McKINLEY ELEMENTARY SCHOOLFINAL DESIGN REPORT | 01.22.2015 RENOVATION AND ADDITION
1
Agenda
1. Project Schedule & Costs
2. Final Building Design
3. Exterior Elevations
4. Interior Views
McKinley Elementary School Renovation + Addition Final Design School Board Information
January 22nd 2015
4 McKinley Elementary School Renovation and Addition
Project Schedule & Costs
3
Grade Current Proposed Average Total# of
Classrooms # of
Classrooms Class Size Capacity Pre‐K 2 2 16.0 32.0Kindergarten 4 4 23.3 93.2Grade 1 5 4 23.3 93.2Grade 2 4 4 23.3 93.2Grade 3 5 4 23.3 93.2Grade 4 4 Relocatables 4 23.3 93.2Grade 5 3 Relocatables 4 23.3 93.2Flex: k‐1 1 2 0.0 0.0Flex 2‐5 1 4 23.3 93.2Total # of classes 29 32 684.4
MORE SEATS FOR MORE STUDENTS :
4
01SCHEDULE :
PROJECT MILESTONES:
• Concept Design ‐ School Board ‐ Information – Feb 6, 2014• Concept Design ‐ School Board ‐ Approval – Mar 6, 2014• Schematic Design to APS Board for Information– April 24, 2014 • Schematic Design to APS Board for Action – May 8, 2014 • Environmental Assessment Report – May, 2014• Design Development – July 15, 2014
• Use Permit – September 2014• Construction Documents – November 30, 2014• Building Permit – February / March, 2015• Bidding – February 6, 2015• Construction – June 2015• Occupancy – September 2016
Exhibit: AExhibit: A 5
01SCHEDULE : PROJECT MILESTONES:
• School Board Information item January 22nd 2015
• School Board Action Item February 5th 2015
• Issue Bid Documents February 6th 2015
• Open Bids March 9th 2015
• School Board Contract Award March 19th 2015
• Notice To Proceed March 26th 2015
• Building Permits June / July 2015
• Construction Start June 22nd 2015
• Occupancy September 5th 2016
Exhibit: AExhibit: A 6
54 McKinley Elementary School Renovation and Addition
DEDUCT ALTERNATES• 1 ‐ Leave Existing Lighting In Minor Renovation ($133,780.44)• 2 ‐ Leave Existing Plumbing In Minor Renovation ($33,126.92)• 3 ‐ Leave Existing Casework In Minor Renovation ($111,350.27)• 4 ‐ Leave Existing Flooring In Area E ($44,864.02)• 5 ‐Minimize Scope In Area A ($67,553.29)• 6 ‐Minimize Scope In Area E ($127,837.53)ALTERNATES TOTAL ($518,512.47)
* Communty Amenities funding to be finalized with County Staff prior to final approval
SUMMARY OF PROJECT COSTS: Cost EstimateSCHEMATIC DESIGN FINAL DESIGN
New Construction $ 8,100,000 $ 8,001,668Renovations $ 3,450,000 $ 5,009,850
SiteWork $ 2,100,000 $ 2,100,352
Contingencies $ 2,000,000 $ 1,101,130
Escalation $ 730,000 $ 300,000
Soft Costs $ 3,720,000 $ 3,587,000
Subtotal $ 20,100,000 $ 20,100,000Community Amenities $ ‐ $ 750,000*TOTAL PROJECT COST $ 20,100,000 $ 20,850,000
7
* Communty Amenities funding to be finalized with County Staff prior to final approval
SUMMARY OF PROJECT COSTS: Funding Sources
Funding authorized in 2012 / 2014 Bonds $ 17,600,000
Funding authorized from the 2010/2012 HVAC‐Roofing Bonds $ 1,866,500
Funding authorized from the 2015 MC/MM Fund $ 285,450
Funding authorized from the 2016 MC/MM Fund $ 348,050
TOTAL APS FUNDING PROPOSED FOR THE MCKINLEY PROJECT $ 20,100,000
Joint ACG/APS Fund (Community Amenities) $ 750,000*
TOTAL PROJECT FUNDING $ 20,850,000
8
* Communty Amenities funding to be finalized with County Staff prior to final approval
SUMMARY OF PROJECT COSTS: Proposed joint ACG / APS funded Items • New McKinley Road crosswalk: (Safe routes to school) $35,392
• New 11th street access ramp: (Safe routes to school) $53,048
• Streetscape improvments along McKinley Rd $84,388
• County emergency repeater system $156,918
• Fire access lane $35,000 • Fire access wet standpipe lane $15,000 • Utility Undergrounding $133,000
• New fire hydrant @ 11th street $7,500 • ConnectArlington Conduit $68,575 • Construction Contingency $23,424 • Soft Costs: 22.5% $137,755
Subtotal McKinley $750,000
9
01Project Specific Costs Items: BEYOND THE NORM
• Strom Water Management: McKinley Elementary school has some significant storm water drainage issues. These will be corrected through enhanced storm water management.
