an integrated approach for water minimisation in a pvc

13
ORIGINAL PAPER An integrated approach for water minimisation in a PVC manufacturing process Jun Hoa Chan Dominic Chwan Yee Foo Sivakumar Kumaresan Ramlan Abdul Aziz Mohd Ariffin Abu-Hassan Received: 23 July 2007 / Accepted: 12 October 2007 / Published online: 30 November 2007 Ó Springer-Verlag 2007 Abstract This paper presents a water minimisation study carried out for a polyvinyl chloride (PVC) resins manu- facturing plant. Due to the complexity of the mixed batch and continuous polymerisation process, an integrated pro- cess integration approach, which consists of process synthesis, analysis and optimisation was used for this work. A simulation model was first developed in a batch process simulation software, SuperPro Designer V6.0, based on the operating condition of a PVC manufacturing process. The batch simulation model captured the essential information needed for a water minimisation study, e.g. process duration, water mass flow, etc. Data extracted from the simulation model was later used in the water minimisation study, utilising the widely established process synthesis technique of water pinch analysis. Two water saving sce- narios were presented. Scenario 1 reports a fresh water and wastewater reduction of 28.5 and 90.1% respectively, for the maximum water recovery scheme without water stor- age system. In Scenario 2, higher fresh water and wastewater reduction are reported at 31.7 and 100% respectively, when water storage tank is installed in the water network. Keywords Process integration Water minimisation Pinch analysis Process modelling Batch processes Polymer manufacturing Introduction Recent development has seen the shift of the process industries from conventional end-of-pipe waste treatment to more sustainable pollution prevention or waste mini- misation practises. Some of the factors that drive this shift include environmental sustainability and stringent emission legislations, as well as increasing cost of resources and waste treatment. One of the active areas for waste mini- misation activities has been that of in-plant water recovery. The benefits of implementing water recovery are twofold. Apart from the reduction of fresh water (and its associated treatment), smaller volume of wastewater is generated. The seminal work on insight-based techniques for water network synthesis was initiated by Wang and Smith (1994), who presented a two-stage pinch analysis technique for fixed load problems, based on the more generalised mass exchange network synthesis problems (El-Halwagi and J. H. Chan GTC Process Technology (Singapore) Pte. Ltd, 3 Science Park Drive, #01-08/09, The Franklin 118223, Singapore e-mail: [email protected] D. C. Y. Foo (&) School of Chemical and Environmental Engineering, University of Nottingham Malaysia, Broga Road, 43500 Semenyih, Selangor, Malaysia e-mail: [email protected] S. Kumaresan School of Engineering and Information Technology, University Malaysia Sabah, Locked Bag 2073, 88999 Kota Kinabalu, Sabah, Malaysia e-mail: [email protected] R. A. Aziz Chemical Engineering Pilot Plant, Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia e-mail: [email protected] M. A. Abu-Hassan Chemical Engineering Department, Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia e-mail: m.ariffi[email protected] 123 Clean Techn Environ Policy (2008) 10:67–79 DOI 10.1007/s10098-007-0127-2

Upload: ahmed-ali

Post on 25-Nov-2015

18 views

Category:

Documents


3 download

DESCRIPTION

WATER

TRANSCRIPT

  • ORIGINAL PAPER

    An integrated approach for water minimisation in a PVCmanufacturing process

    Jun Hoa Chan Dominic Chwan Yee Foo Sivakumar Kumaresan Ramlan Abdul Aziz Mohd Ariffin Abu-Hassan

    Received: 23 July 2007 / Accepted: 12 October 2007 / Published online: 30 November 2007

    Springer-Verlag 2007

    Abstract This paper presents a water minimisation study

    carried out for a polyvinyl chloride (PVC) resins manu-

    facturing plant. Due to the complexity of the mixed batch

    and continuous polymerisation process, an integrated pro-

    cess integration approach, which consists of process

    synthesis, analysis and optimisation was used for this work.

    A simulation model was first developed in a batch process

    simulation software, SuperPro Designer V6.0, based on the

    operating condition of a PVC manufacturing process. The

    batch simulation model captured the essential information

    needed for a water minimisation study, e.g. process

    duration, water mass flow, etc. Data extracted from the

    simulation model was later used in the water minimisation

    study, utilising the widely established process synthesis

    technique of water pinch analysis. Two water saving sce-

    narios were presented. Scenario 1 reports a fresh water and

    wastewater reduction of 28.5 and 90.1% respectively, for

    the maximum water recovery scheme without water stor-

    age system. In Scenario 2, higher fresh water and

    wastewater reduction are reported at 31.7 and 100%

    respectively, when water storage tank is installed in the

    water network.

    Keywords Process integration Water minimisation Pinch analysis Process modelling Batch processes Polymer manufacturing

    Introduction

    Recent development has seen the shift of the process

    industries from conventional end-of-pipe waste treatment

    to more sustainable pollution prevention or waste mini-

    misation practises. Some of the factors that drive this shift

    include environmental sustainability and stringent emission

    legislations, as well as increasing cost of resources and

    waste treatment. One of the active areas for waste mini-

    misation activities has been that of in-plant water recovery.

    The benefits of implementing water recovery are twofold.

    Apart from the reduction of fresh water (and its associated

    treatment), smaller volume of wastewater is generated.

    The seminal work on insight-based techniques for water

    network synthesis was initiated by Wang and Smith (1994),

    who presented a two-stage pinch analysis technique for

    fixed load problems, based on the more generalised mass

    exchange network synthesis problems (El-Halwagi and

    J. H. Chan

    GTC Process Technology (Singapore) Pte. Ltd,

    3 Science Park Drive, #01-08/09,

    The Franklin 118223, Singapore

    e-mail: [email protected]

    D. C. Y. Foo (&)School of Chemical and Environmental Engineering,

    University of Nottingham Malaysia, Broga Road,

    43500 Semenyih, Selangor, Malaysia

    e-mail: [email protected]

    S. Kumaresan

    School of Engineering and Information Technology,

    University Malaysia Sabah, Locked Bag 2073,

    88999 Kota Kinabalu, Sabah, Malaysia

    e-mail: [email protected]

    R. A. Aziz

    Chemical Engineering Pilot Plant,

    Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia

    e-mail: [email protected]

    M. A. Abu-Hassan

    Chemical Engineering Department,

    Universiti Teknologi Malaysia, 81310 Skudai, Johor, Malaysia

    e-mail: [email protected]

    123

    Clean Techn Environ Policy (2008) 10:6779

    DOI 10.1007/s10098-007-0127-2

  • Manousiouthakis 1989). In the first synthesis stage, limiting

    composite curve is used to locate the minimum fresh water

    and wastewater flowrate targets prior to detailed network

    design (second stage of network synthesis). Flowrate con-

    straints and multiple water sources were considered in their

    later work (Wang and Smith 1995a). The basic concept

    underlying these works is that all processes that use water

    are modelled as mass transfer operations.

