Application for Approval of details reserved by Condition Town and Country Planning Act 1990 Planned (Listed Buildings and Conservation Areas) Act 1990 Discharge of Condition Application No. 11 : Supplementary information in relation to Planning Application WDC / 17CC015 No. Condition Documents to Discharge Condition Application for Full or Partial Discharge 16 No development shall commence until a programme detailing the proposed phasing and likely duration of the works required to deliver this development has been submitted to and approved in writing by the County Planning Authority. The programme shall include satisfactory details of, at least, the following phases:- a. Initial Site mobilisation; b. Any demolition of existing structures; c. Construction of new slip roads; d. Construction of realigned existing slip roads; and e. Construction of new structures. A46_Stoneleigh_JIS_2B_Condition_16.pdf A46_SJI_2B_With Factors_ref WF09-C.PDF Confirmation email from Kier No 1 Confirmation email from Kier No 2 Full Discharge

Upload: others

Post on 09-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Application for Approval of details reserved by Condition Town and Country Planning Act 1990

Planned (Listed Buildings and Conservation Areas) Act 1990

Discharge of Condition Application No. 11 : Supplementary information in relation

to Planning Application WDC / 17CC015

No. Condition Documents to Discharge Condition Application for Full or Partial

Discharge

16

No development shall commence until a programme detailing the proposed phasing and likely duration of the works required to deliver this development has been submitted to and approved in writing by the County Planning Authority. The programme shall include satisfactory details of , at least, the following phases:- a. Initial Site mobilisation; b. Any demolition of existing structures; c. Construction of new slip roads; d. Construction of realigned existing slip roads; and e. Construction of new structures.

• A46_Stoneleigh_JIS_2B_Condition_16.pdf

• A46_SJI_2B_With Factors_ref WF09-C.PDF

• Conf irmation email f rom Kier No 1

• Conf irmation email f rom Kier No 2

Full Discharge

Page 2: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Mr DANNY

GREEN

WARWICKSHIRE COUNTY COUNCIL

BARRACK STREET

WARWICK

WARWICKSHIRE

ENGLAND

CV34 4SX

Page 3: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

C:\DesignServices\9.2\A46\083\6 Documents Received\6-41 Colas-SIAC\2020-05-19 Final CPP for LPA

432049 273571

EXISTING JUNCTION OF THE A46 & STONELEIGH ROAD,

STONELEIGH

MAJOR IMPROVEMENT OF THE STONELEIGH JUNCTION ON THE A46 BETWEEN COVENTRY & WARWICK THROUGH

INTRODUCTION OF A GYRATORY LAYOUT WITH TWO BRIDGE ROUNDABOUT & ANCILLARY WORKS TO THE ADJACENT

HIGHWAY

WDC / 17CC015

16) Phasing and likely duration of works

Refer to the attached document for the list of the enclosed documents to the condition discharge, entitled Discharge of

Condition Application No. 11 : Supplementary information in relation to Planning Application WDC / 17CC015

X

17/07/2018

Page 4: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

23/06/2020

DANNY GREEN

[email protected]

01926 412313

X

X

Page 5: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

1

Danny Green

From:

Sent:

To:

Cc:

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals

and RAMS

Importance: High

Hi Mark,

Following a review of the latest revision of the TTM proposal for A46 Stoneleigh Jct Improvements, I can confirm

that all Standard and Relaxation designs are acceptable for use.

Please forward any subsequent revisions/design changes for review.

Many Thanks

Paul Willis

TM Designer/TSCO (HS2)

Kier Highways I Strategic Highways Motorway Maintenance Compound , Seighford Road, Doxey, Stafford, ST18 9LG

M: 07892 702 892 I www.kier.co.uk

Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused Kier Highways Limited I Registered in England No. 5606089 Registered Office: 81 Fountain Street, Manchester, M2 2EE

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Afternoon both, I have reviewed the rolled up programme and confirm that it identifies the phases listed in Condition 16 below. However, not sure that it satisfies the ‘satisfactory details’ requirement as the level of detail required is not defined.

Page 6: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

2

Regards, Mark

____________________________________

Mark Winthorpe Construction Manager (Area 9 ASC) Kier Highways I Strategic Highways I McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham B4 7LR M: 07980 809 922 I www.kier.co.uk

From: THREADGOLD, Russell - Ext (Colas Ltd) [mailto:[email protected]]

Sent: 15 June 2020 19:08

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Hi Mark

Thanks for reviewing the Programme (Condition 16) & RAMS (Condition 21).

Programme (Condition 16) - See attached rolled up programme. This shows only the highest level of detail for the

project. We acknowledge that there is still some fine tuning of the detailed programme to do, to cross reference the

TM drawings against all the TM activity bars. However we propose to send the attached rolled up programme only

for discharge.

RAMS (Condition 21) - We have also received comments back from WCC – Neil Spencer on the RAMS, and will be

addressing both your comments and Neil’s over the next couple of days, then will be sending this condition to WCC

for discharge.

TM phasing’s (Condition 19) – These will be submitted via ‘We transfer’ in the next email, to Paul Willis, following

the latest review of the drawings package between Iain Campbell & Paul on 22-05-2020

Regards

Page 7: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

3

Russ

Subject: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Security warning : Do not click on the links or attachments contained in this message unless you are sure of the

sender’s address.

Afternoon both, I spoke to Russell Threadgold yesterday and he agreed to arrange for the updated TM proposals to be issued for review following the discussions between the Kier TM Designer, Paul Willis with the Colas TM Designer, Ian Campbell. He also advised that there were no fundamental changes and therefore the revised TM arrangements would not have an impact on the Construction Programme (Condition 16) and RAMS (Condition 21). Russell agreed to issue a rolled up programme for the purposes of Condition 16 as discussed at the meeting on 27th May but I agreed to review the attached more detailed programme. Construction Programme

The programme in its current format satisfies the above Condition but as previously agreed contains too much detail for sharing with external parties. The programme detail needs to be reviewed/approved by WCC as Project Manager for construction of the junction improvement scheme. The programme should not be formally accepted until the associated traffic management arrangements are accepted taking account of the potential impact on the A46 (Highways England network). In this regard, some of the TM drawing references need to be completed to ensure there is clarity on what arrangements will be in place for each phase of the works. This needs to be consistent with the attached Construction Methodology, Phases & Risks document. Risk Assessment and Method Statement

Page 8: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

4

The attached Construction Methodology, Phases & Risks document sets out the construction phasing and associated traffic management arrangements. Specific comments and aspects that need to be reviewed/addressed as follows;

1. It includes a summary programme which is consistent with the more detailed construction programme discussed above.

2. The document confirms adherence to Highways England’s NOMS procedure but the reference to Kier (Page 6) needs removing – management of NOMS is now a HE function.

3. There is confirmation that any temporary works that potentially affects the public will be subject to Technical

approval in accordance with CG 300.

4. Each phase of the works and associated construction methodology is described in a reasonable amount of detail and the associated traffic management arrangements are defined.

5. TM drawing references will need to be amended to reflect the final/approved layouts. The TM drawing

extract on Page 17 may need changing for consistency with the final drawing.

6. The document confirms the new bridge deck will be constructed off-line to minimise the impact on the SRN and reduce the risks to workers. It also reduces the overall construction period due to a greater degree of concurrent working.

7. Movement and installation of the deck is described in sufficient detail to provide an understanding of how this

will be achieved including the effect on the SRN.

8. Section 7 identifies the significant risks to the successful delivery of the project. However, the time required to obtain Technical Approval for temporary works should not be underestimated – for Area 9 works this typically takes 6 months!

9. Item 8 in the risk table should be revised to make reference to the latest Government guidelines which take

precedence over the CLC guidance. https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19/construction-and-other-outdoor-work

Subject to incorporation of some minor amendments to address issues identified above I am content that Condition 21 would be satisfied. Regards, Mark

____________________________________

Mark Winthorpe Construction Manager (Area 9 ASC) Kier Highways I Strategic Highways I McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham B4 7LR M: 07980 809 922 I www.kier.co.uk Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused Kier Highways Limited I Registered in England No. 5606089 Registered Office: 81 Fountain Street, Manchester, M2 2EE

This email is sent on behalf of Kier Group. This email and any attachments are confidential and intended solely for

the use of the individual to whom they are addressed. If you are not the addressee, please do not use or publish its

contents; please notify the sender immediately that you have received the email and then delete it. Contracts

cannot be concluded with us nor services effected by email. Emails are not secure and may contain viruses, you are

advised to scan all messages for viruses with your own anti-virus programme. Kier Group may monitor emails. If you

are the intended recipient of the email, upon receipt it is your responsibility to ensure that you comply with data

protection laws that govern its processing and Kier Group policy where appropriate.

