Id Wbs ID Deliverables / Activities Duration Start date Finish Date
1 1 MT QUEEN ANDREA 12 días jue 9/10/15 lun 9/21/15
2 Milestone Vessel Arrival 0 días jue 9/10/15 jue 9/10/15
3 1.1 DRYDOCKING 12 días jue 9/10/15 lun 9/21/15
4 1.1.1 DOCKING 2 días jue 9/10/15 vie 9/11/15
5 Activity Make block arrangement 1 día jue 9/10/15 jue 9/10/15
6 Activity Dock the vessel 1 día vie 9/11/15 vie 9/11/15
7 1.1.2 UNDOCKING 3 días sáb 9/19/15 lun 9/21/15
8 Activity Vessel ballasting 1 día sáb 9/19/15 sáb 9/19/15
9 Activity Float the vessel 1 día lun 9/21/15 lun 9/21/15
10 Activity Take vessel out from dock 1 día lun 9/21/15 lun 9/21/15
11 1.1.3 GENERAL SERVICES 11 días jue 9/10/15 dom 9/20/15
12 Activity To supply shore power 11 días jue 9/10/15 dom 9/20/15
13 Activity To supply cooling water 11 días jue 9/10/15 dom 9/20/15
14 Activity To supply fire line 11 días jue 9/10/15 dom 9/20/15
15 1.2 HULL 10 días sáb 9/12/15 lun 9/21/15
16 1.2.1 BLAST AND PAINT 9 días sáb 9/12/15 dom 9/20/15
17 1.2.1.1 TOP SIDE 7 días sáb 9/12/15 vie 9/18/15
18 Activity High pressure washing 1 día sáb 9/12/15 sáb 9/12/15
19 Activity To blast SA2 3 días dom 9/13/15 mar 9/15/15
20 Activity To apply primer coat 3 días lun 9/14/15 mié 9/16/15
21 Activity To hose down 1 día mié 9/16/15 mié 9/16/15
22 Activity To apply second coat 1 día jue 9/17/15 jue 9/17/15
23 Activity To apply finished coat 1 día vie 9/18/15 vie 9/18/15
24 1.2.1.2 FLAT BOTTOM AND VERTICAL SIDE 8 días sáb 9/12/15 sáb 9/19/15
25 Activity High pressure washing 1 día sáb 9/12/15 sáb 9/12/15
26 Activity To blast SA2 3 días dom 9/13/15 mar 9/15/15
27 Activity To apply primer coat 3 días lun 9/14/15 mié 9/16/15
28 Activity To hose down 1 día mié 9/16/15 mié 9/16/15
29 Activity To apply sealer coat 1 día jue 9/17/15 jue 9/17/15
30 Activity To apply antifouling coat 2 días vie 9/18/15 sáb 9/19/15
31 1.2.1.3 HULL MARKINGS 1 día dom 9/20/15 dom 9/20/15
32 Activity To paint vessel names, plimsoll 1 día dom 9/20/15 dom 9/20/15
33 1.2.2 SEA CHEST 10 días sáb 9/12/15 lun 9/21/15
34 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15
9/10
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
MT QUEEN ANDREA - SHIP REPAIR PROJECT
PROJECT MANAGER: Fernando Remolina, PMP Página 1
Id Wbs ID Deliverables / Activities Duration Start date Finish Date
35 Activity Open sea chest gratings 1 día dom 9/13/15 dom 9/13/15
36 Activity Close sea chest gratings 1 día dom 9/20/15 dom 9/20/15
37 Activity Remove stagings 1 día lun 9/21/15 lun 9/21/15
38 1.2.3 BOTTOM PLUGS 5 días sáb 9/12/15 mié 9/16/15
39 Activity To open bottom plugs 1 día sáb 9/12/15 sáb 9/12/15
40 Activity To close bottom plugs 1 día mié 9/16/15 mié 9/16/15
41 1.2.4 ZINC ANODES 3 días sáb 9/12/15 lun 9/14/15
42 Activity To remove zinc anodes 1 día sáb 9/12/15 sáb 9/12/15
43 Activity To install zinc anodes 2 días dom 9/13/15 lun 9/14/15
44 1.2.5 ECHO SOUNDER 1 día lun 9/14/15 lun 9/14/15
45 Activity To remove and install new echo 1 día lun 9/14/15 lun 9/14/15
46 1.3 PROPULSION 9 días sáb 9/12/15 dom 9/20/15
47 1.3.1 TAIL SHAFT 9 días sáb 9/12/15 dom 9/20/15
48 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15
49 Activity Remove ropeguard 1 día sáb 9/12/15 sáb 9/12/15
50 Activity To measure weardown 1 día dom 9/13/15 dom 9/13/15
51 Activity Install ropeguard 1 día sáb 9/19/15 sáb 9/19/15
52 Activity Remove stagings 1 día dom 9/20/15 dom 9/20/15
53 1.3.2 PROPELLER 9 días sáb 9/12/15 dom 9/20/15
54 Activity Erect Staging 1 día sáb 9/12/15 sáb 9/12/15
55 Activity To polish propeller 1 día dom 9/13/15 dom 9/13/15
56 Activity Remove stagings 1 día dom 9/20/15 dom 9/20/15
57 1.4 RUDDER 11 días jue 9/10/15 dom 9/20/15
58 1.4.1 RUDDER BLADE 11 días jue 9/10/15 dom 9/20/15
