points and crossings laying of points & crossings

74
POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

Upload: william-gallagher

Post on 13-Jan-2016

227 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

POINTS AND CROSSINGS

LAYING OF POINTS & CROSSINGS

Page 2: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

METHODS OF LAYING

• IN-SITU LAYING – In openline, construction and Yard Remodelling (sometimes)

• Assembly – Shifting – Laying – Complete Renewal/Laying : Mechanised– Renewal/Laying by Parts : Either Manual

or Mechanised – Prefabrication in Depot – Assembly can

be done using road crane.

Page 3: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

GENERAL PROVISIONS OF

IRPWM ON TURNOUT LAYOUTS • Para 410 stipulates that

– T/Os on passenger lines should not be laid with ST. SW. sharper than 1 in 12.If there is constraint of space, 1in 8.5 T/O with CU.SW. may be laid.

– Sharper (than 1 in 12) may be used when the turnout is taken off from outside of a curve restricting the radius of lead curve within following limits -

BG – 350 m MG – 220 m NG – 165 m.

Page 4: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

GENERAL PROVISIONS OF IRPWM ON TURNOUT LAYOUTS

– No turn in curve should be sharper than lead curve of 1 in 12 simple turnout.However if track centres are inadequate 220m radius on BG and 120 on MG can be permitted with strengthening of turn in curve.

– 1 in 8.5 T/O should not be laid on inside of curve.

Page 5: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

GENERAL PREPARATION FOR TURNOUT REPLACEMENT

• Field inspection to check site conditions, approach, presence of electrical & signalling gears, posts, boards etc. which may cause obstruction; availability of ballast etc.

• Arranging adequate space for assembly by necessary tools & plants and good quality artisan.

• Checking completeness of all components of P&C as per parts list. Checking of important dimensions.

Page 6: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

GENERAL PREPARATION FOR TURNOUT REPLACEMENT

• Recalculations of overall length vis a vis track centres. Examine scope/need for improvement Distances to be measured accurately and layout to be marked .

• The proposed location of SRJ, ATS, TNC, Glued Joints etc. should be marked on ground.

• Planning the rail cuts in the assembly to minimise wastage.

• Coordination with other departments and obtaining CRS sanction (if required).

• Shifting of fixed structures – OHE mast, signalling roads, signal posts, etc, if required.

Page 7: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

GENERAL PREPARATION FOR TURNOUT REPLACEMENT

• The mid-ordinate and the quarter ordinates of the tongue rails and stock rails should be checked and rectified.

• If existing sleepers are wooden or ST, provision has to be made for additional depth of PSC sleeper along with 300/250 mm ballast cushions.

• The existing ballast should be deep screened and recouped to match levels with approach track.

• Spacing of sleepers to be measured along the mainline starting from beginning.

Page 8: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MANUAL LAYING OF P&C ON PSC SLEEPERS

• Preliminary works

– Survey : Measure & check existing layouts. Examine scope/need for improvement.

– Mark proposed SRJ, ATS, crossing position & location of sleepers on lead and crossing portion.

– Assemble the switch on staging.

– Check housing of TR with SR and Throw.

Page 9: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MANUAL LAYING OF P&C ON PSC SLEEPERS

• Preblock works– On 1 in 12 T/O sleeper nos. 28 to 64 and 73 to 83

can be inserted one by one. Sleeper Nos. 21 to 27 should be kept ready with special bearing plates.

– Shifting and adjustment of OHE alignment of required

– OEHS should be issued on adjoining tracks.• Alternate keys and 2 out of 4 bolts at joints should be

removed. Ballast should be removed from top of the sleepers .

• Speed restriction of 20 kmph should be imposed.