Page 9: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

1

Danny Green

From:

Sent:

To:

Cc:

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals

and RAMS

Attachments: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals

and RAMS

Security warning : Do not click on the links or attachments contained in this message unless you are sure of the

sender’s address.

Afternoon both, The TM proposals have now been reviewed and confirmed as acceptable – see attached. Subject to WCC as the NEC Project Manager for the construction contract being content with the proposals, Condition 19 (included below) should be satisfied.

Regards, Mark

____________________________________

Mark Winthorpe Construction Manager (Area 9 ASC) Kier Highways I Strategic Highways I McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham B4 7LR M: 07980 809 922 I www.kier.co.uk

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Afternoon both,

Page 10: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

2

I have reviewed the rolled up programme and confirm that it identifies the phases listed in Condition 16 below. However, not sure that it satisfies the ‘satisfactory details’ requirement as the level of detail required is not defined.

Regards, Mark

____________________________________

Mark Winthorpe Construction Manager (Area 9 ASC) Kier Highways I Strategic Highways I McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham B4 7LR M: 07980 809 922 I www.kier.co.uk

Subject: RE: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Hi Mark

Thanks for reviewing the Programme (Condition 16) & RAMS (Condition 21).

Programme (Condition 16) - See attached rolled up programme. This shows only the highest level of detail for the

project. We acknowledge that there is still some fine tuning of the detailed programme to do, to cross reference the

TM drawings against all the TM activity bars. However we propose to send the attached rolled up programme only

for discharge.

RAMS (Condition 21) - We have also received comments back from WCC – Neil Spencer on the RAMS, and will be

addressing both your comments and Neil’s over the next couple of days, then will be sending this condition to WCC

for discharge.

TM phasing’s (Condition 19) – These will be submitted via ‘We transfer’ in the next email, to Paul Willis, following

the latest review of the drawings package between Iain Campbell & Paul on 22-05-2020

Page 11: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

3

Regards

Russ

Subject: WCC-Colas/SIAC Ltd, WDC-17CC015 – Construction Programme, TM Proposals and RAMS

Security warning : Do not click on the links or attachments contained in this message unless you are sure of the

sender’s address.

Afternoon both, I spoke to Russell Threadgold yesterday and he agreed to arrange for the updated TM proposals to be issued for review following the discussions between the Kier TM Designer, Paul Willis with the Colas TM Designer, Ian Campbell. He also advised that there were no fundamental changes and therefore the revised TM arrangements would not have an impact on the Construction Programme (Condition 16) and RAMS (Condition 21). Russell agreed to issue a rolled up programme for the purposes of Condition 16 as discussed at the meeting on 27th May but I agreed to review the attached more detailed programme. Construction Programme

The programme in its current format satisfies the above Condition but as previously agreed contains too much detail for sharing with external parties. The programme detail needs to be reviewed/approved by WCC as Project Manager for construction of the junction improvement scheme. The programme should not be formally accepted until the associated traffic management arrangements are accepted taking account of the potential impact on the A46 (Highways England network). In this regard, some of the TM drawing references need to be completed to ensure there is clarity on what arrangements will be in place for each phase of the works. This needs to be consistent with the attached Construction Methodology, Phases & Risks document. Risk Assessment and Method Statement

Page 12: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

4

The attached Construction Methodology, Phases & Risks document sets out the construction phasing and associated traffic management arrangements. Specific comments and aspects that need to be reviewed/addressed as follows;

1. It includes a summary programme which is consistent with the more detailed construction programme discussed above.

2. The document confirms adherence to Highways England’s NOMS procedure but the reference to Kier (Page 6) needs removing – management of NOMS is now a HE function.

3. There is confirmation that any temporary works that potentially affects the public will be subject to Technical

approval in accordance with CG 300.

4. Each phase of the works and associated construction methodology is described in a reasonable amount of detail and the associated traffic management arrangements are defined.

5. TM drawing references will need to be amended to reflect the final/approved layouts. The TM drawing

extract on Page 17 may need changing for consistency with the final drawing.

6. The document confirms the new bridge deck will be constructed off-line to minimise the impact on the SRN and reduce the risks to workers. It also reduces the overall construction period due to a greater degree of concurrent working.

7. Movement and installation of the deck is described in sufficient detail to provide an understanding of how this

will be achieved including the effect on the SRN.

8. Section 7 identifies the significant risks to the successful delivery of the project. However, the time required to obtain Technical Approval for temporary works should not be underestimated – for Area 9 works this typically takes 6 months!

9. Item 8 in the risk table should be revised to make reference to the latest Government guidelines which take

precedence over the CLC guidance. https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19/construction-and-other-outdoor-work

Subject to incorporation of some minor amendments to address issues identified above I am content that Condition 21 would be satisfied. Regards, Mark

____________________________________

Mark Winthorpe Construction Manager (Area 9 ASC) Kier Highways I Strategic Highways I McLaren Building, 2nd Floor, 46 Priory Queensway, Birmingham B4 7LR M: 07980 809 922 I www.kier.co.uk Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused Kier Highways Limited I Registered in England No. 5606089 Registered Office: 81 Fountain Street, Manchester, M2 2EE

This email is sent on behalf of Kier Group. This email and any attachments are confidential and intended solely for

the use of the individual to whom they are addressed. If you are not the addressee, please do not use or publish its

contents; please notify the sender immediately that you have received the email and then delete it. Contracts

cannot be concluded with us nor services effected by email. Emails are not secure and may contain viruses, you are

advised to scan all messages for viruses with your own anti-virus programme. Kier Group may monitor emails. If you

Page 13: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

5

are the intended recipient of the email, upon receipt it is your responsibility to ensure that you comply with data

protection laws that govern its processing and Kier Group policy where appropriate.

Page 14: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

TotalTotal 27-Jul-20 409 25-Mar-22

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002)2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002)27-Jul-20 409 25-Mar-22

MilestonesMilestones 27-Jul-20 409 25-Mar-22

Main Works PhaseMain Works Phase 27-Jul-20 319 05-Nov-21

MobilisationMobilisation 27-Jul-20 130 08-Feb-21

ProcurementProcurement 27-Jul-20 130 08-Feb-21

UtilitiesUtilities 27-Jul-20 80 16-Nov-20

EstablishmentEstablishment 27-Jul-20 25 28-Aug-20

Highway SectionsHighway Sections 17-Aug-20 304 05-Nov-21

Southbound On SlipSouthbound On Slip 19-Jun-21 79 08-Oct-21

Southbound Off SlipSouthbound Off Slip 17-Aug-20 269 17-Sep-21

Stoneleigh Road EastStoneleigh Road East 24-Aug-20 299 05-Nov-21

Northbound On SlipNorthbound On Slip 24-Aug-20 229 29-Jul-21

Northbound Off SlipNorthbound Off Slip 10-Jul-21 49 17-Sep-21

Stoneleigh Road West OfflineStoneleigh Road West Offline 24-Aug-20 236 09-Aug-21

Stoneleigh Road West OnlineStoneleigh Road West Online 20-Apr-21 56 08-Jul-21

A46 Under JunctionA46 Under Junction 13-Apr-21 7 22-Apr-21

Main AlignmentMain Alignment 22-Apr-21 50 05-Jul-21

New A46 BridgeNew A46 Bridge 03-Dec-20 154 27-Jul-21

Series 100 - Traffic Management / UtilitiesSeries 100 - Traffic Management / Utilities 03-Dec-20 154 27-Jul-21

West AbutmentWest Abutment 22-Feb-21 97 12-Jul-21

East AbutmentEast Abutment 11-Feb-21 88 21-Jun-21

DeckDeck 22-Feb-21 108 27-Jul-21

Existing A46 StructureExisting A46 Structure 27-Jul-21 72 05-Nov-21

North VergeNorth Verge 27-Jul-21 34 14-Sep-21

South VergeSouth Verge 14-Sep-21 38 05-Nov-21

Westley BridgeWestley Bridge 27-Jul-20 293 30-Sep-21

Series 100 - Traffic Management / UtilitiesSeries 100 - Traffic Management / Utilities 29-Sep-20 202 27-Jul-21

Temporary DesignTemporary Design 01-Sep-20 54 13-Nov-20

Salmonid Period 2020 (Working allowed)Salmonid Period 2020 (Working allowed) 27-Jul-20 293 30-Sep-21

West AbutmentWest Abutment 26-Nov-20 164 02-Aug-21

East AbutmentEast Abutment 10-Dec-20 154 02-Aug-21

DeckDeck 29-Mar-21 53 16-Jun-21

Traffic SignalsTraffic Signals 28-Sep-21 25 02-Nov-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Rolled Up View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF04 08-Jun-20 16:05

