Project-specific information:Information meeting 19 January 2017
Arne MelandNPRA Eastern Region
Rv 3/Rv 25 Ommangsvollen – Grundset/Basthjørnet
Information meeting1
19.01.2017
County municipality and localgovernment
Information meeting4
19.01.2017
Rv 3/rv 25 Ommangsvollen – Grundset/Basthjørnet
Purpose of building this road
Information meeting6
19.01.2017
● Facilitate freight transport between Oslo and Trondheim● Enhance Hamar and Elverum as one united residential
and labour market region● Provide continuous facilities for pedestrians and cyclists
between Hamar and Elverum● To improve:
– Traffic flow– Road safety– Civil protection
(The current road is the only public road Løten-Elverum, AADT 14,000)
– Residential environment
Plan status
Information meeting7
19.01.2017
• Detailed zoning plan for the new Rv 3/25 in Løten, adopted on 25 January 2012
• 7 changes adopted in 2015/2016
Main volumesRv. 3/rv. 25 Ommangsvollen – Grundset/Basthjørnet
19.01.2017
15.2 km4-lane road
7.1 kmpedestrian/cycle path
10.4 km2/3-lane road
Junctions (national roads)3 grade-separated2 roundabouts2 T-junctions
Minor roadsCounty roads (Fv)Municipal roads
Structures9 bridges18 over-/underpasses2 wildlife crossings
ÅnestadVehicle Licensing Office
Information meeting11
Main challenges
Information meeting12
19.01.2017
• Major earthmoving project
• Scarcity of rock masses for base layers along the road alignment, some acid-forming rock (alum shale).
• Hilly terrain with marshy patches
Main challenges
Information meeting13
19.01.2017
• Highly productive farmland at LøtenCompulsory restoration of farmland and agricultural drainage
• No particularly large or challenging bridges and structures, no tunnels
• New road through active groundwater reservoir at Elverum
• Cultural monuments along the entire route
Main project features
Information meeting14
19 January 2017
• 26 km road through a relatively flat landscape, approx. 1.7 mill. sq.m.
• ±100 mm ~ 170 000 cu.m.
• Drainage is decisive for the vertical alignment.
• Haulage and mass balance of rock/soils are criteria for success
Preliminary quantity estimates
Information meeting15
19 January 2017
• Surplus soil/rock (excavated material): approx. 400 000 cu.m.(surplus in the north, shortage in the south/west)
• Rock blasting: approx. 300 000 cu.m(much of this is black shale/alum shale)
• Earthmoving approx. 3 mill. cu.m.
• Top soil and vegetation: approx. 400 000 cu.m.
• Aggregate for pavement layers etc. approx. 2 mill. cu.m.
Possibilities and limitations
Limitations:● Zonal plans for the road reserve is not prepared specifically with a PPP
project delivery in mind.● The zonal plans give the framework for:
– Protection of agricultural land, cultivation and land utilisation.– Protection of cultural heritage sites.– Detailed design and consideration to aesthetics
● Long planning history.● Land aquisition and forest clearing is under way, however based on the
current, approved zonal plans.
Markedsmøte16
19.01.17
Possibilities and limitations
Possibilities:● Detailed design commenced in 2014/2015, before the project delivery
as a PPP was decided on.● Optimization of the original zonal plan was carried out 2014-2016.
New zonal plan was prepared for some sections.● Reports, drawings and digital models will be made available.● Early start of adaption and detailed design.● Preliminary design is carried out for most of the structures:
From 2011 (need adjustments) and 2015/2016.● The NPRA will actively take part in the procurement process to clarify
the scope for opimization.
Information meeting17
19.01.17
Possibilties and limitations
In the residential / agricultural areas:● Many considerations.● Lengthy zonal planning process: 20 years.● Protection of arable land and re-establishment of
agricultural land after construction. ● Adjacent residential areas, established and
planned ones.
● Relatively small scope for optimization.
Information meeting18
19.01.17
Possibilities and limitations
In the non-residential and forest areas:● Relatively narrow road reserve.● Forest clearing is completed within the road reserve.● Cultural heritage sites are identified and clarifiet
within the road reserve.● Scope for optimization of haulage and mass balance● Frost design, choice of method● Use of locally available materials for pavement and
earthworks.
● Relatively large scope for optimization
Information meeting19
19.01.17
Estimated timeline
● The NPRA is preparing for the following progress plan:– Revision of road toll issue (decision with regard to
guarantees) October 2016– Prequalification PPP January - March 2017– PPP Procurement in 2017– Construction start PPP 2018
– Preparatory work in 2017
Rv 3/Rv 25 Løten-Elverum
19.01.2017
2016 2017 2018 2020/21:
Primo 2017Storting:
Discussion/Decision
2017PPP Tender
phase
October 2016Road toll issue
Locally, Hedmark County Adm
2018Potential
construction start
Potential road opening
2017Prep. work
Information meeting20
www.vegvesen.no/vegprosjekter/OPS-PPP
Information meeting28
19.01.2017