automated boiler wall cleaning and inspection
TRANSCRIPT
Abstract — Power plant boilers need to be cleaned and
inspected on a regular basis. Boiler chambers can be up to 50m
high requiring scaffolding for all works on the water walls. The
scaffolding itself can take several weeks.
To overcome the disadvantage of the time consuming
scaffolding work, an automated boiler wall crawler for wall
cleaning and inspection is being developed by Alstom in
collaboration with Alstom Inspection Robotics and Waterjet
Technologies.
The automated system will be able to drive up the water wall
with the cleaning or inspection application integrated and no
scaffolding will be required anymore.
The cleaning application consists of a patented suspension
cleaning technology where abrasive and water are mixed and
pumped up to a defined pressure.
The inspection will be done using latest ultrasonic technology
to measure remaining wall thicknesses of the tubes.
The deployment system consists of two magnetic track drives
connected by a frame and two passive magnetic wheels.
Laboratory tests have shown promising results. The system is
able to drive up and down the water wall during the cleaning
with the system running at around 100bar.
Index Terms-- Automation, Maintenance, Power Generation,
Reliability, Boiler, Safety, Robotics, Water Jet Cleaning,
Inspection
I. INTRODUCTION
ower plant boilers are elements of thermal power plant
used to convert the chemical energy of the (fossil) fuel
first into thermal energy by combustion and subsequently
transferring the thermal energy of the combustion gases into
thermal energy of highly pressurized water. The water flows
inside of armed pipes arranged at the inside walls of the boiler
chamber. The boiler chambers can measure up to 35m x 35m
x 50m. As an effect of the continuous combustion process the
pipes are more and more covered by a layer of combustion
residues.
These pipes need to be inspected on a regular basis, mainly
for wall thickness. Before a reliable inspection can take place,
the residue layer has to be removed. As of today, this task is
done manually using dry blasting method. The cleaning and
inspection method require the installation of a scaffold at the
Vera de Vries and Simon Honold are with
ALSTOM Power, 5401 Baden, Switzerland , www.alstom.com/power Philipp Roth is with Waterjet Technologies Ltd,
5210 Windisch, Switzerland ,wwww.waterjet-technologies.ch
Wolfgang Zesch is with Alstom Inspection Robotics Ltd. Technoparkstrasse 1, 8005 Zürich, Switzerland, www.inspection-robotics.com
inside of the boiler in order to allow the personnel to access
the wall.
To reduce the cleaning and inspection time and to make
this service task safer, a system is being developed to execute
the working steps without scaffolding. The aim is to reduce
the process time significantly down to a few hours or days.
Also, the new system allows for recording the inspection data
in order to make it available offline for further analysis.
Fig. 1 Typical boiler of a coal power plant
The inspection and cleaning system consists of a magnetic
deployment device with an integrated cleaning or inspection
application. It is able to crawl up the water wall, carry out the
service task in a certain area and send the data back to the
operator standing on the floor area of the boiler controlling the
system.
The benefit in using the new cleaning and inspection tool is
mainly time saving and improvement of EHS (environmental,
health and safety). In terms of EHS, working at height is not
required anymore. The deployment device will be secured
with a safety device, preventing the system from falling down
in at any moment during service time.
In terms of time saving, the main benefit is to avoid
scaffolding. In many cases, only a partial inspection is
required. For these missions, the impact on the time saving is
even higher. The scaffolding for a partial cleaning and
inspection task takes several shifts and requires up to 10
workers. Compared to the relatively short cleaning and
inspection time for the partial area, this is quite time
consuming. With the new system, the several shifts of
scaffolding can be saved.
Automated Boiler Wall Cleaning and Inspection W. Zesch, S. Honold, Ph. Roth, V. de Vries
P
Considering the high number of boilers installed (e.g. 600
in the USA [2]), and assuming a major outage every 5-10
years, the benefit of having an automated system available is
remarkable.
II. SYSTEM DESCRIPTION
The boiler wall cleaning and inspection system consists of
a magnetic deployment device with an integrated cleaning and
inspection application. The system is highly mobile and the
installation time is short.
A. Integration of cleaning application
The cleaning application integrated in the deployment
device is a suspension cleaning technology. Suspension
cleaning by Waterjet Technologies uses a newly patented
pump system [1], [5] to pump a water/abrasive mixture up to
170bar. The pressurized suspension is conducted to a nozzle,
where an abrasive water jet of a defined geometry is formed.
The process is comparable to sludge cleaning, but works at
higher pressure thus resulting in a higher cleaning
performance.
Fig. 2 Water jet suspension cleaning system
The cleaning system (Fig. 2) fits on a euro pallet (size
800mm x 1200mm) and is easily transportable. The setup time
for the system takes about 1 hour.
The working pressure of 170bar allows using hoses for
tubing as thin as 12mm in diameter. They are extremely
flexible (bend radius < 50mm) to conduct the high-pressure
suspension from the pump to the nozzle system (Fig. 3, (1))
This results in low weight of the supply tube (Fig. 3, (2))
which is important because of the limited payload capacity of
the deployment device.
