PUTERI HARBOUR OVERVIEWDevelopment info :
• Total Development area : 1082 acres (Puteri Harbour & Estuari)
• 1st layout approved on 2008
Photo as of 12 Oct 2018
REJUVENATING PUTERI HARBOUR AS PART OF COOL IP INITIATIVE
Iskandar Puteri (IP) as the preferred location for retailers, F&B, and entertainment
Estuari 1C : One˚15 Estuari Sport Center
Completion : Q4 2019
Water Garden & Sandy Beach
Completion : Q2 2019
Tanjung Point Park
Completion : Q4 2020
TM1 : One˚15 Marina Puteri Harbour
Grand Opening : Q1 2021
TH1-1 @ Puteri Harbour
Target to commence : Q2 2021
Tanjung Marina Promenade
Completion : Q4 2019
REJUVENATING PUTERI HARBOUR : INFRASTRUCTURE
Architecture Prospective
Architecture Perspective
One˚15 Marina Puteri Harbour
Water Garden & Sandy Beach Tanjung Point Park Tanjung Marina Promenade
Puteri Harbour Marina Promenade
Architecture Perspective
One˚15 Estuari Sport Center
FUTURE INFRASTRUCTURE
Puteri Harbour Linear Park
Size 2.80 acre
Februa February 2019
Target Completion
August 2019
▪ Pond view
▪ Garden Facilities
▪ Viewing Deck
FUTURE INFRASTRUCTURE
Size 3.45 km of roads
Start Date June 2016
Completion Oct 2018
Key Features
▪ 1-way street for main road
▪ Dedicated bus & bicycle lane
▪ Braille tile
Current Status ▪ Laksamana 2 (Access to Almas Phase 1). Others road already complete.
Puteri Harbour Road Upgrading (Southern Area)
Teega
YSL Freshmart
My News.com
Arashi
Tribus
BUILDING COMMUNITIES: F&B, RETAIL AND PLACEMAKING
Imperia
Yum Shabu
Kinsahi
UEMS Southern Sales Gallery Puteri
Harbour
Ferry to Batam & TgBalai
Shuttle Bus IP to JB
All Year Round Celebrations
‘Makan’ Spot
BUILDING COMMUNITIES : PLACEMAKING EVENTS
DINASOUR KINGDOM
20 Nov –
1 Jan 2019
MOSCOW
CIRCUS
20 Nov –
31 Dec 2018
ISKARNIVAL ‘MAIN-MAIN’
8 - 9
Dec 2018
ISKANDAR PUTERI CONNECTIVITYConnectivity – Current transport available in Puteri Harbour, Iskandar Puteri
• Complimentary shuttle service brought to you by UEM Sunrise & Medini Iskandar Malaysia
• Current Status : 3 number of buses operational since 1 September 2018.
• Pending 1 more bus – pending insurance clearance by Finance. Target operating date is on 1st December2018.
• PHIFT ←→ Puteri Cove ←→ Imperia ←→ Teega ←→ Kota Iskandar ←→ Sunway Iskandar ←→ SunwayInternational School ←→ Medini 6 & 7 ←→ Gleneagles Medini ←→ Mall of Medini ←→ Afiniti Medini←→ Somerset Medini ←→ Legoland ←→ 1 Medini ←→ Educity ←→ East Ledang ←→ Anjung ←→Larkin Sentral
FREE SHUTTLE SERVICE
ISKANDAR PUTERI CONNECTIVITY• Proposed Route - Phase 2 Community Shuttle
M6/M7
Rumah Iskandar
Malaysia (RIM) –
Gelang Patah
Bukit Indah
Taman
Nusa Perdana - Afiniti Medini
- Somerset Medini
- 1 Medini
- Sunway Iskandar
- Sunway
International
School
- Imperia
- Teega
- Puteri Cove
- Ledang
Clubhouse
- Ujana
- Nusajaya Center
- Tesco
Iskandar Puteri Community Shuttle
Service
Route
Route 1 (Morning & Evening only)
RIM - PHIFT
Route 2 Edu City - PHIFT
Route 3(existing)
Terminal Larkin -PHIFT
Route 4 Bukit Indah
Note:-
• Awaiting permit approval from Land Public Transport Commission (SPAD) on the proposed route
Note:Route 1-3 are in operation.Route 4 – Target to commence by 1st December 2018
ISKANDAR PUTERI BUS SCHEDULE
Note:-
• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)• There will be changes in the schedule once 4th bus is in operation.
STATUS UPDATE
NO UPGRADING ITEM STATUS DATELINE
Other upgrading;
Badminton/Basketball court
3. Ventilation – Installation of Exhaust Fan Completed -
4. Benches Completed -
Signages
5. Tower A exit to Jalan Laksamana Boulevard- To add exit signage
Completed -
6. Installation of 2nos of Electric Charging Point for hybrid car
Completed -
NO UPGRADING ITEM STATUS DATELINE
Suites
1. Propose Suites Upgrading – Installation of Big 10 ft fan
Completed
2. Propose Suites Upgrading - Loading/unloading bay path way
Awarded. Included in signages contract.
