ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V, 1250 KVA, 3ph, 50Hz Diesel Generator Set –2 Nos. (Including Control Panel & Accessories) INDEX: I. DIESEL ENGINE WITH ALL ACCESSORIES. II. BRUSHLESS 415V ALTERNATOR WITH ALL ACCESSORIES. III. GENERATOR MONITORING AND CONTROL PANEL IV. INSTRUMENT / PROTECTION TRANSFORMERS. V. TESTS TO BE CARRIED OUT. VI. INSTALLATION REQUIREMENTS. VII. FABRICATION GUIDELINES / INFORMATION ON HANDING OVER. VIII. GTP-1. IX. GTP-2. X. BIFURCATION OF SCOPE OF WORK. XI. SPECIAL TERMS AND CONDITIONS. XII. REALISATION SCHEDULE. XIII. CHECKLIST. XIV. PRICE BID FORMAT. XV. DRAWING NO: 01/SHAR/CMD/2016004307 XVI. DRAWING NO: 02/SHAR/CMD/2016004307

Upload: trankien

Post on 26-Jul-2019

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

ANNEXURE TO INDENT NO: SHSH 2016004307

TECHNICAL SPECIFICATIONS

SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF

LT 415V, 1250 KVA, 3ph, 50Hz Diesel Generator Set –2 Nos. (Including Control Panel & Accessories)

INDEX:

I. DIESEL ENGINE WITH ALL ACCESSORIES.

II. BRUSHLESS 415V ALTERNATOR WITH ALL ACCESSORIES.

III. GENERATOR MONITORING AND CONTROL PANEL

IV. INSTRUMENT / PROTECTION TRANSFORMERS.

V. TESTS TO BE CARRIED OUT.

VI. INSTALLATION REQUIREMENTS.

VII. FABRICATION GUIDELINES / INFORMATION ON HANDING OVER.

VIII. GTP-1.

IX. GTP-2.

X. BIFURCATION OF SCOPE OF WORK.

XI. SPECIAL TERMS AND CONDITIONS.

XII. REALISATION SCHEDULE.

XIII. CHECKLIST.

XIV. PRICE BID FORMAT.

XV. DRAWING NO: 01/SHAR/CMD/2016004307

XVI. DRAWING NO: 02/SHAR/CMD/2016004307

Page 2: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

Supply, Installation, Testing and Commissioning of 415V,1250 kVA,3 phase, 50 Hz, 0.8 p.f, Diesel Generator set and

Control panel with all accessories

BRIEF SCOPE:

Diesel engine of the DG set shall be complete with necessary controls and safety devices conforming to relevant ISS/BSS with

latest amendments. The Diesel Engine shall be suitable for continuous duty operation of Generator set with electronic control panel

(compatible for SCADA) and inclusive of fly wheel, flexible coupling, air cleaner, fuel pump, fuel filter, electronic governor, electrical

starting system with starter, battery, voltage regulator, instrument panel indicating running hours and RPM indicator, residential

type exhaust silencer, protections against Over speed, High water temperature, Low lubrication oil pressure etc as described in

following sections.

The engine shall be air cooled, fluid cooler (remote radiator). The remote radiator has to be installed over a plinth outside

the DG room with necessary pipe lines from air cooler fluid cooler (remote radiator) to the engine. The Alternator shall be of rating

415V, 1250kVA, 3 Phase, 50 Hz, 0.8 p.f, self excited, self regulated, brushless type, drip proof conforming to IS: 4722 with latest

amendments.

The DG set shall be capable of functioning at places situated altitude up to 1000 meters and ambient temperature upto 45

deg. Centigrade and relative humidity upto 95%. The Main system and all sub systems shall have SCADA compatibility such that the

system shall be complete in all respects with required accessories to function in a SCADA environment when it is realized.

The alternator shall have over current relay, earth fault relay, differential and reverse power protections and neutral

grounding resistor and also shall have temperature scanning through RTDs and BTDs with multiple window annunciation.

The engine and alternator shall be coupled over a sturdy common base frame. The scope include complete DG set with all

accessories, exhaust piping, 990 Ltrs. capacity day fuel tank, self supporting steel structures for exhaust pipes and cooling pipes, fuel

lines, flow meters, control panel.

The D.G set should be Prime Rated for 1000kW suitable for withstanding one hour overload in any 12 continuous hours

operation. Commissioning includes satisfactory load testing also. The DG set along with control panel, switch boards etc. shall be

installed in DG room at SVAB substation which is approximately 10-12km from SHAR Main Gate.

The rates shall include the cost of pipes, fittings etc required for fuel line and exhaust piping complete with necessary

supporting arrangements, installation, mechanical protection / cladding arrangements etc. The Exhaust pipes inside DG room should

be covered with Aluminum foil after insulation.

The Diesel Engine and Accessories shall comply with relevant Indian standards / British standards specifications with latest

amendments. The self excited and self regulated alternator, Control panel, and Switch gears shall comply with relevant Indian

Standards / British Standard specifications with latest amendments.

Other requirements:

1. The alternator shall be provided with the following protections

a) IDMT overcurrent .

b) IDMT earth fault.

c) Instantaneous short circuit.

d) Over voltage.

e) Under voltage.

f) Differential protection.

g) Field failure relay to trip ACB as well as Diesel Engine.

h) Reverse power

i) Reverse Reactive power

j) RTD in minimum six locations with scanner.

k) BTD in minimum six location with scanner.