    However, later works (e.g. Dhole et al. 1996; Hallale

    2002; Manan et al. 2004) showed that representing all

    processes that use water with mass transfer model might

    not be always adequate. Some processes that use water e.g.

    boiler blowdown, cooling tower make-up and reactor

    effluent are typical examples where water quantity is more

    important than the quality (always termed as fixed flowrate

    problems). New graphical and numerical approaches have

    been later developed to handle the fixed flowrate problems.

    Some promising techniques in locating the minimum water

    targets for the fixed flowrate problems include the graphi-

    cal tools of water surplus diagram (Hallale 2002), material

    recovery pinch diagram (El-Halwagi et al. 2003; Prakash

    and Shenoy 2005a), source composite curve (Bandyopad-

    hyay et al. 2006; Bandyopadhyay 2006) and the improved

    limiting composite curve (Agrawal and Shenoy 2006), as

    well as the numerical targeting tools such as cascade

    analysis techniques (Manan et al. 2004; Almutlaq et al.

    2005; Foo et al. 2006a; Almutlaq and El-Halwagi 2007;

    Foo 2007a, b).

    Apart from the targeting stage, numerous techniques

    have also been proposed for the systematic design of water

    network, i.e. second stage of the synthesis task. This

    includes water grid diagram (Wang and Smith 1994), load

    table (Olesen and Polley 1996, 1997), water main method

    (Kuo and Smith 1998; Castro et al. 1999; Feng and Seider

    2001), water source diagram procedure (Gomes et al. 2007)

    for fixed load problems; as well as source sink mapping

    diagram (El-Halwagi 1997), nearest neighbour algorithm

    (Prakash and Shenoy 2005a) as well as the load problem

    table (Aly et al. 2005) for fixed flowrate problems. Once

    the flowrate targets are established, the water network is

    designed to achieve the minimum targets using any of the

    above-mentioned design tools. Subsequently, a preliminary

    synthesised network can be evolved to yield a simplified

    network (Prakash and Shenoy 2005b; Ng and Foo 2006).

    In contrast to the active evolvement of water network

    synthesis techniques in continuous processes, water mini-

    misation for batch processes has received far less attention

    due to its nature of complexity. Only recently, similar work

    has received considerable attention for batch water net-

    work. Wang and Smith (1995b) initiated the work in batch

    water network synthesis that focused on mass transfer-

    based processes that use water. Majozi et al. (2006)

    developed a similar technique to account for batch

    processes where no water intake and discharge are per-

    mitted during the operation. The shortcoming of both these

    approaches is their limitation in handling fixed load prob-

    lems. To overcome the limitation of the fixed load

    problems, Foo et al. (2005) proposed the use of water

    cascade analysis technique that was originally developed

    for water network for continuous processes (Manan et al.

    2004; Foo et al. 2006a) in handling the fixed flowrate

    problems. Other works on batch water network synthesis

    are mainly dominated by various mathematical optimisa-

    tion approaches (Almato et al. 1997, 1999a, 1999b;

    Puigjaner et al. 2000; Kim and Smith 2004; Li and Chang

    2006; Majozi 2005a, 2005b, 2006; Shoaib et al. 2007).

    It should be noted that most of the reported works on

    batch water network synthesis have utilised hypothetical

    examples for demonstration. To date, limited numbers of

    industrial cases have been reported, in both pinch-based

    and mathematical-based works. This includes production

    of concentrated fruit juice (Almato et al. 1997) and agro-

    chemicals (Majozi et al. 2006). More industrial case studies

    are needed to help in the development of new water min-

    imisation techniques that are of practical use. This is the

    subject of this paper. El-Halwagi (1997) describes that a

    process integration study consists of three elements: i.e.

    process synthesis, analysis and optimisation. In this work,

    an integrated process integration approach has been used.

    The process synthesis element consists of water network

    synthesis, via pinch analysis technique while process

    analysis and optimisation were carried out by batch process

    simulation and modelling studies.

    In the following section, the water cascade analysis

    technique (Manan et al. 2004; Foo et al. 2006a) for locating

    the minimum targets for a water network is first described.

    This is followed by the description of a PVC manufactur-

    ing case study. A simulation model that was developed

    based on the plant operation data is next described. Batch

    process simulation overcomes the constraint of the mixed-

    batch and continuous operation mode in the polymer

    manufacturing process. Data extracted from the simulation

    model are later used in the water minimisation study car-

    ried out using pinch analysis technique.

    Water cascade analysis technique

    The generic water cascade table (WCT) in Table 1 sum-

    marises how WCA is carried out for water targeting in the

    reuse/recycle scheme (Manan et al. 2004; Foo et al. 2006a).

    The first step in conducting a WCA is to locate the various

    water sinks and sources at their respective concentration

    levels. As shown in the first two columns of Table 1, the

    concentration levels (Ck) are arranged in an ascending

    order (k = 1, 2, , n), and the flow of water sink (Fj) and

    68 J. H. Chan et al.

    123

  • source (Fi) are summed at their respective concentration

    level k in columns 3 and 4. Column 5 represents the net

    flow, (RiFi - RjFj) between water sources and sinks ateach concentration level k; with positive indicating surplus,

    negative indicating deficit. Next, the net water flow sur-

    plus/deficit is cascaded down the concentration levels to

    yield the cumulative surplus/deficit flow (FC, k) in column 6

    with an assumed zero fresh water flow (FFW = 0). This

    assumed flow is to facilitate the search for the minimum

    water flow and will later be replaced once the rigorous

    fresh water target is located.

    Two important parameters to fulfil in water network

    targeting are the water flow and impurity load constraints

    (Foo et al. 2006a). Water flow constraints are fulfilled once

    the above-described flow cascading is carried out. The next

    step involves setting up the cumulative impurity load cas-

    cade (Cum. Dm) to fulfil the load constraint. Impurity loadin column 7 (Dmk) is obtained via the product of cumula-tive flow (FC, k) and the concentration difference across

    two subsequent concentration levels (Ck+1 - Ck). Cascad-

    ing the impurity load down the concentration levels of

    column 8 yields the cumulative load (Cum. Dmk), which isessentially the numerical equivalent of graphical targeting

    tool of water surplus diagram (Hallale 2002). A feasible

    water network is characterised by the presence of only

    positive values of Cum. Dm in column 8. A negative Cum.Dmk means the impurity load is transferred from lower tohigher concentration level, which is infeasible. In such a

    case, an interval fresh water flow (FFW, k, column 9) is

    calculated by dividing Cum. Dmk by the concentrationdifference between level k (Ck) and the fresh water con-

    centration (CFW) i.e.,

    FFW;k Cum. DmkCk CFW : 1

    The absolute value of the largest negative FFW, k will then

    replace the earlier assumed zero fresh water flow in the

    cumulative flow (column 6) to obtain a new set of feasible

    flow cascade and hence a feasible load cascade. This new

    fresh water flow represents the minimum fresh water flow

    (FFW) of the network; while the final row in column 6

    represents the wastewater flow (FWW) generated from the

    network. The network pinch concentration is the impurity

    concentration with zero Cum. Dmk, while the water sourcethat exists at the pinch is called the pinch-causing source

    (Manan et al. 2004; Foo et al. 2006a). Note that once the

    flow and impurity load cascading are carried out using the

    minimum fresh water flow, the final column of Table 1 is

    omitted.

