annex a dotc mrt-3 system maintenance ......annex a dotc mrt-3 system maintenance service provider...
TRANSCRIPT
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 1 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
1
[We] would like to request your good office for permission to
conduct a depot visit of our technical team for further evaluation
and reference relevant to the preparation and finalization of
necessary bidding documents.
Bidders who purchased the Bidding Documents are allowed to
conduct site inspection upon their written request. (Please see GBB
Nos. 02-2014 and 03-2014 for the Site Visit Guidelines)
2 How is LD related to the penalty provisions for not meeting KPI
targets? Liquidated Damages is separate from the penalty provisions.
3
May we be clarified with what is referred to by the last two words
"defective equipment". Are these the equipment which are to be
subject of the maintenance works?
For example, if the contractor is not able to repair the wheel
truing machine due to whatever reason, will the contractor be
held liable to replace the truing machine or pay DOTC an amount
equivalent to the purchase price of a new truing machine?
Yes, defective equipment upon assumption of the new maintenance
provider should be repaired. For wheel truing machine,
replacement may only be an option, however, the Maintenance
Provider should ensure that the wheel truing maintenance activity
is done in accordance with the maintenance specifications.
4
In the definition of terms, it is stated that “Special Repairs”
means any repair of the System required as a result of any
damage thereto caused by any of the following:
(a) Failure of Client or any of their respective affiliates,
contractors, subcontractors or representatives, to operate the
System in accordance with the operating and maintenance
The new maintenance contract is independent of the BLT
Agreement. The peak periods are 6:30 AM - 9:30 AM and 4:30 PM
- 7:30 PM.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 2 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
manuals and established operating rules;
(c) Failure of Client, or any of its respective affiliates,
contractors, subcontractors or representatives to make the System
or any portion thereof, available to Provider for scheduled
maintenance in accordance with the requirements of the
approved Manuals and
the Operating Assumptions (refer to Annex C);
In view of the foregoing, we opine that three (3) hours peak
period in the morning and in the evening may NOT in accordance
with the operating and maintenance manuals and established
operating rules set forth in the BLT Agreement. Longer peak
period does not only subject the system to being overused, it also
affects the performance of scheduled preventive maintenance on
a daily basis in a certain number of LRVs which may be in
violation of the requirements approved Manuals and Operating
Assumptions.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 3 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
5
In that premise, and assuming that payments for Special Repair
work is over and above the base maintenance fee, is our
understanding correct that the winning proponent should not be
penalized for the breakdown of affected assets/equipment (e.g.
tracks, LRV, etc.) based on the aforementioned principle?
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 4 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
6
"The 'inventory and status assessment' document provided by the
outgoing Contractor can be used as the baseline condition of
system asset for information of the incoming Contractor. The
inventory may be validated by an independent third party auditor
in behalf of the Client." Please confirm that during the validation
of the status of the 'system asset' with an independent third party
auditor, the Contractor will not be penalized for the whole
duration of said validation process.
Please confirm that DOTC will be a signatory to the handover
documents.
Penalties shall be imposed in accordance with Section VII Item 4.
Provided however that the validation should not be more than one
(1) month from the issuance of the NTP.
DOTC shall be a witness to the handover documents.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 5 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
7
Considering the condition of MRT3 assets/equipment as
mentioned by DOTC-MRT3 representatives during a senate
hearing last September 1, 2014 i.e. DOTC requires an X amount
in billions of pesos to improve the condition of MRT3 system to
address the common causes of breakdowns/revenue interruptions
particularly the traction motors, we opine that it is unfair to
impose penalty to the winning proponent since it is already
established that a General Overhaul is required to avert frequent
breakdowns. Will DOTC consider lifting the penalty provisions
for this contract until the required improvements are completed?
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
8
Can DOTC consider reducing the minimum no. of available cars
during the peak period and the penalty conditions imposed for
the Escalators/Elevators due to the current condition of the
system and its assets?
No. The minimum number of required trains at revenue operations
shall be twenty (20) trains and penalty conditions for the
escalators/elevators will be imposed in accordance with Section
VII Item 4 only upon completion of the elevator rehabilitation
project.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 6 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
9
Peak Period: We opine that the figure representing the Penalty
Amount for every 20mins is inconsistent with the figure
representing the Reference Penalty which is based on per car
peak period. Considering the 3 hour peak period shown in the
TOR, we opine that the Penalty Amount should be around P9000
only per car for every 20mins. Is our understanding correct?
