appendix d—geotechnical engineering and ......wp-43d oxbow-hickson-bakke ring levee system ii...

326
WP-43D Oxbow-Hickson-Bakke Ring Levee System WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D—Geotechnical Engineering and Geology APPENDIX D—GEOTECHNICAL ENGINEERING AND GEOLOGY

Upload: others

Post on 11-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D—Geotechnical Engineering and

    Geology

    APPENDIX D—GEOTECHNICAL ENGINEERING AND GEOLOGY

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System i

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D—Geotechnical Engineering and

    Geology

    D1 TABLE OF CONTENTS

    Appendix D—Geotechnical Engineering and Geology .................................................. 1

    D2 Introduction ...................................................................................................... 1

    D3 Site Geology ...................................................................................................... 3

    D3.1 Field Work ............................................................................................................3

    D3.1.1 Soil Borings ............................................................................................................................. 3

    D3.2 Laboratory Work ...................................................................................................4

    D3.3 Groundwater Conditions .......................................................................................4

    D3.4 Stratigraphy and Parameters .................................................................................4

    D3.4.1 Stratigraphy ............................................................................................................................ 4

    D3.4.2 Laboratory Test Results .......................................................................................................... 5

    D3.4.3 Shear Strengths....................................................................................................................... 5

    D3.4.4 Compressibility ....................................................................................................................... 7

    D3.5 Geotechnical Analysis ............................................................................................8

    D3.5.1 Pump Station and Gatewell Bearing Capacity ........................................................................ 8

    D3.5.2 Settlement Analyses ............................................................................................................... 8

    D3.5.3 Interior Drainage Pond Slope Stability .................................................................................... 9

    D3.5.4 Pipe Alignment Offset North of levee ................................................................................... 14

    D4 Design Quality Control ..................................................................................... 16

    D4.1 Quality Control .................................................................................................... 16

    D5 Technical Guideliness and Reference Standards................................................ 17

    Tables

    Table 3-1 Summary of Soil Stratigraphy by Cross Section .......................................................................... 5

    Table 3-2 Summary of Moisture Content and Unit Weight by Soil Stratigraphy ....................................... 5

    Table 3-3 Summary of UU Test Results by Soil Stratigraphy ...................................................................... 6

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System ii

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D—Geotechnical Engineering and

    Geology

    Table 3-4 Summary of Drained Peak Strengths by Soil Stratigraphy .......................................................... 6

    Table 3-5 Summary of USACE Unit Weights and Ultimate Shear Strength Parameters Used in Slope

    Stability Analyses ............................................................................................................................................ 7

    Table 3-6 Summary of Consolidation Test Values by Soil Stratigraphy ...................................................... 7

    Table 3-7 Summary of Factors of Safety Against Heave on Landward Leeve Toe and Pond Cut Toe of

    Levee During USACE Case 3 `and 3b Analyses .............................................................................................. 12

    Table 3-8 Slope Stability Results for USSA Conditions .............................................................................. 13

    Table 3-9 Slope Stability Results for ESSA Conditions .............................................................................. 14

    Table 3-10 Slope Stability Results for Sudden Drawdown Conditions ................................................... 14

    Attachments

    Attachment D1 Geotechnical Investigation Locations

    Attachment D2 Boring Logs

    Attachment D3 Laboratory Results

    Attachment D4 Piezometer Readings

    Attachment D5 Strength Plots

    Attachment D6 Bearing Pressure Computation

    Attachment D7 Settlement Computation

    Attachment D8 Gatewell Preconsolidation Report

    Attachment D9 Seepage and Slope Stability Analysis

    Attachment D10 Pipe Offset Model Output

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-1

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Introduction

    INTRODUCTION D2

    The Oxbow-Hickson-Bakke (OHB) Ring Levee under current design will incorporate construction of a levee

    with an assumed top elevation of 927.6 feet to surround the three target communities and portions of

    Pleasant Township for flood protection. In addition, to provide access to the towns within the levee, the

    two primary roadways will need to be raised: Highway 81 at the northeast corner of the proposed levee

    and Highway 18 from the southwest corner of the proposed levee, extending to Interstate Highway I-29

    to the west.

    Appendix D provides support for the geotechnical aspects associated with the pump station and interior

    drainage system for the OHB Ring Levee. The north interior drainage pond (North Pond) is located along

    the interior of the north levee to the west of Highway 81, which will be drained by the combination of a

    pumping system and gravity drain system. Major structural components of the drainage system consist of

    a pump station structure, located near the northeast corner of the North Pond; a gatewell structure,

    located in the levee north of the pump station structure; and an outlet structure to discharge the water

    into the Red River of the North. These structures are connected by piping that extends from the North

    Pond through the pump station and gatewell passing through the levee, east along the northern exterior

    of the levee underneath Highway 81, then to the outlet structure and the river. There will be a second

    west interior drainage pond (West Pond) constructed along the interior of the west levee, south of Bakke.

    This pond, however, will have only gravity drainage; therefore, design of significant structures such as a

    pump station will not be required. Both the North and West Ponds will be operated as dry ponds. The

    North and West ponds are connected via an underground storm sewer reinforced concrete pipe.

    At the time of this report, the following design parameters were understood for each of the proposed

    components:

    • The North Pond will be excavated to a bottom elevation of 898 feet and the West Pond will be

    excavated to a bottom elevation of 902.5 feet (compared to surrounding final grades on the

    order of elevation 914 to 916.5 feet).

    • The pump station will be a deep-well structure with the foundation bearing at elevation 889.5

    feet (approximately 26 to 26.5 feet below surrounding grade). It will be founded on a mat

    foundation, roughly 33.5 feet by 34 feet. The calculated applied bearing capacity of the soil

    underlying the pump station is 6,000 psf (drained) surpassing the applied bearing pressure of

    2,470 psf from the structure and water in the well (normal operating condition).

    • The gatewell will also be a deep-well structure, founded on a mat foundation about 20.5 feet by

    21.5 feet in plan dimension, with the foundation bearing at an elevation of 893.45 feet (22.5 feet

    below surrounding grade or 37.25 feet below the crest of the levee). The calculated applied

    bearing capacity of the soil underlying the gatewell is 6,100 psf (drained) surpassing the

    calculated applied bearing pressure for this structure of 3,800 psf from the structure and water

    in the well (normal operating condition).

    • The gravity drain piping system will generally be comprised of 60-inch diameter RCP pipe that will

    extend through the proposed structures, below the levee section, along the toe of the north

    levee, and underneath Highway 81 before daylighting at the outflow. For the gravity drain

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-2

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Introduction

    segment under Highway 81, the 60-inch RCP pipe will transition to dual 42” welded steel pipes as

    a road raise consolidation mitigation measure. In general, the gravity drain pipe will be

    constructed 20 to 30 feet below surrounding grades.

    • The gravity drain outlet structure to the Red River will be a cast-in-place concrete stilling basin 26

    feet long by 12 feet wide bearing on grade, with sheet pile erosion cutoff protection and a riprap

    armored channel at the downstream end to allow for the gravity drain pipe to daylight to the Red

    River of the North.

    Geotechnical analysis is required for the structures, piping, and North Pond and West Pond to be

    designed. The geotechnical analyses included: (1) calculation of the bearing capacity and settlement for

    the structures, (2) estimation of the amount of settlement that will result from the levee or roadway

    embankment fill affecting pipes and structures, (3) stability of construction excavations and final grades

    for location of piping, and (4) seepage and slope stability of the West Pond and North Pond adjacent to

    the levee. This document includes a discussion of the exploration methodology, seepage and slope

    stability modeling, bearing capacity and settlement analyses, and results for geotechnical aspects of the

    95% submittal of WP-43D, which is based on the available information and assumptions at this time.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-3

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    SITE GEOLOGY D3

    Site geology generally consists of glacio-lacustrine clay formations underlain by glacial till. General

    regional geology is described extensively in USACE (2011).

