Applications of Microgrid for Remote Areas in Indonesia
Pekik Argo Dahono
School of Electrical Engineering and Informatics
Institute of Technology Bandung
INDONESIA
Newcastle 2017
Electrification Ratio
Newcastle 2017
35000 MW Program – to respond sectors challange
• To fulfill growing demand for electricity which is still quite high (8.7% per year) and to promote national economic growth target 7% in 2019.
• To Increase the target of kWh per-capita by1,293 kWh in 2019.
• To achieve the target of electricity ratio by 97.35% in 2019.
2015 2019
Installed capacity of Power Plant (GW) 55.5 98.4
economic growth (%) 4.7 7
kWh per-capita (kWh) 910 1.293
of electricity ratio (%) 88.30 97.35Newcastle 2017
Distribution of 35000MW Projects
Newcastle 2017
Progress of 35.000MW as of December 2016
Newcastle 2017
Progress for Electricity Transmission
Newcastle 2017
Energy Mix
Newcastle 2017
Renewable Energy in 2017-2026 Electricity National Plan
Newcastle 2017
Existing PV Power Generation (Total 9 MW)
Newcastle 2017
Independent PV Power Producers(in Operation)
Newcastle 2017
Independent PV Power Producers (Approved)
In addition, there are tota 5 MWp PV power plants constructed under government budget that will be delivered to local government.
Newcastle 2017
New PV Power Generation Systems in New 2017-2027 Elecitrity National Plan (Draft)
Newcastle 2017
Various Supports and Barriers to the Use of Microgrids
• Ministry of Energy Regulation No 50/2017
• Inviting private sectors to develop microgrids (mini PLN), for remote areas and islands
• PV rooftop and solar home system projects according to the regulation of PLN, No 0733/2013.
• Inviting private sectors to develop a hybrid system for remote areas and islands through BtoB scheme.
Newcastle 2017
Hybrid ( PV-Wind-Diesel ) Power Plant
Wind
Turbine
PV Array
Battery
BankGenset
Solar
Charge
Controller
DC BUS AC BUS
Bidirectional
Inverter / Charger
Control Module
Hybrid Power Conditioner (HPC)
Site Load
Wind
Controller
Hybrid (PV-Diesel) in Bou, North Sulawesi
Newcastle 2017
Wind-Solar-Diesel Nusa Penida Microgrid
Wind Plant
9 x 80 kW
Diesel Plant
Jungut Batu
340 kW
Feeder
Tanglad
Feeder
Lembongan
Feeder
Karangsari
Diesel Plant
Kutampi
2210 kW
Vila
Mutiara
Bali HiPDAM
PENIDA
CENINGAN
LEMBONGAN
Nusa Penida has been declaredas self-sufficient energy island
Newcastle 2017
Pilot Plant – Sumba Smart MicrogridFor Renewable Energy Integration
Newcastle 2017
Microgrid for Remote Areas
Tower-Tower500 m
Load cluster 1
Load cluster 2
Load cluster 3
Load cluster 4
Newcastle 2017
Centralized PV Offgrids
Newcastle 2017
Centralized PV offgrid
Newcastle 2017
Barriers to the Use of Microgrids and Renewable Energy
• Lack of human resources
• Lack of capabilities of local people to pay electrical bill
• Poor coordination between central and local governments
• Vandalism
Newcastle 2017