Please clarify.
Computed on a “per Peak Hour” basis, the penalty of Php
27,000.00 per car for the first 20min and for every 20 minutes
thereafter not exceeding the Reference Penalty amount of Php
80,000 per car per peak period will be imposed if the number
of cars provided at Insertion/Removal area is less than 60 cars
or 20 trains in accordance with the timetable issued by DOTC-
MRT3. During peak hour operations, penalty of Nine
Thousand Pesos (Php 9,000.00) per car per twenty (20) minutes
will be imposed for every car removed from the revenue line.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 7 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
10
The current conditions of the rails have been observed to be not
in their proper state due to either poor maintenance or the outright
lack of maintenance. There have been accurate information and
data gathered wherein this current state of the rails, aside from
the same not being maybe suitable for the system's continued
operations, is not an appropriate basis to determine a reasonable
the adopted KPI.It is not unreasonable to assume that these KPIs
were calculated against a rail condition that is not in a degraded
state. The current degraded condition of the rails is not new to
anyone as news reports about train interruptions have been traced
to poor rail condition of the MRT3 rails. It was also reported that
this was the reason for the reduction of the speed of the trains to
only 40 kph.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 8 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
11
The signaling system, with the proprietary nature of its software,
hardware, and its other appurtenances, have reportedly been not
sufficiently maintained. In fact, there were reported instances of
some glitches in the system that have been traced to such
improper or insufficient maintenance due to the lack of the
needed spare parts caused by obsolescence. Not upon this
degraded condition of the signaling system, we assume that these
KPIs were calculated. We assume, however, that they were
calculated against a properly maintained and perfectly operating
signaling system, which is not obtaining in the present condition.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 9 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
12
We also discussed in the said Pre-Bid Conference the matter of
one 3-hour Peak Service Period in the morning and another 3-
hour Peak: Service Period in the afternoon as appearing in the
Terms of Reference.However, when we look at the BLT
Agreement of the MRT3 Project, we see a required general
overhauling of the rail vehicles every after s" years of use, which
has as basis of rail vehicle usage of a 2-hour Peak: Service Period
in the morning and another 2-hour Peak Service Period in the
afternoon.By the maintenance records of the said vehicles, the
supposed 8th general overhauling must now be implemented this
year, which we think will not happen.It has to be noted that the
observance of the one 3-hour Peak Service Period in the morning
and another 3-hour Peak Service Period in the afternoon has long
been implemented and that the ideal every 8th year general
overhauling is not any more appropriate in view of the real extent
of the past and current usage of these vehicle. Under this type of
use, the 8th year activity must have to be done much ahead. Thus,
we see here also the degraded state of these vehicles.Here, we
assume again that the KPIs in the Terms of Reference were not
calculated against this degraded state of the vehicles.
The three (3) hour peak period is maintained.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 10 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
13
General Bid Bulletin No. 04-2014, which was posted recently in
the DOTC website, seems to be only a partial reply to some
queries raised in this procurement, and it appears to have been
issued seven days prior to 13 October 2014, the bid date, with a
number still unanswered.Does this mean that, as the BAC shall
issue a reply to the remaining queries, it will necessitate the
movement of the bid date to a later day that will just make the
process comply with Section 22.5.1 of the Revised Implementing
Rules and Regulations of Republic Act No. 9184?
Answers to queries shall be in the General Bid Bulletin to be issued.
14
It was mentioned that in the event that any sub-contractor is
found by the procuring entity to be ineligible, the sub-contracting
of such portion of the goods shall be disallowed. In case when
the bidder only identify the sub-contractor during the contract
implementation as allowed under Section 8.2. , will the procuring
entity allow the bidder to replace the disallowed sub-contractor?
If it is allowed, is there a time frame or limit on the replacement
of the disallowed sub-contractor/
Replacement of the submitted bid shall not be allowed as this will
constitute improvements of the bid proposal.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 11 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
15
It was mentioned that similar contracts shall refer to contract
involving the maintenance of railway tracks, rolling stocks,
railway stations and railway power supply. Please clarify why
signaling, telecommunication, OCS,AFCS, station/depot
equipment and facilities was not specifically included under
similar contracts where in fact maintenance of these items will
be part of the contract.
