analisa harga sat

70
Page 1 of 70 document.xls/summit contract-rev The Summit Kelapa gading - Jakarta Contract UNIT PRICE BREAKDOWN NO. DESCRIPTION UNIT QTY rate RATE 1 Bar reinforcement BJTD-40; 10mm dia. kg 1.00 - Bar D. 10mm (incl.waste 3%) kg 1.03 4,400 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310 Total 2 Bar reinforcement BJTD-40; 13mm dia. kg 1.00 - Bar D. 13mm (incl.waste 3%) kg 1.03 4,375 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310 Total 3 Bar reinforcement BJTD-40; 16mm-25mm dia. kg 1.00 - Bar D. 16-25mm (incl.waste 3%) kg 1.03 4,350 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310 Total 4 Bar reinforcement BJTD-40; 29mm dia. kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,375 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310 Total 5 Bar reinforcement BJTD-40; 32mm dia. kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310 Total 6 Wiremesh M6 one layer m2 1.00 - BRC mesh M6 (incl.waste 13.5%) m2 1.14 18,100 18,100 - Spacer nr 2.27 330 290 - Labour m2 1.00 5,000 10,498 Total 7 Trimming and enlarge excavation m3 1.00 - Subcon't m3 1.00 7,740 8,500 Total 8 Excavation for basement not exceeding 1.50m deep m3 1.00 - Subcon't m3 1.00 14,700 16,200 Total 9 Disposal of excavated material off site m3 1.00 - Subcon't m3 1.00 18,650 24,000 Total 10 Backfilling m3 1.00 - Labour m3 1.00 15,000 19,300 - Equipment m3 1.00 2,180 2,800

Upload: hendrikzainudin

Post on 19-Nov-2014

125 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Analisa Harga Sat

Page 1 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

1 Bar reinforcement BJTD-40; 10mm dia. kg 1.00 - Bar D. 10mm (incl.waste 3%) kg 1.03 4,400 - - Tying wire kg 0.015 4,350 3,850 58 - Spacer nr 0.112 330 290 32 - Subcon't fabrication & installation kg 1.00 350 310 310

Total 400

2 Bar reinforcement BJTD-40; 13mm dia. kg 1.00 - Bar D. 13mm (incl.waste 3%) kg 1.03 4,375 - - Tying wire kg 0.015 4,350 3,850 58 - Spacer nr 0.112 330 290 32 - Subcon't fabrication & installation kg 1.00 350 310 310

Total 400

3 Bar reinforcement BJTD-40; 16mm-25mm dia. kg 1.00 - Bar D. 16-25mm (incl.waste 3%) kg 1.03 4,350 - - Tying wire kg 0.015 4,350 3,850 58 - Spacer nr 0.112 330 290 32 - Subcon't fabrication & installation kg 1.00 350 310 310

Total 400

4 Bar reinforcement BJTD-40; 29mm dia. kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,375 - - Tying wire kg 0.015 4,350 3,850 58 - Spacer nr 0.112 330 290 32 - Subcon't fabrication & installation kg 1.00 350 310 310

Total 400

5 Bar reinforcement BJTD-40; 32mm dia. kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 - - Tying wire kg 0.015 4,350 3,850 58 - Spacer nr 0.112 330 290 32 - Subcon't fabrication & installation kg 1.00 350 310 310

Total 400

6 Wiremesh M6 one layer m2 1.00 - BRC mesh M6 (incl.waste 13.5%) m2 1.14 18,100 18,100 20,544 - Spacer nr 2.27 330 290 658 - Labour m2 1.00 5,000 10,498 10,498

Total 31,700

7 Trimming and enlarge excavation m3 1.00 - Subcon't m3 1.00 7,740 8,500 8,500

Total 8,500

8 Excavation for basement not exceeding 1.50m deep m3 1.00 - Subcon't m3 1.00 14,700 16,200 16,200

Total 16,200

9 Disposal of excavated material off site m3 1.00 - Subcon't m3 1.00 18,650 24,000 24,000

Total 24,000

10 Backfilling m3 1.00 - Labour m3 1.00 15,000 19,300 19,300 - Equipment m3 1.00 2,180 2,800 2,800

Page 2: Analisa Harga Sat

Page 2 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Total 22,100

11 Cutt off bored piles 1000mm dia. no 1.00 - Subcon't cutting off pile no 1.00 100,000 129,360 129,360 - Subcon't disposal, cleaning,etc no 1.00 17,500 22,640 22,640

Total 152,000

12 Sand blinding,100mm thk for basement m2 1.00 - Sand bed (incl.waste 7.5%) m3 0.108 76,000 72,200 7,762 - Labour m3 0.10 5,000 6,130 613 - Equipment ls 1.00 2,180 4,926 4,926

Total 13,300

13 Sand blinding,100mm thk; horizontal m2 1.00 - Sand bed (incl.waste 7.5%) m3 0.108 76,000 72,200 7,762 - Labour m3 0.10 5,000 5,300 530 - Equipment ls 1.00 2,180 3,209 3,209

Total 11,500

14 Blinding concrete (1:3:5), 50mm thk m2 1.00 - Ready mix Bo (incl.waste 7.5%) m3 0.0538 257,000 244,150 13,123 - Labour m2 1.00 6,500 7,571 7,571 - Equipment ls 1.00 ga ada 806 806

Total 21,500

15 Concrete grade f'c 250 kg/cm2 m3 1.00 - Ready mix f'c 250 (incl.waste 5%) m3 1.05 319,000 303,050 318,203 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 376,000

16 Concrete grade f'c 300 kg/cm2 m3 1.00 - Ready mix f'c 300 (incl.waste 5%) m3 1.05 332,000 316,288 332,103 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 389,900

17 Concrete grade f'c 350 kg/cm2 m3 1.00 - Ready mix f'c 350 (incl.waste 5%) m3 1.05 354,000 338,764 355,703 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 413,500

18 Concrete grade f'c 400 kg/cm2 m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 437,000

19 Concrete grade f'c 400 kg/cm2 for basement slab, 450mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 14,900 14,900 - Equipment ls 1.00 16,825 37,200 37,200

Total 451,900

Page 3: Analisa Harga Sat

Page 3 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

20 Concrete grade f'c 400 kg/cm2 for basement slab, 400mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 17,500 17,500 - Equipment ls 1.00 16,825 37,200 37,200

Total 454,500

21 Concrete grade f'c 400 kg/cm2 for basement slab, 350mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 19,200 19,200 - Equipment ls 1.00 16,825 37,200 37,200

Total 456,200

22 Concrete grade f'c 400 kg/cm2 for suspended slab, 300mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 22,700 22,700 - Equipment ls 1.00 16,825 37,200 37,200

Total 459,700

23 Concrete grade f'c 400 kg/cm2 for basement slab, 250mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 27,100 27,100 - Equipment ls 1.00 16,825 37,200 37,200

Total 464,100

24 Concrete grade f'c 400 kg/cm2 for basement slab, 150mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 379,203 - Labour m3 1.00 16,000 20,598 20,598 - Mesh separator ls 1.00 15,000 44,500 44,500 - Equipment ls 1.00 16,825 37,200 37,200

Total 481,500

25 Concrete grade f'c 500 kg/cm2 m3 1.00 - Ready mix f'c 500 (incl.waste 5%) m3 1.05 418,000 402,669 422,803 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 480,600

26 Concrete grade f'c 550 kg/cm2 m3 1.00 - Ready mix f'c 550 (incl.waste 5%) m3 1.05 446,000 430,955 452,503 - Labour m3 1.00 16,000 20,598 20,598 - Equipment ls 1.00 16,825 37,200 37,200

Total 510,300

27 Loss formwork for pile cap m2 1.00 - Concrete blockwall (incl.waste 5%) nr 12.50 1,300 1,300 16,250 - Mortar 1:5 m3 0.020 300,620 330,680 6,614 - Labour m2 1.00 10,000 19,636 19,636

Total 42,500

28 Loss formwork for matt foundation m2 1.00 - Concrete blockwall (incl.waste 5%) nr 34.65 1,300 1,300 45,045 - Mortar 1:5 m3 0.105 300,620 330,680 34,721 - Labour m2 1.00 10,000 24,761 24,761 - Concrete lintel m 0.40 49,390 79,932 31,973

Page 4: Analisa Harga Sat

Page 4 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Total 136,500

29 Formwork slab on grade m2 1.00 - Plywood 12mm thk (incl.waste 5%) sht 0.084 105,000 99,750 8,379 - Timber (incl.waste 5%) m3 0.016 1,200,000 1,140,000 18,240 - Nail (incl.waste 5%) kg 0.200 7,000 6,650 1,330 - Form oil (incl.waste 5%) ltr 0.053 6,000 5,700 299 - Fabrication & installation m2 1.00 27,500 18,622 18,622 - Equipment ls 1.00 2,240 1,830 1,830

Total 48,700

30 Formwork column, wall m2 1.00 - Fabrication, installation & dismantle (subcont) m2 1.00 58,000 68,590 68,590 - Equipment ls 1.00 5,000 5,910 5,910

Total 74,500

31 m2 1.00 - Waterproofing Formdexplus 1.5kg/m2 m2 1.00 43,000 43,000 43,000 - Install m2 1.00 3,000 16,000 16,000

Total 59,000

32 Waterstop m' 1.00 - Waterstop Volclay RX 101 m' 1.00 52,000 52,000 52,000 - Install m' 1.00 5,000 21,100 21,100

Total 73,100

33

m' 1.00 - Waterstop Volclay RX 101 (incl.install) m' 1.00 57,000 73,100 73,100 - Hilti chemical anchors; HIT HY 150 nr 3.00 61,200 78,540 235,620 - Chipping and cleaning m' 1.00 7,500 9,680 9,680

Total 318,400

34 Ficher chemical anchor vynilester hybrid nr 1.00 - Subcon't nr 1.00 61,200 78,600 78,600

Total 78,600

35 Dowel, 22mm diameter x 1570mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg - - Cut, bend & fix kg 4.68 300 350 1,638 - Equipment ls 1.00 162 162

Total 1,800

36 Dowel, 25mm diameter x 1780mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg - - Cut, bend & fix kg 6.853 300 350 2,399 - Equipment ls 1.00 201 201

Total 2,600

37 Dowel, 13mm diameter x 780mm long nr 1.00 - Bar D. 13mm (incl.waste 3%) kg- Cut, bend & fix kg 0.811 300 350 284

Waterproofing additive to surface of basement slabs, two coat application, Formdex

Casting new slab on grade up to diaphragm wall to make clean and water tight joint including chipping groove, Volclay RX-101 water stop and Hilti chemical anchors

