Privileged & Confidential 225 PARK AVENUE SOUTH NEW YORK, NEW YORK 10003-1604 (212) 777-4400 FAX: (212) 529-5237 AN EMPLOYEE-OWNED COMPANY PROVIDING QUALITY SERVICE SINCE 1912 Atlantic Yards Construction Summary Report for Week ending 8/29/2014 Weather: Slightly Cooler than Average, temps lo 60‟s to 90; sunny & no rain all week. B2 o 0 new mods installed. Building mods complete through 10 th floor. Currently at 297 mods installed out of 930 total, 31.9%. Mod manufacturing stopped at Navy Yard Bldg 292 according to news reports workers furloughed. o Work on site slowed significantly after news of the mod plant work stoppage. The building was mostly empty on Friday, 8/29 except for buildout work in the subcellar level associated with new employee locker room space for the arena. o The last mods installed was on August 11. B2 had been in the midst of its 2 nd significant mod installation hiatus of greater than 25 work-days (5 weeks+). A previous mod installation hiatus lasted 7 to 8 weeks (April 15 to June 9, 2014) after the building reached the 5 th floor. When mod installation resumed, five floors of mods, Floors 6-10, were installed during a 6+ week timeframe, June 10 - August 1 (and 5 mods on 8/11), a total of 180 mods (5 floors of 36 mods) installed at a rate of 5 mods/work day on average. o At the time of the 12/18/12 groundbreaking the scheduled duration for the 32- story building (plus 2-story headhouse) was 20 months, a 10-month savings over standard construction, and construction was supposed to be complete by July/August 2014. o The module fabrication workforce at the Brooklyn Navy Yard reportedly numbered in the upper 150s at the time of the furlough. This was down slightly from the peak in the lower 160s but still significantly above the original projection of a maximum of 125 workers. A previously mentioned plan to add a second shift never occurred. Only selective O/T was being performed at the Navy Yard plant on weeknights and on Saturdays. o The number of mods per floor are: 27 (Floors 2-4); 36 (Floors 5-19); 29 (Floors 20-23); 20 (Floors 24-32); 8 (Floor 33) and 5 (Floor 34). Mod production began on 7/24/13.

Upload: ayreport

Post on 17-Jul-2016

25 views

Category:

Documents


4 download

DESCRIPTION

Atlantic Yards B2 FOIL, AY STV Report - 8-29-14 - Proposed Redactions_Redacted

TRANSCRIPT

Page 1: Atlantic Yards B2 FOIL, AY STV Report - 8-29-14 - Proposed Redactions_Redacted

Privileged & Confidential

225 PA R K AV EN U E SOU T H

N EW Y OR K , N EW Y OR K 10003-1604

( 212) 777- 4400 FA X : ( 212) 529-5237

A N EM PL OY EE- OW N ED COM PA N Y PROV I D I N G QUA L I T Y SERV I CE SI N CE 1912

Atlantic Yards

Construction Summary Report for Week ending 8/29/2014

Weather: Slightly Cooler than Average, temps lo 60‟s to 90; sunny & no rain all week.

B2

o 0 new mods installed. Building mods complete through 10th floor. Currently at

297 mods installed out of 930 total, 31.9%. Mod manufacturing stopped at Navy

Yard Bldg 292 according to news reports – workers furloughed.

o Work on site slowed significantly after news of the mod plant work stoppage.

The building was mostly empty on Friday, 8/29 except for buildout work in the

subcellar level associated with new employee locker room space for the arena.

o The last mods installed was on August 11. B2 had been in the midst of its 2nd

significant mod installation hiatus of greater than 25 work-days (5 weeks+). A

previous mod installation hiatus lasted 7 to 8 weeks (April 15 to June 9, 2014)

after the building reached the 5th floor. When mod installation resumed, five

floors of mods, Floors 6-10, were installed during a 6+ week timeframe, June 10

- August 1 (and 5 mods on 8/11), a total of 180 mods (5 floors of 36 mods)

installed at a rate of 5 mods/work day on average.

o At the time of the 12/18/12 groundbreaking the scheduled duration for the 32-

story building (plus 2-story headhouse) was 20 months, a 10-month savings over

standard construction, and construction was supposed to be complete by

July/August 2014.

o The module fabrication workforce at the Brooklyn Navy Yard reportedly

numbered in the upper 150‟s at the time of the furlough. This was down slightly

from the peak in the lower 160‟s but still significantly above the original

projection of a maximum of 125 workers. A previously mentioned plan to add a

second shift never occurred. Only selective O/T was being performed at the

Navy Yard plant on weeknights and on Saturdays.

o The number of mods per floor are: 27 (Floors 2-4); 36 (Floors 5-19); 29 (Floors

20-23); 20 (Floors 24-32); 8 (Floor 33) and 5 (Floor 34). Mod production began

on 7/24/13.