Page 10: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MANUAL LAYING OF P & C ON PSC LAYOUT

• Block Works – One batch (40 men) dismantle switch and

approach.– Second batch (20 men) remove sleepers and level

the ballast bed.– Second batch then moves to dismantle crossing

portion and take out sleepers from crossing. – Third batch (15 men) replaces sl. nos. 21 to 27.– The new assembled switch is dragged to proposed

site and linked to approach track.( 40 men)

– Sleepers under crossing and behind HOS are inserted and rails linked.

Page 11: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MANUAL LAYING OF P & C ON PSC LAYOUT

• Block Work (contd..)– Rail linking for main line is completed and switch

portion is packed. Signalling staff start their work.– Crossing is fixed and initial packing is given.– Traffic block is cancelled and trains are allowed on

mainline under speed Restriction treating it as non-interlocked point

– Track on T/O side is completed and traffic permitted on T/O side also.

• Post Block Works– Packing by UNIMAT;Welding of joints;Recording of

measurements.

Page 12: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MECHANISED LAYING OF PSC T/O

• By T-28 crawler cranes of M/s AMECA of Italy.

• One set consists of two self propelled portal cranes, one motorised rail trolley and two non-motorised rail trolley.

• CRS has permitted speed of 10 kmph when the crane runs on its own power.

Page 13: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

T-28 PORTAL CRANES

• Portal crane can run on rails (using rail wheels) as well as on road (using crawlers). The crawlers can be lifted up or opened laterally to accommodate the sleepers.

• The crane can be shifted laterally on the crawlers. These can also be rotated to take angular position. Crawler height can be adjusted individually.

Page 14: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS
Page 15: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

T-28 IN OPERATION

Page 16: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

MAINTENANCE OF POINTS AND CROSSINGS

Page 17: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

INSPECTIONS • Regular Inspection by Engineering Officials

(IRPWM – Para 237).• I/C SE/P.Way and sectional JE/P.Way to inspect

all points on passenger running lines once in 3 months and other points once in 6 months by rotation.

• ADEN to inspect all points on passenger running lines once in a year and 10% of other points every year.

• Sr. DEN/DEN (L) to inspect certain number of points on passenger running lines every year.

• Results of Inspections to be recorded in Points & Crossings Register using prescribed proforma.

Page 18: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

JOINT INSPECTION WITH S&T BRANCH

• Joint Inspection by SE/P.Way (I/C or Sect) and SE/Signal – All interlocked points to be inspected jointly once in a quarter

/half-yearly.– Mainly switch portion is inspected– Results and compliance to be reviewed at Divisional level.

• MAINTENANCE REQUIRENTS FROM SIGNALLING CONSIDERATIONS:– Switch should be reasonably ‘free’ to pull- ‘single person

single pull’– Proper housing of tongue rail: thick-head bolt,burr on stock

rail to be avoided– Switch should not be out of square.– Min. gap between stretcher bar and bottom of rail to be

ensured.

Page 19: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

INSPECTION OF POINTS AND CROSSINGS

• Badly worn and damaged tongue rails should be replaced. A tongue rail is classified as badly worn when– It is chipped/cracked over small lengths

aggregating to 200 mm within a distance of 1000 mm from toe . Chipped length will be portion where tongue rail has worn out for a depth of more than 10 mm over a continuous length of 10 mm.

– Has developed knife edge tip over a length of 100 mm any where up-to a distance of 1000mm from its toe.

– Badly twisted or bent and does not house properly.

Page 20: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

INSPECTION OF POINTS AND CROSSINGS

• Tongue rails should be replaced / reconditioned when– VERT. WEAR > 8 MM ( FOR 60 KG.)

> 5 MM ( FOR 52 KG AND

90R)– LATERAL WEAR > 8 MM ( FOR 60 KG.)

> 6 MM (FOR 52 KG

AND 90R)

Page 21: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

INSPECTION OF POINTS AND CROSSINGS

• Lateral wear at the above said points 13 to 15 mm below stock rails

• Locations for measurement of vertical wear on TR:– Point with 13mm head width– Point where TR and SR are at same

level– The details are given in

Annexure.2/6/1of IRPWM

Page 22: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

INSPECTION OF POINTS AND CROSSINGS

• Wear on stock rails should not exceed the following limits-VERT. WEAR - 13 MM ( FOR 60 KG.)

