wmp 2010 appendix g
Post on 26-Mar-2016
217 Views
Preview:
DESCRIPTION
TRANSCRIPT
FINAL REPORT
Capitol Region Watershed District
June 22, 2009Project No. 13017.002
10 YEAR MAINTENANCE, REPAIR, AND
IMPROVEMENT PLAN FOR THE TROUT
BROOK STORM SEWER INTERCEPTOR
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 1
SAINT PAUL, MINNESOTA
JUNE 22, 2009
FINAL REPORT
10 YEAR MAINTENANCE, REPAIR, AND IMPROVEMENT PLAN FOR THE TROUT BROOK STORM SEWER INTERCEPTOR
2009 - 2018
CAPITOL REGION WATERSHED DISTRICT
PROJECT NO. 13017.002 I hereby certify that this Report was prepared by me or under my direct supervision and that I am a duly Licensed Professional Engineer under the laws of the State of Minnesota.
Ronald S. Quanbeck License No. 19396
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 2
10 YEAR MAINTENANCE, REPAIR, AND IMPROVEMENT PLAN FOR THE TROUT BROOK STORM SEWER INTERCEPTOR
2009 - 2018
CAPITOL REGION WATERSHED DISTRICT PROJECT NO. 13017.002
TABLE OF CONTENTS
PAGE NO.
I. PURPOSE.................................................................................................................................................1
II. BACKGROUND ........................................................................................................................................2
III. SUMMARY OF RECOMMENDED ACTION ITEMS................................................................................5
IV. CAPITAL PROJECTS..............................................................................................................................8
V. OPERATIONS ACTIVITIES....................................................................................................................11
VI. ADDITIONAL ACTION ITEMS TO CONSIDER ....................................................................................13
FIGURES
1. TROUT BROOK STORM SEWER INTERCEPTOR MAP.......................................................................3
TABLES
1. CAPITAL IMPROVEMENT PROJECTS ..................................................................................................6
2. OPERATIONS ACTIVITIES .....................................................................................................................7
APPENDICIES
1. TUNNEL CONDITION REPORT SUMMARY
2. COST SUMMARY
REFERENCES
1. 10 Year Maintenance, Capital Repair, and Improvement Plan for the Trout Brook (TBI) Storm Sewer
Interceptor, dated May 6, 2003, prepared by TKDA
2. Trout Brook Storm Tunnel System Inspection and Assessment Report, dated September 27, 2007,
prepared by CNA Consulting Engineers
3. Review of Trout Brook Storm Sewer Interceptor between Maryland and Interstate-35E, dated June
20, 2007, prepared by Barr Engineering Company
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 3
10 YEAR MAINTENANCE, REPAIR, AND IMPROVEMENT PLAN FOR THE TROUT BROOK STORM SEWER INTERCEPTOR
2009 - 2018
CAPITOL REGION WATERSHED DISTRICT
I. PURPOSE
The Capitol Region Watershed District (CRWD) commissioned TKDA to prepare a 10 year
Maintenance, Repair, and Improvement Plan (CIP) for the Trout Brook Storm Sewer
Interceptor (TBI) in 2003 in anticipation of assuming ownership of TBI from the Metropolitan
Council Environmental Services (TKDA, 2003). The TBI system was transferred to CRWD in
2006, and this CIP serves as an update to the 2003 CIP, which incorporates completed repair
work and identifies ongoing operational activities.
The purpose of this CIP is to serve as an asset management plan and guide to implementing
the action items necessary to improve and maintain the TBI System at a level of “Good
Operating Condition.” As part of the reconveyance of the TBI system in 2006, a legal
definition of “Good Operating Condition” was determined and promulgated in MN Statute
473.5111.
Moving forward on the management of the TBI system, CRWD has defined “Good Operating
Condition” as follows:
“In order for any section of the sewer system to be considered in ‘good operating condition,’
it shall (1) have foundation soil or pile foundations structurally adequate to carry the loads
imposed on it, (2) be free from damage, such as that allowing corrosion of reinforcing steel
and mortar loss between bricks or blocks, that may lead to further deterioration that could
be considered to threaten the structural integrity of the pipe, and (3) be free from defects,
such as offsets or sags, that significantly reduce the flow capacity of the pipe and defects,
such as holes and cracks, that permit significant exfiltration of stormwater or infiltration of
groundwater.”
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 4
II. BACKGROUND
The TBI was constructed as a combined sanitary sewer and storm sewer system from the
late 1800’s to early 1900’s. The combined sewer system was separated in the 1980’s. After
completion of sewer separation projects, Metropolitan Council Environmental Services
(MCES) transferred ownership of the TBI to CRWD.
In 2007, Charles R. Nelson & Associates, Inc. (CNA) was retained to visually inspect the TBI
for defects (i.e., cracks, holes, infiltration, sags, etc.), compare the inspection findings to past
inspections, and determine the existing structural condition of the TBI (CNA, 2007). The
visual inspection of TBI by CNA was the third since 1995, and the first performed on behalf of
CRWD. The previous inspections were performed prior to the TBI transfer from MCES to
CRWD. The reaches of the TBI inspected are shown on Figure 1.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 5
Project 13Sta. 185+82-186+94Date: 2010
Activity 7
END INSPECTION
Project 12Sta. 136+16-168+73Date: 2010
Project 1(Completed)Sta. 169+50-172+00
WEST EXTENSION
Project 14Sta. 0+00-17+62Date: 2010
Project 11Sta. 112+78-136+16Date: 2012
EAST EXTENSION
Project 5(Complete)Sta. 96+20-112+77
Project 2(Completed)Sta. 88+00-96+19
Project 4(Completed)
Sta. 59+45-88+00
Project 10Sta. 33+62-59+45
Date: 2012
Project 9Sta. 32+33-33+34Date: 2011
Project 8Sta. 28+49-32+33Date: 2011
Project 6Sta. 0+00-19+93Date: 2011
BEGIN INSPECTION
Project 7Sta. 23+15-28+49
Date: 2011
Project 3Sta. 23+00-23+15
Date: 2009INTERSTATE 94
INTERSTATE 35E
INTERSTATE 35E
INTERSTATE 94
INTERSTATE 35E
Saint Paul
Roseville MaplewoodD
ALE
ST
N
INTERSTATE 94
INTE
RST
ATE
35E
ARC
AD
E S
T
COMO AVE
7TH ST E
FRONT AVE
SELBY AVE
JAC
KSO
N S
T
WE
STER
N A
VE
N
EDG
ERTO
N S
T
SUMMIT AVE
CASE AVE
THOMAS AVE
MARYLAND AVE E
UNIVERSITY AVE W
WARNER RD
ROSELAWN AVE E
CONCORDIA AVE
ARLINGTON AVE W
ROBERT ST N
6TH ST E
SAINT ANTHONY AVE
FOR
ES
T S
T
PARKWAY
DR
HIG
HW
AY 52
MINNEHAHA AVE W
MOUNDS BLVD
KELLOGG BLVD E
3RD ST E
5TH ST E
MA
RIO
N S
T
9TH S
T E
SHEPARD RD
LARPENTEUR AVE E
KELLOGG BLVD WMARSHALL AVE
CEDAR ST
7TH ST W SAINT PETER ST
EDG
ERTO
N S
T N
WABASHA ST N
RIC
E S
T
MCCARRONS BLVD S
LARPENTEUR AVE W
SIBLEY ST
5TH ST W
MCCARRONS BLVD N
JAC
KSO
N S
T N
WALL ST
MA
PLE
WO
OD
DR
PAR
K S
T
WACOUTA ST
12TH ST W
FILLMORE AVE E
VICTORIA ST N
SYCAMORE ST W
10TH ST W
CHESTNUT ST
HIG
HW
AY 6
1
GRAND AVE
ROSELAWN AVE W
SHEPARD RD
UNIVERSITY AVE W
VIC
TOR
IA S
T N
INTERSTATE 94
WARNER RD
HIG
HW
AY 52
INTER
STATE 35E
VIC
TOR
IA S
T N
ROSELAWN AVE W
0 1,000 2,000 3,000 4,000500
Feet
K:\gis\CRWD\CIP\crwd-cip11x17-072009.mxd
Figure 1Trout Brook Storm Sewer Interceptor
10 Year Maintenance, Repair And Improvement Plan
General Maintenance
Feasibility
Repair and Monitor
Replace/Rehabilitate
Televise
LEGEND
Capitol Region Watershed Dist. Boundary
Date: June 2009
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 6
The information gathered in the 2007 inspection was used in preparing the recommended
activities, as well as information from the Review of Trout Brook Storm Sewer Interceptor
between Maryland Avenue and Interstate 35E (Barr Engineering, 2007).
In summary, the inspection found that the overall condition of the majority of the TBI system
inspected was in good to fair condition for almost its entire length and has remained relatively
the same from previous inspections. The most significant changes are:
1. The section near Willow Reserve Storm Water Pond, Station 168+73 to 171+13,
identified as poor condition in previous inspections was replaced and is now rated
good.
2. Under L’Orient Street Bridge and Maryland Avenue, TBI was downgraded from poor
to urgent (Station 88+20 to 95+10). The major defects in this section were severe
longitudinal fractures and settlement of TBI of one to three feet. Settlement caused
circumferential fractures and joints to open from one to five inches. The structural
inadequacy of this section was severe enough to require immediate corrective
action in 2008/2009. This section is now rated good.
