my home vihanga status report as on 22.04.2014

16
Project Progress – 22 nd April,2014

Upload: praveen-kumar-bonala

Post on 24-May-2015

2.339 views

Category:

Real Estate


0 download

TRANSCRIPT

Page 1: My home vihanga status report as on 22.04.2014

Project Progress – 22nd April,2014

Page 2: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”01” As On 22nd April,2014

1.Basement –II Slab Completed 2.Basement-I 2,3,4 Flats Slab Completed,1,5,6 Bar Bending Completed

Page 3: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”02”As On 22nd April,2014

1.Basement –II Slab Completed 2.Basement-I 2,3-Flats Shuttering Completed,1,4,5,6 flats Columns Completed

Page 4: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”03” As On 22nd April,2014

1.Footing work Completed2.Preparing for Grade Slab

Page 5: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”04” As On 22nd April,2014

1.Footing work Completed2.Preparing for Grade Slab

Page 6: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”05 & 06” As On 22nd April,2014

1.Earth Work In Progress

Page 7: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”07 & 08” As On 22nd April,2014

1.Earth Work In Progress

Page 8: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”09 & 10” As On 22nd April,2014

1.Earth Work In Progress

Page 9: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”11 & 12” As On 22nd April,2014

1.Earth Work In Progress

Page 10: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”13 & 14” As On 22nd April,2014

1.Earth Work In Progress

Page 11: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”15” As On 22nd April,2014

1.PCC-Started

Page 12: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”16” As On 22nd April,2014

1.Ready For PCC

Page 13: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”17” As On 22nd April,2014

1.Footing Competed2.Columns Bar Bending work In Progress

Page 14: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”18” As On 22nd April,2014

1.PCC Competed

Page 15: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”19” As On 22nd April,2014

1.Basement –II Slab Completed Except Flat No 1,6 2.Basement-II Flat No 1, 6 Shuttering work In Progress

Page 16: My home vihanga status report as on 22.04.2014

STATUS REPORT OF MY HOME VIHANGA Block--”20” As On 22nd April,2014

1.Grade Slab Completed2.Columns Bar Bending Work In Progress