Page 1 of 1

Page 15: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

TotalTotal 27-Jul-20 385 22-Feb-22

Project: 2B-A46- CA 27/07/2020 WF09-C 2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002)Project: 2B-A46- CA 27/07/2020 WF09-C 2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002)27-Jul-20 385 22-Feb-22

WBS: 2B-A46- CA 27/07/2020 WF09-C.1 MilestonesWBS: 2B-A46- CA 27/07/2020 WF09-C.1 Milestones 27-Jul-20 385 22-Feb-22

A3130 Main Works Award 27-Jul-20* 0

A3150 Main Works Duration 27-Jul-20 403 22-Feb-22

A5900 Access to Site For Main Works 03-Aug-20* 0

A4800 Main Works Planned Completion 0 05-Nov-21

A4810 Terminal Float 05-Nov-21 67 22-Feb-22

A3140 Main Works Completion Date 0 22-Feb-22

WBS: 2B-A46- CA 27/07/2020 WF09-C.3 Main Works PhaseWBS: 2B-A46- CA 27/07/2020 WF09-C.3 Main Works Phase 27-Jul-20 318 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11 MobilisationWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11 Mobilisation 27-Jul-20 130 08-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2 ProcurementWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2 Procurement 27-Jul-20 130 08-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2.1 MaterialsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2.1 Materials 27-Jul-20 130 08-Feb-21A3160 Place Order and Lead Time for Concrete Beams (Westley Bridge) 27-Jul-20 70 02-Nov-20

A3170 Place Order and Lead Time For Steel Beams (New A46 Bridge) 27-Jul-20 130 08-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2.2 SubcontractorsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.2.2 Subcontractors 27-Jul-20 80 16-Nov-20

A3360 Heavylift Contractor (inc temp design and approval) 27-Jul-20 80 16-Nov-20

A3370 CFA Piling Contractor 27-Jul-20 60 19-Oct-20

A3380 Sheet Piling Contractor (inc temp design and approval) 27-Jul-20 60 19-Oct-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.4 UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.4 Utilities 27-Jul-20 80 16-Nov-20A3290 Give Notice for Severn Trent Main Diversion 27-Jul-20 45 28-Sep-20

A3300 Give Notice for Cadent Gas Main Diversion 27-Jul-20 80 16-Nov-20

A3310 Give Notice for BT Openreach Diversion 27-Jul-20 40 21-Sep-20

A3320 Give Notice for Western Power Distribution Disconnection and Connections 27-Jul-20 40 21-Sep-20

A3330 Give Notice for Vodafone Diversion 27-Jul-20 30 07-Sep-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.3 EstablishmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.11.3 Establishment 27-Jul-20 25 28-Aug-20

D1080 Mark Up site Establishment/ Agree Layout 27-Jul-20 5 31-Jul-20

A3180 Establish Site Compound 03-Aug-20 20 28-Aug-20

B1320 Tree Protection Fencing 03-Aug-20 20 28-Aug-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12 Highway SectionsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12 Highway Sections 17-Aug-20 303 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2 Southbound On SlipWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2 Southbound On Slip 19-Jun-21 77 06-Oct-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.4 Series 400 - VRS 01-Oct-21 3 06-Oct-21

A1190 VRS Adjustments 01-Oct-21 3 06-Oct-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.5 Series 500 - Drainage and Ducting 24-Sep-21 5 01-Oct-21

A1860 Ducting to Verge 24-Sep-21 3 29-Sep-21

A1870 Ducting Across Slip Road 29-Sep-21 2 01-Oct-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.2.7 Series 700 - Pavements 19-Jun-21 1 19-Jun-21

A4550 Tie In Surfacing Into S/B Onlsip and Existing Bridge Deck (TM 04) 19-Jun-21 1 19-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1 Southbound Off SlipWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1 Southbound Off Slip 17-Aug-20 267 15-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1 Series 100 - Traffic Management / Utilities 24-Aug-20 112 10-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.1 Traffic ManagementWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.1 Traffic Management 24-Aug-20 112 10-Feb-21

A1000 Construct Site Access Point Off Stoneliegh Road 24-Aug-20 5 28-Aug-20

A1010 Access Work Site via Stoneleigh Road - Warning Signage Only (TM Drwg No 01) 24-Aug-20 112 10-Feb-21

A1060 A46 Southbound, Off Peak Lane Closures when required (TM Drg No XX) (Off Peak Lane 1 Closures) 25-Nov-20 45 10-Feb-21

A2160 Switch Traffic to New Slip 0 10-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.2 Utility WorksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.2 Utility Works 07-Sep-20 67 09-Dec-20A4920 BPA Site Supervision Required 07-Sep-20 57 25-Nov-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.2.1 Vodafone DiversionWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.1.2.1 Vodafone Diversion 08-Sep-20 66 09-Dec-20

A1040 Protection Works Adjacent to Stoneleigh Road - Vodafone 08-Sep-20 3 10-Sep-20

A1030 Protection Works Adjacent to New A46 Bridge Structure - Vodafone 08-Oct-20 3 12-Oct-20

A1070 Slew Ducting and Chamber Works Adjacent to A46 - Vodafone 25-Nov-20 5 02-Dec-20

A1020 Protection Works Adjacent to A46 Tie In - Vodafone 02-Dec-20 5 09-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.2 Series 200 - Site ClearanceWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.2 Series 200 - Site Clearance 24-Aug-20 0 24-Aug-20

A1080 Vegetation Clearance - Completed During Pre-Construction Phase 24-Aug-20 0

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.3 Series 300 - Fencing 17-Aug-20 49 23-Oct-20

B1260 Permanent/ Temp Site perimeter fencing 17-Aug-20 10 28-Aug-20

A1090 Post and Rail Fencing to verge 08-Oct-20 12 23-Oct-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.4 Series 400 - VRS 16-Dec-20 7 08-Jan-21

A1100 VRS Adjustments 16-Dec-20 7 08-Jan-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.5 Series 500 - Drainage and Ducting 21-Sep-20 202 20-Jul-21

A1490 Filter Drain in Cutting CP58 to CP53 21-Sep-20 9 01-Oct-20

A1480 Filter to Toe of Batter CP53 to RE08 02-Oct-20 5 08-Oct-20

A1580 Filter HW16 to CP44 14-Oct-20 6 21-Oct-20

A1590 HW13 to CP38 20-Oct-20 7 29-Oct-20

A1800 Ducting to New Slip 25-Nov-20 8 04-Dec-20

A1810 Ducting to New Roundabout Area 03-Dec-20 7 14-Dec-20

A1050 Vodafone Ducting to Verge 16-Dec-20 13 18-Jan-21

A1420 Filter Drain to Toe of Roundabout Batter 10-Feb-21 7 19-Feb-21

A1430 Replace Existing Filter Drain 19-Feb-21 3 24-Feb-21

A1500 Filter Drain Replacement to Old Slip Raod 24-Feb-21 13 15-Mar-21

A1820 Ducting to and Across New Bridge Structure 16-Jul-21 2 20-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.6 Series 600 - EarthworksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.6 Series 600 - Earthworks 01-Sep-20 257 15-Sep-21A1970 Topsoil Strip Fill Sections 01-Sep-20 4 04-Sep-20

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 1 of 8Date Revision Checked Approved

Page 16: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

A1990 Build Haul Road Online to Enable Topsoil to Be Removed from Section 01-Sep-20 8 10-Sep-20

B1200 Earthworks Resource (Cut and Fill) 01-Sep-20 14 18-Sep-20

A1980 Topsoil Strip Cut Areas - First Operation For BPA Supervision 07-Sep-20 4 10-Sep-20

A2000 Cut to Formation Inclusive of Road Box and Place Capping 11-Sep-20 6 18-Sep-20

A2010 Place Suitable Cut Material in Lower Fill Areas 11-Sep-20 6 18-Sep-20

A2020 Fill To Subformation and Place Capping, Form Swales 21-Sep-20 13 07-Oct-20

A2030 Topsoil to Batter -Last Operation for BPA Supervision 29-Oct-20 19 25-Nov-20

A2040 Formation Dig and Capping at A46 Tie in Area 25-Nov-20 7 04-Dec-20

A2100 Verge Fill 04-Dec-20 7 16-Dec-20

A2340 Perforate Existing Carriageway and Soil 06-Sep-21 7 15-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.7 Series 700 - Pavements 02-Oct-20 71 25-Jan-21

A2070 Subbase to Cut Area 02-Oct-20 5 08-Oct-20

A2050 Subbase to Fill Area 29-Oct-20 7 06-Nov-20

A2060 Subbase to A46 Tie in area 09-Dec-20 7 17-Dec-20

A2120 Trim Subabse 16-Dec-20 7 07-Jan-21

A2130 Base and Binder 05-Jan-21 7 14-Jan-21

D1000 Prep for Base and Bnder 05-Jan-21 2 07-Jan-21

A2140 Surface Course 14-Jan-21 7 25-Jan-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.8 Series 1100 - Kerbs and Footways 02-Nov-20 61 09-Feb-21