3. The segment downstream from Maryland Avenue across Interstate 35E (Station
60+80 to 88+20) was downgraded from fair condition to poor condition. Longitudinal
cracks were observed that were not identified during previous inspections indicating
that the condition has deteriorated. This segment was repaired in conjunction with
Station 88+20 to 95+10.
4. A large junction chamber along the railroad tracks (Station 23+00 to 23+15) has a
metal grill and wood top. It cannot be closely inspected from inside the pipe, but is
identified as a concern that should be investigated further.
5. Significant invert erosion was identified from Station 185+82 to 186+94. This
segment was downgraded from fair to poor condition.
As identified in earlier reports and again confirmed, the most critical need identified after the
replacement of Willow Reserve segment was the segment under L’Orient Street and
Maryland Avenue, Station 88+20 to 95+10. In addition, a number of areas of the tunnel not
identified above need less extensive work to prevent them from deteriorating further.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 7
While this document is referred to as a CIP it contains not only capital, but also operational
activities. Recently completed CRWD projects and activities are also described.
III. SUMMARY OF RECOMMENDED ACTION ITEMS
TKDA’s recommended prioritized action items and budgeted costs to maintain and improve
the defined limits of the TBI System to a level of “Good Operating Condition” are summarized
in Table 1 and Table 2 and described in the following sections.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 8
PROJECT NO. 13017.002
June 22, 2009 TABLE 1
Prior Years 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Past and Future Projects
1 Replacement Work Sta. 169+50 - 172+00 (Completed 2007) 1,400,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
2 Replacement Work Sta. 88+00 - 96+19 (Note 2) 375,000$ 2,520,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$
3 Feasibility Study Sta. 23+00 - 23+15 -$ 50,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$
4 Repair Work Sta. 59+45 - 88+00 (Note 3) -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
5 Repair Work Sta. 96+20 - 112+77 (Note 4) -$ 50,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$
6 Repair Work Sta. 0 - 19+93 -$ 81,000$ -$ -$ -$ -$ -$ -$ -$
7 Repair Work Sta. 23+15 - 28+49 -$ -$ 22,000$ -$ -$ -$ -$ -$ -$ -$
8 Repair Work Sta. 28+49 - 32+33 -$ -$ 16,000$ -$ -$ -$ -$ -$ -$ -$
9 Repair Work Sta. 32+33 - 33+34 -$ -$ 4,000$ -$ -$ -$ -$ -$ -$ -$
10 Repair Work Sta. 33+62 - 59+45 -$ -$ -$ 105,000$ -$ -$ -$ -$ -$ -$
11 Repair Work Sta. 112+76 - 136+16 -$ -$ -$ 95,000$ -$ -$ -$ -$ -$ -$
12 Repair Work Sta. 136+16 - 168+73 -$ -$ 132,000$ -$ -$ -$ -$ -$ -$ -$
13 Repair Invert Sta. 185+82 - 186+94 -$ -$ 40,000$ -$ -$ -$ -$ -$ -$ -$
14 Repair Work (West Tunnel) Sta. 0+00 - 17+62 -$ -$ 70,000$ -$ -$ -$ -$ -$ -$ -$
15 Tunnel Maintenance Project (Note 5) -$ -$ -$ -$ -$ 150,000$ -$ -$ -$ -$ 150,000$
16 Tunnel Major Repair Fund -$ -$ -$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$ 300,000$
TOTALS 1,775,000$ 2,620,000$ 242,000$ 423,000$ 500,000$ 450,000$ 300,000$ 300,000$ 300,000$ 300,000$ 450,000$ NOTES: 1. MCES agreed to pay $4,200,000 for Projects Number 1 and 2.2. Actual (2008) and Expected (2009) costs for the project to be completed in 2009.
3. Concrete repair costs included in Project No. 2 costs.4. These repairs were conducted after the completion of Project No. 2 by the same contractor.5. Estimated repairs based on TBI inspection in 2012.6. 4% Yearly Inflationary Costs have been added to projects beginning after 2009.7. Total Cost for each Repair and Reconstruction Project includes a 30% Factor for Contingencies and a 20% Factor for Engineering.8. Colored table figures correspond to colored areas indicated on Figure #1, 10 Year Maintenance, Repair and Improvement Plan.
CAPITOL REGION WATERSHED DISTRICT10 YEAR MAINTENANCE, REPAIR, AND IMPROVEMENT PLAN
FOR THE TROUT BROOK STORM SEWER INTERCEPTOR
Page 6
CAPITAL IMPROVEMENT PROJECTS
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 9
PROJECT NO. 13017.002June 22, 2009
Prior Years 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
Past and Future Activities
1 Manhole Location Survey and GIS Mapping 15,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
2 Easement Verification Work 5,000$ -$ 25,000$ -$ -$ -$ -$ -$ -$ -$ -$
3 Expand Hydraulic Model to Trout Brook Outfall (Completed 2005) 30,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
4 Purchase and Install Flow Meters (Note 1) -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
5 Collect Flow Meter Data (Note 1) -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
6 TBI Inspection/Monitoring Program 66,000$ -$ 3,900$ 4,100$ 84,600$ 4,400$ 4,600$ 4,800$ 5,000$ 102,000$ 5,400$
7 Video Inspection Dale Street to Como Lake -$ 6,000$ -$ -$ -$ -$ -$ -$ -$ -$ -$
8 Hydraulic Modeling of the TBI -$ 35,000$ 50,000$ 50,000$ -$ -$ -$ -$ -$ -$ -$
9 Minor Maintenance (Note 3) -$ 15,000$ 15,000$ 15,000$ 15,000$ 16,000$ 16,000$ 16,000$ 18,000$ 18,000$ 18,000$
TOTALS 116,000$ 56,000$ 93,900$ 69,100$ 99,600$ 20,400$ 20,600$ 20,800$ 23,000$ 120,000$ 23,400$
NOTES: 1. See CRWD Monitoring Program for cost information
2. 4% Yearly Inflationary Costs have been added to activities beginning after 2009.3. Minor maintenance work is defined as misc. small repairs and cleaning.
TABLE 2
Page 7
10 YEAR MAINTENANCE, REPAIR, AND IMPROVEMENT PLANFOR THE TROUT BROOK STORM SEWER INTERCEPTOR
OPERATIONS ACTIVITIES
CAPITOL REGION WATERSHED DISTRICT
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 10
IV. CAPITAL PROJECTS
Project No. 1: Replacement Work Station 169+50 to 172+00 (Completed)
A 3.5 foot sag in TBI located in the railroad right-of-way just north of the Willow Reserve
Pond was repaired during the winter of 2006/2007. Two hundred forty feet of the TBI
along the north side of the railroad track was removed and replaced with an 8-foot
diameter reinforced concrete pipe placed on a piling system.
Project No. 2: Replacement and Repair Work Station 88+00 to 96+19 (Completed)
The TBI section under Maryland Avenue and L’Orient Street is in urgent condition and
in need of significant repair. In 2008, CRWD completed the Feasibility Study, including
geotechnical analysis of the repair area, and designed the repairs. By late November
2008, construction commenced on replacing a 200-foot section of TBI under L’Orient
Street Bridge and stabilizing the foundation of 260 feet of TBI under Maryland Avenue.
The replacement and repair work was completed in late spring 2009, which brought this
section of TBI to “Good Operating Condition”.
Project No. 3: Feasibility Study Station 23+00 to 23+15 (Future)
A large junction chamber under the BNSF Rail Yard located southeast of
Interstate 35E is covered by a buried metal grate and wood timbers. This cover cannot
be adequately inspected from inside the TBI and there is concern that it may have
deteriorated and needs replacement. This project provides for excavating the top
portion of the chamber to allow detailed structural inspection and a determination if
replacement of the cover is warranted at this time. In addition, the information
necessary to design the replacement will be gathered, feasible options will be identified
if replacement is necessary, and costs of the work will be estimated.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 11
Project No. 4: Repair Work Station 59+45 to 88+00 (Completed)
The 2007 tunnel inspection downgraded the section of the TBI downstream from
Maryland Avenue to across Interstate 35E from fair condition to poor condition.
Longitudinal cracks were observed that were not identified in the previous reports
indicating that the condition has deteriorated. CNA provided a broad range of potential
actions, from repair and monitoring to complete replacement with an associated broad
range in cost. In 2008, CRWD elected to conduct concrete repairs instead of fully
replacing this section. This work was conducted in conjunction with Project No. 2.
Project No. 5: Repair Work Station 96+20 to 112+77 (Completed)
Although this 1,650-foot section of tunnel was rated in fair condition in 2007, CRWD
identified significant inlet connection defects and longitudinal cracks in an inspection in
2009; therefore, CRWD chose to conduct concrete repairs in this tunnel section in
February 2009 as part of Project No. 2.
Project No. 6 through 12: (See Table 1) (Future)
CNA quantified additional repairs to the other segments of the tunnel which were not
addressed above. The repairs include sealing cracks and joints, patching inverts,
replacing manhole steps and patching pipe penetrations. The repairs will reduce
groundwater infiltration and the risk of pipe foundation or structural integrity problems
from developing in the future.
These repair projects have been scheduled over the next three years beginning in 2010
and completed in 2012. The purpose of this three year time line is primarily for
budgetary and project manageability reasons.
The goal of these projects is to repair the deficiencies identified by “CNA’s 2007
Inspection Report and Field Notes” and maintain the TBI in “Good Operating Condition.”
