banana project final
TRANSCRIPT
-
8/2/2019 Banana Project Final
1/21
LAKE VICTORIA ENVIROMENTAL MANAGEMENT
PROGRAMME (LVEMP II)
PROJECT TITLE: IMPROVEMENT OF FISH HANDLING
ENVIRONMENT AT BANANA FISH LANDING SITE
DURATION: 12 months
CBO NAME: Banana Beach Management Unit.
ADDRESS: PO Box 760 -40300 Homa Bay.
Tel: O723567848/0722116667
EMAIL: [email protected]
CONTACT PERSON: Charles Osir/ Washington Osoo
-
8/2/2019 Banana Project Final
2/21
PRIORITY AREA: Control of Soil Erosion and Improving
Sanitation and Hygiene along the Lake.
EXECUTIVE SUMMARY
Environmental degradation has taken a major course in Kanam Location.
This has been catalyzed by poor farming methods and runoff water
escalated by the topography. This has lead to soil erosion which has
polluted the lake because deposits are been carried to lake. Soil erosion has
led to lake siltation that make lake shore not conducive for fish breeding
thus decrease in fish stocks. This has made the community around
economically inactive.
To address this problem community participation is a paramount approach
to improve the situation. Through capacity building and awareness creation
on lake pollution interventions, issues at hand can be streamlined. Control
of soil erosion reduces lake siltation and prevents the lake from being
polluted by farm chemical being used by horticulture farmers. Construction
of environment friendly toilets and fish Banda will improve sanitation and
hygiene along the lake. Roof top water harvesting will reduce the quantity
and speed of run off water thus reduces soil erosion. Add something on
reforestation and building of gabions.
The expected outcome of this project is realization of environment free from
pollution especially Lake Victoria. Clean and clear water guarantees good
-
8/2/2019 Banana Project Final
3/21
ACRONYMS
BMU- Beach Management UnitBBMU- Banana Beach Management UnitHOPANET- HOMA HILLS PARALEGAL NETWORKIFAD- International Fund for Agricultural DevelopmentGOK- GOVERNMENT OF KENYA
LVFO- Lake Victoria Fisheries OrganizationGEMANET Gender Mainstreaming NetworksCBO- Community Based Organization
-
8/2/2019 Banana Project Final
4/21
TABLE OF CONTENT
EXECUTIVE SUMMARY ..................................................................................... 2
ACRONYMS ..................................................................................................... 3
INTRODUCTION ............................................................................................... 5
2. BACKGROUND ............................................................................................. 62.1. STATEMENTOFTHEPROBLEM....................................................................................................6
2.2. CURRENTSITUATION.............................................................................................................7
2.3. JUSTIFICATION......................................................................................................................7
3. STAKE HOLDER ANALYSIS ........................................................................... 8
4. PROBLEM TREE .......................................................................................... 10
5. OBJECTIVE TREE ........................................................................................ 10
6. ALTERNATIVE/STRATEGY ANALYSIS ............................................................. 11
7. OBJECTIVES ............................................................................................... 12
-
8/2/2019 Banana Project Final
5/21
INTRODUCTION
Banana beach was formed in the year 2001 and registered under Ministry of
Home Affairs, Heritage and Sports , Department of Social Services in the
year 2004 Holding a Certificate of Registration number 1284/2004 underSelf Help Project known as Banana Beach Self Help Group. The Banana
Beach became a Beach Management Unit after qualifying under National
Beach Management Guidelines in the year 2006 and holds BMUs certificate
of registration number FISH/ BMU/REG.NO-121/2011.BMUs are community-
based legally-recognized fisheries management organizations, registered
with Fisheries Department. BMUs have been formed all around Lake Victoria
so that fishing communities manage fisheries resources and protectenvironment with government and other stakeholders.