    The above-described procedure for locating the mini-

    mum water targets was original developed for water

    networks operated in continuous mode (Manan et al. 2004;

    Foo et al. 2006a), in which water flowrate is used instead of

    water flow. Foo et al. (2005) later extended the targeting

    tool for batch water network known as time-dependent

    water cascade analysis. By segregating water sinks and

    sources into the time interval when they exist, cascade

    analysis is carried out in each time interval to locate the

    minimum water targets. More recently, the targeting

    technique was extended to multiple fresh resources (Foo

    2007a) and threshold (Foo 2007b) problems.

    Case study on PVC manufacturing

    Figure 1 shows the process flow diagram for PVC resins

    manufacture. It consists of ten parallel batch polymerisa-

    tion reactors, blow-down vessel, and two parallel trains of

    downstream processing equipment. Each downstream

    processing train consists of a stripper, two decanters and a

    fluid bed dryer. The plant is operated in a semi-batch mode

    where upstream polymerisation reactors are scheduled to

    match the downstream processing trains that are operated

    in continuous mode. The polymerisation process is carried

    Table 1 The generic water cascade table (WCT)

    k Ck RjFj RiFi RiFi - RjFj FC,k Dmk Cum. Dmk FFW,k

    FFW

    k Ck (RjFj)k (RiFi)k (RiFi - RjFj)kFC,k Dmk

    k + 1 Ck+1 (RjFj)k+1 (RiFi)k+1 (RiFi - RjFj)k+1 Cum. Dmk+1 FFW,k+1FC,k+1 Dmk+1

    ..

    . ... ..

    . ... ..

    . ... ..

    . ... ..

    .

    n - 2 Cn-2 (RjFj)n-2 (Ri Fi)n-2 (RiFi - RjFj)n-2FC,n-2 Dn-2

    n - 1 Cn-1 (RjFj)n-1 (RiFi)n-1 (RiFi -Rj Fj) n-1 Cum. Dm n-1 FFW,n-1FC,n-1 = FWW Dmn-1

    n Cn Cum. Dmn FFW,n

    An integrated approach for water minimisation in a PVC manufacturing process 69

    123

  • out subsequently in ten parallel batch reactors. Raw

    materials for the polymerisation process include deminer-

    alised water, mixture of fresh vinyl chloride monomer

    (VCM) and recycled VCM (mainly from blowdown vessel

    and stripper), initiators and suspending agents, which are

    charged into the reactor in sequence.

    The suspending agent is diluted to approximately

    4.0 wt% and is charged into the reactor together with

    demineralised water. This is mainly due to the high vis-

    cosity of the suspending agent solution. Upon completion

    of the suspending agent charge, primary and secondary

    initiators are added into the reactor. It shall also be noted

    that, due to piping constraints, demineralised water can

    only be charged into the reactors one at a time. Charging

    procedure in each of the reactor will only start after the end

    of charging in an earlier reactor. The same situation occurs

    to the charging of VCM and the blowdown operation after

    the reaction ends.

    Upon completion of water charge, the reactor is purged

    by nitrogen and then vacuumed before charging of VCM is

    commenced. This is to ensure that no oxygen is present in

    the reactor, as reaction between VCM and oxygen might

    result in an explosion. Upon the completion of VCM

    charge, heating is commenced to raise the reactor to the

    operating temperature and pressure. Exothermic polymer-

    isation process next commences for a duration of 7.5 h.

    Continuous cooling is needed to remove excess heat and to

    maintain the reactor temperature. A huge amount of chilled

    water is added towards the end of the polymerisation

    process to maintain the reactor temperature. PVC polymer

    is the main product at the end of the polymerisation pro-

    cess. Other by-products of the reaction are the unreacted

    VCM, initiators, suspending agent and some trace amount

    of contaminant. The final reactor content is in slurry form

    (mainly consists of PVC and water).

    The blowdown vessel receives batches of slurry, which

    are intermittently discharged from the reactors. The

    blowdown vessel acts as buffer storage so that slurry can be

    continuously fed to the two parallel downstream processing

    trains. As the slurry enters the blowdown vessel, the major

    portion of the unreacted VCM trapped in the PVC particles

    flashes off and is vented to the gas holder for recovery. The

    VCM vapour is next compressed and condensed into liquid

    form before it is sent for reuse in the polymerisation

    reactors.

    As the effluent from the blowdown vessel enters the

    downstream processing trains, the stripper column further

    removes the unreacted VCM from the PVC slurry. Steam is

    introduced at the base of the stripping column and the

    VCM is removed as an overhead product to the gas holder.

    The stripped slurry is then directed to two parallel

    decanters for water removal. Approximately 80% of water

    is removed by these decanters from the PVC slurry. Wet

    cake from the decanters is dried in the fluidised bed dryer.

    Dried PVC resins are transported to the shifter. Fine resins

    that pass through the shifter are sold as product, while the

    course resins are ground and sold as low-grade resins.

    Process simulation model

    Figure 2 shows the base case process simulation model that

    has been developed based on the operating condition of the

    PVC manufacturing process using SuperPro Designer V6.0

    (Intelligen 2005). The annual operating time of the process

    model is taken as 7920 h. In the modelling environment of

    SuperPro Designer, a few operations take place sequen-

    tially in a single unit procedure (Intellegen 2005). For

    instance, vessel procedure P-1 in Fig. 2 is used to model

    the batch polymerisation procedure that takes place in

    vessel K-207A. The polymerisation procedure consists of

    sequential operations of raw material charges, vacuum

    operation, material heating, polymerisation as well as

    product blowdown. The modelling of these single opera-

    tions is described next.

    The raw material charged into the reactor during the

    start of procedure P-1 includes demineralised water

    (CHARGE-H2O), suspending agent (CHARGE-PVA),

    primary initiator (CHARGE-Init1) and secondary initiator

    (CHARGE-Init2). Note that the model was developed

    based on the operating condition of the manufacturing

    process, where the charging of demineralised water for a

    subsequent reactor is scheduled to start after the water

    charging of the preceding reactor ends. Suspending agent

    and initiators are charged into the reactor during the

    charging of water.