    The shallowest material, the Sherack Formation, was deposited during higher lake levels and may contain

    clays and silts as well as organics. The Sherack Formation is continuously present, except in areas where it

    has been eroded by relatively recent alluvial or fluvial processes. It is often absent at riverbanks, where

    the alluvial deposit directly overlies the Brenna Formation.

    Deposition of weaker clay below the Sherack Formation and above the glacial till is associated with

    temperature fluctuations of Glacial Lake Agassiz. Regionally, Argusville and Brenna Formations are the

    two predominant lower glacio-fluvial units. Due to the location of the OHB site, near the southern extent

    of Lake Agassiz, these two units are understood to be highly interbedded in the project area. Laboratory

    results defining the Lower Lake Agassiz Clays (highly interbedded Argusville and Brenna Formations) are

    discussed extensively in Design Documentation Report (DDR), Oxbow, Hickson, Bakke Ring Levee,

    Attachment D-1, Geotechnical Engineering Parameters (dated 3 January 2014) (USACE Attachment D-1).

    The glacial till is characterized as a clayey hard ground moraine till deposited by the retreating glaciers

    that formed Glacial Lake Agassiz. In some locations, a sandy layer is found immediately overlying the

    clayey glacial till.

    Groundwater is typically found 10 feet below the ground surface regionally. However, the phreatic

    surface, which is depressed due to riverward groundwater flow, is usually lower in elevation near the

    river. Site specific piezometer data is discussed in Section D3.3.

    D3.1 FIELD WORK

    As part of the seepage and slope stability analysis, a geotechnical field exploration was performed. Field

    work used for the analysis was completed in three phases. The first phase, in March 2013, was completed

    under the direction of the Houston Moore Group (HMG) and focused on an area of the golf course near

    Oxbow identified as the proposed WP-43C levee alignment. The second phase of the field investigation,

    beginning in September 2013, encompassed the entire ring levee corridor. The third phase of

    investigations was performed for the northeast area of the site where major structural components of the

    pump station and gatewell will be located. Investigation locations were identified by HMG and the U.S.

    Army Corp of Engineers (USACE) in collaboration. In the third phase of work, borings were completed in

    2014 by Interstate Drilling under contract to the USACE and under the supervision of a USACE geologist. A

    limited number of sites were equipped with fully-grouted, vibrating-wire piezometers. Piezometer data

    was provided by USACE through September 3, 2014.

    D3.1.1 SOIL BORINGS

    Soil borings were completed to: (1) determine the stratigraphy at specific levee cross-section locations,

    the ponds, and outfall, (2) collect soil samples for laboratory testing, and (3) collect in-situ testing data

    from tests such as the standard penetration test (SPT). A map illustrating the completed borings across

    the site is provided in Attachment D1. Both disturbed and relatively undisturbed (Shelby tube) samples

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-4

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    were sealed to minimize moisture loss and delivered to Soil Engineering Testing (SET) in Richfield,

    Minnesota, for additional testing. USACE boring logs in the vicinity of this portion of the project are

    provided in Attachment D2

    D3.2 LABORATORY WORK

    The laboratory testing program including index properties, shear strength, grain-size distribution,

    standard Proctor compaction density, and consolidation characteristics was performed. Test results were

    used to identify important characteristics of the soils for use in design. This characterization was used to

    attempt to identify the different soil formations at the site including: Sherack, Brenna, Argusville, Glacial

    Till (Unit “A” Till), and the newly characterized Lower Lake Agassiz Clays (LLA) (interbedded combination

    of the Brenna and Argusville Formations).

    Index property testing was performed in accordance with ASTM D422, ASTM D2216, and ASTM D4318.

    Standard Proctor and consolidation testing was completed in accordance with ASTM D698 and ASTM

    D2435. Undrained shear strength properties were determined by performing consolidated-undrained

    triaxial compression tests with pore pressure measurements (ASTM D4767) on undisturbed samples.

    Torsional ring-shear tests, in accordance with ASTM D6467, were also performed but ultimately were not

    used in the analysis. The laboratory reports for the testing program are included Attachment D3.

    D3.3 GROUNDWATER CONDITIONS

    Piezometer results provided by USACE through September 3, 2014, indicated that ground water levels

    were roughly 15 to 17 feet below grade. Installation and monitoring of piezometers at select locations

    within the OHB site is ongoing. Due to the limited time period that site-specific data have been collected,

    this report assumes the static groundwater surface to be 10 feet below the ground surface. Based on

    piezometer reading to date, this is a slightly conservative assumption. However, it is consistent with other

    analyses performed for the overall flood control project and with groundwater depths from piezometers

    installed throughout the region. A design water level of 10 feet below grade will be used for analysis.

    Piezometer readings are provided in Attachment D4.

    D3.4 STRATIGRAPHY AND PARAMETERS

    Results of the soil borings and laboratory analyses were used to determine the soil stratigraphy at the site

    and appropriate design parameters for each soil layer. These analyses are discussed in detail below.

    D3.4.1 STRATIGRAPHY

    Our understanding of site stratigraphy is based on field investigations and knowledge of the geology of

    the Red River Valley. The site stratigraphy consists of a thin layer of topsoil followed by (in order of depth)

    the Sherack Formation, interbedded Brenna Formation and Argusville Formation (termed LLA Clay), a

    glacial outwash deposit (where encountered), and clayey glacial till.

    Soil stratigraphy was based on the USACE field boring logs from the geotechnical investigation. Soil

    stratigraphy by cross section is presented in Table 3-1.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-5

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    TABLE 3-1 SUMMARY OF SOIL STRATIGRAPHY BY CROSS SECTION

    Material Contact

    West Pond North Pond Pump Station and

    Gatewell Structures

    Formation Contact Elevation [ft]

    Ground Surface 915 914 914

    Sherack/Brenna Contact 885 885 894

    Brenna/Argusville Contact 868 865 874

    Argusville/Outwash 849 846 837

    Outwash/Unit “A” Till Contact 845 832 832

    D3.4.2 LABORATORY TEST RESULTS

    Laboratory testing performed by the USACE on similar geologic materials for the Fargo-Moorhead

    Diversion project was provided to HMG. Additional testing was done on borings for the OHB project and

    the pump station and gatewell, specifically. These site-specific parameters results and accompanying

    analyses are discussed in the following sections of this report and have been used to determine soil

    parameters for the analyses discussed herein, unless specifically noted.

    The Sherack and LLA Clays (interbedded Brenna and Argusville Formations) all consist of fat clay soils with

    liquid limits ranging from 50 to 97.1 percent, plastic limits ranging from 21.8 to 29.1 percent, and

    plasticity index values ranging from 24.1 to 68.3 percent.

    Natural moisture contents and unit weights of the Sherack and LLA Clays (interbedded Brenna and

    Argusville Formations) are provided in Table 3-2.

    TABLE 3-2 SUMMARY OF MOISTURE CONTENT AND UNIT WEIGHT BY SOIL STRATIGRAPHY

    Material

    Moisture Content Dry Unit Weight In Situ Unit Weight

    Range Average Range Average Range Average

    (%) (pcf) (pcf)

    Sherack Formation 16.4-45.2 37.6 78.3-85.7 82.8 111.7-114.7 113.5

    Brenna Formation 31.7-43.7 38.3 80.4-88.4 84.4 111.4-116.4 113.9

    Argusville Formation 29.3-43.7 39.0 76.2-91.4 82.3 108.8-118.2 113.1

    Outwash/Unit “A” Till 15.6-18.8 17.2 Too stiff for Shelby Tubes–Assumed 123 pcf in situ weight

    Since the in situ unit weights were calculated from the dry unit weight values and corresponding moisture

    contents, it was assumed that these values are representative of saturated unit weights below the water

    table.

