an integrated approach for water minimisation in a pvc
DESCRIPTION
WATERTRANSCRIPT
-
ORIGINAL PAPER
An integrated approach for water minimisation in a PVCmanufacturing process
Jun Hoa Chan Dominic Chwan Yee Foo Sivakumar Kumaresan Ramlan Abdul Aziz Mohd Ariffin Abu-Hassan
Received: 23 July 2007 / Accepted: 12 October 2007 / Published online: 30 November 2007
Springer-Verlag 2007
Abstract This paper presents a water minimisation study
carried out for a polyvinyl chloride (PVC) resins manu-
facturing plant. Due to the complexity of the mixed batch
and continuous polymerisation process, an integrated pro-
cess integration approach, which consists of process
synthesis, analysis and optimisation was used for this work.
A simulation model was first developed in a batch process
simulation software, SuperPro Designer V6.0, based on the
operating condition of a PVC manufacturing process. The
batch simulation model captured the essential information
needed for a water minimisation study, e.g. process
duration, water mass flow, etc. Data extracted from the
simulation model was later used in the water minimisation
study, utilising the widely established process synthesis
technique of water pinch analysis. Two water saving sce-
narios were presented. Scenario 1 reports a fresh water and
wastewater reduction of 28.5 and 90.1% respectively, for
the maximum water recovery scheme without water stor-
age system. In Scenario 2, higher fresh water and
wastewater reduction are reported at 31.7 and 100%
respectively, when water storage tank is installed in the
water network.
Keywords Process integration Water minimisation Pinch analysis Process modelling Batch processes Polymer manufacturing
Introduction
Recent development has seen the shift of the process
industries from conventional end-of-pipe waste treatment
to more sustainable pollution prevention or waste mini-
misation practises. Some of the factors that drive this shift
include environmental sustainability and stringent emission
legislations, as well as increasing cost of resources and
waste treatment. One of the active areas for waste mini-
misation activities has been that of in-plant water recovery.
The benefits of implementing water recovery are twofold.
Apart from the reduction of fresh water (and its associated
treatment), smaller volume of wastewater is generated.
The seminal work on insight-based techniques for water
network synthesis was initiated by Wang and Smith (1994),
who presented a two-stage pinch analysis technique for
fixed load problems, based on the more generalised mass
exchange network synthesis problems (El-Halwagi and
J. H. Chan
GTC Process Technology (Singapore) Pte. Ltd,
3 Science Park Drive, #01-08/09,
The Franklin 118223, Singapore
e-mail: [email protected]
D. C. Y. Foo (&)School of Chemical and Environmental Engineering,
University of Nottingham Malaysia, Broga Road,
43500 Semenyih, Selangor, Malaysia
e-mail: [email protected]
S. Kumaresan
School of Engineering and Information Technology,
University Malaysia Sabah, Locked Bag 2073,
88999 Kota Kinabalu, Sabah, Malaysia
e-mail: [email protected]
R. A. Aziz
Chemical Engineering Pilot Plant,
Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia
e-mail: [email protected]
M. A. Abu-Hassan
Chemical Engineering Department,
Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia
e-mail: [email protected]
123
Clean Techn Environ Policy (2008) 10:6779
DOI 10.1007/s10098-007-0127-2
-
Manousiouthakis 1989). In the first synthesis stage, limiting
composite curve is used to locate the minimum fresh water
and wastewater flowrate targets prior to detailed network
design (second stage of network synthesis). Flowrate con-
straints and multiple water sources were considered in their
later work (Wang and Smith 1995a). The basic concept
underlying these works is that all processes that use water
are modelled as mass transfer operations.
However, later works (e.g. Dhole et al. 1996; Hallale
2002; Manan et al. 2004) showed that representing all
processes that use water with mass transfer model might
not be always adequate. Some processes that use water e.g.
boiler blowdown, cooling tower make-up and reactor
effluent are typical examples where water quantity is more
important than the quality (always termed as fixed flowrate
problems). New graphical and numerical approaches have
been later developed to handle the fixed flowrate problems.
Some promising techniques in locating the minimum water
targets for the fixed flowrate problems include the graphi-
cal tools of water surplus diagram (Hallale 2002), material
recovery pinch diagram (El-Halwagi et al. 2003; Prakash
and Shenoy 2005a), source composite curve (Bandyopad-
hyay et al. 2006; Bandyopadhyay 2006) and the improved
limiting composite curve (Agrawal and Shenoy 2006), as
well as the numerical targeting tools such as cascade
analysis techniques (Manan et al. 2004; Almutlaq et al.
2005; Foo et al. 2006a; Almutlaq and El-Halwagi 2007;
Foo 2007a, b).
Apart from the targeting stage, numerous techniques
have also been proposed for the systematic design of water
network, i.e. second stage of the synthesis task. This
includes water grid diagram (Wang and Smith 1994), load
table (Olesen and Polley 1996, 1997), water main method
(Kuo and Smith 1998; Castro et al. 1999; Feng and Seider
2001), water source diagram procedure (Gomes et al. 2007)
for fixed load problems; as well as source sink mapping
diagram (El-Halwagi 1997), nearest neighbour algorithm
(Prakash and Shenoy 2005a) as well as the load problem
table (Aly et al. 2005) for fixed flowrate problems. Once
the flowrate targets are established, the water network is
designed to achieve the minimum targets using any of the
above-mentioned design tools. Subsequently, a preliminary
synthesised network can be evolved to yield a simplified
network (Prakash and Shenoy 2005b; Ng and Foo 2006).
In contrast to the active evolvement of water network
synthesis techniques in continuous processes, water mini-
misation for batch processes has received far less attention
due to its nature of complexity. Only recently, similar work
has received considerable attention for batch water net-
work. Wang and Smith (1995b) initiated the work in batch
water network synthesis that focused on mass transfer-
based processes that use water. Majozi et al. (2006)
developed a similar technique to account for batch
processes where no water intake and discharge are per-
mitted during the operation. The shortcoming of both these
approaches is their limitation in handling fixed load prob-
lems. To overcome the limitation of the fixed load
problems, Foo et al. (2005) proposed the use of water
cascade analysis technique that was originally developed
for water network for continuous processes (Manan et al.