- 8 MM ( FOR 52 KG )

- 5 MM ( FOR 90R)LATERAL WEAR

• FOR CURVE - 8 MM ( FOR GR. A & B ROUTES)

-10 MM (FOR GR. C&D ROUTES)

FOR STRAIGHT- 6 MM ( FOR GR. A & B ROUTES)

- 8 MM (FOR GR. C & D ROUTES)

Page 23: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

IMP. MEASUREMENTS ON P & C

• Gauge : Uniform Gauge to be maintained except just ahead of ATS where– Nominal gauge if SEA<= 0-20-00– Nominal+6mm if SEA > 0-20-00

Throw Of Switch : – On BG -Minimum on existing lines : 95 mm

Minimum on new works : 115 mm– On MG-Minimum on existing lines : 89 mm

Minimum on new works : 100 mm

Page 24: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• Vertical Wear on crossing (Wing Rail & Nose)• Measured at 100 mm from ANC.• Rajdhani & Shatabdi Routes : As a good

maintenance practice,crossing and wing rails should be planned for reconditioning on reaching following values:

• Built –up crossing: 6 mm• CMS crossing : 8 mm

• Other Routes: 10 mm. In case of CMS crossings 2.0mm in case of 52kg

section and 2.5mm in case of 60kg section should be deducted from observed wear measurements to account for cross slope.

IMP. MEASUREMENTS ON P & C

Page 25: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

BUILT UPCROSSINGS

Page 26: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS
Page 27: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

OTHER IMP. PROVISIONS OF IRPWM ON P& C

• No Junction Fishplate at SRJ or HOC. At least one rail to be of same section.

• Provide spherical washers properly.• Creep anchors and box anchoring of one rail

length.• Desirable to weld SRJ and lead curve joints.• Lubrication of gauge face of tongue rail.• ST sleepers – Wooden blocks under crossing in

case of ST sleepers.• Gauge Tie Plate should be used on proper

locations.

Page 28: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• No change of cant outside ATS and Nose of Crossing for a distance of 18 m on BG and 15 m on MG.

• In case of straight switches, correct amount of bend should be given to the stock rail on the turnout side at the theoretical toe of switch.

• Tongue rail should bear evenly on all the side chair. When the tongue rail is in closed portion, it must bear evenly against distance studs or blocks.

• Insertion or removal of P & C in a running line affecting layout must be carried out only after obtaining sanction of CRS.

OTHER IMP. PROVISIONS OF IRPWM ON P& C

Page 29: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

CHECK-LIST FOR MAINTENANCE OF PSC SLEEPER LAYOUT

• Same track structure for one rail length on the three sides.

• Weld joints as specified.

• Gapless joints as specified.

• Grind gauge face of stock rail if burr is there.

• Regular maintenance by UNIMAT.

• Proper maintenance of CMS crossing.

Page 30: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

WORKING OF UNIMAT

• TAMPING– UNIMAT 08-275/3S has two tamping units

each with 8 side tilting tools. Lateral displacement is also possible. This enables to reach difficult locations.

– The cross section of tools is 20% more than that for normal tampers.

– If obstacle is encountered, the tyne is tilted out and sleeper is packed with as many pairs as possible.

– On straight all 8 pairs are used for tamping.– M/C Pivot can rotate by 8.50.

Page 31: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

UNIMAT-3S 42 Nos.

3rd rail lifting

Page 32: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

UNIMAT-3S 42 Nos.

• Points and crossing tamping machine• Tilting / swirling tools • 3rd rail lifting arrangement in (3s) machines• Manual lifting of 3rd rail in 2s machines• 1 t/out per 75 minitues

Page 33: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

WORKING OF UNIMAT (contd..)