Note: Combinational / separate Numeric relay with SCADA provision (communicable port) shall be

provided for the protections under a) to e). Others relays are preferred with Static version.

Page 3: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

2. The Engine shall have the following additional protections also (in addition to the standard accessories

fitted with engine).

a) Over speed (both alarm and trip)

b) High coolant temperature.

c) Low lub oil pressure trip.

d) High oil temperature (optional)

e) Tripping against Differential protection relay actuation

4. Exhaust Pipe Support Structure: A suitable box type MS structure of cross section minimum 1.8M x 1M

using angle frames (minimum 50x50x6 mm size ) / ISM channels (minimum 100x50 x6mm size ) shall be

with necessary supporting clamps for the exhaust pipes shall be provided from ground level up to the end

of silencer for maintenance. Providing the required structural support base plate also form part of the scope.

The exhaust pipes shall be suitably supported to withstand even cyclonic wind speed conditions.

Necessary concrete Foundation / concrete bed for supporting the structure base plates shall form a part of

the scope of the supplier. However the actual execution shall be done only on the prio approval of the

related structural drawings by the Department.

The height of the box type support structure is likely to be 17m from ground level. The smoke shall be let

out at a height of minimum 7.5m above the roof level which is 9.5m.However as per pollution Board norms,

appropriate height shall be provided such as to safely let out the smoke.

GENERAL POINTS :

1. Installation, Testing and commissioning of DG set shall be as per the guidelines given separately.

2. Schedule for panels and other works are listed in subsequent sections.

3. The Diesel Engine, Alternator, panels, cables, instruments etc. shall conform to respective IS

specifications with latest amendments.

4. The makes of Diesel Engine, Alternator shall be one among the following only:

Diesel Engine : Cummins / Caterpillar / Perkins / Volvo Penta

Alternator : Stamford -AVK / Leroy-Somer / Crompton Greaves

DETAILED SCOPE:

I. DIESEL ENGINE WITH ALL ACCESSORIES:

DG set shall consist of the following:

1. Diesel Engine: The Engine shall be water cooled, turbo charged with after cooler suitable for Generator

application, developing 1470 BHP (nominal) @1500 RPM, under NTP conditions of BS: 649 with an

overload capacity of 10% for one hour in any 12 continuous hours of operation. The engine shall be

suitable for cold starting. The engine shall be of latest technology with Electronic Fuel Control (EFC) with

SCADA Compatibility / communicable port.

Page 4: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

The engine shall be equipped with the following minimum standard accessories.

a) Cooling System (Remote Radiator):

Air cooled fluid coil cooler with remote radiator consisting of finned surface heat transfer coils made of

Copper tube, Aluminum fins, Axial flow propeller fans, Fan motors, Electrical junction box with wiring,

Expansion tank with GI sheet steel casing and Heavy duty base frame suitable for floor/ plinth mounting etc.

The Coil cooler shall be suitable for withstanding coastal weather conditions. Coil cooler should be

designed to withstand cyclonic wind speeds.

b) Fuel System:

Fuel system shall consist of:

a) Fuel Pump - Shall be of latest version suitable to meet the regulation stipulated even under

varying load conditions

b) Injectors – Heavy duty STC preferred

c) Fuel Filters- including primary filter

d) Self contained piping

C) Lubricating System:

Lubricating system shall consists of:

a) Lube Oil Pump (Engine mounted)

b) Strainer

c) Lub oil cooler

d) Lub oil filter

e) Lubricating bypass filter

f) Self contained piping

g) Dip stick

h) Necessary piping with valves etc and provision for draining engine oil from sump during

maintenance of engine shall be provided and the pipe shall be extended suitably (Approx.7 Mtr).

d) Air Intake system: Air Intake System shall consists of :

a) Dry type filter

b) Air intake manifold with necessary connections

c) Turbo Charger with after cooler

Page 5: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

e) Exhaust system:

Exhaust system shall consist of:

a) Exhaust Manifold

b) Flexible piping

c) Exhaust silencer (Residential type) – The type of residential silencer shall be as per the

recommendation of Engine manufacturer.

The pollutants present in exhaust gas shall be within permissible limits, and as indicated by the

pollution control board. Necessary scrubbers, pollutant eliminators shall be included if required.

Check point pockets shall be provided for the Silencer in accordance with PCB regulations for

inspecting and checking the emissions. Provision (pockets) shall also be provided for monitoring

exhaust gas temperature.

Fabricated supports for the exhaust pipe, silencers etc. shall be provided as required at site by

Department. Exhaust pipe shall be raised to the required height above roof slab as per the norms of

Pollution Control Board. The exhaust pipes shall be applied with heat resisting painting after proper

surface treatment. The exhaust pipes within the building shall be provided with thermal insulation

and cladding.

Suitable support structure for each silencer shall be provided during erection at site. The structure

shall be of self standing nature and integrated with rigid MS sections and joineries. The metallic

structure shall be applied with anti corrosive painting of approved shade. The scope also includes

necessary civil foundation works for the support structure. The exposed pipe shall be suitably

supported against cyclonic wind speeds. The drawings of silencer support structure and civil

foundation shall be got approved by Department before execution. Modifications / improvements

pointed out by Department in view of healthy engineering practice shall be incorporated and

executed at site at no extra cost. The preliminary drawings shall be provided with tender

documents.

The civil works required for supporting the structure over roof/walls by making openings for

conveying exhaust pipes, cooling circuit pipe lines, oil drain pipe line, providing grouting for

supports / brackets on wall /floor/ plinth and suitably finishing to match the existing surroundings

shall be the scope of the supplier.