A1760 CKD - KDB30 to 20 02-Nov-20 17 25-Nov-20

A1750 CKD - KDB48 to 47 25-Nov-20 7 03-Dec-20

A1770 CKD - KDB17 to 16 03-Dec-20 4 09-Dec-20

A2090 Kerbing to Splitter Islands 09-Dec-20 4 15-Dec-20

A2080 CKD - KDB30 to 41 17-Dec-20 4 06-Jan-21

A2110 Footway Construction 18-Jan-21 14 04-Feb-21

A1780 CKD - Online Sections 03-Feb-21 4 09-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.9 Series 1200 - Signage and LiningWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.9 Series 1200 - Signage and Lining 16-Dec-20 23 01-Feb-21

A2150 Signage to Slip 16-Dec-20 6 07-Jan-21

A2170 Lining 25-Jan-21 5 01-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.10 Series 1300 - Road LightingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.10 Series 1300 - Road Lighting 16-Dec-20 6 07-Jan-21

A4850 Erect New Street Lighting 16-Dec-20 6 07-Jan-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.12 Series 3000 - Landscaping and EcologyWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.1.12 Series 3000 - Landscaping and Ecology 25-Nov-20 5 02-Dec-20

A4940 Planting and Seeding Works 25-Nov-20 5 02-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3 Stoneleigh Road EastWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3 Stoneleigh Road East 24-Aug-20 298 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.1 Series 100 - Traffic Management / Utilities 24-Aug-20 112 10-Feb-21

A2280 Access Work Site via Stoneleigh Road - Warning Signage Only (TM Drwg No 01) 24-Aug-20 112 10-Feb-21

B1180 Footpath and Footway Closure Notification Period 30-Nov-20 40 08-Feb-21

A2290 Tie In Works - Two Way Traffic Lights (on LNR) (TM Drwg No 09) 03-Feb-21 3 05-Feb-21

B1160 Tie In Works - Two Way Traffic Lights (on LNR) (TM Drwg PC 6a) 05-Feb-21 3 10-Feb-21

B1190 Close Footpath and Footway (Stoneleigh Road East/ West) 08-Feb-21 2 10-Feb-21

A2330 Switch Traffic to New Alignment 0 10-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.3 Series 300 - Fencing 03-Sep-20 5 09-Sep-20

B1270 Permanent/ Temp Site perimeter fencing 03-Sep-20 2 04-Sep-20

A1110 Post and Rail Fencing to verge 07-Sep-20 3 09-Sep-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.4 Series 400 - VRS 03-Dec-20 3 08-Dec-20

A1200 New VRS 03-Dec-20 3 08-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.5 Series 500 - Drainage and Ducting 08-Oct-20 38 30-Nov-20

A1570 HW19 to SRSECP01 08-Oct-20 4 13-Oct-20

A1560 HW17 to HW 15 14-Oct-20 4 19-Oct-20

A1930 Ducting 24-Nov-20 4 30-Nov-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.6 Series 600 - EarthworksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.6 Series 600 - Earthworks 07-Sep-20 64 03-Dec-20

A2190 Topsoil Strip 07-Sep-20 5 11-Sep-20

A2180 Fill to Formation and Place Capping 21-Sep-20 12 06-Oct-20

A2200 Topsoil to Batter 14-Oct-20 3 16-Oct-20

A2210 Verge Fill 30-Nov-20 3 03-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.7 Series 700 - Pavements 09-Nov-20 244 05-Nov-21

A2230 Subbase to Fill Area 09-Nov-20 7 17-Nov-20

A2240 Trim Subabse 17-Nov-20 7 26-Nov-20

A2250 Base and Binder 14-Jan-21 7 25-Jan-21

A2260 Surface Course 25-Jan-21 7 03-Feb-21

A2300 Tie In To Existing Carriageway Nearside (next to existing bridge) 03-Feb-21 3 05-Feb-21

A2350 Tie In to Existing Carriageway Offside (opposite temp site compound) 05-Feb-21 3 10-Feb-21

A2360 Perforate Existing Carriageway and Soil 03-Nov-21 2 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.8 Series 1100 - Kerbs and Footways 17-Nov-20 26 06-Jan-21A1790 CKD - KDB21 to 23 17-Nov-20 5 24-Nov-20

A2270 Footway Construction 03-Dec-20 14 06-Jan-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.9 Series 1200 - Signage and LiningWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.9 Series 1200 - Signage and Lining 03-Dec-20 37 08-Feb-21

A2310 Signage 03-Dec-20 4 09-Dec-20

A2320 Lining 03-Feb-21 3 08-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.10 Series 1300 - Road LightingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.10 Series 1300 - Road Lighting 03-Dec-20 6 11-Dec-20

A4860 Erect Streetlighting 03-Dec-20 6 11-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.12 Series 3000 - Landscaping and EcologyWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.3.12 Series 3000 - Landscaping and Ecology 19-Oct-20 10 30-Oct-20A4950 Planting and Seeding Works 19-Oct-20 10 30-Oct-20

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 2 of 8Date Revision Checked Approved

Page 17: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4 Northbound On SlipWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4 Northbound On Slip 24-Aug-20 228 29-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.1 Series 100 - Traffic Management / Utilities 24-Aug-20 119 19-Feb-21

A2510 Construct Site Access Point Off Stoneliegh Road 24-Aug-20 5 28-Aug-20

A2520 Access Work Site via Stoneleigh Road - Warning Signage Only (TM Drwg No 01) 24-Aug-20 118 18-Feb-21

A4930 BPA Site Supervision Required 01-Sep-20 63 27-Nov-20

B1070 Existing North Bound On Slip Closure for road marking removal Inc Diversion (TM Drwg No 02) 08-Jan-21* 2 11-Jan-21

B1080 Maintain lane 2 running On North Bound on Slip (cylinders) (TM Drwg No 03) 08-Jan-21 30 18-Feb-21

A2530 A46 Northbound, Off Peak Lane Closures when required (TM) (TM Drg No 0XX) (Off Peak Lane 1 Closures)12-Jan-21 28 18-Feb-21

A2540 Switch Traffic to New Slip 0 18-Feb-21

B1100 Removal of TM from existing Northbound on Slip / New works access (TM Drwg No 06) 18-Feb-21 1 19-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.2 Series 200 - Site ClearanceWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.2 Series 200 - Site Clearance 01-Sep-20 0 01-Sep-20

A2500 Vegetation Clearance - Completed During Pre-Construction Phase 01-Sep-20 0

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.3 Series 300 - Fencing 25-Sep-20 9 07-Oct-20

B1280 Permanent/ Temp Site perimeter fencing 25-Sep-20 4 30-Sep-20

A1180 Post and Rail Badger Fencing to verge 01-Oct-20 5 07-Oct-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.4 Series 400 - VRS 10-Feb-21 2 12-Feb-21

A1210 VRS Adjustments 10-Feb-21 2 12-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.5 Series 500 - Drainage and Ducting 01-Sep-20 216 20-Jul-21

A1530 Replace Existing Filter Drain HW21 to CP80 - First Operation Requiring BPA Supervision 01-Sep-20 5 07-Sep-20

A1520 Filter Drain to Toe of Batter 08-Sep-20 17 30-Sep-20

A1540 Carrier CP34 to CP29 18-Nov-20 7 26-Nov-20

A1410 Carrier - HW12 to CP 84/83 26-Nov-20 8 08-Dec-20

A1830 Ducting to New Roundabout Area 29-Jan-21 7 08-Feb-21

A1390 Filter Drain to Toe of Roundabout Batter 07-Jul-21 3 12-Jul-21

A1400 Replace Existing Filter Drain 12-Jul-21 2 14-Jul-21

A1840 Ducting to and Across New Bridge Structure 12-Jul-21 4 16-Jul-21

A1550 Filter Drain to Old Slip 14-Jul-21 4 20-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.6 Series 600 - EarthworksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.6 Series 600 - Earthworks 01-Oct-20 201 29-Jul-21A2370 Topsoil Strip Lower Fill Sections 01-Oct-20 8 12-Oct-20

A2380 Fill To Subformation and Place Capping 13-Oct-20 26 18-Nov-20

A2390 Topsoil to Batter - Last Operation Rquiring BPA Supervision 18-Nov-20 7 27-Nov-20

A2400 Formation Dig and Capping at A46 Tie in Area (TM REF XX) (Off Peak Lane 1 Closures) 12-Jan-21 7 21-Jan-21