Page 5: Analisa Harga Sat

Page 5 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Equipment ls 1.00 16 16 Total 300

38 Dowel, 16mm diameter x 960mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg- Cut, bend & fix kg 1.516 300 350 531 - Equipment ls 1.00 161 161

Total 692

39 WF steel, size 400mm x 200mm x 8mm x 13mm (R1) (66 kg/m) kg 1.00 - Subcon't steel structure kg 1.00 10,180 13,100 13,100

Total 13,100

40m2 1.00

- Mortar 1:3 m3 0.05 400,580 440,640 22,032 - Wire mesh M6 m2 1.00 23,430 31,700 31,700 - Expansion joint; as specified m2 1.00 15,468 15,468 15,468

Total 69,200

41m2 1.00

- Mortar 1:3 m3 0.05 400,580 440,640 22,032 - Chicken wire (incl.waste 5%) m2 1.05 2,000 1,900 1,995 - Bonding agent Sikabond (incl.waste 5%) ltr 0.105 12,000 11,400 1,197 - Portland cement @50 kg (incl.waste 5%) bag 0.105 28,000 26,600 2,793 - Labour m2 1.00 5,000 18,583 18,583

Total 46,600

42 Waterproofing membrane laid on concrete roof slab m2 1.00 - Supply & install waterproofing membrane Fosroc Torcel 3P m2 1.00 45,000 57,800 57,800

Total 57,800

43

m2 1.00 - Rockwool insulation 60kg/m3 density (subcon't) m2 1.00 63,900 82,060 82,060 - Aluminium foil single layer + galv.roof mesh 100x100mm (subcon't) m2 1.00 10,000 12,840 12,840

Total 94,900

44 Metal roof sheeting m2 1.00 - Supply & install zincalume corrugated sheet 0.40mm thk m2 1.00 74,500 95,600 95,600

Total 95,600

45 Brickwork (1:3) 100mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 95 230 230 21,850 - Mortar 1:3 m3 0.02 400,580 440,640 9,253 - Install brickwall m2 1.00 10,000 12,635 12,635 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 75,700

46 Brickwork (1:3) 200mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 43,470 - Mortar 1:3 m3 0.047 400,580 440,640 20,710 - Install brickwall m2 1.00 10,000 19,259 19,259 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 115,400

Reinforced roof screed bed laid to falls and crossfalls, min 50mm thick

Bed 50mm thick, as protective screed (1:3) laid on waterpoofing membrane, at water tank area

Rockwool insulation 50mm thick, 60kg/m3 density, incl.aluminium foil single layer and galvanize roof mesh 100x100mm

Page 6: Analisa Harga Sat

Page 6 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

47 Brickwork (1:3) 225mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 43,470 - Mortar 1:3 m3 0.067 400,580 440,640 29,523 - Install brickwall m2 1.00 10,000 21,546 21,546 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 126,500

48 Brickwork (1:5) 100mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 95 230 230 21,850 - Mortar 1:5 m3 0.02 300,620 330,680 6,944 - Install brickwall m2 1.00 10,000 12,244 12,244 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 73,000

49 Brickwork (1:5) 150mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 147 230 230 33,810 - Mortar 1:5 m3 0.034 300,620 330,680 11,243 - Install brickwall m2 1.00 10,000 15,885 15,885 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 92,900

50 Brickwork (1:5) 200mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 43,470 - Mortar 1:5 m3 0.047 300,620 330,680 15,542 - Install brickwall m2 1.00 10,000 18,727 18,727 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 109,700

51 Brickwork (1:5) 300mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 242 230 230 55,660 - Mortar 1:5 m3 0.101 300,620 330,680 33,399 - Install brickwall m2 1.00 10,000 24,280 24,280 - Concrete lintel m' 0.40 49,390 79,932 31,961

Total 145,300

52 Plaster (1:3) + skimcoat to wall m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.025 400,580 440,640 11,016 - Labour plaster m2 1.00 8,000 11,780 11,780 - Portland cement @50 kg (incl.waste 5%) bag 0.025 28,000 28,000 706 - Labour skimcoat m2 1.00 4,000 5,698 5,698

Total 29,200

53 Plaster (1:5) + skimcoat to wall m2 1.00 - Mortar 1:5 (incl.waste 5%) m3 0.025 300,620 330,680 8,267 - Labour plaster m2 1.00 8,000 11,329 11,329 - Portland cement @50 kg (incl.waste 5%) bag 0.025 28,000 28,000 706 - Labour skimcoat m2 1.00 4,000 5,698 5,698

Total 26,000

54 Aerated concrete block wall (1:5) 100mm thick + lintel m2 1.00 - Aerated concrete block 590x190x100mm thk (incl.waste 5%) m3 0.093 360,000 342,000 31,806 - Drymix mortar MU 380 (incl.waste 5%) bag 0.100 48,000 48,000 4,800 - Install celcon wall m2 1.00 10,000 17,821 17,821 - Concrete lintel m 0.40 49,390 79,932 31,973

Total 86,400

55 Aerated concrete block wall (1:5) 150mm thick + lintel m2 1.00 - Aerated concrete block 590x190x150mm thk (incl.waste 5%) m3 0.140 370,000 351,500 49,034

Page 7: Analisa Harga Sat

Page 7 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Drymix mortar MU 380 (incl.waste 5%) bag 0.150 48,000 48,000 7,200 - Install celcon wall m2 1.00 10,000 21,793 21,793 - Concrete lintel m 0.40 49,390 79,932 31,973

Total 110,000

56 Aerated concrete block wall (1:5) 175mm thick + lintel m2 1.00 - Aerated concrete block 590x190x175mm thk (incl.waste 5%) m3 0.163 370,000 351,500 57,207 - Drymix mortar MU 380 (incl.waste 5%) bag 0.175 48,000 48,000 8,400 - Install celcon wall m2 1.00 10,000 24,421 24,421 - Concrete lintel m 0.40 49,390 79,932 31,973

Total 122,000

57 Aerated concrete block wall (1:5) 200mm thick + lintel m2 1.00 - Aerated concrete block 590x190x200mm thk (incl.waste 5%) m3 0.186 370,000 351,500 65,379 - Drymix mortar MU 380 (incl.waste 5%) bag 0.200 48,000 48,000 9,600 - Install celcon wall m2 1.00 10,000 25,048 25,048 - Concrete lintel m 0.40 49,390 79,932 31,973

Total 132,000

58 Aerated concrete block wall (1:5) 250mm thick + lintel m2 1.00 - Aerated concrete block 590x190x250mm thk (incl.waste 5%) m3 0.232 370,000 351,500 81,724 - Drymix mortar MU 380 (incl.waste 5%) bag 0.250 48,000 48,000 12,000 - Install celcon wall m2 1.00 10,000 29,604 29,604 - Concrete lintel m 0.40 49,390 79,932 31,973

Total 155,300

59 Screed (1:5) trowelled smooth; bed, 50mm thick to landing m2 1.00 - Mortar 1:5 (incl.waste 5%) m3 0.053 300,620 330,680 17,361 - Labour & trowel m2 1.00 6,500 10,239 10,239

Total 27,600

60 Plaster with smooth finish drymix to aerated concrete block wall m2 1.00 - Drymix mortar MU 301 (incl.waste 5%) bag 0.450 14,000 14,000 6,300 - Drymix mortar MU 200 (incl.waste 5%) bag 0.053 48,000 48,000 2,520 - Labour plaster m2 1.00 8,000 12,082 12,082 - Labour skimcoat m2 1.00 4,000 5,698 5,698

Total 26,600

61 Precast concrete panel wall 100mm thick m2 1.00 - Precast concrete wall 100mm thk ex.PATON m2 1.00 100,000 100,000 100,000 - Install precast concrete wall m2 1.00 55,000 55,000 55,000 - Seal & grout m2 1.00 50,000 50,160 50,160 - Handling, anchor & bracket m2 1.00 45,000 45,640 45,640

Total 250,800

62 Prepare and apply acrylic emulsion paint at stair m2 1.00 - Subcon't; acrylic emulsion paint at stair m2 1.00 14,000 18,000 18,000

Total 18,000

63 Prepare and apply weathershield paint m2 1.00 - Subcon't; weathershield paint at wall m2 1.00 14,500 18,600 18,600

Total 18,600

64 Ceramic wall tile 200 x 200mm ROMAN m2 1.00 - Ceramic wall tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 30,450 28,928 30,374 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 12,915 - Grout AM 50 (incl.waste 5%) kg 0.63 6,500 6,500 4,095 - Install ceramic wall m2 1.00 15,000 31,016 31,016

Page 8: Analisa Harga Sat

Page 8 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Total 78,400

65 Ceramic skirting, 100mmH (non slip) m' 1.00 - Ceramic nosing tile 200x100mm ROMAN (incl.waste 5%) m' 1.05 4,550 4,323 4,539 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 1,953 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 683 - Install ceramic skirting tile m' 1.00 8,000 12,026 12,026

Total 19,200

66 Homogenous wall tile 600 x 600mm m2 1.00 - Homogenous wall tile 600x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 135,860 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 12,915 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 2,048 - Install homogenous wall m2 1.00 17,500 23,178 23,178

Total 174,000

67 Homogenous wall tile 300 x 600mm m2 1.00 - Homogenous wall tile 300x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 135,860 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 12,915 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 2,048 - Install homogenous wall m2 1.00 17,500 23,178 23,178

Total 174,000

68 Ceramic floor tile 200 x 200mm ROMAN m2 1.00 - Ceramic floor tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 27,300 25,935 27,232 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.63 6,500 6,500 4,095 - Install ceramic floor m2 1.00 12,500 26,808 26,808

Total 67,900

69 Ceramic floor tile 300 x 300mm ROMAN m2 1.00 - Ceramic floor tile 300x300mm ROMAN (incl.waste 5%) m2 1.05 28,500 27,075 28,429 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.53 6,500 6,500 3,413 - Install ceramic floor m2 1.00 12,500 26,994 26,994

Total 68,600

70 Ceramic floor tile 333 x 333mm ROMAN m2 1.00 - Ceramic floor tile 333x333mm ROMAN (incl.waste 5%) m2 1.05 38,500 36,575 38,404 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.53 6,500 6,500 3,413 - Install ceramic floor m2 1.00 12,500 30,519 30,519

Total 82,100

71 Ceramic floor tile 400 x 400mm ROMAN m2 1.00 - Ceramic floor tile 400x400mm ROMAN (incl.waste 5%) m2 1.05 29,050 27,598 28,977 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.42 6,500 6,500 2,730 - Install ceramic floor m2 1.00 12,500 27,028 27,028