• LIFTING – In 2S series UNIMATS only two rails are lifted

by m/c. Third rail should be lifted manually– In 3S series UNIMATS there is an ‘arm’/lifting

hook for lifting the third rail.– With 4S series of m/c the whole T/O can be

tamped in one go. The M/C moves laterally.– With 3S series of M/C – ML is aligned packed

and levelled. LL is only packed.

Page 34: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

TAMPING OF POINTS & CROSSINGS PRE-TAMPING OPERATIONS

• Ensure layout & spacing of sleeper as per drawing

• Defective crossing should be reconditioned/replaced and sleepers attended.

• High points on the turnout and approaches should be determined and general lift decided.

• Minimum general left should be 10 mm

Note : These are in addition to the regular temping operations prescribed for any tamping operation.

Page 35: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

TAMPING OF POINTS & CROSSINGS

OPERATIONS DURING TAMPING • Mainline to be tamped first. • The lifted end of sleepers should be

adequately supported on wooden wedges till it is packed/tamped.

• Alignment and level correction on main line. Only tamping on turnout side.

• Squeezing pressure:ST/Wooden Sleeper 110-115 kg/sq-cmPSC Sleeper 135-140 kg/sq-cm.

Page 36: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

TAMPING OF POINTS & CROSSINGS POST TAMPING OPERATIONS

• Checking and tightening of loose fittings.

• Replacement of broken fitting.

• Ballast dressing.

• Final track parameters should be recorded.

Page 37: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

TIPS FOR EFFICIENT TAMPING OF P& C

• Wornout crossings should be replaced in advance.• Fittings and Fastenings should be recouped. • Minimum 10 mm lift is desirable. More if required

(depending on track geometry, ballast availability, S & T gear position etc.)

• If unevenness in track is high, longer approach should be tamped.

• On PSC Layout 1 insertion is adequate for 30 mm lift. On ST and wooden layout 2 insertions are required.

• When mainline is being tamped, T/O should be kept supported by wooden wedges.

• Some areas are not reached by M/C. These should be tamped by Off-track tampers or packed manually.

Page 38: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

RECONDITIONING OF POINTS AND CROSSINGS

Page 39: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

NEED FOR RECONDITIONING

• The point and crossing components gets worn out due to passage of traffic and the wear reaches permissible limits in due course of time.

• It is neither economical nor practical to replace them straight away. The life of these components can be prolonged by reconditioning and thus these can be utilized to maximum extent.

Page 40: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SYSTEMS FOR RECONDITIONING• In-situ Reconditioning

– Is carried out on track either under block or under caution order

– Advantage• Traffic block; transportation not required• Reconditioning can be done even if spares are not

available (Imp in case of Special. Layouts) .• Disadvantage - Difficult to ensure quality.Not suitable

for CMS Crossings.

• Depot Reconditioning : Components are brought to welding depot and then they are reconditioned.– Advantage – Better Quality– Disadvantage – Spares, traffic block, transportation

arrangement are required. Cost is more.

Page 41: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SUITABILITY FOR RECONDITIONING

• Only suitable components should be taken up for reconditioning.

• Component should be in sound structural condition.Components containing cracks on the worn-out portion having depths more than 3 mm beyond condemning size should not be taken up for reconditioning .

• Wear should be within prescribed limit. DPT should be carried out to check for cracks.

Page 42: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

DYE PENETRATION TEST

Page 43: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

WELDING ELECTRODES • Only H3 class of electrodes (H3, H3A and H3B)

manufactured by firms approved by RDSO are to be used. RDSO to circulate list every July.

• Traffic carrying capacity of electrodes (of H3 class)

– H3 – Min. service life of 15 GMT

– H3A – Min. service life of 25 GMT

– H3B – Min. service life of 35 GMT

• Discard electrodes with cracked / damaged flux covering.