A2410 Verge Fill 01-Feb-21 7 10-Feb-21

A2420 Perforate Existing Carriageway and Soil 20-Jul-21 7 29-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.7 Series 700 - Pavements 08-Dec-20 41 18-Feb-21A2430 Subbase to Fill Area 08-Dec-20 7 17-Dec-20

A2440 Subbase to A46 Tie in area (TM REF XX) (Off Peak Lane 1 Closures) 21-Jan-21 7 29-Jan-21

A2450 Trim Subabse 29-Jan-21 7 09-Feb-21

A2460 Base and Binder 29-Jan-21 7 09-Feb-21

A2470 Surface Course 09-Feb-21 7 18-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.8 Series 1100 - Kerbs and Footways 17-Dec-20 120 23-Jun-21

A1730 CKD - KDB33 to 35 17-Dec-20 7 11-Jan-21

A1720 CKD - KDB06 to 32 11-Jan-21 7 19-Jan-21

A1700 CKD - KDB42 to 45 19-Jan-21 5 26-Jan-21

A1690 CKD - KDB01 26-Jan-21* 3 29-Jan-21

A2550 CKD - KDB36 to 35 01-Feb-21 7 09-Feb-21

A2560 Footway Construction 09-Feb-21 7 17-Feb-21

A1710 CKD - Online Sections 21-Jun-21 2 23-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.9 Series 1200 - Signage and LiningWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.9 Series 1200 - Signage and Lining 10-Feb-21 6 18-Feb-21

A2480 Signage to Slip 10-Feb-21 6 18-Feb-21

A2490 Lining 11-Feb-21 5 18-Feb-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.11 Series 1400 - Electrical WorksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.11 Series 1400 - Electrical Works 16-Jul-21 4 22-Jul-21

A4870 Erect New Street Lighting 16-Jul-21 4 22-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.12 Series 3000 - Landscaping and EcologyWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.4.12 Series 3000 - Landscaping and Ecology 27-Nov-20 5 04-Dec-20

A4960 Planting and Seeding Works 27-Nov-20 5 04-Dec-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5 Northbound Off SlipWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5 Northbound Off Slip 10-Jul-21 43 10-Sep-21WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.1 Series 100 - Traffic Management / Utilities 12-Jul-21 43 10-Sep-21

A4330 Traffic Switched to New Roundabout at Top of Roundabout. Reduce to Single Lane (OffPeak?) (TM Drg No 20)12-Jul-21 43 10-Sep-21

B1130 Northbound Off Slip Lane 2 closure (TM Drg no 16) 12-Jul-21 43 10-Sep-21

B1140 Northbound off slip lane 1 closure (TM Drg no 17) 12-Jul-21 43 10-Sep-21

B1150 Northbound off slip full closure (TM Drg no 18) 12-Jul-21 43 10-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.3 Series 300 - Fencing 25-Aug-21 10 09-Sep-21

A1170 Post and Rail Fencing to verge 25-Aug-21 10 09-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.5 Series 500 - Drainage and Ducting 23-Jul-21 29 03-Sep-21

A1460 Replace Existing Drain NBCP05 to NBCP04A 23-Jul-21 3 28-Jul-21

A1470 Carrier NBCP04A to CP48 29-Jul-21 4 05-Aug-21

A1880 Ducting to Verge 25-Aug-21 3 31-Aug-21

A1890 Ducting Across Slip Road 31-Aug-21 3 03-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.6 Series 600 - EarthworksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.6 Series 600 - Earthworks 23-Jul-21 29 03-Sep-21

A4340 Topsoil Strip 23-Jul-21 1 27-Jul-21

B1210 Earthworks resources Northbound Off Slip 23-Jul-21 29 03-Sep-21

A4350 Fill to Formation and Place Capping 27-Jul-21 3 29-Jul-21

A4360 Topsoil to Batter 18-Aug-21 3 23-Aug-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 3 of 8Date Revision Checked Approved

Page 18: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

A4370 Verge Fill Offside 23-Aug-21 2 25-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.7 Series 700 - Pavements 10-Jul-21 42 09-Sep-21

A4560 Plane and Regulate to Tie in Existing Slip to New Roadabout (TM Drg No 20) 10-Jul-21 1 10-Jul-21

A4380 Subabse to Offside Widening 05-Aug-21 3 10-Aug-21

A4890 Base and Binder 03-Sep-21 2 07-Sep-21

A4900 Surface Course 07-Sep-21 2 09-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.8 Series 1100 - Kerbs and Footways 10-Aug-21 6 18-Aug-21A1740 CKD - KDB36 to 37 10-Aug-21 3 13-Aug-21

A4390 Kerbing to Offside 13-Aug-21 3 18-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.9 Series 1200 - Signage and LiningWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.9 Series 1200 - Signage and Lining 09-Sep-21 1 10-Sep-21

A4910 Road Markings 09-Sep-21 1 10-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.10 Series 1300 - Road LightingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.10 Series 1300 - Road Lighting 03-Sep-21 5 10-Sep-21

A4880 Erect New Streetlighting 03-Sep-21 5 10-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.12 Series 3000 - Landscaping and EcologyWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.5.12 Series 3000 - Landscaping and Ecology 23-Aug-21 2 25-Aug-21

A4980 Planting and Seeding Works 23-Aug-21 2 25-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6 Stoneleigh Road West OfflineWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6 Stoneleigh Road West Offline 24-Aug-20 236 09-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.1 Series 100 - Traffic Management / Utilities 24-Aug-20 224 23-Jul-21

A3970 Access Work Site via Stoneleigh Road - Warning Signage Only (TM Drwg No 01) 24-Aug-20 187 02-Jun-21

A4000 BT Diversion Phase 1 22-Sep-20 20 19-Oct-20

A4270 Cadent Gas Diversion 17-Nov-20 40 25-Jan-21

A4010 BT Diversion Phase 2 11-Jun-21 30 23-Jul-21

A4280 Weekend Closure to Stoneliegh Road West and Dalehouse Lane 19-Jun-21 2 20-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.2 Series 200 - Site ClearanceWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.2 Series 200 - Site Clearance 01-Sep-20 5 07-Sep-20

A4050 Vegetation Clearance - Completed During Pre-Construction Phase 01-Sep-20 0

A4060 Root Clearance to Flood Area 01-Sep-20 5 07-Sep-20

A5880 Site Clearance to Flood Compensation Area 01-Sep-20 5 07-Sep-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.3 Series 300 - Fencing 25-Aug-20 210 06-Jul-21

B1290 Permanent/ Temp Site perimeter fencing 25-Aug-20 4 28-Aug-20

A1140 Post and Rail Badger Fencing to verge 04-Jun-21 4 10-Jun-21

A1130 Post and Rail Otter Fencing to verge 21-Jun-21 6 28-Jun-21

A1120 Post and Rail Fencing to verge 29-Jun-21 5 06-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.4 Series 400 - VRS 04-Jun-21 4 10-Jun-21A1220 New VRS 04-Jun-21 4 10-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.5 Series 500 - Drainage and Ducting 06-Oct-20 160 07-Jun-21

A1260 Carrier - HW4 to Pond 3 06-Oct-20* 5 12-Oct-20

A4070 HW3 to RE1 13-Oct-20 5 19-Oct-20

A1250 Filter Drain to Toe of Batter 27-Oct-20 12 11-Nov-20

A3990 Subformation Drainage 11-Nov-20 7 20-Nov-20

A1370 Carrier HW05 to CP24 11-Mar-21 3 16-Mar-21

A1380 Carrier HW 06 to CP27 16-Mar-21 4 22-Mar-21

A1270 Carrier - Pond 2 to Pond 3 01-Apr-21 4 09-Apr-21

A1280 Carrier - CP 5 to CP12 12-Apr-21 5 19-Apr-21

A1290 Carrier - CP18 to CP07 20-Apr-21 3 23-Apr-21

A1300 Filter Drain to Roundabout 23-Apr-21 3 28-Apr-21

A1340 Filter - RE7 to ECP05 05-May-21 2 07-May-21

A1320 Carrier - CP22 to CP20 11-May-21 4 17-May-21

A1940 Ducting in Verges 13-May-21 8 25-May-21

A1950 Ducting in Splitter and Roundabout 25-May-21 8 07-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.6 Series 600 - EarthworksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.6 Series 600 - Earthworks 08-Sep-20 179 04-Jun-21

A5850 Topsoil Strip to Flood Compensation Area (Himalayan Balsam Conta,ination) - Stockpile Local 08-Sep-20 5 14-Sep-20

A5860 Reduce Dig to Flood Compensation Area 15-Sep-20 10 28-Sep-20

A5870 Replace Contaminated Topsoil to Flood Compensation Area 29-Sep-20 5 05-Oct-20