59 Activity To erect stagings 1 día jue 9/10/15 jue 9/10/15
60 Activity To disconnect rudder blade 1 día vie 9/11/15 vie 9/11/15
61 Activity To pressure test rudder blade 1 día sáb 9/12/15 sáb 9/12/15
62 Activity To install rudder blade 1 día dom 9/13/15 dom 9/13/15
63 Activity To remove stagings 1 día dom 9/20/15 dom 9/20/15
64 1.4.2 RUDDER STOCK 1 día sáb 9/12/15 sáb 9/12/15
65 Activity To change lower seals 1 día sáb 9/12/15 sáb 9/12/15
66 1.5 ENGINE ROOM 9 días jue 9/10/15 vie 9/18/15
67 1.5.1 SEA VALVES 6 días sáb 9/12/15 jue 9/17/15
68 Activity To overhaul sea valves 6 días sáb 9/12/15 jue 9/17/15
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
MT QUEEN ANDREA - SHIP REPAIR PROJECT
PROJECT MANAGER: Fernando Remolina, PMP Página 2
Id Wbs ID Deliverables / Activities Duration Start date Finish Date
69 1.5.2 SEA WATER PIPES 3 días sáb 9/12/15 lun 9/14/15
70 Activity To renew 4m pipe section 3 días sáb 9/12/15 lun 9/14/15
71 1.5.3 MAIN ENGINE 9 días jue 9/10/15 vie 9/18/15
72 1.5.3.1 CYLINDER HEADS 7 días sáb 9/12/15 vie 9/18/15
73 Activity To overhaul cylinder heads 7 días sáb 9/12/15 vie 9/18/15
74 1.5.3.2 EXHAUST INSULATION 6 días jue 9/10/15 mar 9/15/15
75 Activity Erect Staging 1 día jue 9/10/15 jue 9/10/15
76 Activity To remove insulation 1 día vie 9/11/15 vie 9/11/15
77 Activity to fabricate insulation and install 3 días sáb 9/12/15 lun 9/14/15
78 Activity To remove stagings 1 día mar 9/15/15 mar 9/15/15
79 1.6 TANKS 9 días vie 9/11/15 sáb 9/19/15
80 1.6.1 CHAIN LOCKER 3 días vie 9/11/15 dom 9/13/15
81 Activity To clean chain locker 2 días vie 9/11/15 sáb 9/12/15
82 Activity To paint chain locker 1 día dom 9/13/15 dom 9/13/15
83 1.6.2 CARGO TK #6 8 días sáb 9/12/15 sáb 9/19/15
84 Activity To renew 3ton of steel in bulkhead 7 días sáb 9/12/15 vie 9/18/15
85 Activity To test welding seams with MPI 1 día sáb 9/19/15 sáb 9/19/15
86 1.6.3 BALLAST TK # 1 STB 4 días sáb 9/12/15 mar 9/15/15
87 Activity To renew longitudinal structure 4 días sáb 9/12/15 mar 9/15/15
88 1.7 DECKS 4 días sáb 9/12/15 mar 9/15/15
89 1.7.1 MAIN DECK CRANE 4 días sáb 9/12/15 mar 9/15/15
90 Activity Renew hydraulic hoses 3 días sáb 9/12/15 lun 9/14/15
91 Activity Load test 1 día mar 9/15/15 mar 9/15/15
92 1.7.2 HAND RAILINGS 3 días sáb 9/12/15 lun 9/14/15
93 Activity To renew stb mid ship railings 3 días sáb 9/12/15 lun 9/14/15
94 1.7.3 FIRE LINE 4 días sáb 9/12/15 mar 9/15/15
95 Activity To renew 10m of fire line piping 4 días sáb 9/12/15 mar 9/15/15
96 1.8 ACCOMODATIONS 5 días jue 9/10/15 lun 9/14/15
97 1.8.1 FREE FALL BOAT 1 día sáb 9/12/15 sáb 9/12/15
98 Activity Free fall boat load test 1 día sáb 9/12/15 sáb 9/12/15
99 1.8.2 CAPTAIN ROOM 5 días jue 9/10/15 lun 9/14/15
100 Activity To repair cabinets 5 días jue 9/10/15 lun 9/14/15
101 1.9 ANCHOR AND CHAINS 6 días jue 9/10/15 mar 9/15/15
102 Activity Lower anchor and chains 1 día jue 9/10/15 jue 9/10/15
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
MT QUEEN ANDREA - SHIP REPAIR PROJECT
PROJECT MANAGER: Fernando Remolina, PMP Página 3
Id Wbs ID Deliverables / Activities Duration Start date Finish Date
103 Activity Range anchor and chains 1 día vie 9/11/15 vie 9/11/15
104 Activity To wash anchor and chains 1 día sáb 9/12/15 sáb 9/12/15
105 Activity To calibrate anchor and chains 1 día dom 9/13/15 dom 9/13/15
106 Activity To mark anchor and chains 1 día lun 9/14/15 lun 9/14/15
107 Activity Heaving in anchor and chains 1 día mar 9/15/15 mar 9/15/15
108 Milestone Vessel Departure 0 días lun 9/21/15 lun 9/21/15 9/21
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
MT QUEEN ANDREA - SHIP REPAIR PROJECT
PROJECT MANAGER: Fernando Remolina, PMP Página 4