Total 68,500

72 Ceramic nosing tile 100 x 100mm;stair ROMAN m' 1.00 - Ceramic nosing tile 200x100mm ROMAN (incl.waste 5%) m' 1.05 3,500 3,325 3,491 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 1,953

Page 9: Analisa Harga Sat

Page 9 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 683 - Install ceramic nosing tile m' 1.00 8,000 11,773 11,773

Total 17,900

73 Homogenous floor tile 300 x 300mm m2 1.00 - Homogenous floor tile 300x300mm-PC rates (incl.waste 5%) m2 1.05 103,700 98,515 103,441 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.525 6,500 6,500 3,413 - Install homogeneous floor m2 1.00 15,000 19,082 19,082

Total 135,700

74 Homogenous floor tile 600 x 600mm m2 1.00 - Homogenous floor tile 600x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 135,860 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 9,765 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 2,048 - Install homogeneous floor m2 1.00 15,000 21,128 21,128

Total 168,800

75 Skirting 100mm high, tile size 100 x 600 x 8mm thick m' 1.00 - Homogenous tile 100x600mm-PC rates (incl.waste 5%) m' 1.05 23,154 21,996 23,096 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 1,953 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 683 - Install homogeneous skirting m' 1.00 2,550 11,568 11,568

Total 37,300

76 Skirting 100mm high, tile size 100 x 300 x 8mm thick m' 1.00 - Homogenous tile 100x300mm-PC rates (incl.waste 5%) m' 1.05 31,110 29,555 31,032 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 1,953 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 683 - Install homogeneous skirting m' 1.00 4,500 16,832 16,832

Total 50,500

77 Screed (1:3); bed, 30mm thick with trowel smooth finish m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.0315 400,580 440,640 13,880 - Labour & trowel m2 1.00 6,500 9,820 9,820

Total 23,700

78 Screed (1:3); bed, 20mm thick to receive ceramic floor tiles m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.0210 400,580 440,640 9,253 - Labour m2 1.00 1,047 1,047

Total 10,300

79 Steel grille at ramp; gratting plat 40x10mm, steel frame 50x50x5m m' 1.00 - Subcon't; steel plate 40x10mm kg 11.00 10,080 12,930 142,230 - Subcon't; steel frame 50x50x5mm kg 9.07 10,080 12,940 117,370

Total 259,600

80 Floor hardener m2 1.00 - Subcon't; floor hardener 5kg/m2 ex.SIKA m2 1.00 9,000 11,500 11,500

Total 11,500

81 Waterproofing coating; floor in toilet& r. wudhu m2 1.00 - Supply & install waterproofing coating SIKATOP 107 m2 1.00 24,000 30,800 30,800

Page 10: Analisa Harga Sat

Page 10 of 55 document.xls/summit contract-rev

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Total 30,800

82 Paving stone, 80mm thick m2 1.00 - Paving stone, 80mm thick ex.CISANGKAN (incl.waste 5%) m2 1.05 52,500 49,875 52,369 - Install m2 1.00 12,500 34,431 34,431

Total 86,800

83

nr 1.00 - Subcon't; supply single door nr 1.000 1,871,770 2,345,370 2,345,370 - Subcon't; install single door nr 1.000 125,000 156,630 156,630

Total 2,502,000

84

nr 1.00 - Subcon't; supply & install double steel door nr 1.000 4,879,000 6,262,910 6,262,910 - Subcon't; supply & install hardware nr 1.000 2,080,000 2,669,990 2,669,990

Total 8,932,900

85 Concrete platform for bathtub nr 1.00 - Brickwork 1:3; 100mm thk (incl.install) m2 0.97 60,011 75,700 73,429 - Sirtu m3 0.372 78,580 62,255 23,159 - Plaster 1:3 m2 0.97 18,010 22,796 22,112

Total 118,700

86 Concrete platform for squating closet nr 1.00 - Brickwork 1:3; 100mm thk (incl.install) m2 0.508 60,011 75,700 38,447 - Sirtu m3 0.104 78,580 62,255 6,475 - Plaster 1:3 m2 0.508 18,010 22,796 11,578

Total 56,500

Single timber door (Electronic control room door type PB01), double melaminto leave size 1040 x 2360mm high, cream color duco paint, aluminium frame door 40 x 60mm, with louvre size 800 x 640mm high

Double steel door (Pump room door type PB07), overall size 1800 x 2400mm high, louvre size 2 x 600 x 2050mm high; including hardware

Page 11: Analisa Harga Sat

Page 11 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

1 Bar reinforcement BJTD-40; 10mm dia. kg 1.00 - Bar D. 10mm (incl.waste 3%) kg 1.03 4,400 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310

Total

2 Bar reinforcement BJTD-40; 13mm dia. kg 1.00 - Bar D. 13mm (incl.waste 3%) kg 1.03 4,375 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310

Total

3 Bar reinforcement BJTD-40; 16mm-25mm dia. kg 1.00 - Bar D. 16-25mm (incl.waste 3%) kg 1.03 4,350 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310

Total

4 Bar reinforcement BJTD-40; 16mm-25mm dia. (to matt found.) kg 1.00 - Bar D. 16-25mm (incl.waste 3%) kg 1.03 4,350 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Support; rebar, steel pipes, angle, etc ls 1.00 1,250 960 - Subcon't fabrication & installation kg 1.00 800 620

Total

5 Bar reinforcement BJTD-40; 29mm dia. kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,375 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310

Total

6 Bar reinforcement BJTD-40; 29mm dia. (to matt found.) kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,350 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Support; rebar, steel pipes, angle, etc ls 1.00 1,250 960 - Subcon't fabrication & installation kg 1.00 350 620

Total

7 Bar reinforcement BJTD-40; 32mm dia. kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Subcon't fabrication & installation kg 1.00 350 310

Total

Page 12: Analisa Harga Sat

Page 12 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

8 Bar reinforcement BJTD-40; 32mm dia. (to matt found.) kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 - Tying wire kg 0.015 4,350 3,850 - Spacer nr 0.112 330 290 - Support; rebar, steel pipes, angle, etc ls 1.00 1,250 960 - Subcon't fabrication & installation kg 1.00 350 620

Total

9 Wiremesh M6 one layer m2 1.00 - BRC mesh M6 (incl.waste 13.5%) m2 1.14 18,100 18,100 - Spacer nr 2.27 330 290 - Labour m2 1.00 5,000 10,498

Total

10 Trimming and enlarge excavation m3 1.00 - Subcon't m3 1.00 7,740 8,500

Total

11 Excavation for basement not exceeding 1.50m deep m3 1.00 - Subcon't m3 1.00 14,700 16,200

Total

12 Disposal of excavated material off site m3 1.00 - Subcon't m3 1.00 18,650 24,000

Total

13 Backfilling m3 1.00 - Labour m3 1.00 15,000 19,300 - Equipment m3 1.00 2,180 2,800

Total

14 Cutt off bored piles 1000mm dia. no 1.00 - Subcon't cutting off pile no 1.00 100,000 129,360 - Subcon't disposal, cleaning,etc no 1.00 17,500 22,640

Total

15 Sand blinding,100mm thk for basement m2 1.00 - Sand bed (incl.waste 7.5%) m3 0.108 76,000 72,200 - Labour m3 0.10 5,000 6,130 - Equipment ls 1.00 2,180 4,926

Total

16 Sand blinding,100mm thk; horizontal m2 1.00 - Sand bed (incl.waste 7.5%) m3 0.108 76,000 72,200 - Labour m3 0.10 5,000 5,300 - Equipment ls 1.00 2,180 3,209

Total

17 Blinding concrete (1:3:5), 50mm thk m2 1.00 - Ready mix Bo (incl.waste 7.5%) m3 0.0538 257,000 244,150 - Labour m2 1.00 6,500 7,571

Page 13: Analisa Harga Sat

Page 13 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Equipment ls 1.00 ga ada 806 Total

18 Concrete grade f'c 250 kg/cm2 m3 1.00 - Ready mix f'c 250 (incl.waste 5%) m3 1.05 319,000 303,050 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

19 Concrete grade f'c 300 kg/cm2 m3 1.00 - Ready mix f'c 300 (incl.waste 5%) m3 1.05 332,000 316,288 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

20 Concrete grade f'c 350 kg/cm2 m3 1.00 - Ready mix f'c 350 (incl.waste 5%) m3 1.05 354,000 338,764 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

21 Concrete grade f'c 400 kg/cm2 m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

22 Concrete grade f'c 400 kg/cm2 for matt foundation m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 360,000 342,000 - Labour m3 1.00 16,000 20,598 - Thermocoppel & chilled water ls 1.00 20,500 23,980 - Mesh separator ls 1.00 3,342 4,023 - Equipment ls 1.00 16,825 37,200

Total

23 Concrete grade f'c 400 kg/cm2 for basement slab, 450mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 14,900 - Equipment ls 1.00 16,825 37,200

Total

24 Concrete grade f'c 400 kg/cm2 for basement slab, 400mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 17,500 - Equipment ls 1.00 16,825 37,200

Total

25 Concrete grade f'c 400 kg/cm2 for basement slab, 350mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 19,200

Page 14: Analisa Harga Sat

Page 14 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Equipment ls 1.00 16,825 37,200 Total

26 Concrete grade f'c 400 kg/cm2 for suspended slab, 300mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 22,700 - Equipment ls 1.00 16,825 37,200

Total

27 Concrete grade f'c 400 kg/cm2 for basement slab, 250mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 27,100 - Equipment ls 1.00 16,825 37,200

Total

28 Concrete grade f'c 400 kg/cm2 for basement slab, 150mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 361,145 - Labour m3 1.00 16,000 20,598 - Mesh separator ls 1.00 15,000 44,500 - Equipment ls 1.00 16,825 37,200

Total

29 Concrete grade f'c 500 kg/cm2 m3 1.00 - Ready mix f'c 500 (incl.waste 5%) m3 1.05 418,000 402,669 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

30 Concrete grade f'c 550 kg/cm2 m3 1.00 - Ready mix f'c 550 (incl.waste 5%) m3 1.05 446,000 430,955 - Labour m3 1.00 16,000 20,598 - Equipment ls 1.00 16,825 37,200

Total

31 Loss formwork for pile cap m2 1.00 - Concrete blockwall (incl.waste 5%) nr 12.50 1,300 1,300 - Mortar 1:5 m3 0.020 300,620 330,680 - Labour m2 1.00 10,000 19,636