    The vacuum operations (VACUUM) in procedure P-1

    include a vacuum air purge, followed by a nitrogen gas

    purge and finally another vacuum purge. The vacuum

    operations were carried out before the charging of VCM

    (CHARGE-VCM), to avoid the mixing of VCM with air,

    which will lead to explosion.

    delcyceRMCV

    redloHsaGrosserpmoCresnednoC

    srotcaeRhctaB)stinU01(

    nwodwolBlesseV

    yrrulSreppirtS

    retnaceDreyrD

    derevoceRruopavMCV

    CVPsniseR

    maetS

    hserFMCV

    riatoH

    retfihS

    Fig. 1 Process flow diagram of a PVC manufacturing plant

    70 J. H. Chan et al.

    123

  • During the heating operation, hot water is used to raise

    the reactor temperature (HEAT-1) to 60C where thepolymerisation process (REACT-1) is carried out. The

    polymerisation reaction operation takes an overall duration

    of 7.5 h. Chilled water is added to the reactor (CHARGE-

    Chilled H2O) in the last half-an-hour just before the

    polymerisation reaction ends. Stoichiometric reaction

    model is used and the reaction stoichiometric is defined as

    the conversion of one mass of VCM to one mass of PVC,

    as follows:

    nVCM ! PVCn: 2Upon the completion of the polymerisation process, the

    slurry reactor content is discharged (TRANS-OUT) to the

    blowdown procedure P-14 (in vessel V-101). Similar to the

    case of demineralised water charge, blowdown operation of

    a subsequent reactor is also scheduled to start after the

    completion of a preceding reactor, due to the piping con-

    straint in the PVC plant. The last operation in the vessel

    procedure is the cleaning process. The scheduling summary

    for all reaction procedures (P-1 to P-10) is displayed in the

    process Gantt chart as shown in Fig. 3.

    From the blowdown vessel, the slurry product enters

    into two parallel identical and continuous downstream

    processing trains, which individually consist of a stripper,

    slurry tank, two parallel identical decanters and a fluid-bed

    dryer. Thus, no scheduling is needed in these processes.

    The modelling specifications of each unit procedure in

    these downstream processing trains are next described.

    Stripper procedures (P-16 and P-17) are used for VCM

    removal. Steam at 110C is introduced into the strippers toachieve a VCM removal of 99.9%, before the PVC slurry

    enters into two parallel identical decanters (P-18 and P-19,

    each represents two identical decanters). Solid removal in

    the decanters is specified as 99% for PVC, with water loss

    of 21%. Effluent emits from these decanter units (WW A-D)

    is the main wastewater of the process, while the wet filter

    cake is sent to fluidised-bed dryers for moisture removal. In

    the fluidised-bed dryers (P-20 and P-21), hot air at 95C isused to dry the wet filter cake. Evaporation rate of water and

    the final solid temperature are set at 916 kg H2O/h and 60Crespectively. As a result, 99.8% of the moisture (the com-

    ponent of water and chilled water) is removed.

    From the simulation model, the minimum cycle time for

    the process is determined to be 11.78 h corresponds to the

    completion of the last reactor (P-10/K-207J). Based on the

    annual operating time of 7,920 h, this translates into 671

    batches/year. It should also be noted that all vessel pro-

    cedures (P-1 to P-10) are observed to have different cycle

    times (see Gantt chart in Fig. 3). This is mainly due to the

    scheduling of the TRANS-OUT operations in each of the

    reactor procedures (P-1 to P-10). Since TRANS-OUT

    operation in each of the reactor is scheduled to start after

    the TRANS-OUT operation of the preceding reactor ends,

    this creates a lag time for the product to be discharged from

    the subsequent reactor before the preceding reactor com-

    pletes its TRANS-OUT operation. A good example is

    shown in Fig. 3. As shown, the polymerisation reaction

    Fig. 2 Simulation flowsheet of PVC manufacturing

    An integrated approach for water minimisation in a PVC manufacturing process 71

    123

  • (REACT-1) in P-2/K-207B is completed at 9.62 h. How-

    ever, due to the TRANS-OUT operation of P-1/K-207A

    being still in operation, TRANS-OUT operation in P-2/K-

    207B cannot be started until the TRANS-OUT operation in

    P-1/K-207A ends at 9.78 h.

    Water minimisation study

    This section presents water minimisation study carried out

    for the PVC manufacturing process. Figure 4 shows the

    water usage diagram for the process. This includes the PVC

    manufacturing as well as the utility sections.

    As shown in Fig. 4, the process receives fresh water

    supply from the state water supplier. Since the PVC man-

    ufacturing process requires feed water that is free of

    hardness, the fresh water is further treated in a deionised

    plant (DI plant). Feed water to the utility section (boiler

    and cooling tower make-up) and general cleaning purposes

    tolerate a lower quality of water, and hence treatment in the

    DI plant has been avoided.

    The only water source for the process originates from

    the continuous discharge of the four parallel decanters

    (WW A-D), which are used to dewater the slurry effluent

    from the strippers. The total flowrate of these water sources

    are determined to be 9,243.9 kg/h. Since the four water

    sources have the same characteristics, they are treated as a

    single water source. The main impurity that is of concern

    for water reuse/recycling activity is the suspended solid

    content in the wastewater at a concentration of 50 ppm.

    Water sinks that are considered for water reuse/recycle

    include the PVC manufacturing process (mainly for reactor

    feed), utility section (boiler and cooling tower make-up)

    and miscellaneous usage (e.g. floor cleaning, etc.).

    Limiting water data extraction

    Data extraction is considered to be the most essential step

    of a water minimisation study. Incorrect extraction of data

    leads to sub-optimal water network with reduced water

    saving targets (Foo et al. 2006b). For a batch water net-

    work, apart from the limiting water flow and concentration,

    the occurrences of the processes that use water are to be

    identified. In this work, the start and end time as well as the

    duration for each processes that use water are identified

    with the aid of the base case simulation model.

    Table 2 summarises the limiting data for a single batch

    of polymerisation process. However, if one were to use this

    set of limiting data for the analysis, one may lose the

    greater water saving potential. This is because the raw data

    extracted from the simulation study does not reflect how

    the batch polymerisation process are carried out in actual

    operation. For most industrial batch processes, the

    Fig. 3 Process Gantt chart for base case simulation

    72 J. H. Chan et al.

    123

  • operations are repeated (as cyclic mode) once the equip-

    ment has completed its earlier operation. Figure 5 shows

    such a situation, where three consequent batches of pro-

    cesses occur simultaneously within the time frame of a

    single batch N. As shown, batch (N - 1) completed its

    operations after 4.5 h batch N commences its operation;

    while batch (N + 1) begins its operations 4.5 h before

    batch N ends. The revised limiting data is summarised in

    Table 3.

    It should also be noted that some operations in Fig. 5

    and Table 3 are carried out in sequence. For instance,

    reactor feed operation (SK1) for one reactor takes 20 min

    to complete (CHARGE-H2O as in Fig. 3), hence a total of

    200 min or 3.33 h would be needed for 10 reactors to

    complete their reactor feed operations carried out

    subsequently (Fig. 5). The same situation occurs to line

    flushing (SK2), reactor cleaning (SK5) and flushing (SK7),

    in which each individual operation for each reactor takes

    0.5 h to complete.