Also on our understanding, similar contract would mean a
maintenance contract performed on a system which is "generally
similar to MRT3 System" in terms of rolling stock-light rail,
power supply and OCS, track system, stations and signaling
system.
The observation that similar contract means "generally similar to
MRT3 System" in terms of rolling stock-light rail, power supply
and OCS, track system, stations and signaling system is correct.
16
Sub-contracting the project in full/entirety of the scope of works
is not allowed. This clause is quite confusing and should be
revised considering that it was also mentioned that the contractor
shall sub-contract directly to the OEM of elevator, escalator,
signaling and that DOTC MRT3 may allow the contractor to sub-
contract maintenance of rolling stock, civil and tracks, power and
OCS, signaling and communications, station/depot equipment
facilities and AFCS.
Sub-contracting the project in full/entirety of the scope of works is
not allowed. However, subcontracting elevator/escalator and
signaling to Original Equipment Manufacturer is allowed.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 12 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
17
The supplier shall carry sufficient inventories to assure ex-stock
supply of consumable spares for the Goods for the period as
provided in SCC Clause 17.3
Under SCC Clause 17.3 it was indicated that "For Expendable
Supplies, three (3) months after acceptance by the Procuring
Entity of the delivered Goods or after the Goods are consumed
whichever is earlier. Since there may be cases wherein
Expendable Supplies have to be procured abroad, this clause has
to be extended or modified to provide the Supplier/Contractor
ample time to process the procurement and delivery of the
aforesaid supplies.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 13 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
18
As mentioned, the period of correction of defects in the warranty
period is seven calendar days from notice of defects. This period
is too short and has to be modified considering that correction of
defects may require preparation and approval of
procedures/methodologies and acquisition of parts, equipment,
tools, supplies from either local market and abroad.
The correction of defects during the warranty period shall be done
immediately and the penalty provisions shall be imposed for such
failure.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 14 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
19
Indicated as one of the Contractor's Commitments is to "maintain
at least six (6) months supply of fast moving spare parts,
consumables and other related materials and to replenish the
quantity they have received from the outgoing Maintenance
Contractor. Please harmonize this in accordance with our query
under SCC6.2.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 15 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
20
The contractor will be in charge of the maintenance in normal
operating status the existing magnetic type AFC for a period of 1
year. Is this a guaranteed period? Or is there a possibility that
maintenance take over by the AFC Provider will be earlier or
longer than 1year? In such cases what will be conditions on
maintenance contract payment for this particular system?
Once the new AFC provider is in place the corresponding
maintenance cost for AFC will be deducted. The bid proposal shall
indicate the maintenance cost of existing AFCS.
21
Please clarify the meaning of accumulated contract.Does it mean:
• 15 years cumulative contracts (maintenance of a complete
similar railway system) by a single entity within the JV
• Or 15 years cumulative contracts (maintenance of a complete
similar railway system) of the different members within the JV
• Or 15 years cumulative contracts (maintenance of railway sub-
system) of the different members of the JV
An entity in the Joint Venture (JV) must have at least 15 years-
experience per discipline either accumulated or single contract to
qualify in the experience requirement.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 16 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
22
The bidder is also required to submit the Nominated Sub-
Contractor (for all proprietary fields). Since there are already
existing Sub-Contractors for all proprietary fields it would be
better if the Procuring Entity would just provide the list of these
sub-Contractors to the bidders.
The bidder is also required to submit the list of Suppliers for Parts
and Consumables. Since all the parts suppliers are already known
to the Procuring Entity it is better to just provide the list of
suppliers to the bidders. For consumables, it is very premature at
this stage to indicate the list of suppliers for each item as this will
be sourced out later when the contract is awarded.
The procuring entity cannot provided additional information to
bidders to complete the bid proposal.
23
It was mentioned that one of the specific objective was to provide
Special Repairs for the Rail Vehicles, permanent ways and other
related systems and sub-systems. It has to be clarified however
whether the cost (labor and materials) of performing all special
repairs will be on the account of the Client.
Special repairs include labor cost and materials.
24
In the footnote, it was mentioned that the parameters may change
upon implementation of the CAPEX Project and corresponding
adjustments are subject to instructions of the Client. Does it mean
that an additional contract will be prepared and signed by the
concerned parties to cover the contract changes and cost?
