georgia association of mpos november 29, 2012 north augusta park and ride project
DESCRIPTION
Georgia Association of MPOs November 29, 2012 North Augusta Park and Ride Project. EXIT 5. AUGUSTA METRO AREA. EXIT 5. NORTH AUGUSTA. AUGUSTA. Park & Ride Site. EXIT 5. Palmetto Parkway. October 2009. Issues. Air quality Demand SCDOT to design and construct City to maintain - PowerPoint PPT PresentationTRANSCRIPT
Georgia Association of MPOs November 29, 2012
North Augusta Park and Ride Project
EXIT 5
AUGUSTA METRO AREA
EXIT 5
AUGUSTA
NORTH AUGUSTA
PalmettoParkway
Park & Ride Site
EXIT 5
October 2009
Issues
• Air quality• Demand• SCDOT to design and construct• City to maintain• Sustainable Design: stormwater, energy,
landscaping• Security• Image• Maintenance cost
Main
JANUARY 2010
Chronology
• August 2009 Project conceived• October 2009 User meeting held• January 2010 Sketch design complete• June 2010 ARTS funding approved• January 2011 Design contract advertised • April 2011 URS selected for design• October 2011 URS design contract
approved• October 2012 Preliminary plans at 95%
December 2011
October 2012
Cost Estimates
• January 2010 $ 800,000• June 2010 $ 1,000,000• October 2012 $ 1,473,305
North Augusta Park and Ride Project
QUESTIONS