New elevated road
Creating four lanes in each
direction
Existing M4
Community update | July 2015Widening the M4 Motorway
Illustration only
Work is progressing on widening the M4 between Church Street, Parramatta and Homebush Bay Drive, Homebush, providing an additional lane in both directions for motorists and easing congestion on one of Sydney’s busiest roads.
Work is continuingNew elevated roads are being built and the existing M4 Motorway widened to create four lanes in each direction from Parramatta to Homebush. The additional lane and improved access onto the M4 will ease congestion for motorists and fix the significant pinch point at James Ruse Drive.
Rizzani Leighton Joint Venture was awarded the contract to build the project. It is anticipated the impact on traffic flow will be minimal as most of the work will take place off the roadway. Works will generally occur between 7am and 6pm, Monday to Friday and 8am and 1pm on Saturday, weather permitting. Rizzani Leighton will advise residents of any activities that may need to take place outside these times.
Motorists are asked to follow traffic signs and reduce speed. For up-to-date traffic information, please visit livetraffic.com or download the app, available on iOS and Android in the app stores.
The M4 Widening is jointly funded by the Australian Government and the NSW Government.
We’re building Tomorrow’s SydneyThe NSW Government is building an integrated transport solution including public transport and critical road infrastructure to keep Sydney moving.
WestConnex will widen and extend the M4 and M5 and join them together to form a 33-kilometre continuous free flowing motorway with connections to the city, airport and port. WestConnex will provide relief to the hundreds of thousands of motorists struggling in traffic congestion every day and help return local streets to local residents along these corridors.
M5
M4
Hurstville
Bankstown
Homebush
SydneyOlympic
Park
Rhodes
ConcordAuburn
Granville
Lidcombe
Chullora
Burwood
Summer Hill
Arncliffe
BeverlyHills
Roselands
Campsie
Punchbowl
Riverwood
Five Dock
Strathfield
Botany
Mascot
St Peters
Petersham
Leichhardt
Haberfield
Camperdown
Strathfield South
Sydney
BondiJunction
St Leonards
Botany Bay
NorthSydney
Parramatta
Port Botany
Alexandria
Ryde
Sydney Airport
Jam
es R
use
Driv
e
M5 East
Kingsgrove R
oad
Silv
erw
ater
Roa
d
Roo
kwoo
d R
oad
Hume
Highway
Con
cord
Ro
ad
King Georges R
oad
Fairf
ord
Roa
d
Homeb
ush
Ba
y D
riv
e
City West Link
Ea
ste
rnD
istr
ibu
tor
AnzacBridge
M4 Motorway Hill
Roa
d
Southe
rn C
r os
s D
rive
Foreshore Road
Prince
s High
way
Prince
s
Highway
Gra
nd P
arad
e
PresidentAvenue
Victoria Road
CampbellStreet
Gardeners Road
QantasDrive
Eus
ton
Roa
d
Airport
Drive
Centenary D
rive
Woo
dvill
e R
oad
Bexley R
oad
Chu
rch
Str
eet
Parramatta Road
Parramatta Road
Connection
Surface
Tunnel
New extensionunder investigation
Existing M5 Eastconnection
WestConnex indicative corridor
M4 WideningStart 2015
Completed 2017
Proposed Southern Extension
M4 EastStart 2016
Completed 2019
M4-M5 LinkStart 2019
Completed 2023
New M5Start 2015
Completed 2019
WestConnex project overview
Phone: 1300 660 248 | community.info@RLJV.com.au | westconnex.com.au
We’re building Tomorrow’s Sydney
M4
WID
ENIN
G
M4
MO
TOR
WAY
M4
EAST
M4
WID
ENIN
G
SYDNEYOLYMPIC
PARK
SYDNEYOLYMPIC
PARK
SILVERWATERSILVERWATERGRANVILLEGRANVILLE
HARRISPARK
HARRISPARK
HOLROYDHOLROYD
PARRAMATTAPARRAMATTA
GRANVILLEPARK
HOMEBUSHBUSINESS PARK
LIDCOMBEBUSINESS
PARK
DUCKRIVER
DUCKCREEK
EXISTING NEW
Typical cross section of additional elevated roadway
(Church Street to Wentworth Street)
TO SYDNEY CBD TO PARRAMATTA
4 laneseach way
New bridge over Duck River
Widening within M4 Motorway corridor
Upgraded roads
New lanes/improved ramp
Road
Traffic flow
Community Information Centre
Temporary Work Compound
LEGEND
HAWKSVIEW STREET
PIT
T S
TR
EE
T
WILLIAM STREET
WO
OD
VIL
LE
RO
AD
PARRAMATTA ROAD
WE
NTW
OR
TH
STR
EE
T
JAM
ES
RU
SE
DR
IVE
AL
FR
ED
ST
RE
ET
GO
OD
ST
RE
ET
HA
RR
IS S
TR
EE
T
HASSALL STREET
ALLEN STREET
VICTORIA ROAD
RAW
SON STR
EET
BEACONSFIELD STREET
BLIGH STREETDEAKIN STREET
CARNARVON STREET
SK
AR
RA
TT S
TREET
STU
BB
S S
TREET
ST H
ILLI
ERS
RO
AD
SIL
VER
WA
TER
RO
AD
HIL
L R
OA
D
OLY
MP
IC D
RIV
E
CE
NTE
NA
RY
DR
IVE
PARRAMATTA ROAD
BR
IDG
E
RO
AD
CO
LE
MA
NS
TR
EE
T
PARRAMATTA ROAD
HOMEBUSH BAY DRIVE
JUN
CTI
ON
STR
EE
T
CH
UR
CH
ST
RE
ET
M4 MOTORWAY
M4 MOTORWAY
M4 MOTORWAY
James Ruse Drive
Silverwater Road bottleneck eased with longer ramps.