Total

32 Loss formwork for matt foundation, 200mm thick m2 1.00 - Concrete blockwall (incl.waste 5%) nr 34.65 1,300 1,300 - Mortar 1:5 m3 0.105 300,620 330,680 - Labour m2 1.00 10,000 24,761 - Concrete lintel m 0.40 49,390 79,932

Total

33 Formwork slab on grade m2 1.00 - Plywood 12mm thk (incl.waste 5%) sht 0.084 105,000 99,750 - Timber (incl.waste 5%) m3 0.016 1,200,000 1,140,000

Page 15: Analisa Harga Sat

Page 15 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Nail (incl.waste 5%) kg 0.200 7,000 6,650 - Form oil (incl.waste 5%) ltr 0.053 6,000 5,700 - Fabrication & installation m2 1.00 27,500 18,622 - Equipment ls 1.00 2,240 1,830

Total

34 Formwork column, wall m2 1.00 - Fabrication, installation & dismantle m2 1.00 58,000 68,590 - Equipment ls 1.00 5,000 5,910

Total

35 m2 1.00 - Waterproofing Formdexplus 1.5kg/m2 m2 1.00 43,000 43,000 - Install m2 1.00 3,000 16,000

Total

36 Waterstop m' 1.00 - Waterstop Volclay RX 101 m' 1.00 52,000 52,000 - Install m' 1.00 5,000 21,100

Total

37 m' 1.00 - Waterstop Volclay RX 101 (incl.install) m' 1.00 57,000 73,100 - Hilti chemical anchors; HIT HY 150 nr 3.00 61,200 78,540 - Chipping and cleaning m' 1.00 7,500 9,680

Total

38 Ficher chemical anchor vynilester hybrid nr 1.00 - Subcon't nr 1.00 61,200 78,600

Total

39 Dowel, 22mm diameter x 1570mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg- Cut, bend & fix kg 4.68 300 350 - Equipment ls 1.00 162

Total

40 Dowel, 25mm diameter x 1780mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg- Cut, bend & fix kg 6.853 300 350 - Equipment ls 1.00 201

Total

41 Dowel, 13mm diameter x 780mm long nr 1.00 - Bar D. 13mm (incl.waste 3%) kg- Cut, bend & fix kg 0.811 300 350 - Equipment ls 1.00 16

Total

Waterproofing additive to surface of basement slabs, two coat application, Formdex

Casting new slab on grade up to diaphragm wall to make clean and water tight joint including chipping groove, Volclay RX-101 water stop and Hilti chemical anchors

Page 16: Analisa Harga Sat

Page 16 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

42 Dowel, 16mm diameter x 960mm long nr 1.00 - Bar D. 16-25mm (incl.waste 3%) kg- Cut, bend & fix kg 1.516 300 350 - Equipment ls 1.00 161

Total

43 WF steel, size 400mm x 200mm x 8mm x 13mm (R1) (66 kg/m) kg 1.00 - Subcon't steel structure kg 1.00 10,180 13,100

Total

44 m2 1.00 - Mortar 1:3 m3 0.05 400,580 440,640 - Wire mesh M6 m2 1.00 23,430 31,700 - Expansion joint; as specified m2 1.00 15,468 15,468

Total

45 m2 1.00 - Mortar 1:3 m3 0.05 400,580 440,640 - Chicken wire (incl.waste 5%) m2 1.05 2,000 1,900 - Bonding agent Sikabond (incl.waste 5%) ltr 0.105 12,000 11,400 - Portland cement @50 kg (incl.waste 5%) bag 0.105 28,000 26,600 - Labour m2 1.00 5,000 18,583

Total

46 Waterproofing membrane laid on concrete roof slab m2 1.00 - Supply & install waterproofing membrane Fosroc Torcel 3P m2 1.00 45,000 57,800

Total

47

m2 1.00 - Rockwool insulation 60kg/m3 density (subcon't) m2 1.00 63,900 82,060 - Aluminium foil single layer + galv.roof mesh 100x100mm (subcon't) m2 1.00 10,000 12,840

Total

48 Metal roof sheeting m2 1.00 - Supply & install zincalume corrugated sheet 0.40mm thk m2 1.00 74,500 95,600

Total

49 Brickwork (1:3) 100mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 95 230 230 - Mortar 1:3 m3 0.02 400,580 440,640 - Install brickwall m2 1.00 10,000 12,635 - Concrete lintel m' 0.40 49,390 79,932

Total

50 Brickwork (1:3) 200mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 - Mortar 1:3 m3 0.047 400,580 440,640 - Install brickwall m2 1.00 10,000 19,259 - Concrete lintel m' 0.40 49,390 79,932

Reinforced roof screed bed laid to falls and crossfalls, min 50mm thick

Bed 50mm thick, as protective screed (1:3) laid on waterpoofing membrane, at water tank area

Rockwool insulation 50mm thick, 60kg/m3 density, incl.aluminium foil single layer and galvanize roof mesh 100x100mm

Page 17: Analisa Harga Sat

Page 17 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Total

51 Brickwork (1:3) 225mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 - Mortar 1:3 m3 0.067 400,580 440,640 - Install brickwall m2 1.00 10,000 21,546 - Concrete lintel m' 0.40 49,390 79,932

Total

52 Brickwork (1:5) 100mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 95 230 230 - Mortar 1:5 m3 0.02 300,620 330,680 - Install brickwall m2 1.00 10,000 12,244 - Concrete lintel m' 0.40 49,390 79,932

Total

53 Brickwork (1:5) 150mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 147 230 230 - Mortar 1:5 m3 0.034 300,620 330,680 - Install brickwall m2 1.00 10,000 15,885 - Concrete lintel m' 0.40 49,390 79,932

Total

54 Brickwork (1:5) 200mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 189 230 230 - Mortar 1:5 m3 0.047 300,620 330,680 - Install brickwall m2 1.00 10,000 18,727 - Concrete lintel m' 0.40 49,390 79,932

Total

55 Brickwork (1:5) 300mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 242 230 230 - Mortar 1:5 m3 0.101 300,620 330,680 - Install brickwall m2 1.00 10,000 24,280 - Concrete lintel m' 0.40 49,390 79,932

Total

56 Plaster (1:3) + skimcoat to wall m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.025 400,580 440,640 - Labour plaster m2 1.00 8,000 11,780 - Portland cement @50 kg (incl.waste 5%) bag 0.025 28,000 28,000 - Labour skimcoat m2 1.00 4,000 5,698

Total

57 Plaster (1:5) + skimcoat to wall m2 1.00 - Mortar 1:5 (incl.waste 5%) m3 0.025 300,620 330,680 - Labour plaster m2 1.00 8,000 11,329 - Portland cement @50 kg (incl.waste 5%) bag 0.025 28,000 28,000

Page 18: Analisa Harga Sat

Page 18 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Labour skimcoat m2 1.00 4,000 5,698 Total

58 Aerated concrete block wall (1:5) 100mm thick + lintel m2 1.00 - Aerated concrete block 590x190x100mm thk (incl.waste 5%) m3 0.093 360,000 342,000 - Drymix mortar MU 380 (incl.waste 5%) bag 0.100 48,000 48,000 - Install celcon wall m2 1.00 10,000 17,821 - Concrete lintel m 0.40 49,390 79,932

Total

59 Aerated concrete block wall (1:5) 150mm thick + lintel m2 1.00 - Aerated concrete block 590x190x150mm thk (incl.waste 5%) m3 0.140 370,000 351,500 - Drymix mortar MU 380 (incl.waste 5%) bag 0.150 48,000 48,000 - Install celcon wall m2 1.00 10,000 21,793 - Concrete lintel m 0.40 49,390 79,932

Total

60 Aerated concrete block wall (1:5) 175mm thick + lintel m2 1.00 - Aerated concrete block 590x190x175mm thk (incl.waste 5%) m3 0.163 370,000 351,500 - Drymix mortar MU 380 (incl.waste 5%) bag 0.175 48,000 48,000 - Install celcon wall m2 1.00 10,000 24,421 - Concrete lintel m 0.40 49,390 79,932

Total

61 Aerated concrete block wall (1:5) 200mm thick + lintel m2 1.00 - Aerated concrete block 590x190x200mm thk (incl.waste 5%) m3 0.186 370,000 351,500 - Drymix mortar MU 380 (incl.waste 5%) bag 0.200 48,000 48,000 - Install celcon wall m2 1.00 10,000 25,048 - Concrete lintel m 0.40 49,390 79,932

Total

62 Aerated concrete block wall (1:5) 250mm thick + lintel m2 1.00 - Aerated concrete block 590x190x250mm thk (incl.waste 5%) m3 0.232 370,000 351,500 - Drymix mortar MU 380 (incl.waste 5%) bag 0.250 48,000 48,000 - Install celcon wall m2 1.00 10,000 29,604 - Concrete lintel m 0.40 49,390 79,932

Total

63 Screed (1:5) trowelled smooth; bed, 50mm thick to landing m2 1.00 - Mortar 1:5 (incl.waste 5%) m3 0.053 300,620 330,680 - Labour & trowel m2 1.00 6,500 10,239

Total

64 Plaster with smooth finish drymix to aerated concrete block wall m2 1.00 - Drymix mortar MU 301 (incl.waste 5%) bag 0.450 14,000 14,000 - Drymix mortar MU 200 (incl.waste 5%) bag 0.053 48,000 48,000 - Labour plaster m2 1.00 8,000 12,082 - Labour skimcoat m2 1.00 4,000 5,698

Page 19: Analisa Harga Sat

Page 19 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Total

65 Precast concrete panel wall 100mm thick m2 1.00 - Precast concrete wall 100mm thk ex.PATON m2 1.00 100,000 100,000 - Install precast concrete wall m2 1.00 55,000 55,000 - Seal & grout m2 1.00 50,000 50,160 - Handling, anchor & bracket m2 1.00 45,000 45,640

Total

66 Prepare and apply acrylic emulsion paint at stair m2 1.00 - Subcon't; acrylic emulsion paint at stair m2 1.00 14,000 18,000

Total

67 Prepare and apply weathershield paint m2 1.00 - Subcon't; weathershield paint at wall m2 1.00 14,500 18,600

Total

68 Ceramic wall tile 200 x 200mm ROMAN m2 1.00 - Ceramic wall tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 30,450 28,928 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 - Grout AM 50 (incl.waste 5%) kg 0.63 6,500 6,500 - Install ceramic wall m2 1.00 15,000 31,016

Total

69 Ceramic skirting, 100mmH (non slip) m' 1.00 - Ceramic nosing tile 200x100mm ROMAN (incl.waste 5%) m' 1.05 4,550 4,323 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 - Install ceramic skirting tile m' 1.00 8,000 12,026

