microsoft project gantt chat
DESCRIPTION
This is a Gantt Chart for a project completed by myself on Microsoft Project, It is an example Gantt Chart schedule including resources and a highlighted critical path.TRANSCRIPT
Task Name Duration Start Finish Resource Names
1 Pilkington Tenant Improvement Schedule 193 days Apr 24 Jan 17
1.1 LEASE RELATED ACTIVITIES 15 days Apr 24 May 14
1.1.1 Sign Letter of Intent to Start Design 0 days May 14 May 14 MDesign,Owner
1.1.2 Lease Review 3 wks Apr 24 May 14 MDesign,Owner
1.1.3 Sign Lease Agrement 0 days May 14 May 14 MDesign,Owner
1.2 DESIGN DEVELOPMENT 71 days May 14 Aug 21
1.2.1 Preliminary Design Development (SD) 4 wks May 15 Jun 11 MDesign
1.2.2 Provide Racking Plan (Pilkington) 0 days May 14 May 14 MDesign
1.2.3 Approve Space Plan (Moves 1,2,3) 1 day Jun 26 Jun 26 Owner
1.2.4 Approve Space Plan (Moves 4,5) 1 day Jun 26 Jun 26 Owner
1.2.5 Approve Preliminary Warehouse Space Plan (Dock Locations)0 days Jun 11 Jun 11 Owner
1.2.6 Design Development (Moves 1,2,3) 2 wks Jun 12 Jun 25 MDesign
1.2.7 Design Development (Moves 4,5) 2 wks Jun 12 Jun 25 MDesign
1.2.8 Engineered Racking Drawings (Pilkington) 10 days May 15 May 28 MDesign
1.2.9 Office Allowance Budget Approval 0 days Jun 26 Jun 26 Owner
1.2.10 Finalize Interior Finishes 1 day Jun 27 Jun 27 MDesign,Owner
1.2.11 Bid and Award MEP Design Build Subcontracts 2 days Jul 1 Jul 2 MDesign,Owner
1.2.12 MEP Design Documents 1 day Jun 28 Jun 28 MDesign
1.2.13 Approval of Final Design Documents (Pilkington) 0 days Jun 26 Jun 26 Owner
1.2.14 Bid/Award General Trades/Finishes Packages 0 days Jun 26 Jun 26 MDesign
1.2.15 Reconcile Office/Warehouse Alowance Budget 0 days Aug 21 Aug 21 Owner
1.2.16 Submit Permit Drawings (Moves 1,2,3) 4 wks Jun 27 Jul 24 Owner
1.2.17 Submit Permit Drawings (Moves 4,5) 4 wks Jun 27 Jul 24 MDesign,Owner
1.3 PERMITS 61 days May 29 Aug 21
1.3.1 State of Ohio Building Permit (Moves 1,2,3) 4 wks Jul 25 Aug 21 Owner
1.3.2 State of Ohio Building Permit (Moves 4,5) 4 wks Jul 25 Aug 21 Owner
1.3.3 Racking Plan Review 10 days May 29 Jun 11 MDesign,Owner
1.4 CONSTRUCTION (MOVES 1,2,3) (Phase A) 49 days Aug 22 Oct 29
1.4.1 Warehouse Power/Lighting 2 days Aug 22 Aug 23
1.4.1.1 Trench for Underground plumbing 1 day Aug 23 Aug 23 Cement Crew,Plumbers
5/14
MDesign,Owner
5/14
MDesign
5/14
Owner
Owner
6/11
MDesign
MDesign
MDesign
MDesign,Owner
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SApr 17, '13 Apr 24, '13 May 1, '13 May 8, '13 May 15, '13 May 22, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Task Name Duration Start Finish Resource Names
1.4.1.2 Temporary Lighting 1 day Aug 22 Aug 22 Electrician
1.4.2 Tenant Racking 2 days Sep 4 Sep 5
1.4.2.1 Install Racks 4 days Sep 27 Oct 2 Labors 1
1.4.3 Rough Framing/Carpentry 25 days Aug 26 Sep 27
1.4.3.1 Install Steel Studs 10 days Aug 26 Sep 6 Rough Carpenters
1.4.3.2 Install Door Frames 4 days Sep 17 Sep 20 Rough Carpenters
1.4.3.3 Install Blocking 6 days Sep 9 Sep 16 Rough Carpenters
1.4.3.4 Install Drywall 5 days Sep 23 Sep 27 Finish Carpenters
1.4.4 Office MEP Rough-in 21 days Aug 26 Sep 23
1.4.4.1 Rough in Electric 2 days Sep 9 Sep 10 Electrician
1.4.4.2 Run under slab Pipes for Plumbing 2 days Aug 26 Aug 27 Plumbers
1.4.4.3 Run pipes under slab bathroom 2 days Aug 28 Aug 29 Plumbers
1.4.4.4 Run HVAC 5 days Sep 17 Sep 23 HVAC
1.4.4.5 MEP Rough Inspection 0 days Sep 23 Sep 23 Inspectors
1.4.5 Dock Pit Pour Back 17 days Aug 30 Sep 23