A3980 Excavate and Construct Pond 3 13-Oct-20 10 26-Oct-20

A4020 Topsoil Strip Where Required and Starter Layer to North of Stoneleigh Road, 20-Nov-20 12 07-Dec-20

A4080 Set Aside Contaminated Topsoil 20-Nov-20 7 01-Dec-20

A4030 Fill to Subformation and Cap 07-Dec-20 58 11-Mar-21

A4090 Fill Centre of Roundabout with Contaminated Soil and Seal 02-Mar-21 7 11-Mar-21

A4040 Construct Ponds 1 and 2 11-Mar-21 15 01-Apr-21

A4250 Topsoil to Batters 11-Mar-21 15 01-Apr-21

A4260 Landscape Bunding 01-Apr-21 10 19-Apr-21

A4190 Verge Fill 25-May-21 7 04-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.7 Series 700 - PavementsWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.7 Series 700 - Pavements 19-Apr-21 43 20-Jun-21A4110 Trim Capping and Place Subbase 19-Apr-21 15 11-May-21

A4120 Trim Subbase 17-May-21 4 21-May-21

A4130 Base Course 20-May-21 4 26-May-21

A4140 Binder Course 26-May-21 4 02-Jun-21

A4150 Surface Course 02-Jun-21 2 04-Jun-21

A4170 Tie Ins to Stoneleigh Road (TM Drg No 15) 19-Jun-21 2 20-Jun-21

A4180 Tie In to Dalehouse Road (TM Drg No 14) 19-Jun-21 2 20-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.8 Series 1100 - Kerbs and Footways 26-Apr-21 67 30-Jul-21

A1640 CKD - KDB10 to KDB07 26-Apr-21 3 29-Apr-21

A1650 CKD - KDB4 to KDB02 29-Apr-21 3 05-May-21

A1620 CKD - KDB5 05-May-21 2 07-May-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 4 of 8Date Revision Checked Approved

Page 19: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

A1630 CKD - KDB11 07-May-21 2 11-May-21

A1600 CKD - KDB39 and 12 11-May-21 5 18-May-21

A4100 Kerbs to Splitter Islands 11-May-21 4 17-May-21

A1610 CKD - KDB13 to KDB40 18-May-21 2 21-May-21

A4200 Subase to Footways 07-Jun-21 5 14-Jun-21

A4210 Edgings to Splitters 14-Jun-21 4 18-Jun-21

A1670 CKD - KDB38 to KDB14 21-Jun-21 4 24-Jun-21

A4220 Surfacing to Footways 23-Jul-21 5 30-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.9 Series 1200 - Signage and LiningWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.9 Series 1200 - Signage and Lining 05-Jun-21 1 05-Jun-21

A4160 Lining 05-Jun-21 1 05-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.10 Series 1300 - Road LightingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.10 Series 1300 - Road Lighting 17-May-21 8 27-May-21A4230 Erect Streetlighintg 17-May-21 8 27-May-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.11 Series 1400 - Electrical WorksWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.11 Series 1400 - Electrical Works 07-Jun-21 8 17-Jun-21

A4240 Cabling and Connections to Lights and Signs 07-Jun-21 8 17-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.12 Series 3000 - Landscaping and EcologyWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.6.12 Series 3000 - Landscaping and Ecology 19-Apr-21 79 09-Aug-21

A5000 Planting and Seeding Works (Batters) 19-Apr-21 30 02-Jun-21

D1050 Final Topsoiling and seeding 03-Aug-21 5 09-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7 Stoneleigh Road West OnlineWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7 Stoneleigh Road West Online 23-Apr-21 50 06-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.1 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.1 Series 100 - Traffic Management / Utilities 29-Apr-21 35 19-Jun-21

A4310 Overnight Traffic Temporary Traffic Signals 29-Apr-21 10 14-May-21

A4320 Weekend Closure to Stoneliegh Road West and Dalehouse Lane 19-Jun-21 1 19-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.3 Series 300 - FencingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.3 Series 300 - Fencing 23-Apr-21 46 30-Jun-21B1300 Permanent/ Temp Site perimeter fencing 23-Apr-21 2 26-Apr-21

A1150 Post and Rail Fencing to verge 21-Jun-21 4 24-Jun-21

A1160 Post and Rail Otter Fencing to verge 24-Jun-21 4 30-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.4 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.4 Series 400 - VRS 30-Jun-21 4 06-Jul-21

A1230 New VRS 30-Jun-21 4 06-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.5 Series 500 - Drainage and Ducting 23-Apr-21 14 14-May-21

D1100 Prep works inc material and setting out 23-Apr-21 4 29-Apr-21

A1330 Carrier - ECP 05 to CP 89 29-Apr-21 3 05-May-21

A1350 Carrier HW02 to CP25 05-May-21 2 07-May-21

A1360 Filter RE10 to CP25 07-May-21 1 11-May-21

A1310 Carrier - HW01 to CP22 11-May-21 2 13-May-21

A4290 Online Duct Crossings 13-May-21 2 14-May-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.8 Series 1100 - Kerbs and FootwaysWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.7.8 Series 1100 - Kerbs and Footways 19-Jun-21 1 19-Jun-21

A1680 CKD Online Connectins 19-Jun-21 1 19-Jun-21

A4300 Online Kerbing to Splitter Islands 19-Jun-21 1 19-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13 A46 Under JunctionWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13 A46 Under Junction 14-Apr-21 7 23-Apr-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13.11 Series 400 - VRSWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13.11 Series 400 - VRS 19-Apr-21 4 23-Apr-21A1240 New VRS 19-Apr-21 4 23-Apr-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13.5 Series 500 - Drainage and DuctingWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.13.5 Series 500 - Drainage and Ducting 14-Apr-21 3 19-Apr-21

A1510 Filter Drain SBCP04 to SBCP09 14-Apr-21 3 19-Apr-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.8 Main AlignmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.8 Main Alignment 23-Apr-21 50 06-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.8.1 ADS Signs on Main AlignmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.12.8.1 ADS Signs on Main Alignment 23-Apr-21 50 06-Jul-21

B1330 Signs and Bases to Verge (TM off Peak Lane Closures TM Drwg 13A) 23-Apr-21 50 06-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.8 New A46 BridgeWBS: 2B-A46- CA 27/07/2020 WF09-C.3.8 New A46 Bridge 04-Dec-20 151 23-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.3 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.3 Series 100 - Traffic Management / Utilities 04-Dec-20 151 23-Jul-21

B1110 Southbound A46 Closed/ Northbound Open enabling narrow lanes installation (TM Drwg No 4) 04-Dec-20 3 08-Dec-20

A4820 Narrow Lanes on A46 (TM Drwg No 06) 08-Dec-20 86 23-Apr-21

B1120 Northbound A46 Closed/ Southbound Open enabling narrow lanes installation (TM Drwg No 5) 08-Dec-20 3 11-Dec-20

A2570 Access to Works Via Existing Slip Roads 18-Feb-21 48 29-Apr-21

A4830 Removal of All TM on A46 0 23-Apr-21

A3190 Access to Works Via New Slips 29-Apr-21 59 23-Jul-21

A3270 Switch Traffic Over New Structure 23-Jul-21 0

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.1 West AbutmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.1 West Abutment 18-Feb-21 97 12-Jul-21

A2580 Create Acces and Working Platform to Rear From Slip 18-Feb-21 7 01-Mar-21

A2590 Install Excavation Support System 02-Mar-21 7 11-Mar-21

A2600 Excavate For Abutment 11-Mar-21 8 22-Mar-21

A2610 Blinding 23-Mar-21 1 23-Mar-21

A2620 Abutment Base Steel 24-Mar-21 4 29-Mar-21

A2630 Abutment Base Formork 30-Mar-21 3 01-Apr-21

A2680 Concrete Base 06-Apr-21 1 06-Apr-21

A2670 Waterproof Base, Remove Ground Support and Backfill to Top of Base 07-Apr-21 5 13-Apr-21

A2640 Scaffold Abutment 14-Apr-21 3 16-Apr-21

A2650 Abutment Wall Steel 19-Apr-21 5 23-Apr-21

A2660 Abutment Wall Formwork 26-Apr-21 4 29-Apr-21

A2690 Concrete Abutment Wall to Shelf Level 30-Apr-21 1 30-Apr-21

A2700 Strip Wall Forms 04-May-21 2 05-May-21

D1020 Concrete Abutment Wall to Shelf Level Curing 04-May-21 15 24-May-21

A2710 Waterproof Back of Wall and Strip Scaffold 06-May-21 3 10-May-21

A2720 Reinforced Earth Foundations 11-May-21 10 24-May-21

A2730 Reinforced Earth Walls Upto Bearing Shelf Level 16-Jun-21 15 07-Jul-21

A3080 Complete Reinforced Earth Walls 07-Jul-21 3 12-Jul-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 5 of 8Date Revision Checked Approved