Total

70 Homogenous wall tile 600 x 600mm m2 1.00 - Homogenous wall tile 600x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 - Install homogenous wall m2 1.00 17,500 23,178

Total

71 Homogenous wall tile 300 x 600mm m2 1.00 - Homogenous wall tile 300x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 - Adhesive MU 400 (incl.waste 5%) kg 5.25 1,920 2,460 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 - Install homogenous wall m2 1.00 17,500 23,178

Total

72 Ceramic floor tile 200 x 200mm ROMAN m2 1.00 - Ceramic floor tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 27,300 25,935 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.63 6,500 6,500 - Install ceramic floor m2 1.00 12,500 26,808

Total

73 Ceramic floor tile 300 x 300mm ROMAN m2 1.00

Page 20: Analisa Harga Sat

Page 20 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Ceramic floor tile 300x300mm ROMAN (incl.waste 5%) m2 1.05 28,500 27,075 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.53 6,500 6,500 - Install ceramic floor m2 1.00 12,500 26,994

Total

74 Ceramic floor tile 333 x 333mm ROMAN m2 1.00 - Ceramic floor tile 333x333mm ROMAN (incl.waste 5%) m2 1.05 38,500 36,575 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.53 6,500 6,500 - Install ceramic floor m2 1.00 12,500 30,519

Total

75 Ceramic floor tile 400 x 400mm ROMAN m2 1.00 - Ceramic floor tile 400x400mm ROMAN (incl.waste 5%) m2 1.05 29,050 27,598 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.42 6,500 6,500 - Install ceramic floor m2 1.00 12,500 27,028

Total

76 Ceramic nosing tile 100 x 100mm;stair ROMAN m' 1.00 - Ceramic nosing tile 200x100mm ROMAN (incl.waste 5%) m' 1.05 3,500 3,325 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 - Install ceramic nosing tile m' 1.00 8,000 11,773

Total

77 Homogenous floor tile 300 x 300mm m2 1.00 - Homogenous floor tile 300x300mm-PC rates (incl.waste 5%) m2 1.05 103,700 98,515 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.525 6,500 6,500 - Install homogeneous floor m2 1.00 15,000 19,082

Total

78 Homogenous floor tile 600 x 600mm m2 1.00 - Homogenous floor tile 600x600mm-PC rates (incl.waste 5%) m2 1.05 136,200 129,390 - Adhesive MU 450 (incl.waste 5%) kg 5.25 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.315 6,500 6,500 - Install homogeneous floor m2 1.00 15,000 21,128

Total

79 Skirting 100mm high, tile size 100 x 600 x 8mm thick m' 1.00 - Homogenous tile 100x600mm-PC rates (incl.waste 5%) m' 1.05 23,154 21,996 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 - Install homogeneous skirting m' 1.00 2,550 11,568

Total

80 Skirting 100mm high, tile size 100 x 300 x 8mm thick m' 1.00

Page 21: Analisa Harga Sat

Page 21 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Homogenous tile 100x300mm-PC rates (incl.waste 5%) m' 1.05 31,110 29,555 - Adhesive MU 450 (incl.waste 5%) kg 1.05 1,450 1,860 - Grout AM 50 (incl.waste 5%) kg 0.11 6,500 6,500 - Install homogeneous skirting m' 1.00 4,500 16,832

Total

81 Screed (1:3); bed, 30mm thick with trowel smooth finish m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.0315 400,580 440,640 - Labour & trowel m2 1.00 6,500 9,820

Total

82 Screed (1:3); bed, 20mm thick to receive ceramic floor tiles m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.0210 400,580 440,640 - Labour m2 1.00 1,047

Total

83 Steel grille at drainage size 20x30x260mm m' 1.00 - Subcon't; steel grille 20x30x260mm @30mm kg 16.11 11,200 14,350 - Subcon't; steel frame 30x30x3mm kg 2.72 10,080 12,912

Total

84 Steel grille at ramp; gratting plat 40x10mm, steel frame 50x50x5m m' 1.00 - Subcon't; steel plate 40x10mm kg 11.00 10,080 12,930 - Subcon't; steel frame 50x50x5mm kg 9.07 10,080 12,940

Total

85 Floor hardener m2 1.00 - Subcon't; floor hardener 5kg/m2 ex.SIKA m2 1.00 9,000 11,500

Total

86 Waterproofing coating; floor in toilet& r. wudhu m2 1.00 - Supply & install waterproofing coating SIKATOP 107 m2 1.00 24,000 30,800

Total

87 Paving stone, 80mm thick m2 1.00 - Paving stone, 80mm thick ex.CISANGKAN (incl.waste 5%) m2 1.05 52,500 52,500 - Install m2 1.00 12,500 31,675

Total

88

nr 1.00 - Subcon't; supply single door nr 1.000 1,871,770 2,345,370 - Subcon't; install single door nr 1.000 125,000 156,630

Total

89

nr 1.00 - Subcon't; supply & install double steel door nr 1.000 4,879,000 6,262,910 - Subcon't; supply & install hardware nr 1.000 2,080,000 2,669,990

Total

Single timber door (Electronic control room door type PB01), double melaminto leave size 1040 x 2360mm high, cream color duco paint, aluminium frame door 40 x 60mm, with louvre size 800 x 640mm high

Double steel door (Pump room door type PB07), overall size 1800 x 2400mm high, louvre size 2 x 600 x 2050mm high; including hardware

Page 22: Analisa Harga Sat

Page 22 of 55 document.xls/summit contract

The SummitKelapa gading - Jakarta

Contract

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

90 Concrete platform for bathtub nr 1.00 - Brickwork 1:3; 100mm thk m2 0.97 60,011 75,700 - Sirtu m3 0.372 78,580 62,255 - Plaster 1:3 m2 0.97 18,010 22,796

Total

91 Concrete platform for squating closet nr 1.00 - Brickwork 1:3; 100mm thk m2 0.508 60,011 75,700 - Sirtu m3 0.104 78,580 62,255 - Plaster 1:3 m2 0.508 18,010 22,796

Total

Page 23: Analisa Harga Sat

Page 23 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

- 58 32 310 400

- 58 32 310 400

- 58 32 310 400

- 58 32 960 620 1,670

- 58 32 310 400

- 58 32 960 620 1,670

- 58 32 310 400

Page 24: Analisa Harga Sat

Page 24 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

- 58 32 960 620 1,670

20,544 658 10,498 31,700

8,500 8,500

16,200 16,200

24,000 24,000

19,300 2,800 22,100

129,360 22,640 152,000

7,762 613 4,926 13,300

7,762 530 3,209 11,500

13,123 7,571

Page 25: Analisa Harga Sat

Page 25 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

806 21,500

318,203 20,598 37,200 376,000

332,103 20,598 37,200 389,900

355,703 20,598 37,200 413,500

379,203 20,598 37,200 437,000

359,100 20,598 23,980 4,023 37,200 444,900

379,203 20,598 14,900 37,200 451,900

379,203 20,598 17,500 37,200 454,500

379,203 20,598 19,200

Page 26: Analisa Harga Sat

Page 26 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

37,200 456,200

379,203 20,598 22,700 37,200 459,700

379,203 20,598 27,100 37,200 464,100

379,203 20,598 44,500 37,200 481,500

422,803 20,598 37,200 480,600

452,503 20,598 37,200 510,300

16,250 6,614 19,636 42,500

45,045 34,721 24,761 31,973 136,500

8,379 18,240

Page 27: Analisa Harga Sat

Page 27 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

1,330 299 18,622 1,830 48,700

68,590 5,910 74,500

43,000 16,000 59,000

52,000 21,100 73,100

73,100 235,620 9,680 318,400

78,600 78,600

- 1,638 162 1,800

- 2,399 201 2,600

284 16 300

Page 28: Analisa Harga Sat

Page 28 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

531 161 692

13,100 13,100

22,032 31,700 15,468 69,200

22,032 1,995 1,197 2,793 18,583 46,600

57,800 57,800

82,060 12,840 94,900

95,600 95,600

21,850 9,253 12,635 31,961 75,700

43,470 20,710 19,259 31,961

Page 29: Analisa Harga Sat

Page 29 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

115,400

43,470 29,523 21,546 31,961 126,500

21,850 6,944 12,244 31,961 73,000

33,810 11,243 15,885 31,961 92,900

43,470 15,542 18,727 31,961 109,700

55,660 33,399 24,280 31,961 145,300

11,016 11,780 706 5,698 29,200

8,267 11,329 706

Page 30: Analisa Harga Sat

Page 30 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

5,698 26,000

31,806 4,800 17,821 31,973 86,400

49,034 7,200 21,793 31,973 110,000

57,207 8,400 24,421 31,973 122,000

65,379 9,600 25,048 31,973 132,000

81,724 12,000 29,604 31,973 155,300

17,361 10,239 27,600

6,300 2,520 12,082 5,698

Page 31: Analisa Harga Sat

Page 31 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

26,600

100,000 55,000 50,160 45,640 250,800

18,000 18,000

18,600 18,600

30,374 12,915 4,095 31,016 78,400

4,539 1,953 683 12,026 19,200

135,860 12,915 2,048 23,178 174,000

135,860 12,915 2,048 23,178 174,000

27,232 9,765 4,095 26,808 67,900

Page 32: Analisa Harga Sat

Page 32 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

28,429 9,765 3,413 26,994 68,600

38,404 9,765 3,413 30,519 82,100

28,977 9,765 2,730 27,028 68,500

3,491 1,953 683 11,773 17,900

103,441 9,765 3,413 19,082 135,700

135,860 9,765 2,048 21,128 168,800

23,096 1,953 683 11,568 37,300

Page 33: Analisa Harga Sat

Page 33 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

31,032 1,953 683 16,832 50,500

13,880 9,820 23,700

9,253 1,047 10,300

231,179 35,122 266,300

142,230 117,370 259,600

11,500 11,500

30,800 30,800

55,125 31,675 86,800

2,345,370 156,630 2,502,000

6,262,910 2,669,990 8,932,900

Page 34: Analisa Harga Sat

Page 34 of 55 document.xls/summit contract

UNIT PRICE BREAKDOWN

AMOUNT

73,429 23,159 22,112 118,700

38,447 6,475 11,578 56,500

Page 35: Analisa Harga Sat

Page 35 of 55 document.xls/summit rev02

The SummitKelapa gading - Jakarta

Submission : 19-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Bar reinforcement BJTD-40; 10mm dia. kg 1.00 - Bar D. 10mm (incl.waste 3%) kg 1.03 4,400 4,400 4,532 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Equipment ls 1.00 42 41 41 - Fabrication & installation kg 1.00 300 300 300