Note that the future findings of the TBI Inspection and Monitoring Program will be used
to re-evaluate, and if necessary, revise the current planned repairs for Projects 6
through 12. See Table No. 1 for the Estimated Cost Summaries for these Projects.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 12
Project No. 13: Repair Invert Station 185+82 to 186+94 (Future)
The 2007 tunnel inspection downgraded this segment of the TBI from fair to poor due to
significant invert erosion. This project will patch the invert which has eroded to a depth
of several inches in some locations to prevent further deterioration. Project No. 13 is a
higher priority than Projects 6 through 12.
Project No. 14: Repair Work - West Extension Station 0+00+ to 17+62 (Future)
This 8-foot diameter section of the TBI has many open, leaking joints. The goal of this
project is to properly seal leaking joints to eliminate groundwater infiltration and reduce
the risk of a pipe foundation or an integrity problem such as a sagged pipe condition
from occurring in the future.
Project No. 15: Tunnel Maintenance Project (Future)
Future TBI inspections with one slated for 2012, will likely identify minor repairs needed
throughout the TBI (See Activity No. 6 below). The extent and therefore the cost, will
not be determined until the 2012 inspection is complete, but an estimated amount has
been included in the CIP for planning purposes.
Project No. 16: Tunnel Major Repair Fund (Future)
CRWD will begin accumulating funds for future major repairs. Construction of portions
of the TBI began in 1888. As the system ages, various repairs will be required and
replacement of sections of the TBI is very expensive. A fund accumulated over time is a
tool to help limit the sudden funding spike of a large unforeseen repair project, such as
stabilizing the segment downstream from Maryland Avenue if it continues to deteriorate.
Guidelines for the fund such as capping it if it reaches a certain level or what it can be
used for will need to be established.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 13
V. OPERATIONS ACTIVITIES
Activity No. 1: Manhole Location Survey and GIS Mapping (Completed)
In 2004, all the TBI manholes were located and mapped for inclusion in a GIS
database. Existing base mapping information was collected from the City of Saint Paul
and MCES. During the manhole field survey digital pictures were collected for future
use.
Activity No. 2: Easement Verification Work (Completed and Future)
CRWD and Ramsey County staff verified easement rights needed for operation and
maintenance of the TBI. Easement verification work was completed in 2004. Numerous
discrepancies were discovered during the easement verification work that will need to
be resolved.
Activity No. 3: Expand Hydraulic Model to Trout Brook Outfall (Completed)
An existing XP-SWMM model of the upper watershed was expanded to include the TBI
to the system outlet at the Mississippi River. In addition, major detention facilities
connected to the TBI were added. Approximately 56% of the TBI watershed was
included in the original XP-SWMM model. The Model serves as a tool for managing the
future repairs, replacements, and modifications to the TBI. Expansion of the XP-SWMM
model was completed in 2005.
Activity No. 4 and No. 5: Purchase and Install Flow Meters and Collect Flow Meter Data (Ongoing)
Since 2005, CRWD has been collecting flow data at three locations in the TBI system as
part of the CRWD Monitoring Program. The flow data helps better understand the
hydraulics of TBI and assist in the management of the system. These activities are an
integral part of the CRWD Monitoring Program and are expected to be an ongoing effort.
Costs are included in the CRWD Monitoring Program and therefore not included here.
The activities are identified here to highlight their importance for managing the TBI
system.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 14
Activity No. 6: TBI Inspection/Monitoring Program (Future, Ongoing)
The TBI Inspection/Monitoring Program monitors the condition of the TBI to proactively
identify and address problems. The TBI will be thoroughly inspected every five years and
the CIP updated to reflect the results of that inspection. The invert erosion at Station
186+00 discussed in Project No. 13 will also be checked annually.
Activity No. 7: Video Inspection - Dale Street to Como Lake (Future)
A video inspection of the Maryland Avenue storm sewer line between Dale Street and
Como Lake will be performed. This segment of storm sewer line has a sanitary sewer
pipe encased in concrete inside the storm sewer. The line is not large enough for
personnel to access and was not inspected by CNA. The condition of the storm sewer
pipe will be reviewed and deficiencies noted. The video inspection will provide information
necessary to identify any repairs needed to maintain the line in “Good Operating
Condition”.
Activity No. 8: Hydraulic Modeling of the TBI (Future)
CRWD’s existing XP-SWMM hydrologic and hydraulic model will be updated and
calibrated using data gathered by CRWD’s flow monitoring program. The existing model
will be reviewed and modified, as appropriate, to reflect current conditions. Measured flow
and rainfall data will then be used to adjust model parameters to more accurately reflect
the characteristics of the TBI system. The XP-SWMM model provides a valuable tool for
managing the TBI system and watershed.
Activity No. 9: General (Minor) Maintenance of TBI (Ongoing)
Continued maintenance efforts will be part of the ongoing work to sustain the integrity of
TBI. This work will include replacing manhole lids and frames, clearing inlets and trash
racks, removing debris and sediment from the line, and other general maintenance
practices that will be required when periodic inspections deem them necessary.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 15
Page 13
VI. ADDITIONAL ACTION ITEMS TO CONSIDER
This CIP serves as an asset management plan and guide for implementing the action items
necessary to improve and maintain the TBI System at a level of “Good Operating Condition”.
In addition to this document, TKDA suggests that CRWD consider purchasing and developing
an Asset Management Database for the TBI System using an approved computer software
package. Benefits of developing an Asset Management Database include:
A. It will serve as a one-stop working record to effectively store and view previous and
future sewer inspections, repairs, and replacements. Photographs, record drawings,
sketches, documents, and inspection information can be entered into the database
(station by station). Most Asset Management software packages use GIS platforms
such as ArcView to view the TBI System and select specific sections of the system to
enter or view data. Most software packages can print off NPDES reports if required.
B. Most software packages can print off GASB 34 forms, documenting the replacement
costs of the infrastructure/asset and its depreciation over time.
Such an investment will show a greater return to CRWD and its administrative staff if CRWD
has or will be acquiring other infrastructure assets that require maintenance or capital
improvements. If requested by CRWD, TKDA is available to provide additional information
regarding Asset Management Databases and computer software packages.
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 16