1.4.5.1 FRIPS dock pit 2 days Aug 30 Sep 2 Cement Crew
1.4.5.2 Let Cure 10 days Sep 3 Sep 16 Cement Crew
1.4.5.3 Install Dock Equipment 2 days Sep 17 Sep 18 Labors 1
1.4.5.4 Complete remaining millwork 3 days Sep 19 Sep 23 Finish Carpenters
1.4.6 Tenant Cabling 1 day Sep 24 Sep 24
1.4.6.1 Install Telephone, Internet 1 day Sep 24 Sep 24 Electrician
1.4.6.2 Final runs electric 1 day Sep 24 Sep 24 Electrician
1.4.7 Drywall/Finishes/Ceiling 18 days Sep 24 Oct 17
1.4.7.1 Install Ceiling tile grid 2 days Oct 7 Oct 8 Labors 2
1.4.7.2 Install Ceiling Tiles 3 days Sep 24 Sep 26 Labors 2
1.4.7.3 Mud/Sand Drywall 2 days Sep 30 Oct 1 Rough Carpenters
1.4.7.4 Install Carpet 2 days Oct 2 Oct 3 Carpet Layers
1.4.7.5 Drop cloth Carpet 1 day Oct 4 Oct 4 Painters
1.4.7.6 Paint 2 coats 2 days Oct 9 Oct 10 Painters
1.4.7.7 Install tile 2 days Oct 11 Oct 14 Tile Layers
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SApr 17, '13 Apr 24, '13 May 1, '13 May 8, '13 May 15, '13 May 22, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Task Name Duration Start Finish Resource Names
1.4.7.8 Bathroom recepticles 3 days Oct 15 Oct 17 Labors 1
1.4.8 MEP Finishes 14 days Sep 24 Oct 14
1.4.8.1 Bathroom Fixtures 2 days Oct 11 Oct 14 Labors 1
1.4.8.2 MEP Final Inspections 0 days Sep 24 Sep 24 Inspectors
1.4.8.3 finish all life saftey 1 day Sep 25 Sep 25 Labors 1
1.4.9 Final Inspections/Life Saftey 24 days Sep 25 Oct 29
1.4.9.1 Final Structual Inspections 0 days Oct 8 Oct 8 Inspectors
1.4.9.2 Testing of Life Saftey 0 days Sep 25 Sep 25 Inspectors
1.4.9.3 Certificate of Occupancy 0 days Oct 23 Oct 23 Owner
1.4.9.4 Substanial Completion 1 day Oct 18 Oct 18 Owner
1.4.9.5 Punch List 3 days Oct 21 Oct 23 Labors 1,Labors 2,MDesign
1.4.9.6 Tenant Relocation (Move 1) 1 day Oct 24 Oct 24 Owner
1.4.9.7 Tenant Relocation (Move 2) 1 day Oct 25 Oct 25 Owner
1.4.9.8 Tenant Relocation (Move 3) 1 day Oct 28 Oct 28 Owner
1.4.9.9 Phase A Complete 1 day Oct 29 Oct 29 MDesign
1.5 CONSTRUCTION (MOVES 4,5)(Phase B) 85 days Jul 3 Oct 29
1.5.1 Warehouse Power/Lighting 6 days Jul 3 Jul 10
1.5.1.1 Trench out for plumbing 3 days Jul 4 Jul 8 Cement Crew,Plumbers
1.5.1.2 Run under slab plumbing 2 days Jul 9 Jul 10 Plumbers
1.5.1.3 Temporary Lighting 1 day Jul 3 Jul 3 Electrician
1.5.2 Tenant Racking 3 days Aug 6 Aug 8
1.5.2.1 Install Racks 3 days Aug 6 Aug 8 Labors 1
1.5.2.2 All Final Inspections 0 days Aug 8 Aug 8 Inspectors
1.5.3 Rough Framing/Carpentry 14 days Jul 11 Jul 30
1.5.3.1 Install Steel Studs 10 days Jul 11 Jul 24 Rough Carpenters
1.5.3.2 Install Door Frames 2 days Jul 25 Jul 26 Rough Carpenters
1.5.3.3 Install Blocking 2 days Jul 29 Jul 30 Rough Carpenters
1.5.3.4 Install Drywall 3 days Jul 12 Jul 16 Rough Carpenters
1.5.4 Office MEP Rough-in 15 days Jul 11 Jul 31
1.5.4.1 Rough in electric 1 day Jul 25 Jul 25 Electrician
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SApr 17, '13 Apr 24, '13 May 1, '13 May 8, '13 May 15, '13 May 22, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Task Name Duration Start Finish Resource Names
1.5.4.2 Install bathroom Pipes for Plumbing 1 day Jul 11 Jul 11 Plumbers
1.5.4.3 Run HVAC 1 day Jul 31 Jul 31 HVAC
1.5.4.4 MEP Rough Inspection 0 days Jul 31 Jul 31 Inspectors
1.5.5 Tenant Cabling 3 days Aug 1 Aug 5
1.5.5.1 Install Telephone, Internet 2 days Aug 1 Aug 2 Electrician
1.5.5.2 Final electrical runs 1 day Aug 5 Aug 5 Electrician
1.5.6 Drywall/Finishes/Ceiling 21 days Jul 17 Aug 14