    D3.4.3 SHEAR STRENGTHS

    Shear strengths for each soil stratigraphy were determined using site-specific values and previous USACE

    testing results for the Fargo-Moorhead Diversion project (at feasibility and pre-engineering design stages).

    The results of the USACE laboratory testing can be found in Attachment I-04 of Appendix I, Geotechnical

    Design and Geology of the Fargo-Moorhead Metropolitan Area Flood Risk Management Final Feasibility

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-6

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    Report and Environmental Impact Statement and Attachment I-05 of General Report: Geotechnical Design

    and Geology of the Fargo-Moorhead Metropolitan Area Flood Risk Management Project North Dakota

    Diversion Alignment. Values were obtained for both undrained and drained slope-stability analysis

    conditions determined by USACE. Values were also obtained for both peak strengths (for use in bearing

    capacity/short-term analysis) and “ultimate” (15% strain) strengths (for use in long-term slope-stability

    analysis).

    Peak undrained strengths for the pump station and gatewell structures were determined from triaxial

    unconsolidated-undrained (UU) test results. A summary of the site-specific UU test results for the pump

    station and gatewell is provided in Table 3-3.

    TABLE 3-3 SUMMARY OF UU TEST RESULTS BY SOIL STRATIGRAPHY

    Material

    Site Specific Peak

    Undrained Shear Strengths

    Range

    (psf*)

    Average

    (psf*)

    Sherack Formation 4,060-5,540 4,800

    Brenna Formation (or LLA Clay) 3,370-3,840 3,600

    Argusville Formation 3,080-4,200 3,600

    * PSF = pounds per square foot

    Laboratory data from borings obtained for the OHB Ring Levee project was used to determine the peak

    drained strengths of materials for the bearing pressure analysis. The strength envelopes were determined

    using the 1/3-2/3 method. The peak drained strength values used for design are provided in Table 3-4.

    Shear strength envelopes are illustrated Attachment D5.

    TABLE 3-4 SUMMARY OF DRAINED PEAK STRENGTHS BY SOIL STRATIGRAPHY

    Material Normal Stress

    Range (tsf) ɸ’ (degrees) c’ (psf)

    Normal Stress

    Range (tsf) ɸ’ (degrees) c’ (psf)

    Levee fill 0-0.75 28 150 >0.75 21 372

    Sherack 0-1.0 30 0 >1.0 25 222

    LLA clays 0-1.0 30 0 >1.0 13 693

    Till All 25 225 ― ― ―

    Material properties and ultimate strengths determined by USACE and used for the slope stability analysis

    are summarized in Table 3-5. Development of these parameters is discussed extensively in USACE

    Attachment D-1 and takes into account site-specific testing where possible. Shear strength properties

    were also developed for a new material classification type, Lower Lake Agassiz Clays (ESSA-only), and are

    presented in Table 3-5.

    Laboratory torsional ring shear testing to determine the fully softened strength of the clay was also

    performed on three samples of fat clay obtained during the soil borings for the levee. One test was

    performed on a sample of the Brenna Formation clay and two tests were performed on samples of the

    LLA Clays. Fully softened and residual tests were performed on each sample. The results of the testing are

    provided in Attachment D3 and shown on the strength plots for the drained ultimate strengths for the

    Sherack and Brenna Formation clay provided in Attachment D5. The results of the torsional ring shear

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-7

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    testing indicated the fully softened strengths were roughly equivalent to though slightly higher than the

    ultimate strength (defined by the USACE as the strength at 15 percent axial strain) for the lower

    overburden pressure range of the bilinear function. Therefore, the bilinear ultimate strength of the clay at

    15 percent strain was used for the long-term drained analysis of the clay soils for the project.

    TABLE 3-5 SUMMARY OF USACE UNIT WEIGHTS AND ULTIMATE SHEAR STRENGTH PARAMETERS USED IN SLOPE

    STABILITY ANALYSES

    Material

    Unit

    Weight

    [pcf]

    ESSA-Ultimate USSA-Ultimate

    c'

    [psf]

    φ’

    [deg]

    c

    [psf] φ [deg]

    Sherack Formation 115 c’ = 0, φφφφ’ = 28 until σ’ = 2,000, φφφφ’ = 11

    at higher stresses

    900 0

    Brenna Formation 106 Use Lower Lake Agassiz Clays 575 0

    Argusville Formation 110 Use Lower Lake Agassiz Clays c = 575, increasing 10 per foot depth

    Lower Lake Agassiz Clays Note 1 c’ = 0, φφφφ’ = 25 until σ’ = 2000,

    φφφφ’ = 11 at higher σ’

    Use Brenna and Argusville

    Formations

    Levee fill 120 c’ = 150, φφφφ’ = 24 at 1,500, φφφφ’ = 11 at

    higher σ’

    900 0

    Unit “A” till 123 225 22 1900 0

    Unit “A” till (Sta. A17+00.00)2 Impenetrable

    1 Lower Lake Agassiz Clays were assigned unit weight properties of the Brenna or Argusville Formation based on the

    formation delineation presented in Table 3-2. See USACE Attachment D-1 for further information.

    2 Used in evaluation of block or truncated circular potential failure surfaces where the failure surface intersects the Unit

    “A” Till layer.

    D3.4.4 COMPRESSIBILITY

    Compressibility for the Sherack, Brenna, and Argusville Formation clay soils was determined for the pump

    station and gatewell structures by laboratory testing of relatively undisturbed Shelby-tube samples

    obtained from the borings in the vicinity of these structures. Based on this laboratory testing, the

    settlement parameters contained in Table 3-6 were used to evaluate settlement for the structures.

    TABLE 3-6 SUMMARY OF CONSOLIDATION TEST VALUES BY SOIL STRATIGRAPHY

    Material

    Compression

    Index

    Recompression

    Index

    Max Past

    Pressure

    Initial Void

    Ratio

    Average Average Average Average

    (--) (--) (tsf) (--)

    Sherack Formation 0.45 0.08 4.1 1.166

    Brenna Formation 0.39 0.05 4.5 1.003

    Argusville Formation 0.48 0.10 4.8 1.095

    The values in this table will be used to estimate settlement beneath the pump station structure as

    discussed in Section D3.5.2. Slightly different values, provided in USACE Attachment D-1, for the entire

    OHB Ring Levee have previously been used to evaluate settlement beneath the levees and road raises.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-8

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    D3.5 GEOTECHNICAL ANALYSIS

    Geotechnical analyses for the ponds, pump station, gatewell, and piping included (1) bearing capacity and

    settlement analysis for the pump station and gatewell structures, (2) settlement analysis for the piping,

    (3) offset analysis for pipe installation excavations near the levee toe, and (4) stability analysis for the

    interior drainage pond.. These efforts are discussed below.

    D3.5.1 PUMP STATION AND GATEWELL BEARING CAPACITY

    Bearing capacity for the pump station and gatewell structures was performed using the soil parameters

    shown in Table 3-3 and Table 3-4 of this report. The Meyerhoff model presented in EM 1110-1-1905

    (USACE 1992) was used for preliminary bearing capacity analysis of the pump station, which is located on

    roughly flat ground between the levee and North Pond. Bearing capacity was performed for both peak

    undrained and drained strengths.

    Based on the foundation depths of both the pump station and the gatewell, the foundations are near the

    transition between the Sherack and Brenna Formations. The soil characteristics for the Brenna Formation

    have been used since these are generally lower strength than the Sherack Formation.