Page 20: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.2 East AbutmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.2 East Abutment 10-Feb-21 89 21-Jun-21

A2740 Create Acces and Working Platform to Rear From Slip 10-Feb-21 7 19-Feb-21

A2750 Install Excavation Support System 19-Feb-21 7 03-Mar-21

A2760 Excavate For Abutment 03-Mar-21 8 12-Mar-21

A2770 Blinding 12-Mar-21 1 15-Mar-21

A2780 Abutment Base Steel 15-Mar-21 4 19-Mar-21

A2790 Abutment Base Formork 19-Mar-21 3 24-Mar-21

A2840 Concrete Base 24-Mar-21 1 25-Mar-21

A2830 Waterproof Base, Remove Ground Support and Backfill to Top of Base 25-Mar-21 5 01-Apr-21

A2800 Scaffold Abutment 01-Apr-21 3 08-Apr-21

A2810 Abutment Wall Steel 08-Apr-21 5 15-Apr-21

A2820 Abutment Wall Formwork 15-Apr-21 4 21-Apr-21

A2850 Concrete Abutment Wall to Shelf Level 21-Apr-21 1 22-Apr-21

A2860 Strip Wall Forms 22-Apr-21 2 26-Apr-21

D1010 Concrete Abutment Wall to Shelf Level Curing 22-Apr-21 15 14-May-21

A2870 Waterproof Back of Wall and Strip Scaffold 26-Apr-21 3 29-Apr-21

A2880 Reinforced Earth Foundations 29-Apr-21 10 14-May-21

A2890 Reinforced Earth Walls Upto Bearing Shelf Level 14-May-21 15 07-Jun-21

A3070 Complete Reinforced Eath Walls 16-Jun-21 3 21-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.4 DeckWBS: 2B-A46- CA 27/07/2020 WF09-C.3.8.4 Deck 18-Feb-21 107 23-Jul-21

A2900 Construct Ground Beams and Falsework Supports for Offline Construction 18-Feb-21 15 11-Mar-21

A2910 Erect Tressles 11-Mar-21 3 16-Mar-21

A2920 Construct Crane Platform 16-Mar-21 6 24-Mar-21

A2930 Deliver Beams and Erect on Tressles 24-Mar-21 3 29-Mar-21

A4840 Time Saving for Offline Construction 24-Mar-21 39 21-May-21

A2940 Install Permanent Formwork and Seal 29-Mar-21 3 01-Apr-21

A2950 Erect Parapet Falsework and Edge Protection 01-Apr-21 8 15-Apr-21

A2960 Reinforcement for Deck 15-Apr-21 7 26-Apr-21

A2970 Formwork to Deck 26-Apr-21 4 30-Apr-21

A2980 Concrete Deck 30-Apr-21 1 04-May-21

D1060 Concrete Deck Cure 04-May-21 10 18-May-21

D1070 Prep Works to Parapets area 04-May-21 5 11-May-21

A2990 Parapets to Deck 11-May-21 8 21-May-21

A3000 Waterproofing to Deck 18-May-21 3 21-May-21

A3010 Remove Falsework 18-May-21 4 24-May-21

A3020 Jack Deck to Allow SPMT Installation 21-May-21 5 28-May-21

A3030 Transport Deck and Install On Abutments 28-May-21 1 01-Jun-21

A3040 Formwork and Rebar to Diaphrams 01-Jun-21 10 15-Jun-21

B1250 Clear New Bridge Build Area 01-Jun-21 5 08-Jun-21

A3050 Concrete Diaphrams 15-Jun-21 1 16-Jun-21

A3060 Parapet Gound Beams 25-Jun-21 8 07-Jul-21

A3210 Subabse to Bridge Approaches 05-Jul-21 3 08-Jul-21

D1090 Prep for Kerbs to Deck 05-Jul-21 3 08-Jul-21

A3280 Complete Parapets 07-Jul-21 4 13-Jul-21

A3200 Kerbs to Deck and Approaches 08-Jul-21 3 13-Jul-21

A3230 VRS tie Ins to Parapets 13-Jul-21 4 19-Jul-21

A3220 Ducting to Verges 13-Jul-21 5 20-Jul-21

A3250 Base and Binder 13-Jul-21 1 14-Jul-21

A3260 Surface Course and Lining 14-Jul-21 1 15-Jul-21

A3240 Footway Construction 20-Jul-21 4 23-Jul-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.9 Existing A46 StructureWBS: 2B-A46- CA 27/07/2020 WF09-C.3.9 Existing A46 Structure 23-Jul-21 73 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.9.2 North VergeWBS: 2B-A46- CA 27/07/2020 WF09-C.3.9.2 North Verge 23-Jul-21 34 10-Sep-21

A4410 Push Traffic to South Verge - Single Lane Around Gyratory 23-Jul-21 34 10-Sep-21

A4420 Remove Old Kerbs 23-Jul-21 2 27-Jul-21

B1220 North Verge ground works existing A46 Bridge (resources) 23-Jul-21 33 09-Sep-21

A4430 Plane of Existing Surfacing 27-Jul-21 1 28-Jul-21

A4700 Ducting in Carriageway 27-Jul-21 0 27-Jul-21

A4440 Clean Bridge Deck 28-Jul-21 2 30-Jul-21

A4530 Inspect Deck and Define Repair Extent 30-Jul-21 1 02-Aug-21

A4450 Concrete Repairs to Bridge Deck 02-Aug-21 13 19-Aug-21

D1140 Concrete Repairs to Bridge Deck Cure 19-Aug-21 5 26-Aug-21

A4460 Waterproofing to Bridge Deck 26-Aug-21 2 31-Aug-21

A4470 Install Buried Joint 31-Aug-21 2 02-Sep-21

A4490 Backfill to Deck Ends 31-Aug-21 1 01-Sep-21

A4480 Install Bridge Deck Drainage Kerbs 02-Sep-21 2 06-Sep-21

A4500 Footway Fill and Surface 06-Sep-21 3 09-Sep-21

A4510 Asphalt Surfacing to Road 06-Sep-21 2 08-Sep-21

A4520 APJ 08-Sep-21 2 10-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.9.1 South VergeWBS: 2B-A46- CA 27/07/2020 WF09-C.3.9.1 South Verge 10-Sep-21 39 05-Nov-21

A4740 Push Traffic to South Verge - Single Lane Around Gyratory 10-Sep-21 39 05-Nov-21

A4570 Remove Old Kerbs 10-Sep-21 2 14-Sep-21

B1230 South Verge ground works existing A46 Bridge (resources) 10-Sep-21 38 03-Nov-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 6 of 8Date Revision Checked Approved

Page 21: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

A1920 Ducting in Carriageway 14-Sep-21 2 16-Sep-21

A4710 Remove Old Troughing Lids 14-Sep-21 3 17-Sep-21

A4750 Install Varioguard 14-Sep-21 1 15-Sep-21

A4580 Plane of Existing Surfacing 14-Sep-21 1 15-Sep-21

A4760 Install Temp Edge Protection 15-Sep-21 2 17-Sep-21

A4590 Clean Bridge Deck 15-Sep-21 2 17-Sep-21

A4720 Waterproofing to Troughing 17-Sep-21 2 21-Sep-21

A4770 Remove Exsitng Parapet 17-Sep-21 3 22-Sep-21

A4600 Inspect Deck and Define Repair Extent 17-Sep-21 1 20-Sep-21

A4610 Concrete Repairs to Bridge Deck 20-Sep-21 17 13-Oct-21

A1850 Ducting, Chambers and NAL Sockets in Verge 21-Sep-21 3 24-Sep-21

A4730 Install New Troughing Lids 24-Sep-21 3 29-Sep-21

A4780 Erect New Paraper 06-Oct-21 5 13-Oct-21

A4790 VRS Connection Works 13-Oct-21 2 15-Oct-21

D1150 Concrete Repairs to Bridge Deck Cure 13-Oct-21 5 20-Oct-21

A4620 Waterproofing to Bridge Deck 20-Oct-21 2 22-Oct-21

A4630 Install Buried Joint 22-Oct-21 2 26-Oct-21

A4640 Backfill to Deck Ends 22-Oct-21 1 25-Oct-21

A4650 Install Bridge Deck Drainage Kerbs 26-Oct-21 2 28-Oct-21

A4660 Footway Fill and Surface ????? 28-Oct-21 4 03-Nov-21

A4670 Asphalt Surfacing to Road 28-Oct-21 3 02-Nov-21

A4680 APJ 02-Nov-21 3 05-Nov-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10 Westley BridgeWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10 Westley Bridge 27-Jul-20 293 30-Sep-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.3 Series 100 - Traffic Management / UtilitiesWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.3 Series 100 - Traffic Management / Utilities 29-Sep-20 200 23-Jul-21