Yes, if maintenance of CAPEX will be awarded to the winning
maintenance provider beyond the warranty
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 17 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
25
Considering that MRT3 has been in operation for more than 14
years, we believed that the documents listed are already in
existence or in place. In order to be consistent and provide
continuity with what is being currently practiced and used for the
system, it would be better if these existing documents are
provided to the bidder/s for their improvement, updating or
incorporation of necessary changes. This query is also related to
the same additional duly signed technical documents (reference-
page 77) that must be included in the first envelope.
The bidders should submit these plans and manuals as part of their
bid proposal.
26
To properly prepare a bid which would be responsive to the
current situation and condition of the system, the "Inventory and
Status Assessment" (baseline condition of system assets)
mentioned therein should have been included as part or as
attachment to the bid documents.
Maintenance Audit Report of 2010 may be secured from the BAC
Secretariat.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 18 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
27
In consideration of the present condition of the wayside system
(worn-out or deteriorated tracks/rails, outdated signaling system)
where the failures or service interruption usually last for hours,
the winning maintenance contractor would then be heavily
penalized as the number of trains are reduced due to either
stoppage or implementation of provisional service operation. On
our view, to make the maintenance contract viable and attractive
to the bidders, application of penalties on reduction of trains due
to wayside system failures should either be revised or much
better if removed until such time that the condition of the present
wayside system hasbeen fully rectified.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 19 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
28
For signaling components that are only available for procurement
or repair abroad, the 6 weeks duration seems to short and has to
be adjusted to accommodate processing, shipping, repair/test and
other custom requirements.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 20 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
29
Part of maintenance is the replacement of outdated parts (as
necessary) for the MRT3 AFC Equipment. We are aware of the
fact that presently worldwide, much of the railway system have
already migrated to contactless ticketing system, so it would be
very hard on the part maintenance contractor to source out for
replacement components and better be excluded from the
maintenance requirement.
AFC is part of the Maintenance Contract and provisions in the
contract involving AFC shall be reviewed and modified
accordingly upon implementation of the new AFC project of
DOTC.
Once the new AFC provider is in place the corresponding
maintenance cost for AFC will be deducted. The bid proposal shall
indicate the maintenance cost of existing AFCS.
30
It was mentioned that the Contractor shall keep ready a special
stock of spare parts and equipment for special repairs to be
available in commercially and technically reasonable quantities
and types for immediate use to return the line to normal operation
as soon as possible without waiting for procurement and delivery
of parts. This statement implies that the cost of special repairs is
to the account or responsibility of the maintenance contractor. On
our understanding special repairs are necessary repairs on defects
or damages caused by acts, events or failures beyond the control
of the maintenance contractor and therefore should be borne by
the Client. In addition to the above, we need clarification if the
special stock of spare parts and equipment for special repairs has
already been considered and included in the list of "total
mandatory quantity requirements for 3-year contract" (page 225-
262)
Please refer to Special Repair Provision in the Section VII of the
Bidding Documents.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 21 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
31 Please clarify why there are no fast moving parts included in the
list for power supply, tracks and permanent ways, E & M and
Depot equipment.
The fast moving parts for power supply, tracks and permanent
ways, E & M and Depot equipment shall be included in the bid
proposal as necessary. However, absence of said documents shall
not be ground for disqualification.
32 Please clarify why there are no consumables included in the list
for OCS, power supply, AFC, tracks and permanent ways and
depot equipment.
The list of consumables for power supply, tracks and permanent
ways, E & M and Depot equipment shall be included in the bid
proposal as necessary. However, absence of said documents shall
not be ground for disqualification.
33
Please clarify why the maintenance manuals of the following
equipment were not included in the list:
• Bogie repair hoist
• Bogie turntable
• Car hoist and body stands
• Access tower
• Hydraulic press
• Forklift truck
• Pallet truck
•Points grinder
• Corrugation grinder
• Road rail vehicle re-railing
• Compressed air system
• Train washer plant
• Building electrical and mechanical equipment
Maintenance Manual for such equipment should be part of the bid
proposal.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 22 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
34
In relation to the Pre-Bid Conference held last 14 October 2014
for the Project DOTCMRT-3 System Maintenance Service
Provider, we would like to request copy of minutes of said
meeting.
Prospective bidders will be transmitted a copy of the Minutes of
Meeting of the second Pre-Bid Conference held on 14 October
2014 upon written request.
