asia smart grid 2010_application of iec61850 substation

Upload: nguyen-binh-an

Post on 13-Apr-2018

235 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    1/33

    1

    SUCCESSFUL APPLICATION OFIEC61850 SUBSTATION AND REAL

    TIME ASSET-FOCUSED RISK

    MANAGEMENT

    Truong Huu Thanh

    Power Transmission Company No.4, National

    Power Transmission, Vietnam Electricity

    Tran Anh ThaiApplied Technical Systems Company, Ltd.

    Presentation Overview

    Introduction to Power Transmission

    Company No.4

    Substation modernization initiative

    First phase

    Second phase

    Third phase: IEC 61850 @STATION Real-time and Historian Data application

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    2/33

    2

    Electricity of Vietnam (EVN)

    State-owned utility established 1995

    Generation, transmission, and distribution

    for whole country

    4 transmission

    companies

    79,800 km of

    distribution lines

    Power Transmission Company No.4

    OHL

    500KV 11 765 Km220KV 57 3,376 Km

    Total 68 4,142 Km

    GRID STATION

    500KV 6 5,476 MVA

    220KV 25 9,530 MVA

    Total: 31 15,006 MVA

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    3/33

    3

    Growing Electricity Demand

    Forecasted growth 17% per annum until 2025

    0

    100

    200

    300

    400

    500

    600

    1995 2000 2005 2010 2015 2020 2025

    Production

    Sales

    Terawatt-Hours

    Measuring P/Q/U/I/Cos

    Getting status ON/OFF/OK

    Work orders/permit

    Technical document

    Maintenance log-book

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    4/33

    4

    Measuring P/Q/U/I/Cos

    Counting kWh/kVArh/TOU Geting ON/OFF/OK

    Work schedule

    Customer Information

    Maitenance Log-book

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    5/33

    5

    Open system

    Multi Protocol compatible Multi data transmission media

    Off-the-Shelf

    SMART GRID-Conceptual Model

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    6/33

    6

    The overall picture

    Highlights of Substation Automation

    and Integration in Vietnam

    First Phase Substation

    Modernization Began in 1999

    First computerized 220 kV

    substation commissioned

    in Ho Chi Minh City

    This success resulted

    in digitizing more

    substations through

    2003

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    7/33

    7

    Early Substation Modernization

    Digital protection and control using legacyserial and hardwired connections

    Problems with incompatibilities between

    multiple manufacturers IEDs

    Second Phase Standardization

    To improve IED compatibility, EVN issued

    specification for substation automation based

    on UCA2

    Based on this, first large-scale substation

    automation system (SAS) was implemented

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    8/33

    8

    Second Phase Standardization

    To improve IED

    compatibility, EVN

    issued specification

    for substation

    automation based on

    UCA2 in 2003

    The first large-scale

    substation automation

    system (SAS)commissioned in 2002

    220 kV Thu Duc Substation

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    9/33

    9

    220 kV Thu Duc SubstationSAS makes theretrofit works

    much easier.

    Upgraded

    Protection

    System

    Architecture

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    10/33

    10

    Third Phase IEC 61850

    IEC 61850 Part 10 approved Oct. 2005

    EVN standardized for future projects

    new and retrofit

    All 500 kV

    backbone

    substations

    upgraded by

    2012

    New System Requirements

    Dual redundant fiber-optic LAN with no

    single point of failure affected SAS operation

    IEC 61850 for all substation communication

    IEC 60870-5-101/104 for SCADA

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    11/33

    11

    Host 1 Host 2 Engineering(Bridge to SCADA) HIS Server Router to WAN

    BackupIED

    BackupIED

    MainIED

    MainIED

    BayDevices

    BayDevices

    MainNIM

    BackupNIM

    Bay CubicleBay Cubicle

    Bay Cubicle

    Option 2

    Option 1

    LAN 1

    LAN 2

    GPS Clock

    Backup

    IED

    Main

    IED

    BayDevices

    Fiber-OpticEthernet

    100 Mbps

    Standard System Hardware Architecture

    Standard System Hardware Architecture

    Target Fully Redundant SAS Architecture

    protective relays

    certain IEDs connect to the substation bus viaNetwork Interface Modules

    Ethernet 100 Mbps

    Redundant LAN

    Main

    Backup

    Backup Network InterfaceModule

    Main Network InterfaceModule

    Backup

    IED

    Main

    IED

    Bay Device

    Backup

    IED

    Main

    IED

    Bay Device

    Backup

    IED

    Main

    IED

    Bay Device

    Backup

    IED

    Main

    IED

    Bay Device

    I/O modulessynchrophasors revenue meters

    Internet

    Substation Computer

    Host 2

    Substation Computer

    Host 1

    HIS/WEB

    Servers

    Engineering

    WorkstationGPS clock

    Gateway /

    Router

    WAN / Corporate

    LAN

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    12/33

    12

    Computerized Control and Monitoring

    Local HMI,engineering console,

    and historian

    Redundant system

    servers running on

    Windows 2000 or Linux

    Old Protect ion Panels Replaced

    Microprocessor-based relays perform

    protection, control, and monitoring

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    13/33

    13

    Outdoor Cubicles Reduce Cabling

    Old Copper CablingThu Duc Substation

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    14/33

    14

    Copper

    Cabling

    Reduced

    @STATION System Overview

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    15/33

    15

    Legacy Device GatewayRugged Computing Platform

    SCADA Gateway

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    16/33

    16

    Copyright ATS, EVN, and SEL 2009

    Job-done at Sites

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    17/33

    17

    Real-time web access

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    18/33

    18

    Real-Time Database Management

    System (RTDMS)

