitation. • Should any archaeological or palaeontological remains be exposed during operations,

work on the area where the artefacts were found must cease immediately and the appropriate specialist will be notified as soon as possible.

In the opinion of the Environmental Practitioner, the proposed activity is not fatally flawed and all potential impacts can be mitigated to an acceptable level. As such, it is recommended that the proposed construction of the power line continue if all recommendations and mitigation measures are followed.

Is an EMPr attached?

YES �

NO

The EMPr must be attached as Appendix F.

Page 63: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

63

SECTION F: APPENDIXES The following appendixes must be attached as appropriate: Appendix A: Site Plan(s) Appendix B: Photographs Appendix C: Facility Illustration(s) Appendix D: Specialist Reports Appendix E: Comments and Responses Report Appendix F: Environmental Management Programme (EMPr) Appendix G: Other Information

Page 64: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

64

APPENDIX A: SITE PLAN(S)

Page 65: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

65

Plan A1: Locality Plan of Dumasi-Tombo-Mafini 132 k V Route and Tombo substation

Page 66: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

66

Plan A2: Plan of Tombo-Mafini 132 kV Route to the l eft and previously authorised Dumasi-Tombo 132 kV R oute to the right.

Page 67: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

67

Plan A3: Plan A2: Plan of Tombo-Mafini 132 kV Route to the left and previously authorised Dumasi-Tombo 132 kV Route to the right.

Page 68: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

68

APPENDIX B: PHOTOGRAPHS

Page 69: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

69

Figure A: 360° view from the central point of Alternative Site 1

NORTH WEST

NORTH

NORTH EAST

WEST

CENTRE

EAST

SOUTH WEST

SOUTH

SOUTH EAST

Page 70: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

70

APPENDIX C: FACILITY ILLUSTRATION(S)

Page 71: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

71

Figure C1: Design of the single steel pole structur e

Page 72: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

72

Figure C2: Design of the cross arm

Page 73: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

73

Figure C3: Design of the cross arm

Page 74: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

74

Figure C4: Design of the suspension cross arm assem bly

Page 75: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

75

APPENDIX D: SPECIALIST REPORTS

Page 76: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

76

APPENDIX E: COMMENT AND RESPONSES REPORT

PUBLIC PARTICIPATION The purpose of involvement of Stakeholders and Interested and Affected Parties (I&APs) is to allow them to voice their opinions and concerns of the proposed project. Such engagement is critical as it contributes to a better understanding of the proposed project among I&APs, and raises important issues that need to be assessed in the EIA process. There are four key steps within the overall public participation process. These include - • Notifying I&APs of the EIA; • Holding public and focus group meetings; • Making provision for I&APs to review and comment on all reports before they are finalised and

submitted to the competent authority; and • Making a record of responses to comments and concerns available to I&APs. Prior to the preparation of this Draft Basic Assessment Report (BAR), the above steps have comprised the activities described in Sections below. This Draft BAR will be made available for inspection by all registered I&APs for a period of 30 days. The draft report will be available at strategic places that are easily accessible by the public, such as public libraries and community centres. Comments received will be considered, and necessary changes made to the draft before it is submitted for review to the competent authority as the final BAR. Comments received from I&APs during the review period will be recorded, responses will be prepared, and a record of comments and responses will be maintained.

In terms of the EIA Regulations (2 010), PPP is required to provide: Details of the public participation process conducted, including: (a) fixing a noticeboard at a place conspicuous to the public at the boundary or on the fence

of— (i) the site where the activity to which the application relates is or is to be undertaken; and (ii) any alternative site mentioned in the application;

(b) giving written notice to— (i) the owner or person in control of that land if the applicant is not the owner or

person in control of the land; (ii) the occupiers of the site where the activity is or is to be undertaken or to any

alternative site where the activity is to be undertaken; (iii) owners and occupiers of land adjacent to the site where the activity is or is to be

undertaken or to any alternative site where the activity is to be undertaken; (iv) the municipal councillor of the ward in which the site or alternative site is situated

and any organisation of ratepayers that represent the community in the area; (v) the municipality which has jurisdiction in the area; (vi) any organ of state having jurisdiction in respect of any aspect of the activity; and (vii) any other party as required by the competent authority;

(c) placing an advertisement in— (i) one local newspaper; or and affected parties;

Page 77: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

Notifying Interested and Affected P Newspaper Advertisement The proposed activity was advertised in the Daily Dispatch on advertisement detailed the proposed development and provided Interested & Affected Parties (I&APs) 30 days to register.

Figure E1 : Newspaper advertisement placed in the D

BASIC ASSESSMENT REPORT

Notifying Interested and Affected P arties of the EIA

tivity was advertised in the Daily Dispatch on 17 March 2011 advertisement detailed the proposed development and provided Interested & Affected Parties (I&APs)

: Newspaper advertisement placed in the D aily Dispatch

77

(Figure below). This advertisement detailed the proposed development and provided Interested & Affected Parties (I&APs)

Page 78: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

78

On-Site Notice The NEMA regulations require the erection of a “notice board at a place conspicuous to the public at the boundary or on the fence of the site where the activity to which the application relates is or is to be undertaken; and any alternative site mentioned in the application”. Noticeboards was placed on-site at both the take-off point (Cibeni) and at the end point (Tombo) (Figure E2). The on-site notices are clearly visible and will remain in situ for the duration of the EIA process.