2004; Foo et al. 2006a) in handling the fixed flowrate
problems. Other works on batch water network synthesis
are mainly dominated by various mathematical optimisa-
tion approaches (Almato et al. 1997, 1999a, 1999b;
Puigjaner et al. 2000; Kim and Smith 2004; Li and Chang
2006; Majozi 2005a, 2005b, 2006; Shoaib et al. 2007).
It should be noted that most of the reported works on
batch water network synthesis have utilised hypothetical
examples for demonstration. To date, limited numbers of
industrial cases have been reported, in both pinch-based
and mathematical-based works. This includes production
of concentrated fruit juice (Almato et al. 1997) and agro-
chemicals (Majozi et al. 2006). More industrial case studies
are needed to help in the development of new water min-
imisation techniques that are of practical use. This is the
subject of this paper. El-Halwagi (1997) describes that a
process integration study consists of three elements: i.e.
process synthesis, analysis and optimisation. In this work,
an integrated process integration approach has been used.
The process synthesis element consists of water network
synthesis, via pinch analysis technique while process
analysis and optimisation were carried out by batch process
simulation and modelling studies.
In the following section, the water cascade analysis
technique (Manan et al. 2004; Foo et al. 2006a) for locating
the minimum targets for a water network is first described.
This is followed by the description of a PVC manufactur-
ing case study. A simulation model that was developed
based on the plant operation data is next described. Batch
process simulation overcomes the constraint of the mixed-
batch and continuous operation mode in the polymer
manufacturing process. Data extracted from the simulation
model are later used in the water minimisation study car-
ried out using pinch analysis technique.
Water cascade analysis technique
The generic water cascade table (WCT) in Table 1 sum-
marises how WCA is carried out for water targeting in the
reuse/recycle scheme (Manan et al. 2004; Foo et al. 2006a).
The first step in conducting a WCA is to locate the various
water sinks and sources at their respective concentration
levels. As shown in the first two columns of Table 1, the
concentration levels (Ck) are arranged in an ascending
order (k = 1, 2, , n), and the flow of water sink (Fj) and
68 J. H. Chan et al.
123
-
source (Fi) are summed at their respective concentration
level k in columns 3 and 4. Column 5 represents the net
flow, (RiFi - RjFj) between water sources and sinks ateach concentration level k; with positive indicating surplus,
negative indicating deficit. Next, the net water flow sur-
plus/deficit is cascaded down the concentration levels to
yield the cumulative surplus/deficit flow (FC, k) in column 6
with an assumed zero fresh water flow (FFW = 0). This
assumed flow is to facilitate the search for the minimum
water flow and will later be replaced once the rigorous
fresh water target is located.
Two important parameters to fulfil in water network
targeting are the water flow and impurity load constraints
(Foo et al. 2006a). Water flow constraints are fulfilled once
the above-described flow cascading is carried out. The next
step involves setting up the cumulative impurity load cas-
cade (Cum. Dm) to fulfil the load constraint. Impurity loadin column 7 (Dmk) is obtained via the product of cumula-tive flow (FC, k) and the concentration difference across
two subsequent concentration levels (Ck+1 - Ck). Cascad-
ing the impurity load down the concentration levels of
column 8 yields the cumulative load (Cum. Dmk), which isessentially the numerical equivalent of graphical targeting
tool of water surplus diagram (Hallale 2002). A feasible
water network is characterised by the presence of only
positive values of Cum. Dm in column 8. A negative Cum.Dmk means the impurity load is transferred from lower tohigher concentration level, which is infeasible. In such a
case, an interval fresh water flow (FFW, k, column 9) is
calculated by dividing Cum. Dmk by the concentrationdifference between level k (Ck) and the fresh water con-
centration (CFW) i.e.,
FFW;k Cum. DmkCk CFW : 1
The absolute value of the largest negative FFW, k will then
replace the earlier assumed zero fresh water flow in the
cumulative flow (column 6) to obtain a new set of feasible
flow cascade and hence a feasible load cascade. This new
fresh water flow represents the minimum fresh water flow
(FFW) of the network; while the final row in column 6
represents the wastewater flow (FWW) generated from the
network. The network pinch concentration is the impurity
concentration with zero Cum. Dmk, while the water sourcethat exists at the pinch is called the pinch-causing source
(Manan et al. 2004; Foo et al. 2006a). Note that once the
flow and impurity load cascading are carried out using the
minimum fresh water flow, the final column of Table 1 is
omitted.
The above-described procedure for locating the mini-
mum water targets was original developed for water
networks operated in continuous mode (Manan et al. 2004;
Foo et al. 2006a), in which water flowrate is used instead of
water flow. Foo et al. (2005) later extended the targeting
tool for batch water network known as time-dependent
water cascade analysis. By segregating water sinks and
sources into the time interval when they exist, cascade
analysis is carried out in each time interval to locate the
minimum water targets. More recently, the targeting
technique was extended to multiple fresh resources (Foo
2007a) and threshold (Foo 2007b) problems.
Case study on PVC manufacturing
Figure 1 shows the process flow diagram for PVC resins
manufacture. It consists of ten parallel batch polymerisa-
tion reactors, blow-down vessel, and two parallel trains of
downstream processing equipment. Each downstream
processing train consists of a stripper, two decanters and a
fluid bed dryer. The plant is operated in a semi-batch mode
where upstream polymerisation reactors are scheduled to
match the downstream processing trains that are operated
in continuous mode. The polymerisation process is carried
Table 1 The generic water cascade table (WCT)
k Ck RjFj RiFi RiFi - RjFj FC,k Dmk Cum. Dmk FFW,k
FFW
k Ck (RjFj)k (RiFi)k (RiFi - RjFj)kFC,k Dmk
k + 1 Ck+1 (RjFj)k+1 (RiFi)k+1 (RiFi - RjFj)k+1 Cum. Dmk+1 FFW,k+1FC,k+1 Dmk+1
..