Banana Beach Management Unit is situated in Homa Bay County, West
Karachuonyo Division, and Kanam A Location, Kowuor Sub-Location. The
BMU was formed to address issues of un-employment among the people
within the locality, Co-Manage fisher resource, improve hygiene and
sanitation, environmental conservation and awareness on health anddevelopment issues among the catchment area community. To address
these issues the BMU has undertaken various activities which includes
C d i M i i d S ill i h l k b i
-
8/2/2019 Banana Project Final
6/21
iv. Southern Nyanza Community Development Organization Project
(GOK/IFAD)- on training on Horticulture
v. Homa Hills Community Development Organization- on
Community managed micro-finance (SILCs methodology),toilet
construction, financial management training, gender and
HIV/AIDS awareness campaigns
vi. World Vision PALA IPA- on Community Home Based Care and
roof top water harvesting.
vii. Provincial Administration-Security within the beach and Lake.
Banana Beach Management Unit is a member of the Beach Management
Unit network which promotes equity and justice between BMUs. A BMU
Network is a grouping of all BMUs or lower BMU Networks within a defined
administrative area formed from Location, division, district, provincial,
National to regional level. BBMU has also set networks HOPANET (Homa hills
Paralegal Network), GEMANET (Gender Mainstreaming Networks) and other
CBOs.
2. BACKGROUND
2.1. Statement of the problem.
Environmental degradation has taken a major course in Kanam Location.
This has been catalyzed by i) poor farming methods; ii) excessive run off
water escalated by Homa Hills of which charcoal dealers and subsistence
-
8/2/2019 Banana Project Final
7/21
The effects of lake pollution reduces the economic strength of the
community. This makes the community poverty level to be high due to
these human activities.
2.2. Current situation.
Homa hills degradation and topography has lead to soil erosion which has
brought the emergence of gullies and Lake Siltation, soil fertility has
reduced, hence low crop production. Lake pollution has lead to decline of
fish stocks and baits, water borne diseases are being experienced due to
animal and human excretes being deposited in the lake during rainy
season, due to lack of enough toilets of which contaminates water and the
same water is used for domestic purposes. Horticulture has encouraged use
of chemicals along the lake of which when farmers water their plants using
water pump the same water containing chemicals find its way back to the
lake. Lack of wood fuel for domestic purposes has also resulted in mass
destruction of the few available tree cover. Unfinished fish landing Bandaand unfenced beach has lead to low income and health hazard to the BBMU
members and the community around.
2.3. Justification.
The effects of lake pollution have made the living standard of Kanam
community unbearable hence justifying the importance project. In order to
address these challenges it is essential to intervene with possible strategiesso as to improve the conditions hence improve the livelihood of the
members and community. The beach management unit has managed to
-
8/2/2019 Banana Project Final
8/21
All these interventions are geared towards the realization of the Vision 2030
in attaining better livelihood.
3. STAKE HOLDER ANALYSIS
Stakeholder Their interests in theproject
Importance
Fishers To increase fish catches 4Agricultural farmers To continue farming 3
Environmental activists To conserve environment 3Consumers To eat more fish at affordable
prices4
Traders To get more profits 4Processing plants To process more fish 4Local authorities To achieve better
management of the resource3
Local GovernmentAdministration
To ensure law and order arefollowed
3
Fishing gear manufacturers To sale more fishing gears 4Universities and researchinstitutions
To understand thecharacteristics of the fishery
4
Fisheries officers Sustainable utilization of thefisheries resource
4
National Environment
Management Authority
Protection and conservation
of fisheries resources
4
Political leaders To maintain their politicalsupport
3
NGOs Will oppose the project 2
-
8/2/2019 Banana Project Final
9/21
-
8/2/2019 Banana Project Final
10/21
4. PROBLEM TREE
-
8/2/2019 Banana Project Final
11/21
6. ALTERNATIVE/STRATEGY ANALYSIS
Step 1: Listing of objectives
1. Constructing gabions and terraces
2. Planting trees
3. Training on good farming practices
4. Awareness creation
5. Water harvesting
6. Environmental friendly toilets
7. Construction of fish landing site
Step 2: Clustering of Objectives
Cluster one
Constructing gabions and terraces
Planting trees
Cluster two
-
8/2/2019 Banana Project Final
12/21
project. This will help in comprehensively addressing the environmental
problems bedeviling the Banana beach community.
7. OBJECTIVES
1.1 To control lake pollution in Kanam A by 2012, through
a) By planting 10,000 seedlings
b) Constructing gabions
c) Building stones and Napier grass terraces.
d) Erecting roof top water harvesting tanks.