35
Inventory and Status Assessment or System Declaration should
be provided or made available by the DOTC to all the interested
bidders. This document will allow the bidder/s to have a clearer
picture in order for them to prepare a more responsive bid
proposal. The document should contain among others the
following:
• Status or condition of each vehicles/trains (including its major
equipment! components)
• Status or condition of other sub-systems (Tracks and
Permanent Ways, Signaling, Power Supply, OCS, Telecom,
AFC, Building Facilities, E & M equipment, Depot Equipment,
etc.) including the major equipment/components
• Quantity or stock level of remaining spare parts per subsystem
(including pending orders if available)
Maintenance Audit Report of 2010 may be secured from the BAC
Secretariat.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 23 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
36
The description and quantity of spare parts indicated on the lists
was extracted from the original "Maintenance Agreement
between MRTC and Sumitomo for which the listed spare parts is
for a "newly commissioned railway system and may not fit to the
requirements of the "existing used and degraded system".
Considering that the MRT3 has been operation for 14 years, the
quantity of spare parts should be based on the current
consumption rates, current system condition, and the
requirements necessary to restore and maintain the system. In
addition, please clarify why only the quantity of initial spare parts
for LRV Maintenance was labeled "total mandatory quantity
requirements for 3-year contract" while non for the other sub-
system.
Maintenance Specification is not based on the age of the System.
Please refer to Annex A and B page 222-262.
37
The description and quantity of additional machines and
equipment indicated on the lists was extracted from the original
"Maintenance Agreement between MRTC and Sumitomo" which
was then foreseen and procured to address the maintenance
requirement and activities for a "newly commissioned railway
system". In the absence of the requested Inventory and Status
Assessment or System Declaration we have no idea as to whether
these previously procured additional machines and equipment
are still in existence or operational.
Maintenance Specification is not based on the age of the System.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 24 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
38
The description and quantity of special tools, fixtures and jigs
indicated on the lists was extracted from the original
"Maintenance Agreement between MRTC and Sumitomo" which
was then foreseen and procured to address the maintenance
requirement and activities for a newly commissioned railway
system". In the absence of the requested Inventory and Status
Assessment or System Declaration we have no idea as to whether
these previously procured special tools, fixtures and jigs are still
in existence or operational.
Maintenance Audit Report of 2010 may be secured from the BAC
Secretariat.
39
The description and quantity of measuring instrument on the lists
was extracted from the original "Maintenance Agreement
between MRTC and Sumitomo" which was then foreseen and
procured to address the maintenance requirement and activities
for a "newly commissioned railway system". In the absence of
the requested Inventory and Status Assessment or System
Declaration we have no idea as to whether these previously
procured measuring instruments are still in existence or
operational.
Maintenance Specification is nor based on the age of the system.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 25 of 34
40
In consideration of the present degraded MRT3 system
operations due to problems with tracks, rolling stock and
signaling (as a result of either lack of spare parts, obsolescence
or underprovided maintenance), we believed that the application
of KPI and penalties is truly inappropriate and should be deferred
up to the time that the problems with the above-mentioned
systems have been fully rectified.Please note that rectification
completion will depend on a lot of factors such as:
• Availability of spare parts (inclusive of order, lead and delivery
time). This may be difficult or win take time for obsolete parts
• Availability of necessary maintenance equipment or test
equipment
• Installation rectification duration
• Maintenance window (available non-revenue hours to rectify
the wayside system and the rolling stock)
• Testing and commissioning time
Due to the above, we could not therefore estimate how long I will
it take for the rectification works to be completed. What we could
then suggest is for the DOTC to revise the contract provisions in
such a way that the "winning bidder" will be given ample period
or a "relaxed period" to fully identify and assess the conditions
and requirements to rectify or normalize the system and perform
the necessary corrections without the application or provisions
on KPI's and Penalties.