Project Tunnel Start End Description Modifier D H W L At To Remarks6 Trout Brook 0+00 Miscellaneous Survey Start 915am 72 sunny6 Trout Brook 0+00 9+80 Miscellaneous Dimension/Diam/Shape Change 10 10 10' x 10', cobblestone invert, SS block wall, limestone block arch6 Trout Brook 0+00 4+30 Brickwork Missing Mortar Brickwork Missing Mortar Slight 5 76 Trout Brook 0+00 1+10 Infiltration Weeper 4 5 infiltration at mortar joints6 Trout Brook 0+00 1+45 Infiltration Weeper 7 9 at joints6 Trout Brook 0+00 4+30 Lining Failure Buckled 5 7 invert uneven / buckling6 Trout Brook 0+27 0+30 Point Repair Patch Repair 2 3 9 standard brick6 Trout Brook 2+13 Pipe Failure Hole 1.5 1.5 6 cobblestone pavers missing6 Trout Brook 3+42 Point Repair Patch Repair 1 1 9 granite block6 Trout Brook 4+04 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 6 2 steel steps deteriorating 6 Trout Brook 4+13 4+25 Point Repair Patch Repair 12 126 Trout Brook 4+30 9+80 Miscellaneous Lining Change transition from sandstone to limestone block walls6 Trout Brook 5+38 5+40 Point Repair Patch Repair 7 96 Trout Brook 7+41 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 4 2 rusted broken rungs6 Trout Brook 9+80 10+48 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber CIP crossover chamber 6 Trout Brook 10+48 19+93 Miscellaneous Dimension/Diam/Shape Change 10 10 10' x 10', cobblestone invert, SS block wall, limestone block arch6 Trout Brook 10+58 Miscellaneous General Observation 4 5 angle iron - stop logs for dam6 Trout Brook 10+58 Miscellaneous General Observation 7 8 angle iron - stop logs for dam6 Trout Brook 10+88 Access Point Manhole Access Point Manhole Steps Corroded 4 116 Trout Brook 10+88 Miscellaneous General Observation 2 4 remains of inflatable dam6 Trout Brook 10+88 Miscellaneous General Observation 8 10 remains of inflatable dam6 Trout Brook 14+10 Tap Break-In/Hammer Tap Break-In/Hammer Defective 4 9 patching required around 4' RCP6 Trout Brook 15+30 19+93 Infiltration Runner 9 running through multiple joints6 Trout Brook 16+30 19+93 Brickwork Missing 5 7 random pavers missing6 Trout Brook 16+30 Pipe Failure Hole 0.5 1 6 paver missing6 Trout Brook 16+32 Pipe Failure Hole 0.5 0.66 3 hole at connection6 Trout Brook 18+00 18+02 Brickwork Missing Brickwork Missing Mortar Large 7 86 Trout Brook 18+00 18+02 Infiltration Runner 7 86 Trout Brook 18+40 18+80 Brickwork Missing Mortar Brickwork Missing Mortar Large 26 Trout Brook 18+60 Obstacles/Obstructions Built Into Structure 11 1 DIP6 Trout Brook 18+60 Point Repair Patch Repair Point Repair Patch Repair Defective 11 1 around DIP6 Trout Brook 18+70 18+80 Brickwork Missing Mortar Brickwork Missing Mortar Large 0.10 9 106 Trout Brook 18+89 Access Point Manhole 3 96 Trout Brook 18+90 Point Repair Patch Repair 9 3 epoxy placed randomly in joints 6 Trout Brook 18+91 Pipe Failure Broken 3 4 12 abandoned drain6 Trout Brook 19+93 23+14 Miscellaneous Lining Change 10.5 10 CIP arch 6 Trout Brook 19+93 Miscellaneous General Observation 20' form length, invert & arch cast seperately6 Trout Brook 19+93 23+00 Surface Damage Aggregate Visible 5 76 Trout Brook 19+93 23+00 Surface Damage Reinforcement Visible Surface Damage Reinforcement Visible Corroded 5 7
Trout Brook 20+00 Access Point Manhole Access Point Manhole Steps Corroded 4 103 Trout Brook 23+00 23+14 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 10 14 11 1 grated steel roof covered with wood3 Trout Brook 23+03 Tap Break-In/Hammer Tap Break-In/Hammer Defective 1 10 at connection3 Trout Brook 23+14 26+22 Miscellaneous Lining Change 10 10 stone arch, concrete invert7 Trout Brook 23+44 Access Point Other Special Chamber 4 3 steel grate, daylight7 Trout Brook 23+50 Brickwork Missing Mortar Brickwork Missing Mortar Large 7 57 Trout Brook 23+50 Joint Separated 0.100 7 57 Trout Brook 23+77 Access Point Manhole 1 1 127 Trout Brook 23+79 Joint Separated 0.100 7 57 Trout Brook 24+64 Joint Separated 0.100 7 57 Trout Brook 26+22 28+49 Miscellaneous Dimension/Diam/Shape Change stone arch, brick invert7 Trout Brook 26+22 32+18 Miscellaneous General Observation 5 7 random pavers missing7 Trout Brook 28+10 28+43 Point Repair Patch Repair 12 57 Trout Brook 28+48 32+18 Surface Damage Aggregate Visible 7 57 Trout Brook 28+48 32+18 Surface Damage Reinforcement Visible 10 27 Trout Brook 28+49 32+18 Miscellaneous Lining Change CIP concrete arch, brick invert, walls 4'8 Trout Brook 28+63 Pipe Failure Hole 2 1 7 88 Trout Brook 29+06 Access Point Manhole Access Point Manhole Steps Corroded 3 1 steps corroded8 Trout Brook 29+50 29+80 Infiltration Weeper 38 Trout Brook 30+65 Tap Break-In/Hammer Tap Break-In/Hammer Capped 1.25 3
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 17
Project Tunnel Start End Description Modifier D H W L At To Remarks8 Trout Brook 31+74 Pipe Failure Hole 0.5 0.5 3 58 Trout Brook 32+00 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3.5 2 steps rusted/broken8 Trout Brook 32+18 32+33 Miscellaneous Lining Change block arch, concrete invert8 Trout Brook 32+18 Pipe Failure Broken Pipe Failure Broken Soil Visible 9 108 Trout Brook 32+18 Joint Separated 9 108 Trout Brook 32+33 33+34 Miscellaneous Dimension/Diam/Shape Change transition8 Trout Brook 32+66 Miscellaneous General Observation 7 5 change in block to platteville8 Trout Brook 32+68 Brickwork Missing 1 0.25 38 Trout Brook 33+34 42+57 Miscellaneous Dimension/Diam/Shape Change CIP horseshoe8 Trout Brook 33+34 Surface Damage Aggregate Visible8 Trout Brook 33+48 Pipe Failure Broken Pipe Failure Broken Soil Visible 1 1 78 Trout Brook 33+52 Tap Break-In/Hammer Tap Break-In/Hammer Active 1.25 910 Trout Brook 33+61 Joint Separated 0.021 9 3 0.25" width10 Trout Brook 33+64 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 4 6 11 steps rusted/broken10 Trout Brook 35+86 Access Point Manhole 3 1110 Trout Brook 36+48 Pipe Failure Hole 0.5 310 Trout Brook 36+50 36+70 Lining Failure Buckled 5 710 Trout Brook 36+50 42+57 Surface Damage Reinforcement Visible 10 210 Trout Brook 39+15 39+22 Surface Damage Reinforcement Visible 0.25 10 210 Trout Brook 39+21 39+70 Fracture Longitudinal 9 3 multiple10 Trout Brook 39+28 39+32 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3 4 steps rusted/broken/grated cover10 Trout Brook 39+33 Fracture Circumferential 0.021 9 3 0.25" width, rebar exposed10 Trout Brook 39+70 41+00 Miscellaneous General Observation scrap steel - manhole rings and covers (5)10 Trout Brook 42+57 42+76 Miscellaneous Dimension/Diam/Shape Change transition10 Trout Brook 42+73 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 4 11 steps rusted/broken10 Trout Brook 42+76 44+00 Miscellaneous Dimension/Diam/Shape Change CIPC box10 Trout Brook 42+76 68+61 Pipe Failure Hole 5 7 holes in concrete - invert deteriorating10 Trout Brook 43+55 Point Repair Patch Repair 2 310 Trout Brook 43+99 44+02 Access Point Blind Shaft 3 3 11 110 Trout Brook 44+00 44+28 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber, wye to west10 Trout Brook 44+07 Access Point Manhole 4 11 no steps10 Trout Brook 44+20 Access Wye 7 910 Trout Brook 44+28 59+45 Miscellaneous Dimension/Diam/Shape Change 10.5 9 10.5' x 9' CIPC box10 Trout Brook 44+30 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3 2 steps rusted/broken10 Trout Brook 46+80 46+83 Pipe Failure Hole 3 3 610 Trout Brook 47+07 59+55 Joint Separated 0.042 7 5 .5" width10 Trout Brook 47+07 Surface Damage Reinforcement Visible 8 1010 Trout Brook 47+07 Surface Damage Reinforcement Visible 9 310 Trout Brook 47+36 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3 9 steps rusted/broken10 Trout Brook 47+39 Infiltration Weeper 3 at connection10 Trout Brook 47+41 Tap Break-In/Hammer Tap Break-In/Hammer Active 2.83 4.5 8 span pipe 34" H x 54" wide10 Trout Brook 47+45 Fracture Circumferential 0.031 12 12 0.375" width10 Trout Brook 47+45 Infiltration Gusher 510 Trout Brook 48+57 Pipe Failure Hole 0.5 2 2 610 Trout Brook 48+90 Fracture Circumferential 0.010 7 5 0.125" width10 Trout Brook 50+16 Infiltration Runner 710 Trout Brook 50+51 Infiltration Weeper 3 at pipe10 Trout Brook 50+78 Point Repair Patch Repair Point Repair Patch Repair Defective 1.25 1.25 210 Trout Brook 52+13 Surface Damage Reinforcement Visible 10 110 Trout Brook 52+29 Access Point Manhole 3 11 steps rusted/broken10 Trout Brook 53+34 Fracture Circumferential 0.010 12 12 0.125" width10 Trout Brook 55+50 Access Point Manhole 4 1110 Trout Brook 56+75 Access Point Manhole 3 110 Trout Brook 57+50 Joint Separated 0.083 12 12 1" width10 Trout Brook 58+28 Joint Separated 0.042 12 12 0.5" width10 Trout Brook 59+08 Joint Separated 0.042 12 12 0.5" width10 Trout Brook 59+25 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3.5 1 steps rusted/broken10 Trout Brook 59+35 Fracture Circumferential 0.010 7 5 0.125" width10 Trout Brook 59+45 59+55 Miscellaneous Dimension/Diam/Shape Change transition
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 18
4 Trout Brook 72+46 Pipe Failure Broken 5 at connection