. ... ..
. ... ..
. ... ..
. ... ..
.
n - 2 Cn-2 (RjFj)n-2 (Ri Fi)n-2 (RiFi - RjFj)n-2FC,n-2 Dn-2
n - 1 Cn-1 (RjFj)n-1 (RiFi)n-1 (RiFi -Rj Fj) n-1 Cum. Dm n-1 FFW,n-1FC,n-1 = FWW Dmn-1
n Cn Cum. Dmn FFW,n
An integrated approach for water minimisation in a PVC manufacturing process 69
123
-
out subsequently in ten parallel batch reactors. Raw
materials for the polymerisation process include deminer-
alised water, mixture of fresh vinyl chloride monomer
(VCM) and recycled VCM (mainly from blowdown vessel
and stripper), initiators and suspending agents, which are
charged into the reactor in sequence.
The suspending agent is diluted to approximately
4.0 wt% and is charged into the reactor together with
demineralised water. This is mainly due to the high vis-
cosity of the suspending agent solution. Upon completion
of the suspending agent charge, primary and secondary
initiators are added into the reactor. It shall also be noted
that, due to piping constraints, demineralised water can
only be charged into the reactors one at a time. Charging
procedure in each of the reactor will only start after the end
of charging in an earlier reactor. The same situation occurs
to the charging of VCM and the blowdown operation after
the reaction ends.
Upon completion of water charge, the reactor is purged
by nitrogen and then vacuumed before charging of VCM is
commenced. This is to ensure that no oxygen is present in
the reactor, as reaction between VCM and oxygen might
result in an explosion. Upon the completion of VCM
charge, heating is commenced to raise the reactor to the
operating temperature and pressure. Exothermic polymer-
isation process next commences for a duration of 7.5 h.
Continuous cooling is needed to remove excess heat and to
maintain the reactor temperature. A huge amount of chilled
water is added towards the end of the polymerisation
process to maintain the reactor temperature. PVC polymer
is the main product at the end of the polymerisation pro-
cess. Other by-products of the reaction are the unreacted
VCM, initiators, suspending agent and some trace amount
of contaminant. The final reactor content is in slurry form
(mainly consists of PVC and water).
The blowdown vessel receives batches of slurry, which
are intermittently discharged from the reactors. The
blowdown vessel acts as buffer storage so that slurry can be
continuously fed to the two parallel downstream processing
trains. As the slurry enters the blowdown vessel, the major
portion of the unreacted VCM trapped in the PVC particles
flashes off and is vented to the gas holder for recovery. The
VCM vapour is next compressed and condensed into liquid
form before it is sent for reuse in the polymerisation
reactors.
As the effluent from the blowdown vessel enters the
downstream processing trains, the stripper column further
removes the unreacted VCM from the PVC slurry. Steam is
introduced at the base of the stripping column and the
VCM is removed as an overhead product to the gas holder.
The stripped slurry is then directed to two parallel
decanters for water removal. Approximately 80% of water
is removed by these decanters from the PVC slurry. Wet
cake from the decanters is dried in the fluidised bed dryer.
Dried PVC resins are transported to the shifter. Fine resins
that pass through the shifter are sold as product, while the
course resins are ground and sold as low-grade resins.
Process simulation model
Figure 2 shows the base case process simulation model that
has been developed based on the operating condition of the
PVC manufacturing process using SuperPro Designer V6.0
(Intelligen 2005). The annual operating time of the process
model is taken as 7920 h. In the modelling environment of
SuperPro Designer, a few operations take place sequen-
tially in a single unit procedure (Intellegen 2005). For
instance, vessel procedure P-1 in Fig. 2 is used to model
the batch polymerisation procedure that takes place in
vessel K-207A. The polymerisation procedure consists of
sequential operations of raw material charges, vacuum
operation, material heating, polymerisation as well as
product blowdown. The modelling of these single opera-
tions is described next.
The raw material charged into the reactor during the
start of procedure P-1 includes demineralised water
(CHARGE-H2O), suspending agent (CHARGE-PVA),
primary initiator (CHARGE-Init1) and secondary initiator
(CHARGE-Init2). Note that the model was developed
based on the operating condition of the manufacturing
process, where the charging of demineralised water for a
subsequent reactor is scheduled to start after the water
charging of the preceding reactor ends. Suspending agent
and initiators are charged into the reactor during the
charging of water.
The vacuum operations (VACUUM) in procedure P-1
include a vacuum air purge, followed by a nitrogen gas
purge and finally another vacuum purge. The vacuum
operations were carried out before the charging of VCM
(CHARGE-VCM), to avoid the mixing of VCM with air,
which will lead to explosion.
delcyceRMCV
redloHsaGrosserpmoCresnednoC
srotcaeRhctaB)stinU01(
nwodwolBlesseV
yrrulSreppirtS
retnaceDreyrD
derevoceRruopavMCV
CVPsniseR
maetS
hserFMCV
riatoH
retfihS
Fig. 1 Process flow diagram of a PVC manufacturing plant
70 J. H. Chan et al.
123
-
During the heating operation, hot water is used to raise
the reactor temperature (HEAT-1) to 60C where thepolymerisation process (REACT-1) is carried out. The
polymerisation reaction operation takes an overall duration
of 7.5 h. Chilled water is added to the reactor (CHARGE-
Chilled H2O) in the last half-an-hour just before the
polymerisation reaction ends. Stoichiometric reaction
model is used and the reaction stoichiometric is defined as
the conversion of one mass of VCM to one mass of PVC,
as follows:
nVCM ! PVCn: 2Upon the completion of the polymerisation process, the
slurry reactor content is discharged (TRANS-OUT) to the
blowdown procedure P-14 (in vessel V-101). Similar to the
case of demineralised water charge, blowdown operation of
a subsequent reactor is also scheduled to start after the
completion of a preceding reactor, due to the piping con-
straint in the PVC plant. The last operation in the vessel
procedure is the cleaning process. The scheduling summary
for all reaction procedures (P-1 to P-10) is displayed in the
process Gantt chart as shown in Fig. 3.
