asap methodology sap

Upload: shivdeep-basavaraj

Post on 02-Jun-2018

279 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/10/2019 ASAP Methodology SAP

    1/50

    January 2007 (v1.0) The Rushmore Group, LLC 1

    ASAP Methodology(SAP)

  • 8/10/2019 ASAP Methodology SAP

    2/50

    January 2007 (v1.0) The Rushmore Group, LLC 2

    Phase 1: Project PreparationDuring this phase the team goes through initial planning and preparation for

    SAP project.

    Phase 2: Business BlueprintThe purpose of this phase is to achieve a common understanding of how thecompany intends to run SAP to support their business. The result is the

    Business Blueprint, a detailed documentation of the results gathered during

    requirements workshops.

  • 8/10/2019 ASAP Methodology SAP

    3/50

    January 2007 (v1.0) The Rushmore Group, LLC 3

    Phase 3: RealizationThe purpose of this phase is to implement all the business process requirements

    based on the Business Blueprint. The system configuration methodology is

    provided in two work packages: Baseline (major scope); and Final configuration

    (remaining scope).

    Phase 4: Final PreparationThe purpose of this phase is to complete the final preparation (including testing,

    end user training, system management and cutover activities) to finalize your

    readiness to go live.

    The Final Preparation phase also serves to resolve all critical open issues. On

    successful completion of this phase, you are ready to run your business in your

    live SAP System.

    Phase 5: Go Live & SupportThe purpose of this phase is to move from a project-oriented, pre-production

    environment to live production operation.

  • 8/10/2019 ASAP Methodology SAP

    4/50

    January 2007 (v1.0) The Rushmore Group, LLC 4

    Phases in ASAP

    Project Preparation Business Blue print

    Realization

    Final Preparation Go Live

    Support

  • 8/10/2019 ASAP Methodology SAP

    5/50

    January 2007 (v1.0) The Rushmore Group, LLC 5

    Project Preparation

  • 8/10/2019 ASAP Methodology SAP

    6/50

    January 2007 (v1.0) The Rushmore Group, LLC 6

    Purpose : Initial Planning and Preparation

    Define the project goals, scope and objectives

    Identify, on-board and train Team Members

    Deliverables :

    Project Charter which contains below docs : Project Scope

    Implementation Plan & Rollout Strategy

    Detailed Scope Document Costs and Benefits Validation

    Project Standards

    Project Infrastructure

    Phase 1 : Project Preparations

  • 8/10/2019 ASAP Methodology SAP

    7/50

  • 8/10/2019 ASAP Methodology SAP

    8/50

    January 2007 (v1.0) The Rushmore Group, LLC 8

    SD: Structure for Sales Order Processing

    Client 410

    Company CodeC100

    Plant P100 Plant P101

    Sales Area

    Sales OrgS100

    Distribution

    Channel (RE)

    Division

    (01)