    Two water saving scenarios with and without water

    storage system were analysed using the time-dependent

    water cascade analysis technique (Foo et al. 2005). The

    first stage of the analysis corresponds to the allocation of

    the water sinks and sources in their respective time inter-

    vals. The time interval table in Table 4 is utilised for this

    preliminary analysis. As shown, there are 13 time intervals

    and all water sinks are located in their respective time

    intervals according to their occurrence time. The sum of

    the individual water flow of the water sinks gives the total

    water requirement of each time interval. The flowrate of

    rotcaeR

    tekcaJ

    ydaetSgniraeB

    relioB

    gnilooCrewoT

    retaWtoHknaT

    rellihC

    eruPretaW

    knaT wolBnwod

    reppirtS yrrulSknaT

    retnaceD

    reyrDmaetS

    etasnednoC

    retaWtoHnoitalucriC

    retaWgnilooCnoitalucriC

    retaWtoHnoitalucriC

    slacimehC

    slacimehC

    deeFrotcaeR

    gnihsulF

    dellihCretaW

    gnihsulF

    nihsulFeniL g

    slacimehC

    gniraeBydaetSotretaW

    pUekaMrewoTgnilooC

    puekamrelioBetaw r

    retaWretliF

    deretliFretaW

    knaT

    .I.DtnalP

    riAretaeH

    riAtoH

    riAdloC

    )gnihsulFlaunaM(egasusuoenallecsiM

    retaWtoHknaT

    maetS

    )gnihsaWroolF(egasusuoenallecsiMretawhserF

    gninaelCrotcaeR

    maetS

    gnihsulF

    sniseRCVP

    retawetsaW

    Fig. 4 Water usage diagram

    Table 2 Raw data extracted from base case simulation

    Sinks Operation Flowrate Concentration Start time End time Mass flow

    SKj (kg/h) Cj (ppm) tS (h) tT (h) Fj (kg)

    1 Reactor feed 31,531.53 10 0 3.33 105,000

    2 Line flushing 3,125.00 10 9.28 14.28 15,625

    3 Boiler make-up 1 13,200.00 10 0 0.25 3,300

    4 Boiler make-up 2 13,200.00 10 8 8.25 3,300

    5 Reactor cleaning 1,200 20 9.78 14.78 6,000

    6 Cooling tower 6,300.00 50 0 14.78 93,114

    7 Flushing 2,000.00 200 9.28 14.28 10,000

    8 Floor cleaning 1 6,000.00 500 0 0.25 1,500

    9 Floor cleaning 2 6,000.00 500 8 8.25 1,500

    RjSKj 82,556.53 239,339

    Sources Operation Flowrate Concentration Start time End time Mass flow

    SRi (kg/h) Ci (ppm) tS (h) tT (h) Fi (kg)

    RjSRi Decanter 9,243.90 50 0 14.78 136,625

    An integrated approach for water minimisation in a PVC manufacturing process 73

    123

  • the continuous water source (SR1 from decanter) is also

    scaled according to the duration of each time interval. Both

    water saving scenarios are analysed as follows.

    Scenario 1: water network without water storage system

    In Scenario 1, no water storage tank is installed for the batch

    water network. Hence, water saving can only be carried out

    via direct integration, i.e. when both water sinks and sources

    present together within the same time interval.

    Table 5 shows two examples of flow targeting for time

    interval 00.25 h and 9.289.78 h. Due to the overlapping

    between two consequent batches, water sinks from the

    earlier batch (SK2, SK5, SK6 and SK7) and current batch

    (SK1, SK3, SK6 and SK8) operations are observed

    between 0 and 0.25 h. The water source for this interval is

    available at 2,311 kg and 50 ppm ( column 3 in Table 4).

    Without considering for water reuse/recycle, this interval

    requires 17,414 kg of fresh water and generates 2,311 kg

    of wastewater. As shown in Table 5, maximum water

    recovery enables the fresh water (FFW) to be reduced to

    15,103 kg and wastewater is completely eliminated

    (FWW = 0 kg). Another characteristic to be noted in

    Table 5 is that water targeting this time interval exhibits a

    threshold problem. Hence, flow adjustment is needed for

    the flow cascade, as reflected in the adjusted cumulative

    flow (Adj. FC) column in Table 5. Detailed description for

    the threshold problem is outlined in Foo (2007b).

    1

    368

    1

    3

    6

    8

    2

    567

    2

    45

    7

    hctaB N

    hctaB (N 1+ )

    hctaB (N 1 )

    0 5 01 51(hctaB N strats)1+rh82.01tanoitarepo

    (hctaB N sdne)1rh5.4tanoitarepo0 5 01 51

    rh87.41=emitelcychctaB

    9

    Fig. 5 The overlap of three consequent batches of polymerisationprocesses (only water sinks are shown)

    Table 3 Limiting data that takes into consideration repeated batch processes

    Number of

    batches

    Sinks SKj Operation Flowrate

    (kg/h)

    Concentration

    Cj (ppm)Start time

    tS (h)End time

    tT (h)Mass flow

    Fj (kg)

    N - 1 2a Line flushing 3,125.00 10 0 4 12,500

    5a Reactor cleaning 1,200 20 0 4.5 5,400

    6a Cooling tower 6,300.00 50 0 4.5 28,350

    7a Flushing 2,000.00 200 0 4 8,000

    1b Reactor feed 31,531.53 10 0 3.33 105,000

    2b Line flushing 3,125.00 10 9.28 14.28 15,625

    3b Boiler make-up 1 13,200.00 10 0 0.25 3,300

    4b Boiler make-up 2 13,200.00 10 8.00 8.25 3,300

    N 5b Reactor cleaning 1,200 20 9.78 14.78 6,000

    6b Cooling tower 6,300.00 50 0 14.78 93,114

    7b Flushing 2,000.00 200 9.28 14.28 10,000

    8b Floor cleaning 1 6,000.00 500 0 0.25 1,500

    9b Floor cleaning 2 6,000.00 500 8.00 8.25 1,500

    1c Reactor feed 31,531.53 10 10.28 13.61 105,000

    N + 1 3c Boiler make-up 1 13,200.00 10 10.28 10.53 3,300

    6c Cooling tower 6,300.00 50 10.28 14.78 28,350

    8c Floor cleaning 1 6,000.00 500 10.28 10.53 1,500

    RjSKj 152,213 431,739

    Sources SKi Operation Flowrate (kg/h) Concentration Ci (ppm) Start time tS (h) End time tT (h) Mass flow Fi (kg)

    Continuous 1 Decanter 9,243.90 50 0 14.78 136,625

    RjSKi 9,243.90 136,625

    74 J. H. Chan et al.

    123

  • Table 4 Time interval table for case study on PVC manufacturing

    SKj Flowrate (kg/h) Start time, tS (h)

