Id Wbs ID Deliverables / Activities Duration Start date Finish Date

1 1 MT QUEEN ANDREA 12 días jue 9/10/15 lun 9/21/15

2 Milestone Vessel Arrival 0 días jue 9/10/15 jue 9/10/15

3 1.1 DRYDOCKING 12 días jue 9/10/15 lun 9/21/15

4 1.1.1 DOCKING 2 días jue 9/10/15 vie 9/11/15

5 Activity Make block arrangement 1 día jue 9/10/15 jue 9/10/15

6 Activity Dock the vessel 1 día vie 9/11/15 vie 9/11/15

7 1.1.2 UNDOCKING 3 días sáb 9/19/15 lun 9/21/15

8 Activity Vessel ballasting 1 día sáb 9/19/15 sáb 9/19/15

9 Activity Float the vessel 1 día lun 9/21/15 lun 9/21/15

10 Activity Take vessel out from dock 1 día lun 9/21/15 lun 9/21/15

11 1.1.3 GENERAL SERVICES 11 días jue 9/10/15 dom 9/20/15

12 Activity To supply shore power 11 días jue 9/10/15 dom 9/20/15

13 Activity To supply cooling water 11 días jue 9/10/15 dom 9/20/15

14 Activity To supply fire line 11 días jue 9/10/15 dom 9/20/15

15 1.2 HULL 10 días sáb 9/12/15 lun 9/21/15

16 1.2.1 BLAST AND PAINT 9 días sáb 9/12/15 dom 9/20/15

17 1.2.1.1 TOP SIDE 7 días sáb 9/12/15 vie 9/18/15

18 Activity High pressure washing 1 día sáb 9/12/15 sáb 9/12/15

19 Activity To blast SA2 3 días dom 9/13/15 mar 9/15/15

20 Activity To apply primer coat 3 días lun 9/14/15 mié 9/16/15

21 Activity To hose down 1 día mié 9/16/15 mié 9/16/15

22 Activity To apply second coat 1 día jue 9/17/15 jue 9/17/15

23 Activity To apply finished coat 1 día vie 9/18/15 vie 9/18/15

24 1.2.1.2 FLAT BOTTOM AND VERTICAL SIDE 8 días sáb 9/12/15 sáb 9/19/15

25 Activity High pressure washing 1 día sáb 9/12/15 sáb 9/12/15

26 Activity To blast SA2 3 días dom 9/13/15 mar 9/15/15

27 Activity To apply primer coat 3 días lun 9/14/15 mié 9/16/15

28 Activity To hose down 1 día mié 9/16/15 mié 9/16/15

29 Activity To apply sealer coat 1 día jue 9/17/15 jue 9/17/15

30 Activity To apply antifouling coat 2 días vie 9/18/15 sáb 9/19/15

31 1.2.1.3 HULL MARKINGS 1 día dom 9/20/15 dom 9/20/15

32 Activity To paint vessel names, plimsoll 1 día dom 9/20/15 dom 9/20/15

33 1.2.2 SEA CHEST 10 días sáb 9/12/15 lun 9/21/15

34 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15

9/10

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

MT QUEEN ANDREA - SHIP REPAIR PROJECT

PROJECT MANAGER: Fernando Remolina, PMP Página 1

Id Wbs ID Deliverables / Activities Duration Start date Finish Date

35 Activity Open sea chest gratings 1 día dom 9/13/15 dom 9/13/15

36 Activity Close sea chest gratings 1 día dom 9/20/15 dom 9/20/15

37 Activity Remove stagings 1 día lun 9/21/15 lun 9/21/15

38 1.2.3 BOTTOM PLUGS 5 días sáb 9/12/15 mié 9/16/15

39 Activity To open bottom plugs 1 día sáb 9/12/15 sáb 9/12/15

40 Activity To close bottom plugs 1 día mié 9/16/15 mié 9/16/15

41 1.2.4 ZINC ANODES 3 días sáb 9/12/15 lun 9/14/15

42 Activity To remove zinc anodes 1 día sáb 9/12/15 sáb 9/12/15

43 Activity To install zinc anodes 2 días dom 9/13/15 lun 9/14/15

44 1.2.5 ECHO SOUNDER 1 día lun 9/14/15 lun 9/14/15

45 Activity To remove and install new echo 1 día lun 9/14/15 lun 9/14/15

46 1.3 PROPULSION 9 días sáb 9/12/15 dom 9/20/15

47 1.3.1 TAIL SHAFT 9 días sáb 9/12/15 dom 9/20/15

48 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15

49 Activity Remove ropeguard 1 día sáb 9/12/15 sáb 9/12/15

50 Activity To measure weardown 1 día dom 9/13/15 dom 9/13/15

51 Activity Install ropeguard 1 día sáb 9/19/15 sáb 9/19/15

52 Activity Remove stagings 1 día dom 9/20/15 dom 9/20/15

53 1.3.2 PROPELLER 9 días sáb 9/12/15 dom 9/20/15

54 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15

55 Activity To polish propeller 1 día dom 9/13/15 dom 9/13/15

56 Activity Remove stagings 1 día dom 9/20/15 dom 9/20/15

57 1.4 RUDDER 11 días jue 9/10/15 dom 9/20/15

58 1.4.1 RUDDER BLADE 11 días jue 9/10/15 dom 9/20/15

