2
• Control release of PCBs from Hangar 1 in accordancewith EE/CA (July 2008) and Action Memorandum(December 2008)
Demolition of interior structures
Removal of contaminated siding
Application of weather-resistant coating to steel frame
Project Objective
3
Final Material RemovedJuly 19, 2012
4
Final Scaffolding RemovedOctober 18, 2012
5
Remaining Removal Action Tasks
• Mezzanine prep and coat
• Final coating touch ups
• Soil excavations andconfirmation sampling
• Concrete slab washing andconfirmation sampling
• Perimeter Storm Drainclean-out
• Demobilize
6
Hangar 1 Interactive CD
http://historicproperties.arc.nasa.gov
7
Hangar 1 CERCLA Process
EE/CAand
ActionMemo
RemovalAction
FocusedFeasibility
Study
ProposedPlan
Record ofDecision
Land UseControls
8
Schedule
• NTCRA Demobilization
December 2012
• Draft After ActionCompletion Report
January 2013
• Focused Feasibility Study
April 2013
• Proposed Plan
June 2013
• Public Meeting (tentative)
July 2013
9
Questions?