    0 0.25 3.33 4 4.5 8 8.25 9.28 9.78 10.28 10.53 13.61 14.28

    2a 3,125 781 9,625 2,094

    5a 1,200 300 3,696 804 600

    6a 6,300 1,575 19,404 4,221 3,150

    7a 2,000 500 6,160 1,340

    1b 31,532 7,883 97,117

    2b 3,125 1,563 1,563 781 9,625 2,094

    3b 13,200 3,300

    4b 13,200 3,300

    5b 1,200 600 300 3,696 804 600

    6b 6,300 1,575 19,404 4,221 3,150 22,050 1,575 6,489 3,150 3,150 1,575 19,404 4,221 3,150

    7b 2,000 1,000 1,000 500 6,160 1,340

    8b 6,000 1,500

    9b 6,000 1,500

    1c 31,532 7,883 97,117

    3c 13,200 3,300

    6c 6,300 1,575 19,404 4,221 3,150

    8c 6,000 1,500

    SRi Flowrate

    1 9,244 2,311 28,471 6,193 4,622 32,354 2,311 9,521 4,622 4,622 2,311 28,471 6,193 4,622

    Table 5 Cascade analysis for water flow targeting (00.25 h)

    Ci(ppm)

    RjFj(kg)

    RiFi(kg)

    RiFi - RjFj(kg)

    FC(kg)

    Dm(mg)

    Cum. Dm(mg)

    FFW,k(kg)

    FC(kg)

    Adj. FC(kg)

    Dm(mg)

    Cum. Dm(mg)

    0

    0 15,102 FFW = 15,103 151,032

    10 11,964 -11,964 151,032

    -11,964 -119,641 3,138 3139 31,390

    20 300 -300 -119,641 -5,982 182,422

    -12,264 -367,924 2,838 2839 85,171

    50 3150 2,311 -839 -487,565 -9,751 267,593

    -13,103 -1,965,474 1,999 2000 300,000

    200 500 -500 -2,453,039 -12,265 567,593

    -13,603 -4,080,947 1,499 1500 450,000

    500 1,500 -1,500 -6,533,986 -13,068 1,017,593

    -15,103 -15,095,605,921 -1 FWW = 0 0

    1,000,000 -15,102,139,907 -15,102 1,017,593

    Table 6 Cascade analysis for water flow targeting (9.289.78 h)

    Ci(ppm)

    RjFj(kg)

    RiFi(kg)

    RiFi - RjFj(kg)

    FC(kg)

    Dm(mg)

    Cum. Dm(mg)

    FFW,k(kg)

    FC(kg)

    Dm(mg)

    Cum. Dm(mg)

    0

    0 FFW = 1,250 12,500

    10 1,563 -1,563 12,500

    -1,563 -15,625 -313 -3,125

    20 0 -15,625 -781 9,375

    -1,563 -46,875 -313 -9,375

    50 3,150 4,622 1,472 -62,500 -1,250 0

    -91 -13,583 1,159 173,918 (PINCH)

    200 1,000 -1,000 -76,083 -380 173,918

    -1,091 -327,165 159 47,835

    500 0 -403,248 -806 221,753

    -1,091 -1,090,004,725 FWW = 159 159,370,275

    1,000,000 -1,090,407,973 -1,090 159,592,028

    An integrated approach for water minimisation in a PVC manufacturing process 75

    123

  • Ta

    ble

    7M

    inim

    um

    flo

    wta

    rget

    ing

    for

    Sce

    nar

    io1

    :w

    ith

    ou

    tw

    ater

    sto

    rag

    e

    0

    0.2

    5h

    0.2

    5

    3.3

    3h

    3.3

    3

    4.0

    0h

    4.0

    0

    4.5

    0h

    4.5

    0

    8.0

    0h

    8.0

    0

    8.2

    5h

    8.2

    5

    9.2

    8h

    Ci

    (pp

    m)

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    (a)

    0

    9.2

    8h

    0

    15

    ,10

    31

    26

    ,93

    56

    ,48

    62

    ,27

    80

    4,0

    64

    0

    10

    -1

    1,9

    64

    -1

    06

    ,74

    2-

    2,0

    94

    00

    -3

    ,30

    00

    3,1

    39

    20

    ,19

    34

    ,39

    32

    ,27

    80

    76

    40

    20

    -3

    00

    -3

    ,69

    6-

    80

    4-

    60

    00

    00

    2,8

    39

    16

    ,49

    73

    ,58

    91

    ,67

    80

    76

    40

    50

    -8

    39

    -1

    0,3

    37

    -2

    ,24

    9-

    1,6

    78

    10

    ,30

    47

    36

    3,0

    32

    2,0

    00

    6,1

    60

    1,3

    40

    01

    0,3

    04

    1,5

    00

    3,0

    32

    20

    0-

    50

    0-

    6,1

    60

    -1

    ,34

    00

    00

    0

    1,5

    00

    00

    01

    0,3

    04

    1,5

    00

    3,0

    32

    50

    0-

    1,5

    00

    00

    00

    -1

    ,50

    00

    00

    00

    10

    ,30

    40

    3,0

    32

    1,0

    00

    ,00

    0

    9.2

    8

    9.7

    8h

    9.7

    8

    10

    .28

    h1

    0.2

    8

    0.5

    3h

    10

    .53

    1

    3.6

    1h

    13

    .61

    1

    4.2

    8h

    14

    .28

    1

    4.7

    8h

    Ci

    (pp

    m)

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    (b)

    9.2

    8

    14

    .78

    h

    0

    1,2

    50

    1,6

    90

    15

    ,10

    31

    26

    ,93

    56

    ,48

    62

    ,27

    8R

    FF

    W=

    30

    8,6

    09

    10

    -1

    ,56

    3-

    1,5

    63

    -1

    1,9

    64

    -1

    06

    ,74

    2-

    2,0

    94

    0

    -3

    13

    12

    83

    ,13

    92

    0,1

    93

    4,3

    93

    2,2

    78

    20

    0-

    60

    0-

    30

    0-

    3,6

    96

    -8

    04

    -6

    00

    -3

    13

    -4

    72

    2,8

    39

    16

    ,49

    73

    ,58

    91

    ,67

    8

    50

    1,4

    72

    1,4

    72

    -8

    39

    -1

    0,3

    37

    -2

    ,24

    9-

    1,6

    78

    1,1

    59

    1,0

    00

    2,0

    00

    6,1

    60

    1,3

    40

    0

    20

    0-

    1,0

    00

    -1

    ,00

    0-

    50

    0-

    6,1

    60

    -1

    ,34

    00

    15

    90

    1,5

    00

    00

    0

    50

    00

    0-

    1,5

    00

    00

    0

    15

    90

    00

    00

    RF

    WW

    =1

    3,4

    95

    1,0

    00

    ,00

    0

    76 J. H. Chan et al.

    123

  • Ta

    ble

    8M

    inim

    um

    flo

    wta

    rget

    ing

    for

    Sce

    nar

    io2

    :w

    ith

    wat

    erst

    ora

    ge

    0

    0.2

    5h

    0.2

    5

    3.3

    3h

    3.3

    3

    4.0

    0h

    4.0

    0

    4.5

    0h

    4.5

    0

    8.0

    0h

    8.0

    0

    8.2

    5h

    8.2

    5

    9.2

    8h

    Ci

    (pp

    m)