Rain water drain facility shall be provided at drain point of each silencer by providing 50 mm dia MS

pipe down up to a height of 150 cm (5.0 ft) from the ground level with suitable control valve.

f) Genset Controller:

The DG set shall include a Latest version of Microprocessor based Genset controller with monitoring,

metering, protection and control features. The controller shall be SCADA compatible and it should also be

possible for all system parameters to be monitored and adjusted thro’ Laptop computer / PC. The controller

shall have the following features:

a) Digital governing and voltage regulation.

b) AC output monitoring.

Page 6: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

c) Monitoring of battery system, critical engine parameters.

d) Engine Start / Stop

e) Lube oil pressure indication, Water Temperature indication, Running Hour indication and RPM

indication, battery charging healthy / voltage indication with safety controls for low lubricating oil pressure,

High water temperature, Engine over speed.

Necessary sensors, gauges and trip switches shall be provided for ensuring the above annunciation

and safety controls. The control wiring shall be done by using standard harness / connectors and

terminated by using sleeved cable lugs by providing necessary terminal blocks which shall be vibration and

heat resistant. Proper identification ferrules and markers for easy identification shall be provided at all

terminals.

g) Governing System:

Governing system shall consist of Electronic Fuel Control Governor (EFC) with plus or minus 1% or

better regulations.

h) Starting System:

Starting system shall consists of:

a) Suitable Self Starter

b) Battery charging system (generator) with voltage regulator for providing appropriate DC

charging power to battery when the DG set is running.

i) Other Accessories:

a) High Inertia Fly wheel & Flywheel Housing to suit alternator / Engine

b) Hour meter & RPM indicator

c) Separate Battery charger static type for charging batteries during idle condition, permanently

connected to the batteries. This shall be mounted inside control panel or supplied separately.

i) Batteries:

Batteries of suitable capacity to start the engine from cold conditions are to be provided. The

batteries shall be supplied in fully initial charged condition housed in a separate stand along with suitable

leads and terminals etc,. Batteries shall be of reputed makes and as approved by Department, confirming to

relevant IS standards.

J) Base Frame:

The engine and alternator shall be perfectly aligned and assembled on a sturdily fabricated,

adequately machined base frame made out of high quality MS / heavy duty rolled steel channels. The base

frame shall be provided with lifting facilities and pre-drilled bolt holes for installation with anti-vibration pad

mountings.

Page 7: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

NOTE:

01) Foundation for DG set will be provided by the department, Installation of DG set over the bed shall be

done by supplier .

02) Providing concrete beds for cooling towers, foundation / plinth for exhaust support structure shall form

a part of the scope of the supplier. However the civil drawings shall be executed only after the approval of

the Department.

Civil works like installation / integration of frame supports for exhaust piping, coolant piping, grouting of

accessories, providing openings in walls for pipe entries and making them good as per original condition and

as a part required for the Installation works, shall be all be done by supplier.

h) Fuel Tank:

1) Supply and installation of day fuel tank of 990 litres capacity square / rectangle shape for DG set shall

consists of Fuel Inlet, Outlet pipe connections, Control Valves, Filling cap, Drain plug, Air vent, limit switch to

cut off power supply to the motor pumping diesel to the day tank, analog flow meter to measure the

amount of diesel pumped from the UG tank to the day tank, Level indicator with graduated scale with clear

reading arrangement and manual cover suitable for floor mounting.

2) The diesel flow meter (Kent /equivalent make) of 0.5% accuracy shall be used to indicate the total

quantity of Diesel oil used for pumping to the day fuel tank. Factory calibration / test certificate shall be

furnished during installation.

3) Provision of necessary diesel MS pipe lines of 1” dia. between day fuel tank and UG tank and DFT to

engine (supply and return lines) also form part of scope. The item also includes necessary pipe accessories

like motor pump set, valves, bends, coupling, nipple etc.

II. BRUSHLESS 415V ALTERNATOR WITH ALL ACCESSORIES:

The alternator shall be suitable for continuous operation to give an output of 1000KW / 1250 KVA at

415 Volts, 3 Phase, 0.8 PF (lag) suitable for the diesel engine as specified above and run at 1500 RPM. The

Alternator shall be of self-excited brush less type.

The AC generator shall be with the exciter field supplied by panel mounted solid state voltage

regulators in accordance with IS with latest amendments and Confirming to IS:4722/IEC 60034

specifications. The voltage regulator shall have a minimum regulation 1% or below of rated voltage from

No-load to Full-load.

The alternator shall be suitable to supply to our system loads such as rectifier, UPS, PLC systems and

computer loads without any distortion in output AC voltage wave form.

The transient performance of alternator shall be such that line to line voltage will recover to 97% of

the final steady state voltage within one second when a balanced and symmetrical load of rated KVA at low

PF (0.3 to 0.4 lag) is impressed on an initially unloaded generator.

a) Insulation Class of Alternator:

Page 8: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

The class of insulation for stator, Rotor and exciter windings shall be minimum of class ‘H’ as per relevant

ISS. The winding shall be coated with suitable Gel / appropriate coating that is required for satisfactory and

prolonged operation in saline and moist atmosphere.

b) Overload:The alternator shall be able to meet an over load of 10% for a minimum period of 1 hour in

every 12 hours.

c) Enclosure:

The alternator shall be screen protected, drip proof, ensuring IP: 23 enclosure or better.

d) Terminal Arrangement:

The alternator terminals shall be suitable for terminating 2500A FP bus bar trunking system. The alternator

neutral shall be suitably brought out with appropriate support insulator so as to enable external neutral

earthing.

e) Accessories:

Alternator shall be provided with the following additional accessories:

a) Necessary space heaters with control switch and visual indicators.

b) 6 Nos. Winding Temperature Detectors and 2 Nos. of Bearing Temperature Detectors with suitable

scanner mounted in control panel.

f) Earthing: Alternator shall have two numbers of earthing terminals of adequate capacity.