    Integrates over 100

    IEDs

    Handles more than

    60,000 data points

    Provides customized

    applications

    Real-Time Database Management

    System (RTDMS)

    Integrates over 100 IEDs

    Handles more than 60,000 data points

    Provides customized applications

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    19/33

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    20/33

    20

    Controls Ensure Uninterrupted

    Operation

    Four-level hierarchical system

    Protection and control functions at bay and

    substation levels

    Traditional hardwiring

    Soft interlocking logic

    Remote controls from local mimic panel

    Controls Ensure Uninterrupted

    Operation

    Remote supervision and

    bay controls from PDA

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    21/33

    21

    Performance and Functional Tests

    Factory acceptance testing conducted atATS factory

    10 engineers, 3 weeks

    System capacity

    Communications failure

    System successfully passed all

    requirements

    Performance and Functional Tests

    FAT testing conducted atATS factory 10 engineers, 3 weeks Individual tests Functional tests System tests

    System successfully

    passed all requirements

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    22/33

    22

    Test Results

    User Interface Feature Required byEVN

    Tested

    Display Response Time < 1 s < 1 s

    Data Entry Response Time < 1 s < 1 s

    Display Update Rate < 2 s < 2 s

    Update Completion Rate < 1 s < 1 s

    Test Results

    User Interface FeatureRequired by

    EVNTested

    Alarm/Event

    Response Time< 1 s < 1 s

    Alarm Acknowledge/

    Delete Time< 2 s < 2 s

    Report and Logbook

    Response Time< 0.5 min < 0.5 min

    Display Color PrintoutResponse Time

    < 0.5 min < 0.5 min

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    23/33

    23

    User Interface Feature Required byEVN

    Tested

    Console Inhibit Time for

    Display Hardcopy< 2 s < 1 s

    Analog Data

    Collection Rate < 2 s

    Status Indication

    Collection Rate < 1 s

    Failover Time Between

    Main 1 and Main 2 0 s

    GOOSE Exchange Time < 10 ms < 8 ms

    Test Results

    Benefits of SAS

    Faster system integration with IED

    interoperability

    Reduction of copper cabling and

    hardwiring

    GOOSE for peer-to-peer data

    exchange

    Outdoor cubicles adjacent to feeder or

    bay System malfunctions reduced by nearly

    50%

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    24/33

    24

    Benefits of SAS

    Interoperability between

    different IEDs fastersystem integration

    Reduction of copper

    cabling and hardwiring

    GOOSE for peer-to-

    peer data exchange

    Outdoor cubicles

    adjacent to feeder or

    bay

    System malfunctions

    reduced by nearly 50%

    Substation LAN Architecture

    Facil itates Integrated Systems

    Easy expansion

    Less complex connections

    Multiple communications types

    Metering

    SCADA

    Peer-to-peer

    Engineering access

    Synchrophasors

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    25/33

    25

    Substation LAN Architecture

    Facilitates Integrated Systems Easy expansion

    Less complex

    connections

    Multiple comm types

    Metering

    SCADA

    Peer-to-peer

    Engineering access

    Synchrophasors

    Benefits of Legacy Gateways

    Provide common network connection

    for all devices

    Eliminate dependence on legacy

    protocols

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    26/33

    26

    Benefits of Legacy Gateways

    Eliminates

    dependence on

    legacy protocols

    Provides commonnetwork connection

    for all devices

    Copyright ATS, EVN, and SEL 2009

    Real time and HIS

    Application

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    27/33

    27

    Vietnam Back-bone Transmission Lines

    707 MW (1 line)

    1440 MW (2 lines)

    1080 MW (1 line )

    1420 MW (2 lines )

    1503 MW (2 circuit)

    2005 Black-out in Vietnam

    Background Conditions

    Longitudinal system

    three distinc t electrical areas

    South - Center - North

    signif icant MW transfer from South

    to North on 500 kV line

    double circuit South - Center

    one circuit Center - North

    second circuit due in 2005

    Major deficit in the North unusual load level in 2005

    28% increase from 2004

    severe draught

    on May 17, 2005, the Northern Region

    hydro reservoirs w ere almost empty

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    28/33

    28

    Simulation calculations for

    the Northern area predicted

    that the system would

    approach instability if morethan 887.44 MW were

    transferred from Center to

    North across the 500 kV line

    Calculations before the May 17

    2005 Blackout (cont 'd)

    After Fault Analysis 2005 Blackout

    (cont'd)

    ... evaluated thi s new case (882.2 MW transfer from Center to North) as

    critically stable (less than 1% stability reserve)

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    29/33

    29

    Improve System Reliabili ty

    and Stability

    Increase power transmission across existing

    infrastructure

    Monitor and control voltage and angle

    instabilities

    Require dynamically calculated maximum

    loading conditions in real time

    Wide-Area Synchrophasor

    Application

    New IEDs with synchrophasor measurement

    capability

    Minimal incremental cost

    Fewer CT and VT connections

    High reliability and availability

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    30/33

    30

    Monitor ing Principle

    Synchrophasor Application

    Architecture

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    31/33

    31

    Use MATLAB for Complex Calculations

    Desktop Application Provides

    Real-Time Transmission Capacity

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    32/33

    32

    Web Application for Remote Access

    Visualized system loading

  • 7/26/2019 Asia Smart Grid 2010_Application of IEC61850 Substation

    33/33

    Transformer and OHL on-line

    Ampacity

    Detailed Display of 220 kV Transformer Dynamic Loading Capacity User Interface

    Questions?