Figure E2: On-site Notice

Page 79: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

79

6.1.3 Stakeholder Identification and Notification In addition to the above notification, certain stakeholders were identified based on their potential interest in the project (Table 1). These organisations were contacted directly for comment and were sent a Letter of Notification (Figure E3) and a Background Information Document - BID (Figure E9) via email correspondence (Figures E4 to E8).

Page 80: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

80

Figure E3: Notification sent to SAHRA, DEDEAT, ESKO M, PSJ Local Municipality, Nyandeni Local Municipality, O.R. Tambo District Municipalit y and DRD&LR.

Figure E4: E-mail notification sent to the Nyandeni Local Municipality and the DEDEAT.

Figure E5: E-mail notification sent to the Department of Economic Development, Environmental Affairs and Tourism.

Figure E6: E-mail notification sent to the Port St Johns Local Municipality.

Figure E7: E-mail notification sent to the O.R. Tambo District Municipality.

Page 81: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

81

Figure E8: E-mail notification sent to the Department of Land Affairs.

Page 82: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

82

Table 1: List of Participating Stakeholders

Interested & Affected Party Database Eskom Tombo-Mafini Basic Assessment

COMPANY TITLE

FIRST NAME

SURNAME POSITION CONTACT NO CELLPHONE

NO EMAIL NOTIFICATION SENT

KEY STAKEHOLDERS (e.g. authorities)

Cibeni Village Mr Mtobela Ward Councilor 0828563875

Cibeni Village Mr N Ndamase Chief 083742 5849

Mantusini & Ntsimbini Village Ms Tshitshiliza Ward Councilor 0825645230

Mantusini Village Mr Jabavu Nompandana Chief 0828665178

Ntsimbini Village Mr Sivuyile Msungubali Chief 0710903716

Tombo Village Ms Mtuku Ward Councilor 0825072283/ 0825648982

Tombo Village Mr Z Langa Chief 0828326931

Department of Rural Affairs and Land Reform (officer: Nobantu Lande)

Mr Vuyisa Mdlalo-Sifanele 047 532 5959 [email protected] Sent via emial on the 02/05/2012

Port Saint Johns Municipality Mr Sopela Engineering Manager 047 564 1159 [email protected]

Sent via emial on the 02/05/2012

Dept of Economic Development, Environmental Affairs and Tourism

Mr Qondile Paliso 047 531 1191 [email protected]

Sent via emial on the 02/05/2012

Nyandeni Local Municipality Mr Mandlenkosi

Zide Acting Municipal Manager

(047) 555 0161 [email protected]

Sent via emial on the 02/05/2012

SAHRA Dr. Mariagrazia Galimberti

Archaeology, Palaeontology and Meteorites Unit

[email protected] Sent via Emial on the

08/02/2012

O.R. Tambo District Municipality Mr Siya Busi

047 505 1721 [email protected]

Sent via emial on the 02/05/2012

Adjacent Landowners

Refer to above

GENERAL PUBLIC (all other I&APs)

Indwe Environmental Consulting Mr Brendon Steytler Director and owner 043 735 1890 083 766 7514 [email protected]

Page 83: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

83

Page 84: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

84

Figure E9: Background Information Docu ment

Page 85: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

85

Surrounding and Affected Landowners The Department of Rural Development and Land Reform together with the councillors of the relevant villages were provided a Letter of Notification (Figure E10) and BID (Figure E9). The community themselves were notified during Public Meetings in the relevant areas. A Community Resolution was obtained and forms part of Appendix G.

Figure E10: Landowner Notification

Page 86: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

86

Registered I&APs Since the start of the process, a register of I&APs containing all available contact details of those who responded to the advertisement etc. has been compiled and maintained. I&APs were notified by providing them with a Letter of Notification (Figure E5), a BID (Figure E4), Site Notices (Figure E2) and the Newspaper advertisement (Figure E1). Other than the I&APs initially identified, any person requesting to be registered as an I&AP was included into the I&AP database. No written comments were, however, received from any I&APs. Complete I&AP Database The complete I&AP Database is provided in Table 1. Public Meeting A public meeting was held by ESKOM at the villages of Cibeni, Tombo, Mantusini and Ntsimbini as part of the Community Resolution Process. The details of the project as well as contact personal were identified and any issues or comments recorded. The community resolution can be found within Appendix G.

Page 87: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

87

APPENDIX F: ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr)

Page 88: BASIC ASSESSMENT REPORT - GIBBprojects.gibb.co.za/Portals/3/projects/201208 Eskom Tombo Mafini... · Basic assessment report in terms of the Environmental Impact Assessment Regulations,

BASIC ASSESSMENT REPORT

88

APPENDIX G: OTHER INFORMATION

• Dumasi-Tombo 132 kV powerline Environmental Authorisation

• Community Resolution

• Powerline Co-ordinates