A3340 Diversion of Severn Trent Water Main 29-Sep-20 40 23-Nov-20

A3350 Grout Existing Main 24-Nov-20 5 30-Nov-20

A4540 Switch Traffic Over Sructure 23-Jul-21 0

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.5 Temporary DesignWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.5 Temporary Design 01-Sep-20 54 13-Nov-20B1000 Engage with Temporary Works Designer (for Westley Bridge) 01-Sep-20* 7 09-Sep-20

B1010 Start Westley Bridge Temp Design 10-Sep-20 0

B1020 Design Westley Bridge Temporary Works 10-Sep-20 28 19-Oct-20

B1030 Submit to Client 20-Oct-20 2 21-Oct-20

B1040 Client Review 22-Oct-20 15 11-Nov-20

B1050 Client Sign Off 12-Nov-20 2 13-Nov-20

B1060 Finish Westley Bridge Temporary Design 0 13-Nov-20

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.6 Salmonid Period 2020 (Working allowed)WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.6 Salmonid Period 2020 (Working allowed) 27-Jul-20 293 30-Sep-21

B1240 Identified Salmonid Working Allowed Period START DATE 2020 27-Jul-20* 0

B1241 Identified Salmonid Working Allowed Period END Date 2020 0 30-Sep-20*

D1030 Identified Salmonid Working Allowed Period START DATE 2021 15-Jun-21* 0

D1040 Identified Salmonid Working Allowed Period END Date 2021 0 30-Sep-21*

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.1 West AbutmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.1 West Abutment 26-Nov-20 164 02-Aug-21

B1310 Permanent/ Temp Site perimeter fencing 26-Nov-20 4 01-Dec-20

A3390 Dig Out and Replace Alluviums to Rear of Structure / Piling Platform 01-Dec-20 7 10-Dec-20

A3400 Install Sheet Piling - Ground Support and Protection of Existing Structure 10-Dec-20 10 07-Jan-21

C1000 Build bund 07-Jan-21 7 18-Jan-21

A3410 CFA Piling to Abutment 18-Jan-21 7 27-Jan-21

A3420 Pile Breakdown and Excavate to Founding Level 27-Jan-21 7 08-Feb-21

A3430 Blinding to Pile Cap 08-Feb-21 1 09-Feb-21

A3450 Rebar for Pile Cap 09-Feb-21 4 15-Feb-21

A3440 Formwork and Concrete to Pile Cap 15-Feb-21 4 19-Feb-21

A3470 Scaffold to Abutment 19-Feb-21 3 24-Feb-21

A3460 Rebar to Abutment 24-Feb-21 4 02-Mar-21

A3480 Formwork to Abutment 02-Mar-21 4 08-Mar-21

A3490 Concrete Abutment 08-Mar-21 1 09-Mar-21

A3500 Remove Sheet Piles and Backfill Locally Install Erosion Protection 09-Mar-21 8 19-Mar-21

D1130 Concrete Abutment Cure 09-Mar-21 5 16-Mar-21

A3510 Blinding to Lower Wing Walls 12-Mar-21 1 15-Mar-21

A3520 Rebar to Lower Wing Walls 15-Mar-21 2 17-Mar-21

A3530 Formwork and Concrete Lower Wing Walls 27-Apr-21 4 04-May-21

A3540 Back Fill Locally to Lower Wing Walls 04-May-21 1 05-May-21

A3550 Blinding to Upper Wing Walls 05-May-21 1 06-May-21

A3560 Rebar to Upper Wing Walls 06-May-21 2 10-May-21

A3570 Formwork and Concrete to Upper Wing Walls 10-May-21 4 14-May-21

A3580 6N Back Fill 02-Jun-21 2 04-Jun-21

A3900 Parapet 04-Jun-21 2 08-Jun-21

B1250A Remaining Alluviums dig out and replace 15-Jun-21 20 12-Jul-21

A3590 Brickwork Cladding 13-Jul-21 15 02-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.2 East AbutmentWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.2 East Abutment 10-Dec-20 154 02-Aug-21

A3600 Dig Out and Replace Alluviums to Rear of Structure / Piling Platform 10-Dec-20 7 04-Jan-21

A3610 Install Sheet Piling - Ground Support and Protection of Existing Structure 07-Jan-21 10 21-Jan-21

C1010 Build bund 21-Jan-21 7 01-Feb-21

A3620 CFA Piling to Abutment 01-Feb-21 7 11-Feb-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 7 of 8Date Revision Checked Approved

Page 22: Application for Approval of details reserved by Condition ... · Connect with us I follow us on LinkedIn I follow us on Twitter I Our values are collaborative, trusted and focused

Activity ID Activity Name Start Remaining Duration

Finish

A3630 Pile Breakdown and Excavate to Founding Level 11-Feb-21 7 22-Feb-21

A3640 Blinding to Pile Cap 22-Feb-21 1 23-Feb-21

A3660 Rebar for Pile Cap 23-Feb-21 4 01-Mar-21

A3650 Formwork and Concrete to Pile Cap 01-Mar-21 4 05-Mar-21

A3680 Scaffold to Abutment 05-Mar-21 3 10-Mar-21

A3670 Rebar to Abutment 10-Mar-21 4 16-Mar-21

A3690 Formwork to Abutment 16-Mar-21 4 22-Mar-21

A3700 Concrete Abutment 22-Mar-21 1 23-Mar-21

A3710 Remove Sheet Piles and Backfill Locally Install Erosion Protection 23-Mar-21 8 06-Apr-21

D1120 Concrete Abutment Cure 23-Mar-21 5 30-Mar-21

A3720 Blinding to Lower Wing Walls 26-Mar-21 1 29-Mar-21

A3730 Rebar to Lower Wing Walls 29-Mar-21 2 31-Mar-21

A3740 Formwork and Concrete Lower Wing Walls 14-May-21 4 20-May-21

A3750 Back Fill Locally to Lower Wing Walls 20-May-21 1 21-May-21

A3760 Blinding to Upper Wing Walls 21-May-21 1 24-May-21

A3770 Rebar to Upper Wing Walls 24-May-21 2 26-May-21

A3780 Formwork and Concrete to Upper Wing Walls 26-May-21 4 02-Jun-21

A3790 6N Back Fill 02-Jun-21 2 04-Jun-21

A3910 Parapet 04-Jun-21 2 08-Jun-21

B1260A Remaining Alluviums dig out and replace 15-Jun-21 20 12-Jul-21

A3800 Brickwork Cladding 13-Jul-21 15 02-Aug-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.4 DeckWBS: 2B-A46- CA 27/07/2020 WF09-C.3.10.4 Deck 30-Mar-21 53 17-Jun-21

A3810 Deliver and Erect Bridge Beams and String Course 30-Mar-21 3 06-Apr-21

A3820 Permanent Formwork to Deck 06-Apr-21 2 08-Apr-21

A3830 Rebar to Deck and Diaphrams 08-Apr-21 12 26-Apr-21

A3840 Formwork to Diaphrams 13-Apr-21 9 26-Apr-21

A3850 Concrete Deck 26-Apr-21 1 27-Apr-21

A3890 Parapet Stich 27-Apr-21 0 27-Apr-21

D1110 Parapet Stitch cure 27-Apr-21 10 12-May-21

A3870 Deck Waterproofing 12-May-21 3 17-May-21

A3860 Parapet to Deck 04-Jun-21 5 11-Jun-21

A3920 Kerbing Across and and Approaches 04-Jun-21 3 09-Jun-21

A3930 Ducting Across Deck 09-Jun-21 2 11-Jun-21

A3950 Base and Binder Across Deck and Approaches 09-Jun-21 1 10-Jun-21

A3960 Surface Course and Lining Across Deck and Approaches 10-Jun-21 1 11-Jun-21

A3940 Footway Construction Across Deck 11-Jun-21 4 17-Jun-21

WBS: 2B-A46- CA 27/07/2020 WF09-C.6 Traffic SignalsWBS: 2B-A46- CA 27/07/2020 WF09-C.6 Traffic Signals 24-Sep-21 25 29-Oct-21

A5010 Traffic Signal and ANPR Camera Installation and Commissioning 24-Sep-21 25 29-Oct-21

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2020 2021 2022

2B- A46 Stoneleigh Tender Submission Programme (Award 27-07-2020) Factors (Client 002) JH A46 Main View: . For Review. What If

Project ID 2B-A46- CA 27/07/2020 WF09-C 17-Jun-20 10:39

Remaining Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Page 8 of 8Date Revision Checked Approved