NOTE:

1) The alternator should be suitably designed such that it should not cause any interference to the existing

Telecommunication net work.

2) One AVR shall be installed in alternator frame or with suitable cubicle with required CTs etc and one no.

spare AVR shall be supplied for which rates shall be quoted separately.

III. GENERATOR MONITORING & CONTROL PANEL WITH METERING, PROTECTION,

CONTROLS & ANNUNCIATION FOR DG-I & II

Note: DG Main Panel board comprising of the incomer ACBs for the two DG sets shall form a part of the

scope of the Department. Necessary Control Cabling between the DG Control Panel (supplied by bidder) and

the DG Main Panel (provided by Department ) shall also form a part of the scope of the supplier.

The Generator control panel shall be complete with all components and wiring and shall consists of

the metering, protection, controls and annunciation required for both DG I & DG II, with two independent

compartments clubbed together that can be split up (if required) based on the site requirements and as

follows:

Page 9: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

a) Protection: DG sets shall be provided with Numerical Relays with the following protections.

Combinational relays are also acceptable.

1.0) Combined Earth fault and over current with IDMTL characteristics (This can be provided in control

panel or VCB panel)

2.0) Instantaneous type differential relay for protecting alternator windings

3.0) Field failure protection

4.0) Reverse Power protection

5.0) Reverse KVAR protection

6.0) Under Voltage protection

7.0) Over Voltage protection 8.0) Differential Protection

NOTE:

01. All relays shall be of one of the make as approved by Department.

02. In case of operation of differential relay, Unit tripping shall be provided, i.e, the prime mover must

also stop so as that the alternator comes to rest immediately apart from tripping of the ACB.

b) Metering: All meters shall be Digital and LED display of approved make. Any other meters apart from

below if required to ensure monitoring of DG set shall also be provided.

a) Ammeter of suitable range with built in selector switch. - 1 No / DG Set.

b) Volt meter with built in selector switch. - 1 No / DG Set.

c) Power Factor meter. - 1 No / DG Set.

d) Frequency Meter. - 1 No / DG Set.

e) DC Ammeter & Volt meter for monitoring Field Current & Voltage. - 1 No / DG Set.

f) Tri-vector (KVA/KVAR/KW) meters/ Multi function meter with communication feature - 1 Set / DG Set

c) Indications: LED indication shall be provided to indicate the Generator ‘ON’ & ACB ‘ON’ ‘OFF’ & ‘TRIP’

Condition for both the DG sets.

d) Push button with Actuators for DG I & II:

Each DG set shall be furnished with the following Push button actuators in the Control Panel for:

a) Engine Start

b) Engine Stop

c) Fault Accept/Reset

d) Emergency Stop

e) Switches:

Switches shall be provided for speed raise / lower option & Voltage raise / lower option. Necessary

Protection shall be provided in order that both raise / lower options are not exercised at the same time.

f) Temperature Scanner: Auto Scanner with required number of channels to measure and indicate the

temperature of windings and bearing with automatic tripping and alarm facilities and with 1 No. hooter shall

be provided.

g) Annunciation: Annunciation system shall contain audio and visual annunciation’s provided for Diesel

Engine and Alternator. The multiple window annunciation shall be complete with accept/reset push buttons

for hooter and visual indication systems.

Page 10: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

IV. INSTRUMENT / PROTECTION TRANSFORMERS:

Instrument transformers of adequate nos. for realising the total protection and metering

requirements shall be provided. All the instrument transformers shall be of resin cast encapsulated type and

of Department approved make. The burden and ratios shall be appropriately selected. The accuracy of

metering transformers shall be class 0.5. Necessary interconnections from alternator to these transformers

and to all panels are in the scope of supplier.

The makes of components such as relays/meters/CTs shall be one among the following only with the given

order of preference. Only the approved makes are to be adopted during fabrication.

Meters : A.E, L&T, Conzerv, GE Digital, Clectro systems, CG Schlumberger

CTs : Kappa Electricals, A.E, Intrans, Nippen, Neutronics, C&S

Relay : Prok-DV’s, Siemens, GE-Alstom /GEP

Push buttons/actuators/LED : L&T, Siemens, Vaishnav, BCH, Tecnic, GEP, Schneider, - indicating

lamps : ABB, CG, Binay

MCBs & metal clad sockets : MDS legrand, Siemens, Hager, Merlin Gerin, S&S

SFUs : L&T, Siemens, ABB , Schneider/Merlin Gerin

Fuse base/ carriers & Fuses : L&T, Siemens, Standard, Havells, Indo-kopp, GEP

V. TESTS TO BE CARRIED OUT

The tests as described below are required to be carried out as per relevant standards. In case, the

acceptance tests does not show satisfactory results, the contractor shall at his own expense rectify and

replace the defective components or any part thereof as directed by the authorised representative of the

Department within one week. The installation shall be re-tested after rectification / replacement of the

defective components without any extra cost. For such tests the cost of fuel and engine oil shall be borne by

the supplier.