• Damp Electrodes not to be used. Either packing of electrodes should be absolutely intact and all the electrodes should be consumed within six hours of opening of pack. Or electrodes to be dried at 1300- 1700 for at-least one hour.

• 4 mm dia electrodes to be used for welding.

Page 44: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• Reconditioning of Switch : Recondition the Stock Rail first. A wornout tongue rail shall be reconditioned in closed position i.e. resting against the stock rail. In case of broken tip the TR is to be built up initially in the open condition and thereafter it should be closed with SR to attain final profile.

• Welding Current – The current range as recommended by the manufacture of electrode should be adhered to.

• Electrical Appliances – All appliances should be properly earthed. Generator should be capable of supplying 200 amperes at 60% duty cycles.OCV (Open Circuit Voltage) should be in the range 65V to 85V.

Page 45: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

RECONDITIONING OF MM/90 UTS BUILT UP CROSSINGS

• Surface treatment by cleaning and grinding• Welding to be done in flat position .• Preheating : The component should be

preheated on the surface by to and fro play of oxy-acetylene torch to obtain 2500C to 3000C.

• Welding to start immediately after preheating. Use short arc length.

• Care to be taken to fill the crater to the full weld size before breaking the arc.

• At restart arc should be stuck ahead of crater and then drawn back so as to fill the crater.

Page 46: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

RECONDITIONING OF MM/90 UTS BUILT UP CROSSINGS( Continue)

• Inter-pass temperature of 2500 – 3000C should be maintained.

• Each bead should be thoroughly peened with ball- peen hammer.

• While depositing the adjacent layer about 50% of previous layer should be covered.

• Weld metal to be deposited to provide an excess of 3 mm to be finished by grinding.

Page 47: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

BUILT UP CROSSINGS

Page 48: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

RECONDITIONING OF CMS CROSSING

• Surface treatment by cleaning and grinding• Welding operations to be done in flat position.• Preheating not required.• The temp during welding process not to go up

beyond 150 0C. • Temperature to be controlled by by proper intervals

between the runs and by means of compressed air jet or water quenching . Or, the crossing may be kept submerged in water bath with only top 1 cm above water level.

• Welding cycle should be short (2 min).

Page 49: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• Care to be taken to fill the crater to the full weld size before breaking the arc.

• At restart arc should be stuck ahead of crater and then drawn back so as to fill the crater.

• Each bead should be thoroughly peened with ball peen hammer.

• While depositing the adjacent layer about 50% of previous layer should be covered.

• Weld metal to be deposited to provide an excess of 3 mm to be finished by grinding.

Page 50: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

DEPOT RECONDITIONINGCMS CROSSINGS

Page 51: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

WELDING SEQUENCE

Page 52: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

OTHER STEPS OF RECONDITIONING PROCESS

• Testing and Inspection – Visual Inspection:- Check for surface defects –

undercut, slag inclusion, porosity, crack etc. – Dimensional measurement:- By straight-edge and

template – DPT or Magnaflux test to detect surface cracks– Rectification

If cracks found, the portion should be gouged either by pneumatic gouging or grinding and remaining portion should be re-examined for crack. If no cracks are found, the portion should be rewelded, ground and inspected.

Page 53: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

IMPORTANT STEPS OF RECONDITIONING PROCESS

• Grinding :- The reconditioned area should be ground to the original contour. Grinding wheel should be continuously moved back and forth and not stopped at one location to avoid high localised heating and subsequent cooling.

• Passage of Trains :-Trains can be passed at normal speed over the weld metal on crossing even before completion of welding. After passage of train, welding can be restarted. After passage of train, welding can be started again. However, weld metal should be allowed to cool for 2 to 3 minutes before allowing passage of train.