Three tungsten carbide nozzles form the jet in the nozzle
system with a jet velocity of approximately 150 m/s. Each
nozzle generates a fanjet with an angle of approximately 50
degrees (Fig. 3), so width of up to 200mm is cleaned in one
pass.
Fig. 3 Integrated water jet nozzle system
For this cleaning application corundum of mesh size 220 is
used. To eliminate the risk of corrosion, an anti-corrosive is
added to the suspension in the mixing tank. Several tests have
shown that the base material removal is negligible (in the
range of microns) [1].
The reasons of using suspension water jet technology
instead of conventional blasting methods are manifold:
Improved surface quality resulting in better inspection
results.
Negligible base material removal
Improved progress speed due to the use of fan jet nozzles
Light weight and flexible supply hoses
Fast system set-up time
Highly mobile system
Recirculation of suspension possible
B. Integration of inspection application
The inspection method used is conventional ultrasound
technology. With the probe and the probe holder mounted on
the deployment system, the focus is to measure the remaining
wall thickness, in a next stage also to find cracks, both from
the hot side only. In order to save inspection time the goal is to
acquire the UT signals simultaneously with cleaning. The
defining factor is the cleaning speed, which is significantly
lower than the possible UT scan speed. The inspection result is
a map (C-scan) of the water wall, presenting the exact
locations of all irregularities, such as depicted in Fig. 4.
The main challenges for integrating the UT system in this
inspection system are:
Large surface roughness of the tubes due to long
exposure to a very aggressive atmosphere. This requires
sufficient couplant feed in order to provide good acoustic
coupling
Couplant supply through >50m tube. An onboard tank
seems not feasible due to large couplant consumption.
Transmission of UT signal to the controller due to the
large distances to the operator (>50m) the digitization
has to be performed on-board
Shielding of inspection part from cleaning part with its
abrasives in the water jet.
(1)
(2)
(3)
Fig. 4 Typical C-scan showing the wall thickness variation using a color code
for the deviation from the nominal thickness
C. Deployment device
The deployment device is a mobile robotic platform
equipped with 2 drive units on both sides (Fig. 5). Different to
the approach presented in [3] [4], each drive unit consists of 5
magnetic wheels and a tooth belt driven by a brushless DC
motor.
Fig. 5: Bottom view of the deployment system, showing the 2 drive units
(blue) with a traction belt and 5 magnetic wheels each
The magnetic wheels are specially designed to overcome
air gaps present in the undulating surface between the water
wall tubes. These wheels press the belt onto the iron tubes thus
creating sufficient friction even if only 2 or 3 wheels are in
contact with the water wall surface. The belt on one side
provides traction but on the other side also prevent the robot
from getting stuck in the gaps between the tubes. Some basic
parameters are given in Tab. 1.
Steering is necessary to both correct for errors in the
robot’s path but also to circumvent obstacles on the water
wall, such as viewing windows, coal and air nozzles or tube
branches. This steering is performed by differential control of
the 2 drive units. Although the tracks tend to move straight,
path radii as small as 750mm can be achieved.
Due to the limited width of the tracks and the magnetic
wheels not all orientation of the robot relative to the directions
of the tubes can be traverse with the same speed and
reliability. To overcome this, the next generation shall
incorporate a combination of wider rollers and belts.
TAB 1 BASIC DATA OF THE ROBOTIC PLATFORM
size (L x W x H) 500 x 350 x 100 mm
weight 5.7 kg
payload capacity ca. 10 kg
speed 150 mm/s
The current prototype system is controlled from a
stationary controller at the operator’s site. A 50m long
umbilical cable provides the power to the 2 motors and feeds
back the position information (motor encoders) to the
controller. In a next step, the controller shall be placed on-
board. The umbilical will then provide DC power and
communication to the robot via an Ethernet connection.
The operator controls the prototype robot with a joystick. In
cleaning mode the speed is set to an optimum given by the
water jet system, i.e. as fast as possible, but still below the
limit where cleaning becomes incomplete. The operator
corrects the straight path of the robot from time to time in
order to cover the water wall completely and not to leave
certain spots unclean. In manual mode the user has full control
over speed and rotation rate of the robot. This is used, to
maneuver the robot to a certain location quickly or to
circumvent obstacles.
In the future, the system shall clean and inspect the water
wall more autonomously relying on several sensors. Contour
sensors (e, g, inductive, laser, camera) will allow the robot to
follow the tube direction or to use this information for position
estimation. An inclination sensor provides the orientation of
the robot on the water wall and thus aids to increase accuracy
of the odometric system. Eventually a global positioning
sensor, such as a laser tracker will provide continuous position
information free of integration errors.
III. VERIFICATION IN THE LABORATORY
First test with the prototype system were executed in the
lab of Alstom Inspection Robotics on a clean wall of tubes
(Fig. 6). The system was run under dry condition at first.
