Technical planning - organisationTechnical planning - organisation
« MEditerranean Development of Innovative Technologies for
integrAted waTer managEment »
Kick-off meeting [7th-8th May 2004]
Work packages Status• Integrated compound of the project• Under the responsibility of the WP leader• Aware of the links with other Wpackages
WP0: Overall management of the MEDITATE project
WP 1 : (A) Hydrogeological catchments characterisation and (B) aquifers - catchment modelling
WP 2 : Socio-economic study
WP 4 : WMSS methodology, development, implementation
WP 3 : Technological innovation
WP 5: Dissemination, technology transfer
Participants to WP• Man months of different partners have been decided
in the W description,– to contribute on the good results of the WP, – in order to achieve the objectives of the WP and of
the MEDITATE project• Shared responsibility of partners involved in WP
under the co-ordination of the WP Leader
Participants to MEDITATE
Participants to MEDITATE
Organisation, direction of research, responsibilities
Management group
Partner responsibility
Wp leader responsibility
Deliverables - planning 1st year
• Respect of the delay for Deliverables and milestones
• If problems, refer to the co-ordinator => management : arguments, decision to postpone….
Deliverables - planning 1st year
Deliverables - planning 1st year
D10 Collated report oncase study socio-political andgovernancecircumstances
2 CRANFIELD R PU 12
D11 Report on vehicle(AUV) test
3 CNRS-LIRMM-HSM
R PU 12
D9 Intermediate ProjectReport
0 BRGM R PU 12
Exchanges, communication• E-mail exchanges Newsletter every 3 months or for specific events or
results, written by the co-ordinator with contribution of WP leaders
• Newsletters send by e-mail and stored on the website (specific Newsletters sections on the home page; chronological number)
• When Partner faces problems, please refer it to the co-ordinator which will find solutions with the Management group
Next meetings in 2005-2007• Meeting in April 2005 in Lebanon• Meeting in Dec-Jan 2005-06 in Syria• Meeting in Sept-Oct 2006 in Jordan• Meeting in April 2007 in Montpellier – L or S or T or J ?
Miscellaneous
Thanks !
Lookingforewardworkingwith you !