1

Former NAS Moffett Field

Hangar 1 Removal Action Update

Bryce Bartelma, PG

Navy BRAC PMO West

August 9, 2012

RAB Meeting

2

• Control release of PCBs from Hangar 1 in accordancewith EE/CA (July 2008) and Action Memorandum(December 2008)

Demolition of interior structures

Removal of contaminated siding

Application of weather-resistant coating to steel frame

Project Objective

3

Continued Monitoring andProtection Measures

• Continued biological activity andnesting deterrents

• Maintain storm water and groundsurface protection

• Navy and NASA air monitoring datademonstrates control of air emissions

4

April 2012

5

July 2012

6

Final Material Removed – July 19, 2012

7

Fixing the Holiday Star

• Replacement ofelectrical components

8

Remaining Tasks

• Scaffolding deconstruction

• Mezzanine prep and coat

• Final touch ups, cleaningand surface soil removal

9

Schedule

• Complete Fieldwork andDeconstruct Scaffolding

October 2012

• Final Cleaning andDemobilize

November 2012

• Submit After ActionCompletion Report

Winter/Spring 2013

10