Once the "relaxed period" has been determined and agreed
between DOTC and the winning bidder, the imposition of the
KPI's and Penalties could then be established
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 26 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
41
In view of the current condition and status of the MRT3 rail
system of which the public is not fully aware or exactly aware,
bidders are apprehensive of the expectation of the public with the
assumption of a new maintenance provider. As it is widely
accepted among persons who are knowledgeable of the only
available solutions to this current status and condition, that these
solutions are not that which are achievable overnight, and it will
take a while to have them implemented, the BTC cannot be
assured of the public's acceptance of the fact that this condition
or status cannot be improved overnight.In support to assure a
bidder's confidence that it is protected from this problem, the
issuance of a (a) System Status Declaration - to cover the whole
system, and (b) Subsystems Status Declaration - to cover each
subsystem is requested and this issuance will achieve the
following:a. A baseline upon which the accurate calculation of
the technical and financial proposal of a bidder can be based,b.
the real status of the system and its subsystems can be made
known upon which the assessment by anyone of the performance
of the winning contractor can be calculated.
Maintenance Audit Report of 2010 may be secured from the BAC
Secretariat.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 27 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
42
As it has been deemed that the Terms of Reference of the tender
as having been based on a system that is in proper and good
condition, which condition is not obtaining in the current MRT3
system, the measures and gauges that have been adopted (KPIs)
through which penalties are to be imposed, have been described
as unreasonable.This unreasonableness had made the tender not
attractive to bidders.This being such, the revision of the
conditions and grounds for the imposition of the penalties, and
the same to be observed only upon the completion of the
rehabilitation of works that have been put on stream to improve
the degraded rail system, must have to be pursued.The graduated
re-imposition of the grounds and conditions for the imposition of
the penalties is fair and reasonable to both the procuring entity
and the maintenance provider. An example would be: once the
signaling system shall have been rehabilitated/upgraded, the
penalties imposable by reason of lack or improper maintenance
of the signaling system or any part thereof must already be
observed, this will not relieve the maintenance provider from
undertaking the required maintenance works.
KPIs and the Maintenance Specifications are not usually based on
age and status of system but is premised on the desired level of
service.
Page 138 of the Bidding Documents, shall now read as follows:
“Reduction, removal or sidetracking of trains (Degraded Service)
due to failure of system/s other than the Rolling Stock. This shall
include all systems, subsystems and components of the Traction
Power Supply, OCS, Tracks (excluding the tracks involve for
replacement as rehabilitation project), Signaling (except for MAN
900 defects) and Permanent Ways
The winning Maintenance Provider should maintain sixty nine (69)
cars only since four (4) LRVs are unserviceable.
Upon rehabilitation of these four (4) LRVs the Maintenance
Provider shall maintain all seventy three (73) LRVs.”
Page 137 of the Bidding Documents:
“60 cars / LRVs or 20 trains per Peak Hour.”
The third column for the Annexes in Pages 225 to 234 shall read as
follows:
“TOTAL MANDATORY QUANTITY REQUIREMENTS FOR
SPARE PARTS FOR 3-YEAR CONTRACT SHOULD ONLY
COMMENCE THREE (3) MONTHS AFTER THE ISSUANCE
OF NOTICE TO PROCEED”
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 28 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
43
One of the ways that will assist a bidder to confidently calculate
its technical and financial proposal is to allow them to have full
access to all records and documents of performance of previous
and current maintenance works done on the whole system.
Such access must be available not only during contract
implementation, but more importantly, way ahead before bid
submission.
Maintenance Audit Report of 2010 may be secured from the BAC
Secretariat.
44
In GBB No. 07-2014, Annex A item 4, we requested for the
average hourly ridership data during weekdays at peak periods
during the past 12 months. The answer we got is that the Head of
Primary BAC Secretariat shall provide Bidders access to
ridership data.
Can DOTC please simply provide the data to all bidders? If it is
too voluminous, can we just get the average hourly ridership data
for June 2013, December 2013 and January 2014. If this request
cannot be granted, can you please provide name and contact
number of the Head of the Primary BAC Secretariat? May we
please invoke that the information requested be provided within
the period stated in ITB clause 10.2.
Bidders may request for access to ridership data from the Head of
the Primary BAC Secretariat:
ATTY. ZENAIDA B. BITENG
Head of the Primary BAC Secretariat
Unit 22, 2nd Floor, The Columbia Tower, Ortigas Avenue, Brgy.