Project Tunnel Start End Description Modifier D H W L At To Remarks4 Trout Brook 59+55 68+61 Miscellaneous Dimension/Diam/Shape Change 11.5 10.75 11.5' x 10.75' CIPC horseshoe4 Trout Brook 59+68 Fracture Circumferential 0.042 12 12 0.5" width4 Trout Brook 60+46 Joint Separated 0.042 9 5 0.5" width4 Trout Brook 60+57 60+65 Access Point Other Special Chamber 3 11 drainage structure - vert. rebar4 Trout Brook 60+63 Access Point Manhole 2 114 Trout Brook 60+80 Joint Separated 0.042 12 12 0.5" width4 Trout Brook 61+92 Joint Offset 0.25 7 5 3" offset4 Trout Brook 62+52 Obstacles/Obstructions Object Protruding Thru Wall 5 piling through invert4 Trout Brook 62+54 62+56 Pipe Failure Hole 1 1 74 Trout Brook 62+55 Lining Failure Buckled 5 7 invert buckling4 Trout Brook 62+65 Joint Separated 0.063 7 5 0.75" width4 Trout Brook 62+65 68+61 Surface Damage Aggregate Visible 10 24 Trout Brook 62+65 68+61 Surface Damage Reinforcement Visible 10 24 Trout Brook 63+15 Joint Offset 0.167 7 5 2" offset4 Trout Brook 63+15 Joint Separated 0.083 7 5 1" width4 Trout Brook 63+50 Fracture Angular 0.0104 7 1 0.125" width4 Trout Brook 64+14 Fracture Circumferential 0.042 7 5 0.5" width4 Trout Brook 64+14 Joint Offset 0.042 7 5 0.5" offset4 Trout Brook 64+33 Joint Separated 0.0104 7 5 0.125" width4 Trout Brook 64+94 Joint Separated 0.042 7 5 0.5" width4 Trout Brook 65+53 Joint Separated 0.031 7 5 0.375" width4 Trout Brook 65+93 Joint Separated 0.021 7 5 0.25" width4 Trout Brook 66+18 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3 10 steps rusted/broken4 Trout Brook 66+44 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 67+01 67+05 Pipe Failure Hole 1 4 5 soil visible4 Trout Brook 67+13 Fracture Circumferential 0.031 12 12 0.375" width, 0.5" max4 Trout Brook 67+16 67+24 Pipe Failure Hole 1 5 soil visible4 Trout Brook 68+27 Fracture Circumferential 0.010 12 12 0.125" width4 Trout Brook 68+41 88+20 Miscellaneous Dimension/Diam/Shape Change 11.5 10.75 11.5' x 10.75' CIPC horseshoe4 Trout Brook 68+41 68+98 Crack Longitudinal 114 Trout Brook 68+41 Miscellaneous General Observation 5 7 holes in concrete - invert deteriorating4 Trout Brook 68+41 112+69 Surface Damage Aggregate Visible 10 24 Trout Brook 68+41 112+69 Surface Damage Reinforcement Visible 7 54 Trout Brook 68+45 68+98 Crack Longitudinal 114 Trout Brook 68+61 Miscellaneous Survey End 1:45pm rainy4 Trout Brook 68+62 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 68+80 69+32 Crack Longitudinal 14 Trout Brook 68+98 69+38 Crack Angular 11 84 Trout Brook 69+32 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 69+34 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3 10 steps rusted/broken/missing4 Trout Brook 69+35 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 69+85 Crack Circumferential 0.021 7 5 0.25" width4 Trout Brook 70+38 70+96 Crack Longitudinal 14 Trout Brook 70+38 75+26 Crack Longitudinal 114 Trout Brook 70+38 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 70+96 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 71+00 71+07 Pipe Failure Hole 1 7 74 Trout Brook 71+13 Crack Circumferential 7 54 Trout Brook 71+53 Joint Separated 0.031 7 5 0.375" width4 Trout Brook 71+78 Fracture Circumferential 0.042 7 5 0.5" width4 Trout Brook 71+80 Crack Circumferential 7 54 Trout Brook 71+80 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 71+99 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 72+04 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 72+09 72+10 Crack Multiple 7 54 Trout Brook 72+31 72+56 Fracture Longitudinal 0.000 9 0.005" width4 Trout Brook 72+45 Joint Separated 0.06 7 5 0.75" width; open @ 7 & 5, tight @ 124 Trout Brook 72+46 Access Point Manhole 3Access Point Manhole Steps Corroded 10 steps rusted
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 19
APPENDIX 1
4 Trout Brook 88+00 89+21 Fracture Longitudinal 0.000 11 0.005" width
Project Tunnel Start End Description Modifier D H W L At To Remarks4 Trout Brook 72+47 73+86 Fracture Longitudinal 0.000 1 0.005" width4 Trout Brook 72+48 Fracture Circumferential 0.002 9 5 0.02" width4 Trout Brook 72+77 Crack Circumferential 1 54 Trout Brook 72+77 Fracture Circumferential 0.010 7 11 0.125" width4 Trout Brook 73+12 Fracture Circumferential 0.016 7 5 3/16" width4 Trout Brook 73+68 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 74+38 Fracture Circumferential 0.021 7 5 0.25" width4 Trout Brook 74+51 Crack Circumferential 7 114 Trout Brook 74+81 75+26 Crack Longitudinal 14 Trout Brook 74+81 Joint Separated 0.021 7 5 0.25" width4 Trout Brook 75+46 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 75+85 76+05 Crack Longitudinal 104 Trout Brook 75+85 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 75+88 Access Point Manhole 3Access Point Manhole Steps Missing/Broken/Corroded 10 steps rusted/broken/missing4 Trout Brook 76+04 Fracture Circumferential 0.000 7 5 0.005" width4 Trout Brook 76+53 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 76+71 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 77+11 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 77+11 Miscellaneous Water Level 0.67 6 water depth 0.67'4 Trout Brook 77+70 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 77+70 Miscellaneous General Observation rebar exposed in circ fractures4 Trout Brook 77+85 Fracture Circumferential 0.000 7 5 0.005" width4 Trout Brook 77+98 Fracture Circumferential 0.000 7 12 0.005" width4 Trout Brook 78+24 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 79+34 80+20 Crack Longitudinal 2 3 5 cracks4 Trout Brook 79+34 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 79+36 Access Point Manhole 3Access Point Manhole Steps Missing/Broken/Corroded 10 steps rusted/broken4 Trout Brook 79+42 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 79+49 Fracture Circumferential 0.001 7 5 0.01" width4 Trout Brook 79+55 Fracture Circumferential 0.000 7 5 0.005" width4 Trout Brook 79+66 Fracture Circumferential 0.002 7 5 0.02" width4 Trout Brook 79+73 Crack Circumferential 7 54 Trout Brook 79+85 Fracture Circumferential 0.004 7 5 0.05" width4 Trout Brook 80+00 Fracture Circumferential 0.001 7 5 3/16" width4 Trout Brook 80+20 81+42 Crack Longitudinal 14 Trout Brook 80+20 81+42 Crack Longitudinal 24 Trout Brook 80+21 Fracture Circumferential 0.010 7 5 0.125" width4 Trout Brook 80+43 Fracture Circumferential 0.002 7 5 0.02" width4 Trout Brook 80+43 Joint Separated 5 7 underwater4 Trout Brook 80+79 Crack Circumferential 7 54 Trout Brook 81+00 81+01 Pipe Failure Hole 0.5 1 64 Trout Brook 81+92 Fracture Circumferential 0.000 7 5 0.005" width4 Trout Brook 82+32 Access Point Manhole 3 104 Trout Brook 82+34 86+34 Fracture Longitudinal 104 Trout Brook 82+67 Fracture Circumferential 0.004 9 5 0.05" width4 Trout Brook 83+56 Joint Separated 0.010 7 5 0.125" width4 Trout Brook 84+02 Fracture Circumferential 0.005 7 5 1/16" width4 Trout Brook 84+42 Joint Separated 0.004 7 5 0.05" width4 Trout Brook 84+58 Fracture Circumferential 0.021 7 5 0.25" width4 Trout Brook 84+70 Fracture Angular 0.010 7 5 0.125" width4 Trout Brook 85+43 85+48 Fracture Circumferential 0.005 7 5 1/16" width4 Trout Brook 85+85 Joint Separated 0.005 7 5 1/16" width4 Trout Brook 85+87 Access Point Manhole 3Access Point Manhole Steps Missing/Broken/Corroded 10 steps rusted, broken4 Trout Brook 86+09 Fracture Circumferential 0.004 12 12 0.05" width4 Trout Brook 87+50 87+10 Fracture Circumferential 0.010 10 5 0.125" width4 Trout Brook 87+54 Fracture Circumferential 0.06 7 5 0.75" width4 Trout Brook 87+69 Joint Separated 0.063 7 5 0.375" width4 Trout Brook 88+00 Deposits Settled Fine 6
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 20
APPENDIX 1
5 Trout Brook 109+29 Miscellaneous General Observation 6 manhole cover in invert