• Steep terrain: The 60 foot grade change across the site, (5 stories high) results in a high number of retaining walls.
• Pentagon Wing Replacement: The unanticipated replacement of the pentagon wing results in an increased scope of work.
• Site Accessibility & Community improvements: The proposed new off campus cross walk on McKinley Road and new accessible ramp from 11th street are scope of work increases.
• Site Landscaping: Through creative design of the new storm water management system, several existing trees may be saved. However, additional piping, landscaping and other measures are required.
10
01 McKinley Ashlawn
Projected new school total area: 95,780 97,363 Sq. Ft.
Projected area of new addition;Including pentagon replacement: 34,225 28,010 Sq. Ft.
• Cost per square foot of total building: $209.86 $209.53
• Cost per square foot of new addition only: $413.24 $468.09
• Cost per total new projected school capacity: $29,385.96 $29,781.02 (684 seats new school capacity)
• Cost per seat new added capacity: $83,402.49 $90,999.67 (684 seats projected – 443 seats current)
Unit Project Costs:
11
01Risk Management: POTENTIAL RISK EXPOSURE ITEMS
• Building Permit Conditions: Building Permit requirements causing additional costs
• Challenging Project Schedule: Occupied renovations necessitating a tight construction schedule controls, a slip the schedule can result in project delays
• Storm Water Management: Additional costs and compliance with new MS4 stormwater permit and resulting learning process for APS, County and State stakeholders
• Improved Market Costs: A continued resurgence of the construction sector, translating to potential General Constrictors being more conservative with Bid numbers
• Off site improvements: Improvements to McKinley Boulevard cross walk and striping and accessible ramp from 11th Street
• Unforeseen renovation issues: Abatement, connections to existing systems, existing construction anomalies and other unforeseen circumstances
12
FINAL BUILDING DESIGN
13
SITE AREA:7.54 Acres
PARKING:36 Spaces on site26 Spaces along McKinley Road
STUDENT DROP OFF ZONE:Along McKinley Road (North of Site Driveway)
RELOCATABLE CLASSROOMS:3 Buildings on site
SITE AMENITIES:2 Playgrounds Paved Play Area Outdoor Classroom Rain Garden
SITE GRADE:High Point (South): +346.0’ Low Point (North): +280.0’
SITE OVERVIEWEXISTING SITE PLAN
14
Concept Design 4Concept Design 3
Concept Design 2Concept Design 1
CONCEPT + SCHEMATIC DESIGNSITE DESIGN PROGRESSION
15
CONCEPT + SCHEMATIC DESIGNSITE PLAN
EXTERIOR MATERIALS
red brick
colored accent glass
cement panel
3 STORYCLASSROOM ADDITION
1 STORYCLASSROOM ADDITION
1 STORYENTRY ADDITION
16
FINAL DESIGNSITE PLAN
LANDSCAPE CONCEPT
The site development and landscape improvementsfor McKinley Elementary School focus on creatingnew outdoor activity and learning spaces andpreserving open space.