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    (a)

    0

    9.2

    8h

    0

    15

    ,10

    31

    26

    ,93

    56

    ,48

    62

    ,27

    80

    26

    40

    0

    10

    -1

    1,9

    64

    -1

    06

    ,74

    2-

    2,0

    94

    00

    -3

    ,30

    00

    3,1

    39

    20

    ,19

    34

    ,39

    32

    ,27

    80

    -6

    60

    .00

    0

    20

    -3

    00

    -3

    ,69

    6-

    80

    4-

    60

    00

    00

    2,8

    39

    16

    ,49

    73

    ,58

    91

    ,67

    80

    -6

    60

    .00

    0

    50

    -8

    39

    -1

    0,3

    37

    -2

    ,24

    9-

    1,6

    78

    10

    ,30

    47

    36

    3,0

    32

    2,0

    00

    6,1

    60

    1,3

    40

    00

    15

    00

    .00

    0

    20

    0-

    50

    0-

    6,1

    60

    -1

    ,34

    00

    00

    0

    1,5

    00

    00

    00

    15

    00

    .00

    0

    50

    0-

    1,5

    00

    00

    00

    -1

    ,50

    00

    00

    00

    00

    .00

    0

    1,0

    00

    ,00

    0

    FS

    T0

    00

    01

    0,3

    04

    -1

    ,42

    43

    ,03

    2

    9.2

    8

    9.7

    8h

    9.7

    8

    10

    .28

    h1

    0.2

    8

    10

    .53

    h1

    0.5

    3

    13

    .61

    h1

    3.6

    1

    14

    .28

    h1

    4.2

    8

    14

    .78

    h

    Ci

    (pp

    m)

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    RiF

    i-

    RjF

    j

    (kg

    )

    FC

    (kg

    )

    (b)

    9.2

    8

    14

    .78

    h

    0

    1,2

    50

    16

    10

    98

    51

    12

    0,1

    96

    6,4

    86

    2,2

    78

    RF

    FW

    =2

    95

    ,11

    4

    10

    -1

    ,56

    3-

    1,5

    63

    -1

    1,9

    64

    -1

    06

    ,74

    2-

    2,0

    94

    0

    -3

    13

    48

    -2

    11

    31

    3,4

    54

    4,3

    93

    2,2

    78

    20

    0-

    60

    0-

    30

    0-

    3,6

    96

    -8

    04

    -6

    00

    -3

    13

    -5

    53

    -2

    41

    39

    ,75

    83

    ,58

    91

    ,67

    8

    50

    1,4

    72

    1,4

    72

    -8

    39

    -1

    0,3

    37

    -2

    ,24

    9-

    1,6

    78

    1,0

    00

    10

    00

    20

    00

    6,1

    60

    1,3

    40

    0

    20

    0-

    1,0

    00

    -1

    ,00

    0-

    50

    0-

    6,1

    60

    -1

    ,34

    00

    00

    15

    00

    00

    0

    50

    00

    0-

    1,5

    00

    00

    0

    00

    00

    00

    RF

    WW

    =0

    1,0

    00

    ,00

    0

    FS

    T1

    59

    -8

    1-

    5,2

    52

    -6

    ,73

    90

    0

    An integrated approach for water minimisation in a PVC manufacturing process 77

    123

  • On the other hand, only three water sinks from current

    operation are observed between 9.28 and 9.78 h (observed

    from Table 4). As shown in Table 6, targeting for this time

    interval yields fresh water and wastewater flows of 1,250

    and 159 kg, respectively, with a pinch concentration

    observed at 50 ppm.

    Similar water flows targeting were carried out for all

    other time intervals, and the summary is shown in Table 7

    (only net water flow and cumulative flow are shown). The

    final column of Table 7 shows that the total fresh water and

    wastewater flows for the network are determined to be

    308,609 and 13,495 kg respectively. This corresponds to a

    reduction of 28.5% fresh water and 90.1% of wastewater,

    compared to current water network without any water

    reuse/recycle practice.

    Scenario 2:water network with water storage system

    In Scenario 1, due to the absence of a water storage tank,

    wastewater are discharged at certain time intervals without

    being further utilised. This includes time intervals of 4.50

    8.00, 8.259.28 and 9.289.78 h. By utilising a water

    storage tank, wastewater at these time intervals may be

    stored for further usage at time intervals that exhibit water

    deficit. Table 8 shows how this indirect integration scheme

    is materialised. The last row of Table 8 displays the water

    flow (FST) that enters or leaves the water storage. As

    shown, water is stored between intervals that generate

    wastewater (given as positive FST value) and utilised at

    other intervals (given as negative FST value) to reduce their

    fresh water demand. As such, the fresh water flow is

    reduced to 295,114 kg (31.7% reduction), while wastewa-

    ter flow is completely removed. A cumulative water mass

    chart is shown in Fig. 6, indicating that a tank with a

    capacity of 12 tons is needed to achieve the maximum

    water recovery as in Scenario 2. The flow sheet for the final

    water reuse/recycling scheme is shown in Fig. 7.

    Fig. 6 Cumulative mass in water storage tank

    Fig. 7 Flow sheet after water reuse/recycling

    78 J. H. Chan et al.

    123

  • The decision as to which scenarios would be imple-

    mented eventually will rely on the decision of the plant

    authority after a detailed economic assessment of each

    scenario, which is beyond the scope of this work.

    Conclusion

    A water minimisation scheme was developed for a PVC

    manufacturing case study. An integrated approach that

    consists of process synthesis, analysis and optimisation

    steps was utilised to identify the true minimum water tar-

    gets for the water network that is operated in mixed batch

    and in continuous mode. Two water saving scenarios were

    presented to analyse the maximum water saving potential

    of the process.

    Acknowledgment The technical assistance of Mr. Yoeng CheeNyok is gratefully acknowledged.

    References

    Agrawal V, Shenoy UV (2006) Unified conceptual approach to

    targeting and design of water and hydrogen networks. AIChE J

    52(3):10711081

    Almato M, Sanmart E, Espuna A, Puigjaner L (1997) Rationalizing

    the water use in the batch process industry. Comput Chem Eng

    21:S971S976

    Almato M, Espuna A, Puigjaner L (1999a) Optimisation of water use

    in batch process industries. Comp Chem Eng 23:14271437

    Almato M, Sanmat E, Espuna A, Puigjaner L (1999b) Economic

    optimization of the water reuse network in batch process

    industries. Comput Chem Eng 23:S153S156

    Almutlaq AM, Kazantzi V, El-Halwagi MM (2005) An algebraic

    approach to targeting waste discharge and impure fresh usage via

    material recycle/reuse networks. Clean Technol Environ Policy

    7(4):294305

    Almutlaq AM, El-Halwagi MM (2007) An algebraic targeting

    approach to resource conservation via material recycle/reuse.

