mv network managementgurgaonfirst.org/wp-content/uploads/2017/05/amit_sharma...- case 5: recloser...

Post on 06-Mar-2019

228 Views

Category:

Documents

3 Downloads

Preview:

Click to see full reader

TRANSCRIPT

MV NETWORK MANAGEMENT

Amit SharmaAnil Kadam

Schneider Electric 2

kWh

Medium IndustrialkWh

Large Commercial

Public DistributionPrimary Substation

Urban Distribution

kWh

20MVA33/11kV

20MVA33/11kV

Farm (ruraldistribution)

ProcessIndustry

MV Public Distribution NetworkPrimary Distribution

Schneider Electric 3

Radial network

LoadCentre 1

LoadCentre 2

LoadCentre 3

LoadCentre 11

33kV

11kV

20MVA

Primary1

LoadCentre 11

Schneider Electric 4

Open ring network33kV

11kV

20MVA

Primary1

LoadCentre 11

LoadCentre 3

Schneider Electric 5

Open ring network33kV

11kV

20MVA

Primary1

LoadCentre 11

LoadCentre 3

NOP

Schneider Electric 6

- Why improve MV distribution?

● To obtain the best possible power quality

The main issue is to reduce outage time and cost to the utility and its customers

Schneider Electric 7

- How can outage time be reduced?

● By improving MV networks:

● By improving the MV networks management:

Large number of shortsections

Redundant networks

Reliable components…

With Fault Passage Indicators (FPI’s)

Or with remote controlled load break switches

Or with fully automated reclosers and sectionalizers

Or Ring Main Units with FPI’s

Schneider Electric 8

R

- Different types of devices

R2

Schneider Electric 9

- overhead networks: types of faults● Temporary

faults● Permanent

faults

80% 20%

Schneider Electric 10

- temporary faults

● Temporary faults can be cleared by the use of Automatic Circuit Reclosers (ACRs)

Schneider Electric 11

R

- temporary fault: one recloser

Schneider Electric 12

R

15 s

C

O

Time

100%

- temporary fault: one recloser

Schneider Electric 13

R

15 s

C

O15 s

Time

100%

- temporary fault: one recloser

Schneider Electric 14

R

15 s

C

O15 s

Time

100%

- temporary fault: one recloser

Schneider Electric 15

R

15 s

C

O15 s

15 s

Time

100%

- temporary fault: one recloser

Schneider Electric 16

R

15 s

C

O15 s

15 s

Time2 mn

100%

- temporary fault: one recloser

Schneider Electric 17

R1

- temporary fault: TWO reclosers

R2

Schneider Electric 18

R1Network A-50%

Network B-50%

Network B

Time

- temporary fault: TWO reclosers

R2

Schneider Electric 19

- permanent faults

Permanent faults cannot be cleared by automatic reclosing

To manage “permanent faults”, the

best solution is to add some “sectionalizers”

Schneider Electric 20

R

5H – 6H

100%

- case 1: no network automationPermanent fault

Schneider Electric 21

R

5H – 6H

100% 95%

- case 1: no network automationPermanent fault

Schneider Electric 22

R

- case 2: addition of non-communicating fault passage indicators (FPI)An FPI for each branch of the network

Add an FPI around each major «obstacle»…

Schneider Electric 23

- case 3: addition of communicating FPIs

R

Put several communicating FPIs in strategic locations

Schneider Electric 24

- case 4: addition of communicating FPIs and remote controlled load break switches

RT

TT

T

T remote controlled load breakswitchesCommunicating FPI

Schneider Electric 25

- case 5: recloser and sectionalizer load break switches

R

Schneider Electric 27

S4

S3

S3

S2

S1

1 1

1 S2

- case 5: recloser and sectionalizer load break switches

R

Permanent fault

Schneider Electric 28

S4

S3

S3

S2

S1

2 2

2 S2

- case 5: recloser and sectionalizer load break switches

R

Permanent fault

Schneider Electric 29

S4

S3

S3

S2

S1

2 2

2 S2

- case 5: recloser and sectionalizer load break switches

R

Permanent fault

2’

Schneider Electric 30

S4

S3

S3 S2

S2

S1

- case 5: recloser and sectionalizer load break switches

R

Permanent fault

2’ 60’

75%

95%

Schneider Electric 31

- summary of overhead networks 1/2Permanent fault

95%Case 2

A recloser

+ FPIs3 h

6 h

95%

Case 1

A recloser

95%Case 3

A recloser

+ FPI with Com1h30

Schneider Electric 32

- summary of overhead networks 2/2Permanent fault

95%

1h

2’

75 %Case 5

A recloser

and sectionalizers

95%

1h

10’

70 %Case 4: A recloser,

remote controlled switches

and FPI with Com

Schneider Electric 33

●SAIDI (System Average Interruption Duration Index) can vary from a few minutes to several hours,

●SAIFI (System Average Interruption Frequency Index) can vary from 1 to 10 and more, depending on :

● population density (rural or urban area)● proportion between underground and overhead distribution● maximum accepted costs for non distributed energy

Excellent Average PoorUrban area < 10 mn 30 mn >2 hrsRural area < 30 mn 2 hrs >10 hrs

Permanent Interruptions (>1 mn)

SAIDI/SAIFI variations – Quality Power

Schneider Electric 34

OPEN POINT

51/51N 51/51N

MAIN SUBSTATION

OPEN RING SYSTEM

What would happen to this network

if a fault occurred here ??

Schneider Electric 35

MAIN SUBSTATION

OPEN POINT

51/51N

OPEN RING SYSTEM

What would you do to get the customers back on supply ??

Schneider Electric 36

MAIN SUBSTATION

NEW OPEN POINTS SHIFTED FROM

OPEN RING SYSTEM

Schneider Electric 37

Thank You!!

top related