My Home Vihanga Status Report

TRANSCRIPT

Project Progress – 25th Jan 2014

BLOCK-1 SOUTH SIDE VIEW

BLOCK-1 BEAM BOTTOM SHUTTERING STARTED FOR BASEMENT-2 SLAB

BLOCK-1 BEAM BOTTOM SHUTTERING STARTED FOR BASEMENT-2 SLAB

BLOCK-2 COLUMNS ABOVE GRADE SLAB IN PROGRESS

BLOCK-2 SOUTHSIDE VIEW

BLOCK-1&2 GRADE SLAB DONE & CURING IN PROGRESS-NORTH SIDE VIEW

BLOCK-2 NORTH-EAST SIDE CORNER BEAM BOTTOM SHUTTERING IN PROGRESS

BLOCK-3 PCC & FOOTINGS IN PROGRESS

BLOCK-3 PCC & FOOTINGS IN PROGRESS

BLOCK 19 NORTH WEST CORNER PCC & FOOTINGS IN PROGRESS

BLOCK -19 NORTH WEST SIDE PCC & FOOTINGS IN PROGRESS

TOWER CRANE FOUNDATION DONE IN BLOCK 19

BLOCK-20 WORK UNDER PROGRESS

RETAINING WALL-SOUTH SIDE WORK UNDER PROGRESS

PART-1/SVS 17 &18 BLOCKS IN PROGRESS

PART-1/SVS 17 &18 BLOCKS IN PROGRESS

PART-2/JBEM BLOCK 5 & 6 IN PROGRESS

PART-2/JBEM BLOCK 15 &16 IN PROGRESS

PART-3/GBL BLOCK 7 &8 IN PROGRESS

PART-3/GBL BLOCK 13 &14 IN PROGRESS

PART-4/CEIPL BLOCK 9 &10 IN PROGRESS

PART-4/CEIPL BLOCK 11 &12 IN PROGRESS

WEIGH-BRIDGE CONSTRUCTION DONE ,ERECTION TO BE DONE

SAFETY TOOL BOX MEETING HELD IN SITE