59 Activity To erect stagings 1 día jue 9/10/15 jue 9/10/15

60 Activity To disconnect rudder blade 1 día vie 9/11/15 vie 9/11/15

61 Activity To pressure test rudder blade 1 día sáb 9/12/15 sáb 9/12/15

62 Activity To install rudder blade 1 día dom 9/13/15 dom 9/13/15

63 Activity To remove stagings 1 día dom 9/20/15 dom 9/20/15

64 1.4.2 RUDDER STOCK 1 día sáb 9/12/15 sáb 9/12/15

65 Activity To change lower seals 1 día sáb 9/12/15 sáb 9/12/15

66 1.5 ENGINE ROOM 9 días jue 9/10/15 vie 9/18/15

67 1.5.1 SEA VALVES 6 días sáb 9/12/15 jue 9/17/15

68 Activity To overhaul sea valves 6 días sáb 9/12/15 jue 9/17/15

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

MT QUEEN ANDREA - SHIP REPAIR PROJECT

PROJECT MANAGER: Fernando Remolina, PMP Página 2

Id Wbs ID Deliverables / Activities Duration Start date Finish Date

69 1.5.2 SEA WATER PIPES 3 días sáb 9/12/15 lun 9/14/15

70 Activity To renew 4m pipe section 3 días sáb 9/12/15 lun 9/14/15

71 1.5.3 MAIN ENGINE 9 días jue 9/10/15 vie 9/18/15

72 1.5.3.1 CYLINDER HEADS 7 días sáb 9/12/15 vie 9/18/15

73 Activity To overhaul cylinder heads 7 días sáb 9/12/15 vie 9/18/15

74 1.5.3.2 EXHAUST INSULATION 6 días jue 9/10/15 mar 9/15/15

75 Activity Erect Staging 1 día jue 9/10/15 jue 9/10/15

76 Activity To remove insulation 1 día vie 9/11/15 vie 9/11/15

77 Activity to fabricate insulation and install 3 días sáb 9/12/15 lun 9/14/15

78 Activity To remove stagings 1 día mar 9/15/15 mar 9/15/15

79 1.6 TANKS 9 días vie 9/11/15 sáb 9/19/15

80 1.6.1 CHAIN LOCKER 3 días vie 9/11/15 dom 9/13/15

81 Activity To clean chain locker 2 días vie 9/11/15 sáb 9/12/15

82 Activity To paint chain locker 1 día dom 9/13/15 dom 9/13/15

83 1.6.2 CARGO TK #6 8 días sáb 9/12/15 sáb 9/19/15

84 Activity To renew 3ton of steel in bulkhead 7 días sáb 9/12/15 vie 9/18/15

85 Activity To test welding seams with MPI 1 día sáb 9/19/15 sáb 9/19/15

86 1.6.3 BALLAST TK # 1 STB 4 días sáb 9/12/15 mar 9/15/15

87 Activity To renew longitudinal structure 4 días sáb 9/12/15 mar 9/15/15

88 1.7 DECKS 4 días sáb 9/12/15 mar 9/15/15

89 1.7.1 MAIN DECK CRANE 4 días sáb 9/12/15 mar 9/15/15

90 Activity Renew hydraulic hoses 3 días sáb 9/12/15 lun 9/14/15

91 Activity Load test 1 día mar 9/15/15 mar 9/15/15

92 1.7.2 HAND RAILINGS 3 días sáb 9/12/15 lun 9/14/15

93 Activity To renew stb mid ship railings 3 días sáb 9/12/15 lun 9/14/15

94 1.7.3 FIRE LINE 4 días sáb 9/12/15 mar 9/15/15

95 Activity To renew 10m of fire line piping 4 días sáb 9/12/15 mar 9/15/15

96 1.8 ACCOMODATIONS 5 días jue 9/10/15 lun 9/14/15

97 1.8.1 FREE FALL BOAT 1 día sáb 9/12/15 sáb 9/12/15

98 Activity Free fall boat load test 1 día sáb 9/12/15 sáb 9/12/15

99 1.8.2 CAPTAIN ROOM 5 días jue 9/10/15 lun 9/14/15

100 Activity To repair cabinets 5 días jue 9/10/15 lun 9/14/15

101 1.9 ANCHOR AND CHAINS 6 días jue 9/10/15 mar 9/15/15

102 Activity Lower anchor and chains 1 día jue 9/10/15 jue 9/10/15

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

MT QUEEN ANDREA - SHIP REPAIR PROJECT

PROJECT MANAGER: Fernando Remolina, PMP Página 3

Id Wbs ID Deliverables / Activities Duration Start date Finish Date

103 Activity Range anchor and chains 1 día vie 9/11/15 vie 9/11/15

104 Activity To wash anchor and chains 1 día sáb 9/12/15 sáb 9/12/15

105 Activity To calibrate anchor and chains 1 día dom 9/13/15 dom 9/13/15

106 Activity To mark anchor and chains 1 día lun 9/14/15 lun 9/14/15

107 Activity Heaving in anchor and chains 1 día mar 9/15/15 mar 9/15/15

108 Milestone Vessel Departure 0 días lun 9/21/15 lun 9/21/15 9/21

8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

MT QUEEN ANDREA - SHIP REPAIR PROJECT

PROJECT MANAGER: Fernando Remolina, PMP Página 4