    Calculated allowable net bearing capacity for the pump station is 8,600 pounds per square foot (psf) for

    the undrained condition and 6,000 psf for the drained condition. The allowable net bearing capacity for

    the gatewell is 9,300 psf for the undrained condition and 6,500 psf for the drained condition. The

    allowable bearing pressure calculations use a factor of safety of 3.0 and are determined by the structural

    engineer. The detailed bearing capacity calculation is provided in Attachment D6. The applied bearing

    pressures below the current mat foundation for of the pump station exceed determined by the structural

    engineer are structure of 4,000 psf for the high-water level/flood case (undrained conditions) and 2,530

    psf for the normal operating condition (drained conditions). The applied bearing pressures of the

    gatewell determined by the structural engineer are 5,200 psf for the high- water level/flood case

    (undrained conditions) and 3,800 psf for the normal operating condition (drained conditions). Based on

    the values discussed above, the allowable bearing capacity of the soil will be able to support the applied

    bearing pressures of the structures.

    D3.5.2 SETTLEMENT ANALYSES

    Construction of the levee and the road raises will cause significant settlement of the underlying lacustrine

    clay soils. This settlement will potentially affect the design, construction method, construction sequence,

    schedule, and long-term operation and maintenance for the pump station structures and piping system—

    as well as the roadways over the levees. From previous geotechnical analysis of gatewell preconsolidation

    (Attachment D7), the magnitude of settlement for the levees is estimated at 4 to 6 inches below the crest

    of the levee. The estimated time for primary settlement to occur (the bulk of the estimated settlement) is

    10 to 15 years following construction, assuming double-faced or horizontal drainage of pore pressure

    occurs. Single-faced or drainage in one direction will significantly increase the time for completion of

    primary consolidation.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-9

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    Since the gatewell will be located within the levee, it is assumed that the settlement of the structure will

    be similar to the ground beneath the levee—4 to 6 inches. This settlement will not be tolerated by the

    gatewell structure and mitigation will be needed. Settlement mitigation will also be needed for the piping

    entering and leaving the structure to avoid stress from differential settlement. Differential settlement is

    caused when spanning occurs between areas where settlement is allowed to occur naturally and areas

    where mitigation has been performed.

    Two options for settlement mitigation beneath the gatewell and adjacent piping were considered: (1)

    surcharging and wick drains to accelerate settlement prior to construction and (2) soil improvement (such

    as deep-soil mixing or controlled modulus columns) to reduce compressibility of the underlying lacustrine

    clay soils. Considering that preconsolidation could be performed starting this year and start 180 to 200

    days before start of the subsequent construction activities, and that the anticipated costs for using wick

    drains and surcharge in this area, preconsolidation was selected to preconsolidate the clay soil below the

    gatewell structure. Design methodology for the preconsolidation beneath the gatewell is discussed in

    Attachment D8 of this appendix. Construction of the wick drains and surcharge took place in early fall

    2014. The preconsolidation is currently underway began in 2015 with regular monitoring being performed

    to evaluate settlement progress.

    Settlement of the gravity drain pipe beneath the Highway 81 road raise may also be an issue for design.

    Settlement beneath the roadway embankment is expected to be greater than away from the

    embankment, where little-to-no settlement is anticipated. Differential settlement and pipe stress will

    occur if settlement at the pipe crossing is not considered in the design. To counter the potential for

    differential settlement, the gravity drain below Highway 81 will be two 42-inch diameter steel pipes,

    extending outside of the anticipated settlement zone of the road raise. The steel pipes selected are

    capable of withstanding the differential settlement while allowing proper gravity drainage of the system.

    The pump station structure is located on roughly level ground between the levee and the North Pond.

    Settlement of the pump station will be due to the load from the structure added to unloading from the

    excavation and compressibility of the underlying clay soils. The compressibility of the clay was determined

    from the laboratory consolidation tests of site-specific soil borings, as shown in Table 3-6. EM 1110-1-

    1904 (USACE 1990) was used as a guidance document for settlement calculations.

    Using these consolidation test values and the current pump station mat foundation design, a total

    settlement of about 1 inch is estimated for the pump station at the applied bearing pressures provided for

    the current design. The materials are over-consolidated, even with the additional pump station loads;

    therefore, secondary compression and creep are considered negligible. It is anticipated that settlement of

    about 1 inch will be tolerable for the pump station.

    D3.5.3 INTERIOR DRAINAGE POND SLOPE STABILITY

    The interior drainage pond slope stability analysis incorporated the following features: (1) the levee with

    respect to the West Pond, (2) the levee with respect to the North Pond, and (3) the Highway 81 road raise

    with respect to the North Pond. These locations were considered critical. The analysis was completed

    using the shear strength parameters developed in USACE Attachment D-1. Design methodology is

    provided in Design Documentation Report (DDR), Oxbow, Hickson, Bakke Ring Levee Attachment D-2

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-10

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    Geotechnical Engineering Seepage and Slope Stability Methodology (dated 6 February 2014, USACE

    Attachment D-2).

    MODELING METHODS

    Seepage conditions and slope stability were analyzed with software created by GEO-SLOPE International

    Ltd. The integrated software suite is called GeoStudio 2007, which includes modules SEEP/W and

    SLOPE/W. SEEP/W is a finite-element program that analyzes groundwater flow within porous materials

    like rock and soil using traditional steady-state or transient analyses. The computed pore-water pressures

    and corresponding phreatic surface can then be imported into a SLOPE/W analysis. SLOPE/W uses limit-

    equilibrium methods to perform slope stability analyses.

    MODEL STRATIGRAPHY/GEOMETRY

    Three cross sections were analyzed to assess the stability of the interior drainage pond slopes

    (Attachment D1). The cross sections through the levees in the North and West Ponds were provided by

    Moore. The Moore cross section through Highway 81 in the North Pond was offset 500 feet to the

    northeast to examine a greater volume of fill necessary to complete the road raise. The existing ground

    surface, levee alignment/configuration, and pond cuts used in the models were constructed using

    information provided by Moore. Both the North Pond and West Pond are designed to be dry, except

    during storm events.

    The West Pond levee model consists of a 176.2-foot offset from the toe of the levee to the crest of the

    pond slope. Beginning at the crest of the pond slope, the slope is 7H:1V (horizontal:vertical) for

    80 horizontal feet. The elevation of the modeled pond bottom is approximately 902.5 feet at the toe of

    the pond slope.

    The North Pond levee model consists of a 63-foot offset from the toe of the levee to the crest of the pond

    slope. Beginning at the crest of the pond slope, the slope is 7H:1V for 80 horizontal feet. The elevation of

    the modeled slope toe is approximately 902.7 feet at the toe of the 7H:1V slope with a ditch bottom

    elevation of 896.3 feet.

    The North Pond road-raise model consists of a 114-foot offset from the toe of the road-raise slope to the

    crest of the pond slope. Similar to the north interior drainage pond levee model, the pond slope is 7H:1V

    for 102 horizontal feet. The elevation of the slope toe is approximately 899.3 feet at the toe of the 7H:1V

    slope with a ditch bottom elevation of 896.9 feet.

    HMG understands the North Pond configuration has been changed, such that the pond bottom has been

    increased in elevation to have an upstream ditch bottom at 900.4 feet sloping to a downstream elevation

    of 898.0 feet. Because the original modeling assumed an even deeper pond bottom, the factor of safety

    should also slightly increase and re-evaluation was not necessary.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-11

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    MODELING PARAMETERS

    The model parameters were developed based on the with-diversion project design scenario. Seepage and

    stability parameters used for the interior drainage pond modeling are discussed in USACE Attachment D-

    1.