  • 8/10/2019 ASAP Methodology SAP

    9/50

    January 2007 (v1.0) The Rushmore Group, LLC 9

    SD: Internal Sales Structure

    US Sales OfficeS100

    Western Sales

    Office

    Northwest Sales

    Group

    Southwest Sales

    Group

    Salesperson 1

    Eastern Sales

    Office

    Northwest Sales

    Group

    Southwest Sales

    Group

    Salesperson 2

    Salesperson 3

    Salesperson 4

    Salesperson 5

    Salesperson 6 Salesperson 7

    Salesperson 8

    Salesperson 9

  • 8/10/2019 ASAP Methodology SAP

    10/50

    January 2007 (v1.0) The Rushmore Group, LLC 10

    SD: Structure for Distribution

    Client 410

    Company Code

    C100

    Plant P100 Plant P101

    Shipping Point

    Express Dock

    Loading Point

    LP01

    Shipping Point

    Freight Dock

    Shipping Point

    Rail Dock

    Loading Point

    LP02

    Loading Point

    LP03

  • 8/10/2019 ASAP Methodology SAP

    11/50

    January 2007 (v1.0) The Rushmore Group, LLC 11

    SD: Master Data

    Customer Master Data

    Material Master Data

    Cust/Mat Info Record

    Output Master Data

    Condition Master Data

  • 8/10/2019 ASAP Methodology SAP

    12/50

    January 2007 (v1.0) The Rushmore Group, LLC 12

    SD: Customer Master Data

    Customer Master Contains all of the information

    necessary for processing

    orders, deliveries, invoices and

    customer payment

    Every customer MUST have amaster record

    Customer Master Data is

    created by Sales Area Sales Organization

    Distribution Channel

    Division

  • 8/10/2019 ASAP Methodology SAP

    13/50

    January 2007 (v1.0) The Rushmore Group, LLC 13

    SD: Customer Master Data

    The customer masterinformation is divided

    into 3 areas:

    General Data

    Company Code Data Sales Area Data

  • 8/10/2019 ASAP Methodology SAP

    14/50

    January 2007 (v1.0) The Rushmore Group, LLC 14

    SD: Customer Master

    Company Code 102

    Company Code 101Company Code 100

    Client 410

    Sales Org. 101

    Sales Org. 100

    General Informationrelevant for the entire organization:Name

    Address

    Communication

    Company Code specific information:

    Acc. Mgmt

    Payment

    Bank

    Sales Area specific information:

    Sales Office

    Currency

  • 8/10/2019 ASAP Methodology SAP

    15/50

    January 2007 (v1.0) The Rushmore Group, LLC 15

    SD: Master Data

    Material Master

    Contains all the information a

    company needs to manage

    about a material

    It is used by most components

    within the SAP system Sales and Distribution

    Materials Management

    Production

    Plant Maintenance

    Accounting/Controlling

    Quality Management

    Material master data is stored

    in functional segments called

    Views

  • 8/10/2019 ASAP Methodology SAP

    16/50

    January 2007 (v1.0) The Rushmore Group, LLC 16

    SD: Material Master Views

    Material Master

    Basic Data

    Sales Data

    Controlling Data

    Forecasting Data

    Purchasing Data

    Mat. Plan. Data

    Accounting Data

    Storage Data

    Quality Data

  • 8/10/2019 ASAP Methodology SAP

    17/50

    January 2007 (v1.0) The Rushmore Group, LLC 17

    SD: Material Master

    Plant 102

    Plant 101Plant 100

    Client 410

    Storage Location 20

    Storage Location 10

    General Informationrelevant for the entire organization:Name

    Weight

    U/M

    Sales specific information: Delivery Plant

    Loading GrpStorage Location specific information:

    Stock Qty

  • 8/10/2019 ASAP Methodology SAP

    18/50

    January 2007 (v1.0) The Rushmore Group, LLC 18

    SD: Customer-Material Information Record

    Data on a material defined fora specific customer is stored

    in a Customer material info

    record.

    Info Records contain:

    customer-specific material number

    customer-specific material

    description

    customer-specific data on deliveries

    and delivery tolerances

    You can also maintain default text

    to appear on sales orders for that

    customer

  • 8/10/2019 ASAP Methodology SAP

    19/50

    January 2007 (v1.0) The Rushmore Group, LLC 19

    SD: Condition Master (Pricing)

    Condition master data includes: Prices

    Surcharges

    Discounts

    Freights

    Taxes

    You can define the condition master

    to be dependent on various data:

    Material specific

    Customer specific

    Conditions can be dependent on

    any document field

  • 8/10/2019 ASAP Methodology SAP

    20/50

    January 2007 (v1.0) The Rushmore Group, LLC 20

    SD: Output

    Output is information thatis sent to the customerusing various media, suchas:

    E-mail

    Mail EDI

    Fax

    XML

    Output examples:

    Quotation Confirmation

    Invoice

  • 8/10/2019 ASAP Methodology SAP

    21/50

    January 2007 (v1.0) The Rushmore Group, LLC 21

    Sales & DistributionSales

    Sales Order Process

  • 8/10/2019 ASAP Methodology SAP

    22/50

    January 2007 (v1.0) The Rushmore Group, LLC 22

    Sales: The Process

    Sales OrderEntry

    Post Goods

    Issue

    Invoice

    Customer

    Pick

    MaterialsReceipt of

    Customer Payment

    PackMaterials

    Check

    Availability

    Pre-salesActivities

  • 8/10/2019 ASAP Methodology SAP

    23/50

    January 2007 (v1.0) The Rushmore Group, LLC 23

    SD: Pre-Sales Activities (CRM Light)

