Applications of Microgrid for Remote Areas in Indonesia

Pekik Argo Dahono

School of Electrical Engineering and Informatics

Institute of Technology Bandung

INDONESIA

Newcastle 2017

Page 2: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Electrification Ratio

Newcastle 2017

Page 3: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

35000 MW Program – to respond sectors challange

• To fulfill growing demand for electricity which is still quite high (8.7% per year) and to promote national economic growth target 7% in 2019.

• To Increase the target of kWh per-capita by1,293 kWh in 2019.

• To achieve the target of electricity ratio by 97.35% in 2019.

2015 2019

Installed capacity of Power Plant (GW) 55.5 98.4

economic growth (%) 4.7 7

kWh per-capita (kWh) 910 1.293

of electricity ratio (%) 88.30 97.35Newcastle 2017

Page 4: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Distribution of 35000MW Projects

Newcastle 2017

Page 5: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Progress of 35.000MW as of December 2016

Newcastle 2017

Page 6: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Progress for Electricity Transmission

Newcastle 2017

Page 7: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Energy Mix

Newcastle 2017

Page 8: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Renewable Energy in 2017-2026 Electricity National Plan

Newcastle 2017

Page 9: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Existing PV Power Generation (Total 9 MW)

Newcastle 2017

Page 10: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Independent PV Power Producers(in Operation)

Newcastle 2017

Page 11: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Independent PV Power Producers (Approved)

In addition, there are tota 5 MWp PV power plants constructed under government budget that will be delivered to local government.

Newcastle 2017

Page 12: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

New PV Power Generation Systems in New 2017-2027 Elecitrity National Plan (Draft)

Newcastle 2017

Page 13: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Various Supports and Barriers to the Use of Microgrids

• Ministry of Energy Regulation No 50/2017

• Inviting private sectors to develop microgrids (mini PLN), for remote areas and islands

• PV rooftop and solar home system projects according to the regulation of PLN, No 0733/2013.

• Inviting private sectors to develop a hybrid system for remote areas and islands through BtoB scheme.

Newcastle 2017

Page 14: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Hybrid ( PV-Wind-Diesel ) Power Plant

Wind

Turbine

PV Array

Battery

BankGenset

Solar

Charge

Controller

DC BUS AC BUS

Bidirectional

Inverter / Charger

Control Module

Hybrid Power Conditioner (HPC)

Site Load

Wind

Controller

Hybrid (PV-Diesel) in Bou, North Sulawesi

Newcastle 2017

Page 15: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Wind-Solar-Diesel Nusa Penida Microgrid

Wind Plant

9 x 80 kW

Diesel Plant

Jungut Batu

340 kW

Feeder

Tanglad

Feeder

Lembongan

Feeder

Karangsari

Diesel Plant

Kutampi

2210 kW

Vila

Mutiara

Bali HiPDAM

PENIDA

CENINGAN

LEMBONGAN

Nusa Penida has been declaredas self-sufficient energy island

Newcastle 2017

Page 16: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Pilot Plant – Sumba Smart MicrogridFor Renewable Energy Integration

Newcastle 2017

Page 17: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Microgrid for Remote Areas

Tower-Tower500 m

Load cluster 1

Load cluster 2

Load cluster 3

Load cluster 4

Newcastle 2017

Page 18: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Centralized PV Offgrids

Newcastle 2017

Page 19: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Centralized PV offgrid

Newcastle 2017

Page 20: Applications of Microgrid for Remote Areas in Indonesiamicrogrid-symposiums.org/wp-content/uploads/2017/08/... · 2017-11-09 · Installed capacity of Power Plant (GW) 55.5 98.4 economic

Barriers to the Use of Microgrids and Renewable Energy

• Lack of human resources

• Lack of capabilities of local people to pay electrical bill

• Poor coordination between central and local governments

• Vandalism