Page 54: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEED OVER TURNOUTS

Page 55: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEEDS ON POINTS & CROSSINGS • CRITERIA FOR PERMISSIBLE SPEED ON MAIN

LINE :

– Standard of Interlocking

• Speeds on Main Line :– Standard I Interlocking 50 kmph– Standard II Interlocking 75 kmph– Standard III Interlocking Unrestricted– Irrespective of interlocking, speed shall be

restricted to 50 kmph in case of a point taking off in the block section

Page 56: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEEDS ON POINTS & CROSSINGS

• CRITERIA FOR PERMISSIBLE SPEED ON MAIN LINE :

-Curvature of Main Line• No restriction in case of straight Main Line • Main line & Turnout having curvature in

opposite direction: CANT given to mainline acts as negative CANT for turnout. This restricts permissible speed on main line.

• Main line & Turnout having curvature in same direction : CANT given to Main line is also given to Loop Lines. This puts restriction on permissible speed on Main Line.

Page 57: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEED POTENTIAL ON TURNOUTS• Factors which restricts speed potential on Turnout:

– Abrupt change in direction at Toe of Switch quantified by Switch Entry Angle

– Absence of Transition– Deficiency of Super elevation on lead– Discontinuity at Crossing– Un-transitioned entry from curved lead to straight crossing– Straight or un-flexed crossing.

• However out of above only SEA has significant bearing on speed potential of T/O at low speeds.

Page 58: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEED POTENTIAL ON BG

Description Speed (kmph)1 in 8 ½ T/O with St. SW 10

1 in 8 ½ T/O with Cu. Sw. 25

1 in 12 T/O with St. Sw 15

1 in 12 T/O with Conv. Cu. Sw.

(SEA : 00 27’ 35”)

40

1 in 12 T/O with Impr. Cu. Sw. 50

1 in 12 T/O with Thick Web Sw. 50

1 in 16 T/O with Conv. Cu. Sw. 50

1 in 16 Impr.T/O with Cu. Sw. 65

1 in 20 Impr.T/O with Cu. Sw. 85

Page 59: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEED POTENTIAL ON BG

Description Speed (kmph)

1 in 8 ½ Symm. Split T/O with Cw. Sw

40

1 in 12 Symm. Split T/O with Impr. Cw. Sw

70

1 in 16 Symmetrical split T/O with Cu.Sw.

75

Page 60: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SPEED POTENTIAL ON MG

DESCRIPTION SPEED (KMPH)

1 in 12 T/O with Cu. Sw 25

1 in 12 T/O with St. Sw. 15

1 in 8 ½ T/O with Cu. Sw 15

1 in 8 ½ T/O with St. Sw 10

1 in 8 ½ Symm. Split T/O with Cu. Sw.

15

1 in 8 ½ Symm. Split T/O with St. Sw.

10

Page 61: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

Increase in speed of turnouts Rly bd letter no. 2000/CE-II/TK/9 dtd.

24/1/07

• Speed of 30 kmph can be permitted on turnouts, provided the following conditions are satisfied.

• Higher speed turnouts are provided on a reasonably long section in a continuous stretch.

Page 62: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• Turn in curves and running loops on which higher speed is permitted, are suitably strengthened.

• Arrangements for detection of facing points(including siding points) available in loop line, if any

• Higher speed turnouts are those which permit a speed of 30 kmph or higher as indicated below -

Page 63: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

SN Type of turnout Permissible speedPSC sleeper Steel

sleeper

1 1:8.5 symmetrical split with curved switches 52/60kg including TWS on PSC sleepers

40 kmph 30 kmph

2 1:12 curved switch 52/60 kg including TWS on PSC sleepers

50 kmph 30 kmph

3 1:16 curved switch 60 kg on PSC sleepers

65 kmph -

4 1:20 curved switch 60 kg on PSC sleepers

85 kmph -

Page 64: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• As a substantial number of 1 in 8.5 symmetrical split turnouts are existing on running lines, it is feasible to increase the sped upto 40 kmph only, in spite of the fact that turnouts with higher speed potential are available. Speed upto 40 kmph can be permitted if the following additional provisions (over and above para 1) are fulfiled.