01. ACCEPTANCE TEST AT MANUFACTURER’S WORKS:

The DG set and panels shall undergo the following acceptance tests at the factory / manufacturer’s

premises of Engine/ alternator / panel.

A). ENGINE:

1) Fuel Consumption test

2) Governing test

B) ALTERNATOR:

1) Measurement of Resistance

2) Phase sequence test

3) Regulation test (Cold condition)

4) Measurement of short circuit characteristics

5) Measurement of Open circuit characteristics

6) Measurement of Insulation resistance

7) High voltage test

8) Voltage balance test

Page 11: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

C) CONTROL PANEL

1) Physical inspection – Check for inventory / components as per

approved drawings, dimension & sizes.

2) Electrical Tests – Test for satisfactory operation of all meters, relays, instrument transformers etc,

IR test, HV test

NOTE:

1. Acceptance tests other than above, as applicable to the relevant items shall also be carried out.

2. Necessary Test certificates shall be submitted along with supply.

02. ACCEPTANCE TESTS AT SITE: Phase – I

On completion of all the installation works, the DG sets and panels shall undergo the following tests at

site.

a) Visual examination of all parts and accessories

b) Measurement of resistance

c) Insulation resistance test

d) Earth continuity

e) Tests for normal operations of all protective relays and instruments

f) No load test to check the normal performance of Engine, Alternator, and all other accessories

03. ACCEPTANCE TESTS AT SITE: Phase – II

a) On satisfactory completion of Phase – I tests, the DG set shall undergo the following tests for 12 hours,

by directly loading the DG set. Necessary loads will be arranged by the department. Lubricating oil and fuel

required for the above tests will also be provided by the department at free of cost. The engine should be

supplied complete with the first filling of lubricating oil by the supplier.

b) During the above tests, following parameters shall be checked:

1. Cooling system temperature

2. Lubricating oil temperature

3. Lubricating oil pressure to the engine and turbo charger

4. Fuel oil consumption

5. Speed cum frequency variation on throwing ‘ON’ and ‘OFF’ at full load

6. Voltage variations.

7. Transient voltage dip / recovery on applying step loads.

8. Testing of failure conditions by simulation.

a) Following tests, are also to be conducted at site:

1) Phase sequence test

2) Regulation test

3) Winding & Bearing temperatures while running the DG set

4) Temperature of windings after continuous full load test

5) Testing of all panels including Relays.

Page 12: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

VI. INSTALLATION REQUIREMENTS

Particulars Description

Acceptance to be

furnished by the

tenderer

1. Installation

of DG set

Installation of DG set includes following:

1) Positioning on existing concrete bed

2) Providing foundation bolts and proper placement

3) Providing all necessary Aux. equipments

4) Providing cooling system with piping Bellows etc.

5) Providing fuel pipe lines

6) Providing exhaust piping with bellows, Silencers

and up to standard minimum height

7) Alignment of DG set.

8) First filling of coolant, lubricants, filters etc.

9) Providing Battery system and charger.

10) Providing AVR with necessary CTs

11) Engine EFC panel with Metering / indication etc.

12) Installation of Coil cooler over the Plinth and piping

13) Providing Electronic Fuel Control (EFC) with SCADA

Compatibility / communicable port.

14) Providing Auto Lubricating oil feed system, Auto Cooling

Water feed system at site.

15) Associated miscellaneous works for all the above

Items complete as required.

1. Installation

of DG

Control Panel

Installation of DG control panel includes

1) Positioning at trench

2) Providing Base Channels

3) Fixing all Components

4) Executing all associated external wiring / cabling

5.Installation of

Fuel Tank

Installation of Fuel Tank includes

1) Positioning in the niche

2) Providing all inlet / out let piping related works

6. Laying of

Cables

Laying of cables includes Transportation to site,

providing necessary clamps Brackets / trays / spacer

& saddle etc, Providing clear indentification for cables.

7. Termination of

Cables

Termination of cables with the help of

Suitable glands, interconnection among panels /

Equipments / systems etc

8. Installation of

Aux Equipment

Panel

Installation of Aux Equipment Panel Includes

1) Positioning at trench

2) Providing Base Channels

3) Fixing all Components

9.Installation of Installation of Diesel flow meter with necessary extra fittings

like Coupling, collar, butterfly valve as required in the main line

Page 13: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

Diesel flow meter

from UG tank as instructed by Dept.

10. Other items The scope includes supply and installation of any other

Items required for completing the scope of P.O.in entirety.

11.Civil Works

1. Foundation and Pedestal Works for Remote Radiator

2. Foundation and associated civil works for exhaust pipe support

structure.

However, the civil works shall be executed only after getting the

drawings approved from the Department.

12. Testing and

Commissioning

As per Point No: V in the Annexure.

13. Miscellaneous items

Before commissioning, the following also are to be provided:

1) Rubber mats for panels

2) Fire buckets with stand

3) Danger boards

4) Hand gloves

5) Operating handles

6) Other safety items like First aid chart.

7) Required coordination and compliance to relevant points when

CEA inspection is arranged by Department for obtaining necessary

statutory clearances is in the scope of the supplier. However

requisite statutory inspectorate fees if any will be paid by Dept.

8) After successful installation and testing the system may be

commissioned and all documents / completion drawings as

relevant may be prepared and handover over.

DEVIATIONS IF

ANY

Tenderers are adviced to bring out deviations if any and explain

alternate arrangement to provide desired functional provision as

per Department indent requirement.