    The hydraulic boundary conditions on the wet side of the levee were established at 10 feet below the

    ground surface, at an elevation of 922.5 feet or 926.0 feet (max pool). Because the analyzed embankment

    cross section is located completely within the ring levee and adjacent to a pond (considered a critical

    cross section), flood conditions were modeled with the phreatic surface coincident with the ground

    surface. Hydraulic boundary conditions on the dry side of the levee were assigned considering dry ponds

    (both West Pond and North Pond) for flood events, as well as for a 500-year, 24-hour storm coinciding

    with and without a 100-year flood event. Sudden draw-down conditions within the pond were evaluated

    for the 500-storm, expected to raise the water level in the West Pond to an elevation of 911.3 feet (pump

    drainage in North Pond) or 911.1 (gravity drainage in North Pond). This slight difference in maximum pond

    elevation is due to the how the North Pond and West Pond water surfaces respond water flow between

    backings up from the north pond during instance when water is pumped from the North Pond verses

    being drained by gravity. This slight difference in maximum pond elevation is due to the water flow

    between backings up from the North Pond during instance when water is pumped from the North Pond

    versus being drained by gravity.

    Assuming it can be emptied by gravity drain during a 500-year storm event (non-flood event outside of

    the levee perimeter) the anticipated pond water elevation for the North Pond is 908.0 feet. If a flood

    event occurs outside the levee perimeter, the pond will be drained by pumps, with an anticipated

    elevation of 911.2 feet for a 500-year precipitation event. Variations of these scenarios were modeled and

    are reported in the following section. If additional site-specific data (piezometer data) indicates

    groundwater depths less than 10 feet below the ground surface, the models should be updated.

    SEEPAGE ANALYSIS

    Seepage modeling was conducted to gain a better understanding of the groundwater conditions for the

    slope stability analysis and to assess the heave potential at the toe of the upstream levee and each pond

    cut.

    As stated in USACE Attachment D-2, the minimum required factor of safety against heave at the landward

    toe of the levee cross sections is 1.6 for USACE Case 3 (100-year-flood event is 922.5 feet) and 1.3 for

    USACE Case 3b (maximum pool elevation is 926.0 feet). The factor of safety is estimated by dividing the

    critical gradient (buoyant soil unit weight/unit weight of water) by the exit gradient (change in

    head/distance between measured heads). The exit gradient was calculated between the ground surface

    and 2 feet below the toe of the landward levee/cut.

    SEEPAGE RESULTS

    Results of the seepage analysis for USACE Case 3 and Case 3b are provided in Table 3-7. Because the

    phreatic surface did not exist at the surface for all locations, heave could not be calculated. Heave is not

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-12

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    expected to occur in these instances. The seepage analysis indicates the interior drainage pond slopes

    maintain adequate factors of safety for levee toe and pond cut toe heave.

    TABLE 3-7 SUMMARY OF FACTORS OF SAFETY AGAINST HEAVE ON LANDWARD LEEVE TOE AND POND CUT TOE

    OF LEVEE DURING USACE CASE 3 `AND 3B ANALYSES

    Cross Section

    Case 3 (Water Surface Elev=922.5

    ft) Req’d FoS2 = 1.6

    Case 3b (Water Surface Elev=926

    ft) Req’d FoS2 = 1.3

    West Pond Levee Toe 5.58 2.28

    West Pond Cut Toe 2.94 2.79

    North Pond Levee Toe N/A1 3.24

    North Pond Cut Toe 3.17 2.94

    1. Modeling indicates seepage does not exist at the toe of the levee in this condition (total

    head < elevation).

    2. Based on requirements found in USACE Attachment D-2.

    SLOPE STABILITY ANALYSIS

    The main objective of the slope stability analysis of the interior West Pond and North Pond was to

    evaluate the stability of the pond slopes while considering offsets to the toes of the levees and the

    Highway 81 road raise.

    Two types of slope stability analyses are typically performed for slopes: the undrained strength stability

    analysis (USSA) and the effective stress stability analysis (ESSA).

    The USSA is performed to analyze the case in which loading or unloading is applied rapidly and excess

    pore-water pressures do not have sufficient time to dissipate during shearing. This scenario typically

    applies to loading from embankment construction, where the loadings take place quickly relative to the

    permeability of the soils. It is often referred to as the “end-of-construction” case.

    The ESSA is performed to account for much slower loading or unloading, or no external loading, where the

    drained shear strength of the materials is mobilized and no excess pore-water pressures are allowed to

    develop. For example, a slowly moving landslide is best analyzed using the ESSA method. For this reason,

    the ESSA is often referred to as the “long-term” case.

    Both the USSA and ESSA were performed as part of the slope stability analysis for this project. The factor

    of safety was computed by incorporating the results of the seepage analysis under steady-state

    conditions. Incorporating the groundwater flow with the limit-equilibrium calculations captures the effect

    of fluid/soil interaction on the factor of safety calculation. In this manner, emphasis was placed on

    evaluating the impact of groundwater flow on stability.

    Stability of a slope is often reported using a factor of safety value. The factor of safety is the ratio of the

    summation of forces and moments resisting slope movement to the summation of forces and moments

    that cause slope movement. These forces and moments could be the result of increased loading or

    decreased resistance caused by pore-water pressure changes that result from fluctuations in the ponded

    water level, changes in the buttressing effect caused by the flood events, and the removal of material

    during excavation of the ponds.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-13

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    The grid-radius method was used to determine the size and location of the potential failure surface. This

    method was selected because the search examines localized potential failure surfaces (pond slope only or

    levee slope only) in addition to larger global potential failure surfaces encompassing both the pond and

    levee slopes.

    Initial factors of safety were identified by Slope/W from circular failure surfaces defined by the grid-radius

    method. The optimize failure surfaces option in Slope/W was used as preferred by USACE. The

    optimization adjusts the shape of the failure surface to preferentially pass through weaker soil layers

    which will slightly reduce the computed factor of safety. The optimized factors of safety are discussed in

    the following sections of this report.

    Seepage gradients at the toe of the levee are also commonly evaluated as a part of levee stability.

    However, the levee analysis contained herein was only to assess stability of the pond slopes adjacent to

    the levees and road raises. Seepage gradients for the purposes of levee analysis and design will be

    performed for levee design in a separate work package of this project.

    SLOPE STABILITY RESULTS

    Factor of safety requirements for the interior drainage pond slope stability analyses were defined by

    USACE Attachment D-2. The factors of safety for end-of-construction (USSA) and long-term (ESSA) are 1.3

    and 1.4, respectively, and 1 for (sudden drawdown). A 2-foot-minimum slip surface was used in all

    analyses eliminating the need to consider very thin failures which will not affect levee or pond

    performance. Model outputs from the slope stability analyses are included Attachment D9. Results of the

    analyses are provided in Table 3-8, Table 3-9, and Table 3-10. The slope stability analysis indicates the

    interior drainage pond slopes maintain adequate factors of safety for USSA, ESSA, and sudden drawdown

    conditions.

    TABLE 3-8 SLOPE STABILITY RESULTS FOR USSA CONDITIONS

    Analysis

    Required

    Minimum

    Factor of

    Safety2

    West Pond

    Levee Cross Section

    Factors of Safety1

    North Pond

    Levee Cross Section

    Factors of Safety1

    North Pond Hwy. 81

    Road Raise

    Cross Section

    Factors of Safety1

    Groundwater= 10' below Ground Level

    Surface : Empty Pond 1.3 2.72 1.82 2.03

    1. Reported factors of safety are from optimized failure surfaces.

    2. Based on requirements found in USACE Attachment D-2.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-14

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    TABLE 3-9 SLOPE STABILITY RESULTS FOR ESSA CONDITIONS

    Analysis

    Required

    Minimum

    Factor of

    Safety2

    West Pond

    Levee Cross Section

    Factors of Safety1

    North Pond

    Levee Cross Section

    Factors of Safety1

    North Pond Hwy. 81

    Road Raise

    Cross Section

    Factors of Safety1

    Groundwater= 10 feet below ground-level

    surface: empty pond 1.4 2.69 2.72 2.49

    100-year flood stage H= 922.5 feet: empty

    pond 1.4 2.01 1.77 2.21

    Max Pool H= 926 feet: empty pond 1.4 1.76 1.77 -

    1. Reported factors of safety are from optimized failure surfaces.

    2. Based on requirements found in USACE Attachment D-2.

    TABLE 3-10 SLOPE STABILITY RESULTS FOR SUDDEN DRAWDOWN CONDITIONS

    Analysis

    Required

    Minimum

    Factor of

    Safety2

    West Pond

    Levee Cross

    Section Factors

    of Safety1

    North Pond Levee

    Cross Section

    Factors of Safety1

    North Pond Hwy. 81

    Road Raise

    Cross Section

    Factors of Safety1

    Groundwater=10 feet below ground-level surface:

    500-year rain event emptied via gravity drain 1 1.57 1.46 1.39

    100-year flood H=922.5 feet: 500-year rain event

    emptied via pump 1 1.56 1.32 1.27

    1. Reported factors of safety are from optimized failure surfaces.

    2. Based on requirements found in USACE Attachment D-2.

    D3.5.4 PIPE ALIGNMENT OFFSET NORTH OF LEVEE

    Construction of the gravity pipe will occur north of the proposed levee alignment, extending from north of

    the gatewell structure and east across Highway 81 to the outflow. Stability analyses of the construction

    excavations were performed to determine an appropriate offset for the pipe excavation to prevent failure

    caused by the surcharge from the previously constructed levee. Review of the levee stability was

    performed using methods similar to those discussed in Section D3.5.3.

    Peak undrained shear strengths were used to evaluate potential stability of the construction excavations

    along the toe of the north levee. Peak undrained strengths are considered appropriate for these analyses

    due to the relatively short time period the excavations will remain open. It is estimated that several

    months may be required to complete the pipe installation. Due to low permeability of the clay, drainage

    should not occur and drained or effective stress should not govern the analyses. In fact, near-vertical

    excavations have been observed in borrow pits near Fargo, North Dakota, within similar clay formations

    over extended periods of time. Based on the analyses, a suitable pipe alignment offset is about 75 feet

    from the toe of the levee to the shoulder of the trench cut and sloped trench 25 to 30 feet deep. For the

    analysis it was assumed the excavation sidewalls would be constructed at 2H:1V and meet a factor of

    safety of 1.3 (end-of-construction condition). A 4-foot minimum slip surface was used to evaluate the pipe

    alignment offset. Model output is provided in Attachment D10.

    Because HMG does not dictate the means and methods the contractor will use to construct the gravity

    drain, a trench box was not considered in the design. The analysis considered a worst case (widest) offset

    from the levee, which could reasonably be considered in lieu of a trench box. HMG anticipates a trench

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-15

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Site Geology

    box will be considered/used for gravity drain installation. The design and incorporation of any shoring or

    trench box in any excavation for this project will be the responsibility of the contractor, with the

    exception of the drain excavation within the 75-foot offset after the levee is in place. A trench box or

    other means of excavated sidewall protection would be required in this case.

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-16

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D – Design Quality Control

    DESIGN QUALITY CONTROL D4

    D4.1 QUALITY CONTROL

    Quality control for all geotechnical analysis was completed in accordance with the project quality control

    plan.

    Geotechnical Component Designer Calculations Check Engineer of Record

    Geostudio Models Bill Kussman Jed Greenwood Bill Kussman

    Bearing Capacity Analysis Bill Kussman Joel Swenson Bill Kussman

    Settlement Analysis Bill Kussman Joel Swenson Bill Kussman

    Appendix D Bill Kussman Jed Greenwood Bill Kussman

    Technical Specification

    31 00 00 04 Earthwork for

    Non-Road Raise Features

    Bill Kussman Mike Haggerty Bill Kussman

  • WP-43D Oxbow-Hickson-Bakke Ring Levee System D-17

    WP-43D BCOE 4/1/2016 DDR Pump Station, Volume 2 – Appendix D –

    Technical Guideliness and Reference Standards

    TECHNICAL GUIDELINESS AND REFERENCE STANDARDS D5

    The following listed technical guidelines and reference standards were used to complete the structural

    evaluation within this appendix.

    1. EM 1110-1-1905, Bearing Capacity of Soils, U.S. Army Corps of Engineers, Washington DC, 10

    October 1992.

    2. EM 1110-1-1904, Settlement Analysis, U.S. Army Corps of Engineers, Washington DC, 30

    September 1990.

    3. U.S. Army Corps of Engineers. “Final Feasibility Report and Environmental Impact Statement.”

    Fargo-Moorhead Metropolitan Area Flood Risk Management. July 2011.

    4. U.S. Army Corps of Engineers. “Design Documentation Report (DR), Oxbow, Hickson, Bakke Ring

    Levee Attachment D-1 Geotechnical Engineering Parameters.” Fargo-Moorhead Metropolitan

    Area Flood Risk Management. January 2014.

    5. U.S. Army Corps of Engineers. “Design Documentation Report (DR), Oxbow, Hickson, Bakke Ring

    Levee Attachment D-2 Seepage and Slope Stability Methodology.” Fargo-Moorhead Metropolitan

    Area Flood Risk Management. February 2014.

  • Oxbow-Hickson-Bakke Ring Levee System

    Attachment D1 – Geotechnical Investigation Locations

    ATTACHMENT D1 – GEOTECHNICAL INVESTIGATION LOCATIONS

  • !(

    !(!(

    !(!(

    !(!(

    !(!!(

    !(!(

    !(

    !(!(

    !(!!(

    !(

    !(!(

    !(!(

    !(

    !(

    !(

    !(

    !(

    !(!!(

    !(!( !(!(

    !

    !

    !

    !

    !

    !

    !

    !

    !

    (

    (

    (

    !!

    !!

    !

    !

    !!

    !

    !!

    !

    !

    !!

    !

    !

    !

    !

    !

    !

    !

    !

    ((

    ((

    (

    (

    ((

    (

    ((

    (

    (

    ((

    (

    (

    (

    (

    (

    (

    (

    (

    !!

    !!

    ((

    ((

    "

    "

    "

    "

    )

    )

    )

    )£¤81

    ")25

    Main

    Elm

    Plum Tree

    7th Oxbow

    Schnell

    1st Sunse

    t

    Riverben

    d

    §̈¦29

    ")81

    ")18 52nd

    SB-5

    SB-7

    SB-6

    SB-2

    SB-1

    SB-4SB-3

    93-1M

    CPT3A

    CPT4A

    CPT2A

    13-20M

    13-9M

    13-8M

    13-7M13-6M

    13-5M13-4M

    13-3M

    13-2M

    13-17M

    13-18M13-19M

    13-16M

    13-15M

    13-14M

    13-13M

    13-12M

    13-11M

    13-10M

    13-3MU

    13-2MU

    CPT1Aalt

    13-21M

    A05+57

    .07

    A34+25.85

    C37+37.16

    C26+67.69

    C11+40.96

    C17+33.53

    C0+80.00

    A21+09.02

    A11+10.94

    A17+00.00

    West Interior DrainagePond 1 ext

    North Interior DrainagePond 1

    North InteriorDrainage Pond 2

    West Pond

    North Pond

    14-24M14-23M

    14-22P14-22M

    13-11P

    14-24MU14-23MU

    13-5P

    Geotech Locations") Completed CPT Location (Barr, 2013)!!(

    Completed Boring Location andPiezometer Location (Barr, 2013)!( Completed Boring Location (NTI, 2010)!( Completed Boring Location (USACE, 2013)!!(

    Completed Boring and PiezometerLocation (USACE, 2013 & 2014)Cross-Section

    WP-43A and WP-43C AreasDrainage Ponds

    Proposed LeveePhase WP-43APhase WP-43BPhase WP-43B

    Figure 1GEOTECHNICAL INVESTIGATIONWP-43D 95% SubmittalOxbow, Hickson, Bakke LeveeFM Metro Flood Risk Reduction ProjectCass County, North Dakota

    Barr Fo

    oter: A

    rcGIS 1

    0.3, 20

    15-01-

    28 09:

    46 File

    : I:\Pro

    jects\3

    4\09\1

    004\Ma

    ps\Rep

    orts\WP

    43D_95

    Pct_Su

    bmitta

    l\Fig01

    Geote

    chnical

    Invest

    igation

    .mxd U

    ser: ar

    m2

    I0 1,200 2,400Feet

  • Oxbow-Hickson-Bakke Ring Levee System

    Attachment D2 – Boring Logs

    ATTACHMENT D2 – BORING LOGS

  • 916.6

    912.8

    0.8

    4.629

    42

    40

    41

    50

    47

    51

    52

    74

    72

    76

    77

    0' to 0.8' Gravelly lean clay (CL); black;slightly moist; about 100% fines, lowplasticity; clay; with gravel; and organics.