1.2 To construct 20 ecosan toilets in Kanam A community by 2012.
1.3 To fence, complete fish Banda and erect 2 green houses by 2012.
8. METHODOLOGY
-
8/2/2019 Banana Project Final
13/21
i. Community participation- BBMU will develop Community Action
Plans in consultation with the community members, agricultural
officers, forestry officers, NEMA personnel and stakeholders soas to make the implementation participatory approach.
ii. Procurement- all procurement will be done as per the agreed
terms and conditions by all stakeholders.
iii. Implementation- the process will start by identifying key areas
to plant trees. Schools and churches compound will be givenfirst priority. The community will take part in building of
gabions, terraces and good land tilting methods. Agricultural
officers and ministry of forest will provide technical assistance.
Objective 2: To construct 20 ecosan toilets in Kanam community by
2012.
Procedures- The following activities will take place
i. Community participation: BBMU incorporation with ministry of public
health will engage the community in developing community action
plan.
ii. Procurement: all procurements will be done according to terms and
conditions laid down in action plans in consultation with otherstakeholders.
iii Implementation: the implementation will start by identifying artisans
-
8/2/2019 Banana Project Final
14/21
iii. Implementation: Being a livelihood project, BBMU members and
community members with artisanal expertise will be part of the
implementation team; ministry of public works and ministry offisheries will offer technical assistance during implementation.
MONITORING AND EVALUATION
Banana beach management unit will use participatory Monitoring and
Evaluation approach where all stakeholders will be involved. Evaluation will
be done periodically so as to establish progress of planned targets and goals
so as to asses effects and impact of resources consumed. The information
gathered will be used to make informed decision to renew the energy in the
project momentum with an opportunity to meet the indicators provided in
logical framework matrix. The reporting tools developed by LVEMP II will be
periodically shared with District Project Coordination Team (DPCT) and all
stakeholders.
10. INSTITUTIONAL CAPACITY
10.1. Organizational Management capacity
Banana Beach Management Unit project executive committee comprises of
development focused members who have shown leadership skills. Three
leaders i.e. the chairperson, secretary and treasurer have all undergone
leadership training, financial management training and management offisher resources training. One member holds a diploma in community
development and project management and has undergone various resource
mobilization trainings One member is an accountant by profession
-
8/2/2019 Banana Project Final
15/21
10.2. Organizational structure / chart
Banana Beach Management Unit has a Management Committee, Assembly
and Sub Committee. BMU committee comprises of nine members and made
up of chairperson, assistant chairperson, secretary, assistant secretary,
treasurer and four committee members. The work of the BMU committee is
to keep all BMU records, draft and implement decision approved by BMUAssembly. The BMU Assembly is the highest decision making organ. The sub
committees are in charge of implementing activities approved by Assembly
b h lf f BMU itt
-
8/2/2019 Banana Project Final
16/21
The current and planned collaboration are as follows:
Ministry of health technical advice in establishing goodhygiene.
Ministry of agriculture technical advice in adopting best
farming methods and land use.
Ministry of fisheries network on management of fisher
resources.
SNCDP/ IFAD/GOK assist in developing in irrigation.
NEMA assist in environmental management along the
lake.
World vision training on water harvesting techniques.
Ministry of public works technical advice during
completion of construction beach Banda.
Provincial administration community mobilization and
linkage with other stakeholder.
ACCOUNTING CAPACITY
BBMU holds functional bank account with Co-operative bank of Kenya
Homa-Bay branch. The CBO has financial records which allow transparency
and accountability. The signatory to the bank account are the chairperson,
-
8/2/2019 Banana Project Final
17/21
support and linkages with other funding arrangements and
interventions.
c) Through capacity building, the knowledge gained by members will be
transferred to community for continuity in the absences of donor
funding.
d) Service fee collected from fishing activities will be pumped back to the
project to sustain various activities.
e) Revenue collected from the sale of produce from green house will be
ploughed back to the project for sustainability.