• Turnouts should be on PSC sleepers

Page 65: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• Aspects of home signal to be modified suitably so as to enable the driver to know whether he is passing through the loop line/main line or has to stop on the same so that he can control the train speed accordingly. This can be achieved by arranging the signalling as shown in Annexure I. The two sketches Annexue 1A & 1B are for single distant and double distant territory. The aspects of only those signals have been specified which are coming in the route of the train

Page 66: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS
Page 67: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS
Page 68: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• LED signal should be provided for all signal aspects to realize the full potential of the arrangement through improved visibility of signals.

• Detailed instructions stipulating the track structure for permitting 30 kmph speed on turnouts have been incorporated in para 410 of IRPWM vide correction slip no. 94. Based on the experience with 40 kmph, provisions of IRPWM can be considered for suitable amendment.

Page 69: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• The speed over turnouts in a section can be further increased to 50 kmph provided all the 1 in 8.5 turnouts on running lines of the proposed section have been replaced by such turnouts which permit a speed of 50 kmph or higher.

• Para 4.10 of General Rules 1978 specifies that speed over turnout and crossovers shall not exceed15 kmph, unless otherwise prescribed by approved special instruction, which may permit a higher speed. Suitable provision for this shall be made with approved special instructions to permit such higher speeds.

• Increase in speed on turnouts shall be taken up as detailed above. Top priority shall be accorded to achieving a speed 30 kmph on Group A routes.

Page 70: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

Detailed instructions for permitting 30 kmph speed on turnouts (para 410)

• Length of Section -should cover a number of contiguous stations at a time The works described below, should cover all the running loops on the stretch of line taken up.

• Turnouts - Speed, in excess of 15 kmph, should be permitted on turnouts laid with ST or PRC sleepers only. All turnouts on the running loops shall be laid with curved switches, with minimum rail section being 52 Kg. All rail joints on these turnouts should also be welded to the extent possible.

Page 71: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

• (ii) Track on running loops - Speed in excess of 15 kmph, should not be permitted on running loops laid with wooden sleepers. The minimum track structure on the running loops should be 90R rails laid as Short Welded Panels, M+4 density on PRC, ST, CST- 9 sleepers and 150 mm ballast cushion. Out of 150 mm total cushion, clean cushion of 75 mm at least should be available. Proper drainage to be ensured.

• (iii) Turn-in curves - Speed in excess of 15 kmph, should not permitted on Turn-in curves laid with wooden sleepers. Turn-in curves should be laid with the same rail section as on the turn-out with PRC, ST or CST-9 sleepers with sleeper spacing

• being 65 cm centre to center (maximum).• Turn-in curve should conform to Para 410 (2) of IRPWM

and especially so in respect of curvature of the lead curve.

Page 72: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

Extra shoulder ballast of 150 mm should be provided on outside of the turn-in curve.The frequency of inspection of turn-in curves should be same as that for main line turn-outs.if CST-9 sleepers are used in running loops or turn-in curves :- (i) There is no crack or fracture at rail seat in two consecutive sleepers. (ii) There is no excessive wear of lug and rail seat. (iii) All the fittings, keys, cotters and tie bars are fitted properly. Rail is held firmly with sleepers. (iv) Tie bars should not be broken or damaged by falling brake gear, wagon parts etc. and they should not have excessive corrosion or elongated holes. The corrosion of tie-bars inside the CST-9 plate should be especially checked as this results in their removal and adjustment becoming difficult.if ST sleepers are used in Turnouts, Turn-in curves or running loops:- (i) There is no crack or fracture at rail seat in two consecutive sleepers.

Page 73: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

(ii) There is no excessive wear of lug, MLJ andrail seat.(iii) All the fittings are effective and rail is heldwith sleepers properly.(iv) The sleepers and fittings do not have excessivecorrosion, elongated holes etc.

Page 74: POINTS AND CROSSINGS LAYING OF POINTS & CROSSINGS

Thanks