Total 4,930

Bar reinforcement BJTD-40; 13mm dia. kg 1.00 - Bar D. 13mm (incl.waste 3%) kg 1.03 4,375 4,375 4,506 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Equipment ls 1.00 42 47 47 - Fabrication & installation kg 1.00 300 300 300

Total 4,910

Bar reinforcement BJTD-40; 16mm-25mm dia. kg 1.00 - Bar D. 16mm-25mm (incl.waste 3%) kg 1.03 4,350 4,350 4,481 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Equipment ls 1.00 42 42 42 - Fabrication & installation kg 1.00 300 300 300

Total 4,880

Bar reinforcement BJTD-40; 16mm-25mm dia. (to matt found.) kg 1.00 - Bar D. 16mm-25mm (incl.waste 3%) kg 1.03 4,350 4,350 4,481 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Support; D22mm @1m ls 1.00 1,250 1,250 1,250 - Equipment ls 1.00 42 42 42 - Fabrication & installation kg 1.00 300 300 300

Total 6,130

Bar reinforcement BJTD-40; 29mm dia. kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,375 4,375 4,506 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Equipment ls 1.00 42 47 47 - Fabrication & installation kg 1.00 300 300 300

Total 4,910

Bar reinforcement BJTD-40; 29mm dia. (to matt found.) kg 1.00 - Bar D. 29mm (incl.waste 3%) kg 1.03 4,375 4,375 4,506 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Support; D22mm @1m ls 1.00 1,250 1,250 1,250 - Equipment ls 1.00 42 47 47 - Fabrication & installation kg 1.00 300 300 300

Total 6,160

Bar reinforcement BJTD-40; 32mm dia. kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 4,400 4,532

Page 36: Analisa Harga Sat

Page 36 of 55 document.xls/summit rev02

The SummitKelapa gading - Jakarta

Submission : 19-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Equipment ls 1.00 42 41 41 - Fabrication & installation kg 1.00 300 300 300

Total 4,930

Bar reinforcement BJTD-40; 32mm dia. (to matt found.) kg 1.00 - Bar D. 32mm (incl.waste 3%) kg 1.03 4,400 4,400 4,532 - Tying wire kg 0.015 1,800 1,800 27 - Spacer nr 0.112 268 270 30 - Support; D22mm @1m ls 1.00 1,250 1,250 1,250 - Equipment ls 1.00 42 41 41 - Fabrication & installation kg 1.00 300 300 300

Total 6,180

Concrete grade f'c 250 kg/cm2 m3 1.00 - Ready mix f'c 250 (incl.waste 5%) m3 1.05 319,000 319,000 334,950 - Labour m3 1.00 16,000 16,180 16,180 - Equipment ls 1.00 16,825 20,670 20,670

Total 371,800

Concrete grade f'c 300 kg/cm2 m3 1.00 - Ready mix f'c 300 (incl.waste 5%) m3 1.05 332,000 332,000 348,600 - Labour m3 1.00 16,000 16,170 16,170 - Equipment ls 1.00 16,825 20,730 20,730

Total 385,500

Concrete grade f'c 350 kg/cm2 m3 1.00 - Ready mix f'c 350 (incl.waste 5%) m3 1.05 354,000 354,000 371,700 - Labour m3 1.00 16,000 16,160 16,160 - Equipment ls 1.00 16,825 20,640 20,640

Total 408,500

Concrete grade f'c 400 kg/cm2 m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 377,000 395,850 - Labour m3 1.00 16,000 16,140 16,140 - Equipment ls 1.00 16,825 20,510 20,510

Total 432,500

Concrete grade f'c 400 kg/cm2 for matt foundation m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 360,000 360,000 378,000 - Labour m3 1.00 16,000 21,020 21,020 - Thermocoppel & chilled water ls 1.00 20,500 20,760 20,760 - Mesh separator ls 1.00 3,342 3,380 3,380 - Equipment ls 1.00 16,825 17,040 17,040

Total 440,200

Concrete grade f'c 400 kg/cm2 for basement slab, 400mm thick m3 1.00 - Ready mix f'c 400 (incl.waste 5%) m3 1.05 377,000 377,000 395,850 - Labour m3 1.00 16,000 16,140 16,140 - Mesh separator ls 1.00 15,000 15,170 15,170 - Equipment ls 1.00 16,825 21,540 21,540

Page 37: Analisa Harga Sat

Page 37 of 55 document.xls/summit rev02

The SummitKelapa gading - Jakarta

Submission : 19-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

Total 448,700

Concrete grade f'c 500 kg/cm2 m3 1.00 - Ready mix f'c 500 (incl.waste 5%) m3 1.05 418,000 418,000 438,900 - Labour m3 1.00 16,000 16,120 16,120 - Equipment ls 1.00 16,825 20,180 20,180

Total 475,200

Concrete grade f'c 550 kg/cm2 m3 1.00 - Ready mix f'c 550 (incl.waste 5%) m3 1.05 446,000 446,000 468,300 - Labour m3 1.00 16,000 16,130 16,130 - Equipment ls 1.00 16,825 20,670 20,670

Total 505,100

Loss formwork for matt foundation, 200mm thick m2 1.00 - Concrete blockwall nr 33.00 1,300 1,800 59,400 - Mortar 1:5 m3 0.105 300,592 416,610 43,744 - Install blockwall m2 1.00 10,000 13,920 13,920 - Concrete lintel m 0.40 51,837 71,840 28,736

Total 145,800

Brickwork (1:3) 100mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 90.00 230 310 27,900 - Mortar 1:3 m3 0.02 400,576 542,230 11,387 - Install brickwall m2 1.00 10,000 13,655 13,655 - Concrete lintel m' 0.40 51,837 70,170 28,058

Total 81,000

Brickwork (1:3) 200mm thick + lintel m2 1.00 - Local red brick (incl.waste 5%) nos 180.00 230 310 55,800 - Mortar 1:3 m3 0.05 400,576 542,230 25,485 - Install brickwall m2 1.00 10,000 13,993 13,993 - Concrete lintel m' 0.40 51,837 70,330 28,122

Total 123,400

Plaster (1:3) + skimcoat to wall m2 1.00 - Mortar 1:3 (incl.waste 5%) m3 0.025 400,576 542,230 13,556 - Labour plaster m2 1.00 8,000 11,297 11,297 - Portland cement @50 kg (incl.waste 5%) bag 0.02 28,000 38,630 927 - Labour skimcoat m2 1.00 4,000 5,520 5,520

Total 31,300

Celcon (1:5) 100mm thick + lintel m2 1.00 - Celcon block 590x190x100mm thk m3 0.086 378,000 551,650 47,442 - Drymix mortar MU 380 (incl.waste 5%) bag 0.10 1,400 2,040 204 - Install celcon wall m2 1.00 10,000 14,594 14,594 - Concrete lintel m 0.40 51,837 75,650 30,260

Total 92,500

Celcon (1:5) 150mm thick + lintel m2 1.00 - Celcon block 590x190x150mm thk m3 0.086 388,500 710,700 61,120 - Drymix mortar MU 380 (incl.waste 5%) bag 0.10 1,400 2,040 204 - Install celcon wall m2 1.00 10,000 18,344 18,344 - Concrete lintel m 0.40 51,837 94,830 37,932

Total 117,600

Celcon (1:5) 175mm thick + lintel m2 1.00

Page 38: Analisa Harga Sat

Page 38 of 55 document.xls/summit rev02

The SummitKelapa gading - Jakarta

Submission : 19-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Celcon block 590x190x175mm thk m3 0.086 388,500 710,700 61,120 - Drymix mortar MU 380 (incl.waste 5%) bag 0.10 1,400 2,040 204 - Install celcon wall m2 1.00 10,000 27,896 27,896 - Concrete lintel m 0.40 51,837 106,200 42,480

Total 131,700

Celcon (1:5) 200mm thick + lintel m2 1.00 - Celcon block 590x190x200mm thk m3 0.086 388,500 710,700 61,120 - Drymix mortar MU 380 (incl.waste 5%) bag 0.10 1,400 2,040 204 - Install celcon wall m2 1.00 10,000 34,264 34,264 - Concrete lintel m 0.40 51,837 113,780 45,512

Total 141,100

Celcon (1:5) 250mm thick + lintel m2 1.00 - Celcon block 590x190x250mm thk m3 0.086 388,500 710,700 61,120 - Drymix mortar MU 380 (incl.waste 5%) bag 0.10 1,400 2,040 204 - Install celcon wall m2 1.00 10,000 51,744 51,744 - Concrete lintel m 0.40 51,837 134,580 53,832

Total 166,900

Plaster + skimcoat drymix to celcon wall m2 1.00 - Drymix mortar MU 301 (incl.waste 5%) bag 0.450 14,700 19,890 8,951 - Drymix mortar MU 200 (incl.waste 5%) bag 0.05 50,400 68,200 3,410 - Labour plaster m2 1.00 8,000 10,830 10,830 - Labour skimcoat m2 1.00 4,000 5,410 5,410

Total 28,600

Ceramic wall tile 200 x 200mm ROMAN m2 1.00 - Ceramic wall tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 31,970 42,960 45,108 - Adhesivet MU 400 (incl.waste 5%) kg 5.00 2,020 2,710 13,555 - Grout AM 50 (incl.waste 5%) kg 0.60 6,500 8,740 5,254 - Install ceramic wall m2 1.00 15,000 20,182 20,182

Total 84,100

Homogenous wall tile 600 x 600mm GRANITO m2 1.00 - Homogenous wall tile 600x600mm GRANITO (incl.waste 5%) m2 1.05 143,330 189,910 199,406 - Adhesivet MU 400 (incl.waste 5%) kg 5.00 2,360 2,710 13,555 - Grout AM 50 (incl.waste 5%) kg 0.30 6,500 8,740 2,622 - Install homogenous wall m2 1.00 15,000 21,917 21,917

Total 237,500

Ceramic floor tile 200 x 200mm ROMAN m2 1.00 - Ceramic floor tile 200x200mm ROMAN (incl.waste 5%) m2 1.05 28,670 38,520 40,446 - Adhesivet MU 450 (incl.waste 5%) kg 5.00 1,520 2,040 10,200 - Grout AM 50 (incl.waste 5%) kg 0.60 6,500 8,740 5,244 - Install ceramic floor m2 1.00 12,500 16,810 16,810