From the blowdown vessel, the slurry product enters
into two parallel identical and continuous downstream
processing trains, which individually consist of a stripper,
slurry tank, two parallel identical decanters and a fluid-bed
dryer. Thus, no scheduling is needed in these processes.
The modelling specifications of each unit procedure in
these downstream processing trains are next described.
Stripper procedures (P-16 and P-17) are used for VCM
removal. Steam at 110C is introduced into the strippers toachieve a VCM removal of 99.9%, before the PVC slurry
enters into two parallel identical decanters (P-18 and P-19,
each represents two identical decanters). Solid removal in
the decanters is specified as 99% for PVC, with water loss
of 21%. Effluent emits from these decanter units (WW A-D)
is the main wastewater of the process, while the wet filter
cake is sent to fluidised-bed dryers for moisture removal. In
the fluidised-bed dryers (P-20 and P-21), hot air at 95C isused to dry the wet filter cake. Evaporation rate of water and
the final solid temperature are set at 916 kg H2O/h and 60Crespectively. As a result, 99.8% of the moisture (the com-
ponent of water and chilled water) is removed.
From the simulation model, the minimum cycle time for
the process is determined to be 11.78 h corresponds to the
completion of the last reactor (P-10/K-207J). Based on the
annual operating time of 7,920 h, this translates into 671
batches/year. It should also be noted that all vessel pro-
cedures (P-1 to P-10) are observed to have different cycle
times (see Gantt chart in Fig. 3). This is mainly due to the
scheduling of the TRANS-OUT operations in each of the
reactor procedures (P-1 to P-10). Since TRANS-OUT
operation in each of the reactor is scheduled to start after
the TRANS-OUT operation of the preceding reactor ends,
this creates a lag time for the product to be discharged from
the subsequent reactor before the preceding reactor com-
pletes its TRANS-OUT operation. A good example is
shown in Fig. 3. As shown, the polymerisation reaction
Fig. 2 Simulation flowsheet of PVC manufacturing
An integrated approach for water minimisation in a PVC manufacturing process 71
123
-
(REACT-1) in P-2/K-207B is completed at 9.62 h. How-
ever, due to the TRANS-OUT operation of P-1/K-207A
being still in operation, TRANS-OUT operation in P-2/K-
207B cannot be started until the TRANS-OUT operation in
P-1/K-207A ends at 9.78 h.
Water minimisation study
This section presents water minimisation study carried out
for the PVC manufacturing process. Figure 4 shows the
water usage diagram for the process. This includes the PVC
manufacturing as well as the utility sections.
As shown in Fig. 4, the process receives fresh water
supply from the state water supplier. Since the PVC man-
ufacturing process requires feed water that is free of
hardness, the fresh water is further treated in a deionised
plant (DI plant). Feed water to the utility section (boiler
and cooling tower make-up) and general cleaning purposes
tolerate a lower quality of water, and hence treatment in the
DI plant has been avoided.
The only water source for the process originates from
the continuous discharge of the four parallel decanters
(WW A-D), which are used to dewater the slurry effluent
from the strippers. The total flowrate of these water sources
are determined to be 9,243.9 kg/h. Since the four water
sources have the same characteristics, they are treated as a
single water source. The main impurity that is of concern
for water reuse/recycling activity is the suspended solid
content in the wastewater at a concentration of 50 ppm.
Water sinks that are considered for water reuse/recycle
include the PVC manufacturing process (mainly for reactor
feed), utility section (boiler and cooling tower make-up)
and miscellaneous usage (e.g. floor cleaning, etc.).
Limiting water data extraction
Data extraction is considered to be the most essential step
of a water minimisation study. Incorrect extraction of data
leads to sub-optimal water network with reduced water
saving targets (Foo et al. 2006b). For a batch water net-
work, apart from the limiting water flow and concentration,
the occurrences of the processes that use water are to be
identified. In this work, the start and end time as well as the
duration for each processes that use water are identified
with the aid of the base case simulation model.
Table 2 summarises the limiting data for a single batch
of polymerisation process. However, if one were to use this
set of limiting data for the analysis, one may lose the
greater water saving potential. This is because the raw data
extracted from the simulation study does not reflect how
the batch polymerisation process are carried out in actual
operation. For most industrial batch processes, the
Fig. 3 Process Gantt chart for base case simulation
72 J. H. Chan et al.
123
-
operations are repeated (as cyclic mode) once the equip-
ment has completed its earlier operation. Figure 5 shows
such a situation, where three consequent batches of pro-
cesses occur simultaneously within the time frame of a
single batch N. As shown, batch (N - 1) completed its
operations after 4.5 h batch N commences its operation;
while batch (N + 1) begins its operations 4.5 h before
batch N ends. The revised limiting data is summarised in
Table 3.
It should also be noted that some operations in Fig. 5
and Table 3 are carried out in sequence. For instance,
reactor feed operation (SK1) for one reactor takes 20 min
to complete (CHARGE-H2O as in Fig. 3), hence a total of
200 min or 3.33 h would be needed for 10 reactors to
complete their reactor feed operations carried out
subsequently (Fig. 5). The same situation occurs to line
flushing (SK2), reactor cleaning (SK5) and flushing (SK7),
in which each individual operation for each reactor takes
0.5 h to complete.
