In 2011 under the project of “LINC” USA international development agency USAID Mykolaiv took part in thein the competitive selection of land plots, that have the greatest potential for their development under the industrial and logistics parks to attract investors. As a result the land plot of Mykolaiv passed the competitive selection, and the group of experts group of experts on the development of industrial parks USAІD «Local investments and national competitiveness» in cooperation with structural units of Mykolaiv City Council developed a conceptual design of the industrial park at the territory of the land plot of ІІ Industrial Zone, that can become a basis of future concept of industrial park in Mykolaivin accordance with the Law of Ukraine "On industrial parks”.
Located within the city limits attached to old industrial sites (industrial “edge” of the city)
New General plan, that supports the concept.
No direct collision with residential areas
Relevant site size to the city size – sufficient labor sources
Excellent access from national/regional road network Mykolaiv – Kherson and Mykolaiv-Krivyj Rig
Partial uncertainties mainly in water supply and
sewage treatment – to be investigated further
Stage Area
(ha)
Proposed general
function
Not recommended
Stage I 22,00 Industrial and
commercial facilities:
commercial services
alongside P06, retail and
wholesale facilities,
offices,
assembly/disassembly
operations
heavy machinery,
chemical production,
paper production,
food processing, wood
processing
Stage Area
(ha)
Proposed general
function
Not recommended
Stage II 78,0 Productive and research
investments: electronic, semi-
electronic, assembly/disassembly
activities, light processing, value
added productions – all with features
of science technological park,
production of energy saving.
Logistic and wholesale:
Storage halls, wholesale centers,
logistic facilities connected with rail,
truck cargo stores, similar.
heavy machinery, chemical
production, paper production, food
processing, wood processing
Settings Required power Available facilities / sources
Water up to 256 m3 / h up to 100 m3 / h available in the main existing water supply:
enough for the development of phases I and II, but also
depends on the rate of Leninsky district
Wastewater up to 2 000 m3 / day
2500 m3 / day available for existing water treatment plants:
enough to fully develop the site, but also depends on the
rate of Leninsky district
Gas supply 14.8 million. m3 / year Required more thorough study
Electricity 15 MW Required more thorough study
Surface waters up to20 000 m3 /h (in case
of intense rain: 60 min.)
On the site there is no diversion of rainwater: 25% of surface
water will be recycled investors, 75% routed in holding lake
or the new drainage system to natural watercourses
Stages Approxi
mate
area
(ha)
Industrial /
business premises
halls - the total
area (sqm)
The estimated number of
employees (persons)
Stage I 22, 00 41 000 520
Stage II 78,0 128 702 1.578
Total 100,00 169 702 2.098
Note: indicative valuation based on approx. Central European unit prices, approx. price level 2009-2011. To be recalculated according to local price level with inclusion of all additional investment.
Item
No.:
Item Unit Units needed with all
plots fully developed
unit price (EUR) total price
(EUR)
1. Purchase of the land ha 0 0 0
2. Public paved site roads incl. road
signs
sq.m 23.625 60 1.417.500
3. Public parking places incl. road signs sq.m 1.000 x 60= 60.000
4. Public footpaths incl. orientation
system
sq.m 6.000 30 180.000
5. Public green areas incl. landscaping sq.m 12.000 15 180.000
6. Public green barriers sq.m. 50.000 5 250.000
7. Backbone infrastructure - gas network
incl. sub-connection points, Dn 150-
200 mm
m 1.750 120 210.000
8. Backbone infrastructure - water
network inc. sub-connection points,
Dn 300mm
m 1.750 210 367.500
9. Backbone infrastructure - electric
network incl. sub-transformer
station[2]
m 1.750 150 262.500
10. Backbone infrastructure - sewage
network incl. sub-connection points,
Dn up to 600 mm
m 1.750 250 437.500
11. Backbone infrastructure - surface
water network/drainage incl. sub-
connection points, Dn up to 800 mm
m 1.750 250 437.500
total EUR 3.622.500
-Application of exemption from customs duties on
importation into the customs territory of Ukraine of certain
goods (p. 6 article 287 CCU);
- Exemption from equity participation in the development of
infrastructure of the settlement in the case of construction
projects in the framework of industrial parks (Law of
Ukraine «On industrial parks»);
-Getting financial support on arrangement of the industrial
park by the resources of state and local budgets(Law of
Ukraine «On industrial parks»);
-The possibility of obtaining interest-free loans for the target
funding on irrevocable basis for arrangement of industrial
parks(Law of Ukraine «On industrial parks»).
Favorable
location Innovative
production New jobs High quality Investment
attractiveness Tax incentives Large profits
Income taxes
in the budget Energy-saving
technologies Minimal impact
on the environment
INDUSTRTIAL PARK
“MYKOLAIV”
Contacts: Economic and Investment Department of Mykolaiv City Council
phone.: +38 0512 37 20 37; +38 0512 37 07 18
e-mail: investprom.nikgor@gmail.com; invest_prom@nikgor.mk.ua
top related