-
STATUS UPDATE
13. WIFI Service in Common Area and Lifts Others are completed.Pending installation in Cabana Lift only.
June 2018
10. WIFI Service in Common Area and Lifts Completed. Aug 2018
11. Water dispenser Delivered. -
12. Mosquito repellant bulb Delivered. July 2018
13. Missing Links Roof at E-deck Awarded. Work in progress.
Feb 2019
14. Child care and multipurpose room furnishings Awarded. Jan 2019
15. Upgrading of fencing Awarded. 90% completed, pending fencing at LG only.
Jan 2019
16. Signages Upgrading Awarded – 50 % completed
Jan 2019
17. Security Upgrading Awarded. Jan 2019
NO UPGRADING ITEM STATUS DATELINE
Changing Room
7. Installation of Changing Room Fittings(hanger, towel racks and locker)
Completed. July 2018
9. Benches Completed. -
FIT-OUT WORKS• Project duration : 12th November 2018 – 21st January 2019 (10 weeks)• Items included under this project are as follows;
No. Location Item
1. Fit-out for childcare centre • Indoor Play area• Reading nook(Please refer to Perspective)
2. Cabana Lobby • Arm chair and coffee table
3. Games Room • Storage Cabinet to be fixed
4. Multipurpose Room / Function Room (E-deck Tower A & B)
• Foldable rectangular table• Block Curtain• Additional Banquet Chair
5. Pantry at Multipurpose / Function Room (Sky-lounge Tower A, B & Suites)
• Cabinet and wash basin
6. Mailroom at Suites • To provide metal strips at corner to avoid crack/damages to the glass.
TEEGA RETAIL LOTS
GROUND LEVEL
LOWER GROUND
Teega Handover Office
Tribus Café SUTL Sales Gallery
Note: 1. Occupied unit delineated in green2. Units in negotiation delineated in yellow3. Vacant unit delineated in red
SUTL-One Degree 15 Marina Puteri HarbourTarget to open: 1 October 2018
YSL FreshmartTarget to open: 1 December 2018The Tribus
Target to open: 1
December 2018
COMMON AREA DEFECTS UPDATE
Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.
OVERALL PROGRESS
CLOSED/ COMPLETED
1671(78.2%)
WIP/ NEW
466(21.8%)
PREVIOUS DEFFECT RECTIFICATION WORK PROGRESS
1 SEPTEMBER 2018 - 30 SEPTEMBER 2018
CLOSED/ COMPLETED
1831(84.2%)
WIP/ NEW
343(15.8%)
CURRENT DEFECTS RECTIFICATION WORK PROGRESS
1 OCTOBER 2018 - 31 OCTOBER 2018
DEFECTS RECTIFICATION WORK RECORD
DESCRIPTION
TEEGA TOWER
(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK
CONDOMINIUM
E-DECKRETAIL
SERVICE
APARTMENT
E-DECK
TOTAL
DEFECTS
PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT
Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18
CLOSED/
COMPLETED 220 250 560 602 145 183 227 247 14 21 427 437 20 20 39 46 19 25 1671 1831
WIP/ NEW 20 9 51 12 117 91 183 164 7 0 35 25 21 23 18 11 14 8 466 343
LODGED 240 259 611 614 262 274 410 411 21 21 462 462 41 43 57 57 33 33 2137 2174
Variance, σClosed : 160
WIP : -123
COMMON AREA DEFECTS UPDATE
423
678
868
1000
1208
1454
1671
1831
1163
1045
901
810742
641
466
343
0
200
400
600
800
1000
1200
1400
1600
1800
2000
Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18
NU
MB
ER
OF
DE
FE
CT
S
MONTH
COMMON AREA DEFECTS RECTIFICATION WORK PROGRESSMARCH 2018 - SEPTEMBER 2018
Completed/Closed Work In progress (WIP)
Variance, σClosed : 217
WIP : -175
Variance, σClosed : 246
WIP : -101Variance, σClosed : 208
WIP : -68Variance, σClosed : 132
WIP : -91
Variance, σClosed : 190
WIP : -144
Variance, σClosed : 225
WIP : -118
Variance, σClosed : 160
WIP : -123
Defects / Month Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18
Completed/Closed 423 678 868 1000 1208 1454 1671 1831
Work In progress (WIP) 1163 1045 901 810 742 641 466 343
Closed/Completed Variance, s - 255 190 132 208 246 217 160
Work in Progress (WIP), s - -118 -144 -91 -68 -101 -175 -123
COMMON AREA DEFECTS UPDATE
Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.
WORK IN PROGRESS BY AGING
DEFECTS < 30 DAYS
109(23.4%)
DEFECTS > 30 DAYS
356(76.6%)
PREVIOUS WORK IN PROGRESS (WIP) BY AGING
01 SEPTEMBER 2018 - 30 SEPTEMBER 2018
DEFECTS < 30 DAYS
18(5.2%)
DEFECTS > 30 DAYS
325(94.8%)
CURRENT WORK IN PROGRESS (WIP) BY AGING
1 OCTOBER 2018 - 31 OCTOBER 2018
WORK IN PROGRESS (WIP) DEFECTS CATEGORY BY AGING
DEFECTS
AGING
TEEGA TOWER
(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK
CONDOMINIUM
E-DECKRETAIL
SERVICE
APARTMENT
E-DECK
TOTAL
DEFECTS
PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT
Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18
DEFECTS < 30
DAYS 11 1 9 0 29 10 21 2 0 0 11 2 8 2 16 1 4 0 109 18
DEFECTS > 30
DAYS 9 8 42 12 88 81 161 161 7 0 24 23 13 21 2 11 10 8 356 325