    0.8' to 4.6' Fat clay (CH); greenish gray toyellowish brown; slightly moist; about 100%fines, low plasticity; clay.

    4.6' to 26.3' Fat clay (CH); yellowish brown;moist; laminated structure; about 100%fines, high plasticity; clay; with gypsumcrystals.

    80

    100

    100

    100

    1

    2

    3

    4

    SPT=140lbs at a 30" drop,autohammer usedBoring located at N5169639E0667560 UTM NAD83

    Set 3" HSA to 5.0'

    Set 3" HSA to 10.0'

    Set 3" HSA to 15.0'

    CL

    CH

    CH

    7

    8

    7

    6

    13-2M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    0.0

    2.5

    5.0

    7.5

    10.0

    12.5

    15.0

    17.5

    20.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 1 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-2M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/11/13

    N 383,774.0 E 2,894,731.0

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    73.8

    HORIZONTALNAD83

    917.4

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/12/13

    14. ELEVATION GROUND WATER

    41

    OHB-13

    Grant Riddick Geologist

    2

    3

    4

    6

    3

    4

    4

    5

    2

    3

    4

    4

    3

    3

    3

    5

  • 891.1

    886.2

    26.3

    31.2

    37

    57

    38

    42

    44

    12

    40

    38

    67

    37

    64

    60

    4.6' to 26.3' Fat clay (CH); yellowish brown;moist; laminated structure; about 100%fines, high plasticity; clay; with gypsumcrystals. (continued)

    26.3' to 31.2' Fat clay (CH); yellowishbrown to gray; moist to saturated; beddedstructure; about 100% fines, high plasticity;clay; with interbedded clayey silt;interbedded with clayey silt consisting of60% silt, 40% clay.

    31.2' to 45' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; trace fine gravel; and coarsesand.

    100

    100

    100

    100

    5

    6

    7

    8

    Set 3" HSA to 20.0'

    Set 3" HSA to 25.0'

    Set 3" HSA to 28.0'Mixed 80 gallons of waterwith 10 pounds of bentonite;drilled out and cleaned holeto 35.0' with roller bit

    CH

    CH

    8

    5

    6

    7

    13-2M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    20.0

    22.5

    25.0

    27.5

    30.0

    32.5

    35.0

    37.5

    40.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 2 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-2M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/11/13

    N 383,774.0 E 2,894,731.0

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    73.8

    HORIZONTALNAD83

    917.4

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/12/13

    14. ELEVATION GROUND WATER

    42

    OHB-13

    Grant Riddick Geologist

    3

    4

    4

    5

    2

    3

    2

    4

    3

    2

    4

    4

    3

    4

    3

    4

  • 872.4

    858.1

    45.0

    59.3

    46

    43

    39

    46

    58

    37

    76

    85

    60

    31.2' to 45' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; trace fine gravel; and coarsesand. (continued)

    45' to 59.3' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; some fine gravel; tracecoarse sand.

    100

    90

    100

    100

    9

    10

    11

    12

    Cleaned hole to 40.0' with3" roller bit

    Cleaned hole to 45.0' with3" roller bit

    Cleaned hole to 50.0' with3" roller bit

    Cleaned hole to 55.0' with3" roller bit

    CH

    6

    5

    5

    25

    13-2M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    40.0

    42.5

    45.0

    47.5

    50.0

    52.5

    55.0

    57.5

    60.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 3 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-2M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/11/13

    N 383,774.0 E 2,894,731.0

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    73.8

    HORIZONTALNAD83

    917.4

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/12/13

    14. ELEVATION GROUND WATER

    43

    OHB-13

    Grant Riddick Geologist

    2

    3

    3

    4

    2

    2

    3

    3

    2

    2

    3

    3

    3

    8

    17

    14

  • 852.8

    845.9

    843.6

    64.6

    71.5

    73.8

    59.3' to 64.6' Clayey sand with gravel (SC);gray; wet; about 30% fines; sand.(continued)

    65' to 71.5' Sandy lean clay with gravel(CL); gray; moist to wet; about 65% fines,low plasticity; clay.

    71.5' to 73.8' Poorly graded sand with clay(SP-SC); gray; saturated; about 5% fines;sand.

    75

    100

    38

    13

    14

    15

    Cleaned hole to 60.0' with3" roller bit

    Cleaned hole to 64.6' with3" roller bitDrill outCleaned hole to 65.0' with3" roller bit

    Cleaned hole to 70.0' with3" roller bitDrill out

    Backfilled boring with tremied high solids bentonite grout

    SC

    CL

    SP-SC

    18

    58

    50

    13-2M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    60.0

    62.5

    65.0

    67.5

    70.0

    72.5

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 4 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-2M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/11/13

    N 383,774.0 E 2,894,731.0

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    73.8

    HORIZONTALNAD83

    917.4

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/12/13

    14. ELEVATION GROUND WATER

    44

    OHB-13

    Grant Riddick Geologist

    8

    8

    10

    50

    18

    23

    35

    45

    57

    50

  • 100 1

    13-2MU Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    0.0

    2.5

    5.0

    7.5

    10.0

    12.5

    15.0

    17.5

    20.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 1 of 3

    REMARKSN60

    Laboratory

    Boring Designation 13-2MU

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    8" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    57.0

    HORIZONTALNAD83

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling Service

    Scott Anderson14. DEPTH GROUND WATER

    31

    OHB-13

    Grant Riddick Geologist

  • 100

    100

    2

    3

    13-2MU Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    20.0

    22.5

    25.0

    27.5

    30.0

    32.5

    35.0

    37.5

    40.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 2 of 3

    REMARKSN60

    Laboratory

    Boring Designation 13-2MU

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    8" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    57.0

    HORIZONTALNAD83

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling Service

    Scott Anderson14. DEPTH GROUND WATER

    32

    OHB-13

    Grant Riddick Geologist

  • 100 4

    Backfilled boring with tremied high solids bentonite grout

    13-2MU Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    40.0

    42.5

    45.0

    47.5

    50.0

    52.5

    55.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 3 of 3

    REMARKSN60

    Laboratory

    Boring Designation 13-2MU

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    8" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    57.0

    HORIZONTALNAD83

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling Service

    Scott Anderson14. DEPTH GROUND WATER

    33

    OHB-13

    Grant Riddick Geologist

  • 916.0

    910.7

    0.7

    6.0

    27

    32

    38

    44

    55

    53

    49

    51

    78

    76

    73

    80

    0' to 0.7' Fat clay (CH); black; slightlymoist; about 100% fines, medium plasticity;clay; some organics.

    0.7' to 6' Fat clay (CH); greenish gray toyellowish brown; slightly moist; about 100%fines, medium plasticity; clay; traceorganics.

    6' to 27' Fat clay (CH); yellowish brown;moist; laminated structure; about 100%fines, high plasticity; clay; some gypsumcrystals.

