The Challenge to Install 1,300 New Water Meters

ScopeScope

• Install electromagnetic meters (mostly) + telemetry + solar power

• ~700 sites in Upper Murray Valley

• ~600 sites in Murrumbidgee Valley

• Data forwarded to NOW and SWC

Sites: Upper MurraySites: Upper Murray

• Regulated, unregulated and groundwater sites

Sites: MurrumbidgeeSites: Murrumbidgee

• Regulated entitlement licences only

Challenge 1: Early PlanningChallenge 1: Early Planning

• Align stakeholder expectations

• Scope the practical challenges in detail

• Integrate two projects into a single contract

• Ensure legislative backing (installing meters into private infrastructure)

• Collect extensive site data

• Prepare project plan

Challenge 2: ProcurementChallenge 2: Procurement

• Appoint Managing Contractor

• Draft the meter specifications and establish supply contracts.

Challenge 3: Detailed PlanningChallenge 3: Detailed Planning

• Site data proofing

• Prepare concept designs

• Identify resource requirements

• WHS, QA and Environmental assessment procedures

• Prepare a work schedule

• Establish the Guaranteed Maximum Price

• Review and approve

Challenge 4: ImplementationChallenge 4: Implementation

• Landholder consultation

• Appoint subcontractors

• Site variability (!)

• Buried sites (unable to inspect prior)

• Clarity in specifications for installers

• Consistency in subcontractor outputs (QA)

Murray StatusMurray Status

(31 May 2012)(31 May 2012)

Murrumbidgee StatusMurrumbidgee Status

(31 May 2012)(31 May 2012)

Original SiteOriginal Site

Original SiteOriginal Site

Original SiteOriginal Site

STW

Original SiteOriginal Site

Original SiteOriginal Site

Site Under ConstructionSite Under Construction

Completed SiteCompleted Site

Completed SiteCompleted Site

LessonsLessons

• Require reliable site data

• Regulatory support is critical

• Benefits from an experienced team

• Appropriate landholder consultation

• Need for some flexibility

• Clear specifications and quality control

• Good data management

• Fast roll-out possible with good planning.