shivam patel cm option technical assignment 1 dr ed gannon september 16 th 2013 image courtesy of...
Post on 17-Jan-2016
212 Views
Preview:
TRANSCRIPT
Shivam PatelCM Option
Technical Assignment 1
Dr Ed Gannon
September 16th 2013
The Tower
Image courtesy of Hines
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation• Privately owned real estate firm
• Purpose for building The Tower?
• Cost, quality, schedule, safety expectations
• Sequencing issues
• Keys to completing project to satisfaction
Images from Hines website
OwnerHines
Design/Production Architect
Pei Cobb Freed & Partners
Ground Lessor/OwnerPacolet/Milliken Enterprises, IncConstruction Manager
Turner Construction Company
PlumbingJES Plumbing & Heating
Excavation/FoundationUrban Engineering/
Foundation
ElectricalFive Star Electrical Corp
MasonryKelly Masonry Corporation
Structural SteelW & W Steel, LLC
HVACWDF, Inc
Curtain WallBenson Industries
All Other Subcontractors
MEP EngineerJaros, Baum, & Bolles
Structural EngineerThornton Tomasetti
Civil EngineerLangan Engineering &
Environmental Services
All Other Engineers
Lump Sum Contract
Leasing Agreement
GMP contract with CM @ RiskCommunication
Legend
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation
Project ExecutivePat Murray
Project ManagerMike Nolan
Project SuperintendentRandy Brzezinski
Project EngineerSusan Fusi
MEP ManagerArthur D’Antonio
Project AccountantCraig Buxbaum
MEP EngineerChris Stafford
BIM Engineer Pushkar
Mahabaleshwarkar
Assistant EngineerMarjorie Mayrock
Arch EngineerNoah Payne
Arch EngineerChristopher Mase
Arch EngineerAoivne Reid
SuperintendentJohn Ingerson
Safety Superintendent
Anthony Reneaud
Assistant Superintendent
Mohammed Sheikh
Site Safety ManagerRonald Mark
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost EvaluationYes No Scope of Work X Demolition RequiredX Structural Steel FrameX Cast in Place Concrete X Precast ConcreteX Mechanical SystemX Electrical System
X MasonryX Curtain WallX Support of Excavation
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost EvaluationYes No Scope of Work X Demolition RequiredX Structural Steel FrameX Cast in Place Concrete X Precast ConcreteX Mechanical SystemX Electrical System
X MasonryX Curtain WallX Support of Excavation
Client Information Project Delivery System Staffing Plan
Existing Conditions Schedule Summary Systems Summary
Cost Evaluation
Building System System Total (Turner) System Total (SF Estimate) $/SF (Turner) Percent of Total $/Sf (SF Estimate) Percent of Total2Excavation and Foundations 12,292,510.00$ 3,516,000.00$ 28.43$ 7.13% 8.36$ 4.35%Superstructure Concrete 19,457,000.00$ 16,492,500.00$ 45.01$ 11.29% 38.67$ 20.40%Curtain Wall/Storefront Panels 26,154,000.00$ 16,560,000.00$ 60.50$ 15.17% 38.62$ 20.50%Roofing and Waterproofing 1,296,000.00$ 521,000.00$ 3.00$ 0.75% 1.28$ 0.64%Electrical 22,276,380.00$ 12,291,500.00$ 51.53$ 12.92% 28.84$ 15.20%HVAC 21,009,090.00$ 10,638,500.00$ 48.60$ 12.19% 24.91$ 13.20%Equipment/Hoisting 5,042,000.00$ 3,678,000.00$ 11.66$ 2.93% 8.61$ 4.55%Plumbing 4,833,000.00$ 2,534,500.00$ 11.18$ 2.80% 5.93$ 3.13%
Construction Cost 162,803,910.00$ 80,855,000.00$ 379.74$ 189.54$ Total Project Cost 208,000,000.00$ 107,132,000.00$ 398.72$ 251.14$
Thank You
Questions?
top related