Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 The Tower Image courtesy of Hines

Upload: quentin-robertson

Post on 17-Jan-2016

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Shivam PatelCM Option

Technical Assignment 1

Dr Ed Gannon

September 16th 2013

The Tower

Image courtesy of Hines

Page 2: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation• Privately owned real estate firm

• Purpose for building The Tower?

• Cost, quality, schedule, safety expectations

• Sequencing issues

• Keys to completing project to satisfaction

Images from Hines website

Page 3: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

OwnerHines

Design/Production Architect

Pei Cobb Freed & Partners

Ground Lessor/OwnerPacolet/Milliken Enterprises, IncConstruction Manager

Turner Construction Company

PlumbingJES Plumbing & Heating

Excavation/FoundationUrban Engineering/

Foundation

ElectricalFive Star Electrical Corp

MasonryKelly Masonry Corporation

Structural SteelW & W Steel, LLC

HVACWDF, Inc

Curtain WallBenson Industries

All Other Subcontractors

MEP EngineerJaros, Baum, & Bolles

Structural EngineerThornton Tomasetti

Civil EngineerLangan Engineering &

Environmental Services

All Other Engineers

Lump Sum Contract

Leasing Agreement

GMP contract with CM @ RiskCommunication

Legend

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation

Page 4: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Project ExecutivePat Murray

Project ManagerMike Nolan

Project SuperintendentRandy Brzezinski

Project EngineerSusan Fusi

MEP ManagerArthur D’Antonio

Project AccountantCraig Buxbaum

MEP EngineerChris Stafford

BIM Engineer Pushkar

Mahabaleshwarkar

Assistant EngineerMarjorie Mayrock

Arch EngineerNoah Payne

Arch EngineerChristopher Mase

Arch EngineerAoivne Reid

SuperintendentJohn Ingerson

Safety Superintendent

Anthony Reneaud

Assistant Superintendent

Mohammed Sheikh

Site Safety ManagerRonald Mark

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation

Page 5: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation

Page 6: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation

Page 7: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost EvaluationYes No Scope of Work X Demolition RequiredX Structural Steel FrameX Cast in Place Concrete X Precast ConcreteX Mechanical SystemX Electrical System

X MasonryX Curtain WallX Support of Excavation

Page 8: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost EvaluationYes No Scope of Work X Demolition RequiredX Structural Steel FrameX Cast in Place Concrete X Precast ConcreteX Mechanical SystemX Electrical System

X MasonryX Curtain WallX Support of Excavation

Page 9: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Client Information Project Delivery System Staffing Plan

Existing Conditions Schedule Summary Systems Summary

Cost Evaluation

Building System System Total (Turner) System Total (SF Estimate) $/SF (Turner) Percent of Total $/Sf (SF Estimate) Percent of Total2Excavation and Foundations 12,292,510.00$ 3,516,000.00$ 28.43$ 7.13% 8.36$ 4.35%Superstructure Concrete 19,457,000.00$ 16,492,500.00$ 45.01$ 11.29% 38.67$ 20.40%Curtain Wall/Storefront Panels 26,154,000.00$ 16,560,000.00$ 60.50$ 15.17% 38.62$ 20.50%Roofing and Waterproofing 1,296,000.00$ 521,000.00$ 3.00$ 0.75% 1.28$ 0.64%Electrical 22,276,380.00$ 12,291,500.00$ 51.53$ 12.92% 28.84$ 15.20%HVAC 21,009,090.00$ 10,638,500.00$ 48.60$ 12.19% 24.91$ 13.20%Equipment/Hoisting 5,042,000.00$ 3,678,000.00$ 11.66$ 2.93% 8.61$ 4.55%Plumbing 4,833,000.00$ 2,534,500.00$ 11.18$ 2.80% 5.93$ 3.13%

Construction Cost 162,803,910.00$ 80,855,000.00$ 379.74$ 189.54$ Total Project Cost 208,000,000.00$ 107,132,000.00$ 398.72$ 251.14$

Page 10: Shivam Patel CM Option Technical Assignment 1 Dr Ed Gannon September 16 th 2013 Image courtesy of Hines

Thank You

Questions?