Two water saving scenarios with and without water
storage system were analysed using the time-dependent
water cascade analysis technique (Foo et al. 2005). The
first stage of the analysis corresponds to the allocation of
the water sinks and sources in their respective time inter-
vals. The time interval table in Table 4 is utilised for this
preliminary analysis. As shown, there are 13 time intervals
and all water sinks are located in their respective time
intervals according to their occurrence time. The sum of
the individual water flow of the water sinks gives the total
water requirement of each time interval. The flowrate of
rotcaeR
tekcaJ
ydaetSgniraeB
relioB
gnilooCrewoT
retaWtoHknaT
rellihC
eruPretaW
knaT wolBnwod
reppirtS yrrulSknaT
retnaceD
reyrDmaetS
etasnednoC
retaWtoHnoitalucriC
retaWgnilooCnoitalucriC
retaWtoHnoitalucriC
slacimehC
slacimehC
deeFrotcaeR
gnihsulF
dellihCretaW
gnihsulF
nihsulFeniL g
slacimehC
gniraeBydaetSotretaW
pUekaMrewoTgnilooC
puekamrelioBetaw r
retaWretliF
deretliFretaW
knaT
.I.DtnalP
riAretaeH
riAtoH
riAdloC
)gnihsulFlaunaM(egasusuoenallecsiM
retaWtoHknaT
maetS
)gnihsaWroolF(egasusuoenallecsiMretawhserF
gninaelCrotcaeR
maetS
gnihsulF
sniseRCVP
retawetsaW
Fig. 4 Water usage diagram
Table 2 Raw data extracted from base case simulation
Sinks Operation Flowrate Concentration Start time End time Mass flow
SKj (kg/h) Cj (ppm) tS (h) tT (h) Fj (kg)
1 Reactor feed 31,531.53 10 0 3.33 105,000
2 Line flushing 3,125.00 10 9.28 14.28 15,625
3 Boiler make-up 1 13,200.00 10 0 0.25 3,300
4 Boiler make-up 2 13,200.00 10 8 8.25 3,300
5 Reactor cleaning 1,200 20 9.78 14.78 6,000
6 Cooling tower 6,300.00 50 0 14.78 93,114
7 Flushing 2,000.00 200 9.28 14.28 10,000
8 Floor cleaning 1 6,000.00 500 0 0.25 1,500
9 Floor cleaning 2 6,000.00 500 8 8.25 1,500
RjSKj 82,556.53 239,339
Sources Operation Flowrate Concentration Start time End time Mass flow
SRi (kg/h) Ci (ppm) tS (h) tT (h) Fi (kg)
RjSRi Decanter 9,243.90 50 0 14.78 136,625
An integrated approach for water minimisation in a PVC manufacturing process 73
123
-
the continuous water source (SR1 from decanter) is also
scaled according to the duration of each time interval. Both
water saving scenarios are analysed as follows.
Scenario 1: water network without water storage system
In Scenario 1, no water storage tank is installed for the batch
water network. Hence, water saving can only be carried out
via direct integration, i.e. when both water sinks and sources
present together within the same time interval.
Table 5 shows two examples of flow targeting for time
interval 00.25 h and 9.289.78 h. Due to the overlapping
between two consequent batches, water sinks from the
earlier batch (SK2, SK5, SK6 and SK7) and current batch
(SK1, SK3, SK6 and SK8) operations are observed
between 0 and 0.25 h. The water source for this interval is
available at 2,311 kg and 50 ppm ( column 3 in Table 4).
Without considering for water reuse/recycle, this interval
requires 17,414 kg of fresh water and generates 2,311 kg
of wastewater. As shown in Table 5, maximum water
recovery enables the fresh water (FFW) to be reduced to
15,103 kg and wastewater is completely eliminated
(FWW = 0 kg). Another characteristic to be noted in
Table 5 is that water targeting this time interval exhibits a
threshold problem. Hence, flow adjustment is needed for
the flow cascade, as reflected in the adjusted cumulative
flow (Adj. FC) column in Table 5. Detailed description for
the threshold problem is outlined in Foo (2007b).
1
368
1
3
6
8
2
567
2
45
7
hctaB N
hctaB (N 1+ )
hctaB (N 1 )
0 5 01 51(hctaB N strats)1+rh82.01tanoitarepo
(hctaB N sdne)1rh5.4tanoitarepo0 5 01 51
rh87.41=emitelcychctaB
9
Fig. 5 The overlap of three consequent batches of polymerisationprocesses (only water sinks are shown)
Table 3 Limiting data that takes into consideration repeated batch processes
Number of
batches
Sinks SKj Operation Flowrate
(kg/h)
Concentration
Cj (ppm)Start time
tS (h)End time
tT (h)Mass flow
Fj (kg)
N - 1 2a Line flushing 3,125.00 10 0 4 12,500
5a Reactor cleaning 1,200 20 0 4.5 5,400
6a Cooling tower 6,300.00 50 0 4.5 28,350
7a Flushing 2,000.00 200 0 4 8,000
1b Reactor feed 31,531.53 10 0 3.33 105,000
2b Line flushing 3,125.00 10 9.28 14.28 15,625
3b Boiler make-up 1 13,200.00 10 0 0.25 3,300
4b Boiler make-up 2 13,200.00 10 8.00 8.25 3,300
N 5b Reactor cleaning 1,200 20 9.78 14.78 6,000
6b Cooling tower 6,300.00 50 0 14.78 93,114
7b Flushing 2,000.00 200 9.28 14.28 10,000
8b Floor cleaning 1 6,000.00 500 0 0.25 1,500
9b Floor cleaning 2 6,000.00 500 8.00 8.25 1,500
1c Reactor feed 31,531.53 10 10.28 13.61 105,000
N + 1 3c Boiler make-up 1 13,200.00 10 10.28 10.53 3,300
6c Cooling tower 6,300.00 50 10.28 14.78 28,350
8c Floor cleaning 1 6,000.00 500 10.28 10.53 1,500
RjSKj 152,213 431,739
Sources SKi Operation Flowrate (kg/h) Concentration Ci (ppm) Start time tS (h) End time tT (h) Mass flow Fi (kg)
