Antti Laukkanen
MoS Seminar in
Brussels 21.11.2019
DOOR2LNG -project
• Upgrade of the maritime links integrated in the multimodal container transport routes
• Member states involved: Finland, Germany, United Kingdom and the Netherlands
• Implementation time: 16/02/2016-30/06/2020• Maximum EU grant: EUR 16 863 000
• The Project in practice:• Implementation of environmental efforts of
four new LNG-fueled container vessels –Containerships Oy
• Development of port infrastructure –removing bottlenecks of inefficiency and investing in cargo handling capacity and infrastructure – RST, PD Ports, Multi-Link Terminals Ltd
DOOR2LNG -project
• LNG-fuelled vessels:• Three vessels investment done and vessels
are operational in Europe• One vessel to be delivered from China Dec
2019• In addition Containerships have ordered two
additional LNG-fuelled vessels (outside the project)
• Crane investments within RST (Rotterdam):• Done
• Crane & infra investments within PD Ports (Teesport):• Crane investments done• Gate upgrade done• Transparency pilot to be finalised end 2019
beginning 2020• Crane investments within Multi-Link Terminals
• Crane investment ongoing• Crane upgrade to be done spring 2020
DOOR2LNG –project – current status
Delay in the Project: Typhoon Mangkhut September 16th 2018
Source: The Atlantic / Japan Meteorological Agency
Source: Mapsofworld.com / Containerships
Shipyard
• River Pearl flooded heavily in the dock of Shipyard
• Shipyard missed to screw in the bottom plugs of the vessel and to close the ICCP openings during those days.• Vessel was in the “dry dock”
• Water flooded into second vessel cargo hold & engine room with 2,5 meters => delay caused for the vessels to be delivered
• For next vessels: Main engine, shaft generator, gear box & other equipment in the dock / warehouse => water flooded there as well
• Chain reaction: Only one vessel can be equipped at time: Second delayed -> third vessel delayed -> fourth vessel delayed
• Inspection of damage done, drying the equipment, ordering new equipment…many months
Delay of almost 12 months for whole project
Delay in the Project: Typhoon Mangkhut Source: The Atlantic / Jennifer Pollard via Reuters
Source: The Atlantic Bobby Yip / Reuters
DOOR2LNG –project – experiences
• Get commitment from each project partner before sending the application to INEA (memorandum of understanding etc.)
• Have frequent monthly project meetings & minutes of those Skype / physical meetings
• Ensure full time resource for project administration (either internal or external)
• Pay attention to clear & simple language in reports and forget business specific jargon
• In case of changes in Actions, inform / consult your INEA Project Manager before sending official Amendment Request
Clean Business Innovation
Intra Europe Door to Door deliveries, via the
Motorways of the Sea, reducing trucks pollution for an Environment friendly solutions
Clean Business Innovation• Co2 reduction (reduce regional transport footprint)
• Boldness (lead the technology change : from LNG to Electric)
• Integrity (Respect our staff, our customers, our environment)