Signature of Tenderer

Page 14: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

VII. FABRICATION GUIDELINES / INFORMATION ON HANDING OVER

01. PANEL FABRICATION :

All the panel cubicles shall be fabricated from 2mm thick CRCA sheet steel and shall be folded and

braced to provide rigid support for all components. All joints in sheet shall be seam welded, all slags shall be

rounded off and welding pits smoothened. All panels and covers shall be properly fitted. The board shall be

of totally enclosed design and completely dust and vermin proof. Gasket between all covers shall be used to

render the joints effectively dust tight. Soft compressible gaskets shall be used between all metal joints,

doors and with covers to prevent ingress of dust.

A horizontal wire way with screwed cover shall be provided at the top to take interconnecting

control wiring between different vertical sections with suitable provision for supporting all the cables

leading inside. Any control wiring inside shall be neatly bunched and tied with cable ties and positioned in

UPVC cable tray / channels where required inside. Separate and adequate compartments shall be provided

for accommodating instruments, indicating lamps, selector switches, control fuses etc.

The mechanical design of the panel doors shall be such as to avoid buckling and supported with

adequate hinges. Tool operated fasteners shall be provided for the panel doors.The provision for earthing

the body of panels shall be provided at two distinct places.

02. PAINTING:

Special attention shall be paid to the finish and general appearance of the work. The panels body

shall undergo suitable metal surface treatment by 7 tank process before final painting with powder coat of

Dept. approved shade.

The supplier shall ensure that no scratches appear on the painted surface while transporting and

installing the DG set / panels. Pipe lines shall be painted in accordance with IS: 23479/1963 with latest

amendments. The parts of the DG set installation which are not factory painted shall be given three coats of

oil paint consisting of one primer coat of red oxide, one under coat and one finishing coat of superior quality

paint.

The exhaust pipe and silencer must be painted with heat resistant aluminum paint and should be

guaranteed for one year. All the interiors of all the panel boards shall be painted with fire retardant paint.

Page 15: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

03. The supplier is required to complete the installation /system as per statutory provisions in order to

facilitate obtaining of clearance from Central Electricity authority ( CEA ) for energisation of the system

and from the Pollution Control Board for the DG set as required. Necessary documents, drawings etc shall

be handed over to Department. However Department will pay the inspection fee and arrange for the

inspection. In case any rectification points are adviced by the Statutory body as applicable for the system,

shall also be executed.

04. TAKING OVER :

The DG sets and allied equipment / panels shall be taken over by Department after satisfactory

completion of all the Acceptance tests and after obtaining statutory clearances. In case the acceptance

tests as described separately, does not produce satisfactory results, the supplier shall at his own expense

rectify and replace the defective components or any part thereof as directed by the authorised

representative of the Department. The installation shall be re-tested after rectification / replacement of the

defective components without any extra cost. For such tests the cost of the fuel and engine oil shall be

borne by the supplier.

At least three complete sets of documents like, O&M manuals (one in original), Complete as built

installation Drawings, wiring drawings, Test certificates etc. must be submitted for all the equipments for

taking over the system.

During Guarantee period, defects noticed if any affecting the performance of the system /

installation, they shall be set right by the supplier at no extra cost. During the Guarantee period, the supplier

shall depute their own service Engineer or authorised service Engineer to make minimum 4 visits

(quarterly basis) for regular maintenance. The cost of consumables required during the one year warranty

shall also be quoted in the price bid and indicated in the price bid format.

During post warranty period, authorised nearest AMC agency for the DG set shall be identified so

as to avail regular service. The particulars of service agency shall also be furnished in Techno commercial

bid.

VIII. GTP 1

Page 16: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

(Guaranteed Technical Particulars to be furnished by the tenderer in respect of Engine, Alternator, Panels)

Tenderers to confirm / clarify / furnish appropriately all the information as per the technical particulars. Necessary technical

catalogues / test certificates shall also be enclosed. Deviations if any shall be clearly brought out in the technical bid.

Sl. No. Description Department Specification** Tenderer’s specification

1 Engine Make Cummins / Caterpillar / Perkins/ Volvo Penta

2 Alternator Make Stamford – AVK / Crompton Greaves / Leroy

Somer

3 Load /application Induction motors/ Lighting, Air-conditioning

and UPS systems including PC & SMPS loads

through 11kv/433v Transformers

Tenderer to confirm the suitability of DG for above

loads

4 Diesel Engine

a Make and Model Tenderer to specify

b BHP 1470 BHP

c RPM 1500 RPM

d Cooling System Air cooled coil cooler

e Fuel System Tenderer to confirm compliance to provisions

as per indent schedule

f Lubricating System Tenderer to confirm compliance to provisions

as per indent schedule

g Air In-take system Tenderer to confirm compliance to provisions

as per indent schedule

h Exhaust System Tenderer to confirm compliance to provisions

as per indent schedule

i Governing system

EFC with 1% regulation

Electronic governor

j Starting system Electrical with 12V/24V DC batteries,

charging system, battery stand,

interconnecting cables

k Instrument Panel with:

Starting Switch, display for

Lub. Oil Pr., Water Temp.,

RPM, Run-hour, Battery

Voltage and safety controls

Tenderer to confirm

l Mounting of DG set Indicate whether direct floor mounting

5.0 Alternator

a. Rated Capacity 1250 KVA

b. Make and Model Tenderer to specify

c. Self Excited, Brush-less,

1500 RPM, 415V, 50 Hz,

3Phase, 4 wire, 0.8 PF lag,

with AVR of 1% regulation,

suitable for the above Diesel

Engine

Tenderer to confirm

d. Nominal current rating Tenderer to specify

e. Efficiency Tenderer to specify

Page 17: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

f. Insulation Class Class H or better

g. Over load capacity Tenderer to specify the % over load

permissible

h. Enclosure IP 23 or better

i. Terminals 3 Line and Neutral

6.0 Control Panel Tenderer to confirm compliance to provisions

as per indent schedule

a. Make of meters Tenderer to specify the

make & model also

b. Protective Relays Tenderer to specify the

make & model also

c. Other Standard Protections Tenderer to specify protections other than

those under 6.2 above, if offered

d. Indications All with LED lamps

e. Built-in Battery Charging

arrangement

Required

f. Annunciation as specified in

tender

Tenderer to confirm compliance to provisions

as per indent schedule

Deviations if any

** REFER `DETAILED SCOPE’ FOR FURTHER DETAILS

Signature of Tenderer

Page 18: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

IX GTP 2 : OTHER GENERAL PARTICULARS

(To be furnished by Tenderer)

Sl. No Particulars As per Indent To be furnished by the

Party

1.0 Guarantee / Service during

Guarantee period

Guarantee : Min. 12 months from the date of

commissioning.

Service: Minimum 4 quarterly visits during

Guarantee period (Ref Annexure VII-04 for

details). Details of nearest service agency are

to be furnished in tender document.

2.0 Vendor Details

a. Company Confirm if you are OEM/ Authorized dealer/

set builder and Furnish necessary certificate

from concerned manufacturer.

b. Company Profile To Furnish brief information

c. List of customers To furnish details of previous similar supplies

to Govt. Organizations/ Undertaking and

performance certificate if any to be enclosed.

3.0 Any other relevant

information.

To be Furnished by Tenderer

Page 19: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

X BIFURCATION OF SCOPE OF WORK:

S.No Description Scope

1 Supply of 2nos. Of 415V, 1250 kVA DG sets including all accessories,

electronic engine controller, DG control panel, stack, exhaust pipes, fuel

day tanks, interconnecting pipelines from day tank to engine and external

fuel pipelines to connect to Department's UG tank, cooling towers, its

associated pipelines, control and power cables and starter panels,

batteries, battery chargers as per the Department specifications.

Supplier

2 Transporting the entire DG sets' consignment from factory / works to SDSC

SHAR Supplier

3 Unloading the consignment at a desired location identified by Department

authorities inside SDSC SHAR. Supplier

4 Material Handling equipments and manpower for unloading the DG set

consignment. Refer foot note of this table. Supplier

5 Construction of concrete pedestal / bed for positioning the DG based on

the input received from the Supplier after the receipt of PO. Department

6

Support steel structures for the exhaust pipe up to the required height

including foundation for the structure and the associated civil works

including foundation at site. Supplier

7 Concrete pedestal civil works for the cooling towers and silencer support

civil foundation based on the approval of the drawings by the Department

after the receipt of PO.

Supplier

8 Checking the consignment for safe arrival of all items along with all fixing

materials as per the manufacturer's checklist after the arrival of DG set

consignment in SDSC SHAR. Supplier

9 Positioning / Assembling the DG set on the concrete pedestal.

Supplier

10 Tools and materials required for assembling the DG sets

Supplier

11 All necessary interconnections between the engine and its electronic

engine controller, control cables between the engine control panel and the

DG control panel, control cables between the DG Control Panel and the DG

Main Panel.

Supplier

Page 20: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

*** Incase of inability of the contractor to arrange for material handling equipments, the same shall be

arranged, ONLY based on the then availability of Department equipments, on chargeable basis. However,

manpower shall be arranged ONLY by the Supplier.

12 Interconnecting the alternator and the DG Main Panel using bus duct.

Department

13 DG control panel with all its necessary inventory and interconnections with

alternator and other panels as per the Department specifications. Supplier

14 Installation of cooling towers on the pedestals along with other associated

works like supply and installation of starter panels, necessary pipeline

interconnections along with any minor required civil works, power and

control cables for the cooling towers and starter panels, their necessary

interconnections with the AC power source identified by the Department.

Supplier

15 Installation of day fuel tank with all necessary pipelines, pumps, motor

starters and associated minor civil works like opening of walls, plastering,

finishing etc.

Supplier

16 External fuel supply system, that is, from UG fuel tank to day tank using

necessary pipelines, butterfly valves, flowmeters, overflow pipeline system

from day tank to UG fuel tank and associated minor civil works.

Supplier

17 Earthing of Alternator, control panel including earth strips, provision of

earth pits, necessary interconnections. Department

18 Installation of exhaust pipelines including necessary minor civil works.

Supplier

19 Testing and Commissioning of DG sets at site as per relevant standards. Supplier

20 Arranging Inspection visit of Central Electricity Authorities. Department

21 Any modifications brought out by CEA authorities with respect to DG sets

and control panel. Supplier

Page 21: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

XI SPECIAL TERMS AND CONDITIONS

01. The tenderer should furnish OEM certificate from concerned Manufacturer.

02. The tenderer shall provide all the technical information as called for in the Annexures and also provide all the technical

literatures and drawings related to their products and all other instructions to be followed for installation along with offer as

per rules and regulation. Any deviations against our indented specifications shall be clearly mentioned.

