Georgia Association of MPOs November 29, 2012
North Augusta Park and Ride Project
EXIT 5
AUGUSTA METRO AREA
EXIT 5
AUGUSTA
NORTH AUGUSTA
PalmettoParkway
Park & Ride Site
EXIT 5
October 2009
Issues
• Air quality• Demand• SCDOT to design and construct• City to maintain• Sustainable Design: stormwater, energy,
landscaping• Security• Image• Maintenance cost
Main
JANUARY 2010
Chronology
• August 2009 Project conceived• October 2009 User meeting held• January 2010 Sketch design complete• June 2010 ARTS funding approved• January 2011 Design contract advertised • April 2011 URS selected for design• October 2011 URS design contract
approved• October 2012 Preliminary plans at 95%
December 2011
October 2012
Cost Estimates
• January 2010 $ 800,000• June 2010 $ 1,000,000• October 2012 $ 1,473,305