Total 72,700

Ceramic floor tile 400 x 400mm ROMAN m2 1.00 - Ceramic floor tile 400x400mm ROMAN (incl.waste 5%) m2 1.05 30,500 39,190 41,150 - Adhesivet MU 450 (incl.waste 5%) kg 5.00 2,000 2,040 10,200 - Grout AM 50 (incl.waste 5%) kg 0.40 6,500 8,740 3,496

Page 39: Analisa Harga Sat

Page 39 of 55 document.xls/summit rev02

The SummitKelapa gading - Jakarta

Submission : 19-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE AMOUNT

- Install ceramic floor m2 1.00 12,500 18,554 18,554 Total 73,400

Homogenous floor tile 300 x 300mm m2 1.00 - Homogenous floor tile 300x300mm GRANITO (incl.waste 5%) m2 1.05 103,700 103,700 108,885 - Adhesivet MU 450 (incl.waste 5%) kg 5.00 2,000 2,040 10,200 - Grout AM 50 (incl.waste 5%) kg 0.50 6,500 8,740 4,370 - Install ceramic floor m2 1.00 12,500 11,545 11,545

Total 135,000

Homogenous floor tile 600 x 600mm m2 1.00 - Homogenous floor tile 600x600mm GRANITO (incl.waste 5%) m2 1.05 136,200 136,200 143,010 - Adhesivet MU 450 (incl.waste 5%) kg 5.00 2,000 2,040 10,200 - Grout AM 50 (incl.waste 5%) kg 0.30 6,500 8,740 2,622 - Install ceramic floor m2 1.00 12,500 11,668 11,668

Total 167,500

Page 40: Analisa Harga Sat

Page 40 of 55

The SummitKelapa gading - Jakarta

READY MIX SUPPLIER

No Material Unit Price (Rp) Remarks

1 Readymix concrete Bo m3 257,000 Trumix; 13 (-1/+2)2 Readymix concrete f'c 250 m3 319,000 Trumix; 13 (-1/+2)3 Readymix concrete f'c 300 m3 332,000 Trumix; 13 (-1/+2)4 Readymix concrete f'c 350 m3 354,000 Trumix; 13 (-1/+2)5 Readymix concrete f'c 400 m3 377,000 Trumix; 13 (-1/+2)6 Readymix concrete f'c 400 (MF) m3 360,000 Trumix; 13 (-1/+2)7 Readymix concrete f'c 500 m3 418,000 Trumix; 13 (-1/+2)8 Readymix concrete f'c 550 m3 446,000 Trumix; 13 (-1/+2)

Page 41: Analisa Harga Sat

Page 41 of 55 document.xls/summit rev01

The SummitKelapa gading - Jakarta

Submission : 08-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Bar reinforcement BJTD-40; 10mm dia. kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,700 4,700 - Tying wire kg 1.50% 1,650 1,650 - Spacer nr 11.20% 268 270 - Equipment ls 100.00% 42 44 - Fabrication & installation kg 100.00% 150 150

Total

Bar reinforcement BJTD-40; 13mm dia. kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,675 4,675 - Tying wire kg 1.50% 1,650 1,650 - Spacer nr 11.20% 268 270 - Equipment ls 100.00% 42 50 - Fabrication & installation kg 100.00% 150 150

Total

Bar reinforcement BJTD-40; 16mm-25mm dia. kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,650 4,650 - Tying wire kg 1.50% 1,800 1,800 - Spacer nr 11.20% 268 270 - Equipment ls 100.00% 42 43 - Fabrication & installation kg 100.00% 150 150

Total

Bar reinforcement BJTD-40; 16mm-25mm dia. (to matt found.) kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,650 4,650 - Tying wire kg 1.50% 1,800 1,800 - Spacer nr 11.20% 268 270 - Support; D22mm @1m ls 100.00% 1,200 1,200 - Equipment ls 100.00% 42 43 - Fabrication & installation kg 100.00% 250 250

Total

Bar reinforcement BJTD-40; 29mm dia. kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,675 4,675 - Tying wire kg 1.50% 1,650 1,650 - Spacer nr 11.20% 268 270 - Equipment ls 100.00% 42 50 - Fabrication & installation kg 100.00% 150 150

Total

Bar reinforcement BJTD-40; 29mm dia. (to matt found.) kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,675 4,675 - Tying wire kg 1.50% 1,800 1,800 - Spacer nr 11.20% 268 270 - Support; D22mm @1m ls 100.00% 1,200 1,194 - Equipment ls 100.00% 42 44 - Fabrication & installation kg 100.00% 250 250

Total

Page 42: Analisa Harga Sat

Page 42 of 55 document.xls/summit rev01

The SummitKelapa gading - Jakarta

Submission : 08-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Bar reinforcement BJTD-40; 32mm dia. kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,700 4,700 - Tying wire kg 1.50% 1,650 1,650 - Spacer nr 11.20% 268 270 - Equipment ls 100.00% 42 44 - Fabrication & installation kg 100.00% 150 150

Total

Bar reinforcement BJTD-40; 32mm dia. (to matt found.) kg 100.00%- Bar D. 10mm (incl.waste 3%) kg 103.00% 4,700 4,700 - Tying wire kg 1.50% 1,800 1,800 - Spacer nr 11.20% 268 270 - Support; D22mm @1m ls 100.00% 1,200 1,198 - Equipment ls 100.00% 42 44 - Fabrication & installation kg 100.00% 250 250

Total

Concrete grade f'c 250 kg/cm2 m3 100.00%- Ready mix f'c 250 (incl.waste 5%) m3 105.00% 311,000 446,800 - Labour m3 100.00% 8,000 11,490 - Equipment ls 100.00% 16,825 24,170

Total

Concrete grade f'c 300 kg/cm2 m3 100.00%- Ready mix f'c 300 (incl.waste 5%) m3 105.00% 324,000 463,950 - Labour m3 100.00% 8,000 11,460 - Equipment ls 100.00% 16,825 24,092

Total

Concrete grade f'c 350 kg/cm2 m3 100.00%- Ready mix f'c 350 (incl.waste 5%) m3 105.00% 341,000 487,530 - Labour m3 100.00% 8,000 11,440 - Equipment ls 100.00% 16,825 24,053

Total

Concrete grade f'c 400 kg/cm2 m3 100.00%- Ready mix f'c 400 (incl.waste 5%) m3 105.00% 368,000 523,960 - Labour m3 100.00% 8,000 11,390 - Equipment ls 100.00% 16,825 23,952

Total

Concrete grade f'c 400 kg/cm2 for matt foundation m3 100.00%- Ready mix f'c 400 (incl.waste 5%) m3 105.00% 368,000 523,960 - Labour m3 100.00% 8,000 11,390 - Thermocoppel & chilled water ls 100.00% 20,500 28,942 - Mesh separator ls 100.00% 3,342 4,760 - Equipment ls 100.00% 16,825 23,950

Total

Page 43: Analisa Harga Sat

Page 43 of 55 document.xls/summit rev01

The SummitKelapa gading - Jakarta

Submission : 08-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Concrete grade f'c 400 kg/cm2 for basement slab, 400mm thick m3 100.00%- Ready mix f'c 400 (incl.waste 5%) m3 105.00% 368,000 523,960 - Labour m3 100.00% 8,000 11,390 - Mesh separator ls 100.00% 15,000 21,400 - Equipment ls 100.00% 16,825 25,052

Total

Concrete grade f'c 500 kg/cm2 m3 100.00%- Ready mix f'c 500 (incl.waste 5%) m3 105.00% 404,000 572,230 - Labour m3 100.00% 8,000 11,330 - Equipment ls 100.00% 16,825 23,828

Total

Concrete grade f'c 550 kg/cm2 m3 100.00%- Ready mix f'c 550 (incl.waste 5%) m3 105.00% 444,000 625,820 - Labour m3 100.00% 8,000 11,280 - Equipment ls 100.00% 16,825 23,709

Total

Loss formwork for matt foundation, 200mm thick m2 100.00%- Concrete blockwall nr ### 1,300 1,770 - Mortar 1:5 m3 10.50% 300,592 410,330 - Install blockwall m2 100.00% 10,000 13,801 - Concrete lintel m 40.00% 51,837 70,760

Total

Brickwork (1:3) 100mm thick + lintel m2 100.00%- Bata kuo shin (incl.waste 5%) nos ### 340 460 - Mortar 1:3 m3 2.10% 400,576 547,390 - Install brickwall m2 100.00% 10,000 14,079 - Concrete lintel m' 39.99% 51,837 70,840

Total

Brickwork (1:3) 200mm thick + lintel m2 100.00%- Bata kuo shin (incl.waste 5%) nos ### 340 460 - Mortar 1:3 m3 4.70% 400,576 547,390 - Install brickwall m2 100.00% 10,000 15,431 - Concrete lintel m' 39.99% 51,837 71,380

Total

Plaster (1:3) + skimcoat to wall m2 100.00%- Mortar 1:3 (incl.waste 5%) m3 2.50% 400,576 547,390 - Labour plaster m2 100.00% 8,000 10,609 - Portland cement @50 kg (incl.waste 5%) bag 2.40% 28,000 37,770 - Labour skimcoat m2 100.00% 4,000 5,400

Total

Celcon (1:5) 100mm thick + lintel m2 100.00%- Celcon block 590x190x100mm thk m3 8.60% 429,975 615,950 - Drymix mortar MU 380 (incl.waste 5%) bag 10.00% 1,400 2,010

Page 44: Analisa Harga Sat

Page 44 of 55 document.xls/summit rev01

The SummitKelapa gading - Jakarta

Submission : 08-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

- Install celcon wall m2 100.00% 10,000 14,323 - Concrete lintel m 40.00% 51,837 74,260

Total

Celcon (1:5) 150mm thick + lintel m2 100.00%- Celcon block 590x190x150mm thk m3 8.60% 445,725 808,920 - Drymix mortar MU 380 (incl.waste 5%) bag 10.00% 1,400 2,010 - Install celcon wall m2 100.00% 10,000 18,200 - Concrete lintel m 40.00% 51,837 94,080

Total

Celcon (1:5) 175mm thick + lintel m2 100.00%- Celcon block 590x190x175mm thk m3 8.60% 445,725 808,920 - Drymix mortar MU 380 (incl.waste 5%) bag 10.00% 1,400 2,010 - Install celcon wall m2 100.00% 10,000 29,196 - Concrete lintel m 40.00% 51,837 105,840

Total

Celcon (1:5) 200mm thick + lintel m2 100.00%- Celcon block 590x190x200mm thk m3 8.60% 445,725 808,920 - Drymix mortar MU 380 (incl.waste 5%) bag 10.00% 1,400 2,010 - Install celcon wall m2 100.00% 10,000 37,044 - Concrete lintel m 40.00% 51,837 114,220

