Association of Cost EngineersNEC: Option C Cost Audits

Page 2: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC Option C Cost Audits• NEC Audit Provisions• NEC Payment Provisions• Audit Objectives• Audit Plan• Audit Considerations• Implementation of Audit Plan• Rolling Programme of Cost Audits• Potential Audit Problems

Page 3: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Solomons Europe Limited

• Solomons Europe is a Chartered Quantity Surveying Practice Established in 1998

• Provide support to UK’s Major EPC and Industrial Services Contractors

Page 4: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Solomons Europe Limited• Specialise in

Page 5: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC AUDIT PROVISIONSNEC ECC Option C

Target contract with an Activity Schedule

Page 6: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC AUDIT PROVISIONS• Contract Clause

– No express reference to cost audits in the NEC

– 52.3 Contractor allows the PM to inspect accounts and records required to be kept at any time within the working hours

Page 7: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC Payment Provisions• (50.1) Project Manager assesses the amount

due– Price for Work Done to Date

• Defined Cost + Fee

Page 8: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC Payment Provisions• Defined Cost =

– Option C:• Payments due to Subcontractors…

and• The cost of components in the Schedule of Cost

Components

Page 9: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

NEC Payment Provisions• Payment timescales

– 51.1 PM certifies a payment within one week of the assessment date

– Hence, high level review of any application with more thorough audit in the following weeks

– Any audit findings are then incorporated into next PM assessment of amount due

Page 10: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Objectives• Audits ensure costs paid are

• Accurate

• Allowable and

• Appropriate

Page 11: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Plan• Managing Reality Book Two: Procuring an

Engineering and Construction Contract:– Appendix 3: Audit Plan

Page 12: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Plan• The audit process should be detailed in the

Works Information

Page 13: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Plan• Audit Task Sections – Monthly Report

• People• Equipment• Plant & Materials• Charges• Manufacture & Fabrication• Design

Page 14: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Generally

– Specific contract provisions– Have payments actually been made? - access to

bank statements– Allocation to correct cost codes / WBS

Page 15: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Subcontractors

– Pre-appointment• Order placed in accordance with any Works

Information requirements

Page 16: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Subcontractors

– Post-appointment• Properly administered

– Change control– Assessment of PWDD– Payments made within timescales– Final accounts reflect contract

Page 17: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• People

– Place of work: Working Areas: “used only for this contract”

– Time capture procedure– Payslips (weekly & monthly) – Payroll burden: per Schedule of Cost

Components

Page 18: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Equipment

– Rates: reflective of current market rates (whether internal or not)

– Idle plant– Purchased Equipment– Maintenance / repair

Page 19: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Plant and Materials

– Orders– Goods received notes– Invoices– Payments– Check quants required v quants delivered

Page 20: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Charges

– Costs necessary to carry out the works– Costs included in Working Area overheads /

people overheads are not also included elsewhere

Page 21: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Manufacture and Fabrication

– Outside the Working Areas– Should be agreed and form part of the Contract

Data• “wholly or partly designed for the works”

Page 22: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Audit Considerations• Design

– Outside the Working Areas– Should be agreed and form part of the Contract

Data– Rates x hours + travel to Working Areas

Page 23: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Rolling Programme of Cost Audits• Plan to cover 10% of cumulative costs• Plan to audit each major cost element• Element audit schedule to reflect programme• Frequency of element audits reflect relative

values– Some elements may warrant a monthly audit:

e.g. prelims, staff costs

Page 24: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Potential Audit Problems• Vagueness of the Schedule of Cost

Components • Non-availability of substantiating information

may result in reduced payments

Page 25: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Potential Audit Problems• Ability to audit down the supply chain where

no direct contractual relationship exists• Reluctance to provide “commercially

sensitive” substantiating information / Data protection (!)

• Where the supporting information is held

Page 26: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Summary• Vital for Contractors (and subcontractors) to

keep full and organised records relating to costs to demonstrate validity and appropriateness

• Audits are a pragmatic way of ensuring accurate allowable and appropriate costs are reimbursed

Page 27: Association of Cost Engineers - Solomons Europe€¦ · Association of Cost Engineers NEC: Option C Cost Audits. NEC Option C Cost Audits • NEC Audit Provisions • NEC Payment

Summary• Successful audits create commercial

confidence for both parties throughout the project

• Successful audit outcomes assist early settlement of final accounts