APPENDIX 4 Processing Land Use Permit Requests for Change of Limited Access Control (Changes typically involve shifting, moving or breaking right-of-way control) Draft Resolution Right-of-Way Division Commonwealth Transportation Board District Administrator Chief Engineer Review & Recommendation Right-of-Way Division **The Chief Engineer must approve the permit request prior to the issuance of a land use permit authorizing work within the limited access right of way. Transportation and Mobility Planning Division Land Use Permit Staff will ensure that all district reviews have been completed, CTB approval has been granted, monetary compensation has been paid and any/all other conditions have been satisfied prior to submitting the permit request to the Chief Engineer. Review & Comment Appropriate District Staff District Administrator Recommendation District Director of Transportation & Land Use Recommendation Permit issuance by District Administrator’s Designee Permit Request Receipt District Administrator’s Designee Transportation & Mobility Planning Division Approval Recommendation** District Director of Transportation & Land Use Transportation & Mobility Planning Division District Director of Transportation & Land Use Approval Recommendation Chief Engineer Review & Approval

Upload: kato-phelps

Post on 31-Dec-2015

20 views

Category:

Documents


1 download

DESCRIPTION

APPENDIX 4 Processing Land Use Permit Requests for Change of Limited Access Control (Changes typically involve shifting, moving or breaking right-of-way control). Permit Request Receipt District Administrator’s Designee. Right-of-Way Division. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: APPENDIX 4 Processing Land Use Permit Requests for Change of Limited Access Control

APPENDIX 4 Processing Land Use Permit Requests for Change of Limited Access Control

(Changes typically involve shifting, moving or breaking right-of-way control)

Draft Resolution Right-of-Way Division

Commonwealth Transportation Board

District Administrator

Chief EngineerReview & Recommendation

Right-of-Way Division

**The Chief Engineer must approve the permit request prior to the issuance of a land use permit authorizing work within the limited access right of way. Transportation and Mobility Planning Division Land Use Permit Staff will ensure that all district reviews have been completed, CTB approval has been granted, monetary compensation has been paid and any/all other conditions have been satisfied prior to submitting the permit request to the Chief Engineer.

Review & Comment Appropriate District Staff

District Administrator Recommendation

District Director of Transportation & Land Use Recommendation

Permit issuance by District Administrator’s Designee

Permit Request Receipt District Administrator’s Designee

Transportation & Mobility Planning

Division Approval Recommendation**

District Director of Transportation & Land Use

Transportation & Mobility Planning Division

District Director of Transportation & Land Use Approval Recommendation

Chief EngineerReview & Approval