Sports fans and concert goers will be able to avoid traffic jams with direct eastbound access to the M4 Motorway.
Four lanes in each direction on M4 Motorway to ease congestion.
Silverwater Road connections
New Olympic Park connection eastbound
New Homebush Bay Drive connection
Widening the M4 Motorway Map not to scale – indicative only
Motorists from the north bypass traffic lights for direct access to the M4 Motorway. North/south congestion will be eased.
Phone: 1300 660 248 | community.info@RLJV.com.au | westconnex.com.au Phone: 1300 660 248 | community.info@RLJV.com.au | westconnex.com.au
Learn more by visiting www.westconnex.com.au/yourlanguage to watch project videos in your language and read more about WestConnex. If you need an interpreter, call the Translating and Interpreting Service on 131 450.
Arabic اعرف املزيد بزيارة املوقعwww.westconnex.com.au/yourlanguage
وذلك ملشاهدة الفيديوهات الخاصة باملرشوع باللغة العربيةوقراءة املزيد عن وست كونكس. إذا كنت يف حاجة إىل
مرتجم، اتصل بخدمة الرتجمة الخطيّة والشفهيّة عىل الرقم .131 450
Chinese了解詳情請上網 www.westconnex.com.au/yourlanguage觀看(普通話)視頻, 並查閱有關WestConnex的更多訊息。如需要傳譯員請。。 撥電話傳譯服務 131 450
Hindi:ँएाप ीराकनाज किधअ रप टईासबेव सइ
www.westconnex.com.au/yourlanguage सइ ंेम )ीद्निह( व ंेम ेराब ेक स्केनॉकट्सेव रऔ ंेखेद ंोयिडीव ंेम ेराब ेक ानजोयिरप
व दावुनअ ोत एिहाच ायिषाभुद ोकपआ िदय ।ें ़ढप ीर्गमास किधअ रऔ ोक ावेस ायिषाभुद 131 450 ।ेंरक नो़फ रप
GreekΜάθετε περισσότερα επισκεπτόμενοι το www.westconnex.com.au/yourlanguage για να δείτε τα βίντεο του έργου στα ελληνικά και να διαβάσετε περισσότερα για το WestConnex. Εάν χρειάζεστε διερμηνέα, καλέστε την Υπηρεσία Μετάφρασης και Διερμηνείας στο 131 450.
ItalianPer saperne di più visiti il sito www.westconnex.com.au/yourlanguage, dove potrà guardare i video del progetto in lingua italiana e trovare maggiori informazioni su WestConnex. Se ha bisogno di un interprete, contatti il Servizio di Traduzione ed Interpretariato (Translating and Interpreting Service) al numero 131 450.
Koreanwww.westconnex.com.au/yourlanguage 를 방문하여한국어로 된 프로젝트 비디오를 보고 WestConnex 에 관해 읽고 배우세요. 통역이 필요하시면 번역 및 통역 서비스 131 450 (TIS) 으로 전화하십시오.VietnameseHãy tìm hiểu thêm và viếng trang mạng www.westconnex.com.au/yourlanguage để xem phim ảnh bằng Việt ngữ về công trình này và đọc thêm về WestConnex. Nếu quý vị cần thông ngôn viên, xin vui lòng gọi Dịch Vụ Thông Ngôn Phiên Dịch số 131 450.
We speak your language
Extending the M4Following an extensive assessment process Leighton Samsung John Holland was selected to deliver the extension of the M4 Motorway from Homebush to Haberfield.
The extension will end the bottleneck at the end of the M4, saving travel time for motorists and removing cars off local streets.
The M4 will be extended by building twin tunnels from Homebush to Parramatta Road and the City West Link, Haberfield. The tunnels will have three lanes in each direction and connect to the work already started on Stage 1, widening the M4 Motorway from Church Street, Parramatta to Homebush Bay Drive, Homebush.
Motorists can enter and exit the M4 East tunnel at:
• The M4 Motorway at Homebush
• Concord Road at North Strathfield
• Parramatta Road at Haberfield
• City West Link at Haberfield
Visit usYou are welcome to drop into our Community Information Centre at Silverwater or visit westconnex.com.au for more information.
M4 Widening Community Information Centre
Location: 75 Carnarvon Street, Silverwater Ground level (Corner of Stubbs and Carnarvon streets)
Times: Monday to Friday, 8.30am to 5pm (excluding public holidays)
M4 Western Motorway
Silv
erw
ater
Ro
ad
Stub
bs S
tree
t Carnarvon StreetAsquith StreetBeaconsfield Street
Community Information Centre75 Carnarvon Street
Community update | July 2015Widening the M4 Motorway
Easing congestion
Creating jobs
Connecting communities