architect’s field report van h. gilbert architect … field repor… · architect’s field...
TRANSCRIPT
ARCHITECT’S FIELD REPORT VAN H. GILBERT ARCHITECT PC
2428 Baylor Drive SE
Albuquerque, NM 87106
Project: East Grand Plains Elementary School Report No: 7
Date: October 26, 2011 Time: 10:00 a.m. Weather: Sunny
Temperature: 80 degrees
PRESENT AT SITE: Kevin Dillon, Roswell Independent School District
Damon Armstrong, John King, Rod Shaw; PSFA
Drew Dacy, Wayne Dacy, Paul Dacy; DDC Inc.
James Dunn, Mark Fitzwater; J & G Electric
John Scott, Rhodes Company
Andy Benson, VHGA
WORK IN PROGRESS: Electrical rough-in of Phase 1 is approximately 75% complete. Drywall subs are drywalling
one side of walls. A color sample has been placed in the restrooms for the Principal to look at for the polished concrete.
Plumbing rough-in for Phase 1 appears to be 100% complete. Soffit trim work is being completed on Phase 1.
Insulation has been installed. Kitchen rough-in plumbing is 50% complete. Mechanical rough-in in the cafeteria is 70%
complete. Site work is being completed on the MCR on the grading and paving. Framing contractor is on site,
approximately 90% complete in Phase 1. Kauffman Fire Protection is also on site, approximately 75% complete.
OBSERVATIONS:
1. A sample of the stained concrete floor was reviewed as in the restroom. Kevin Dillon and Andy agreed the
sample had a good quality and good appearance. Later the sample was reviewed with Elisa, the Principal, who
had decided to select a different color. “Sumatra Brown” is the color that she would like to use and there was a
request made by the principal that a 25 percent, 50 percent and 75 percent sample be provided. The sample will
be reviewed by Elisa and selection can be made at that time.
2. The gymnasium building was reviewed at the exterior walls to determine how the stucco could be applied over
the insulation. It was determined that the foam insulation on the exterior walls would need to be mechanically
fastened in order to provide an acceptable substrate for the stucco finish.
3. A scissor lift was provided to look above the ceiling in the gymnasium. The existing angle iron trusses were
reviewed and measured. A solution for hanging the backstops will be provided. The intent will be for two
I-beams to span from the exterior masonry wall to the top of the bottom cord of the steel truss. The structure of
the basketball goals can be suspended from those wide flange beams.
4. The soffit panels around the exterior of the building were reviewed. Existing panels showed some with fence and
some without fence. It’s requested that all soffit panels be including vents. It’s best for the space underneath the
roof surface to be vented in all locations.
5. The ceiling in the cafeteria will be lowered to a height of 12’ to make room for the fire protection and ductwork.
6. Kevin Dillon reviewed the flush valve control sensors and determined that the specified item will work for the
District.
7. The contractor was concerned that the wood doors may not be arriving on schedule and has requested that the
existing wood doors for the classrooms be utilized until the new ones arrive. All agreed this would acceptable.
8. There is a ramp in the corridor that is a 1 in 12 slope. A review of ANSI A-117.1 – 2009 indicated a handrail will
be required on the North wall of the corridor for the full length of the ramp. 12” handrail extensions are not
required because of an exception for renovations.
Cc: Kevin Dillon, Joe Baca; RISD
John King, Rod Shaw; PSFA
Paul Dacy, Wayne Dacy, Drew Dacy; DDC
Attachment: Site Photographs (22 images)