Continuous 1 Decanter 9,243.90 50 0 14.78 136,625
RjSKi 9,243.90 136,625
74 J. H. Chan et al.
123
-
Table 4 Time interval table for case study on PVC manufacturing
SKj Flowrate (kg/h) Start time, tS (h)
0 0.25 3.33 4 4.5 8 8.25 9.28 9.78 10.28 10.53 13.61 14.28
2a 3,125 781 9,625 2,094
5a 1,200 300 3,696 804 600
6a 6,300 1,575 19,404 4,221 3,150
7a 2,000 500 6,160 1,340
1b 31,532 7,883 97,117
2b 3,125 1,563 1,563 781 9,625 2,094
3b 13,200 3,300
4b 13,200 3,300
5b 1,200 600 300 3,696 804 600
6b 6,300 1,575 19,404 4,221 3,150 22,050 1,575 6,489 3,150 3,150 1,575 19,404 4,221 3,150
7b 2,000 1,000 1,000 500 6,160 1,340
8b 6,000 1,500
9b 6,000 1,500
1c 31,532 7,883 97,117
3c 13,200 3,300
6c 6,300 1,575 19,404 4,221 3,150
8c 6,000 1,500
SRi Flowrate
1 9,244 2,311 28,471 6,193 4,622 32,354 2,311 9,521 4,622 4,622 2,311 28,471 6,193 4,622
Table 5 Cascade analysis for water flow targeting (00.25 h)
Ci(ppm)
RjFj(kg)
RiFi(kg)
RiFi - RjFj(kg)
FC(kg)
Dm(mg)
Cum. Dm(mg)
FFW,k(kg)
FC(kg)
Adj. FC(kg)
Dm(mg)
Cum. Dm(mg)
0
0 15,102 FFW = 15,103 151,032
10 11,964 -11,964 151,032
-11,964 -119,641 3,138 3139 31,390
20 300 -300 -119,641 -5,982 182,422
-12,264 -367,924 2,838 2839 85,171
50 3150 2,311 -839 -487,565 -9,751 267,593
-13,103 -1,965,474 1,999 2000 300,000
200 500 -500 -2,453,039 -12,265 567,593
-13,603 -4,080,947 1,499 1500 450,000
500 1,500 -1,500 -6,533,986 -13,068 1,017,593
-15,103 -15,095,605,921 -1 FWW = 0 0
1,000,000 -15,102,139,907 -15,102 1,017,593
Table 6 Cascade analysis for water flow targeting (9.289.78 h)
Ci(ppm)
RjFj(kg)
RiFi(kg)
RiFi - RjFj(kg)
FC(kg)
Dm(mg)
Cum. Dm(mg)
FFW,k(kg)
FC(kg)
Dm(mg)
Cum. Dm(mg)
0
0 FFW = 1,250 12,500
10 1,563 -1,563 12,500
-1,563 -15,625 -313 -3,125
20 0 -15,625 -781 9,375
-1,563 -46,875 -313 -9,375
50 3,150 4,622 1,472 -62,500 -1,250 0
-91 -13,583 1,159 173,918 (PINCH)
200 1,000 -1,000 -76,083 -380 173,918
-1,091 -327,165 159 47,835
500 0 -403,248 -806 221,753
-1,091 -1,090,004,725 FWW = 159 159,370,275
1,000,000 -1,090,407,973 -1,090 159,592,028
An integrated approach for water minimisation in a PVC manufacturing process 75
123
-
Ta
ble
7M
inim
um
flo
wta
rget
ing
for
Sce
nar
io1
:w
ith
ou
tw
ater
sto
rag
e
0
0.2
5h
0.2
5
3.3
3h
3.3
3
4.0
0h
4.0
0
4.5
0h
4.5
0
8.0
0h
8.0
0
8.2
5h
8.2
5
9.2
8h
Ci
(pp
m)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
(a)
0
9.2
8h
0
15
,10
31
26
,93
56
,48
62
,27
80
4,0
64
0
10
-1
1,9
64
-1
06
,74
2-
2,0
94
00
-3
,30
00
3,1
39
20
,19
34
,39
32
,27
80
76
40
20
-3
00
-3
,69
6-
80
4-
60
00
00
2,8
39
16
,49
73
,58
91
,67
80
76
40
50
-8
39
-1
0,3
37
-2
,24
9-
1,6
78
10
,30
47
36
3,0
32
2,0
00
6,1
60
1,3
40
01
0,3
04
1,5
00
3,0
32
20
0-
50
0-
6,1
60
-1
,34
00
00
0
1,5
00
00
01
0,3
04
1,5
00
3,0
32
50
0-
1,5
00
00
00
-1
,50
00
00
00
10
,30
40
3,0
32
1,0
00
,00
0
9.2
8
9.7
8h
9.7
8
10
.28
h1
0.2
8
0.5
3h
10
.53
1
3.6
1h
13
.61
1
4.2
8h
14
.28
1
4.7
8h
Ci
(pp
m)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
(b)