Wack-Wack 1555 Mandaluyong City, Philippines
Tel. Nos.: (+632) 727-7960 local 229
Email Address: [email protected]
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 29 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
45
In GBB No. 07-2014, Annex A item 19 to 24 queries got a similar
response as follows "Please refer to Item 11I(55)(c) of the
Technical Specifications." The reference item reads "Failure of
Client, or any of its respective affiliates, subcontractors or
representatives to make the System or any portion thereof,
available to Provider for scheduled maintenance in accordance
with the requirements of approved Manuals and the Operating
Assumptions (refer to Annex C);" The quoted reference item III
(55) (c) of the Technical Specifications does not answer queries
19 to 24. Can we please have a simple "Yes" or "No" answer.
Item III (55)(c) states that: “Special Repairs” means any repair of
the System required as a result of any damage thereto caused by
any of the following:
(a) Failure of Client or any of their respective affiliates, contractors,
subcontractors or representatives, to operate the System in
accordance with the operating and maintenance manuals and
established operating rules;
(b) Acts of passengers or trespassers other than the Client’s or
Maintenance Provider Personnel resulting in failure or interruption
of service;
(c) Failure of Client, or any of its respective affiliates, contractors,
subcontractors or representatives to make the System or any portion
thereof, available to Provider for scheduled maintenance in
accordance with the requirements of the approved Manuals and the
Operating Assumptions (refer to Annex C);
(d) Actions of unauthorized or unqualified persons unless the same
are caused by the negligence of the Contractor;
(e) Animals, birds or foreign objects unless the same is the
consequence of the negligence of the Provider;
(f) An event of force majeure;
(g) Vandalism or other criminal activity;
(j) Flooding, unless the same is the result of the negligence of the
Contractor, such as improper provision of maintenance of drainage;
(h) System improvements initiated by MRT-3.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 30 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
46
In GBB No. 07-2014, Annex A item 35, we quote the last
paragraph of DOTC's response "Warranties extended by the
OEM to the Maintenance Provider for spare parts procured shall
also be assigned to DOTC-MRT3. OEM shall ensure the
availability of spare parts for at least five (5) years after
termination of warranty period".
It is not within the control of the bidder to impose such
requirements from the OEM. We opine that this requirement is
very unreasonable. Can you please reconsider?
The warranties for spare parts procured should be in favor of the
DOTC-MRT3 as end-user/Client. In addition, the maintenance
provider shall ensure that the availability of spare parts for at least
five (5) years after the termination of warranty period is included
in the contract with the OEM.
47
In GBB No. 07-2014, Annex A item 36, yes we agree that the
maintenance contract is independent of the BLT agreement. But
the technical considerations such as design capacity indicated in
the BLT are obviously a main parameter of the maintenance
contract. As stated in the recent Senate Hearings and also on
many news articles, the MRT 3 system is already subject to
overload. If this is true, then the system is being operated under
conditions defined in item III (55) of the Technical
Specifications.Was there any time in the past that the capacity of
23,600 PPHPD at AW3 crush loading as stated in Section VII of
the Technical Specifications (page 86 of 289), been exceeded? If
yes, then please confirm that the system is being operated, in
some instances, above the design capacity?
The system is operated in accordance with the design of eight (8)
passengers per square meter, headways are more than the design of
three (3) minute headway. The MRT3 is actually operating at crush
load but overloading the trains are not possible.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 31 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
48
In GBB No. 07-2014, Annex A item 37.
Can DOTC simply provide the information being requested to all
bidders? Please. Please. If this request cannot be granted, can you
please provide name and contact number of the Head of the
Primary BAC Secretariat? May we please invoke that the
information requested be provided within the period stated in
ITB clause 10.2.
Bidders may request for access to Control Center Daily Report
from the Head of the Primary BAC Secretariat:
ATTY. ZENAIDA B. BITENG
Head of the Primary BAC Secretariat
Unit 22, 2nd Floor, The Columbia Tower, Ortigas Avenue, Brgy.
Wack-Wack 1555 Mandaluyong City, Philippines
Tel. Nos.: (+632) 727-7960 local 229
Email Address: [email protected]
49
In GBB No. 07-2014, Annex A item 44.Please allow us to
reiterate our request for the list of consumables? How can a
prospective bidder estimate the cost of consumables if the list of
consumables will not be provided by DOTC? May we please
invoke that the information requested be provided within the
period stated in ITB clause 10.2.
Please refer to pages 229 to 231 of the Bidding Documents.
50
In GBB No. 07-2014, Annex A item 50.
How many stations is equivalent to 172,000 sq.m? Shouldn't this
fall under "Special Repairs?"