17
FINAL DESIGNFLOOR PLAN MAIN LEVEL: 319’-4”
3 STORY CLASSROOM ADDITION
1ST 1ST
1ST 1ST
2ND
FLEX2ND
MEDIA CENTER - MAJOR RENOVATION
2ND
DINING - MAJOR RENOVATION
2ND
1 STORY ENTRY ADDITION
FLEX
PRE-K
K
K
PRE-K
K
K
3RD 3RD
3RD 3RD
FLEX
FLEX
1 STORY CLASSROOM ADDITION
18
FINAL DESIGN3 STORY CLASSROOM ADDITION, MAIN LEVEL: 319’-4”
ART
VOCAL MUSIC
INSTRUMENTAL MUSIC
SMALL GROUP INSTRUCTION
19
FINAL DESIGN3 STORY CLASSROOM ADDITION, GYM LEVEL: 307’-2”
GYM STAGE SMALL GROUP INSTRUCTION4TH GRADE CLASSROOM
FLEX CLASSROOM
20
FINAL DESIGN3 STORY CLASSROOM ADDITION, FIELD LEVEL: 293’-2”
5TH GRADE CLASSROOM
FLEX CLASSROOM
21
FINAL DESIGNMEDIA CENTER - MAJOR RENOVATION, MAIN LEVEL:
CIRCULATION DESK
STACKSCOMPUTERS
STORY TELLING SMALL
STORY TELLINGMEDIUM
STORY TELLING
LARGE
22
319’-4”
ARLINGTON PUBLIC SCHOOLS FINAL DESIGN REPORT | 01.22.2015
FINAL DESIGNDINING - MAJOR RENOVATION, MAIN LEVEL: 319’-4”
KITCHEN
BUILT IN SEATS, TYPICAL
QUIET DINING ZONE
DINING
23
FINAL DESIGN1 STORY ENTRY ADDITION, MAIN LEVEL: 319’-4”
MAIN ENTRY
RECEPTION
ASST. PRINCIPAL
PRINCIPALCOUNSELOR
PSYCHOLOGIST
24
FINAL DESIGN1 STORY CLASSROOM ADDITION, MAIN LEVEL: 319’-4”
GIFTED RESOURCE TEACHER
3RD GRADE CLASSROOM
SMALL GROUP INSTRUCTION
25
EXTERIOR VIEWS
26
FINAL DESIGNNORTHEAST VIEW 3 STORY ADDITION
27
FINAL DESIGNEAST ELEVATION 3 STORY ADDTITION
28
North Perspective
CONCEPT + SCHEMATIC DESIGNNORTH ELEVATION OF 3 STORY ADDITION
29
CONCEPT + SCHEMATIC DESIGNNORTH ELEVATION OF 3 STORY ADDITION
30
CONCEPT + SCHEMATIC DESIGNNEW 1 STORY MAIN ENTRY
31
FINAL DESIGNCOMMUNITY ENTRANCE
32
FINAL DESIGNNEW 1 STORY MAIN ENTRY
33
INTERIOR VIEWS
34
FINAL DESIGNINTERIOR DESIGNCONCEPT
MAIN STREET, MAJOR ACCESS
LOCATIONS FOR TEMPORARY ART
LOCATIONS FOR PERMANENT ART
ADDED TRANSPARENCY
COLLABORATIVE BREAKOUT SPACE
35
FINAL DESIGNMAIN ENTRY / MAIN STREET
36
FINAL DESIGN3 STORY ADDITION, MAIN LEVEL CORRIDOR - COLLABORATION | ART |PERFORMANCE
37
FINAL DESIGN3 STORY ADDITION, GYM LEVEL CORRIDOR - COLLABORATION | ART |
PERFORMANCE
38
FINAL DESIGNCOMMUNITY ENTRANCE
39
FINAL DESIGNCOMMUNITY ENTRANCE - SECTION PERSPECTIVE
40
FINAL DESIGNGYMNASIUM + STAGE
41
FINAL DESIGNGYMNASIUM LOOKING NORTH
42
FINAL DESIGNDINING LOOKING EAST
43
FINAL DESIGNDINING LOOKING WEST
44
FINAL DESIGNMEDIA CENTER
45
ARL FINAL DESIGNWAY FINDING, FLOOR MATERIALS + ACCENTS
PRE K + K
1 ST
OR
YC
LAS
SR
OO
M
AD
DIT
ION
3 ST
OR
Y C
LAS
SR
OO
M
AD
DIT
ION
1ST GRADE
2ND GRADE
5TH GRADE
4TH GRADE
3RD GRADE
PTGYM, MUSIC + ART
F TFIELD COLORS
CPTMEDIA CENTER CORRIDOR
WAINSCOTS
F T
F T
CPT
F T
F TF T P T
PT
PT
PT
PT
PT
PT
FT - LINOLEUM FLOOR TILE CPT - CARPET TILEPT - WALL PAINT
46
2000 Duke StreetSuite 105
Alexandria, VA 22314
571.388.7761www.hcm2.com
750 East Pratt Street Suite 1100
Baltimore, MD 21202
410.837.7311www.hcm2.com
McKINLEY ELEMENTARY SCHOOLFINAL DESIGN REPORT | 01.22.2015 RENOVATION AND ADDITION
47
top related