balance work at ir-22.03.15
DESCRIPTION
balance worksTRANSCRIPT
Sheet1PENDING WORKS AT INDORAMA as on 22.03.2015INTERFACE
PIPINGAREADETAILS OF ACTIVITIESSTATUSCONSTRAINTSN0. of working days
for 01 gangCompletion date1BG & PG lines1.Hydrotest of PG line
is balance (30 Mtr)2.Card board blasting of PG3. Final painting
balance for 3 joints of valve shifting1. Hydrotest completed -
26.03.20152. Cardboadr blasting of PG line shall be done after 14"
relocation job3. painting shall be done after acceptance of
RTPainting contractor is not coming to site.430.03.15Packing plates
are balance at few locations in both BG & PG lineswork In
progress 730.03.152PP area5 nos of Guide supports are balance for
DM water lineScofolding work for prepartion of access in
progressshall be commenced on 23.03.2015 completed on
23.03.15123.03.153PE plant - Hydrogen linesFinal painting balance
in PE & olefins areaScofolding done & ready for
painting;Painting contractor is not coming to site.24NG Skid
erection/ Power PlantInstallation of foundation bolts &
grouting of NG skidshall be done after increasing the size of base
plate hole130.03.151" Flare line - Fabrication/ erection
balanceshall be done after mobilzing gang to Powerplant areato be
commenced from 25.03.15329.03.153/4" Instrument air lineSupporting
clamping balanceMaterial to be arranged by Indorama125.03.15 1"
steam lineReducer installation & supporting balanceMaterial to
be arranged by Indorama126.03.156" Flare linePenumatic testing to
be done after connecting 1" flare line130.03.1502 nos strcuturals
support to be installed in 6"-FG lineSupports are ready; completed
on 24.03.2015125.03.155Cooling towermonkey ladder
erectionAdditional work102.04.15Guide supports at 1 location
balance102.04.156DM Plant/ Fire water pumpFinal allignment
balanceto be done after replacing inlet valvesvalve replacement to
be done; valve under procurement1Piping hydrorest , final painting
balalnceGrouting for fire water pumps- 3nos balanceIn
progress325.03.15Footings & strurctural supports after piping
erectionin progress430.03.15Installation of silencer & Exhaust
pipingScheme not finalized by Indorama32" & 1/2" diesel line -
100 Mtrscommenced on 23.03.15Extra work & Shutdown reqd. from
Indorama47Holding pond areaCivil works for valve housingAdditional
work28Nitrogen PlantNitrogen line Tie-in with exisitng lineLine
ready; waiting for shut-downshut-down planned on
24.03.2015124.03.15
Admin: Admin:Rescheduled to next weekInstallation of FT in
Instrument air lineMaterial not reced. By Indorama19Borewell
lines6" lines with 6" x 10 " reducer - 50 mtrs approx , 50 joints
approxTo be done after completion of borewell activities410" lines
at Borewell 5- 18 mtrs2Civil works for footings - 10 nos
approx4