    Int J Environ Poll 29(1/2/3):418

    Aly S, Abeer S, Awad M (2005) A new systematic approach for water

    network design. Clean Technol Environ Policy 7(3):154161

    Bandyopadhyay S, Ghanekar MD, Pillai HK (2006) Process water

    management. Ind Eng Chem Res 45:52875297

    Bandyopadhyay S (2006) Source composite curve for waste reduc-

    tion. Chem Eng J 125:99110

    Castro P, Matos H, Fernandes MC, Nunes CP (1999) Improvements

    for mass-exchange networks design. Chem Eng Sci 54:1649

    1665

    Dhole VR, Ramchandani N, Tainsh RA, Wasilewski M (1996) Make

    your process water pay for itself. Chem Eng 103:100103

    El-Halwagi MM, Manousiouthakis V (1989) Synthesis of mass

    exchange networks. AIChE J 35(8):12331244

    El-Halwagi MM (1997) Pollution prevention through process inte-

    gration: systematic design tools. Academic Press, San Diego

    El-Halwagi MM, Gabriel F, Harell D (2003) Rigorous graphical

    targeting for resource conservation via material recycle/reuse

    networks. Ind Eng Chem Res 42:43194328

    Feng X, Seider WD (2001) New structure and design method for

    water networks. Ind Eng Chem Res 40:61406146

    Foo DCY, Manan ZA, Tan YL (2005) Synthesis of maximum water

    recovery network for batch process systems. J Clean Prod

    13(15):13811394

    Foo DCY, Manan ZA, Tan YL (2006a) Use cascade analysis to

    optimize water networks. Chem Eng Prog 102(7):4552

    Foo DCY, Manan ZA, El-Halwagi MM (2006b) Correct identification

    of limiting water data for water network synthesis. Clean

    Technol Environ Policy 8(2):96104

    Foo DCY (2007a) Water cascade analysis for single and multiple

    impure fresh water feed. Chem Eng Res Des 85(A8):11691177

    Foo DCY (2007b) Flowrate targeting for threshold problems and

    plant-wide integration for water network synthesis. J Environ

    Manage (in press)

    Gomes JFS, Queiroz EM, Pessoa FLP (2007) Design procedure for

    water/wastewater minimization: single contaminant. J Clean

    Prod 15:474485

    Hallale N (2002) A new graphical targeting method for water

    minimisation. Adv Environ Res 6(3):377390

    Intelligen Inc. (2005) SuperPro Designer1 users guide. Intelligen

    Inc., Scotch Plains, New Jersey

    Kim J-K, Smith R (2004) Automated design of discontinuous water

    systems. Trans Inst Chem Eng, Part B 82(B3):238248

    Kuo W-CJ, Smith R (1998) Designing for the interactions between

    water use and effluent treatment. Trans Inst Chem Eng, Part A,

    287301

    Li BH, Chang C (2006) A mathematical programming model for

    discontinuous water-reuse system design. Ind Eng Chem Res

    45:50275036

    Majozi T, Brouckaert CJ, Buckley CA (2006) A graphical technique

    for wastewater minimisation in batch processes. J Environ

    Manage 78:317329

    Majozi T (2005a) Wastewater minimisation using central reusable

    water storage in batch plants. Comp Chem Eng 29:16311646

    Majozi T (2005b) An effective technique for wastewater minimisa-

    tion in batch processes. J Clean Prod 13(15):13741380

    Majozi T (2006) Storage design for maximum wastewater reuse in

    multipurpose batch plants. Ind Eng Chem Res 45:59365943

    Manan ZA, Tan YL, Foo DCY (2004) Targeting the minimum water

    flowrate using water cascade analysis technique. AIChE J

    50(12):31693183

    Ng DKS, Foo DCY (2006) Evolution of water network with improved

    source shift algorithm and water path analysis. Ind Eng Chem

    Res 45:80958104

    Olesen SG, Polley GT (1996) Dealing with plant geography and

    piping constraints in water network design. Trans Inst Chem

    Eng, Part B 74:273276

    Olesen SG, Polley GT (1997) A simple methodology for the design of

    water networks handling single contaminants. Trans Inst Chem

    Eng, Part A 75:420426

    Prakash R, Shenoy UV (2005a) Targeting and design of water

    networks for fixed flowrate and fixed contaminant load opera-

    tions. Chem Eng Sci 60(1):255268

    Prakash R, Shenoy UV (2005b) Design and evolution of water

    networks by source shifts. Chem Eng Sci 60(7):20892093

    Puigjaner L, Espuna A, Almato M (2000) A software tool for helping

    in decision-making about water management in batch process

    industries. Waste Manage 20:645649

    Shoaib AM, Aly SM, Awad ME, Foo DCY, El-Halwagi MM (2007)

    A hierarchical approach for the synthesis of batch water network.

    Comp Chem Eng (in press)

    Wang YP, Smith R (1994) Wastewater minimisation. Chem Eng Sci

    49:9811006

    Wang YP, Smith R (1995a) Wastewater minimization with flowrate

    constraints. Trans Inst Chem Eng, Part A 73:889904

    Wang YP, Smith R (1995b) Time Pinch Analysis. Trans Inst Chem

    Eng, Part A 73:905914

    An integrated approach for water minimisation in a PVC manufacturing process 79

    123

    An integrated approach for water minimisation in a PVC manufacturing processAbstractIntroductionWater cascade analysis techniqueCase study on PVC manufacturing Process simulation modelWater minimisation studyLimiting water data extractionScenario 1: water network without water storage systemScenario 2:water network with water storage system

    ConclusionAcknowledgmentReferences

    /ColorImageDict > /JPEG2000ColorACSImageDict > /JPEG2000ColorImageDict > /AntiAliasGrayImages false /DownsampleGrayImages true /GrayImageDownsampleType /Bicubic /GrayImageResolution 150 /GrayImageDepth -1 /GrayImageDownsampleThreshold 1.50000 /EncodeGrayImages true /GrayImageFilter /DCTEncode /AutoFilterGrayImages true /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict > /GrayImageDict > /JPEG2000GrayACSImageDict > /JPEG2000GrayImageDict > /AntiAliasMonoImages false /DownsampleMonoImages true /MonoImageDownsampleType /Bicubic /MonoImageResolution 600 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.50000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict > /AllowPSXObjects false /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile (None) /PDFXOutputCondition () /PDFXRegistryName (http://www.color.org?) /PDFXTrapped /False

    /Description >>> setdistillerparams> setpagedevice