9.2
8
14
.78
h
0
1,2
50
1,6
90
15
,10
31
26
,93
56
,48
62
,27
8R
FF
W=
30
8,6
09
10
-1
,56
3-
1,5
63
-1
1,9
64
-1
06
,74
2-
2,0
94
0
-3
13
12
83
,13
92
0,1
93
4,3
93
2,2
78
20
0-
60
0-
30
0-
3,6
96
-8
04
-6
00
-3
13
-4
72
2,8
39
16
,49
73
,58
91
,67
8
50
1,4
72
1,4
72
-8
39
-1
0,3
37
-2
,24
9-
1,6
78
1,1
59
1,0
00
2,0
00
6,1
60
1,3
40
0
20
0-
1,0
00
-1
,00
0-
50
0-
6,1
60
-1
,34
00
15
90
1,5
00
00
0
50
00
0-
1,5
00
00
0
15
90
00
00
RF
WW
=1
3,4
95
1,0
00
,00
0
76 J. H. Chan et al.
123
-
Ta
ble
8M
inim
um
flo
wta
rget
ing
for
Sce
nar
io2
:w
ith
wat
erst
ora
ge
0
0.2
5h
0.2
5
3.3
3h
3.3
3
4.0
0h
4.0
0
4.5
0h
4.5
0
8.0
0h
8.0
0
8.2
5h
8.2
5
9.2
8h
Ci
(pp
m)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
(a)
0
9.2
8h
0
15
,10
31
26
,93
56
,48
62
,27
80
26
40
0
10
-1
1,9
64
-1
06
,74
2-
2,0
94
00
-3
,30
00
3,1
39
20
,19
34
,39
32
,27
80
-6
60
.00
0
20
-3
00
-3
,69
6-
80
4-
60
00
00
2,8
39
16
,49
73
,58
91
,67
80
-6
60
.00
0
50
-8
39
-1
0,3
37
-2
,24
9-
1,6
78
10
,30
47
36
3,0
32
2,0
00
6,1
60
1,3
40
00
15
00
.00
0
20
0-
50
0-
6,1
60
-1
,34
00
00
0
1,5
00
00
00
15
00
.00
0
50
0-
1,5
00
00
00
-1
,50
00
00
00
00
.00
0
1,0
00
,00
0
FS
T0
00
01
0,3
04
-1
,42
43
,03
2
9.2
8
9.7
8h
9.7
8
10
.28
h1
0.2
8
10
.53
h1
0.5
3
13
.61
h1
3.6
1
14
.28
h1
4.2
8
14
.78
h
Ci
(pp
m)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
RiF
i-
RjF
j
(kg
)
FC
(kg
)
(b)
9.2
8
14
.78
h
0
1,2
50
16
10
98
51
12
0,1
96
6,4
86
2,2
78
RF
FW
=2
95
,11
4
10
-1
,56
3-
1,5
63
-1
1,9
64
-1
06
,74
2-
2,0
94
0
-3
13
48
-2
11
31
3,4
54
4,3
93
2,2
78
20
0-
60
0-
30
0-
3,6
96
-8
04
-6
00
-3
13
-5
53
-2
41
39
,75
83
,58
91
,67
8
50
1,4
72
1,4
72
-8
39
-1
0,3
37
-2
,24
9-
1,6
78
1,0
00
10
00
20
00
6,1
60
1,3
40
0
20
0-
1,0
00
-1
,00
0-
50
0-
6,1
60
-1
,34
00
00
15
00
00
0
50
00
0-
1,5
00
00
0
00
00
00
RF
WW
=0
1,0
00
,00
0
FS
T1
59
-8
1-
5,2
52
-6
,73
90
0
An integrated approach for water minimisation in a PVC manufacturing process 77
123
-
On the other hand, only three water sinks from current
operation are observed between 9.28 and 9.78 h (observed
from Table 4). As shown in Table 6, targeting for this time
interval yields fresh water and wastewater flows of 1,250
and 159 kg, respectively, with a pinch concentration
observed at 50 ppm.
Similar water flows targeting were carried out for all
other time intervals, and the summary is shown in Table 7
(only net water flow and cumulative flow are shown). The
final column of Table 7 shows that the total fresh water and
wastewater flows for the network are determined to be
308,609 and 13,495 kg respectively. This corresponds to a
reduction of 28.5% fresh water and 90.1% of wastewater,
compared to current water network without any water
reuse/recycle practice.
Scenario 2:water network with water storage system
In Scenario 1, due to the absence of a water storage tank,
wastewater are discharged at certain time intervals without
being further utilised. This includes time intervals of 4.50
8.00, 8.259.28 and 9.289.78 h. By utilising a water
storage tank, wastewater at these time intervals may be
stored for further usage at time intervals that exhibit water
deficit. Table 8 shows how this indirect integration scheme
is materialised. The last row of Table 8 displays the water
flow (FST) that enters or leaves the water storage. As
shown, water is stored between intervals that generate
wastewater (given as positive FST value) and utilised at
other intervals (given as negative FST value) to reduce their
fresh water demand. As such, the fresh water flow is
reduced to 295,114 kg (31.7% reduction), while wastewa-
ter flow is completely removed. A cumulative water mass
chart is shown in Fig. 6, indicating that a tank with a
capacity of 12 tons is needed to achieve the maximum
water recovery as in Scenario 2. The flow sheet for the final
water reuse/recycling scheme is shown in Fig. 7.
Fig. 6 Cumulative mass in water storage tank
Fig. 7 Flow sheet after water reuse/recycling
78 J. H. Chan et al.
123
-
The decision as to which scenarios would be imple-
mented eventually will rely on the decision of the plant
authority after a detailed economic assessment of each
scenario, which is beyond the scope of this work.
Conclusion
A water minimisation scheme was developed for a PVC
manufacturing case study. An integrated approach that
consists of process synthesis, analysis and optimisation
steps was utilised to identify the true minimum water tar-
gets for the water network that is operated in mixed batch
and in continuous mode. Two water saving scenarios were
presented to analyse the maximum water saving potential
of the process.
Acknowledgment The technical assistance of Mr. Yoeng CheeNyok is gratefully acknowledged.
References
Agrawal V, Shenoy UV (2006) Unified conceptual approach to
targeting and design of water and hydrogen networks. AIChE J
52(3):10711081
Almato M, Sanmart E, Espuna A, Puigjaner L (1997) Rationalizing
the water use in the batch process industry. Comput Chem Eng
21:S971S976
Almato M, Espuna A, Puigjaner L (1999a) Optimisation of water use
in batch process industries. Comp Chem Eng 23:14271437
Almato M, Sanmat E, Espuna A, Puigjaner L (1999b) Economic
optimization of the water reuse network in batch process
industries. Comput Chem Eng 23:S153S156
Almutlaq AM, Kazantzi V, El-Halwagi MM (2005) An algebraic
approach to targeting waste discharge and impure fresh usage via
material recycle/reuse networks. Clean Technol Environ Policy
7(4):294305
Almutlaq AM, El-Halwagi MM (2007) An algebraic targeting
approach to resource conservation via material recycle/reuse.