The 172,000 sq.m. covers all painted portions of the thirteen (13)
stations/terminals and the depot.
This is included in the Maintenance Contract.
51
General
Please confirm if the original maintenance contractor's monthly
fee 10 years ago is around 1.4M USD (exclusive of escalation)?
The contract for bidding is with a different Approved Budget for
the Contract (ABC).
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 32 of 34
52
We opine that the original monthly maintenance fee is an
average of the foreseen monthly costs (plus margin) during the
original contract duration of 10 years or 120 months of the
original maintenance contractor. Although the average is 1.4M
USD per month (which is approximately the same monthly ABC
of this contract being bid), the monthly costs actually vary from
month to month throughout the 10 year term. The variation of
actual monthly price which may be represented as "peaks and
valleys" in a time-cost graph, is significant (i.e. monthly standard
deviation is high). During the 10 year original maintenance
contract term, the total annual cost for year 1 would normally
increase the following year and would continuously increase
until it reaches a peak perhaps during the implementation of the
rolling stock overhauls. After which, the total annual cost would
logically drop again. The cycle is repeated. Therefore, even if the
average maintenance price is 1.4M USD per month, logic would
dictate that the monthly ABC of 1.4M USD would be more than
sufficient on some months or insufficient on other months,
depending on schedule and impact of the different maintenance
cycles of the different core systems. The preceding statement,
taken together with the fact that the system is already old and
most of its equipment may have reached its design life, then the
monthly average maintenance price of 1.4M USD per month may
be insufficient.Can DOTC re-validate the ABC? Instead of using
past experience or this 1.4M USD average, we believe the
maintenance price should be estimated considering actual needs
and recent price estimates.
The present ABC is computed based on the new maintenance
specifications.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 33 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
53
May we suggest that DOTC clearly differentiate the following
activities in relation to the Terms of Reference (TOR) or
Technical Specifications of this 3-year contract (a) Regular
Preventive Maintenance based on O&M Manuals (b) Upgrading,
rehabilitation, restoration activities - or interventions required to
extend the design life of assets (c) Design life cycle
replacementsIs item (b) and (c) not part of the base maintenance
fee? Since item (a) is clearly the scope of this bid, then any KPI
impact of non-implementation of (b) and (c) should not be the
responsibility of the maintenance contractor. Will this be the
principle applied in this contract?
The new maintenance specifications covers regular maintenance,
preventive maintenance and system replacement excluding eight
year major overhauling and other rehabilitation projects of DOTC-
MRT3.
54
We would like to propose and request your good office for the
relaxation of Key Performance Indicator (KPI) in the imposition
of penalty and propose a gradual mandatory KPI in the transition
period due to the status, condition and reliability of LRVs in this
manner:
Period Key Performance
Indicators (KPI)
First Month to Third Month 0 (No KPI)
Fourth Month to Sixth Month 15 LRVs
Sixth Month to Ninth Month 18 LRVs
Ninth Month Onwards 20 LRVs
Computed on a “per Peak Hour” basis, the penalty of Php 27,000.00
per car for the first 20min and for every 20 minutes thereafter not
exceeding the Reference Penalty amount of Php 80,000 per car per
peak period will be imposed if the number of cars provided at
Insertion/Removal area is less than 60 cars or 20 trains in
accordance with the timetable issued by DOTC-MRT3. During
peak hour operations, penalty of Nine Thousand Pesos
(Php9,000.00) per car per twenty (20) minutes will be imposed for
every car removed from the revenue line.
In the event of an upgrade in operation such as operating a four (4)-
car train and/or reduction of headway to two and a half minutes, an
additional payment of Nineteen Thousand Six Hundred Thirty Four
and 7/100 United States Dollars (19,634.7 USD) per car shall be
payable to the maintenance contractor subject to availability of
funds and amendment of the maintenance contract.
ANNEX A
DOTC MRT-3 SYSTEM MAINTENANCE SERVICE PROVIDER
General Bid Bulletin No. 09-2014
Page 34 of 34
Item
No.
Query
(lifted from the written queries submitted by prospective
bidders; names of bidders have been omitted)
Response
55 We would like to propose and request your good office for an
extension of 30 days for the final submission of bidding
documents.
Due to the urgency of the project the submission and opening of
bids is scheduled on 28 October 2014 at 2:00 p.m. (Please refer to
GBB No. 06-2014).