    Sales Support is a component of SD that assists in the sales,distribution, and marketing of a companies products andservices to its customers. It contains the following functionality:

    Creating and tracking customer contacts and communications(sales activity)

    Phone call records

    On-site meeting

    Letters

    Campaign communication

    Implementing and tracking direct mailing, internet, and trade faircampaigns based on customer attributes

    Pre-sales documents need to be managed within the presalesactivities: Inquiries and Quotations. These documents helpidentify possible sales related activity and determine salesprobability.

  • 8/10/2019 ASAP Methodology SAP

    24/50

    January 2007 (v1.0) The Rushmore Group, LLC 24

    SD: Pre-Sales Activities (CRM Light)

    The ultimate goal of all pre-sales activities is to equipthe sales technician with allthe information necessary tonegotiate and complete thepotential sale.

    Information needed: Past sales activity

    Past communication

    Contact information

    General Company info

    Credit limits and usage

    Current backorders

    360 view of your customer

  • 8/10/2019 ASAP Methodology SAP

    25/50

    January 2007 (v1.0) The Rushmore Group, LLC 25

    SD Process: Inquiry

    An inquiry is a customers request to a company forinformation or quotation in respect to their products

    or services without obligation to purchase.

    How much will it cost

    Material/Service availability

    May contain specific quantities and dates

    The inquiry is maintained in the system and a

    quotation is created to address questions for thepotential customer.

  • 8/10/2019 ASAP Methodology SAP

    26/50

    January 2007 (v1.0) The Rushmore Group, LLC 26

    SD Process: Quotation

    The quotation presents thecustomer with a legally

    binding offerto deliver

    specific products or a

    selection of a certain

    amount of products in a

    specified timeframe at a

    pre-defined price.

  • 8/10/2019 ASAP Methodology SAP

    27/50

    January 2007 (v1.0) The Rushmore Group, LLC 27

    SD Process: Sales Order

    Sales order processing can originate from a variety ofdocuments and activities Customer contacts us for order: phone, internet, email

    Existing Contract

    Quotations

    The electronic document that is created should contain thefollowing basic information: Customer Information

    Material/service and quantity

    Pricing (conditions)

    Specific delivery dates and quantities

    Shipping information

    Billing Information

  • 8/10/2019 ASAP Methodology SAP

    28/50

    January 2007 (v1.0) The Rushmore Group, LLC 28

    SD Process: Sales Order

    The sales document ismade up of three primaryareas: Header

    Data relevant for the entiresales order: Ex: customer data,total cost of the order

    Line Item Information about the specific

    product: Ex: material andquantity, cost of an individualline

    Schedule Lines Uniquely belongs to a Line

    Item, contains deliveryquantities and dates for partialdeliveries

  • 8/10/2019 ASAP Methodology SAP

    29/50

    January 2007 (v1.0) The Rushmore Group, LLC 29

    SD Process: Sales Order

    The sales order contains all of the informationneeded to process your customers request, the

    following information is determined for each sales

    order:

    Delivering Schedule

    Shipping point and route determination

    Availability Check

    Transfer of requirements to MRP Pricing

    Credit limit check

  • 8/10/2019 ASAP Methodology SAP

    30/50

    January 2007 (v1.0) The Rushmore Group, LLC 30

    Sales Order: Delivery Scheduling

    When an order is created the you must enter arequested delivery date for the order or each line

    item.

    The system will then determine a delivery timeline,

    this will be used when determining our material

    availability, or ATP (Availablity to Promise) date.

    The system will determine this date using forward

    and backward scheduling rules you have defined.

  • 8/10/2019 ASAP Methodology SAP

    31/50

    January 2007 (v1.0) The Rushmore Group, LLC 31

    Sales Order: Backward Scheduling

    Requested

    Delv. Date

    GoodsIssueLoading

    Material

    Availability

    OrderDate

    Transp.

    Sched.