Project Tunnel Start End Description rModifie D H W L At To Remarks2 Trout Brook 88+23 Joint Separated 0.010 7 5 0.125" width2 Trout Brook 88+36 88+58 Fracture Angular 0.031 7 5 0.375" width2 Trout Brook 88+36 89+21 Fracture Angular 7 5 multiple at 8' intervals2 Trout Brook 88+48 88+71 Fracture Angular 0.010 11 5 0.125" width2 Trout Brook 89+21 Fracture Longitudinal 10 2 multiple longitudinal fractures, number varies 1~52 Trout Brook 89+21 Joint Separated 0.010 7 5 0.125" width2 Trout Brook 89+21 Miscellaneous General Observation 0.167 crown down 2"2 Trout Brook 89+23 Access Point Manhole 3Access Point Manhole Steps Corroded 10 steps rusted2 Trout Brook 89+23 Pipe Failure Hole 1 1.00 3 1' deep2 Trout Brook 89+23 Tap Break-In/Hammer Tap Break-In/Hammer Defective 1.5 3 5 at connection2 Trout Brook 89+99 Fracture Circumferential 0.167 7 5 2" width2 Trout Brook 90+50 Miscellaneous Water Level 2 water 2' deep2 Trout Brook 90+63 Fracture Circumferential 0.083 7 5 1.5" @ 5 & 7, 1/2" @ 122 Trout Brook 90+98 Fracture Circumferential 0.146 7 5 3" @ 7 & 5, 1/2" @ 122 Trout Brook 90+98 Joint Offset 0.083 7 5 1" offset2 Trout Brook 91+24 Fracture Circumferential 0.090 7 5 0.5" width, 1/5" @ 5, 2" @ 7, 3/4" @ 22 Trout Brook 91+55 Fracture Circumferential 0.063 7 5 0.75" width2 Trout Brook 91+55 Joint Separated 0.042 5 7 0.5" width2 Trout Brook 92+03 92+11 Fracture Angular 0.330 7 9 4" width2 Trout Brook 92+06 92+11 Fracture Angular 0.042 3 5 0.5" width2 Trout Brook 92+11 Joint Offset 0.042 12 0.5' @ 122 Trout Brook 92+11 Joint Separated 7 52 Trout Brook 92+35 Joint Separated 0.063 7 5 0.75" width2 Trout Brook 92+40 Access Point Manhole Access Point Manhole Steps Corroded 3 10 steps rusted2 Trout Brook 92+71 92+79 Access Point Manhole Access Point Manhole Steps Corroded 4 2 steps rusted2 Trout Brook 93+02 Access Wye 7.5 32 Trout Brook 93+19 Fracture Circumferential 0.33 12 12 4" width2 Trout Brook 94+13 94+15 Pipe Failure Broken 0.25 2.00 7 5 3" depth2 Trout Brook 94+15 Joint Offset 0.67 122 Trout Brook 94+15 Miscellaneous Water Level 2 water 2' deep2 Trout Brook 95+10 Fracture Circumferential 0.208 7 5 2.5" width2 Trout Brook 96+15 Access Point Manhole Access Point Manhole Steps Corroded 2.5 11 steps rusted/bent, manhole near wendy's2 Trout Brook 96+15 Miscellaneous General Observation flow guage in invert5 Trout Brook 96+26 96+49 Crack Longitudinal 125 Trout Brook 96+26 Fracture Circumferential 0.042 7 5 0.5" width5 Trout Brook 96+26 Joint Separated 0.021 5 7 0.25" width5 Trout Brook 96+31 Crack Circumferential 7 105 Trout Brook 96+81 96+98 Crack Longitudinal 115 Trout Brook 96+81 Joint Separated 0.005 7 5 1/16" width5 Trout Brook 97+50 100+52 Crack Longitudinal 115 Trout Brook 98+70 Fracture Circumferential 0.000 7 5 0.005" width5 Trout Brook 99+35 Crack Circumferential 7 55 Trout Brook 99+87 100+52 Crack Longitudinal 25 Trout Brook 99+88 Point Repair Patch Repair 1 1 125 Trout Brook 100+77 101+08 Line Left5 Trout Brook 100+80 Miscellaneous General Observation 6 manhole cover in invert5 Trout Brook 100+88 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3.5 10 steps rusted/broken5 Trout Brook 100+89 Joint Separated 0.010 0.125" width5 Trout Brook 101+46 Joint Separated 0.021 7 5 0.25" width5 Trout Brook 101+74 Joint Separated 0.021 7 5 0.25" width5 Trout Brook 101+74 Joint Separated 0.104 5 7 1.25" width5 Trout Brook 103+60 Miscellaneous General Observation 6 manhole cover in invert5 Trout Brook 105+09 Tap Break-In/Hammer Tap Break-In/Hammer Defective 1.25 2 at tee5 Trout Brook 105+53 Access Point Manhole 3Access Point Manhole Steps Missing/Broken/Corroded 10 steps rusted/missing5 Trout Brook 107+10 Miscellaneous General Observation 6 manhole cover in invert5 Trout Brook 107+12 Joint Separated 0.042 5 7 0.5" width5 Trout Brook 109+13 109+54 Line Right5 Trout Brook 109+27 Access Point Manhole 3Access Point Manhole Steps Missing/Broken/Corroded 10 steps rusted/broken
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 21
Trout Brook Sewer Inspection APPENDIX 1Project Tunnel Start End Description r W LModifie D H At To Remarks
5 Trout Brook 109+90 110+28 Deposits Attached Encrustation 2 55 Trout Brook 109+90 110+28 Infiltration Weeper 2 55 Trout Brook 109+90 Infiltration Weeper 115 Trout Brook 110+08 Pipe Failure Hole 0.5 0.5 1 0.5' deep5 Trout Brook 112+31 112+39 Access Point Manhole Access Point Manhole Steps Corroded 3 2 steps rusted5 Trout Brook 112+45 112+47 Pipe Failure Hole 1 4 3' deep5 Trout Brook 112+55 112+69 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber transition chamber5 Trout Brook 112+69 117+24 Miscellaneous Dimension/Diam/Shape Change 9 9' dia CIPC5 Trout Brook 112+69 116+23 Miscellaneous General Observation steep slope5 Trout Brook 112+69 117+29 Point Repair Patch Repair Point Repair Patch Repair Defective 5 75 Trout Brook 112+69 Point Repair Patch Repair 4 85 Trout Brook 112+69 117+29 Surface Damage Aggregate Visible 8 411 Trout Brook 114+09 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3.5 1011 Trout Brook 117+24 117+40 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber11 Trout Brook 117+29 Access Wye 8 411 Trout Brook 117+29 117+71 Deposits Settled Gravel 1 5 711 Trout Brook 117+38 Access Point Manhole Access Point Manhole Steps 4 1 steps good11 Trout Brook 117+40 130+36 Miscellaneous Dimension/Diam/Shape Change 9 9' dia CIPC11 Trout Brook 120+84 Access Point Manhole Access Point Manhole Steps Missing/Broken/Corroded 3.5 10 accessible11 Trout Brook 121+31 121+83 Crack Longitudinal 1211 Trout Brook 121+73 Infiltration Weeper 9 311 Trout Brook 122+64 122+70 Surface Damage Surface Spalling 2 411 Trout Brook 124+00 124+59 Crack Longitudinal 1211 Trout Brook 125+91 Access Point Manhole 3Access Point Manhole Steps Corroded 10 steps rusted11 Trout Brook 126+36 Joint Offset 0.2 9 311 Trout Brook 126+36 Point Repair Patch Repair 9 311 Trout Brook 126+55 Joint Offset 0.2 9 311 Trout Brook 126+55 Point Repair Patch Repair 9 311 Trout Brook 126+65 126+85 Crack Longitudinal 1211 Trout Brook 126+85 Joint Separated 0.010 12 12 0.125" width11 Trout Brook 127+41 Infiltration Weeper 211 Trout Brook 127+41 Joint Offset 9 311 Trout Brook 127+41 Point Repair Patch Repair 9 311 Trout Brook 127+50 128+00 Deposits Attached Encrustation 3 511 Trout Brook 127+50 128+00 Deposits Attached Encrustation 7 911 Trout Brook 127+50 128+00 Infiltration Weeper 311 Trout Brook 127+50 128+00 Infiltration Weeper 911 Trout Brook 127+85 128+00 Crack Longitudinal 111 Trout Brook 129+60 Crack Circumferential 12 1211 Trout Brook 129+97 130+36 Infiltration Weeper 911 Trout Brook 129+97 Joint Separated 0.010 7 5 0.125" width11 Trout Brook 130+36 130+51 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber11 Trout Brook 130+42 130+49 Infiltration Weeper 8 1011 Trout Brook 130+42 130+49 Point Repair Patch Repair 5 811 Trout Brook 130+45 Access Wye 8 3 main tunnel is still 9' dia CIPC11 Trout Brook 130+65 135+91 Miscellaneous Dimension/Diam/Shape Change 9 CIPC11 Trout Brook 130+65 Access Point Manhole 3Access Point Manhole Steps Corroded 1011 Trout Brook 130+65 135+91 Deposits Attached Encrustation 3 5 intermittent11 Trout Brook 130+65 135+91 Deposits Attached Encrustation 7 9 intermittent11 Trout Brook 130+65 135+91 Infiltration Weeper 3 intermittent11 Trout Brook 130+65 135+91 Infiltration Weeper 9 intermittent11 Trout Brook 130+65 164+21 Surface Damage Aggregate Visible 9 311 Trout Brook 130+76 Joint Separated 0.010 9 3 0.125" width intermittent11 Trout Brook 130+78 130+81 Pipe Failure Hole 10 2 rebar exposed11 Trout Brook 134+56 Joint Separated 0.021 9 3 0.25" width11 Trout Brook 135+91 136+07 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber, wye to right, 8' dia abandoned11 Trout Brook 136+07 164+21 Miscellaneous Dimension/Diam/Shape Change 8 8' CIP11 Trout Brook 136+14 Access Point Manhole 2.5 10
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 22
Trout Brook Sewer Inspection
12
1
APPENDIX 1Project Tunnel Start End Description rModifie D H W L At To Remarks
12 Trout Brook 136+83 Joint Separated 0.010 9 3 0.125" width12 Trout Brook 137+18 Joint Separated 0.010 9 3 0.125" width12 Trout Brook 138+65 Joint Separated 12 12 construction joints deteriorating12 Trout Brook 139+04 Miscellaneous General Observation 71.5' form length12 Trout Brook 139+63 Fracture Circumferential 0.001 12 12 0.01" width12 Trout Brook 141+48 141+50 Fracture Angular 0.021 1 3 0.25" width12 Trout Brook 141+48 141+50 Fracture Angular 0.021 9 11 0.25" width12 Trout Brook 141+50 Joint Separated 0.042 3 9 0.5" width12 Trout Brook 142+15 Access Point Manhole 3 10 rice street12 Trout Brook 142+54 143+59 Deposits Settled Fine 0.512 Trout Brook 145+48 Access Point Manhole 4 1012 Trout Brook 148+63 Access Point Manhole 3 212 Trout Brook 150+82 151+56 Line Right12 Trout Brook 151+42 Tap Break-In/Hammer Tap Break-In/Hammer Active 1.25 10 RR ditch drain12 Trout Brook 152+53 Joint Separated 0.010 12 12 0.125" width12 Trout Brook 153+23 Fracture Circumferential 0.010 12 12 0.125" width12 Trout Brook 153+83 Joint Separated 0.010 3 9 0.125" width12 Trout Brook 154+05 Access Point Manhole Access Point Manhole Steps Corroded 3.50 212 Trout Brook 156+21 Fracture Circumferential 0.010 12 12 0.125" width12 Trout Brook 156+65 157+40 Fracture Longitudinal 0.010 10 0.125" width12 Trout Brook 157+40 Fracture Circumferential 0.021 12 12 0.25" width12 Trout Brook 157+57 Access Point Manhole 3 212 Trout Brook 158+00 Fracture Circumferential 0.002 12 12 .02" width12 Trout Brook 158+14 160+25 Crack Longitudinal 11 1212 Trout Brook 159+23 Crack Circumferential 9 312 Trout Brook 159+23 Joint Separated 0.010 3 9 0.125" width12 Trout Brook 160+76 Access Point Manhole 3 212 Trout Brook 161+31 Fracture Circumferential 0.010 8 4 0.125" width12 Trout Brook 162+09 Fracture Circumferential 0.010 3 9 0.125" width12 Trout Brook 162+09 Joint Separated 0.010 9 3 0.125" width12 Trout Brook 162+79 Fracture Circumferential 0.031 12 12 0.375" width12 Trout Brook 163+29 Fracture Circumferential 0.010 3 9 0.125" width12 Trout Brook 163+29 Joint Separated 0.010 9 3 0.125" width12 Trout Brook 163+89 Fracture Circumferential 0.006 3 9 0.075" width12 Trout Brook 163+89 Joint Separated 0.010 9 3 0.125" width12 Trout Brook 164+21 Miscellaneous Survey Start 8:45am; 80 deg sunny12 Trout Brook 164+21 168+73 Miscellaneous Dimension/Diam/Shape Change 8 8' CIPC12 Trout Brook 164+21 Access Point Manhole Access Point Manhole Steps Corroded 2.5 2 rungs rusted12 Trout Brook 164+21 168+73 Surface Damage Aggregate Visible 10 212 Trout Brook 164+21 Tap Break-In/Hammer Tap Break-In/Hammer Active 2.5 412 Trout Brook 164+21 Miscellaneous Survey End 4:25 PM12 Trout Brook 166+87 166+95 Surface Damage Reinforcement Visible 8 412 Trout Brook 166+90 168+00 Deposits Settled Gravel 0.3312 Trout Brook 167+75 Access Point Manhole Access Point Manhole Steps Corroded 2.5 2
