state and local road project updates: part 2
Post on 21-Jan-2015
609 Views
Preview:
DESCRIPTION
TRANSCRIPT
2011 Charlotte Regional Transportation Summit
April 8, 2011
Division 10 Project Updates
MUMPO Orientation
State Transportation Improvement Program (STIP)
Schedule:
Draft STIP will cover the 12-18 Fiscal Years
Anticipated Draft TIP should be adopted in July 2011
State Transportation Improvement Program
Facts:
Statewide Equity Budget is Projected to be $9.21 Billion.
Does not include Loop Program Dollars
Does not include Public Transportation Dollars
Or Congestion Mitigation/Air Quality Dollars
State Transportation Improvement Program
Division 10:
Our 10 Year Work Plan Proposes to Bring $2,659,500,960 into our Region.
Also we are currently working on a new Loop Prioritization process as well as the Mobility Fund Prioritization.
This could bring additional dollars to the region.
Up Coming Projects
R-2248E
The last roadway section of I-485 and in conjunction with R-2123CE will complete the 485 loop.
Contract to be let to bid May 28, 2010.
$185 Million
Let T
o Contra
ct
Let T
o Contra
ctR-2123CE
Interchange of I-485 and I-85. The other project to complete the loop. High speed design interchanging freeway to freeway.
Contract to be let to bid September 2, 2010.
$155 Million
I-3803B
Widening of I-85 from interchange with I-485 to the interchange with NC 73. Project is 5.5 miles long and will widen to an 8 lane section.
Contract to be let to bid August 5, 2010.
$200 MillionLet T
o Contra
ct
R-2248H
Complete interchange at Garrison Rd and will serve both CLT Airport and Norfolk Southern Inter-modal facility current under construction. Good example to partnership with both the Airport and Railroad. Will be completed before Inter-modal facility opens.
Contract to be let to bid July 2010.
$1.5 MillionLet T
o Contra
ct
R/W U
nderway
U-0209B
Converting Independence Blvd. to Expressway from Albemarle Rd. to Conference Drive. Will provide for center lanes for future transit and/or managed lanes.
Contract to be let to bid July 2012 with R/W beginning May of this year.
$170 Million
R-4902
Widen I-485 from existing 4 lanes to 6 lanes with auxiliary lanes between Johnston Road and NC 51. 6.6 Miles
Current Let Date is scheduled for FY 2014. With an Anticipated Cost of $70 Million.
Let Date Moved to February 2012
I-4733
Reconstruction of Catawba Ave. interchange with I-77. Originally proposed as new interchange at a cost of $35 million. Has a federal earmark of $5 million.
Looking at the use of a Diverging Diamond design which will reduce cost to $6 million and will use the existing bridge.
Monroe Bypass
The Monroe Bypass; this will be a Design Build contract administered by the Turnpike Authority.
RFQ Advertisement April 15, 2010
Bid Opening October 22, 2010
Approx. Cost $750 million
Rail Projects
Two rail projects will be let to contract within next two years as part of the $545 million NC received through competitive ARRA grants.
12 Double track as part of high speed rail.
Norfolk Southern/CSX grade separation
$250 million
I-5405
I-277 (BROOKSHIRE FREEWAY) TO WESTCATAWBA AVENUE (EXIT 28).
CONSTRUCT HIGH OCCUPANCY TOLL(HOT) LANES AND CONVERT EXISTING
HIGH OCCUPANCY VEHICLE (HOV) LANESTO HIGH OCCUPANCY TOLL (HOT)
Estimated Cost $64 Million
I-3802A
Widening of I-85 for the existing 4 lanes to 8 lanes from NC 73 to Rowan County Line.
New Let Date January 2013 from last TIP of 2017.
Estimated Cost $120 Million.