    TransitTime

    (2 days)

    LoadingTime

    (1 day)

    Pick & PackTime

    (2 days)

    Transp.Sched.Time

    (1 day)

    2nd 3rd 4th 5th 6th1st

  • 8/10/2019 ASAP Methodology SAP

    32/50

    January 2007 (v1.0) The Rushmore Group, LLC 32

    Sales Order: Forward Scheduling

    Transit

    Time

    (2 days)

    Loading

    Time

    (1 day)

    Transp.Sched.Time

    (1 day)

    New

    Delv.

    Date

    1st 3rd 4th 5th 6th2nd

    Pick & Pack

    Time (2 days)

    7th

    Requested

    Delv.

    DateGoodsIssueLoading

    Material

    Availability

    OrderDate

    Transp.

    Sched.

  • 8/10/2019 ASAP Methodology SAP

    33/50

    January 2007 (v1.0) The Rushmore Group, LLC 33

    Sales Order: Shipping & Route Determination

    During the creation of the sales order the system mustdetermine the shipping point from which the material will be

    shipped and the route the material will take to get from your

    warehouse to your customers location.

    A shipping point is determined for each line item within theorder.

    The route determination will is used to define the transit

    time of the material that we used in scheduling.

  • 8/10/2019 ASAP Methodology SAP

    34/50

    January 2007 (v1.0) The Rushmore Group, LLC 34

    Sales Order: Availability Check

    Availability Check Determines the material

    availability date

    Considers all inward andoutward inventory

    movements Proposes 3 methods of

    delivery One-time delivery

    Complete delivery

    Delayed proposal

    Rules are created by YOU

  • 8/10/2019 ASAP Methodology SAP

    35/50

    January 2007 (v1.0) The Rushmore Group, LLC 35

    Sales Order: Transfer to Planning

    The order is transferred to Material Requirements Planningas an (CIR) Customer Independent Requirement. If a

    deficit is found the system will propose a Purchase Req. or

    Order to fulfill the shortage.

  • 8/10/2019 ASAP Methodology SAP

    36/50

    January 2007 (v1.0) The Rushmore Group, LLC 36

    Sales Order: Pricing

    The system displays pricing information for all salesdocuments on the pricing screens at both the header and

    the line item level.

    Header pricing is valid for the whole order it is the cumulitive of all

    line items within the order

    Line item pricing is for each specific material.

    The system will automatically search for price, discounts,

    surcharges, calculate taxes and freight. You have the

    ability to manually manipulate the pricing at both the header

    and line item level within the sales order by entering acondition type and amount.

    Taxes and freight can be set-up so we cant manually enter.

  • 8/10/2019 ASAP Methodology SAP

    37/50

    January 2007 (v1.0) The Rushmore Group, LLC 37

    Sales Order: Credit Check

    Allows your company to manage its credit exposure and risk for eachcustomer by specifying credit limits.

    During the sales order process the system will alert the sales rep about

    the customers credit situation that arises, if necessary the system can

    be configured to block orders and deliveries.

  • 8/10/2019 ASAP Methodology SAP

    38/50

    January 2007 (v1.0) The Rushmore Group, LLC 38

    SD Process: Shipping & Transportation

    The shipping process begins when you create thedelivery documentfor the sales order. This

    document controls, supports, and monitors

    numerous sub-processes for shipping processing:

    Picking

    Packing

    Post Goods Issue

    Integrated with the Material Management (MM) andFinance (FI) modules

  • 8/10/2019 ASAP Methodology SAP

    39/50

    January 2007 (v1.0) The Rushmore Group, LLC 39

    SD Process: Shipping

    Order

    Combination

    Sales Order 1

    Sales Order 2

    Sales Order 3

    Delivery 812

    Partial

    Delivery

    Sales Order 4

    Delivery 813

    Delivery 814

    Delivery 815

    Complete

    Delivery

    Sales Order 5

    Delivery 816

  • 8/10/2019 ASAP Methodology SAP

    40/50

    January 2007 (v1.0) The Rushmore Group, LLC 40

    SD Process: Delivery Creation

    Checks order and materials to determine if adelivery is possible delivery block (hold),

    completeness

    Confirms availability

    Confirms export/foreign trade requirements

    Determines total weight & volume

  • 8/10/2019 ASAP Methodology SAP

    41/50

    January 2007 (v1.0) The Rushmore Group, LLC 41

    SD Process: Delivery Creation

    Generates packing proposal Calculates weight and volume

    Checks scheduling

    Considers partial deliveries

    Updates route assignment

    Assigns picking location

    Determines batches

    Quality check (if needed)