Trout Brook 168+73 171+13 Miscellaneous Lining Change 8 8' RCP pipeTrout Brook 168+89 Miscellaneous General Observation 3 5 fiberglass reinforced plastic in jointsTrout Brook 168+98 170+48 Joint Separated 0.073 12 12 0.5" to 1.25" width
1 Trout Brook 169+47 Miscellaneous General Observation 10 2 fiberglass reinforced plastic in joints1 Trout Brook 169+74 Miscellaneous General Observation 3 2 fiberglass reinforced plastic in joints1 Trout Brook 170+75 Joint Separated 0.125 12 12 1.5" width1 Trout Brook 171+13 178+09 Miscellaneous Lining Change 8 8' CIPC1 Trout Brook 171+13 Miscellaneous General Observation old stationing 171+18
Trout Brook 171+35 Fracture Circumferential 0.063 12 12 0.75" widthTrout Brook 172+69 Fracture Circumferential 0.063 12 12 0.75" widthTrout Brook 172+69 Surface Damage Aggregate Visible 12 12Trout Brook 172+89 Fracture Circumferential 0.021 3 12 0.25" widthTrout Brook 173+13 Tap Break-In/Hammer 5Tap Break-In/Hammer Active 9 chamber in pondTrout Brook 173+52 Fracture Circumferential 0.063 12 12 0.75" width
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 23
Project
13
Trout Brook 202+76 Access Point Manhole Access Point Manhole Steps Corroded 3 12
Trout Brook West (South) 1+91 Miscellaneous Survey End 3:15pm
Trout Brook Sewer Inspection APPENDIX 1Tunnel Start End Description rModifie D H W L At To RemarksTrout Brook 174+50 Fracture Circumferential 0.010 12 12 0.125" widthTrout Brook 174+96 Joint Separated 0.021 12 12 0.25" widthTrout Brook 176+39 Access Point Manhole 2.5 10Trout Brook 178+09 178+10 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Bulkhead bulkhead with 18" x 18" cutout in invertTrout Brook 178+10 178+21 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber outlet structure @ pondTrout Brook 178+10 181+65 Deposits Settled Fine 0.5 0.5' deepTrout Brook 178+10 180+57 Surface Damage Aggregate Visible 5 7Trout Brook 180+57 180+73 Miscellaneous Dimension/Diam/Shape Change 8 8 8' x 8' transitionTrout Brook 180+73 185+65 Miscellaneous Dimension/Diam/Shape Change 8 8 8' x 8' CIP boxTrout Brook 183+33 185+82 Deposits Settled Fine 1 1' depthTrout Brook 183+78 Fracture Circumferential 0.000 12 12 0.005" widthTrout Brook 183+78 Tap Break-In/Hammer 1Tap Break-In/Hammer Active 3Trout Brook 183+99 Fracture Circumferential 0.000 12 12 0.005" widthTrout Brook 184+86 Fracture Circumferential 0.010 12 12 0.125" widthTrout Brook 185+65 185+82 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamberTrout Brook 185+80 Access Point Manhole 4 1 rungs in good shape
13 Trout Brook 185+82 186+94 Miscellaneous Dimension/Diam/Shape Change 8 8' dia CIPC, 2 pours, 1/2 pipe13 Trout Brook 185+82 186+94 Surface Damage Aggregate Visible Surface Damage Mechanical Aggregate Projecting 5 713 Trout Brook 185+85 186+94 Miscellaneous General Observation multiple abandoned service connections @ 10 & 213 Trout Brook 186+08 Fracture Circumferential 0.031 9 3 0.375" width13 Trout Brook 186+94 187+03 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber
Trout Brook 186+94 187+03 Access Point Manhole 4 9Trout Brook 187+03 189+12 Miscellaneous Dimension/Diam/Shape Change 8 8' dia RCPTrout Brook 188+06 Access Point Manhole Access Point Manhole Steps 4 12 rungs in good shapeTrout Brook 189+12 198+15 Miscellaneous Dimension/Diam/Shape Change 8 8' CIPCTrout Brook 189+12 189+14 Line Up 0.5Trout Brook 189+35 Fracture Circumferential 0.001 9 3 0.01" widthTrout Brook 189+99 Joint Separated 0.010 9 3 0.125" widthTrout Brook 190+62 Joint Separated 0.001 9 3 0.01" widthTrout Brook 191+88 Fracture Circumferential 0.0104 9 3 0.125" widthTrout Brook 192+60 Access Point Manhole 3 1Trout Brook 192+64 Obstacles/Obstructions Object Protruding Thru Wall 11 1Trout Brook 193+05 Obstacles/Obstructions Object Protruding Thru Wall 10 2Trout Brook 193+67 Obstacles/Obstructions Object Protruding Thru Wall 11 1Trout Brook 195+00 Miscellaneous General Observation shotcrete patches on cold joints and fractures falling offTrout Brook 198+15 198+24 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber transition sectionTrout Brook 198+17 Access Wye 5 9 RCPTrout Brook 198+24 206+40 Miscellaneous Dimension/Diam/Shape Change 5 5' CIPCTrout Brook 198+46 Access Point Manhole 4 12Trout Brook 200+70 Obstacles/Obstructions Object Protruding Thru Wall 11 1
Trout Brook West (South) 0+00 Miscellaneous Survey Start 2:45pm, 80 deg sunnyTrout Brook West (South) 0+00 0+19 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamberTrout Brook West (South) 0+00 1+91 Deposits Settled Other 2 6 sandTrout Brook West (South) 0+14 Access Point Manhole 4 11Trout Brook West (South) 0+19 0+96 Miscellaneous Dimension/Diam/Shape Change 8 8' dia RCPTrout Brook West (South) 0+29 Infiltration Gusher 8 at jointTrout Brook West (South) 0+96 1+04 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamberTrout Brook West (South) 1+04 1+91 Miscellaneous Dimension/Diam/Shape Change 8 8' dia RCPTrout Brook West (South) 1+89 Access Point Manhole 4 12 no stepsTrout Brook West (South) 1+91 Miscellaneous General Observation end of tunnelTrout Brook West (South) 1+91 Obstacles/Obstructions Built Into Structure bulkhead with 2' dia pipe @ end of tunnel
Trout Brook West (North) 0+00 Miscellaneous Survey Start 8:15am 75 deg, clear skiesTrout Brook West (North) 0+00 3+00 Miscellaneous Dimension/Diam/Shape Change 8 RCP - with back slopeTrout Brook West (North) 0+00 3+00 Deposits Attached Encrustation 0.5
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 24
Project
Trout Brook Sewer Inspection APPENDIX 1Tunnel Start End Description r WModifie D H L At To RemarksTrout Brook West (North) 0+37 Infiltration Gusher 4Trout Brook West (North) 0+43 Joint Separated 0.33 1 3 Gasket ShowingTrout Brook West (North) 0+45 Access Point Tee Connection 1 3Trout Brook West (North) 0+97 Infiltration Runner 3 4Trout Brook West (North) 1+36 Infiltration Runner 4Trout Brook West (North) 2+92 Infiltration Weeper 8Trout Brook West (North) 3+00 3+08 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamberTrout Brook West (North) 3+06 Access Point Manhole 4 11 CIPCTrout Brook West (North) 3+08 3+25 Miscellaneous Dimension/Diam/Shape Change 4 RCP - connecting between 8' RCP sectionsTrout Brook West (North) 3+16 Infiltration Runner 3Trout Brook West (North) 3+25 3+31 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber chamber, 2-outlet pipe - 6' to endTrout Brook West (North) 3+31 8+69 Miscellaneous Dimension/Diam/Shape Change 8 6 RCPTrout Brook West (North) 3+31 7+42 Infiltration Runner 5 7 at each jointTrout Brook West (North) 3+31 Joint Separated 0.27 1" - 5.5"Trout Brook West (North) 8+69 8+80 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber CIPC w/ wye to leftTrout Brook West (North) 8+72 Access Point Manhole 4 11Trout Brook West (North) 8+80 11+77 Miscellaneous Dimension/Diam/Shape Change 8 RCPTrout Brook West (North) 9+13 Infiltration Runner 10 at connectionTrout Brook West (North) 11+77 11+96 Miscellaneous Dimension/Diam/Shape Change CIPC chamberTrout Brook West (North) 11+83 Access Point Manhole 4 11Trout Brook West (North) 11+85 Tap Break-In/Hammer Tap Break-In/Hammer Capped 2 3Trout Brook West (North) 11+96 17+56 Miscellaneous Dimension/Diam/Shape Change 8 RCPTrout Brook West (North) 14+94 Infiltration