1.5.6.1 Install Ceiling Rack 2 days Jul 31 Aug 1 Labors 2
1.5.6.2 Install carpet and VCT 4 days Jul 17 Jul 22 Carpet Layers,Tile Layers
1.5.6.3 Install Ceiling Tiles 3 days Aug 6 Aug 8 Labors 1
1.5.6.4 Mud/Sand Drywall 2 days Jul 23 Jul 24 Rough Carpenters
1.5.6.5 Paint 2 coats 4 days Aug 9 Aug 14 Painters
1.5.7 MEP Finishes 61 days Aug 5 Oct 29
1.5.7.1 Bathroom Fixtures 2 days Aug 15 Aug 16 Labors 2
1.5.7.2 MEP Final Inspections 0 days Aug 5 Aug 5 Inspectors
1.5.7.3 Substanial Completion 1 day Aug 9 Aug 9 MDesign,Owner
1.5.7.4 Punch List 2 days Aug 19 Aug 20 MDesign
1.5.7.5 Tenant Relocation (Move 4) 1 day Aug 21 Aug 21 Owner
1.5.7.6 Phase B Complete 0 days Aug 22 Aug 22 MDesign,Owner
1.5.7.7 Project Complete 0 days Oct 29 Oct 29 MDesign,Owner
1.5.7.8 Tenant Relocation (Move 5) 1 day Aug 21 Aug 21 Owner
1.5.7.9 Tenant Relocation (Move 5) ALTERNATE 1 day Aug 22 Aug 22 Owner
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F SApr 17, '13 Apr 24, '13 May 1, '13 May 8, '13 May 15, '13 May 22, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
5/14
MDesign,Owner
5/14
MDesign
5/14
Owner
Owner
6/11
MDesign
MDesign
MDesign
6/26
MDesign,Owner
MDesign,Owner
MDesign
6/26
6/26
8/21
Owner
MDesign,Owner
Owner
Owner
MDesign,Owner
Cement Crew,Plumbers
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 22, '13 May 29, '13 Jun 5, '13 Jun 12, '13 Jun 19, '13 Jun 26, '13 Jul 3, '13 Jul 10, '13 Jul 17, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Electrician
Rough Carpenters
Rough Carpenters
Rough Carpenters
Electrician
Plumbers
Plumbers
HVAC
Cement Crew
Cement Crew
Labors 1
Finish Carpenters
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 22, '13 May 29, '13 Jun 5, '13 Jun 12, '13 Jun 19, '13 Jun 26, '13 Jul 3, '13 Jul 10, '13 Jul 17, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Cement Crew,Plumbers
Plumbers
Electrician
Labors 1
8/8
Rough Carpenters
Rough Carpenters
Rough Carpenters
Rough Carpenters
Electrician
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 22, '13 May 29, '13 Jun 5, '13 Jun 12, '13 Jun 19, '13 Jun 26, '13 Jul 3, '13 Jul 10, '13 Jul 17, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Plumbers
HVAC
7/31
Electrician
Electrician
Labors 2
Carpet Layers,Tile Layers
Labors 1
Rough Carpenters
Painters
Labors 2
8/5
MDesign,Owner
MDesign
Owner
8/22
Owner
Owner
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T WMay 22, '13 May 29, '13 Jun 5, '13 Jun 12, '13 Jun 19, '13 Jun 26, '13 Jul 3, '13 Jul 10, '13 Jul 17, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
MDesign
Owner
Owner
6/11
MDesign
MDesign
MDesign
6/26
MDesign,Owner
MDesign,Owner
MDesign
6/26
6/26
8/21
Owner
MDesign,Owner
Owner
Owner
MDesign,Owner
Cement Crew,Plumbers
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SJul 24, '13 Jul 31, '13 Aug 7, '13 Aug 14, '13 Aug 21, '13 Aug 28, '13 Sep 4, '13 Sep 11, '13 Sep 18, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Electrician
Labors 1
Rough Carpenters
Rough Carpenters
Rough Carpenters
Finish Carpenters
Electrician
Plumbers
Plumbers
HVAC
9/23
Cement Crew
Cement Crew
Labors 1
Finish Carpenters
Electrician
Electrician
Labors 2
Labors 2
Rough Carpenters
Carpet Layers
Painters
Painters
Tile Layers
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SJul 24, '13 Jul 31, '13 Aug 7, '13 Aug 14, '13 Aug 21, '13 Aug 28, '13 Sep 4, '13 Sep 11, '13 Sep 18, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Labors 1