Total

Celcon (1:5) 250mm thick + lintel m2 100.00%- Celcon block 590x190x250mm thk m3 8.60% 445,725 808,920 - Drymix mortar MU 380 (incl.waste 5%) bag 10.00% 1,400 2,010 - Install celcon wall m2 100.00% 10,000 56,724 - Concrete lintel m 40.00% 51,837 135,270

Total

Plaster + skimcoat drymix to celcon wall m2 100.00%- Drymix mortar MU 301 (incl.waste 5%) bag 45.00% 14,700 19,410 - Drymix mortar MU 200 (incl.waste 5%) bag 5.00% 50,400 66,530 - Labour plaster m2 100.00% 8,000 10,559 - Labour skimcoat m2 100.00% 4,000 5,280

Total

Ceramic wall tile 200 x 200mm ROMAN m2 100.00%- Ceramic wall tile 200x200mm ROMAN (incl.waste 5%) m2 105.00% 31,970 42,040 - Adhesivet MU 400 (incl.waste 5%) kg 500.20% 2,020 2,660 - Grout AM 50 (incl.waste 5%) kg 60.12% 6,500 8,550 - Install ceramic wall m2 100.00% 15,000 19,713

Total

Homogenous wall tile 600 x 600mm GRANITO m2 100.00%- Homogenous wall tile 600x600mm GRANITO (incl.waste 5%) m2 105.00% 143,330 185,670 - Adhesivet MU 400 (incl.waste 5%) kg 500.20% 2,360 2,660 - Grout AM 50 (incl.waste 5%) kg 30.00% 6,500 8,550 - Install homogenous wall m2 100.00% 15,000 21,376

Total

Page 45: Analisa Harga Sat

Page 45 of 55 document.xls/summit rev01

The SummitKelapa gading - Jakarta

Submission : 08-04-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY rate RATE

Ceramic floor tile 200 x 200mm ROMAN m2 100.00%- Ceramic floor tile 200x200mm ROMAN (incl.waste 5%) m2 105.00% 28,670 37,680 - Adhesivet MU 450 (incl.waste 5%) kg 500.00% 1,520 2,000 - Grout AM 50 (incl.waste 5%) kg 60.00% 6,500 8,550 - Install ceramic floor m2 100.00% 12,500 16,406

Total

Ceramic floor tile 400 x 400mm ROMAN m2 100.00%- Ceramic floor tile 400x400mm ROMAN (incl.waste 5%) m2 105.00% 30,500 38,340 - Adhesivet MU 450 (incl.waste 5%) kg 500.00% 2,000 2,000 - Grout AM 50 (incl.waste 5%) kg 40.00% 6,500 8,550 - Install ceramic floor m2 100.00% 12,500 18,123

Total

Homogenous floor tile 300 x 300mm GRANITO m2 100.00%- Homogenous floor tile 300x300mm GRANITO (incl.waste 5%) m2 105.00% 110,250 142,420 - Adhesivet MU 450 (incl.waste 5%) kg 500.00% 2,000 2,000 - Grout AM 50 (incl.waste 5%) kg 50.00% 6,500 8,550 - Install ceramic floor m2 100.00% 12,500 18,984

Total

Homogenous floor tile 600 x 600mm GRANITO m2 100.00%- Homogenous floor tile 600x600mm GRANITO (incl.waste 5%) m2 105.00% 143,330 185,650 - Adhesivet MU 450 (incl.waste 5%) kg 500.00% 2,000 2,000 - Grout AM 50 (incl.waste 5%) kg 30.00% 6,500 8,550 - Install ceramic floor m2 100.00% 12,500 19,102

Total

Page 46: Analisa Harga Sat

Page 46 of 55 document.xls/summit rev01

UNIT PRICE BREAKDOWN

AMOUNT

4,841 25 30 44 150 5,090

4,815 25 30 50 150 5,070

4,790 27 30 43 150 5,040

4,790 27 30 1,200 43 250 6,340

4,815 25 30 50 150 5,070

4,815 27 30 1,194 44 250 6,360

Page 47: Analisa Harga Sat

Page 47 of 55 document.xls/summit rev01

UNIT PRICE BREAKDOWN

AMOUNT

4,841 25 30 44 150 5,090

4,841 27 30 1,198 44 250 6,390

469,140 11,490 24,170 504,800

487,148 11,460 24,092 522,700

511,907 11,440 24,053 547,400

550,158 11,390 23,952 585,500

550,158 11,390 28,942 4,760 23,950 619,200

Page 48: Analisa Harga Sat

Page 48 of 55 document.xls/summit rev01

UNIT PRICE BREAKDOWN

AMOUNT

550,158 11,390 21,400 25,052 608,000

600,842 11,330 23,828 636,000

657,111 11,280 23,709 692,100

58,410 43,085 13,801 28,304 143,600

41,400 11,495 14,079 28,326 95,300

82,800 25,727 15,431 28,542 152,500

13,685 10,609 906 5,400 30,600

52,972 201

Page 49: Analisa Harga Sat

Page 49 of 55 document.xls/summit rev01

UNIT PRICE BREAKDOWN

AMOUNT

14,323 29,704 97,200

69,567 201 18,200 37,632 125,600

69,567 201 29,196 42,336 141,300

69,567 201 37,044 45,688 152,500

69,567 201 56,724 54,108 180,600

8,735 3,327 10,559 5,280 27,900

44,142 13,305 5,140 19,713 82,300

194,954 13,305 2,565 21,376 232,200

Page 50: Analisa Harga Sat

Page 50 of 55 document.xls/summit rev01

UNIT PRICE BREAKDOWN

AMOUNT

39,564 10,000 5,130 16,406 71,100

40,257 10,000 3,420 18,123 71,800

149,541 10,000 4,275 18,984 182,800

194,933 10,000 2,565 19,102 226,600

Page 51: Analisa Harga Sat

Page 51 of 55

The SummitKelapa gading - Jakarta

Submission : 21-03-2005

UNIT PRICE BREAKDOWN

NO. DESCRIPTION UNIT QTY RATE AMOUNT

1 Bar reinforcement BJTD-40 kg 1.00 Bar D. 10-12mm (incl.waste 5%) kg 0.04 6,240 250 Bar D. 13mm (incl.waste 5%) kg 0.19 6,210 1,180 Bar D. 16-25mm (incl.waste 5%) kg 0.31 6,170 1,913 Bar D. 29mm (incl.waste 5%) kg 0.04 6,210 255 Bar D. 32mm (incl.waste 5%) kg 0.42 6,240 2,621 Rebar subcon't (fabrication & installation) kg 1.00 532 532

Total 6,750

2 Concrete grade f'c 250 kg/cm2 m3 1.00 Ready mix f'c 250 (incl.waste 5%) m3 1.00 498,910 498,910 Labour m3 1.00 11,340 11,340 Equipment ls 1.00 23,850 23,850

Total 534,100

3 Loss formwork for matt foundation, 200mm thick m2 1.00 Concrete blockwall nr 33.00 1,680 55,440 Mortar 1:5 m3 0.105 388,890 40,833 Install blockwall m2 1.00 13,003 13,003 Concrete lintel m 0.40 67,060 26,824

Total 136,100

4 Brickwork (1:3) 100mm thick + lintel m2 1.00 Bata kuo shin (incl.waste 5%) nos 90.00 440 39,600 Mortar 1:3 m3 0.02 521,540 10,952 Install brickwall m2 1.00 13,261 13,261 Concrete lintel m' 0.40 67,490 26,987

Total 90,800

5 Celcon (1:5) 100mm thick + lintel m2 1.00 Celcon block 590x190x100mm thk m3 0.086 562,100 48,341 Drymix mortar MU 380 bag 0.10 1,830 183 Install celcon wall m2 1.00 13,072 13,072 Concrete lintel m 0.40 67,760 27,104

Total 88,700

6 Ceramic wall tile 200 x 200mm ROMAN m2 1.00 Ceramic wall tile 200x200mm ROMAN (incl.wast m2 1.00 40,080 40,080 Adhesivet MU 400 (incl.waste 5%) kg 5.00 3,110 15,556 Grout AM 50 (incl.waste 5%) kg 0.60 8,560 5,146 Install ceramic wall m2 1.00 19,718 19,718

Total 80,500

7 Ceramic floor tile 200 x 200mm ROMAN m2 1.00 Ceramic floor tile 200x200mm ROMAN (incl.was m2 1.00 35,990 35,990 Adhesivet MU 450 (incl.waste 5%) kg 5.00 2,640 13,200 Grout AM 50 (incl.waste 5%) kg 0.60 8,560 5,136 Install ceramic floor m2 1.00 16,474 16,474

Total 70,800

Page 52: Analisa Harga Sat

Page 52 of 55

The SummitKelapa gading - Jakarta

MATERIAL PRICE

No Material Unit Price (Rp) Remarks

1 Rebar BJTD 40; dia.10-12mm kg 4,400 2 Rebar BJTD 40; dia.13mm kg #REF!3 Rebar BJTD 40; dia.16-25mm kg #REF!4 Rebar BJTD 40; dia.29mm kg #REF!5 Rebar BJTD 40; dia.32mm kg #REF!6 Readymix concrete f'c 250 m3 319,000 7 Concrete block nr 1,300 size 90x200x400mm8 Bata kuoshin nr 230 size 51x100x210mm9 Celcon block m3 378,000 size 100x190x590mm

10 Ceramic wall tile m2 31,970 Roman gol.A; 200x200mm11 Ceramic floor tile m2 28,670 Roman gol.A; 200x200mm12 Drymix mortar MU 380 bag 1,400 13 Adhesive MU 400 kg 2,020 14 Adhesive MU 450 kg 1,520 15 Grouting AM 50 kg 6,500

Page 53: Analisa Harga Sat

Page 53 of 55

The SummitKelapa gading - Jakarta

LABOUR PRICE

No Labour Unit Price (Rp) Remarks

1 Labour concreting m3 16,180 2 Labour install concrete block m2 13,920 3 Labour install brickwall m2 13,655 4 Labour install celcon m2 14,594 5 Labour install ceramic wall m2 20,182 6 Labour install ceramic floor m2 16,810

Page 54: Analisa Harga Sat

Page 54 of 55

The SummitKelapa gading - Jakarta

EQUIPMENT PRICE

No Equipment Unit Price (Rp) Remarks

1 Concrete pump mth2 Mortar mixer mth3456789

101112131415

Page 55: Analisa Harga Sat

198,681,996 top sheet 18 mar '05