Runner 10 at connectionTrout Brook West (North) 16+59 Miscellaneous General Observation 12 lift hole plugged with woodTrout Brook West (North) 17+56 17+62 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 17+59 Access Point Manhole Access Point Manhole Steps 4 11Trout Brook West (North) 17+62 17+66 Miscellaneous Dimension/Diam/Shape Change 8 transitionTrout Brook West (North) 17+66 20+94 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 17+67 Tap Break-In/Hammer Tap Break-In/Hammer Active 0.75 11Trout Brook West (North) 17+97 Obstacles/Obstructions Object Protruding Thru Wall Tap Break-In/Hammer Intruding 1 1 2Trout Brook West (North) 20+94 21+00 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 20+98 Access Point Manhole Access Point Manhole Steps 4 1 steps good, albemarleTrout Brook West (North) 21+00 24+23 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 24+23 24+30 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 24+28 Access Point Manhole 4 1 woodbridgeTrout Brook West (North) 24+30 27+23 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 27+23 27+41 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 27+28 Access Point Manhole 4 11Trout Brook West (North) 27+41 33+96 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 31+82 Infiltration Dripper 9 through connectionTrout Brook West (North) 32+80 Point Repair Patch Repair Point Repair Patch Repair Defective 10Trout Brook West (North) 33+96 34+03 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 34+01 Access Point Manhole Access Point Manhole Steps 4 11Trout Brook West (North) 34+03 40+68 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook West (North) 34+60 Point Repair Patch Repair 2Trout Brook West (North) 34+62 Point Repair Patch Repair Point Repair Patch Repair Defective 11Trout Brook West (North) 34+69 Point Repair Patch Repair Point Repair Patch Repair Defective 10Trout Brook West (North) 34+84 Deposits Attached Encrustation 0.2 0.5 12 12Trout Brook West (North) 35+61 Tap Break-In/Hammer Tap Break-In/Hammer Active 0.5 1Trout Brook West (North) 36+35 Point Repair Patch Repair Point Repair Patch Repair Defective 11Trout Brook West (North) 36+47 Point Repair Patch Repair Point Repair Patch Repair Defective 11Trout Brook West (North) 36+82 Point Repair Patch Repair 11Trout Brook West (North) 39+88 Point Repair Patch Repair Point Repair Patch Repair Defective 11Trout Brook West (North) 40+68 40+75 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 40+73 Access Point Manhole Access Point Manhole Steps 4 11Trout Brook West (North) 40+75 43+48 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 41+24 Tap Break-In/Hammer Tap Break-In/Hammer Active 1 1 full of encrustationsTrout Brook West (North) 41+43 Tap Break-In/Hammer Tap Break-In/Hammer Active 1 1
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 25
Project
Trout Brook West (North) 49+58 Miscellaneous Survey End 11:30am
Trout Brook East (South) 8+25 Access Point Manhole Access Point Manhole Steps 4 1
Trout Brook East (South) 15+63 Access Point Manhole Access Point Manhole Steps 4 2
Trout Brook East (North) 15+40 Access Point Manhole Access Point Manhole Steps 2.5 1
*Tables Based on Reference from CNA Consulting Engineers 2007 Trout Brook Sewer Interceptor Logs - Dated September 27th, 2007
Trout Brook Sewer Inspection APPENDIX 1Tunnel Start End Description Modifier D H W L At To RemarksTrout Brook West (North) 43+48 43+54 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 43+50 Access Point Manhole Access Point Manhole Steps 4 11Trout Brook West (North) 43+54 45+96 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 45+44 Point Repair Patch Repair Point Repair Patch Repair Defective 1Trout Brook West (North) 45+96 46+02 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 45+99 Access Point Manhole 4 1Trout Brook West (North) 46+02 47+48 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook West (North) 47+48 47+57 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 47+57 48+28 Miscellaneous Dimension/Diam/Shape Change 7 6 RCPTrout Brook West (North) 48+28 48+33 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook West (North) 48+31 Access Point Manhole 4 11Trout Brook West (North) 48+33 49+58 Miscellaneous Dimension/Diam/Shape Change 7 6 RCP
Trout Brook East (South) 0+00 Miscellaneous Survey Start 7 3:45pm, 85 deg sunnyTrout Brook East (South) 0+05 0+09 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook East (South) 0+09 0+51 Miscellaneous Dimension/Diam/Shape Change 7.5 RCPTrout Brook East (South) 0+51 0+57 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook East (South) 0+51 8+38 Miscellaneous General Observation 3 2 6 9 start of sanitary sewerTrout Brook East (South) 0+51 8+38 Miscellaneous General Observation concrete spalling at SS boxTrout Brook East (South) 0+56 Access Point Manhole Access Point Manhole Steps 5 3 12 double lockdown hatch coverTrout Brook East (South) 0+57 4+82 Miscellaneous Dimension/Diam/Shape Change 7.5 RCPTrout Brook East (South) 4+82 4+88 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook East (South) 4+84 Access Point Manhole Access Point Manhole Steps 2 11Trout Brook East (South) 4+88 7+80 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook East (South) 7+80 8+23 Miscellaneous Dimension/Diam/Shape Change 6 6' dia shotcrete liningTrout Brook East (South) 8+23 8+44 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 8 10
Trout Brook East (South) 8+44 10+23 Miscellaneous Dimension/Diam/Shape Change 6 shotcrete lining
Trout Brook East (South) 10+23 11+34 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook East (South) 11+34 11+53 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 10 10Trout Brook East (South) 11+43 Access Point Manhole Access Point Manhole Steps 2.5 11Trout Brook East (South) 11+53 15+61 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook East (South) 15+46 Obstacles/Obstructions Object Protruding Thru Wall 3 2 2 10 at connectionTrout Brook East (South) 15+61 15+69 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 8 8 chamber
Trout Brook East (South) 15+69 Miscellaneous Survey End 4:35pm
Trout Brook East (North) 0+00 Miscellaneous Survey Start 4:35pm, 80 deg sunnyTrout Brook East (North) 0+00 Access Point Manhole 4 2 same as 15+63 Trout Brook East Extension - South LegTrout Brook East (North) 0+06 0+15 Miscellaneous Dimension/Diam/Shape Change 7Miscellaneous Dimension/Diam/Shape Change ChamberTrout Brook East (North) 0+15 6+15 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook East (North) 1+92 Infiltration Runner 3 4Trout Brook East (North) 2+57 Infiltration Runner 9Trout Brook East (North) 3+42 Point Repair Patch Repair 1Trout Brook East (North) 6+15 6+26 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 7 6Trout Brook East (North) 6+20 Access Point Manhole 4Access Point Manhole Steps 1Trout Brook East (North) 6+26 13+44 Miscellaneous Dimension/Diam/Shape Change 7 RCPTrout Brook East (North) 10+67 Point Repair Patch Repair 1Trout Brook East (North) 13+44 13+54 Miscellaneous Dimension/Diam/Shape Change Miscellaneous Dimension/Diam/Shape Change Chamber 8 6Trout Brook East (North) 13+52 Access Point Manhole Access Point Manhole Steps 4 11Trout Brook East (North) 13+54 15+42 Miscellaneous Dimension/Diam/Shape Change 7 RCP
Trout Brook East (North) 15+42 Miscellaneous Survey End 5:00pm
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 26
ESTIMATED COST SUMMARY
Trout Brook Storm Sewer Repair Work (Sta. 0+00 - 186+94) Comm. No.: 13017.002
Trout Brook Storm Sewer West Tunnel (Sta. 0+00 - 17+62) By: Ron Quanbeck
Date: 07/02/09
Repair Labor and MaterialProject Location Length Unit Unit Cost Total
6 Repair Work Sta. 0+00 - 19+93 1993 LF 40.50$ 81,000$ 7 Repair Work Sta. 23+15 - 28+49 534 LF 40.50$ 22,000$ 8 Repair Work Sta. 28+49 - 32+33 384 LF 40.50$ 16,000$ 9 Repair Work Sta. 32+33 - 33+34 101 LF 40.50$ 4,000$
10 Repair Work Sta. 33+62 - 59+45 2583 LF 40.50$ 105,000$ 11 Repair Work Sta. 112+76 - 136+16 2340 LF 40.50$ 95,000$ 12 Repair Work Sta. 136+16 - 168+73 3257 LF 40.50$ 132,000$ 14 Repair Work (West Tunnel) Sta. 0+00 - 17+62 1762 LF 40.50$ 70,000$
SUBTOTAL 12954 525,000$
TOTAL ESTIMATED PROJECT COST 525,000$
Notes:1 Unit Cost calculated from estmates in Figure 8.7 - 2007 CNA Tunnel Condition Report2 See Figure 1 and Table 1 for project location and schedule
APPENDIX #2
CRWD 2010 Watershed Management Plan - 9/1/2010 Appendix G - 27
top related