EXPECTED OUTPUT/ RESULTS
Training farmers on good farming methods will improve soil fertility, free
lakes pollution from agricultural chemicals used in horticulture, and reducelake siltation due run off water from irrigation pumps and rain water all
these will mean increased farm yields and fish catch in that baits will be now
available.
1. Controlled soil erosion will reduce Lake Siltation, improve soil fertility
hence increase crop production this will translate to improved living
standard.
2. Constructed of environmental friendly toilets will reduce water borne
diseases hence impro ed health of members and comm nit
-
8/2/2019 Banana Project Final
18/21
PROJECT PLANNING MATRIX/LOGICAL FRAMEWORK
OBJECTIVES OBJECTIVELY VARIFIABLEINDICATORS
MEANS OF VARIFICATIONS ASSUMPTION/EXTERNAL FACTORS
Development ObjectiveImproved livelihood of Kanamcommunity
Impact indicators-Sustainable fish catch-High crop yields-clean and safe water-good hygiene and reducedwaterborne diseases
-project reports-Interviews and observationvisits
-Controlled soil erosion-controlled lake pollution-community participation-stakeholders good will.
Core objectiveControlled lake pollution
Outcome indicators-improved tree /vegetativecover in the area-Clean and clear lake water-Reduced lake siltation-enhanced fish catch-improved hygiene and
sanitation-reduced soil erosion
-Project reports-interviews and observationvisits-healing gullies-clean and clear lake water.
-Enhanced afforestation- provision of sustainable livelihood-Improved hygiene and sanitation.
Project out putAfforestation in the areaWater harvesting andinventory system
Alternative livelihood strategy
Out put indicators10,000 trees planted within thecommunity-availability 20 erected watertanks-Availability of 20 constructedtoilets-Availability of fenced andcompleted fish Banda-sustainable fish catch-functioning green house
-project reports-project concept-observation visit-liquidation documents.
-Planting of 10,000 trees-Erected water tanks-constructed environmental friendlytoilets.-Completed and fenced fish Banda
Project ActivitiesPlanting of treesBuilding gabionsErecting water tanksTraining farmers on greenhouse use farmingCompletion and fencing of fishBandaConstruction of environmentalfriendly toilets.
Activity indicators-Liquidation reports anddocuments-Project completion reports
-Availability of funds-Availability of materials.
18
-
8/2/2019 Banana Project Final
19/21
11. WORK PLAN AND BUDGET
19
No Sub project Main activity(s) particulars uni No of Amo Total Comm LVEMP Responsible
-
8/2/2019 Banana Project Final
20/21
20
objective (s) ts units untperunit
estimatecost
unitycontribution
persons
1 Toreforestation
i)Training offarmers
Facilitatorstransport
No 12 3000 36,000
36,000 BBBMU members,community,Agricultural officers,ministry of forestry,ministry of fisheries,ministry of publicworks (DPCT)
Note books No 25 30 750 750Pens No 25 15 375 375Flip chart No 10 300 3,000 3,000Marker pen box
es3 300 900 900
SUB TOTAL41,025
41,025
ii)setting upgreen house
no 2 25000
500,000
500,000
SUB TOTAL 500,000
iii)planting of
tree seedlings
Assorted
seedlings
No 10,00
0
30 300,0
00
300,000
Transport Trip 2 30,000
60,000
60,000
labor holes
10,000
10 100,000
100,000
SUB TOTAL 460,000
100,000
360,000
iv)Buildinggabions andterraces
Chain links Rolls
40 5000 200,000
200,000
hardcore Ton 50 10000
500,000
500,000
Cider poles No 200 320 64,00
0
64,000
Round poles No 100 150 15,000
15,000
u-nail Kgs 30 200 6,000 6,000
Nails Kgs 20 200 800 800Pangas No 20 300 6,000 6,000Jembes No 20 500 10,00
010,000
Wheel barrows No 10 3500 35,000
35,000
Spades No 10 600 6,000 6,000
Transport Trip 3 12000
36,000
36,000
labor No 60 2000 120,000
120,000
998,8
-
8/2/2019 Banana Project Final
21/21
Total project cost Ksh4, 838,675. Amount requested for Ksh3, 487,075. Community participation Ksh1, 351,600.