03. The tenderer shall furnish the list of customers and their addresses with similar capacities of DG sets and panels installed by

them. Also performance certificates from customers shall be enclosed along with their offer.

04. All test facilities required shall be provided for conducting the tests prescribed in the schedule by the party at the factory /

works concerned as well as at site for commissioning. The tests shall be carried out in the presence of our Department CLIP

inspection team before despatch from their works and during commissioning of the same.

05. On receipt of Purchase Order the agency shall be submitting the following drawings for approval before manufacturing :

i) General arrangement and schematic drawings

ii) Foundation drawings

iii) Control wiring drawings

iv) Product catalogues / relevant manuals

06. The proposed place of installation of DG set is approximately 12 kM from the Department stores.

07. The scope of work include all transportation of the DG set and panels and their accessories to the work site with utmost

care in handling. All loading and unloading arrangements with necessary plants / equipment and tools shall be the part of

the scope of work and all required man power shall also be provided by the agency for unloading in the room and installing

in position as required. However material handling support like Hydra etc, will be arranged by Department at our site, based

on then availability on chargeable basis.

08. The tenderer shall be responsible for all the safe custody of the panels and accessories from the time of supply at site till

installation, testing and commissioning and handing over the same to the department on satisfactory completion of work.

09. The tenderer shall co-ordinate with other agencies during the course of the installation, testing and commissioning of the

panels and ensure safe commissioning.

10. The terms of payment may be quoted with possible split up details as under:

i) Supply of DG sets / panels at site after testing at factory/works of the manufacturer and acceptance.

ii) Installation works at site with split up rates against possible items

iii) Testing and commissioning charges etc.

11. The DG sets and panels shall be guaranteed for a period of 12 months from the date of commissioning. The supplier shall

repair / replace the damaged equipment without any extra cost during the guarantee period. Also during Guarantee period 4

nos service visits (quarterly service) is to be made by authorised service Engineer.

12. The installation work shall be started and completed immediately once the readiness of site is intimated to the agency

without any delay.

13. Details required for installation viz., providing MS channels / foundation bolts shall be furnished. Proper installation and

positioning of panels over the floor shall be the scope of the tenderer.

14. The works of installation, Testing and commissioning shall be done by employing qualified competent engineers / supervisors

and all instructions of the department shall be strictly followed for the completion of work with good workmanship as

required and as per the IE rules and regulations and other mandatory / safety requirements.

15. Any mandatory requirement specified by the inspecting authorities like CEA, Pollution Control Board shall be carried out

such that statutory clearances are availed by Department. However the inspection fee to CEA / PCB will be arranged by

Department.

16. The tenderer shall provide complete sets of operation and maintenance manuals to the department for the operation and

maintenance purpose of the department as mentioned under clause of “Taking over”.

Page 22: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

17. The department shall reserve the right to accept / reject any part of work, which is not acceptable as healthy engineering

practice of carrying out such work as the case may be. In case of any failure to carry out the scope of work in time as per the

instruction of department, the work shall be carried out / got done by the department at the cost and risk of the agency and

the entire amount with supervision charges shall be recovered from the agency.

18. In case End Use certificate from Department is required for procuring the Engine, Alternator etc, the same shall be mentioned

in your quotation itself by clearly stating the reasons.

19. Special terms and conditions in this Annexure shall also form part of the work.

20. At the time of Testing and Commissioning of DG Sets, the representatives of different agencies who have manufactured /

installed their equipment like DG set, HT panel, Control panel etc., shall remain present and it will be essential to coordinate

with other agencies as required and as directed by the Department.

Page 23: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

XII REALISATION SCHEDULE: SCHEDULE FLOWCHART

PO release (A)

Submission of all drawings

(B)

Approval of Drawings by Department

(C)

Manufacturing / Integration

(D)

Intimation of readiness (E)

Inspection at works (F)

Delivery to site (G)

Readiness intimation by Dept. for Installation

(H)

Testing & Commissioning

(J)

Installation (I)

Page 24: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

The following delivery schedule is to be duly filled by the supplier and submitted along with the technical bid:

S.NO ACTIVITY NO OF DAYS REQUIRED (to be filled by the supplier)

1. PO Date (A)

2. Submission of all drawings on receipt of PO (B) A + ‘x’ days

3. Approval of drawings by the Department (C)

4. Manufacturing on approval of drawings. ( D ) C + ‘x’ days

5. Intimation of readiness of DG Sets for inspection. (E) D + ‘x’ days

6. Inspection at works. (F)

7. Delivery of DG Sets on clearance for dispatch by Dept. inspecting engineers (G)

F + ‘x’ days

8. Readiness intimation by Dept. (H)

9. Installation of DG Sets on intimation of readiness by the Department (I)

H + ‘x’ days

10. Testing & Commissioning (J) I + ‘x’ days

Total Realisation Schedule

Page 25: ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL … · ANNEXURE TO INDENT NO: SHSH 2016004307 TECHNICAL SPECIFICATIONS SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF LT 415V,

XIII CHECKLIST:

S.NO DESCRIPTION SUPPLIER’S CONFIRMATION

1. Detailed Technical Specifications, Signed & Enclosed. Yes / No

2. Filling and furnishing GTP-I & II Yes / No

3. OEM Certificate from manufacturer, Enclosed Yes / No

4. Acceptance for all commercial terms, Signed & Enclosed Yes / No

Deviations if any: Acceptance of the supplier:____________________________

(Supplier to sign and send along with their offer)