    Updates sales order

    S

  • 8/10/2019 ASAP Methodology SAP

    42/50

    January 2007 (v1.0) The Rushmore Group, LLC 42

    SD Process: Delivery Document

    The Delivery Document initiates the deliveryprocess and is the control mechanism for this

    process Picking

    Packing Loading

    Posting Goods Issue

    Changes to delivery are allowable - products,

    quantities

    D li Pi ki

  • 8/10/2019 ASAP Methodology SAP

    43/50

    January 2007 (v1.0) The Rushmore Group, LLC 43

    Delivery: Picking

    Quantities based on delivery note Assigned date when picking should begin

    Automated storage location assignment

    Supports serial number/lot number tracking andbatch management

    Integrated with Warehouse Management (WM)

    D li L di d P ki

  • 8/10/2019 ASAP Methodology SAP

    44/50

    January 2007 (v1.0) The Rushmore Group, LLC 44

    Delivery: Loading and Packing

    Identifies which packaging is to be used forspecified products (customer preference and UCC-

    128 considerations)

    Identifies and updates accounts associated with

    returnable packaging

    Tracks the packed product by container

    Insures weight/volume restrictions are enforced

    All packed items are assigned to the requiredmeans of transportation

    D li G d I

  • 8/10/2019 ASAP Methodology SAP

    45/50

    January 2007 (v1.0) The Rushmore Group, LLC 45

    Delivery: Goods Issue

    Event that indicates the legal change in ownershipof the products

    Reduces inventory and enters Cost of Goods Sold

    Automatically updates the General Ledger (G/L)

    accounts

    Ends the shipping process and updates the status

    of the shipping documents

    SD P Billi

  • 8/10/2019 ASAP Methodology SAP

    46/50

    January 2007 (v1.0) The Rushmore Group, LLC 46

    SD Process: Billing

    The billing document is created by coping datafrom the sales order and/or delivery document.

    Order-based billing

    Delivery-based billing

    The billing process is used to generate the

    customer invoice.

    It will update the customers credit status.

    SD P Billi D t

  • 8/10/2019 ASAP Methodology SAP

    47/50

    January 2007 (v1.0) The Rushmore Group, LLC 47

    SD Process: Billing Documents

    The billing document willautomatically create a debit

    posting to your customer

    sub-ledger account and

    credit your revenue account.

    It is at this point that the

    sales process is passed over

    to Financial Accounting to

    await payment.

    SD P Billi M th d

  • 8/10/2019 ASAP Methodology SAP

    48/50

    January 2007 (v1.0) The Rushmore Group, LLC 48

    SD Process: Billing Methods

    Collective

    Invoicing

    Delivery based

    Invoicing

    Delivery 834

    Delivery 833

    Order 14

    Order 9

    Delivery 856

    Invoice 968

    Order 6Delivery 820

    Delivery 821

    Invoice 945

    Invoice 946

    Split

    InvoicingOrder 32 Delivery 886

    Invoice 992

    Invoice 991

    SD P P t

  • 8/10/2019 ASAP Methodology SAP

    49/50

    January 2007 (v1.0) The Rushmore Group, LLC 49

    SD Process: Payment

    Payment is the final step in the sales order process, thisstep is managed by the Financial Accounting

    department.

    Final payment includes:

    Posting payments against invoices.

    Reconciling differences between payment and invoice.

    Payment will create a posting clearing the liability in the

    A/R account and decreasing your bank account.

    SD P D t Fl

  • 8/10/2019 ASAP Methodology SAP

    50/50

    January 2007 (v1 0) The Rushmore Group LLC 50

    SD Process: Document Flow

    The document flow andorder status feature allows

    you to find the status of an

    order at any point in time.

    The SAP updates the order

    status every time a change

    is made to any document

    created in the customer

    order management cycle

    (Order-to-Cash).