Labors 1
9/24
Labors 1
10/8
9/25
10/23
Owner
Labors 1,Labors 2,MDesign
Owner
Owner
Owner
MDesign
Cement Crew,Plumbers
Plumbers
Electrician
Labors 1
8/8
Rough Carpenters
Rough Carpenters
Rough Carpenters
Rough Carpenters
Electrician
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SJul 24, '13 Jul 31, '13 Aug 7, '13 Aug 14, '13 Aug 21, '13 Aug 28, '13 Sep 4, '13 Sep 11, '13 Sep 18, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Plumbers
HVAC
7/31
Electrician
Electrician
Labors 2
Carpet Layers,Tile Layers
Labors 1
Rough Carpenters
Painters
Labors 2
8/5
MDesign,Owner
MDesign
Owner
8/22
10/29
Owner
Owner
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S SJul 24, '13 Jul 31, '13 Aug 7, '13 Aug 14, '13 Aug 21, '13 Aug 28, '13 Sep 4, '13 Sep 11, '13 Sep 18, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
8/21
Owner
MDesign,Owner
Owner
Owner
Cement Crew,Plumbers
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TSep 18, '13 Sep 25, '13 Oct 2, '13 Oct 9, '13 Oct 16, '13 Oct 23, '13 Oct 30, '13 Nov 6, '13 Nov 13, '13 Nov 20, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Electrician
Labors 1
Rough Carpenters
Rough Carpenters
Rough Carpenters
Finish Carpenters
Electrician
Plumbers
Plumbers
HVAC
9/23
Cement Crew
Cement Crew
Labors 1
Finish Carpenters
Electrician
Electrician
Labors 2
Labors 2
Rough Carpenters
Carpet Layers
Painters
Painters
Tile Layers
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TSep 18, '13 Sep 25, '13 Oct 2, '13 Oct 9, '13 Oct 16, '13 Oct 23, '13 Oct 30, '13 Nov 6, '13 Nov 13, '13 Nov 20, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Labors 1
Labors 1
9/24
Labors 1
10/8
9/25
10/23
Owner
Labors 1,Labors 2,MDesign
Owner
Owner
Owner
MDesign
Labors 1
8/8
Rough Carpenters
Rough Carpenters
Rough Carpenters
Electrician
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TSep 18, '13 Sep 25, '13 Oct 2, '13 Oct 9, '13 Oct 16, '13 Oct 23, '13 Oct 30, '13 Nov 6, '13 Nov 13, '13 Nov 20, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
HVAC
7/31
Electrician
Electrician
Labors 2
Labors 1
Rough Carpenters
Painters
Labors 2
8/5
MDesign,Owner
MDesign
Owner
8/22
10/29
Owner
Owner
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W TSep 18, '13 Sep 25, '13 Oct 2, '13 Oct 9, '13 Oct 16, '13 Oct 23, '13 Oct 30, '13 Nov 6, '13 Nov 13, '13 Nov 20, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MNov 20, '13 Nov 27, '13 Dec 4, '13 Dec 11, '13 Dec 18, '13 Dec 25, '13 Jan 1, '13 Jan 8, '13 Jan 15, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Labors 1
Finish Carpenters
HVAC
9/23
Finish Carpenters
Electrician
Electrician
Labors 2
Labors 2
Rough Carpenters
Carpet Layers
Painters
Painters
Tile Layers
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MNov 20, '13 Nov 27, '13 Dec 4, '13 Dec 11, '13 Dec 18, '13 Dec 25, '13 Jan 1, '13 Jan 8, '13 Jan 15, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
Labors 1
Labors 1
9/24
Labors 1
10/8
9/25
10/23
Owner
Labors 1,Labors 2,MDesign
Owner
Owner
Owner
MDesign
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MNov 20, '13 Nov 27, '13 Dec 4, '13 Dec 11, '13 Dec 18, '13 Dec 25, '13 Jan 1, '13 Jan 8, '13 Jan 15, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy
10/29
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MNov 20, '13 Nov 27, '13 Dec 4, '13 Dec 11, '13 Dec 18, '13 Dec 25, '13 Jan 1, '13 Jan 8, '13 Jan 15, '13
Nov 5 Warehouse WBS Mike Deskin
Perpared for client: Jeff Suchy