Fig. 6: Prototype of cleaning system on test mockup: dry run
During these tests the payload of the device was measured
and improved. Additionally the movement was analyzed and
the drive control optimized.
Afterwards a durability test on a mockup in the lab of
Waterjet Technologies has been undertaken.
Fig. 7: Durability test on test mockup
With the running cleaning system the crawler was moved up
and down in a loop on the mock up (Fig. 7). The durability test
lasted for more than 8 hours of constant system run.
The Test showed promising results:
The cleaning rate and quality was sufficient and proven
during 8 hours of constant run.
The crawler was not affected by the abrasive water jet.
Fig. 8: Cleaning test result
They payload was sufficient to carry the complete system
during cleaning, no detachment of the crawler occurred.
IV. OUTLOOK
As a next step, a test under real conditions in a boiler
environment on-site is planned. The deposit on the boiler
walls (slug – Fig. 9) has to be removed manually in order to
prevent heavy and big parts falling down on the operator. The
second cleaning step will be carried out using the new
automated device to prepare the surface for the subsequent
inspection.
Fig. 9: Slug on the boiler wall
The on-site tests will serve to validate the cleaning process as
well as the handling of the tool, the reliability and the safety.
The cleaning time will be measured, recorded and compared
to the conventional process. The surface quality will as well be
measured and recorded. The handling of the tool and the
accessibility (Fig. 10) will be validated and documented.
Fig. 10: Manhole to enter the boiler
V. CONCLUSIONS
The cleaning and inspection system being developed in
collaboration with Alstom Switzerland, Alstom Inspection
Robotics and Waterjet Technologies is a compact and
automated tool for cleaning and inspection of boiler water
walls. The main benefits are the time saving due to omitting of
scaffolding works and the increase of safe operation since no
working at height is required.
The deployment system is a mobile device able to drive
across the boiler wall tubes. The system is controlled from a
stationary controller by one operator. Different speed rates
depending on the application are possible optimizing the
installation, cleaning and inspection process time.
The integrated cleaning system is based on a suspension
cleaning technology resulting optimal cleaning quality and
performance. Followed by the cleaning, the integrated
ultrasound technology allows a reliable wall thickness
measurement.
The lab tests show promising results in terms of system
reliability and cleaning performance. The validation under real
conditions will prove the reliability and improved performance
using the automated cleaning and inspection tool.
VI. REFERENCES
Technical Reports: [1] 2011_01_03_Summary_WJCleaning.doc, Project summary report,
Alstom Switzerland, V. de Vries [2] Business Case scenario 2.xls: Business case for partial cleaning and
inspection, Alstom Switzerland, V. de Vries
Papers Presented at Conferences (Unpublished): [3] Slocum H. Magnebots – A Magnetic Wheels Based Overhead
Transportation Concept International Workshop on Advances in Service Robotics, 2003
[4] Hirose S, Tsutsumitake H, Toyama R, Kobayashi K. Disk Rover: A
Wall-Climbing Robot Using Permanent Magnet Discs IEEE/RSJ Int. Conf. on Intelligent Robots and Systems, 1992
Patents: [5] P. Roth, “Method for working on workpieces by means of a water jet
that contains abrasive and emerges under high pressure from a nozzle,
water jet installation for executing the method, and application of the method”, European Patent EP2308646, Sep. 28. 2010
[6] J. Brignac, R. Moser; “Automated system for waterwall cleaning and
inspection”; U.S: Patent US2008308128, Jun. 12 2007
VII. BIOGRAPHIES
Simon Honold graduated in 2006 from École
Polytechnique Fédérale Lausanne in Microsystem Engineering. Since his graduation he’s working for
Alstom (Switzerland) AG in different positions
related to robotic & diagnostic equipment for power plant inspections.
Vera de Vries graduated in 2001 (Mechanical
Engineering) from the Swiss Federal Institute of
Technology (ETH) in Zürich. After her PhD at the
Department of Mechanical Engineering at the ETH
(2006) she was working as project manager in the
field of Inspection Technologies R&D at ALSTOM Power. Since September 2011 she is the Manager
Department Manager R&D Robotics and Automation
s in ALSTOM Power in Baden
Philipp Roth graduated in 2004 from the University
of Applied Sciences Aargau in Brugg-Windisch. After his studies he was working for two years as a
research assistant at the Institute for Thermal and
Fluid Engineering at the University of Applied Sciences Aargau. In 2007 he co-founded Waterjet
Technologies Ltd and is since then CEO of the
company.
Wolfgang Zesch graduated as a M.Sc. in
mechatronics from the Swiss Federal Institute of Technology (ETH) in Zürich and earned his Ph.D. in
micro robotics at the Institute of Robotics of the
same university. During a post-doctoral stay at the University of California at Berkeley (UCB) he
conducted research in automated handling of micro parts. After 8 years in engineering and project
management in mechatronics, sensors & actuators
and optics he joined ALSTOM Inspection Robotics Ltd as General Manager in 2007, now occupying the
positions of CTO.