assign resources to a project and produce a project schedule with a gantt chart
DESCRIPTION
Lesson-14 Project Management(2). Assign resources to a project and produce a project schedule with a Gantt chart. Assign people to tasks and direct the team effort. Use critical path analysis to adjust schedule and resource allocations in response to schedule and budget deviations. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/1.jpg)
Assign resources to a project and produce a project schedule with a Gantt chart.Assign people to tasks and direct the team effort.Use critical path analysis to adjust schedule and resource allocations in response to schedule and budget deviations.Manage user expectations of a project and adjust project scope.
Lesson-14 Project Management(2)
![Page 2: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/2.jpg)
Activity 4: Specify Intertask Dependencies
• Finish-to-start (FS)—The finish of one task triggers the start of another task.
• Start-to-start (SS)—The start of one task triggers the start of another task.
• Finish-to-finish (FF)—Two tasks must finish at the same time.
• Start-to-finish (SF)—The start of one task signifies the finish of another task.
![Page 3: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/3.jpg)
Entering Intertask Dependencies
![Page 4: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/4.jpg)
Scheduling StrategiesForward scheduling establishes a project start date and then schedules forward from that date. Based on the planned duration of required tasks, their interdependencies, and the allocation of resources to complete those tasks, a projected project completion date is calculated.Reverse scheduling establishes a project deadline and then schedules backward from that date. Essentially, tasks, their duration, interdependencies, and resources must be considered to ensure that the project can be completed by the deadline.
![Page 5: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/5.jpg)
A Project Calendar
![Page 6: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/6.jpg)
Activity 5: Assign Resources
• People—inclusive of all the system owners, users, analysts, designers, builders, external agents, and clerical help that will be involved in the project in any way, shape, or form.
• Services—a service such as a quality review that may be charged on a per use basis.
• Facilities and equipment—including all rooms and technology that will be needed to complete the project.
• Supplies and materials—everything from pencils, paper, notebooks, toner cartridges, etc.
• Money—A translation of all of the above into the language of accounting—budgeted dollars!
![Page 7: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/7.jpg)
Defining Project Resources
![Page 8: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/8.jpg)
Assigning Project Resources
![Page 9: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/9.jpg)
Resource Leveling
Resource leveling is a strategy used to correct resource overallocations by some combination of delaying or splitting tasks.
There are two techniques for resource leveling:
• task delaying
• task splitting
![Page 10: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/10.jpg)
Task Splitting and Delaying
• The critical path for a project is that sequence of dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest possible completion date of the project.
– Tasks that are on the critical path cannot be delayed without delaying the entire project schedule. To achieve resource leveling, critical tasks can only be split.
• The slack time available for any noncritical task is the amount of delay that can be tolerated between the starting time and completion time of a task without causing a delay in the completion date of the entire project.
– Tasks that have slack time can be delayed to achieve resource leveling
![Page 11: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/11.jpg)
Activity 6: Direct the Team Effort
• Supervision resources– The DEADLINE – A Novel
About Project Management
– The One Minute Manager
– The Care and Feeding of Monkeys
• Stages of Team Maturity (see figure to the right)
Ÿ Establish structure and rulesŸ Clarify team member relationshipsŸ Identify responsibilitiesŸ Develop a plan to achieve goals
ORIENTATION STAGE
Ÿ Resolve interpersonal conflictŸ Further clarify rules and goalsŸ Develop a participative climate
INTERNAL PROBLEM-SOLVING STAGE
Ÿ Direct team activity toward goalsŸ Provide and get feedbackŸ Share ideas–growing cohesionŸ Individuals feel good about each other
GROWTH AND PRODUCTIVITY STAGE
Ÿ More feedback and evaluationŸ Adherence to team normsŸ Roles of team strengthenedŸ Strong team motivation to share goals
EVALUATION AND CONTROL STAGE
FORMING
STORMING
NORMING
PERFORMING
![Page 12: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/12.jpg)
Activity 7: Monitor and Control Progress
• Progress reporting
• Change management
• Expectations management
• Schedule adjustments—critical path analysis (CPA)
![Page 13: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/13.jpg)
Sample Outline for a Progress Report
I. Cover PageA. Project name or identificationB. Project managerC. Date or report
II. Summary of progressA. Schedule analysisB. Budget analysisC. Scope analysis (describe any changes that may have
an impact on future progress)D. Process analysis (describe any problems encountered
with strategy or methodology)E. Gantt progress chart(s)
III. Activity analysisA. Tasks completed since last reportB. Current tasks and deliverablesC. Short term future tasks and
deliverablesIV. Previous problems and issues
A. Action item and statusB. New or revised action items 1. Recommendation 2. Assignment of responsibility 3. Deadline
V. New problems and issues
A. Problems (actual or anticipated)B. Issues (actual or anticipated)C. Possible solutions 1. Recommendation 2. Assignment of
responsibility 3. Deadline
VI. Attachments(include relevant printouts
from project management software)
![Page 14: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/14.jpg)
Progress on a Gantt Chart
![Page 15: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/15.jpg)
Expectations Management
An expectations management matrix is a rule-driven tool for helping management understand the dynamics and impact of changing project parameters such as cost, schedule, scope, and quality.
![Page 16: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/16.jpg)
Lunar Project Expectations Management
![Page 17: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/17.jpg)
Typical, Initial Expectations for a Project
![Page 18: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/18.jpg)
Adjusting Expectations
![Page 19: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/19.jpg)
Changing Priorities
![Page 20: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/20.jpg)
Critical Path Analysis (and Slack Time)
1. Using intertask dependencies, determine every possible path through the project.
2. For each path, sum the durations of all tasks in the path.
3. The path with the longest total duration is the critical path.– The critical path for a project is that sequence of
dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest completion date of the project.
– The slack time available for any noncritical task is the amount of delay that can be tolerated between the starting time and completion time of a task without causing a delay in the completion date of the entire project.
![Page 21: Assign resources to a project and produce a project schedule with a Gantt chart](https://reader036.vdocuments.us/reader036/viewer/2022070402/568138eb550346895da09e59/html5/thumbnails/21.jpg)
Critical Path
The critical path is highlighted in red
TASKC
Fri 2/9/01 2 days
Fri 2/9/01 0 days
TASKD
Tue 2/20/01 7 days
Tue 2/20/01 0 days
TASKI
Tue 2/27/01 5 days
Tue 2/27/01 0 days
TASKE
Mon 2/19/016 days
Tue 2/20/01 1 day
TASKB
Wed 2/7/01 2 days
Wed 2/7/01 0 days
TASKA
Mon 2/5/01 3 days
Mon 2/5/01 0 days
TASKH
Thu 2/15/01 1 day
Tue 2/20/01 3 days
TASKF
Wed 2/14/013 days
Fri 2/16/01 2 days
TASKG
Fri 2/16/01 2 days
Tue 2/20/01 2 days
Duration
Slack Time