Int J Environ Poll 29(1/2/3):418
Aly S, Abeer S, Awad M (2005) A new systematic approach for water
network design. Clean Technol Environ Policy 7(3):154161
Bandyopadhyay S, Ghanekar MD, Pillai HK (2006) Process water
management. Ind Eng Chem Res 45:52875297
Bandyopadhyay S (2006) Source composite curve for waste reduc-
tion. Chem Eng J 125:99110
Castro P, Matos H, Fernandes MC, Nunes CP (1999) Improvements
for mass-exchange networks design. Chem Eng Sci 54:1649
1665
Dhole VR, Ramchandani N, Tainsh RA, Wasilewski M (1996) Make
your process water pay for itself. Chem Eng 103:100103
El-Halwagi MM, Manousiouthakis V (1989) Synthesis of mass
exchange networks. AIChE J 35(8):12331244
El-Halwagi MM (1997) Pollution prevention through process inte-
gration: systematic design tools. Academic Press, San Diego
El-Halwagi MM, Gabriel F, Harell D (2003) Rigorous graphical
targeting for resource conservation via material recycle/reuse
networks. Ind Eng Chem Res 42:43194328
Feng X, Seider WD (2001) New structure and design method for
water networks. Ind Eng Chem Res 40:61406146
Foo DCY, Manan ZA, Tan YL (2005) Synthesis of maximum water
recovery network for batch process systems. J Clean Prod
13(15):13811394
Foo DCY, Manan ZA, Tan YL (2006a) Use cascade analysis to
optimize water networks. Chem Eng Prog 102(7):4552
Foo DCY, Manan ZA, El-Halwagi MM (2006b) Correct identification
of limiting water data for water network synthesis. Clean
Technol Environ Policy 8(2):96104
Foo DCY (2007a) Water cascade analysis for single and multiple
impure fresh water feed. Chem Eng Res Des 85(A8):11691177
Foo DCY (2007b) Flowrate targeting for threshold problems and
plant-wide integration for water network synthesis. J Environ
Manage (in press)
Gomes JFS, Queiroz EM, Pessoa FLP (2007) Design procedure for
water/wastewater minimization: single contaminant. J Clean
Prod 15:474485
Hallale N (2002) A new graphical targeting method for water
minimisation. Adv Environ Res 6(3):377390
Intelligen Inc. (2005) SuperPro Designer1 users guide. Intelligen
Inc., Scotch Plains, New Jersey
Kim J-K, Smith R (2004) Automated design of discontinuous water
systems. Trans Inst Chem Eng, Part B 82(B3):238248
Kuo W-CJ, Smith R (1998) Designing for the interactions between
water use and effluent treatment. Trans Inst Chem Eng, Part A,
287301
Li BH, Chang C (2006) A mathematical programming model for
discontinuous water-reuse system design. Ind Eng Chem Res
45:50275036
Majozi T, Brouckaert CJ, Buckley CA (2006) A graphical technique
for wastewater minimisation in batch processes. J Environ
Manage 78:317329
Majozi T (2005a) Wastewater minimisation using central reusable
water storage in batch plants. Comp Chem Eng 29:16311646
Majozi T (2005b) An effective technique for wastewater minimisa-
tion in batch processes. J Clean Prod 13(15):13741380
Majozi T (2006) Storage design for maximum wastewater reuse in
multipurpose batch plants. Ind Eng Chem Res 45:59365943
Manan ZA, Tan YL, Foo DCY (2004) Targeting the minimum water
flowrate using water cascade analysis technique. AIChE J
50(12):31693183
Ng DKS, Foo DCY (2006) Evolution of water network with improved
source shift algorithm and water path analysis. Ind Eng Chem
Res 45:80958104
Olesen SG, Polley GT (1996) Dealing with plant geography and
piping constraints in water network design. Trans Inst Chem
Eng, Part B 74:273276
Olesen SG, Polley GT (1997) A simple methodology for the design of
water networks handling single contaminants. Trans Inst Chem
Eng, Part A 75:420426
Prakash R, Shenoy UV (2005a) Targeting and design of water
networks for fixed flowrate and fixed contaminant load opera-
tions. Chem Eng Sci 60(1):255268
Prakash R, Shenoy UV (2005b) Design and evolution of water
networks by source shifts. Chem Eng Sci 60(7):20892093
Puigjaner L, Espuna A, Almato M (2000) A software tool for helping
in decision-making about water management in batch process
industries. Waste Manage 20:645649
Shoaib AM, Aly SM, Awad ME, Foo DCY, El-Halwagi MM (2007)
A hierarchical approach for the synthesis of batch water network.
Comp Chem Eng (in press)
Wang YP, Smith R (1994) Wastewater minimisation. Chem Eng Sci
49:9811006
Wang YP, Smith R (1995a) Wastewater minimization with flowrate
constraints. Trans Inst Chem Eng, Part A 73:889904
Wang YP, Smith R (1995b) Time Pinch Analysis. Trans Inst Chem
Eng, Part A 73:905914
An integrated approach for water minimisation in a PVC manufacturing process 79
123
An integrated approach for water minimisation in a PVC manufacturing processAbstractIntroductionWater cascade analysis techniqueCase study on PVC manufacturing Process simulation modelWater minimisation studyLimiting water data extractionScenario 1: water network without water storage systemScenario 2:water network with water storage system
ConclusionAcknowledgmentReferences
/ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 150 /GrayImageDepth -1 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 600 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile (None) /PDFXOutputCondition () /PDFXRegistryName (http://www.color.org?) /PDFXTrapped /False
/Description >>> setdistillerparams> setpagedevice