    80

    100

    100

    100

    1

    2

    3

    4

    SPT=140lbs at a 30" drop,autohammer usedBoring located at N5169729E0667927 UTM NAD83

    Set 3" HSA to 5.0'

    Set 3" HSA to 10.0'

    Set 3" HSA to 15.0'

    CH

    CH

    CH

    10

    8

    8

    7

    13-3M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    0.0

    2.5

    5.0

    7.5

    10.0

    12.5

    15.0

    17.5

    20.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 1 of 5

    REMARKSN60

    Laboratory

    Boring Designation 13-3M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/13/13

    N 384,092.3 E 2,895,929.2

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    79.8

    HORIZONTALNAD83

    916.7

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/13/13

    14. ELEVATION GROUND WATER

    51

    OHB-11

    Grant Riddick Geologist

    5

    5

    5

    6

    2

    4

    4

    5

    3

    3

    5

    5

    3

    3

    4

    5

  • 889.7

    885.9

    27.0

    30.8

    50

    43

    37

    42

    72

    12

    58

    45

    99

    36

    79

    69

    6' to 27' Fat clay (CH); yellowish brown;moist; laminated structure; about 100%fines, high plasticity; clay; some gypsumcrystals. (continued)

    27' to 30.8' Fat clay (CH); yellowish brownto gray; wet to saturated; laminatedstructure; about 100% fines, high plasticity;clay; thin bedded with clayey silt.

    30.8' to 63.6' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; well developed siltylaminations.

    100

    100

    100

    100

    5

    6

    7

    8

    Set 3" HSA to 20.0'

    Set 3" HSA to 25.0'

    Set 3" HSA to 30.0'Mixed 80 gallons of waterwith 5 pounds of bentonite;drilled out and cleaned holeto 30.0' with roller bit

    Cleaned hole to 35.0' with3" roller bit

    CH

    CH

    7

    5

    8

    6

    13-3M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    20.0

    22.5

    25.0

    27.5

    30.0

    32.5

    35.0

    37.5

    40.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 2 of 5

    REMARKSN60

    Laboratory

    Boring Designation 13-3M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/13/13

    N 384,092.3 E 2,895,929.2

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    79.8

    HORIZONTALNAD83

    916.7

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/13/13

    14. ELEVATION GROUND WATER

    52

    OHB-11

    Grant Riddick Geologist

    3

    3

    4

    5

    3

    2

    3

    4

    2

    4

    4

    5

    2

    3

    3

    4

  • 41

    44

    44

    41

    41

    46

    50

    49

    66

    71

    73

    75

    30.8' to 63.6' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; well developed siltylaminations. (continued)

    100

    100

    100

    100

    9

    10

    11

    12

    Cleaned hole to 40.0' with3" roller bit

    Cleaned hole to 45.0' with3" roller bit

    Cleaned hole to 50.0' with3" roller bit

    Cleaned hole to 55.0' with3" roller bit

    4

    6

    5

    5

    13-3M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    40.0

    42.5

    45.0

    47.5

    50.0

    52.5

    55.0

    57.5

    60.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 3 of 5

    REMARKSN60

    Laboratory

    Boring Designation 13-3M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/13/13

    N 384,092.3 E 2,895,929.2

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    79.8

    HORIZONTALNAD83

    916.7

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/13/13

    14. ELEVATION GROUND WATER

    53

    OHB-11

    Grant Riddick Geologist

    2

    2

    2

    3

    2

    3

    3

    3

    2

    2

    3

    3

    2

    2

    3

    3

  • 853.1

    848.5

    847.7

    842.7

    836.9

    63.6

    68.2

    69.0

    74.0

    79.8

    30.8' to 63.6' Fat clay (CH); gray; wet;laminated structure; about 100% fines, highplasticity; clay; well developed siltylaminations. (continued)

    63.6' to 68.2' Clayey sand with gravel (SC);gray; wet; about 30% fines, no plasticity;sand.

    68.2' to 69' Gravelly lean clay with sand(CL); gray; moist to wet; about 60% fines,low plasticity; clay.

    73' to 74' Poorly graded sand with clay(SP-SC); gray; saturated; about 10% fines;sand.

    78' to 79.8' Gravelly lean clay with sand(CL); gray; wet; about 60% fines, lowplasticity; clay.

    100

    90

    100

    100

    13

    14

    15

    Cleaned hole to 60.0' with3" roller bit

    Cleaned hole to 65.0' with3" roller bit

    Cleaned hole to 69.0' with3" roller bitDrill out

    Cleaned hole to 74.0' with3" roller bitDrill out

    SC

    CL

    SP-SC

    CL

    6

    48

    65

    79

    13-3M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    60.0

    62.5

    65.0

    67.5

    70.0

    72.5

    75.0

    77.5

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 4 of 5

    REMARKSN60

    Laboratory

    Boring Designation 13-3M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/13/13

    N 384,092.3 E 2,895,929.2

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    79.8

    HORIZONTALNAD83

    916.7

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/13/13

    14. ELEVATION GROUND WATER

    54

    OHB-11

    Grant Riddick Geologist

    4

    3

    3

    4

    5

    20

    28

    35

    25

    65

    19

    29

    50

    50

  • Backfilled boring with tremied high solids bentonite grout

    13-3M Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    dFIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 5 of 5

    REMARKSN60

    Laboratory

    Boring Designation 13-3M

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    9/13/13

    N 384,092.3 E 2,895,929.2

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    3" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    79.8

    HORIZONTALNAD83

    916.7

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson

    9/13/13

    14. ELEVATION GROUND WATER

    55

    OHB-11

    Grant Riddick Geologist

  • 100 1

    13-3MU Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    0.0

    2.5

    5.0

    7.5

    10.0

    12.5

    15.0

    17.5

    20.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 1 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-3MU

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    8" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY FOR BORING

    6. THICKNESS OF OVERBURDEN

    7. DEPTH DRILLED INTO ROCK

    8. TOTAL DEPTH OF BORING

    N/A---

    ---

    61.8

    HORIZONTALNAD83

    VERTICAL

    Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring Levee

    INSTALLATION

    NAVD88

    Interstate Drilling

    Scott Anderson14. DEPTH GROUND WATER

    41

    OHB-11

    Grant Riddick Geologist

  • 100 2

    13-3MU Fargo-Moorhead Metro PED - Oxbow, Hickson, Bakke Ring LeveeMVP FORM 1836-A

    ELEV DEPTH

    MC

    Gra

    vel

    PI

    LL

    San

    d

    20.0

    22.5

    25.0

    27.5

    30.0

    32.5

    35.0

    37.5

    40.0

    FIELD CLASSIFICATION OF MATERIALS(Description)

    %REC

    Sam

    p N

    o.

    Blo

    ws/

    0.5

    ft

    Fin

    es

    DEC 07SHEET 2 of 4

    REMARKSN60

    Laboratory

    Boring Designation 13-3MU

    LEG

    EN

    D

    Nf

    3. DRILLING AGENCY

    LOCATION COORDINATES

    16. ELEVATION TOP OF BORING

    COMPLETED15. DATE BORING

    BEARING

    SHEETS

    1. PROJECT

    4. NAME OF DRILLER

    DEG FROMVERTICAL

    DRILLING LOG

    12. TOTAL SAMPLES

    STARTED

    2. HOLE NUMBER

    ---

    8" Roller Bit

    Diedrich D-50

    ---

    INCLINED ---

    St. Paul District

    5. DIRECTION OF BORING

    13. TOTAL NUMBER CORE BOXES

    9. COORDINATE SYSTEM

    10. SIZE AND TYPE OF BIT

    State Plane

    OF

    UNDISTURBED

    ---

    SHEET

    Mississippi Valley Division

    VERTICAL

    18. SIGNATURE AND TITLE OF INSPECTOR

    DISTURBED

    DIVISION

    11. MANUFACTURER'S DESIGNATION OF DRILL

    17. TOTAL CORE RECOVERY